SOP QC-101 ASME B31.9 Shop and Field Inspection - Supervisor Intro RFS - Rev. 1
SOP QC-101 ASME B31.9 Shop and Field Inspection - Supervisor Intro RFS - Rev. 1
design temperature: the temperature equal to or higher shielding may or may not be obtained from an externally
than the highest working temperature, used in deter- supplied gas or gas mixture.
mining the required wall thickness or component full fillet weld: a fillet weld whose size is equal to the thick-
rating. See para. 901.3. ness of the thinner member joined. See size of weld.
design thickness: the sum of the minimum thicknesses fusion: the melting together of filler and base material, or
required by the design conditions and corrosion, mechan- of base material only, that results in coalescence.
ical, and other allowances.
gas metal arc welding (GMAW): an arc welding process that
employer: the owner, manufacturer, fabricator, contractor, employs a continuous solid filler metal (consumable) elec-
assembler, or installer responsible for the welding, trode. Shielding is obtained entirely from an externally
brazing, and NDE performed by their organization, supplied gas or gas mixture. (Some methods of this
including procedure and performance qualifications. process have been called MIG or CO2 welding.)
engineer: the engineer as agent of the owner is the party gas pocket: see porosity, the preferred term.
responsible for design of piping systems to meet operating
and safety standards. gas tungsten arc welding (GTAW): an arc welding process
that employs a tungsten (nonconsumable) electrode.
engineering design: the detailed design for a piping instal- Shielding is obtained from a gas or gas mixture. Pressure
lation, developed from the building systems requirements may or may not be used and filler metal may or may not be
and conforming to Code requirements, including neces- used. (This process has sometimes been called TIG
sary drawings and specifications. welding.)
equipment connection: an integral part of equipment such gas welding: see oxyfuel gas welding.
as boilers, pressure vessels, heat exchangers, and pumps
designed for attachment of piping. groove weld: a weld made in the groove between two
members.
erection: the complete installation of a piping system,
including field fabrication and assembly. header: see main.
d Record examination: any of a number of quality control operations heat-affected zone (HAZ): that portion of the base metal
that use visual or other methods to reveal imperfections that has not been melted but whose mechanical properties
(indications) and to evaluate their significance. or microstructure has been altered by the heat of welding,
brazing, soldering, forming, or cutting.
examiner: a person employed by the piping manufacturer,
fabricator, or erector who is competent to perform exam- heat fusion: a joining process in which melted surfaces of
inations. plastic pipe and fittings are engaged and held together
under moderate pressure until cool.
expansion joint: a component installed in a piping system
4
Copyrighted material licensed to University of Toronto by Techstreet LLC, subscriptions.techstreet.com, downloaded on 2021-03-13 18:47:09 +0000 by
No further reproduction or distribution is permitted.
ASME B31.9-2020
Chapter VI
Inspection, Examination, and Testing
46
Standard Operating Procedure
QC-101
ASME B31.9 Shop and Field Examination
For
1. PURPOSE
To establish a standard procedure for Shop & Field Examinations and Testing.
To ensure ACCO is meeting the expectations of this procedure when an authorized examiner discovers
non-compliant deficiencies they will report to the local QC lead and responsible supervisor to discuss
appropriate resolution. If required, the Construction Leadership Team will be notified to assist with any
further means to resolve non-compliant work activities.
In the absence of specific written instructions from the client, this SOP shall be used. Client
specifications that limit or exceed those contained in this SOP, shall be agreed to in writing by the
Client and ACCO Engineered Systems.
2. SCOPE
This procedure outlines code requirements for Examination and Testing of Shop/Field fabrication and
installations of piping systems and components on commercial projects. Examination and testing
criteria are in strict compliance with ASME B31.9, and related ACCO standards.
3. RESPONSIBILITIES
Examinations, Testing and required documentation will be performed by/or witnessed by ACCO
authorized personnel. These quality control functions are mandatory and require a concerted effort of
shop and field personnel.
Shop personnel may fulfill examination requirements for shop fabrication and assembly, while field
personnel may fulfill examination and testing requirements for field fabrication and installation.
Shop and Field Examiners shall have training and experience commensurate with the needs of the
specific examinations. Examination shall be performed personnel other than personnel performing the
work. Shop and Field Examiners shall be approved by the Regional Quality Control Supervisor prior
to performing examinations.
ACCO Shop and Field Examiner Log shall be maintained by ACCO QAQC and be kept current.
4. REFERENCES
ASME Section IX
______________________________________________________________________________________
PROPERIETARY AND CONFIDENTIAL
ACCO ENGINEERED SYSTEMS, INC.
Page 2 of 5
SOP # QC-101 Rev.1
Quality Control
ASTM B828 Standard Practice for Making Capillary Joints by Soldering of Copper and Copper Alloy
Tube and Fittings
5. PROCEDURES
5.1 Visual Examination – Observation of the portions of materials, components, joints, supports, and other
piping elements that are or can be exposed to view before, during, or after manufacture, fabrication,
assembly, or erection. This examination includes verification of Code and engineering design
requirements for materials and components, dimensions, joint preparation, alignment, joining practices,
supports, assembly, and erection.
______________________________________________________________________________________
PROPERIETARY AND CONFIDENTIAL
ACCO ENGINEERED SYSTEMS, INC.
Page 3 of 5
SOP # QC-101 Rev.1
Quality Control
6. EXAMINATION
Perform random Visual Examinations of the various stages and elements of the fabrication and
installation process in accordance with section 5.1 above.
Perform Leak Testing of each installation in accordance with section 5.2 above and document each test.
7. Welded Fabrication
Fillet, Socket & Seal Welds – Same as above for Cracks, Lack of Fusion, Undercut, and Weld
Surfaces.
8. Grooved and Rolled Fabrication – Verify groove & depth is per manufacture specifications.
9. Threaded Joints - There shall be no severe chipping or tearing of visible threads. No more than six
and no fewer than two threads shall be visible after makeup of the joint.
10. Flanged Joints - The flange faces shall be parallel with in 1 degree. Nuts and bolts shall be fully
engaged.
11. Flared, Flare-Less, and Compression Joints - There shall be no cracks in flare or tube ends. Tube ends
shall be cut square and be free of distortion or grooves that would hinder assembly or sealing. Negligible
force shall be required to align ends.
______________________________________________________________________________________
PROPERIETARY AND CONFIDENTIAL
ACCO ENGINEERED SYSTEMS, INC.
Page 4 of 5
SOP # QC-101 Rev.1
Quality Control
12. Copper Fabrication & Installation - Brazed and Soldered Joints – Verify materials, flux, solder &
brazing rod meets the job specifications and ACCO’s submittals. Verify all Copper Installers have been
CAT Trained.
o Acceptance Criteria: Penetration of filler metal inside the pipe shall not exceed 100% of the
wall thickness.
o There shall be no visible unfilled joint space.
o There shall be no visible evidence of excessive over-heating.
12.1 Copper Fabrication & Installation - Mechanical Press – Verify materials meets the job
specifications and ACCO’s submittals. Installers must be CAT Trained and have their Press
Certification.
Be sure tube ends are square cut, de-burred, and clean prior to joining.
Randomly verify insertion depth is being marked along with completion mark.
Properly support tubing before heating to maintain alignment. Perform final examination. Document
results on the Daily Inspection Report. Imperfections in mechanical and proprietary joints shall be
within the limitations established by the manufacturer.
13. Solvent-Cemented, Adhesive, and Heat-Fusion Joints – Verify primer / cement are not expired, and
have been properly stored.
Pipe ends must be cut square, de-burred and prepped per manufacturer instructions.
Piping and valves must be properly supported. Internal protrusion shall not exceed 50% of wall
thickness for solvent-cemented and 25% for adhesive and heat-fusion joints.
There shall be no visible unfilled or un-bonded areas.
Excess cement/adhesive shall be wiped clean.
End of Section
______________________________________________________________________________________
PROPERIETARY AND CONFIDENTIAL
ACCO ENGINEERED SYSTEMS, INC.
Page 5 of 5
BLANK
PAGE