We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 12
Ex. 12: For the following project:
(1) Draw network diagram.
(2) Find critical path and project completion time.
(3) Identify critical and non-critical activities.
Activity Preceding Activity | Time (days)
A - 6
B A 5
c A 2
D B 4
E Cc 2
F D 1
G D&E 5
H F&G 3
Solution:
(1) Network Diagram:
Fig. 7.29
(2) Paths in the network:
(3)
(a) A-B-D-F-H: Duration = 19 days
(b) A-B-D-X,-G-H: Duration = [23 days]
() A-C-E-G-H: Duration = 18 days
«Critical path =A-B-D-X,:-G-H
Project completion time _= 23 days
Critical activities: Activities A, B, D, X1,G and H
Non critical activities: Activities C, E and F
erPy
\
|
i
etwork Analysis - 1 VU0 30s
fx. 13: For the following project:
() Draw network diagram.
( Find critical path and project completion time.
()_Identify critical and non-critical activities.
Activity Preceding Activity’ Time (days)
A - 4
B A 3
) C A 5
D B 1
E B&C 2
| F D&E 2
G E 3
Solution:
() Network Diagram:
Fig. 7.30
Q) Paths in the network:
(@) A-B-D-F: Duration = 10 days
(2) A-B-X;-E-X2-F: Duration = 11 days
(3) A-B-X;-E-G: Duration = 12 days
(4) A-C-E-X2-F: Duration = 13 days
() A-C-E-G: Duration = [14 days|
~.Critical path =A-C-E-G
Project completion time = 14 days
(3) Critical activities : Activities A.C, E, and G
Non critical activities : Activities B,D, F, X; and X2
Ex. 14: For the following project:
(1) Draw network diagram.
Q) Find critical path and project completion time.
() Identify critical and non-critical activities.iv
Vipul’s Operations Research (BMS) (NK) a
306
Activity Time (days)
1-2 4
1-3 5
2-4 3
3-5 2
4-6 2
5-6 4
Solution:
In this example, the activities are given in the form of ‘Node
relationship’.
(2) Network Diagram:
(2) Paths in the network:
Fig. 7.31
(a) 1-2-4-6: Duration =9 days
(b) 1-3-5-6: Duration = 11 days
Critical path
=1-3-5-6
Project completion time = 11 days
(3) Critical activities:
Non critical activities:
(1) Draw network diagram.
(2) Find critical path and project completion time. _
Activities 1-3,3-5,5-6
Activities 1-2, 2-4,4-6.
Ex. 15: For the following project:
(3) Identify critical and non-critical activities.
Activity Time (days)
1-2 3
1-3 1
2-3 zero
2-4 2
2-5 5
3-5 7
4-6 4
5-6 3
if
ye|
network Analysis - | u a a
Solution: Node relationship is given
Activity 2-3 takes zero days, it means it is a dummy activity
() Network Diagram:
_ Q) Paths in the network:
| (a) 1-2-4-6: Duration =9 days
| (b) 1-2-3-5-6: Duration = 13 days
() 1-2-5-6: Duration =11 days
(a) 1-3-5-6: Duration =11 days
Critical path
Project completion tim
(3). Critical activities: Activities 1-2,2-3,3-5,5-6
Non critical activities: Activities 1—3,2-4,2-5,4-6.
3077.10 SOLVED PROBLEMS: eee
Ex. 17: For the following project:
(1) Draw network diagram.
(2) Find critical path and project completion time.
(3) Find earliest and latest starting and finishing times of all activities.
(4) Find floats and slacks for all activities.
Preceding Activity Time (days)316 ua Vipul’s Operations Research (BMS) (Nk)
Solution:
(1) Network Diagram:
@
(2) Paths in the network:
() A-B-E-G: Duration = 14 days
(2) A-B-D-F-H: Duration = [22 days] —
(3) A-C-F-H: Duration = 12 days
<.Critical path =A-B-D-F-H
Project completion time = 22 days
(3) Time estimates:
Note: When we do forward pass and backward pass,
ForEs : Activity 10+6=16
Activity C+ 4+2=6
° 16
Forl; : ActivityE>21-3=18
Activity D> 16-6 = 10
cL3= 10
ForL2 : ActivityB>10-6=4
Activity C > 16-2 = 14
va=4
Table 7.6 Earliest and Latest Starting and Finishing Times
Activity | EST=E& | EFT= st +u | LST=LFT-ty | LFT=1j
A E=0 4-420 la=4
B Ep=4 Ly= 10
iG Ep=4 Ly=16
D E3=10 Ly= 16
E E3=10 Ls=21
Ee a>
=B\ \
eTVi gietinanse's
[cE
G
H
Activity Head Slack = L;- E
A 4-4=0
B 10-10=0
i 16-16=0
D 16-16=0
E 21-13=8
F 20-20=0
c 2-22=0
H 2-2=0
Table 7.8: Floats
Activit | “Total Float = | Free Float= | Independent | Interfering
y LST-EST | TF-Head | Float=FF- | Float=Head
Slack Tail Slack Slack
A o- 0
B - 4 0
¢€ G -4=10 0
D 10-10=0 0
E 18-10=8 8
F 16-16=0 0
G 21-13=8 0
H 20-20=0 9
Ex. 18:
A small assembly plant assembles PC’s through 9 interlinked
activities. The time duration for which is given below:
Activity T72]13] 14] 25] 36| 37 | 46 | 58] 6973] 89
Duration(hrs) | 2 1211141815 [3][1/5 [413
(1) Draw a network diagram for it.
) Calculate and tabulate for each activity:
Earliest Start (ES), Earliest Finish (EF), Latest Start-(LS) and
Latest Finish (LF) times.
(3) Find the critical and sub critical paths.
(® Calculate and tabulate Total Float, Free Float, Interfering Float and
Independent Float.
(MU, Oct. 2003)318 a
Solution:
Vipul’s Operations Research (BMS) (Nk)
(1) ‘Network Diagram:
(2) Paths
in the network:
(a) 1-2-5-8-9 : Duration = 10 hrs
(b) 1-3-7-8-9 : Duration = 14 hrs
-3-6-9 — : Duration =|15 hrs|
@ 1
qd) 1
~4-6-9 : Duration = 09 hrs
Critical path =1-3-6-9 (15 hrs)
Project completion time = 15 hrs
Sub critical path =1-3-7-8-9 (14 hrs)
Table 7.9: Earliest and Latest Starting and Finishing Times
Activity ij | EST=E, | EFT=EST+t; | LST=LFT-t) | LFT=l
1-2 Ei=0 0+2=2 ; La=7
1-3 Ei=0 O+2=2 Ls=2
1-4 E,=0 O+1=1 Li=7
2-5 Ep=2 24+4=6 Ls=11
3-6 E3=2 2+8=10 10
3-7 E3=2 24527 8
4-6 E=1 1+3=4 10
5-8 Es=6 6+1=7
6-9 Es=10 10+5=15
7-8 Ey=7 7+4=11
8-9 Es=11 11+3=14
Table 7.10: Slacks
Activity Head Slack = L;- Fj
1-2 7-2=5
1-3 2-2=0
1-4 7-1=6
ENT
rs
RZvv
\
lysis -
network Analysis -1 GUO as
Table 7.11: Floats.
Activity Total Float =| Free Float =| Independent Interfering
LST-EST | TF-Head |Float=FF-Tail| Float = Head
Slack
1-2 5
1-3 0
1-4 6
2-5 5
3-6 0
3-7 1
4-6 0
5-8 1
6-9 0
7-8 1
8-9 | 12-11=1 o
Note: In this problem, students need not calculate slacks as it is not
asked in the question. They can also calculate floats using formulae
given in Table 7,4 (Example 11).
Ex, 19: ea
Following are the details of estimated times of activities for a certain
Project.
‘Activity A[B|c| DIE F]
Immediate Predecessor/Activity -[Aal[alpc[-[e
Estimated Time (Weeks) 2:[3jiah 6 [2]8
(1) Find the critical path and expected time of the project.
2) Calculate the earliest start time and earliest finish time for each
activity. Ms : :
(3) Calculate the slack for each activity. (Mu, April 2004)-
200M Vipul’s Operations Research (BMS) (Nk)
Solution:
@)_ Network Diagram f
é
4
i
1
0
if
§
f
it
i!
(2) Paths in the network:
(a) A-B-X;:-D : Duration = 11 weeks
(b) A-C-D : Duration = 12 weeks
() E-F : Duration = 10 weeks
Project completion time
Table 7.12: Earliest Starting and Finishing Times b
Activity ij | EST=5
A Ei=0
B Ep=2
@ E;
D
E
F
X Ey=5
Table 7.13: Slacks
Activity Tail Slack=L;-E; | Head Slack = Lj- 5
A 0-0=0 2-2=0
B 6-5=1
iG 6-6=0
D 12-12=0
E 4-2=2r
| yawork Analysis - 1
F 4-2
| Xx AA 6-5=
Ex. 20:
Activities involved in a small project are given below along with
relevant information.
Activity 12 [13 [23 | 24 | 34 [45
DurationInDays | 20 | 25 | 10 | 12 | 6 | 10
() Construct the network and find critical path.
(2) Find and tabulate Earliest Start Time, Earliest Finish Time, Latest
Start Time, Latest Finish Time and Total Float. Verify the critical
path found earlier. (M.U,, April, 2009)
Solution:
() Network Diagram
321
a
aw
10
Fig. 7.39
@) Paths in the network:
(a) 1-2-4-5 — : Duration = 42 days
(6) 1-2-3-4-5 : Duration = [46 days]
(9 1-3-4-5 _: Duration = 41 days
=1-2-3-4-5
-. Critical path
Project completion time = 46 days
Table 7.14: Earliest and Latest Starting and Finishing Times
Activity ij EFT =EST+t | LST=LFT-ty | LFT=Lj
12 0+20=20 20-20=0 12=20
1-3 04+25=25 13=30
2-3 20+10=30 La=30
2-4 20+12=32 Li=36
3-4 30 +6 =36 Ly =36
4-5 36 +10 = 46 Ledsf
\
Vipul’s Operations Research (BMS) (NK) fi
322 Q
SR
<
Table 7.15
Total Float = LST - EST
From the total float calculation, we can see that activities 1-3 and fe
2-4 have 5 days and 4 days of float available respectively. Hence, these _¢
are non-critical activities. All other activities ie. 1-2,2-3,3-4and
4-5 have zero float. It means these are critical activities.
Thus, the critical path 1 - 2-3-4 -5 found earlier is verified.