03 Master Schedule For Flat House 3F

The document outlines the tasks, duration, start and finish dates for a flat house construction project. It involves preliminary works over 5 days in November 2017, followed by structure works over 84 days through early February 2018. Various architectural, electrical, air conditioning, plumbing and defect works are then scheduled from January through July 2018, with a total project duration of 242.75 days ending in early July 2018.

Uploaded by

nita168saang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views1 page

03 Master Schedule For Flat House 3F

The document outlines the tasks, duration, start and finish dates for a flat house construction project. It involves preliminary works over 5 days in November 2017, followed by structure works over 84 days through early February 2018. Various architectural, electrical, air conditioning, plumbing and defect works are then scheduled from January through July 2018, with a total project duration of 242.75 days ending in early July 2018.

Uploaded by

nita168saang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start Finish

September 2017 January 2018 May 2018


September 1 November 1 January 1 March 1 May 1 July 1
9/24 10/22 11/19 12/17 1/14 2/11 3/11 4/8 5/6 6/3 7/1 7/29 8/
1 Flat House 3F @ TK 242.75 days Sat 11/11/17 Wed 7/11/18 11/11 242.75 days
2 Preliminary Works 5 days Sat 11/11/17 Thu 11/16/17 11/11 5 days
3 Temporary site fencing 5 days Sat 11/11/17 Thu 11/16/17 5 days 11/11
4 Temporary worker camp, toilet 4 days Sat 11/11/17 Wed 11/15/17 4 days 11/11
5 Structure Works 84 days Sat 11/11/17 Sat 2/3/18 11/11 84 days
6 Basement works 22 days Sat 11/11/17 Sun 12/3/17 11/11 22 days
24 GF Structure Works 21 days Sun 12/3/17 Sun 12/24/17 12/3 21 days
44 1F Structure Works 14 days Sun 12/24/17 Sun 1/7/18 12/24 14 days
60 2F Structure Works 14 days Thu 1/4/18 Thu 1/18/18 1/4 14 days
76 3F Structure Works 14 days Mon 1/15/18 Mon 1/29/18 1/15 14 days
92 4F (Roof) Structure Works 8 days Fri 1/26/18 Sat 2/3/18 1/26 8 days
98 Architect Works 242.75 days Sat 11/11/17 Wed 7/11/18 11/11 242.75 days
99 Wall and Partition 184.88 days Sat 11/11/17 Mon 5/14/18 11/11 184.88 days
117 Wall Finish 85 days Mon 3/12/18 Mon 6/4/18 3/12 85 days
126 Floor Finish 73 days Sun 4/1/18 Tue 6/12/18 4/1 73 days
141 Ceiling Works 146.88 days Thu 2/15/18 Wed 7/11/18 2/15 146.88 days
158 Door and Window 162.88 days Sat 1/13/18 Sun 6/24/18 1/13 162.88 days
186 Other Works 56 days Sun 3/11/18 Sat 5/5/18 3/11 56 days
205 Electrical Works 69.88 days Tue 1/23/18 Mon 4/2/18 1/23 69.88 days
206 GF Electrical works 50.88 days Tue 1/23/18 Wed 3/14/18 1/23 50.88 days
214 1F Electrical works 37.88 days Sat 2/3/18 Mon 3/12/18 2/3 37.88 days
221 2F Electrical works 34.88 days Tue 2/13/18 Mon 3/19/18 2/13 34.88 days
228 3F Electrical works 38.88 days Fri 2/23/18 Mon 4/2/18 2/23 38.88 days
236 Ari-con Works 68.88 days Tue 1/23/18 Sun 4/1/18 1/23 68.88 days
237 GF - Air Con Works 49.88 days Tue 1/23/18 Tue 3/13/18 1/23 49.88 days
241 1F - Air Con Works 36.88 days Sat 2/3/18 Sun 3/11/18 2/3 36.88 days
245 2F - Air Con Works 33.88 days Tue 2/13/18 Sun 3/18/18 2/13 33.88 days
249 3F - Air Con Works 37.88 days Fri 2/23/18 Sun 4/1/18 2/23 37.88 days
253 Plumbing Works 198.88 days Thu 11/30/17 Sat 6/16/18 11/30 198.88 days
254 Wast Water System 12 days Thu 11/30/17 Tue 12/12/17 11/30 12 days
264 Cold Water System 65 days Fri 12/15/17 Sun 2/18/18 12/15 65 days
273 Stom Water System 73 days Fri 12/15/17 Mon 2/26/18 12/15 73 days
282 Sanitary Fixture 12 days Tue 6/5/18 Sat 6/16/18 6/5 12 days
287 Defected Works & Final Cleaning 7 days Sat 11/11/17 Sat 11/18/17 7 days 11/11

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Project1 Milestone External Tasks Inactive Summary Manual Summary Deadline
Date: Tue 8/1/17 Split External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only