2023 Fundamentals 5 Scope
2023 Fundamentals 5 Scope
starts at 18h30.
Audio checks
are done at
18h20 & 18h25
Fundamentals of Construction
Law 2023: Scope
Please log in using either
It’s important this URL
to register https://studygoal.jisc.ac.uk/
login/
your
attendance or via
at today’s
session
Your code for this session
is in the chat
Practice Assignment
Red/amber
similarity score
may prompt
action
Practice Assignment
• Referencing: cases
– can shorten names in text but full names & citation in
reference list
Page Referencing Tips
CONTRACT
Parties INITIAL CONTRACT
Works Desire/ Original parties
Price need for + NEW CONTRACT
change
Time Changed works,
price and
+ time
Varying the Scope
Certainty
• Legal ie contract must have certainty of object
– entirely fixed or
– with change management mechanism
"I am unable to proceed with your "A letter of this day's date from you has
building for want of the floors being just been put into my hands, but I defy
put down, which are not part of my anyone to understand your meaning.
contract. If you wish me to put them Be good enough to state whether I am
down, I will do so on having an order to understand that you are not going to
from you to that effect. Unless they put in the floors, or whether you are not
are put down immediately I will not be going to nail them down, plane, or fit
able to complete my contract by the them, or what is it that you do not
time fixed, and if they are not down intend to do.”
within four days from this time I shall ...Contractor left site so employer
conclude that you do not intend for used alternative labour and
me to go on with my contract, and I ordered floorboards to finish the
will measure the work that I have
job
done, so as to be paid for that only.”
Is it a Change?
“Pillow”
cladding
As defined by subcontract:
“any alteration or addition to or omission from the
Sub-Contract Works or any change in the design,
quality or quantity of the Sub-Contract Works
which is required by a direction of the Contractor
issued under the Sub-Contract.”
Is it a Change?
Scope = deficient tender drawings + all other information
in subcontractor’s possession
“It is legitimate, in my opinion, when interpreting the
contractual obligation undertaken by the [subcontractor]
in terms of the pricing schedule to have regard to the
greater degree of specification contained in the table.
Such specification constituted background knowledge
available to the parties at the time when the contract was
entered into and thus relevant to identification of the
intention of the parties”
Right to Finish?
Colledge (1999)
Is it Permitted?
A clause entitling [a party] Omissions
to vary the works must be Right to finish
construed carefully so as Do not deprive contractor
not to deprive the of profit
contractor of his Clear words to pass to
contractual right to the another contractor
opportunity to complete Motive is irrelevant
the works and realise such
profit as may then be
made.
• Conditions precedent
– impact on rights of parties
– enforceable?
Change in Practice
Change in Practice (1)
Similar conditions?
• Arbitrator examined pre-contract data relating to ground
conditions (the relevant conditions for the change)
• Court restricted to determining similar conditions from
contract documents