Safety Pre-Construction Meeting GKS .

This document outlines safety procedures for an airport expansion project. It establishes 10 ground rules for safety and outlines responsibilities for project managers, HSE managers, supervisors, engineers, and workers to maintain safety. An organogram shows the contractor's organizational structure and employee numbers in different safety roles. A daily construction cycle is also outlined, with emphasis on inspections, toolbox talks, and supervision before starting each task. The goal is to build a culture of preventative commitment and ensure all risks are eliminated or controlled to achieve zero accidents on the project.

Uploaded by

ce.rashed12
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
91 views66 pages

Safety Pre-Construction Meeting GKS .

This document outlines safety procedures for an airport expansion project. It establishes 10 ground rules for safety and outlines responsibilities for project managers, HSE managers, supervisors, engineers, and workers to maintain safety. An organogram shows the contractor's organizational structure and employee numbers in different safety roles. A daily construction cycle is also outlined, with emphasis on inspections, toolbox talks, and supervision before starting each task. The goal is to build a culture of preventative commitment and ensure all risks are eliminated or controlled to achieve zero accidents on the project.

Uploaded by

ce.rashed12
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 66

Safety is Our Top Priority

HAZRAT SHAHJALAL
INTERNATIONAL AIRPORT
EXPANSION PROJECT

GUANGZHOU GOLD KINGS BUILDING MATERIAL CO.LTD


Contents
Ⅰ 10 HSE ground rule and Safety management practices

Ⅱ Subcontractors staff role and responsibilities

Ⅲ Organogram

Ⅳ Daily Construction Cycle

V Method of statement Process

VI Heavy Equipment SOP

VII Emergency response plan


Top 10 Safety ground rules- Written Oath & Safety Pledge

Written Oath; Safety Pledge;
In order to build consensus among ADC, sub-contractors, workers and clarify the Establish and maintain a safe and healthy working environment and Ensure that
roles and responsibilities, thereby establishing a culture where everyone engages in significant risks arising from work activities under our control are eliminated or
preventive commitment against accident in HSIA PJT, We are committed of mutual adequately controlled.
engagement for the zero-accident:
Ⅱ Subcontractors HSE roles and responsibilities
Project manager:- HSE manager:-
• Provide Subcontractor/s Occupational Health and Safety Plan • Initiate and assist supervisory personnel in conducting their
and exercise good Occupational Health and Safety discipline daily Toolbox Meetings
over all personnel • Participate in providing accident prevention program and, take
• Participate in the Contractor HSE Committee part in discussion on dangerous occurrence, injury, and illness
• Ensure that all levels of supervisors are qualified with and property damage incidents
appropriate training • Foster a good Occupational Health and Safety working
• Organize and conduct regular Occupational Health and Safety relationship among Subcontractors
promotion activities with the aim of promoting Occupational • Keep and maintain all Occupational Health and Safety records
Health and Safety awareness among workers pertaining to the site Occupational Health and Safety
• Report on safety performance, safety activities, and any Management Program
accident or near misses, to the employer’s representative in a • Report all accidents, incidents and near hits to the Site HSE
regular and timely manner. Manager

Engineer / Officer / Supervisor:- Worker:-


• Participate in monitoring the HSE activities including auditing, • All employees must have a basic level of health and safety
sampling and inspection. knowledge if they are to be safe when working on site and aware
• Attends Tool Box Talk and Daily Tool Box Meetings in particular of their responsibilities to their own organization and work
area and make sure that these meetings are effective colleagues
• Identifies HSE training needs based on the work activities and • To cooperate with the Contractor and follow any information,
incident trends for the particular area and advise site instructions and training that is provided
supervisors to spare the workers for HSE trainings • Not to interfere with or misuse anything the Contractor has
• Actively participates in risk assessments for critical operations to provided in the interests of health, safety and welfare
• Take responsible care at all times and make sure that their actions
help identify and mitigate hazards
or omissions do not endanger themselves or any other person
• Take action and report immediately to the Project HSE Manager
• Use all tools and equipment safely and in accordance with
in case of dangerous actions and/or situations
instructions given or training received
• To actively participate in the investigation of all incidents,
• Report any defects or potential hazards in equipment to the
accidents and near misses Contractor (or supervisor if appropriate) as soon as possible
• To be of constant advisor on the field for any problem related to • Use the personal protective equipment supplied by your
HSE for all the personnel Contractor correctly, take care of it and report any loss or defects
in the equipment
Ⅲ. Organogram
III.i. Subcontractor Organogram & Employee number Employee
Position
Local Staff (L)
Foreign staff
(F)
Total
(L+F)

Project Director HSE Manager 01 - 01


HSE officer 08 - 08

Senior Project HSE Supervisor 12 - 12


Project
Manager Controller Lifting Supervisor 02 02
Scaffolding
Supervisor
01 - 01
Design Project Manager HSE Manager
Manager Rigger man 08 - 08
Construction Mgr. Logistic & Supply Mgr. Signal man 08 - 08
Flag man 10 - 10
HSE Officer HSE Officer HSE Officer HSE Officer
Boom lift operator 08 - 08
HSE Supervisor HSE Supervisor HSE Supervisor HSE Supervisor
Scissor lift
Left wing Center zone Right wing MLCP operator
02 - 02

HSE Officer HSE Officer HSE officer HSE Officer

HSE supervisor HSE supervisor HSE supervisor Sub Con safety


HSE Supervisor

HSE supervisor HSE supervisor HSE supervisor HSE supervisor


Ⅳ Daily Construction Cycle
TBM Order Details
1.Carry out an TBM at a place of the work by teams of each unit
Work site TBM 2.Share work details, order ,methods, risks and safety measure with all workers
3.Supervisor instructs and supports the TBM of the work he/she is in charge of by monitoring
Tips :Construction Manager /Engineer encourage to participate work teams and encourage in their activities
1. Inspection and observation prior to start work
➢ Work requiring PTW should be inspected and approved by the construction manager
Inspection ➢ Subcontractor should inspected and monitor those require PTW before starting work. The result should be
observation reported construction manager .if necessary, construction manager should inspect in person.
2. During work
➢ Designated high risk wok and the risk assessment ,must be inspected by supervisor , subcontractor manager
,construction engineer ,construction manager and take corrective as required also ensure record the finding.
➢ PM and HSE manager /Officer should conduct site patrol at all worksite and manage record keeping .
3. After work
➢ Subcontractor manager should report the result of inspection and observation to the construction manager after
work
Quality safety ➢ Construction manager should review the final inspection and observation result of each work

progress meeting
➢ Discuss matters to improve by sharing the inspection/monitoring result of before/during /after work.
➢ Check the work plan and safety measure for the next day. Check and adjust the innervation between work types.
➢ Non regular risk assessment PTW work ,Designated hazardous work require review and need approval before start work
Worksite TBM
TBM should be carried out before starting afternoon work
Inspection
Inspection and observation should be carried out on afternoon work.
observation
Worksite and workshop should be cleaned and organized by each work team.
Cleaning
Report the completion of the work (subcontractor construction manager)
Report ➢ incase of the night work be sure transfer shift and conduct inspection and observation through TBM
V. Method statement and process
V .i. HSE Operation Procedure

Permit to Work Hold Point Risk Assessment (RA)


1. For any high risk/non-routine work activities, - Hold point 16 nos. work items(Total 34)
PTW system must be followed. Working at height, Hot Work, Unauthorized
2. A permit to work system can be valid for only Entry, Crane Movement, Lifting, Opening over
twelve hours. Structure, Scaffolding etc.
3. If work group or nature of job change, new Currently 16 nos. of hold point items are
permit require to generate and follow. applicable according to our work scope
4. Without authorization of permit to work out of total 34 hold points
system, work should not be started.

Almost
Likelihood
Occasiona Certain
Severity Rare Remote Frequent (5)
Prior to work (1) (2)
l
(4)
(Reflect to R/A, JSA) (3)

Catastrophic (5) M (5) M (10) H (15) H (20) H (25)

During the Work Major (4) M (4) M (8) H (12) H (16) H (20)

(Check to comply with H/P implementation) Moderate (3) L (3) M (6) M (9) M (12) H (15)

Minor (2) L (2) M (4) M (6) M (8) M (10)

After work Negligible (1) L (1) L (2) L (3) M (4) M (5)

- Reflect H/P to next work plan H: High Risk M: Medium Risk L: Low Risk
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Acoustic layer installation APP –With scaffold
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Acoustic layer installation APP –Without scaffold
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
ALCP Subframe and panel installation
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Metal ceiling work ALP1
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Metal ceiling work ALP2
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
subframe hoisting by pulley and rope
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
subframe hoisting by pulley and rope
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards

Man lift
Boom lift operation
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Scissor lift operation
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Man lift lifting ground floor to level 1 and level 2
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Scaffold Erection
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
Hot work
V. Method statement and process
V .i. HSE Operation Procedure
Prior to conduct high risk work Job Safety Analysis require to produce for workers to
□ Job Safety Analysis understand potential hazards
XPM
V. Method statement and process
V .ii. ADC Training List
V. Method statement and process
V - iii. Subcontractor Conducted Training

S/N Training Name Duration Trained by Date Time


01 Hot Work 60 minute HSE Manager 05/11/2022 1330 hrs.
Awareness Course

02. Fire watch man 45 minute HSE Manager 06/11/2022 1330m hrs.
Training

03 Work at height 45 minute HSE Manager 08/11/2022 1430 hrs.


Awareness
Training

04 Emergency rescue 40 minute HSE Manager 9/11/2022 1430 hrs.


mock drill course

05 Manual material 45 minute HSE officer 10/11/2022 1530 hrs.


handling course
V. Method statement and process
Preparation Works:
Unloading ,Lifting & Shifting ● Secure duly signed & Approved PTW, Unloading Plan, Equipment Plan & JSA/HP
● Inspection of Equipment, Lifting Belt & Loading Platform by Safety Equipment Team
● Safety Tool Box & Briefing before Start Unloading.

2
1
Once rigging works is done slowly pull-out the subframe materials
Parking the container on flat and stable terrain, Open the pallet out from Container & transfer the pallet to loading platform
container, position the loading platform & start rigging works to stablish Forklift position.
Using lifting belt.

5
4
3

Repeat safe process for other pallets until the


unloading materials completed.
When pallet is loaded to fork lift – bring down the
Once pallet is in safe position on the transfer loading pallet to desired safe level and move for shifting.
Platform, removed the lifting belt and fork lift will load
The pallet for shifting.

Materials lifting ground floor to level 1


VI. Heavy Equipment SOP

Equipment procedure

- New Equipment Work plan


· Lifting/Sling Gear, Lifting
Radius Plan, Crane capacity etc

- Work plan approved procedure

Sub-con Construction HSE Team SPM


preparing Approval Approval Approval

(New Equipment Work plan)


JSA for lifting Operation Lifting operation Permit
General work permit for lifting
operation

Daily lifting Operation Plan


1. Apply permit to work GWP ,WAH
permit and Work plan
2. MEWP (Scissor lift, Man lift) required
third party inspection certificate
3. Competent Operator with valid
license
4. Monthly inspection tag to and
Signage need to be provided
5. Crash prevention sensor at least two
to be provided for man basket
6. MEWP Scissor lift Working Platform
must cover by zinc sheet and man lift
working platform must cover by steel
net/green net .
7. Provide wheel stoper
8. Barricade around the equipment with
signage
Number of scissor lift
9. Competent Operator banksman use:04
jacket to be worn and flag to be used
(Red &green) and ensure no body
stand under suspended load .
10. Update daily pre use checklist - Lifeline shall be used while
11. Fire extinguisher must be place on performing work on top of
the platform of man lift . Duct & Cable Tray.
12. Two rope grab should be place on the - Appropriate Scissor Lift shall be
platform of man lift . used for access.
13. Operator must check normal - Scissor Lift shall be secured with
operation of crash preventive bar appropriate supporting method
and safety devices before operate.
- Check equipment specifications, presence of
excessive load, and nondestructive test results (HP)
-Installation of life line (tie with two points)-HP

Monthly work plan for scissor lift


- Check equipment specification, presence of excessive load, and
nondestructive test result (HP)
-Installation of life line (tie with points) installation fall arrestor. (HP)
-Ensure Manlift work area is with Barricade
- No load allowed more than SWL 230 kg considering Man, Material and tools.
- No Man/Equipment access below the extended boom, ground watch by Banksman.
- Wheel stopper pad must be provided through the operation
- Separate harness anchor point provided for each individual
separately from structure using rope grape/fall arrestor. NO HOOK-ON BASKET
-Allowable Wind Limit to work (12.5 M/s), Lower down the basket.
-Trained competent /authorized personnel allowed to operate equipment.
- Emergency Stop & Strict ignition key management must be in
Place.
- Preventive maintenance and daily inspection check to done and displayed
Lifting materials on top

• Provide safety net under the structure Life line


• Safety life line provide for securing body harness 100%
tie off .
• Material lifting by winch , pully and rope.
• Provide temporary work platform by scaffold plank on
top purlin /Truss plank with proper secure .
• Use boom lift/ man basket for welding and settings
others materials or items

Safety net

Boom lift
• Movable Scaffold plank
secure with truss

Temporary working platform

Man basket
VI Method statement and process
Metal ceiling Risk Assessment for individual work acoustic layer installation

Work Activity Hazards / Risk Impact Risk Control


Unloading, o Telescope forklift o Ensure stable or even ground condition
shifting and o Dropping materials ★★★ o No overloading of forklift
storing materials
by forklift o Hit by materials or forklift o Deploy banksman RWS

Lifting of the Main


subframe ,ceiling o o Use lifting plan
Falling of load
accessories pulley ★★ o No over loading of of winch machine
with rope o Hit by load
o No lifting operation during rough weather

o Fire prevention control(i.e, Remove fire agents ,deploy fire watch man
o Fire Hazard due to hot work with fire extinguisher
Fastener and wire o o Provide fire curtain for protect spark to fall down,
Trip and fall ★★★
mesh setup
o Drop object o Competent worker and with valid hot work tools .
o Use proper ppe .

Wire rope and o Use fall protection net & Anchor body harness with designated life
o Fall from height
rock wool ★★★ line (100% tie off)
o Falling objects
installation o Secure loose materials

Lifting Fastener
Material Stacking operation Wire mesh and rockwool installation
component weld
Metal ceiling Risk Assessment for individual work in acoustic insulation layer work

Man basket handle or shift on truss procedure

Life line
Secure with lifting belt and u shackle

• While need to shift man basket


on truss use lifting belt and
shackle to secure with life line to
protect drop.
• Man basket shift one place to
another place by manual
handling (Load weight 15 kgs)

Man basket secured


by eye clump with
truss
Metal ceiling Risk Assessment for individual work acoustic insulation layer work

Hot work
▪ Apply permit to work for hot work
▪ All permit and related document must be display hot work
location
▪ Use valid and good condition hot work tools
▪ Deploy fire watch at hot work location with fire fighting
equipment
▪ Competent person carried out hot work
▪ Before start hot work check no combustible material present
near hot work
▪ Use proper PPE for Hot work (leather hand gloves ,apron
,welding shield.
▪ Welding hose gas hose segregate properly .
▪ Welding cable and welding holder make sure no wire exposed .

Fire watch deploy at hot work


location with fire fighting
Extinguisher and provided
adequate fire curtain, fire tray to
protect spark.
Acoustic insulation layer

Use safe working platform to install steel cable

Tie up steel cable with subframe with


tightener Installed life line

100% tie off body


harness

Safety net provided at under truss

Laid the rock wool

Additional safe work


Laid the metal mesh platform will provide on top
purlin
V. Method statement and process
-Risk Assessment for individual work –acoustic insulation layer

Work Activity Hazards / Risk Impact Risk Control

o Sharp edge of the wire mesh, steel o Use padding or cover the sharp edge
Manual handling ★★
cable , clump o Hand gloves for material handling workers

Shifting of metal o Falling during shifting o Follow safer lifting and handling method.
mesh on Roof ★★★ o Don’t lift or handle more then 25 kg
o Hit by load or vertical posts
Top o Maintain 3 point contact while climb up scaffold .
o Provide the safety net underneath of substructures
o Falling from height, o Fire prevention control (i.e.; Remove fire agents, Fire blanket, Fire
Installation o Falling objects ★★★ watchmen)
HP
o Fire o All hand tools shall be tied properly with lanyards
o All loose bolts and nuts shall be carried in bags

Manual handling Shifting material Installation Execution


VI. Method statement and process
Metal ceiling Risk Assessment for individual work (APP) installation Subframe
Work Activity Hazards / Risk Impact Risk Control
Unloading, o Topple of forklift o Ensure stable or even ground condition
shifting and o Dropping materials ★★★ o No overloading of forklift
storing materials
by forklift o Hit by materials or forklift o Deploy banksman
RWS
o Fire hazard due to hot work o Fire prevention control (i.e.; Remove fire agents, Fire blanket, Fire
fabrication ★★
o Trip and fall watchmen)
HP
o Use fall protection net & Anchor body harness with designated life
o Fall from height line
Clump installation ★★★ o Secure loose item
o Drop object
o Hit by load
o Use fall protection net & Anchor body harness with designated life
line
Additional o Fall from height
o Secure loose materials
subframe o Falling objects ★★★ HP
o Fire prevention control (i.e.; Remove fire agents, Fire blanket, Fire
installation o Fire
watchmen)

Unloading shifting and storing


Fabrication Clump Installation Additional subframe installation
materials by forklift
VI. Method statement and process

Wire mesh and rock wool installation without scaffolding area by using movable platform
Setup with praline. Parallel life line installed
Movable work platform for panel installation setup with
additional subframe
APP installation (Work at
Work Height)

Activity
Hazard/ o Fall from height
Risk o Falling objects
Impact ★★★

Risk o Use Fall Arrest System & Full


Control Body Harness
o Secure loose materials with a
tool bag or Tool Tethers
APP interior ceiling

Scaffold working platform at 14 meters provided by ADC, additional scaffold will provide
by GKS
APP interior ceiling

The stepped scaffolding is responsible by the sub-


Working platform provided by ADC contractor

ADC shall provide the scaffold to height of 1st layer of APP ceiling system. GKS shall
provide the additional scaffold above to reach different installation height
Scaffold erection and dismantle
Employee Local Foreign Total
position staff staff

Scaffolding 02 - 02
supervisor

Scaffolding 10 - 10
worker

• The environment free from hazard in which the scaffold is to be used including well compact,
Total 12
flat and sturdy surface condition (6 times the intended load). manpower
• Overturning need to be prevented by affixing the scaffolding or by installing outriggers’ scaffold
• Platform will planked and decked (L16'xW10"xH2"), space between the platform and in-
between platform and toe board max. L inch (2.5 cm) Wide.4.
• Scaffold platforms capable at least for light-duty:25, Medium-duty:50 & Heavy-duty:75 pounds
per square foot[1 p/sf equal 4.88 kg/m2]
• each span/bay must need minimum 250 pounds load bearing capability for each person.6.
• The distance between each post/ standard of scaffold shall be within: (1.5 to 1.8m)
• For every 10m of spacing between columns, cross bracing on 45 degree angles need to install.
• The overall height of the scaffold maximum 40m. If the height is more than 20m, the height of
the mainframes shall be within 2m. The gap between each mainframe shall be 1.8m.
• The width of a ramp shall be 90cm & angle of inclination maximum 30 degrees.
• Max. distance between brackets to which scaffolding and guardrail supports are attached 3.2m.
(10.5 feet)
• Safety handrails, toe board, Stairway, ana an opening-closing type of platform gate need to
install
APP interior ceiling
Build
Build passages
passages between
between scaffolding
scaffolding
脚手架之间搭设过人通道
platforms

A walkway is set up between the scaffolding, and the load capacity is greater than 500KG. The
single handling weight of the passage is not allowed to exceed 100KG, and the load of the
passage is not allowed to exceed 3 people at the same time..
APP interior ceiling

When installation of subframes completed, the safety net shall be laid to prevent the falling accident of
operators or materials during operation over the structures
APP interior ceiling

The access passage for top operation shall be removed after the construction of this area is
completed, before that the last ceiling module shall be installed
ALCP exterior ceiling

A pedestrian passage shall be set up at the place where allow operators go over to the upper, which
ensures the safe access (Caution: the height distance between column top to ceiling top is more than
2m, extra guardrails need to be added.
ALCP exterior ceiling

Lifeline shall be set in the vertical


Set up safety net on main and horizontal direction of
sub-frame primary steel structure
ALCP exterior ceiling

Safe Working
platform by scaffold
plank secure with
additional subframe
or primary structure

Safety net provided bellow


subframe

• Life line install between the primary structure and body harness shall be 100% tie
off
• Use Fall arrester
ALCP exterior ceiling

Fall arrester

• Install adequate life line.


• Ensure body harness 100% tie off with life line .
• Provide adequate lighting for proper illumination at
work place
• Use fall arrester
• Provide adequate ventilation
• Do not stand directly on ceiling panel
ALCP exterior ceiling

• Safety net will be installation with sub frame at fabrication yard


• Winch machine to use for lifting
• Fixing by welding with primary structure
• Safety net will be tie-up with others frame
• Use fall arrester
ALCP exterior ceiling
•Prepare permit to work and take approval
from ADC.
•Use Winch machine ,ground pulley ,pulley
and sling wire with manufacture
pulley block certificate, third party certificate and get
ADC approval before use
•Use tag line to control swing load
•Do not hoist over the load .
•Competent person to operate winch
machine
• Avoid putting sudden shock loads on
winch
•Check hook latch is properly closed or
not. Also, the hook latch should not be
associating with the load.
•Put the weight in the center of the hook
Ground pulley •Before start using, double-check if all the
parts, bolts, and accessories are in the
right position. Then, tighten the loose
parts and bolts to avoid any uncertainty.
•Ensure suspension points and anchorage
are adequate for the full imposed load.
•Check the load chain /wire rope is
hanging freely and is not twisted or
knotted
•Position the hook over the center of
gravity of the load
•Ensure the slings are secure and load is
free to be lifted
500 mm •Check the travel place is clear .
•Do not stand under suspended the load

2M
fix the winch and ground pulley on the hardened ground, and fix the guide pulley and
lifting pulley at high altitude
ALCP exterior ceiling
ALCP exterior ceiling finishing work

• Third party inspection certificate ,apply permit to


work and get approval from ADC to use Boom lift
• Banks man signal man deploy at work location.
• Do not override or turn off any hydraulics or
safety features.
• Don't move the lift from one location to another
while the work platform is in the air or while
someone is working on the platform
• Always pay attention to how much weight the lift
can handle and never exceed the limit
• Pay attention to power lines and overhead
hazards.
• Always use brakes and stabilizers.
• Keep your feet firmly on the platform floor
• Don’t sit on the railing, lean out of the basket, or
prop your feet up on any structure
• Never brace yourself with one foot outside the
lift.
The lift inspection should include:
Operating controls,
Emergency controls, Personal safety devices
Insulation Any missing or unreadable safety
information, including placards Hydraulics,
pneumatics, electricity, and fuel Fasteners and
pins Stabilizers , Wiring harnesses, Guardrails
Any loose or missing parts
TE3 Carparking & MLCP Ceiling and Cladding

Installation of lower layer of XPM ceiling modules


tighten by thread nut bolt

• Use scissor lift to lift up xpm panel


• Use Scaffold mobile platform to install XPM
panel
• Chain pully use for manual lifting
Site Control: Housekeeping
Global Wall is always looking for ways to work safely, work better and more efficiently. One way we can save
time is by keeping a clean and orderly worksite. Good housekeeping practices will save time and help make
work areas safer.
Housekeeping is a job that will be ongoing, conducted daily, and should never be put off. Global Wall will
center-pile scrap and debris at designated area for removal by the Main Contractor.
GKS RESCUE TEAM

Rescue Team
Leader Report to GKS Report to ADC

Atiqullah Mr. Wang


Jian
Report direct to ADC for major and
serious injury
Rescue co- First Aider Rescue Team
ordinator
Mr.Hafizur Abul Mr. Kamrul
kashem
BD CIVIL 02-9555555
DIFENCE
GKS CONTACT NUMBER
Mr. Mannan
EMERGENCY 999
Mr.Atiqulah +88 01313802363 EMERGENCY CONTACT
NUMBER
Mr. Hafiz +88 01778916630 ADC
Mr. Saifur
Mr. kamrul +88 01766740166
Rahman HSE - +88 01722329802
ADC +88 01989974801
Mr.Abul kashem +8801732585708 ADC
SECURITY
+88 01810144440
Mr.Manik +8801773611175 Mr. Mahbub +88 01726114576
Manik
Mr. Mannan +88 0184748733 ADC +88 01732499723
MEDICAL
CENTER
Rescue with nil Robertson

stretcher ,rescue cradle

Mustering point left wing level 1


Emergency Response Plan

Emergency rescue procedure:

Nil Robertson stretcher of choice in difficult rescue


situations, where a casualty needs to be
maneuvered, lowered or lifted to safety.
If casualty serious injured cant walk

[Emergency Contact Number:


GKS HSE Contact: ADC HSE Contact: ADC Medical Centre &
+8801313802363 Amblance Contact:
+88019899748012
+8801732499723
+8801778916630
• The project constitutes an emergency rescue leading group with a team leader, three deputy
team leaders, two safety officers, one firefighter, and several rescue teams.
• The team will coordinate its emergency rescue work with the leadership of the emergency
command headquarters of the main contractor.

Emergency Response: Self-Rescue


If the person working at height has properly selected and used his/her fall protection equipment, the self-rescue includes these steps:
•The rescue ladder will be lowered to the fallen worker, who will grab and climb back up to a safe level.
•The worker will be evaluate for possible medical attention.
•All components of fall arrest system impacted by the fall event will be collected for inspection, service and documentations (bag and tag). Name, date
and activity at time of fall shall be recorded and the equipment handed over to management.
Roles and responsibilities of the hazard assessment team:

i. Conduct risk assessment according to the characteristics of the construction site and the
hazards of the production safety process;
ii. Provide guidance to the safety team to implement and monitor safety measures to reduce
and avoid accidents from dangerous sources.
iii. Ensure accurate risk assessment data and information of hazard sources to provide a
reasonable and accurate basis for emergency response assessment;
iv. Implement effective social communication resources for emergency response and provide
timely emergency response support measures;
v. Determine the location of the emergency response on-site command center where various
accidents may occur so that the emergency response can be activated promptly.

vi. Formulate emergency response materials, equipment and manpower plans.


❖ Roles and responsibilities of on-site medical rescue team:
i. Rescue injured personnel at the scene;
ii. Transport the injured personnel to the hospital where appropriate;
iii. Assess the personnel’s injuries and determine the most appropriate first aid.

❖ Roles and responsibilities of emergency rescue team:


i. Organize personnel to facilitate rescue work on site;
ii. Set up on-site fire brigade;
iii. Ensure smooth channel for rescues teams on site.
iv. Control the development of accidents and eliminate dangerous situations.

❖ Roles and responsibilities of the Post-Emergency Working Group:


i. Establish effective communication to provide updates to Casualties and their family members.
ii. Ensure proper tracking on medical rescue of injured personnel, coordinate and deal with any conflicts
that may arise with the relevant medical rescue department;

Assist the insurance department on compensation for casualties and property losses;
Roles and responsibilities of the accident investigation team:
i. Preserve & protect the accident scene;
ii. Taking samples and sealing of relevant physical evidence on site;
iii. Investigate and understand the main cause of the accident and the responsibilities of the relevant
personnel;
iv. Provide an investigation report on the accident & recommend remediation actions where appropriate.

v. Provide assistance to local authorities where necessary.

❖ Rescue materials and equipments:


i. Assess the nature and characteristics of each construction site and determine the actual needs of emergency
rescue work are equipped with emergency appropriate rescue equipments;
ii. Emergency rescue equipments are regularly maintained and are always ready for use in emergency
situations. Example of emergency rescue equipments: first aid kit (equipped with commonly used drugs), fire
fighting equipment (fire extinguisher, fire bucket, fire sand, etc.), lighting equipment (hand lamp, flashlight,
etc.), transportation(vehicle), other rescue equipment (stretcher, etc.).
According to the characteristics of large ceiling construction, there is higher probability accidents
occurring. For example, falling, object strike, mechanical injury, electric shock, collapsed large
mechanical equipment, etc.

1. Commencement of the plan: Emergency plan is activated immediately when an accident occurs.

2. Emergency measures: The on-site safety Manager will assess whether the accident will escalate
further according to the type of accident and takes appropriate measures to prevent any further
escalations. Upon confirmation that no harm will be caused to the rescuers, the rescue team will
be directed to enter the scene of the accident to rescue the injured personnel. When the injuries
are serious, to immediately call the local emergency center for assistance.
3.Termination of the emergency plan: The emergency commander can issue an emergency termination
order when the following conditions are met:
i. Emergency rescue operations have been completed and the hazards causing the accident are
effectively controlled and eliminated;

ii. All on-site personnel are accounted for;


iii. There are no other factors that affect the termination of the emergency rescue plan;

4.Resumption of work: After the emergency rescue plan is terminated, effective measures should be undertaken to
prevent further accidents. The site clean-up must be carried out in an organized manner to prevent further property
damage and/or casualties, and protect related physical evidence. After the cleaning is completed, construction and
production can be resumed after approval by the relevant local authorities or departments.

5.Accident summary report: After the conclusion of the rescue, contractors should report the accident
accordingly. Summarize the entire process of emergency rescue plan implementation, improve the deficiencies
and defects in the emergency rescue plan where necessary and provide experience for the establishment,
formulation and modification of future plans.
Penalty procedure
Monthly HSE Execution Plan

Items Title Date Main Content Remark

→ Lifting & Rigging Training, Work at Height Training


→ Hot Work awareness training
→ Work at Height awareness training Subcon. req. to
01st~30th submit request
Training Practical Training → Fire Watchman, Electrical Safety
August form for specific
→ Scaffolding Training, Hold Point Training training
→ Forklift operation Training
→ Manual Handling Training, PTW Training

- Emergency Rescue Drill September - Emergency Rescue Drill Will Conduct at Site As per monthly
Event
- Monthly safety award 2022 - Safety Day Celebration plan

- A/S : 16:30 (SIC room), Government holiday Attendance


Coordination Meeting Daily
1600 hrs . PM/CM/HSE
Meeting
Committee Meeting Monthly - As Per Meeting Minutes of SCM -

- Potential High Risk Identification Activity


Others S-CAR Registration Monthly Avg. 1.0 per pax.
∙ Sub-contractor manager, more than 1 case/month