Synchronization Specification - DG PLC PDF - PDF 2
Synchronization Specification - DG PLC PDF - PDF 2
www.arpnjournals.com
ABSTRACT
Microgrid is an aggregation of multiple distributed generators like renewable energy sources, conventional
generators, and energy storage systems that provide electric power to consumers. It operates in two modes namely grid
connected mode and islanded mode. The transition of microgrid from islanded mode to grid connected mode poses crucial
grid synchronization issues. This is a key challenge to protection engineers. This paper proposes the implementation of 9
no’s 2/2.5 MVA low voltage (LV)- Diesel Generator (DG) sets synchronization in a real-time microgrid network using bus
coupler logic to restrict the fault current vide programmable logic controller (PLC) during utility power failure based on
load requirement.
3193
VOL. 11, NO. 5, MARCH 2016 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences
©2006-2016 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
The memory unit stores the program for the DG 1 in ON condition at Bus section 2 and DG 2, 3, 4 are
microprocessor. It stores input data for processing and synchronized at Bus section 1 where the maximum fault
buffers data to output. current is restricted to 100 KA/sec by having the bus
The input and output interfaces assists in coupler 1 and 2 in open condition.
communicating with external or peripheral devices. ETAP result of Scenario 1 is shown in Figure-3
Switches or sensors could act as input devices. Motor and it indicates that the maximum fault current is within
starter coils, solenoid valves, or actuators may act as 100 KA. Likewise the ETAP software tests all the
output devices. considered scenarios.
The communications interface is used to receive and
transmit data on communication networks. It is Scenario 2: 100% Utility power failure and 70% loading
responsible for device verification, data acquisition, at Main PCC-1:
synchronization between user applications, and DG 1 in ON condition at Bus section 2 and DG 3, 4 are
connection management. synchronized at Bus section 1 where the maximum fault
current is restricted to 70KA/sec by having the bus coupler
LV DG synchronization case study 1 and 2 in open condition.
The LV DG synchronization scheme is
implemented on a real-time major Information Scenario 3: 100% Utility power failure and 50% loading
Technology (IT) company shown in Figure-2 where 100% at Main PCC-1:
DG backup is essential due to its critical load operation. DG 1 in ON condition at Bus section 2 and DG 4 in ON
The critical loads include servers in the data center, condition at Bus section 1 where the maximum fault
personal computers of each employee, emergency loads current is restricted to 50KA/sec by having the bus coupler
like life safety and security systems. Due to circuit 1 and 2 in open condition.
breakers and switchboard design availability constraint, it
is mandatory to ensure that fault current is within 100KA Scenario 4: 100% Utility power failure and 25% loading
on the LV system. This is achieved by calculating the at Main PCC-1:
maximum short circuit current and accordingly switching Only DG 1 in ON condition at Bus section 2 where the
ON the appropriate DG’s as per load requirements in a maximum fault current is restricted to 50KA/sec by having
logical pattern by PLC. the bus coupler 1 and 2 in closed condition.
This real-time networks’ demand load is in the tune of
17.5 MVA. Hence 33/0.415 KV dry type transformers Scenario 5: 100% Utility power failure, fault/maintenance
along with 100% DG back up vide 415V, LV DG sets in a of DG 4 at Bus section 1 and 100% loading at Main PCC-
micro grid as specified below is proposed: 1:
DG 1 in ON condition at Bus section 2 and DG 2, 3 in ON
Transformer configuration condition at Bus section 1 & standby DG 10 in ON
Main PCC-1: 3No’s 2.5 MVA Transformers condition at Bus section 3 where the maximum fault
HVAC PCC: 3No’s 2.5 MVA Transformers current is restricted to 100KA/sec by having the bus
Main PCC-2: 1No 2 MVA Transformer coupler 1 in closed condition and bus coupler 2 in open
condition.
DG configuration
DG synchronization panel 1: 2No’s 2 MVA + 2No’s 1.5 Scenario 6: 100% Utility power failure, fault/maintenance
MVA DG sets of DG 1 at Bus section 2 and 100% loading at Main PCC-
DG synchronization panel 2: 4No’s 2 MVA + 1No 1.5 1:
MVA DG sets DG 1 in OFF condition at Bus section 2 and DG
Common standby DG panel: 1No 1.5 MVA DG set 2,3,4 in ON condition at Bus section 1 and standby DG 10
Since multiple LT DG sets are proposed, special care in ON condition at Bus section 3 where the maximum
is given towards DG synchronization as the fault current fault current is restricted to 100KA/sec by having the bus
must be restricted within 100KA. This is realized by coupler 1 in open condition and bus coupler 2 in closed
employing bus couplers to facilitate restriction on the fault condition.
current adopting a programmable logic controller during Table-2 indicates the interlock logic adopted for
100% utility power failure and partial fault/maintenance of DG synchronization panel 2. Six scenarios are considered
transformer/DG sets in a micro grid. and the logic is programmed in PLC to attain appropriate
Table-1 indicates the interlock logic adopted for DG DG synchronization.
synchronization panel 1. Six scenarios are considered and
the logic is programmed in PLC to attain appropriate DG Scenario 1: 100% Utility power failure and 100% loading
synchronization. at Main PCC-2 & HVAC PCC:
DG 7, 8, 9 are synchronized at Bus section 1and DG5,6
Scenario 1: 100% Utility power failure and 100% loading are synchronized at Bus section 3 where the maximum
at Main PCC-1: fault current is restricted to 100KA/sec by having the bus
coupler 1 and 2 in open condition.
3194
VOL. 11, NO. 5, MARCH 2016 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences
©2006-2016 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
Scenario 2: 100% Utility power failure & 70% loading at Scenario 5: 100% Utility power failure, fault/maintenance
Main PCC-2 and HVAC PCC: of DG 9 at Bus section 1 and 100% loading at Main PCC-
DG 8, 9 are synchronized at Bus section 1 and DG 5, 6 2 & HVAC PCC:
are synchronized at Bus section 3 where the maximum DG 7,8 are synchronized at Bus section 1 and
fault current is restricted to 70KA/sec by having the bus DG 5, 6 are synchronized at Bus section 3 & standby DG
coupler 1 and 2 in open condition. 10 in ON condition at Bus section 2 where the maximum
fault current is restricted to 100KA/sec by having the bus
Scenario 3: 100% Utility power failure and 50% loading coupler 1 in closed condition and bus coupler 2 in open
at Main PCC-2 and HVAC PCC: condition.
DG 7, 9 are synchronized at Bus section 1 and DG 6 in
ON condition at Bus section 3 where the maximum fault Scenario 6: 100% Utility power failure, fault/maintenance
current is restricted to 50KA/sec by having the bus coupler of DG 6 at Bus section 3 and 100% loading at Main PCC-
1 and 2 in open condition. 2 & HVAC PCC:
DG 7,8,9 are synchronized at Bus section 1 and DG 5 in
Scenario 4: 100% Utility power failure and 25% loading ON condition at Bus section 3 & standby DG 10 in ON
at Main PCC-2 and HVAC PCC: condition at Bus section 2 where the maximum fault
DG 9 in ON condition at Bus section 1 and DG 5 in ON current is restricted to 100KA/sec by having the bus
condition at Bus section 3 where the maximum fault coupler 1 in open condition and bus coupler 2 in closed
current is restricted to 50KA/sec by having the bus coupler condition.
1 and 2 in open condition.
3195
VOL. 11, NO. 5, MARCH 2016 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences
©2006-2016 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
3196
VOL. 11, NO. 5, MARCH 2016 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences
©2006-2016 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
REFERENCES
[11] B. Bradu B., Gayet P. , S. I. Niculescu. 2009. A
[1] X. Lin, R. Zhang, N. Tong, X. Li, M. Li, D. Yang. Process and Control Simulator for Large Scale
2015. Regional Protection Scheme Designed for Cryogenic Plants. Control Engineering Practice.
Low-Voltage Micro-Grids. Electrical Power and
Energy Systems. (64): 526–535. [12] M. Behary, R. T. F. A. King, H. C. S. Rughooputh.
2004. Automation of Sugar Boiling Process in Batch
[2] M. Jing, W. Xi, Z. Yagang, Y. Qixun, A. G. Phadke. Vacuum Pans Using ABB-Freelance PLC (AC 800F)
2012. A Novel Adaptive Current Protection Scheme and Conductor NT SCADA. IEEE International
for Distribution Systems with Distributed Conference on Industrial Technology.
Generation. Int J Electr Power Energy Syst. 43(1):
1460–1466. [13] S. Abdallah, S. Nijmeh. 2009. Two Axes Sun
Tracking System with PLC Control. Jordan Journal
[3] A. H. A. Bakar, B. J. Ooi , P. Govindasamy, C. K. of Mechanical and Industrial Engineering.
Tan , H. A. Illias, H. Mokhlis. 2014. Directional
Overcurrent and Earth-Fault Protections for a [14] S. Abdallah, R. Abu-Mallouh. 2008. Heating
Biomass Microgrid System in Malaysia. Electrical Systems with PLC and Frequency Control. Energy
Power and Energy Systems. (55): 581–591. Conversion and Management.
[4] J. J. Justo, F. Mwasilu, J. Lee, J. W. Jung. 2013. AC- [15] S. Da’na, A. Sagahyroon, A. Elrayes, A. R. Al-Ali,
Microgrids versus DC-Microgrids with Distributed R. Al-Aydi. 2008. Development of a Monitoring and
Energy Resources: A Review. Renew Sustain Energy Control Platform for PLC-Based Applications.
Rev. (24): 387–405. Computer Standards & Interfaces.
[5] O. V. G. Swathika, S. Hemamalini. 2015. Kruskal [16] E. Ozdemir, M. Karacor. 2006. Mobile Phone Based
Aided Floyd Warshall Algorithm for Shortest Path SCADA for Industrial Automation. ISA
Identification in Microgrids. ARPN Journal of Transactions. 45: 67–75.
Engineering and Applied Sciences. 10(15): 6614–
6618. [17] S. Medida. 2008. Pocket Guide on Industrial
Automation. First ed. Perth (Australia).
[6] F. Blaabjerg, R. Teodorescu, M. Liserre, V. A.
Timbus. 2006. Overview of Control and Grid [18] S. Da'na, A. Sagahyroon, A. Elrayes, A. R. Al-Ali,
Synchronization for Distributed Power Generation and R. Al-Aydi. 2008. Development of a Monitoring
Systems. IEEE Transactions on Industrial and Control Platform for PLC-Based Applications.
Electronics. p. 53. Computer Standards & Interfaces. p. 30.
[10] A. Honda, F. Okano, K. Ooshima, N. Akino, K. [22] K. G. Shankar. 2008. Control of Boiler Operation
Kikuchi, Y. Tanai. 2008. Application of PLC to Using PLC-SCADA. Proc. of the International Multi
Dynamic Control System for Liquid Hecryogenic Conference of Engineers and Computer Scientists.
Pumping Facility on JT-60U NBI System. Fusion
Engineering and Design.
3197