PaperID 22-404
PaperID 22-404
Abstract- Northern areas of Pakistan are endowed with vast hydropower generation
potential. Many micro-hydropower plants (MHPP) working in private and public sectors
are without proper engineering design. The proposed project has been designed on a stream
in the peochar valley, Swat, Pakistan. The stream is having enough discharge and most
importantly adequate head that can be easily available to generate electricity. The flow data
of the stream was collected from SRSP’s office. For suitable positioning of civil
components of the hydropower plant, a survey has been made to mark proper points. Such
point was marked which had a large head because greater the head, the more is the capacity
of the plant. A favorable point on the stream was selected where diversion works were
designed to divert a part of water from stream to a canal. Canal conveys water to the settling
basin and forebay. Through the penstock, water strikes the blade of turbine and generate
electricity. The net head obtained at the site is 76ft. The designed discharge was determined
to be 10 cusec. After determining these parameters, the design of civil components was
undertaken. The approach channel dimensions were designed to be 2.5 ft × 2.24 ft. Settling
basin forebay were designed according to the design discharge. This plant was designed to
have a power generation capacity up to 40 kW.
Keywords- Micro-hydro power plant, Hydropower generation, Stream water flow, Green
Energy
1 Introduction
There is a very rapid depletion of non-renewable resources for generating electricity and the electricity demand is
increasing due to the growing population and the desire for standard living. According to an estimation, presently more
than 1.5 billion people are deprived of access to electricity throughout the world [1]. Pakistan is also facing multifaceted
challenges in the power sector and almost 50 million people are having no access to the electric grid [2]. Alternatively,
harnessing water, tidal and solar energy can overcome the power shortages and to meet the electricity. Subsequently,
MHPP is considered one of the desirable sources for power generation because of its environment-friendly nature and
extensive potential available throughout the world [3]
The energy of the moving water is used for the generation of hydropower. The energy production from moving water dates
back to ancient Greek times. Ancient Greek used to grind wheat into flour by rotating wheels through moving water. The
water wheel is placed in a stream that picks up the moving water in buckets. The kinetic energy of the flowing water turns
the wheel and is converted into mechanical energy that grinds the wheat into flour. In the late 19 th century, a tremendous
development had been made to generate electricity from hydropower. Many MHPP working in private and public sectors
are without proper engineering design. In the present study, the work has been carried out to propose and design MHPP
on a stream in the peochar valley, Swat, Pakistan. The stream is having enough discharge and most importantly, sufficient
head that can be easily used to generate electricity for the local people. The flow data of the stream was collected from
SRSP’s office.
2 Design Methodology
Design methodology deals with the numerical background related to design of the micro hydro power plant. It involves
the identification of some basic equations and relation to be used for the project. In the present work, two types of design
methodology are involved: 1) Hydraulic design and 2) structure design.
a) b)
The size of slope and cross-section of an approach channel should be designed in such a way that the required turbine
discharge (design discharge) can be economically traveled to the head tank (fore-bay). Generally, the size of cross-section
and slope are interrelated. During the designing of a channel, the slope should be not higher to prevent more head loss.
This gentler slope will produce low velocity and ultimately result in greater cross-section. On contrary, when the slope is
steep, the velocity will be higher and resulting in smaller cross-section but the head loss, in this case, will be more. The
cross-sectional shape of canal is decided according to the site conditions and stability. It may be rectangular, trapezoidal
or some other possible shape. By using Manning’s equation find the depth and width of the channel.
𝟏.𝟒𝟗 𝐀 𝐑𝟐/𝟑
Q= (2)
𝐧
×
= = 1.26H (3)
. √
The equation (3) provided the height of approach channel. Provided with height, calculating the width and Cross-sectional
area of the channel by W = 2H and A = W x H respectively.
When the flow is diverted from stream or river, there are some suspended particles. The settling basin is used to settle
down these suspended particles. Settling basin has two portions: the first portion is called sand trap which settles down
smaller size particles and the second portion is called gravel trap which settles down larger particles. There are different
components of settling basin like, inlet zone, settling zone and outlet zone as shown in Figure 2.
a) b)
×
𝐿 = (4)
( × )
D = (5)
( × )
Where, Dc = average collection depth, 𝑉𝑂 = volume of silt stored in the basin in m3 and Ls = Basin length
2.1.4 Design of fore-bay
Structurally, the fore bay and settling basin are same but in forebay, outlet transition is replaced with a trash rack. The
typical fore bay for MHPP is shown Figure 3. The recommended size for forebay should be such that a person can go
inside for cleaning and at least once a year to repair.
It has been recommended that the minimum submergence head for a penstock should be calculated as below:
𝑽𝟐
𝒉𝒔 ≥ (6)
𝟐𝒈
For the design of the weir and approach channel, different moments are calculated and sliding and overturning stability
checks are applied to check the stability. For the structural design of the settling basin, determine the dimension (length,
width and height) of the tank from hydraulic design. The tank should be designed according to the situation (whether the
length to width ratio is more or less than 2), so in this case it is more than 2. Thus, assuming the long wall is a cantilever
and the short wall to act like a beam with both ends fixed. In the present study the shape of the tank is rectangular. The
tank that is resting on ground the slab, the slab should be designed in such a way that it can safely transfer water weight
and the structure self-weight to the ground. Normally, the floor slab thickness ranges from 150 mm to 250 mm with a
minimum of 3% reinforcement.
Intake structure
Approach Channel
Discharge Slope (S) Max Velocity Height Width (W) Area (A) Actual Depth of
(Q) (Vmax) (H) Velocity (V) Approach
Channel
10 cusecs 1/500 4.92 ft/sec 1.24 ft 2.48 ft 3.09 ft² 3.23 ft/sec 2.24 ft
Width of Settling Settling Silt Load Silt Density Volume of Collection Depth
Discharge Settling Velocity of Basin (𝑺𝒍 ) (𝑺𝒅 ) Silt (𝑽𝑶𝒔 ) required for
(Q) Basin (Ws) Particles Length (Ls) settling basin (𝑫𝒄 )
(Vv)
10 cusecs 4.94 ft 0.197 ft/s 16.2 ft 12096 kg 73.68 kg/ft³ 328.34 ft³ 4.1ft
Design of forebay
Discharge Storage Volume Length Width Actual Velocity Min head in Storage Min
(Q) Capacity (V) (L) (W) Depth in Fore-bay Req Depth Depth
of Fore- Penstock above crown (𝒉𝒔 ) (𝒅𝒃 ) (𝒉𝒔 +
bay 𝒅𝒃 )
10 cusec 60 sec 600 ft³ 16.1ft 4.94 ft 7.5 ft 9.8 ft/sec 2.25 ft 1 ft 3.25 ft
Approach Channel
Discharge Slope (S) Max Velocity Height Width (W) Area (A) Actual Depth of
(Q) (Vmax) (H) Velocity (V) Approach
Channel
10 cusec 1/500 4.92 ft/sec 1.24 ft 2.48 ft 3.09 ft² 3.23 ft/sec 2.24 ft
Design of long wall Design of short wall Design of base slab for settling basin
and forebay
12 inches #4 bar @ 9in c/c #4 bar @ 9in c/c 6 inches #4 bar @ 9in c/c
4 Conclusion
In this study, the design of different components of Peochar MHPP is done by using standard rule and procedure. The
different components include; the intake structure, approach channel, settling basin and forebay are designed. From the
hydraulic design the sizes of these components are determined. The results obtained from the redesign are more economical
as compared to the existing MHPP at the site. MHPP will tremendously improve the socio-economic life in northern
regions of Pakistan. This will ultimately reduce the wood cutting issue which northern people are using for energy
consumption, particularly in the winter season. This will result in discouraging deforestation and ultimately preserve the
ecosystem.
5 Recommendations
The following recommendations have been suggested in these studies:
• The proposed project in the present studies, is economically viable and it can be attractive for private investors. Therefore,
the government of KPK should invite and encourage the private sector to take up this project for implementation.
• A single turbine unit has been proposed. In future, a design scheme having two smaller turbine units equivalent in capacity
to a single unit could be worked out. This would be beneficial in a way that during lower flows a single turbine unit would
be operational while during full design flow both the units will be working.
• In the proposed scheme, economic analysis is done by doing an economic comparison between the proposed MHPP and
an equivalent capacity thermal power plant. Another way of doing this economic analysis is through Long Run Marginal
Cost Method (LRMC). An economic study based on LRMC could be done in the future.
References
[1] K. Sørnes, "Small-scale Water Current Turbines for River Application," p. 24, 2010.
[2] F. Z. Hussain Samad, "Electrification and Household Welfare evidence from pakistan," South Asia
Region Office of cheif economist, 2018.
[3] A. Wube, "Design and Analysis of Small Hydro Power for Rural Electrification," vol. 16, no. 6, 2016.
[4] BINOD PANDEY 2011, “design of micro hydro power plant”
[5] Anil Kunwar, 2012, Bachelor degree Thesis on “Technical Specifications of Micro Hydropower System Design”.