Construction Project Schedule HO

The document outlines the work breakdown structure and schedule for constructing a 220kv substation. It involves structure work for a GIS building and DG building from foundation to roof slabs, as well as finishing work like blockwork, plastering, screeding and door/window fixing for both buildings. The project start date is November 4th 2022 and overall completion date is May 4th 2023, taking 181 days.

Uploaded by

Ravikumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views4 pages

Construction Project Schedule HO

The document outlines the work breakdown structure and schedule for constructing a 220kv substation. It involves structure work for a GIS building and DG building from foundation to roof slabs, as well as finishing work like blockwork, plastering, screeding and door/window fixing for both buildings. The project start date is November 4th 2022 and overall completion date is May 4th 2023, taking 181 days.

Uploaded by

Ravikumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Project Name : Construction of 220kv Substation at ITPL, Whitefield

Client : Micron Electricals


Project Contractor: Pinnacle Prime Constructions Pvt. Ltd
Project Start Date: 11/4/2022

WBS ID Activity Duration Lead Start Date End Date Remarks/Assumptions


Building Project 181 0 11/4/2022 5/4/2023
By considering site handing over date as 04-11-2022 0 0 11/4/2022 11/4/2022
A Structure Work-GIS Building
Foundation
Excavation 11 0 11/4/2022 11/15/2022
PCC 6 0 11/10/2022 11/16/2022
Reinforcement & Shuttering For Footing 4 0 11/13/2022 11/17/2022
Casting of Footing 2 0 11/17/2022 11/19/2022
Upto Plinth Level
Backfilling & Compaction upto plinth beam 6 0 11/19/2022 11/25/2022
Plinth Beam Reinf. & Shuttering 5 0 11/26/2022 12/1/2022
Casting of Plinth Beam 2 0 12/2/2022 12/4/2022
Filling Upto plinth Top 5 0 12/5/2022 12/10/2022
WET Mix Filling & Compaction 2 0 12/11/2022 12/13/2022
PCC for Grade Slab 1 0 12/14/2022 12/15/2022
Upto Ground Floor Slab
Columns & RT Wall up to GF Slab 10 0 12/15/2022 12/25/2022
Shuttering & Reinforcement of Beams & Slab 10 0 12/17/2022 12/27/2022
Casting of GF Floor Beams & Slab 1 0 12/30/2022 12/31/2022
Upto First Floor Slab
Tie Beam & Columns Upto FF Slab 10 0 1/2/2023 1/12/2023
Shuttering & Reinforcement of Tie Beams, Roof Beams & Slab 16 0 1/8/2023 1/24/2023
Casting of Bemas & Slab 1 0 1/25/2023 1/26/2023
Upto Terrace Floor Slab
Columns up to Beam Bottom 7 0 1/29/2023 2/5/2023
Shuttering & Reinforcement of beams & Slab 13 0 2/3/2023 2/16/2023
Casting of Beams with Slab 1 0 2/17/2023 2/18/2023
B Structure Work-DG Building
Foundation
Excavation 9 0 11/6/2022 11/15/2022
PCC 2 0 11/14/2022 11/16/2022
Reinforcement & Shuttering 2 0 11/15/2022 11/17/2022
Casting of Footings 2 0 11/17/2022 11/19/2022
Upto Plinth Level
Backfilling & Compaction upto plinth beam 8 0 11/20/2022 11/28/2022
Plinth Beam Reinf. & Shuttering 13 0 11/25/2022 12/8/2022
Casting of Plinth Beam 9 0 12/1/2022 12/10/2022
Filling Upto plinth Top 8 0 12/5/2022 12/13/2022
WET Mix Filling & Compaction 6 0 12/10/2022 12/16/2022
PCC for Grade Slab 5 0 12/13/2022 12/18/2022
Upto Ground Floor Slab
Columns & RT Wall up to First Slab 10 0 12/20/2022 12/30/2022
Shuttering & Reinforcement of Beams & Slab 14 0 12/25/2022 1/8/2023
Casting of GF Floor Beams & Slab 1 0 1/9/2023 1/10/2023
Upto First Floor Slab
Tie Beam & Columns Upto FF Slab 9 0 1/11/2023 1/20/2023
Shuttering & Reinforcement of Tie Beams, Roof Beams & Slab 13 0 1/15/2023 1/28/2023
Casting of Beams & Slab 1 0 1/29/2023 1/30/2023
Upto Second Floor Slab
Tie Beam & Columns Upto FF Slab 9 0 2/1/2023 2/10/2023
Shuttering & Reinforcement of Tie Beams, Roof Beams & Slab 15 0 2/6/2023 2/21/2023
Casting of Bemas & Slab 1 0 2/22/2023 2/23/2023
Upto Terrace Floor Slab
Columns up to Beam Bottom 7 0 2/25/2023 3/4/2023
Shuttering & Reinforcement of Tie Beams 15 0 2/28/2023 3/15/2023
Casting of Beams with Slab 1 0 3/16/2023 3/17/2023
C Finishing Work GIS Room
Block Work
Blockwork for Ground Floor 15 0 2/15/2023 3/2/2023
Blockwork for First Floor 20 0 3/10/2023 3/30/2023
Blockwork for Parapet & Head Room 5 0 2/22/2023 2/27/2023
Internal Plastering
Cellar Floor 21 0 1/20/2023 2/10/2023
Plaster for Ground Floor 23 0 2/25/2023 3/20/2023
Plaster for First Floor 16 0 3/20/2023 4/5/2023
Plaster for Parapet & Head Room 15 0 3/5/2023 3/20/2023
External Plastering
External 31 0 3/15/2023 4/15/2023
Screeding
Cellar 3 0 2/12/2023 2/15/2023
GF 3 0 3/22/2023 3/25/2023
FF 4 0 4/8/2023 4/12/2023
Terrace floor Water Proofing 8 0 3/22/2023 3/30/2023
Doors & Windows Fixing
Doors & Windows Fixing for Ground Floor 38 0 2/20/2023 3/30/2023
Doors & Windows Fixing for First Floor 31 0 3/15/2023 4/15/2023
D Finishing Work DG Room
Block Work
Blockwork for Ground Floor 13 0 2/20/2023 3/5/2023
Blockwork for First Floor 15 0 3/16/2023 3/31/2023
Blockwork for Second Floor 7 0 4/7/2023 4/14/2023
Blockwork for Parapet & Head Room 16 0 3/25/2023 4/10/2023
Internal Plastering
Cellar Floor 24 0 2/1/2023 2/25/2023
Plaster for Ground Floor 19 0 3/1/2023 3/20/2023
Plaster for First Floor 15 0 4/5/2023 4/20/2023
Plaster for Second Floor 15 0 4/18/2023 5/3/2023
Plaster for Parapet & Head Room 12 0 4/3/2023 4/15/2023
External Plastering
External 20 0 4/10/2023 4/30/2023
Screeding
Cellaar 4 0 3/1/2023 3/5/2023
GF 5 0 3/25/2023 3/30/2023
FF 5 0 4/25/2023 4/30/2023
SF 3 0 5/1/2023 5/4/2023
Terrace floor Water Proofing 8 0 4/12/2023 4/20/2023
Doors & Windows Fixing
Doors & Windows Fixing for Ground Floor 34 0 2/25/2023 3/31/2023
Doors & Windows Fixing for First Floor 29 0 4/1/2023 4/30/2023
Doors & Windows Fixing for Second Floor 21 0 4/13/2023 5/4/2023
SlNo. Activity
GIS Building GF Slab to First Floor Slab
1 Column Starter -14 Nos
2 Scaffolding for Column Rise
3 1st Lift shuttering for Columns
4 1st Lift Concreting of Columns
5 2nd Lift Shuttering for Columns-Upto Tie Beam-98.50m
6 2nd lift Concreting for columns-upto tie beam-98.50m
7 Bottom shuttering for Tie beams-98.50m
8 Steel fixing of Tie Beams
9 Side shuttering of 98.50m lvl Tie Beams
10 Concreting of 98.50m lvl Tie beams
11 Column Starter above 98.50m lvl Tie beams
12 Scaffolding above 98.50m lvl Tie beams for columns
13 Steel lapping & fixing of columns
14 1st lift columns shuttering
15 1st lift columns concreting
16 2nd lift columns shuttering upto 102.005m lvl Tie beams
17 2nd lift columns concreting upto 102.005mlvl Tie beams
18 Bottom shuttering for 102.005mlvl Tie beam bottom
19 steel fixing of 102.005m lvl tie beams
20 Tie beams side shuttering
21 Concreting of 102.005m lvl Tie beams
22 Columns starter above 102.005m lvl tie beams
23 Scaffolding for column rise above 102.005m lvl
24 Steel fixing for columns above 102.005m lvl
25 1st lift columns shuttering for columns above 102.005m
26 1st lift columns concreting
27 2nd lift columns shuttering upto 1st floor beam bottom
28 2nd lift columns concreting upto 1st floor beam bottom
29 Scaffolding & shuttering of 1st floor beams & slab
30 steel fixing for 1st floor beams & slab
31 concreting of 1st floor Beams & slab
GIS Building GF Slab to First Floor Slab
1 Column Starter above 1st floor slab
2 Scaffolding for column rising
3 Steel fixing for columns
4 1st lift column shuttering
5 1st lift columns concreting
6 2nd lift columns shuttering upto terrace floor beam bottom
7 2nd lift columns concreting upto terrace floor beam bottom
8 Scaffolding & shuttering of Terrace floor beams & slab
9 steel fixing for Terrace floor beams & slab
10 concreting of Terrace floor Beams & slab