Process Plant Design and Simulation Handbook
Process Plant Design and Simulation Handbook
Handbook
Ajay S. Satpute
TABLE OF CONTENTS
CHAPTER 1: GETTING STARTED
Process engineering
What does a Process Engineer do?
Skillset required for Process Engineers
Various packages used in industry
Concept / Feasibility Study
Front End Engineering Design
Detail Engineering Design
As-built drawings
Process Standards
Exercises
CHAPTER 2: DESIGN CONDITION EVALUATION
Temperature System
Operating Temperature
Maximum Operating Temperature
Upset Temperature
Design Temperature
Minimum metal temperature
Pressure System
Operating pressure
Maximum operating pressure
Design pressure
Vapor and vapor-liquid systems protected by relief
valves
Vapor and vapor-liquid systems protected by rupture
disks
Liquid-Full systems
Shell & tube heat exchangers
Pipeline systems
Lower Design pressure
Maximum allowable working pressure
Maximum allowable incidental pressure
Hydrostatic Test Pressure
Exercise
CHAPTER 3: PROCESS DELIVERABLES
Process Design Basis
Block Flow Diagram
Process Flow Diagram
Piping & Instrumentation Diagram
Operating, Control & Safeguarding Philosophy
Process Datasheet
HAZID
HAZOP
Exercises
CHAPTER 4: PROCESS SIMULATION SOFTWARE
Aspen HYSYS
Aspen Flare System Analyzer
Aspen Exchanger Design and Rating
FluidFlow (from Flite Software NI Ltd.)
Bentley WaterGEMS
Bentley HAMMER
PIPESIM (from Schlumberger)
FlareSim (from Schlumberger)
OLGA (from Schlumberger)
VMGSim (from Schlumberger)
UniSim (from Honeywell)
PIPENET (from Sunrise Systems Ltd.)
Flow Master (from TechNet Alliance)
EPANET (from EPA)
PRO II (from AVEVA)
MySep (from Kranji Solutions)
Pipeline Studio (from Emerson)
Petro-SIM (from Yokogawa)
Exercise
CHAPTER 5: LINE SIZING USING ASPEN HYSYS
Velocity criteria
Pressure drop criteria
Misc. criteria
Water service
Liquid and Gas service
Flow-induced vibrations
Pulsation and transient vibrations
High-frequency acoustic excitation
Transient/Surge analysis
Measures for mitigating surge pressure in pipeline
Simulation
Exercises
CHAPTER 6: PUMP SIZING USING ASPEN HYSYS
Centrifugal Pump
Positive Displacement Pump
PD Pump behavior and safety
PD Pump Types
Minimum Flow By-Pass
Centrifugal Pumps Guidelines
Positive Displacement Guidelines
Capacity Adjustment for Metering Pumps
Pressure Relief for Positive Displacement Pumps
Pulsation Devices for Positive Displacement Pumps
Net positive suction head available
Net positive suction head required
Differential Pressure or Differential head
Pump Motor Brake Kilowatt
Typical Pump Curve
Simulation
Exercises
CHAPTER 7: CONTROL VALVE SIZING USING ASPEN HYSYS
What is a control valve?
What is a Cv?
Control Valve Sizing Criteria
Valve Sizing Criteria
Common flow characteristic curves
Control Valve selection process
Self-acting regulators
Types of self-acting regulators
Simulation
Exercises
CHAPTER 8: ORIFICE SIZING USING ASPEN HYSYS
Simulation
Exercises
CHAPTER 9: SEPARATOR SIZING USING ASPEN HYSYS
Types of Separators
Separator Basic Design Criteria
Mist Extraction Equipment
Souders-Brown Equation
Recommended values of k
Simulation
Exercises
CHAPTER 10: HEAT EXCHANGER SIZING USING ASPEN EDR
Simulation
Exercises
CHAPTER 11: DISTILLATION COLUMN SIZING USING ASPEN
HYSYS
Exercises
CHAPTER 12: OPTIMIZER TOOL IN ASPEN HYSYS
Exercises
CHAPTER 13: PSV SIZING USING ASPEN HYSYS
Terminology
When to provide a PRV?
Types of PSV
Chatter
Chatter solution
Rupture disc
quiz
Review of API 520 Part 1
Review of API 521
Review of API 526
Simulation
Exercises
CHAPTER 14: PROCESS PLANT DESIGN USING ASPEN
HYSYS
Maximum design pressure
Minimum design pressure
Maximum design temperature
Minimum design temperature
Line sizing criteria
Separator sizing
Atmospheric tank design
Heat exchanger design
Operational drain, vent and flushing requirements
Plant design problem
Simulation
Exercises
CHAPTER 15: ASPEN HYSYS DYNAMICS (SIMPLE PROBLEM)
CHAPTER 16: ASPEN HYSYS DYNAMICS (PROJECT
PROBLEM)
CHAPTER 17: TYPICAL INTERVIEW QUESTIONS
CHAPTER 1: GETTING STARTED
Process engineering
Process engineering is the utilization of the laws of
physics and chemistry to convert less useful raw materials
to more useful products. This involves process plant
design, operation, optimization, and troubleshooting.
Process engineering is required in almost all industries
like agriculture, automotive, biochemical, chemical,
material development, mining, nuclear, oil & gas,
petrochemical, pharmaceutical, etc.
As-built drawings
The constructed plant and designed plant do not match
exactly all the time. This happens due to many reasons
given as below;
Piping Systems
Exercises
Pressure System
A pressure system is a single equipment or a group of
equipment along with associated piping that within its
boundaries remains open under all conditions, and with no
possibility of blockage due to freezing, , fouling,
sublimation, debris etc. It will not be higher than the
pressure rating of any system component. The effects of
static head will be considered.
When a system approach is taken, the hydraulics shall be
evaluated to ensure that no equipment exceeds its design
pressure before a pressure relief device activates, and
during relieving conditions, no equipment exceeds the
allowable accumulation permitted by either the applicable
code or local requirements.
Operating pressure
The Operating Pressure (OP) is the gauge pressure which
prevails inside equipment and piping during any intended
operation.
Maximum operating pressure
The Maximum Operating Pressure (MOP) is typically at
least 105% of the OP to provide adequate flexibility for
the control of the intended operations. The MOP may not
be less than 1.0 bar above the OP. For pipeline
application Maximum Allowable Operating Pressure
(MAOP) or MOP is the maximum internal pressure at
which a pipeline system or parts thereof can be operated.
MAOP will not exceed 80% of the hydrotest pressure.
Design pressure
The Design Pressure (DP) is the highest gauge pressure
that, according to mechanical design codes, an equipment
can be continually subjected to at or below the Upper
Design Temperature, and above the Lower Design
Temperature. It may be rounded up to the next 0.5 barg
increment. This pressure provides the basis for relief
valve set pressure.
Vapor and vapor-liquid systems protected by relief
valves
Equipment that is protected by a relief valve discharging
into a flare system or combined vent system shall have a
minimum design pressure of at least 3.5 barg due to the
potential back pressure exerted on the relief device. When
using sonic flare tips, the minimum design pressure will
be considerably higher than 3.5 barg. Design pressures
lower than 3.5 barg may be considered if the relief valve
discharges directly to the atmosphere or is routed to a
downstream system that has a design pressure of less than
3.5 barg.
If a DP of 110% MOP is substantially more costly than a
DP of 105% MOP, then 105% MOP can be applied,
subject to the approval of the client.
The DP is greater than MOP by adequate margin.
For pumps and compressors with an isolation valve
between it and upstream system, the suction lines from and
including the suction valve shall have the same design
pressure as on the discharge side.
The DP of compressor suction and intermediate stage
systems (e.g. coolers, condensers, knock-out drums) will
be sufficiently high to prevent the opening of pressure
safety valves through pressure equalization “settle out”
after the compressor has shut down.
Design pressure and temperature should be optimized to
eliminate and reduce relief cases where practically
possible, to provide an inherently safe and sustainable unit
design, and to reduce costs.
Vapor and vapor-liquid systems protected by rupture
disks
Rupture disks are highly stressed in service. To avoid
premature failure because of corrosion, creep and fatigue,
a substantial margin (at least 30% of the normal rupture
pressure for tension-loaded disks, and at least 10% of the
minimum rupture pressure for reverse-buckling disks) will
be allowed between the MOP and the design pressure of
the equipment.
Liquid-Full systems
Liquid-Full systems will be designed to withstand pump
shut-off pressure, if they can be “blocked in” while pumps
feeding them could continue to operate. The shut-off
pressure is the pressure at the discharge of a centrifugal
pump with the suction pressure at the maximum possible
value and the discharge system closed.
For systems that do not normally operate liquid full but
could become liquid fill during an upset condition, it may
be determined whether the system is to be designed for
shut-in pressure or whether some other means of
safeguarding is required.
For steam or gas turbine-driven pumps and variable speed
electric motor driven pumps, the maximum possible speed
during operation of the pump shall be evaluated since this
can influence the design pressure considerably.
Shell & tube heat exchangers
The most unfavorable combination of design pressures on
the shell and tube side that occur, will be used in the
calculations for tube sheets, floating heads and tubes.
The design pressure of the high-pressure side of the
exchanger should be lower than the corrected hydrotest
pressure of the low-pressure side of the exchanger or a
relief device is required to protect against tube rupture.
If design pressure is specified to eliminate the need for a
relief device for tube rupture, the (mechanical) design
pressure of the low-pressure side of the exchanger will be
extended up to and including the block valves.
Pipeline systems
The design pressure at any point will be equal to or
greater than the MAOP.
Lower Design pressure
The Lower Design Pressure (LDP) is the external design
pressure or the sub-atmospheric pressure at the top of the
equipment in its operating position.
LNG rundown, loading, and circulation lines, as well as
boil-off gas lines, will be designed for full vacuum to
enable vacuum drying during commissioning.
Vessels that are in steam service should be designed for
full vacuum at 150 °C.
For vapor with an atmospheric dewpoint of 0 °C or
above, it will be checked whether vacuum can develop in
the equipment if the heat input to the equipment fails.
If the pressure drops below atmospheric pressure due to
utility failure, instrument failure, etc., the minimum
possible absolute pressure shall be stated in the
documents for mechanical design.
Steaming-out and draining operations shall be evaluated
when determining the LDP.
Maximum allowable working pressure
The Maximum Allowable Working Pressure (MAWP) is
the maximum gauge pressure permissible at the top of the
equipment with the equipment installed in its operating
position and at a designated temperature. The MAWP is
equal to or greater than the DP.
Maximum allowable incidental pressure
Maximum Allowable Incidental Pressure (MAIP) is a
term used to describe infrequent short periods during
which the pipeline system may be subjected to pressures
greater than MAOP.
Examples of incidental pressure include surge, failure of
pressure controlling equipment, and cumulative pressure
during activation of overpressure protection devices. The
MAIP should not exceed 90% of the hydrotest pressure.
Hydrostatic Test Pressure
The test pressure shall be 1.5 times the design pressure.
Pressurizing of the system shall be carried out in
increments of 25% total pressure value or as designated
by the Client at the time of testing up to the test pressure.
There will be a hold for 15 minutes at each increment.
This is to ensure that the system is stabilized and to avoid
over pressurizing. Once the test pressure has been
attained, it is to be maintained for one hour before the
detailed inspection takes place. The test medium shall be
potable water.
Exercise
Process Control
Safeguarding
Overpressure protection
HP/ LP Interfaces
Non-Return valves
Miscellaneous Technical
Stream numbers on major process streams
Equipment
Piping
Safeguarding
Aspen HYSYS
General process simulation and modeling software very commonly used in
the upstream oil and gas industry is HYSYS. HYSYS is extensively used for
developing PFD and mass and heat balance.
FluidFlow Liquid
FluidFlow Gas
FluidFlow Two-Phase
FluidFlow Non-Newtonian & Slurry
Bentley WaterGEMS
It is used for the analysis and design of water networks.
Create and manage customized reports that automatically
combine graphs, data tables, color-coded and annotated
plan views, and more into a single report. Fire flow,
hydraulics, operations, criticality, and water quality can
be modeled.
Bentley HAMMER
HAMMER determines appropriate surge control
strategies and reduce transients. It uses the Method of
Characteristics, the benchmark standard for hydraulic
transient analyses. One can run both transient and steady-
state analyses in HAMMER.
PIPESIM (from Schlumberger)
A simulation and modeling software used for steady-state
modeling of “pipelines” both for single-phase, two-phase
and three-phase flow.
FlareSim (from Schlumberger)
Flaresim provides full 3D flame-shape analysis with
complete flexibility in the location and orientation of
multiple stacks, and rapid evaluation of flare systems
under different wind speeds and directions. Shield options
can be included. Working from the opposite perspective,
Flaresim allows you to design stack or boom length to
meet specific radiation, noise, or surface-temperature
limits at defined receptor points.
Flow assurance
Designing, routing, sizing of pipeline networks
Upset, leak and survival time analysis
Strategic, operational and capacity planning
Rapid assessment of unscheduled changes in
operation
Operational prognosis
Compressor requirements
Fuel consumption calculations
Line pack management
Assessment of storage requirements
Surge Analysis
Exercise
Misc. criteria
Pipe Roughness
For all calculations of pressure drop, the following pipe
roughness values should be used:
Water service
Hazen-Williams equation is used for pressure drop
calculation.
The Hazen–Williams equation is an empirical relationship
that relates the flow of water in a pipe with the physical
properties of the pipe and the pressure drop caused by
friction. It is used in the design of water pipe systems such
as fire sprinkler systems, water supply networks, and
irrigation systems. It is named after Allen Hazen and
Gardner Stewart Williams.
The Hazen–Williams equation has the advantage that the
coefficient "C" is not a function of the Reynolds number,
but it has the disadvantage that it is only valid for water.
Also, it does not account for the temperature or viscosity
of the water.
Where;
Equation 1:
This equation is valid for both laminar and turbulent flow
regimes of any fluid with fully developed and
incompressible flow. It can be used for gas services as
long as there is only a negligible change in gas density
across the pipe length. The formula for calculating the
Darcy friction factor is different for laminar (equation 2)
and turbulent flow (equation 3 - Haaland equation).
Laminar flow meaning Reynolds number less than
2000.
Equation 2:
Equation 3:
∆P : Pressure drop, Pa
fD : Darcy friction factor
L : Length of pipe, m
V : Velocity, m/s
NRe : Reynolds number
ϵ/ d : Relative roughness
d : Inside pipe diameter, m
ρ : Liquid density, kg/m3
n : Constant (n=1 for liquid services and
n=3 for gas services)
Flow-induced vibrations
Flow-induced vibrations are more predominant in turbulent flow regime
piping systems. The turbulent flow regime generates potentially high levels
of kinetic energy local to the turbulent source. This energy is distributed
across a wide frequency range, most of the excitation is concentrated at low
frequency. This type of vibration leads to displacement of the piping system
and in some cases also leads to damage to pipe supports.
Susceptibility to failure of piping systems due to flow-induced vibrations:
Table 5.1:
Piping system falls under medium and high susceptibility
failure categories shall be further assessed and designed
per Section 3, “Energy Institute guidelines for the
avoidance of vibration induced fatigue failure in process
pipework”.
If the piping system cannot meet detailed assessment
“Energy Institute guidelines for the avoidance of vibration
induced fatigue failure in process pipework” requirements
for medium and high susceptibility failure categories, the
piping system shall be evaluated using dynamic analysis
methods.
Pulsation and transient vibrations
Pulsation due to periodic flow-induced excitation, which
is only relevant for gas lines containing dead legs, is
defined as follows;
where
where:
We will learn how to use the “Adjust” function. As per the problem
statement, the water flow rate is 30 m3 /h, so that will be the target and the
variable will be the mass flow rate value of stream “1”.
Select “Adjust” function from the model palette.
Figure 5.4: Adjust function
Double click on “ADJ-1” to open the Adjust window. Select “Target
Variable” and “Adjusted variable”.
Figure 5.5: Adjust function
Figure 5.6: Adjust function
The back-calculated mass flow rate value is 29973.3 kg/h which is equal to
30 m3 /h.
Figure 5.10: Adjust function
Use Model Palette to insert the Pipe segment, Material Stream and Energy
Stream.
Figure 5.11: Pipe segment
Use the “Attach” function to connect the streams.
Figure 5.12: Attach function
We will consider no heat loss or gain for this pipe segment. Double click on
energy stream and write heat flow value as zero.
Figure 5.13: Energy stream
Now let’s change the problem statement again. Instead of feed as liquid, we
will change it to saturated steam at 5 barg pressure. Adjust function is
deleted. The mass flow rate of steam is 10000 kg/h. Temperature is deleted.
The vapor fraction is 1. Saturation temperature calculated by HYSYS is
158.9 o C.
Figure 5.21: Material stream
Double click on Pipe table. Replace liquid velocity by Outlet vapor velocity.
Figure 5.22: Show table
Double click on the pipe segment and change pipe NB from 65 NB to 300
NB. Pipe length shall be 100 m. The calculated velocity is 12 m/s and
pressure drop 0.005 bar. As per API 14E gas maximum allowable velocity is
18 m/s. As above velocity is less than 18 m/s, 300 mm NB pipe size is
adequate.
Figure 5.23: Pipe segment
Let’s now carry out two-phase line sizing. The material stream shall be 5%
(mole) Propane and 95% (mole) n-Butane at 7 barg and 66 oC. The mass
flow rate is 1000 kg/h.
Figure 5.35: Two phase line sizing
The fluid package used is Peng Robinson.
Figure 5.36: Two phase line sizing
BIP are available for these components.
Figure 5.37: Two phase line sizing
Figure 5.38: Two phase line sizing
Figure 5.39: Two phase line sizing
Double click on Pipe segment Select flow correlations as shown below.
Figure 5.40: Two phase line sizing
Pipe length is 1000 m with an elevation rise of 50 m. Pipe size selected is 80
mm NB.
Figure 5.41: Two phase line sizing
Heat transfer data is as below;
Figure 5.42: Two phase line sizing
Select “Flow Assurance” tab. Then choose the “Erosion”
tab. Check “Do Erosion Calc” box. It will calculate fluid
velocity and erosion velocity as per API 14E. Fluid
velocity should be comfortably less than erosion velocity.
For pipe size of 80 mm NB, fluid velocity is less than
erosion velocity for the given pipe length. Hence 80 mm
NB is adequate for this application.
Where,
PD Pump Types
A positive displacement pump can be further classified
according to the mechanism used to move the fluid:
Intermittent service
Minimum flow bypass using orifice plate, in
which case pump design flow rate shall be the
process flow rate (as per heat and material
balance) plus the minimum flow bypass rate.
For reflux pumps, the design flow rate shall be at
least 120% of the operating flow rate.
Minimum Flow By-Pass
API STD 610 defines the following two minimum flows
for centrifugal pumps:
Where:
Pd : Differential pressure, m
Ρ : Density of the liquid at the pumping
temperature, kg/m3
g : Acceleration due to gravity, 9.81 m/s2
η : Pumping efficiency, expressed as a
fraction
Typical Pump Curve
Figure 6.4: Pump curve (head vs flowrate)
Figure 6.5: Pump curve (head vs pump efficiency)
Figure 6.6: Pump curve (head vs NPSHr)
Simulation
Let’s now solve a pump sizing problem using Aspen HYSYS.
Water at 30 o C and 0 barg pressure is pumped to 3 barg pressure. The water
flow rate is 30 m3 /h.
To solve this problem, we need to first select water as a component and
IAPWS as Fluid Package.
Figure 6.7: Component list
Figure 6.8: Fluid package
Use model palette to get 2 material streams and a pump, connect those items,
and provide given data in the inlet stream as shown below. Use Adjust
function to achieve 30 m3 /h flow by varying the mass flow rate of stream
“1”.
Figure 6.9: Pump
Provide outlet pressure as 3 barg.
Figure 6.10: Pump
Double click on Pump P-100. In the Design\Parameter tab, default pump
efficiency is given as 75%. Change it to 60%.
Figure 6.11: Pump
Select “Rating\Nozzles” Tab and change Inlet and Outlet pipe diameter as 0.1
m and 0.065 m (considering velocity criteria).
Figure 6.12: Pump
Select “Rating\NPSH” and check the “NPSH activate” box. HYSYS
calculates NPSHavailable as 10 mlc.
Figure 6.13: Pump NPSHA
We can also provide pump curve data (H v/s Q and Efficiency v/s Q). Select
“Rating\Curves” tab. “Add Curve” and provide the flow rate, head, and
efficiency. This data should come from the pump vendor catalog.
Figure 6.14: Pump curve
Check the “Use Curve” box, so that the provided pump curve data is used in
the model. But HYSYS points out that it is “Overspecified”. That means we
have given more information than required.
Figure 6.15: Pump curve
It may be noted that we have earlier provided pump efficiency (60%) and
discharge pressure (3 barg) as input parameters. We will now delete these 2
input parameters. Also, provide a table for the pump as shown below.
Figure 6.16: Pump
Now if we use the same pump (with same pump
characteristic curves), but change the liquid from water to
benzene, then let’s see what would be the effect on pump
discharge pressure and NPSHavailable values. Use NRTL as
a fluid package.
Figure 6.17: Pump
What is a Cv?
Cv is a flow coefficient that provides the capacity of a
valve.
Where;
Equal percentage:
Self-acting regulators
Self-acting regulators shall only be used in services that
meet all the following requirements:
Fluid services that are all the following:
Clean.
Not very toxic.
Below its auto-ignition temperature.
Permanent installations that require no operator
intervention (e.g., changing of the setting).
In the “Fluid Packages”, click on the “Add” button to specify a fluid package.
Doing so will bring you to a list of all the different equations of state HYSYS
uses. The simplest fluid package, you might be aware of the Antoine equation
for calculating the vapor pressure of a fluid.
Figure 7.10: Fluid package
See the figure below for some general guidelines on picking the appropriate fluids
packages.
Figure 7.11: Fluid package selection guideline
As the calculated Cv is 190.8, the adequate Cv as per the above table shall
be 225. This falls under 4” valve size and 3.5” trim size. This is how the
valve size is selected.
Now save this example as Example 2. In example 2, we will consider the
same process parameters, but instead of the ON/OFF valve, XV-01 shall be a
Flow control valve (FCV-01). Also, it is to be noted that the 360 m3 /h
(347608 kg/h) flow rate is the maximum or design flow rate. Most control
valve vendors recommend operating range from 20% to 80%, meaning for
minimum flow conditions, valve opening shall not below 20% and for
maximum flow conditions, valve opening shall not be more than 80%. This
helps better control of the process parameter. For the flow control valve, the
suggested
trim characteristic is Linear.
The model snapshot is given below;
Figure 7.26: Control valve sizing
The interpretation of the above results is as below;
Cv of 190.8 is required when the valve is at its maximum capacity, but in this
case, the actual valve opening shall be 80%. Hence, we need to first get the
vendor catalog for Linear trim and search for the Cv value equal or greater
than 190.8 in the 80% valve opening column. (100% valve opening in the
above snapshot is correct).
The below table is for the Linear trim control valve.
Table 7.4: Cv table for linear trim
As per the above vendor catalog, FCV-01 size is 6” and trim size is 3”.
Although Cv in 80% column is 190 (and not 190.8), 190 is selected as it is
very close to 190.8.
We will do one more exercise here. If instead of 3” trim size, you select 3.5”
trim (6” valve size), what will be the valve opening for the same pressure
drop and flow rate?
FCV-01 opening shall be around 60%. Can you figure out, how?
Now let’s change the problem statement again. Let the pressure be the same,
but instead of sub-cooled liquid, it shall be saturated steam. The flow rate is
changed to 10000 kg/h, which is the normal flow rate. It shall be a pressure
control valve. Double click on stream “In” and delete temperature value.
Provide vapor fraction as 1. It shall automatically calculate Tsat at 680 kPa.
Change flow rate to 10000 kg/h. Change valve tag to PCV-01.
Figure 7.27: Control valve sizing
Liquid-Liquid Separator
Two immiscible liquid phases can be separated using the
same principles as gas-liquid separators except that they
must be designed for much lower feed velocities because
of the difference in density between two liquids is less
and the separation becomes more difficult.
Gas-Liquid (Oil)-Liquid (Water) Separator (Three
Phase Separator)
A vessel that separates the well fluids into gas and two
types of liquid oil & water. A three-phase separator can
be horizontal, vertical, or spherical. This type of separator
is commonly called a free water knock because its main
purpose is to remove free water that can cause problems
such as corrosion and formation of hydrates.
Figure 9.3: Horizontal separator (3 phase)
Classification by Application
Oil and gas separators are further classified according to
the application as below:
Test Separator
A test separator is used to separate and to meter the well
fluids. The test separator can be referred to as a well
tester. They can be permanently installed or portable. Test
separators can be equipped with various types of
measuring devices for measuring the Gas oil ratio (GOR),
Water cut, Basic sediments & water (BS & W).
Production Separator
Production separator is used to separate the produced
well fluid from a well on continuous basis.
Separator Basic Design Criteria
Following three main factors are to be considered in
separator sizing:
Vapor capacity:
Liquid capacity:
Operability:
Most mesh pads are 150 mm thick with 144 – 192 kg/m3 bulk density.
Minimum recommended pad thickness is 100 mm. Typical mesh pad
installation is shown below.
Figure 9.4: Mist extractor
Vane pack
Vane or chevron-type mist extractors (vane-pack) use
closely spaced blades arranged to provide sinusoidal or
zigzag flow paths. The changes in gas flow direction
combined with the inertia of the entrained liquid droplets,
cause impingement of the droplets onto the plate surface,
followed by coalescence and drainage of the liquid to the
liquid collection section of the separator.
Figure 9.5: Vane pack
Cyclonic Separator
Cyclonic separator removes particulates from an air, gas
or liquid stream, without the use of filters, due to vortex
separation. Gravity and rotational effects are used to
separate mixtures of solids and fluids. The method is also
used to separate fine droplets of liquid from a gaseous
stream.
Souders-Brown Equation
The Souders–Brown equation is used to calculate the
maximum allowable vapor velocity in vapor-liquid
separation vessels (variously called flash drums, knockout
drums, knockout pots, compressor suction drums, and
compressor inlet drums). The equation is given below;
Where:
Notes:
Simulation
Let’s solve an example.
Design a shell and tube exchanger for the following duty 20000 kg/h of
benzene. It enters the heat exchanger at 90 o C and to be cooled to 60 o C. The
cooling medium is cooling water entering the exchanger at 30 o C and exits at
37 o C. Benzene inlet pressure is 5 bar and that of water is 6.5 bar.
A pressure drop of 0.8 bar is permissible on both the sides. Allowance
should be made for fouling by including a fouling factor of 0.0003 m2 .K/W
on the Benzene side and 0.0001 m2 .K/W on waterside.
We limit the exchanger length as 5 m.
Figure 10.1: Heat exchanger problem
SOLUTION
Open Aspen EDR new file. Check the “Shell & Tube” box and “Create” the
new file.
Figure 10.2: New case
CW required =
33218 kg/h
Heat exchanged =
250555 kcal/h
LMTD = 39.7 o C
UD = 509.8
kcal/(h.m2 .o C)
No. of tube = 42
No. of tube passes = 2
Shell ID = 205 mm
Figure 10.13: TEMA sheet
Exercises
The error message states that the pressure drop calculated per bed height is
less than the default value.
Figure 11.23: Distillation column
The default value can be changed with the consultation with the vendor.
Assuming the vendor-provided value for “minimum pressure drop per unit
packed height” is 0.01 inch H2 O/ft.
Figure 11.24: Distillation column
Exercises
Calculate:
The reflux ratio and the distillate rate under the specified
conditions.
Data:
Note:
Profit = (Total Toluene selling price + Total THF selling
price) - (Feed cost + Heating cost + Cooling Cost)
Use a range of 0.99 to 0.999 for the THF limit & 0.9 to
0.99 for the toluene.
Add components and select the fluid package.
Figure 12.1: Components
Click “Next”.
Figure 12.8: Distillation column
Figure 12.9: Distillation column
Figure 12.10: Distillation column
Figure 12.11: Distillation column
Click “Done”.
Figure 12.12: Distillation column
Click “Monitor”.
Figure 12.13: Distillation column
Click “Add Spec.”.
Click “Column Component Fraction” and “Add Spec.”.
Figure 12.14: Distillation column
Optimization
We need to check if the operating conditions are optimum or not. The
Variables to check are: THF Purity & Toluene Purity.
Using the Optimizer tool.
Click “Home” >> “Optimizer”.
Figure 12.17: Optimizer
Select “Original” as “Data Model” and click “Variable”.
Figure 12.18: Optimizer
Click “Add”.
Figure 12.19: Optimizer
Figure 12.20: Optimizer
Click “Select”.
And do the same steps to add the other variable “Toluene Purity”.
Figure 12.21: Optimizer
Click “Select”.
Use a range of 0.99 to 0.999 for the THF limit & 0.9 to 0.99 for the toluene.
Figure 12.22: Optimizer
Click “Spreadsheet”.
Figure 12.23: Spreadsheet
Click “Done”.
Right click “B3” >> “Import Variable” >> “ovhd” >> “Mass Flow”.
Figure 12.29: Spreadsheet
The same procedure is to be used and other parameters are imported in the
spreadsheet.
Figure 12.30: Spreadsheet
Figure 12.31: Spreadsheet
Terminology
Operating pressure
MAWP
Design pressure
Pressure, together with the design temperature, is used to determine the
minimum permissible thickness or physical characteristic of each vessel
component as determined by the vessel design rules. The design pressure
is selected by the user to provide a suitable margin above the most
severe pressure expected during normal operation at a coincident
temperature. This pressure may be used in place of the maximum
allowable working pressure (MAWP) in all cases where the MAWP has
not been established. The design pressure is equal to or less than the
MAWP.
Design pressure here is calculated to be 7.5 barg.
Set pressure
The inlet gauge pressure at which the pressure relief device is set to open
under service conditions.
Set pressure in this example will be a 7.5 barg. As per API 520 Part 1,
we could have set it at less than 7.5 barg (say at 7 barg) also, but we
didn’t, to avoid unnecessary popping of PSV and loss of material. But if
the vessel is derated (due to aging leading to reduction of shell
thickness), then one may choose to set the PSV at even lower pressure.
If there are 2 PSVs (both working) protecting a single vessel, then the
first PSV can be set at 7.5 barg (max. 100% of design pressure) and
second will be set at 7.875 barg (max. 105% of design pressure).
Accumulation
The above table from API 520 Part 1 can be used to determine allowable
set pressure and maximum accumulated pressure. If there is a single PSV,
then for non-fire (blocked outlet) case, the vessel shall be allowed to
have a maximum pressure of 110% of design pressure. If design pressure
is 7.5 barg, then maximum pressure allowable shall be 110% of 7.5 barg
(8.25 barg).
For the fire case, maximum accumulated pressure shall be 121% of
design pressure, irrespective of the number of PSVs.
In the above table, the only variable is design pressure. Hence it is
advisable to prepare an excel sheet to calculate all the parameters given
in the table w.r.to design pressure. So whenever PSV sizing has to be
done, the same table can be referred.
Overpressure
The pressure increase over the set pressure of the relieving device.
Overpressure is expressed in pressure units or as a percentage of set
pressure. Overpressure is the same as accumulation only when the
relieving device is set to open at the maximum allowable working
pressure of the vessel.
Blowdown
The difference between the set pressure and the closing pressure of a
pressure relief valve expressed as a percentage of the set pressure or in
pressure units.
The closing pressure of PSV is a bit less than that of its set point. If the
set pressure is 7.5 barg, then closing pressure may be 7.4 barg (depends
on the PSV model). 0.1 bar shall be the blowdown.
Superimposed backpressure
Types of PSV
Conventional Spring-Loaded Safety Relief Valve
Advantages
Most reliable type if properly sized and operated
Can be used in many services
Disadvantages
Relieving pressure affected by back pressure
Susceptible to chatter if built-up back pressure is
too high
Advantages
Relieving pressure not affected by
back pressure to a certain extent
Can handle higher built-up
backpressure
Disadvantages
Bellows susceptible to
fatigue/rupture
May release flammables/toxics to
atmosphere
Requires separate venting system
Advantages
Relieving pressure not affected by
back pressure
Disadvantages
Pilot is susceptible to plugging
Potential for backflow
Chatter
Chatter causes:
Avoid long
piping runs
Avoid bends/turns
Minimize inlet loss
Install smaller PRV
Inlet line size must be at least equal to PRV inlet
flange size
Inlet piping should slope continuously upward
from vessel to avoid traps
Inlet piping should be heat traced if freezing
liquids could occur
A continual clean purge should be provided if
coke/polymer formation or solids deposition
could occur
Discharge line diameter must be at least equal to
PRV outlet flange size
Maximum discharge velocity should not exceed
70% of sonic velocity
No check valves, orifice plates or other
restrictions permitted
Atmospheric discharge risers should have a drain
hole
The piping design must consider thermal
expansion due to hot/cold release
Auto-refrigeration and need for brittle fracture-
resistant materials
Closed discharge piping should slope
continuously downward to header to avoid liquid
traps
quiz
Q. If a single safety valve is present only for fire, it is
permissible to set it at 110% of the MAWP . (T/F)
A. False. A single safety valve must be set no higher than
the MAWP. Only if it is a second valve for a fire
contingency may it be set at 105% of MAWP. And a third
valve can be set at 110% of MAWP.
Q. The highest allowable set pressure of any safety
valve is the maximum allowable working pressure of
the vessel being protected . (T/F)
A. False. Under certain conditions, such as multiple
valves, additional safety valves may be provided set at
pressures higher than the MAWP. However, at least one
must be set no higher than MAWP.
Q. The Design Pressure and the Maximum Allowable
Working Pressure of a vessel are the same. (T/F)
A. False. Design Pressure is a process design term that
specifies the minimum pressure to which the vessel must
be designed. The MAWP, on the other hand, is a
mechanical design term. It goes with the vessel, i.e, it is
the pressure on the vessel’s nameplate and stays with the
vessel no matter where the vessel is used. In practice, the
two are often the same, but not necessarily.
Q. An oversized safety valve can be vulnerable to the
phenomenon known as chatter. (T/F)
A. True.
Q. Safety valve chatter in liquid service is potentially
more serious than in vapor service. ( T/F)
A. True. Because of the liquid hammer effect.
Q. For operating contingencies, the API Code allows
the capacity of a single safety valve to be calculated at
110% of the MAWP. (T/F)
A. True.
Q. Under a fire contingency, the vessel is allowed to
reach a higher pressure than under an operating
contingency. (T/F)
A. True. It is allowed to reach 121% of MAWP.
Q. Accumulation means the same as blowdown. (T/F)
A. False.
Q. If there are two safety valves on a vessel, pressure
during discharge is allowed to reach 116% of the
MAWP. (T/F)
A. True, assuming the second valve is set at 105% of
MAWP as permitted by the code. With 10% accumulation,
maximum pressure becomes 110% of 105%, or (rounded)
116%.
Review of API 520 Part 1
This standard applies to the sizing and selection of
pressure relief devices used in refineries and related
industries for equipment that has a maximum allowable
working pressure of 15 psig (103 kPag) or greater. The
pressure relief devices covered in this standard are
intended to protect unfired pressure vessels and related
equipment against overpressure from operating and fire
contingencies.
This standard includes basic definitions and information
about the operational characteristics and applications of
various pressure relief devices. It also includes sizing
procedures and methods based on a steady-state flow of
Newtonian fluids. One can refer sizing equations for PSV
and RD sizing for gas (critical and subcritical), steam,
liquid (with/without capacity certifications) from API 520
Part 1.
API 520 Part 2, however, deals with the installation
procedure for the PSV and RD. It also provides the line
sizing criteria for the PSV inlet line, which is that the
pressure drop in the PSV inlet line should be less than 3%
of set pressure.
Review of API 521
This standard applies to pressure-relieving and vapor
depressuring systems. Although intended for use primarily
in oil refineries, it is also applicable to petrochemical
facilities, gas plants, liquefied natural gas (LNG)
facilities, and oil and gas production facilities. The
information provided is designed to aid in the selection of
the system that is most appropriate for the risks and
circumstances involved in various installations.
This standard specifies requirements and gives guidelines
for the following:
examining the principal causes of overpressure;
determining individual relieving rates;
selecting and designing disposal systems,
including such parts as piping, vessels, flares,
and vent stacks.
Simulation
Let’s solve an example. In this
example, the following relief requirements are given:
Where;
Q is the total heat absorption (input) to the wetted surface,
expressed in W (Btu/h);
C is a constant [= 43,200 in SI units (21,000 in USC units)
when adequate drainage and firefighting Equipment exist];
[= 70,900 in SI units (34,500 in USC units) when
adequate drainage and firefighting Equipment do not
exist];
F is an environmental factor;
Aws is the total wetted surface, expressed in m2 (ft2 ).
The heat absorbed by the wetted surface shall be used to
increase the liquid temperature (sensible heat) and to
vaporize liquid (latent heat). Accordingly, the vapor load
is calculated by HYSYS. In this example, if sensible heat
is excluded (which is negligible anyway), Q calculated to
be 34500 x 0.3 x 73.40.82 = 350600 Btu/h. Latent heat of
vaporization is 141.6 Btu/lb. Hence vapor load will be
2476 lb/h. Once the vapor load is calculated, the same
formulae from API 520 Part 1 can be used for PSV sizing.
Thermal Relief Valve (TRV)
Equipment and piping that can be blocked in and can be
exposed to increased temperatures shall be protected
against overpressure. TRVs may be installed with
pocketed inlet and outlet lines where plugging and
freezing within the inlet or outlet lines cannot occur or are
prevented from occurring with tracing and insulation.
TRVs shall discharge back into the process, the storage
system, or a plant disposal system.
TRVs shall not discharge to an open drain unless the
following are met:
Separator sizing
Oil retention time shall depend on o API of oil as per API
12J. If o API is more than 35, then retention time can be
considered as 1 minute. If it is between 20 to 30 o API, the
retention time may be taken as 1 to 2 minutes and if o API
is less than 20, then retention time may be considered as 2
to 4 minutes.
For mixed-phase feed with less vapor content, horizontal
separator may be suggested and vice versa.
Typical L/D ratio for horizontal separator is 2.5 to 5 and
H/D ratio for vertical separator is 2 to 4.
Atmospheric tank design
For atmospheric tanks containing flammable liquids, the
purge/blanketing gas flow rate shall be at least 5% higher
than maximum pumping capacity.
In some cases, flame arrestors are recommended for use
on atmospheric tanks. The use of a flame arrestor within
the tank’s relief path introduces the risk of overpressure
due to the flame arrestor clogging/fouling. Flame arrestors
shall be located for easy access and included in a rigorous
maintenance program. Continuous monitoring of
differential pressure across the flame arrestor is advised
if the process fluid is known to contain particulates or
substances which may block the flame arrestor. The
materials in the vent pipe should be corrosion resistant to
reduce the risk of plugging the flame arrestor.
Separator sizing
Heater sizing
Pump sizing
Line sizing
LCV sizing
PCV sizing
FCV sizing
Flow orifice sizing
PSV sizing
Let’s simulate.
First, get the components added and the fluid package
selected shall be Peng Robinson.
The feed stream is converged.
Figure 14.3: Material stream
Feed shall the shell side fluid and hot oil shall be the tube
side fluid in the pre-heater. Pressure drop across pre-
heater (E-100) and Heater is considered at 0.5 bar each.
Figure 14.9: Process scheme
Revised heat duty is given below;
Let’s design.
Separator sizing (as per standard API 12J)
Figure 14.10: Separator sizing
HTA = 28 m2
No. of tubes = 86
No. of passes = 4
Tube length = 5000 mm
Shell ID = 307 mm
UD = 622 W/m2 .K
Pump sizing
Figure 14.19: Pump sizing
Figure 14.20: Pump sizing
Results
Exercises
Methane : 0.04
Ethane : 0.02
Propane : 0.04
i-Butane : 0.15
n-Butane : 0.05
n-Octane : 0.40
n-Decane : 0.30
Methane : 0.04
Ethane : 0.02
Propane : 0.04
i-Butane : 0.15
n-Butane : 0.05
n-Octane : 0.40
n-Decane : 0.30
Click Dynamics\Integrator
Start the simulation for 120 minutes. This is to check, how much time it takes
to fill in the separator (14 m3 * 60% = 8.4 m3 ), when liquid in-flow is 5.4 m3
/h.
Figure 15.20: Integrator 1
Refer below the plot (blue curve). It shows the separator level from 0% to
60%. It takes around 95 minutes to fill the separator to a 60% level.
Figure 15.21: Strip chart
Similarly, refer below the plot for the FCV-1 valve opening (red curve) and
FCV-1 flow rate. Valve opening is around 64%, which means the considered
valve Cv and type is adequate.
Figure 15.22: Strip chart
Similarly, refer below the plot for the PCV-1 valve opening (red curve) and
PCV-1 flow rate. Valve opening is around 43%, which means the considered
valve Cv and type is adequate.
Figure 15.23: Strip chart
Let’s try to simulate a case, where the pressure at inlet stream increases from
5 barg to 15 barg for 1 min and comes back to normal condition (5 barg)
afterward.
Figure 15.24: Integrator
Separator level Alarm will sound at 70% level and Effect (SDV-1 closure)
will initiate at 80% level. In this case “High” checkbox is checked, as trip
happens at High High condition. If there was any trip action for Low Low
condition, then this box would be kept unchecked.
Figure 15.37: Cause & effect matrix
Let’s increase the FIC-1 set point from 4000 kg/h to 8500 kg/h. It shall
increase the separator level. Change Kc of FIC-1 to 0.2.
Figure 15.41: FIC
Click on “Integrator”.
Figure 16.53: Integrator
We can assign run duration, speed, and Calculation step size in “Integrator”.
Figure 16.54: Integrator