Spare Parts Management
Spare Parts Management
Structure
7.1 Aim of Spare Parts Inventory Management
7.2 Types of Spare Parts
7.3 Life Cycle of Spare Parts
7.3.1 Stage 1: Design and Specifications
7.3.2 Stage 2: Determination of Initial Requirements
7.3.3 Stage 3: Procurement
7.3.4 Stage 4: Receipt, Storage and Preservation
7.3.5 Stage 5: Issue and Replenishment :
The Reorder Level System of Inventory Control
7.3.6 ABC Analysis – Pareto’s Law
7.3.7 Criticality Analysis (V-E-D Analysis)
7.3.8 Periodic Review System
7.3.9 Slow Moving Items
7.3.10 Stage 6: Disposal of Damaged, Surplus and Obsolete Spare Parts
7.4 Management Information System (MIS)
7.5 Cost Control for Spare Parts-Role of Maintenance
7.6 Organizing for Effective Spare Parts Management
7.7 Unique Problems of Spare Parts Management
7.8 Summary
7.9 Self-Assessment Questions
7.10 Bibliography and Suggested Readings
7.11 Case Study in Spare Parts Management-I
7.12 Case Study in Spare Parts Management-II
30
Information Technology
7.1 AIM OF SPARE PARTS INVENTORY (IT) Enabled Maintenance
Management
MANAGEMENT
The aim of spare parts inventory management is to make available to
maintenance, the right spare part, at the right place, at the right time, in the right
quantity, at the right price, and at the lowest total cost to the enterprise. Of
these, the first four represent the ‘service to the maintenance engineer’ and must
be given first priority. The next part means paying the least for a purchased
item by locating and negotiating with the suppliers for a reasonable price-provided
the item meets the technical needs of maintenance. The last part of the aim
minimizes the total cost, consisting of the cost of administering the system and
procedures, the price paid for the parts and the cost of machine downtime
incurred if the needed part was not available when required.
Stock
Value
(Rs.) OQ
1500
Figure 1 Figure 2
The inventory carrying cost consists of borrowing (or the interest lost) on the
capital tied up in inventory and that of handling damage, aging, storage,
preservation and obsolescence. These depend upon the nature of the part but can
be approximated to an annual 20% of the cost of the spare part i.e., Rs.300 per
year. We can reduce this cost by ordering less-say only 150 numbers (Rs.1500)
at a time. The stock graph will now be as shown by the lower line in Figure
7.2. The average inventory carrying cost per year will be Rs.750, but we will
have to order twice as frequently as before. The ordering cost is for
advertisement for supply, contacting and selecting the supplier, paper work and
postage involved in correspondence, receiving, inspecting, and putting in bins.
Local purchase from dealer’s stock may be less expensive.
In the present case, if ‘S’ is the cost of placing an order, say, Rs,100 per order,
then we will spend Rs.100 on ordering 300 pieces once annually, or Rs.200 if we
order 150 pieces twice annually. If the annual cost of carrying inventory ‘I’ is
20%. It will be (Q) (I) /2 for an order size of Q. If the value of annual usage of 33
Maintenance Resource the item is Rs. N, we will place N/Q order per year, and the annual ordering
Management and Costing cost will be (S)(N/Q). The annual total cost is the sum of these two opposite
costs will be [(Q)(I)/2+(S)(N/Q)]. It can be shown that this cost will be
minimum when Q = . This minimum is called Economic Ordering
Quantity (EOQ).
In Figures 3, a replenishment time of three weeks has been set off (Point D)
backwards from the day when stock is expected to fall to Zero. On this day (D)
the stock would have fallen to 30 i.e., the expected consumption during LT.A
little safety stock, of say 5 pieces, to cater for any unexpected increase in this
consumption after the order is placed, is added. The order should be initiated
when the stock falls to 30+5=35(point E). This stock level is called the Re Order
Level (ROL).
A C
Reorder
Level
35
(E)
Safety ↓
(D) (B)
Stock ↑
0 7 10 Weeks
Figure 3
Studies have established that the consumption of repair parts during any period
(such as LT) varies randomly and asymmetrically, following the Poisson
probability distribution. From this, we can calculate Safety Stock (SS) as under:
Note that the safety factor ‘k’ increases rapidly with the demand for higher
assurance so that for every additional item in SS we get relatively less and less
additional assurance. At some point it may not be worth spending so much on SS
inventory. This is used in a decision matrix shown later in Figure 5. This matrix
has to be approved by the top management as it reflects their policy of delivering
different levels of service for investment in this non-moving inventory (safety
stock). Incidentally, an assurance level of 90% does not mean that 90% of the
quantity ordered will be delivered ex-stock. It means that 90% of the orders will
arrive on time, on time, or that the risk of non-availability ex-stock was 10%.
M
7.3.6 ABC Analysis – Pareto’s Law
In 1948, the Chief Materials Manager of General Electric Co. in USA listed the
annual consumption value of each and every material that the company used in
decreasing order of magnitude. He noticed that the top 15 to 20 percent of the
whole range of items contributed to almost 80% of the total cost contributed by
all items. He designated them as A items (Figure 4). The next 30 to35% of the
range of items contributed to 15 to 20% of the total cost (B items). Finally, the
last 50%of the range of items contributed to barely 5 to 10% of the total cost (C
items). ABC analysis suggests that we should control ‘A’ items tightly, ’B’ items
carefully and “c” items loosely i.e. concentrate on preventive and corrective
action only for a few, worthwhile items. For spare parts we should give generous
safely stock for C items (we can afford it), adequate for B items and minimum
for A items – in short, allot high, medium and low value of ‘k’, respectively.
The Italian economist wilfredo Pareto, after whom it is named, first discovered
this pattern eighty year ago. He had shown that that every natural phenomenon
seems to concentrate in a few points or stages. Typical examples are city traffic
on a few roads, failures concentrating in a few components of a machine; most
cost of spare parts contributed by only a few spares.
35
Maintenance Resource Annual Consumption Value
Management and Costing
___________________________________
___________________________ A items (20% range; 80% value)
______________________
————————————————————————————-
______________
________
_____ B items (30% range; 15% value)
___
————————————————————————————-
__
__ C items (50% range; 5% value)
__
__
__
__
__
__
__
__
The Materials Manager listened to all this new fangled talk with growing
impatience. Finally when the presentation was over, he asked Anil just one
question, “Where is the inventory reduction?” Anil was ready with the
answer. He said, “Well Sir, don’t you see that very high cost contribution
of copper-the top item in the Pareto analysis? Our Management must give
it the closest attention- by exerting the tightest control over its consumption,
purchase price, ordering on the basis of EOQ, and sharpening other
inventory parameters”
This was too much for Onkar. He thundered, “Look son, this fancy ABC
analysis or whatever you call it has told me precisely what I have known
by my old fashioned instinct. As regards control on cost of copper etc,
why, I spend more time on this one item than all others put together.
36
I even dream of it at night. The boss himself decides when to buy copper Information Technology
(IT) Enabled Maintenance
and how much. Nobody has taught him anything about your EOQ and Management
what have you – and we are still the best in this business. Now go back
and do something more useful - like stock taking for all the raw materials
as of today”
Activity B
Comment on the manner in which Anil had done the ABC analysis,
keeping in view the extent of the study, its aim and objective, and the logic
of costing adopted by him.
......................................................................................................................
.....................................................................................................................
Suggested response:
The suggested response is contained in the follow up action in this case
study
3) The cost contribution from items also has a pattern according to the
class of items. Thus, raw materials should be treated as one class and
ABC analysis for items within this class should be done. In that cast,
the contribution of copper would probably be closer to about 60% or so
amongst all items of raw materials only- and not as 0.04% of all
materials. There would be a similar pattern for the class of General
Stores.
4) Within the class, the base period should be the same. Raw material is
consumed constantly and in large quantities. A base period of six to
twelve months is adequate. For General Stores one to two years would
be satisfactory. If a few items were not consumed in that period they
need not be included in the calculation.
5) Spare parts are a unique class. Unlike other materials, the consumption
value of spare parts is very little in comparison to their stock value.
This is due to the unique relationship of safety stock-this may be as
high as 0.5to5or times the annual consumption value, or even more. For
the many nonmoving items (in particular, the insurance items) the
consumption in several years may be nil. In these cases, one refers to
their inventory in terms of years of stock, whereas the Stock of raw
37
Maintenance Resource
Management and Costing materials is in terms of days or weeks of consumption. Therefore in
case of spare parts, ABC analysis of consumption value is less useful
than ABC analysis of stock value (except as explained below). For
the ‘A’ items from the latter analysis, steps could be taken to examine
why the stocks were so high , whether they could be sold off, whether
the inventory parameters were incorrect, whether they could be shared
by other units etc.
This time Anil was on surer ground. He had understood the purpose of
theoretical analysis and its relationship with practical utility. He had been
so struck by the complexity and challenges in spare parts management that
he volunteered and was sent for a special training program on spare parts
management.
The following example will show the calculations using different value of A and T:
Let A=Rs.2,000 Rs.20,000 Rs.50,000
Q=Rs.4,000 (Common for all cases for illustrative purposes)
T= 1 yr 5 yrs 10 yrs 1 yr 5yrs 10 yrs 1yr 5yrs 10yrs
1-[(Q)/(A) (T)]= 0.00* 0.60 0.80 0.80 0.96 0.98 0.92 0.98 0.99
*In this case, the assurance level becomes negative. Negative or Zero assurance
means that no safety stock is needed (k = 0). The high OQ itself gives the
protection against stock out.
The appropriate values of k, the safety factor to be used to calculate safety
stock can now be read off from a table of Poisson probabilities. Typically, if
A=Rs.20,000 and Q = Rs.4,000 then for T=1 year, the assurance level works
out to 80% for which the value of k ( from Poisson tables) is 0.80. For T = 10
years, k will be 2.1. As will be seen, the value of k (and the safety stock
associated with it) rises as the ‘stock out-free’ period increases from1 year
to 10 years
In the Reorder Level (ROL) system, the ROL and Q are fixed but the time for
replenishment varies inversely with consumption. The ROL is like the ‘reserve’ in
the fuel tank of a motorcycle. Replenishment quantity is always the same i.e. full
tank, but the time for replenishment will vary.
Order is placed at A,B,C etc; stock is received at D,E,F, etc after Lead Time
(LT), and Quantity on order = Liability – Assets
= [Consumption during (AB+BE)+SS}]-[Stock on
hand and on order]
= [Consumption during AE] + [AH+0], (assuming
that no order was pending)
= HG
39
Maintenance Resource G
Management and Costing
LT LT LT
0 A D B E C F
Weeks
Figure 7.6 : An ordering cycle with a review period of six months
SS is calculated as for the ROL system using the appropriate safety factor, k.
Thus, if the consumption during Review Period Plus LT was 50, the SS was 10,
the stock in hand was 20 and the stock on order (also called ‘dues in’) was 12,
the OQ can be calculated as under:
OQ = Liability – Assets = (50+10) – (20 +12) = 60 – 32 = 28
Theoretically, this system requires higher safety stock than the ROL system but
in both systems, for most spare parts the error caused by rounding off fractional
order quantity overshadows the precision of other calculations and this
disadvantage can be ignored. The review cycle can be matched to the supplier’s
production cycle so as to get stable, predictable lead times for supply- especially
for the parts that are not normally sold off the shelf through a dealer network.
All spares from the same suppliers can be packed and transported together
cheaply, unlike the piecemeal – and hence expensive- deliveries for the ROL
system. Therefore, large transport companies who deal directly with their
suppliers prefer this system. Those having distributed stocks of spares (users or
dealers), obviously have to use this system. It does not need the excessive
amount of documentation of the ROL system. An ‘Economic Review Period’ can
also be calculated for this system. However, for the same reasons mentioned
earlier for the ROL system, other factors (such as matching with supplier’s
production cycle etc) neutralize the economic advantage.
7.3.9 Slow Moving Items
The consumption rates for fast moving items can be assessed fairly accurately
even without any consumption data. Later, data accumulates quickly and the rates
can be updated fast. The relative period-to-period variation in consumption
increases as the mean value of a Poisson distribution goes down. For items
having low consumption rates, consumption data over moderate period does not
give a reliable average; an average based on short periods is extremely
unreliable. Most spares fall into this category.
The variation of consumption from period to period is so great that any moving
average that we may use will have large error. Basing the SS on the ‘higher-
40
than-true-average’ will further inflate safety stock. Hence, we have to apply the Information Technology
statistical approach of ‘Prediction Intervals’ in which the ROL is calculated from (IT) Enabled Maintenance
Management
the following formula:
When M, the consumption during LT is only a small fraction, the rounding off
error is large, as can be seen from the following examples. (k is kept at 2.1 for
all values of M, for easy comparison).
The rounding off error in the last two cases is (-100% to + 40% ) and (-100%
to + 350%). This will increase further for still lower consumption rates (i.e. for
very long life items). The safety stock given is already large, since k=2.1 (98%
assurance). Rounding off adds still more to safety stock. If these spares are
extremely critical (and expensive) both the options i.e., of stocking zero or 1 are
wrong, have a large margin of error, and extremely expensive. Such spares are
called ‘insurance spares’. They are indeed in the nature of insurance as both the
options have a large order of error.
41
Maintenance Resource The maintenance engineer naturally prefers to stock these items (which
Management and Costing eventually become the non-moving items) whereas the high cost of stocking
makes the management question the wisdom of stocking them. This decision has
to be made on the basis of risk/cost relationship. Thus, if C1 = Cost of the spare
(as quoted by the supplier at the time of buying the machine), say Rs.1 lakh, C2
is the expected loss due to non-functioning of the machine during later period of
its life, say Rs.20 lakh, then the ratio (C1/C2) = 1/20=5% can be used as a
‘break even point’ for making this decision. The maintenance engineer makes his
best judgment as to whether the probability of requiring the spare part during the
lifetime of the machine would exceed this figure, if it is likely to, then the spare
is to be stocked; otherwise the decision is postponed till more experience on the
machine is available. At that point the same question is again asked.
Rotables/Floats/Repair Pool
A repairable item or assembly is called a rotable, float, or repair pool. It goes
through a repair cycle. That can be treated as the LT, the other calculations
being the same as for other repair parts. They, amongst the installed costly
electric motors (‘A’ item) of a particular model which is also very critical to
production (‘V’ item) there are on an average 3 failures per year. The Repair
cycle time (treated as LT) is two months. A-V items are given 85% assurance
in this organisation (k=1.0).
.............................................................................................................................
.............................................................................................................................
.............................................................................................................................
.............................................................................................................................
42 .............................................................................................................................
Information Technology
7.4 MANAGEMENT INFORMATION SYSTEM (MIS) (IT) Enabled Maintenance
Management
The MIS for spare parts is similar to that for other materials and has the same
aims. Typical reports generated by the MIS are:
• Stock and Consumption Status Report
• Pending Indents Report
• Pending Purchase Orders Report
• Stock-out Report (also dangerously low stock position report)
• Over-stock/Under-stock Report
• ABC analysis- separately for repair items and overhaul items
In addition, the computer should automatically adjust the inventory parameters,
such as ROL, SS, LT for routine indenting. Special’ ‘alerts’ may be build into
the system to identify deviations from expectations e.g. sudden rise/fall of
consumption rates of spares. Typically, a sudden increase in the usage rate of a
component may be due to related increase in failure rate, which in turn could be
due to poor quality for latest supplier. If the drop in consumption of a part is
accompanied by sudden rise in the consumption of the assembly into which is
goes, evidently for some reason maintenance had started replacing assemblies
instead of parts.
The range of spare parts is so vast that computers have to be sued for getting
replies to the numerous queries that will arise in managing spare parts.
Activity E
Design a MIS for spare parts inventory management in your organisation or in an
assembly unit. Which type of reports you are likely to get from your spare parts
MIS?
.............................................................................................................................
.............................................................................................................................
.............................................................................................................................
.............................................................................................................................
.............................................................................................................................
Cost due to and of spare parts occurs as (a) Cost due to non-availability when
required for the machine, (b) Consumption value (c) Inventory carrying cost, and
(d) capital cost of non-moving items. To minimize the need for troublesome
repair parts, operations must prevent failures, and maintenance must ensure that
maintenance is done on time and is of high quality. Maintenance must give top
priority to eliminate failures requiring the high cost items that are also critical.
Worn parts can often be rebuilt at a fraction of the price of new parts.
Standard parts, low LT, purchase from OEM/reliable suppliers will reduce cost.
Simple procedures, using computer for scientific analysis and updating of
inventory parameters will reduce the operating cost of the spare parts system.
Maintenance must assist in identification, preservation, and inspection of
spare parts.
43
Maintenance Resource
Management and Costing 7.6 ORGANIZING FOR EFFECTIVE SPARE PARTS
MANAGEMENT
In large organizations there should be a ‘spare parts cell’ consisting of a
representative each of maintenance, purchasing, and stores. Apart from initiating
the indents, this cell should operate the MIS and continuously look for
improvement in inventory control and cost control, introduce computers for MIS,
carry out various analyses, and in general, act as ‘internal consultants’ in the
complex area of spare parts management. They should report to a senior level in
the Technical Services Department. The members of the cell should develop
expertise in this area. In a medium size organisation the spare parts cell may
have part-time members. They should report to the Chief of materials. This
places the responsibility of planning and providing spare parts squarely where it
belongs. In small organizations, only those maintenance engineers who are trained
in scientific inventory control of spare parts should be allow ed to indent spares
parts. Their services should be utilized during a period (say, every two or three
years) updating of the system as a whole.
7.8 SUMMARY
Managing spare parts is the biggest challenge in materials and maintenance
management. With the scientific tools available now, much improvement can be
achieved, provided those tools are used. The spare parts go through six stages in
their life cycle: Design and specifications; Determination of initial requirements;
44
Procurement; Storage and preservation; Issue and replenishment; Disposal and Information Technology
damaged, surplus and obsolete spares. Like inventory management, ABC and (IT) Enabled Maintenance
Management
VED analysis play important role in spare parts management. For low
consumption and slow moving spares, the re-order level has been computed. MIS
of spare parts management can be effectively used for preparation of reports for
stock and consumption, pending indents, purchase orders, stock-out etc.
1) What is the aim of spare parts inventory management? In what way does it
influence the different stages of the life cycle of spare parts?
2) What are the different types of spare parts, and when are they used?
3) What is EOQ? Why is the EOQ formula not useful for spare parts?
4) What is Pareto’s Law? In what ways is it used for spare parts?
5) What is VED analysis and how is it used?
6) Using the following decision matrix calculate the ROL for the following
spares:
7) Which problems are unique to spare parts that other materials do not exhibit?
Why do these problems occur?
Anil found this analysis intriguing. At the business school he was told that usually
about 15% to 20% of the range of the items in an inventory contributed to some
70% to 80% of the total annual consumption value. Books on inventory control
also quoted these figures while referring to the lopsided behavior of inventory
costs with respect to range. The present analysis showed a far more lopsided
pattern. He had not overlooked a single item in the inventory. He had even
included the sweeper’s brooms.
While doing the analysis he had been a little undecided about how the annual’
usage value’ of nonmoving items was to be included-since the consumption was
zero. Should he remove them from the analysis? But then, some of them had
been issued only a few weeks or months before the year under consideration.
How was he to allow for their cost contribution? would it be better to take a
two-year data? If yes, why not a five-year data base?
Not having any answer to this question for the non-moving items, he just decided
to ignore the consumption value but used the stock value in stead. He made an
appointment with Onkar to show him what he had done. With much enthusiasm
he explained to the older man, the great advantages of ABC analysis for the
management of inventory, he also explained the steps that could be taken to
control the top few high cost-contributing items as explained in various textbooks
on materials management, which he had avidly studied in the business course.
His big problem was that the maintenance engineers were never happy about
supply of parts. He had to accept their indents, even when he felt that the
quantity indented was inflated. His function did not permit him to question the
maintenance engineer’s judgement. All too often, the indents from maintenance
were delayed too much and left no time for him to procure. Rush purchases
had become the rule.
Suggested Response: The GM was concerned with avoiding the need for
spare parts in the first instance
Follow up on the Above Discussion:
Operations manager had nothing to say but the maintenance manager had
realized that this was the same ABC pattern he had heard about somewhere in
connection with materials but did not know enough about it. The same pattern
was obviously applicable to the frequency of failures too. In answer to the
GM’s query, he said that the top few faults, which caused the most interruptions
to machine operation, had to be attended to first. The GM then went a stage
beyond. He stated that more than attending quickly to the repair of the top few
faults it was necessary to see that they did not occur at all. He discussed this
further with the other managers and gave the following decisions:
1. Maintenance and operations should jointly study the causes of the top 14
faults in the frequency table above and go all out to reduce their occurrence.
They should be given higher priority to those faults, which took longer time to
rectify, and/or needed expensive spares.
2. At the same time, the spare parts manager should show the ABC analysis of
annual consumption value of spare parts and give a list of the ‘A’ items to
maintenance to see that the faults that needed these spares were also
included in the list for reduction of failures.
3. Spare parts manager should look into the reasons for accumulation of the ‘A’
items from the ABC analysis of stock value and jointly with the maintenance
manager take steps to avoid this in future. Maintenance should also find
alternative uses for these items. If any of them were truly in excess of
foreseen needs, they should be disposed off.
4. Progress should be reported in the next two conferences.
Requirement II: What is the most important lesson you can draw from this Cost
Study?
Suggested Response: Spare parts management begins with minimizing their
need in the first instance.
49