Reporting Point in REM
Reporting Point in REM
Nilesh S. Pagar
SAP PP Consultant
P a g e 1 | 14
SAP PP – REM Reporting Point
To do this, operations are defined as reporting points and the backflush is carried out at these reporting points
➢ Prerequisites:
➢ To carry out a reporting point backflush for a material, you must have assigned an appropriate Repetitive
Manufacturing Profile to the material in the material master record.
➢ This type of backflushing corresponds to the milestone confirmation. Therefore, in the routing, you
must
select a control key which has indicator 1 (= milestone confirmation) in the confirmation field.
➢ You must have entered the routing in the production version of the material. If you create a run schedule
quantity for the material to be produced using this routing, the operations with the control key for
milestone confirmations are then automatically copied to the run schedule header as reporting points.
When
creating a run schedule header, the system first tries to copy the routing entered in the detailed planning
section. If no entry exists here, the system then uses the routing from the rate-based planning section.
Nilesh S. Pagar
SAP PP Consultant
P a g e 2 | 14
SAP PP – REM Reporting Point
➢ Features
➢ A separate function exists in the main menu of Repetitive Manufacturing for the reporting point backflush.
➢ When backflushing at reporting points, the system backflushes all materials that are withdrawn and
consumed at the reporting point operation and at the previous operations. The system also determines
costs. If you backflush a production quantity, the system reduces the dependent requirements of the oldest
run schedule quantities.
➢ In the repetitive manufacturing profile, you can set that the goods receipt is automatically posted when
backflushing the last reporting point. The system does not reduce capacity quantities until backflushing the
last reporting point.
➢ You can also backflush actual times. The production activities are then posted based on the time that
was taken for production.
➢ You have two options for backflushing scrap:
o Assembly scrap
o Component scrap
➢ If you backflush assembly scrap, the system backflushes production activities, and the goods issues for the
components. If you backflush component scrap, the system only backflushes the goods issues for the
components.
Nilesh S. Pagar
SAP PP Consultant
P a g e 3 | 14
SAP PP – REM Reporting Point
➢ Configuration:
➢ Go to the following path or go to transaction code OSP2 to create REM Profile
Nilesh S. Pagar
SAP PP Consultant
P a g e 4 | 14
SAP PP – REM Reporting Point
In the profile we need to check RP backflush and need to select whether you want optional or mandatory
Nilesh S. Pagar
SAP PP Consultant
P a g e 5 | 14
SAP PP – REM Reporting Point
➢ Master Data: -In the MRP 4 view of material master you need to check Repetitive mfg. indicator and assign the
repetitive mfg. profile
In REM Profile, also you need to create production version.
Nilesh S. Pagar
SAP PP Consultant
P a g e 6 | 14
SAP PP – REM Reporting Point
➢ Routing: -Also you can create Routing or Rate routing with the control key which supports milestone
confirmation, In the routing below both operations are milestone operations, One material assigned for each
operation
Nilesh S. Pagar
SAP PP Consultant
P a g e 7 | 14
SAP PP – REM Reporting Point
Nilesh S. Pagar
SAP PP Consultant
P a g e 8 | 14
SAP PP – REM Reporting Point
➢ Product Cost Collector: - Go to KKF6N to create Product Cost Collector with production version as the option
to create it.
After calculation cost, system shows the BOM and routing with costs.
Nilesh S. Pagar
SAP PP Consultant
P a g e 9 | 14
SAP PP – REM Reporting Point
After MRP run planned order type PE (Run Schedule Header) is created.
Nilesh S. Pagar
SAP PP Consultant
P a g e 10 | 14
SAP PP – REM Reporting Point
▪ Backflush: - In MFBF backflush you need to enter planned order number and click on RP Backflush and Enter
Nilesh S. Pagar
SAP PP Consultant
P a g e 11 | 14
SAP PP – REM Reporting Point
Nilesh S. Pagar
SAP PP Consultant
P a g e 12 | 14
SAP PP – REM Reporting Point
Nilesh S. Pagar
SAP PP Consultant
P a g e 13 | 14
SAP PP – REM Reporting Point
After all reporting point will get posted, Stock will be updated in MD04