SKAB4113 - Topic 5 Part 2
SKAB4113 - Topic 5 Part 2
ND03122022
innovative • entrepreneurial • global | www.utm.my
2
QUICK CHECK
• TOPICS
Topic 1 : Overview Current Issue in The Construction Industry
Topic 2 : Project Management Project Development Process
Topic 3 : Project Manager: Roles, Ethical Responsibilities
Organizational Management
Topic 4 : Introduction to project planning
Topic 5 : Introduction to the networking technique
Topic 6 : Introduction to scheduling software & Demonstration
• ASSESSMENTS (30%)
Case Study : 5%
Test 1 : 10%
Project : 15%
• FINAL EXAMINATION (50%)
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Organizing Project Task
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
1) Work Breakdown Structure (WBS)
• Work Breakdown Structure (WBS) is a part of activity involved
in organizing project task.
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
1) Work Breakdown Structure (WBS)
• There are few practical consideration for WBS which are:
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
1) Work Breakdown Structure (WBS)
• Process of sub-diving the project and task into a smaller level of
components, e.g.:
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
2) Grouping
• Grouping is a process of organizing the project activities into a
smaller bands so that it is easy to exert control over the entire
project.
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
2) Grouping - Example
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
2) Grouping - Example
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
2) Grouping
• Using Numbering System
• Using Alphabhet System
• Combination Of Both
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Critical Path Method (CPM)
• The critical path method (CPM) is a technique that allows
project manager to identify tasks that are necessary for
project completion.
• Any delays in critical tasks will delay the rest of the project.
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Critical Path Method (CPM)
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Elements of Critical Path Method (CPM)
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
CPM Calculation
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Benefits of Critical Path Method (CPM)
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Critical Path Method (CPM) Terminology
1. Early Start (ES)
• The earliest possible time to start an activity
2. Early Finish (EF)
• The earliest possible time to finish an activity
3. Late Start (LS)
• The latest possible time to start an activity without delaying the overall
completion of the project
4. Late Finish (LF)
• The latest possible time to finish an activity without delaying the overall
completion of the project
5. Total Float (TF)
• The total time available to delay the start or finish of an activity without
delaying the overall completion of the project
6. Free Float (FF)
• The total time available to delay the start or finish of the activity without
delaying the Early Start (ES) time of the proceeding activity.
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Critical Path Method (CPM) Terminology
Example: ADM/AOA & PDM
Or AOA
Activity
Node
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Critical Path Method (CPM) Formula
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Lag Time
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Network Technique
Lag Time - Examples
Site Clearing
Pour Slab
Cutting
Lag = 5d
Plastering Plastering
ND03122022
innovative • entrepreneurial • global | www.utm.my