Method of Statement For Swirchgear
Method of Statement For Swirchgear
METHOD STATEMENT
FOR
22 KV SWITCHGEARS
SYSTEM
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
[email protected]
www.elsewedy.com
INDEX
1.0 Purpose
2.0 Scope
3.0 Reference
7.0 Procedure
1.0 PURPOSE
The purpose of this method statement is to provide the guidelines for 33KV GIS installation and associated
activities to satisfy all the relevant specifications and requirements.
2.0 SCOPE
This procedure shall be applicable to installation and testing of 33kV switchgears (GIS). The Procedures also
covers installation and testing of 33kV GIS under the project .
3.0 REFERENCES
IEC 60044-1
IEC 60044-2
IEC 62271-100
4.2 DEFINITIONS
Company : This shall mean Gulf for building & Construction or it’s nominated representative
He shall be responsible for overall execution, administration, monitoring and control of the project as per the
contractual requirements including but not limited to:
Assess manpower, equipment and other resources required to achieve targets set and co-ordinate with
RAY Management for obtaining necessary resources for the project and deploy as required
Coordinating for all the procurement and subcontracting activities related to the project.
Identify Training needs and Coordinate for fulfilling the Training Requirements.
Sequence of activities to be carried out for the work as per this work procedure
Contract specific requirements for installation and testing of earthing system, if any specified shall be
identified and the requirements of such specification shall prevail in addition to the non-conflicting
Toolbox talks with the concerned work force prior to start of the work is a mandatory requirement.
Ensure that relevant permits applied and obtained prior to the commencement of work.
Ensure all PPEs are available with all the workers involved in the work.
Ensuring the sufficient First Aiders and Fire Wardens are available with the crew.
Permit to work system shall be followed with due care wherever applicable.
Ensure all PPEs are available with all the workers involved in the earthing related works
All required equipment and tools should be checked before start of work for suitability and integrity.
Ensure that the work is done under the supervision of Supervisor I Engineer.
All necessary tools are to be taken along once and for all till the completion of the work.
Incidents I Accidents if any shall be reported to concerned authorities in the prescribed written format.
Flint gun for firing (Inspector Required for one joint at least)
Cleaning scrapper
Caution tape
Drilling machine
Hammer
Crimping tool
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
[email protected]
www.elsewedy.com
Earth tester
Multimeter
Spanners
7 PROCEDUR
7.1 Receiving
· 33kV GIS is either collected from the stores or received directly from the manufacturer's works. The
equipment shall be inspected (verify with purchase order, Delivery order, specification & FAT) for any
abnormalities and damage. In case of any damage, it is reported to manufacturer for necessary action.
Ensure the floor opening for the power I control cable as per the approved I AFC drawing.
Ensure the 33 kV GIS base frame channel is fixed as per approved Drawing.
Ensure the temporary closing of all opening such as cable, windows and doors.
Ensure all the floor openings are supports from the bottom by using scaffolding materials.
Ensure the cleanness of the room free from dust and other.
Obtain the necessary clearance from MJEC/DEC for shifting the equipment to the room.
Cordon off area around installation locations for restricting access to unauthorized personnel and fix
The environment within the switchgear rooms shall be kept to acceptable limits to allow equipment
storage
Proper Ventilation & lighting shall be provided inside the 33KV GIS Room/ Sub-station.
GIS room screed shall be completed before moving the switch gear to the room.
I 3. Erect a temporary off-loading platform (using scaffolding materials for a site of 6 Mtr Length & 6 Mtr
Width) along with the off-loading platform for easy handling of GIS if permanent loading platform not
ready/available.
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
[email protected]
www.elsewedy.com
Ensure the proper access road to reach the offloading platform of 33 kV GIS room
Arrange the necessary trailers & suitable crane (25T) to load from store yard or unload the equipment at
site.
Equipment shall be transported from store to the erection site by using proper material handling
equipment
and tackles in a safe way and shifted to the required area. Use the lifting hooks only for lifting the panel.
Identify the correct packages based on the arrangement in the GIS room which will be taken first.
Switchgear shall be supported properly during the transportation from stores to site or directly to site.
Check impact recorder is attached to Switchgear assemblies transported from factory to site. The
recorder shall be operative from the time of packing to the time of un packing at site and shall record an
uninterrupted record of all registered data. The recorder shall be sealed and the seal shall be broken in
the presence of MJEC/DEC. Interpretation of the readings registered in the impact recorder shall be
furnished to MJEC/DEC.
Unload the 33KV GIS package from trailer and place the packages in the identified area near the crane.
Unpack the Accessories and shift the same to inside 33 KV GIS room.
Store the accessories in the wooden racks provided in the GIS Room.
Remove all the unpacked wooden materials & shift to scrap yard or identified area.
Check the equipment for any damage and verify the bay no against approved drawing.
Lift and place the GIS on the pallet trolley, which is located on the off loading platform. (Hand Rail of plat
Move the GIS by using pallet trolley and bring the same to the location as per the equipment layout.
(Door
Off load the GIS from pallet trolley and place over GI pipes.
Move the GIS to its position as per the marking done on the GIS room.
Check the clearance with wall as per the approved equipment layout.
Position the GIS and fix the same permanently in the embedded channel.
Repeat the steps 7 to 17 for consecutive bays and couple with the bay installed.
Provide the Earthing I Grounding for the GIS according to the Approved earthing layout drawing.
Fill the SF6 gas for the bus bar components as per the Manufacturer Recommendation.
Ensured that all the test equipment have valid calibration certificate.
Check that all control wiring has been made and is secure.
Check that the control wiring gland plate shall be refitted and the water tight seal is intact.
Check the SF6 gas pressure is at or above 0.5 bar gauge(normal working pressure at 20 degree
centigrade)
Check that the legs shall be secured properly and anchored to the foundation.
High Voltage test for the switchgear shall be carried out with circuit breaker in closed state & in service
condition.
The incoming and outgoing cables shall be connected as per the approved drawings I cable schedules.
Termination shall be carried out using specified kits. Properly trained jointers shall only be used for HV
Cable termination.
Inter panel wiring for control shall be carried out as per the approved wiring I termination diagrams.
The control cabling for remote control and auxiliary power supplies shall be connected and terminated
After completion of testing viz. Ductor Test, CB Test, CT Test, VT Test & Relay Test as applicable, the
switch gear shall be subjected to the final installation check. The checks I tests as indicated in the
construction check sheet for HV switch gear Form and Functional check sheet for HV switch gear shall
7.8 Acceptance
The results obtained during the testing shall be verified with records of routine Test Reports, if any,
On completion of checks I tests; the applicable test records shall be signed off by the Discipline QA/QC
Engineer I Test Engineer and the company Representative's signature shall be obtained on the records
for acceptance.
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
[email protected]
www.elsewedy.com
8. Records
As built drawings
Calibration certifications
. . . END OF PROCEDURES. . . .