Method Statement Hdpe Welding PDF Free
Method Statement Hdpe Welding PDF Free
NOTE: This document and all its contents is the property of CHEC. It is confidential
and is given to you for a limited purpose and must be returned on request. Neither this
document nor any information concerning it can be copied, exhibited or furnished to
others without the consent of CHEC
Table of Contents
1. Purpose of the Method Statement ................................................................................ 4
4.Welding procedure.......................................................................................................... 4
5. Welding ..........................................................................................................................17
9. Resources .....................................................................................................................28
3. Referenced Document
4.Welding procedure
4.1General Description
All the connections of the HDPE pipes and fittings will be performed by
electrofusion welding.
Two different connection systems will be used for the project depending
of the type of the pipes to be connected:
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 5 / 34
All the project stub ends will be welded by using Intern al/External
electrofusion couplings.
the gaps are closed, the continued melt expansion gene rates pressure within
the heated zones.
The electrofusion wires will be installed on site in order to avoid the wire
corrosion or wire damages which could happen during the materials transport
to the site or during the pipes & fittings storage and handling.
The pipe’s inner diameter will be taken as the reference for the pipe milling
control. The welding supervisors shall also determine whether is required to cut or
not some pipe end (in case the pipe end is damaged or in case it had lost its
perpendicularity).
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 9 / 34
The placement of the pipe on the grinding machine shall be done taking care in
order to avoid damaging the support wheels of the milling station which will support
the HDPE pipes.
The pipe shall be positioned properly centred in the machine. This task can be
performed with the help of a forklift or of the gantry cranes.
In case the pipe cutting is required, the circular saw shall be placed in the
‘cutting position’. For the right positioning of the saw it is required to check the
parallelism between the circular saw support and the pipe support.
Once the saw is switched on, a full turn of the HDPE pipe will be performed in
order to mark the position where the cut will be made, subsequently beginning to cut
the section ensuring that the saw maintains the perpendicularity with the pipe.
Both the speed and movement of the saw will be regulated as per the welding
supervisor instructions.
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 10 / 34
Once the cutting of the pipe is finished, the pipes ends milling may start.To
perform a proper grinding of the pipe ends, the reference support shown in the
picture included below, which takes into account the pipe’s inner face as a
reference.
The speed and the movement of the grinder tool will be adjusted in order to
mill 250mm pipe length (extra-thickness length).
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 11 / 34
The pipes are supported over provisional removable (two halves) and
adjustable in height supports.
The pre-casted concrete ballasts have been previously placed over the
concrete ramp.
The two pipes ready to be welded will be placed in front one of each other on
the ramp. Once supported and aligned they will be approached.
The purpose of the hydraulic internal ring is to keep in contact the surfaces
to be welded. These tools are able of re-rounding the pipe keeping the couplings
and the pipe ends in contact. As the polyethylene surfaces melt they also expand in
volume to close any gaps between the pipe and fitting. After the gaps are closed,
the continued melt expansion generates pressure within the heated zones.
- External clamp.
The external clamps work together with the internal ring in order to re-round
the pipes to be welded, ensuring that the parts to be melt are in contact.
Once the internal tensioning ring, the external clamp and electrofusion
couplings are placed in its final welding position the tensioning tools shall be
adjusted (centring and tightening). If necessary, wooden or metal wedges may be
used to help in this task.
Once the internal ring is pressurized, the couplings installed and the external
clamp is tightened, the welding process may start
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 14 / 34
The PR profile pipes (corrugated external surface) will be welded by welding the
pipes socket-Spigot ends. Every PR pipe is supplied including one spigot end (male)
and one socket end (female).
The pipes & fitting´s socket incorporate integrated electrofusion wires. With the
tension transmitted by the welding machine, the electrofusion wire generates the
needed heat to melt together the material of the socket and the spigot end.
The socket and the spigot ends have a specific ‘taper’ to improve the connection
between them.
One electrofusion wire will be installed on every socket end. This wire will be
composed by two halves, requiring therefore using simultaneously two welding
equipments to perform each welding.
The internal tension ring keeps in touch molten material of the male (spigot) and
the female (socket) ends during the welding process.
We describe below the steps required to perform an electrofusion welding of
every socket / spigot connection:
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 15 / 34
EXTERNAL CLAMP
WELDING ADAPTOR
SOCKET END
ELECTROFUSION
WIRE
SPIGOT END
5. Welding
Each weld must be numbered in order to control its traceability and that
the welding procedure has been accomplished d*uring its execution. The way
of numbering the welds shall ensure that:
▪ Each weld is own number and that this number is not repeated in the
project.
▪ The numbering of the welds shall not affect the welding execution. It must
be noted that the welds will be performed in the ramp or in the stock in
order to store 12/18 meters welded pipes.
The project requires performing DN1800 welds for the intake pipelines
and DN1600 welds for the outfall pipelines. Each Intake pipeline is split in 8
sections and each outfall pipeline is split in 9 sections. The DN1800 intake is
composed by two pipelines and the DN1600 outfall by other two pipelines.
For every weld, a welding control sheet shall be fulfil by the welding
supervisors in order to record the weld traceability.
The cleanliness is one of the critical points of any weld therefore special
care is required to perform this task. The use of water to clean is not allowed
as the water could remain affecting the welding. The cleaning of the surface
areas to be welded shall be performed by using isopropyl alcohols or similar
as the alcohol will be evaporated avoiding any rest of it affecting the welding.
Rags or paper (materials which do not leave residues) shall be used to wipe
the surfaces to be cleaned.
Once the electrofusion welds are finished (including the cooling times )
the internal extrusion welds shall be done.
The purpose of the internal extrusion welds is to allow testing the
electrofusion welds but these welds provide additional advantages as to
minimize the hydraulic losses of the connections softening the weldi ng
surfaces.
For the electrofusion welds performed with electrofusion couplings,
the below listed internal extrusion welds shall be performed:
- Where both faces of the internal electrofusion fitting meet
- Where both faces of the external electrofusion fitting meet
- In the ends of the internal electrofusion fitting around the entire
circumference.
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 20 / 34
The spark produced by the high frequency tester detects the conductive
material installed on the electrofusion internal coupling ends in case there is
any pore in the weld.
The inner surface of the spigot end of the pipes to be tested will be
drilled on site with two holes (ᴓ 12-14 mm). These holes will communicate
with the air camera generated in each electrofusion welding, as represented
below.
In one of the holes a valve will be screwed. This valve will allow
introducing air inside the chamber generated between electrofusion welding
and the extrusion welding.
The second perforation, it will work as an air outlet. Before fil ling the
chamber with air, a properly screwed manometer will be installed. This
manometer will verify the pressure to be applied and it will close the
perforation.
Introduce pressurized air using the inlet valve with the manometer
installed. Increase the air pressure up to 1 Kg/cm 2 .
Keep the system pressurized for about 20 minutes. During this time the
joint shall be inspected looking for any leak or defect.
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 24 / 34
Figure 24. Left - Air chamber Inlet valve and manometer. Right pressure
test.
Keep the staff informed about the work scheduled. Avoid the presence of
non-specialists in the work environment.
In the case that pressure test detects any problem in the electrofusion
welding. The welding can be repeated as defined in electrofusion welding
procedure.
After repeated the weld it the pressure test can be repeated. If the
results are successful the leak has been solved. Otherwise proceed with the
installation of an internal electrofusion fitting inside the pipe over the joint.
Once the extruder weldings have been performed the second phase casting
of the concrete ballasts should proceed.The process shown as following.
(1) Place the concrete ballasts on the steel rollers suitable for the movement
over the rail of the ramp. Check that the concrete ballasts are centered over
the rails.
(2) Shifting the concrete ballasts over the rails to center them on the axis of
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 25 / 34
the pipe weldedjoints. Use tools to perform this operation to facilitate the
maneuver.
(3) Place the formwork for the second phase cast. The formworks will have
an octagonal shape, as shown in the photograph below.
(4) Two workers will be at the top of the pipe pouring the second phase
concrete with a concrete bucket through the prefabricated hole located on
the top part of the concreteballast, arranged for this purpose. The concrete
will be poured from the casting tank or concrete bucket into the ballast filling
hole using a funnel
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 26 / 34
(5) Once the setting time of the second phase concrete has finished,
remove the formworks.
8.RECOMMENDATIONS TO COMPLY
9. Resources
Main manpower and equipment are listed in table1 and table2: (tentative
quantity).Contractor shall work 2 shifts if necessary to increase production as
per schedule.
2 Foreman EA 2 In charge of
construction
workers
3 QC Inspector EA 2 Mechanical
and Civil Qc
inspect at site
5 Flagman EA 2 Guarding
Forklift
8 Welder EA 31 Welding
Activity
Transport,
4 Mobile Crane 50t 2
Casting
10.QUALITY CONTROL
A welding control check list including all the points described below will
be filled up for each and every welding performed which covers all the
technical data of each union:
RESPONSIBLE
CHARACTERISTICS FREQUENCY OF
ITEM TASKS DOCUMENT OF THE
TO CONTROL THE INSPECTION
INSPECTION
1 BEFORE WELDING OF PIPES
At the project Welding
1.01 WELDERS CERTIFICATE Document
beggining supervisor
As per method Welding check Welding
1.02 PIPE CUTTING Each welding
statement list supervisor
ELECTROFUSION FITTING
Each welding Welding check Welding
1.07 CLEANING INCLUDING BRASS Cleaning
list supervisor
WIRE
Each welding Welding check Welding
1.08 BRASS WIRE CONTINUITY Visual
list supervisor
- The work will be executed taking the appropriate safety precautions to avoid
an accident or incident when performing the activity.
- All personnel involved with the grinding and welding of pipes should use
their Personal Protective Equipment (PPE) consisting of helmet, goggles,
gloves, ear plugs, reflective vest and safety shoes.
- The working area should be defined and marked. Only authorized persons
who execute the activities described in this method statement are allowed
to enter the working area.
- Safety induction has to be done to the staff in charge of shifting the pipes to
the ramp (drivers, riggers, workers, etc.)
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 32 / 34
- Workers involved in this activity and those who are close to the work front
should compulsory use their Personal Protective Equipment (PPE)
consisting of helmet, goggles, gloves, ear plugs, reflective vest and safety
Method Statement for DOCUMENT CHEC-JECCP-80-GE-
JEC Commercial NUMBER MST-0018
Port Project
HDPE Pipes&Fittings
Welding Procedure REVISION A01
ISSUED BY CHEC ISSUED DATE 4 Dec 2017 PAGE 33 / 34
shoes, due to excessive and harmful noise which exceeds the maximum
permissible limits and is harmful to the health of workers.
- The workers involved in the pipes milling process should use earplugs due
to excessive and caused by the milling station.
- The workers involved in the pipe grinding should compulsory use
disposable safety masks which will protect them from inhaling polyethylene
particles that may be harmful.
- It is mandatory to switch off the cutting and grinding machine for reviewing
and checking for any inconvenience to avoid incidents or accidents.
- Only the staff responsible to perform the activity will be found on the work
front.
PIPE WELDING
- Promote training from the project manager to the last worker assistant, in
order to know the rules and always put priority on safety issues in their
work.
- For the selection of personnel to perform each task, it must be taken into
consideration the knowledge in health, safety and risk prevention, and
minimum requirements should apply.
- Continually develop staff training, in the theme of hazard identification and
risk assessment, until an acceptable standard of knowledge is achieved.
- Conduct safety briefings which are participatory and dynamic, so that
workers can take more emphatically security issues and may have greater
knowledge of the risks involved in each activity carried out in the field.