Irrigation Structure
Irrigation Structure
1 INTRODUCTION
Hydraulic structures are structures that are fully or partially submerged in water. The essence of
building hydraulic structures is to either divert, disrupt, store, or completely stop the natural flow
of water bodies. Based on the work they are designed to perform on streamflow, hydraulic
structures are categorized as water-retaining structures (dams and barrages), water-conveying
structures (artificial channels), and special-purpose structures (structures for hydropower
generation or inland waterways)
I. Water-retaining structures
The dam is an essential hydraulic structure that all other structures directly or indirectly relied
upon. Dams and barrages are typical water-retaining structures that are built purposely to
impound water. The retained water behind dams and barrages could be used for other purposes
such as irrigation, recreational activities, navigation, and a lot more. Regardless of their size and
type, dams demonstrate high complexity in their load response and interactive relationship with
site hydrology and geology. Dams are of different sizes and shapes and made of various
BY HABTAMU M. 1
IRRIGATION STRUCTURES HANDOUT
materials such as soil or rockfill embankment, mass concrete, reinforced concrete, masonry, and
wood. However, based on the construction materials used, dams are broadly classified into
concrete dams and embankment dams.
Concrete dams comprised of gravity, arch, buttress, barrage, and multiple-arch dams as shown
in Figure a–e. All these dams are constructed of mass concrete and sometimes of masonry with
appropriate structural quality. Recent statistics show that concrete dams occupied only 20–22%,
while embankment dams accounted for 78–80%.
Embankment dams are of two types, earthfall and rockfill, both of which are constructed by
mass filling of naturally existing ground materials (soil and rocks). The construction materials
are graded and well compacted to resist seepage and sliding. Embankment dams are
characterized by having similar moderate face slopes at both upstream and downstream. This
feature gives rise to a broad trapezoidal cross section and a high construction volume, which is
relative to the dams’ height that can cover >300 m.
Any artificial facility cut in the ground with the sole purpose of transporting water diverted
from main sources (river and dams) is termed as the water-conveying structure. These types
of structures are comprised of canals (Figure a) and tunnels (Figure b) (usually made from
BY HABTAMU M. 2
IRRIGATION STRUCTURES HANDOUT
soil and rocks) or siphons, aqueducts (Figure c), flumes (Figure d), and pipelines (usually
made from concrete and metals). Before the construction of any water-conveying structure, a
detailed geotechnical soil test and analysis is recommended to avail the surface and
subsurface properties of the soil on which the structure is upon rest. The same soil test and
analysis also applies to other types and classes of hydraulic structures to ensure safety and to
save resources.
As the name implies, special-purpose hydraulic structures are built as an integral part of
hydraulic project to meet a special purpose such as hydropower generation (e.g., surge towers
and shafts, forebays, and head ponds), navigation (e.g., landings, berths, substations for ship
repair, etc.), fishing (e.g., fish nursery ponds, fish lifts and locks, fishways, etc.), water supply for
domestic and industrial uses (e.g., water intakes to treatment plant, pumping stations, etc.), waste
disposal/sewerage (e.g., sewage headers, pumping stations, channels after treatment plant to
water bodies, etc.), and land reclamation (e.g., irrigation canals, drainage systems, silt tanks, etc.)
BY HABTAMU M. 3
IRRIGATION STRUCTURES HANDOUT
Hydraulic structures are purposely for managing and controlling the flow of water in natural and
built environment systems. Moreover, the primary purposes may include the following flood
control, water conveyance, irrigation, navigation, power generation, domestic and industrial
purposes, environment protection, and recreation, among others.
1. Flood control
Flooding is a geophysical hazard that nonuniformly dispersed in both space and time. Over a
decade, several watershed areas are frequently suffering from flood disaster, which causes
massive destruction and loss of lives, farmlands, crops, access roads, and houses. The effective
way of flood control and reducing its negative impacts is by the construction of dams, water
conveyance structures, culverts, canals, and reservoirs. Many control structures are not solely
constructed mainly for dealing with flood control only. However, sometimes, hydraulic structures
are purposely built for flood control only. In the designing and building of flood control
structures, some vital point of views must be taken into consideration in such that the cost of
construction of such a project structure should be of benefit, concerning the damage reduction
and the public interest when comparing to similar benefits to be derived by the alternative means.
Also, the flood control structures should be reliable and effective as predicted. Even in some
instance, the methods of controlling floods should rather be automatic, not manual.
2. Power generation
Hydropower generation is the production of electrical energy from running water through
turbines without reducing its quantity. The flexibility; long-lasting, storing capability; less
environmental pollution; and the cost-effectiveness of hydropower plants make it attract more
investment as a renewable energy source and role as a way of drought mitigation. The
hydropower system is the leading global source of an estimated 71% of total renewable energy.
Furthermore, hydropower plant reservoirs can also be used as a tool in minimizing the adverse
impacts of climate change and in achieving sustainable development goals.
3. Navigation
BY HABTAMU M. 4
IRRIGATION STRUCTURES HANDOUT
Inland water transportation plays a significant role in the national and global markets. Building
dams and draining of river streams will considerably raise the capacity of inland water
transportation, thereby allowing the smooth movement of a shipping vessel. An important point
to note is that a chain of storage reservoirs would advance navigation depth, straightening out
navigation channels, and support the passage of both small, medium, and even large ships.
However, it is recommended to provide pathways or locks for vessels when dam structures are
built on a large river stream for easy navigation from upstream to the downstream. Also, the
topography of the surrounding environment should be taken into consideration. Hence, the
pathways might be an integral part of the dam or a completely different structure.
4. Irrigation schemes
The irrigation system consists of a (main) intake structure or (main) pumping station, a
conveyance system, a distribution system, a field application system, and a drainage system.
The (main) intake structure, or (main) pumping station, directs water from the source of supply,
such as a reservoir or a river, into the irrigation system.
The conveyance system assures the transport of water from the main intake structure or main
pumping station up to the field ditches.
The distribution system assures the transport of water through field ditches to the irrigated fields.
The field application system assures the transport of water within the fields.
The drainage system removes the excess water (caused by rainfall and/or irrigation) from the
fields.
A large quantity of freshwater is being consumed daily by food processing; mineral mining and
processing; textile, paper, and pulps; nuclear and thermal power plants; and drugs and
pharmaceutical, petrochemical, and metallurgical industries, among others. However, some of
the major industries that use a large volume of water are nuclear and thermal power plants. To
meet both domestic and industrial needs, due to the higher demand for water by many industries,
especially in industrially developed nations, large capacity storage structures are always built to
store local rainfall runoff and water diverted from other river basins. Multipurpose hydraulic
BY HABTAMU M. 5
IRRIGATION STRUCTURES HANDOUT
structures are the primary storage and sources of most water supply for domestic and industrial
purposes.
6. Environment protection
Another vital reason for hydraulic projects is for environmental protection and water
management, which may include farmland improvement by controlling soil erosion;
environmentally friendly hydropower supply; improved quality water supply for human, animal,
and industrial consumption; aquatic food supply; and recreational development. Nevertheless,
the negative impacts posed by the massive hydraulic structures on the environment and public
safety should always be considered in the course of design and construction processes. The
essential environmental issues are for the well-being of people living around the hydraulic
projects and to the other plants and animals for the social needs of humankind.
Many hydraulic projects also serve as a place for tourism, recreational, and sports activities. In
fact, in some countries, sometimes hydraulic projects are specially constructed for recreation
purposes. Some recreational activities carried out at the hydraulic project sites might include
swimming, fishing, boating, canoeing, scuba diving, and lakeside walking. Recreational
activities provide job opportunities to the teeming population and generate incomes to the
government and, at the same time, conserve the natural environment.
They are used to regulate the flow and pass excess flow. They might be gates, spillways, valves,
or outlets.
They are used to measure discharge. They are weirs, orifices, flumes etc.
Division structures
They are used to divert the main course of water flow. They are coffer dams, weirs, canal
headwork’s, intake works.
BY HABTAMU M. 6
IRRIGATION STRUCTURES HANDOUT
Conveyance structures
They are used to guide the flow from one place to another. They are open channels, pressure
conduit, pipes, canals and sewers
Collection structures
They are used to collect water for disposal. They are Drain inlets, infiltration galleries, wells.
They are used to prevent erosion and structural damage. They are stilling basins, surge dams,
check dams.
They are used to maintain river channel and water transportation. Levees, cutoffs, locks, piers,
culverts.
They are used to control or remove sediments and other pollutants. They are racks, screens, traps,
sedimentation tanks, filters, sluiceways.
Hydraulic machine
They are used to convert energy from one form to another. They are turbines, pumps, and ramps.
Storage Structures
They are used for the purpose of storage of water. These may be dams or tanks etc.
Shore protection Structures
They are used to protect banks. Dikes, groins, jetties, revetments.
BY HABTAMU M. 7
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 8
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 9
IRRIGATION STRUCTURES HANDOUT
distributaries (also called ‘distributaries or raj Baha) carry 0.25 to 5 m 3/s of discharge. These
distributaries take their supplies generally from the branch canal and sometimes from the main
canal. The distributaries feed either water courses through outlets or minor distributaries. Minor
distributaries (also called ‘minors’) are small canals which carry a discharge less than 0.25 m 3/s
and feed the watercourses for irrigation. They generally take their supplies from major
distributaries or branch canals and rarely from the main canals. A watercourse is a small channel
which takes its supplies from an irrigation channel (generally distributaries) through an outlet
and carries water to the various parts of the area to be irrigated through the outlet.
The technical aspect of the layout of irrigation is meant for the physical possibility of putting the
proposed infrastructure on the ground. For instance, without the presence of rock-cutting
equipment’s, it is not possible to align a canal on a hard rock formation. Thus, one has to look an
alignment through which canals can easily be excavated.
The economic feasibility of an alignment will be determined after making a comparison between
various technically possible alternatives on an economic basis. For specific irrigation system
alignment there can be different alternatives; still, one has to assess all and choose the one with
the lowest costs.
Contour canal: is a canal aligned nearly parallel to the contour lines. However, the canal
should have sufficient slope along the flow in order to produce the required velocity of
flow. Such a canal irrigates only on one side of the canal (lower side). Such canals would
cross maximum number on natural drainages.
BY HABTAMU M. 10
IRRIGATION STRUCTURES HANDOUT
150m
125n
-------
ALIGNMENT
F O LLOW S
R ID G IN E
R IG H T
BA K
C ANAL
(RBC)
ALlG N\1E
FOL.LO\VS
R IDGE L IN
BY HABTAMU M. 11
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 12
IRRIGATION STRUCTURES HANDOUT
Evaporation losses: The loss due to evaporation is generally a small percentage of the total loss
in unlined canal. It hardly exceeds 1 to 2 percent of the total water entering into the canal. The
evaporation losses depend upon: (i) Climatic factors such as temperature, humidity and wind
velocity and (ii) Canal factors such as water surface area, water depth and velocity of flow.
Maximum loss is there in summer months when temperature are high and wind velocities are
also high. Similarly, losses are maximum in unlined canals due to wider water surface area,
shallow water depth and low velocity. The average evaporation loss per day may vary between
4mm to 10mm.
Transpiration losses: The transpiration loss takes place through lot of vegetation and weeds
growth along the bank of canal. However, this forms an extremely small part of loss.
Seepage losses: Seepage losses constitute major portion of loss in an unlined canal. The seepage
losses are due to: (i) absorption of water in the upper layer of soil below the canal bed and due to
(ii) percolation of water into the water table, thus raising the water table. If, however water table
is much lower, seepage losses are only due to absorption. Percolation losses are always much
more than the absorption losses.
Percolation (or seepage) losses: When the water table is close to the canal bed, Percolation (or
seepage) occurs from the canal to the water table. There is a direct flow from the canal to the
ground water reservoir. Almost all the water which seeps from the channel joins the ground water
reservoir. The seepage losses mainly depend upon the total seepage head (difference between
canal water level and water table level) and the type of soil and are independent of the depth of
water in the channel.
a. Canal lining: Canal lining is the process of making the bed and side of the canal
impervious to reduce canal losses.
b. Increasing the height of the canal despite width: This reduces evaporation and
percolation losses
c. Provision of proper slope gradient to the canal to increase the velocity of the water.
d. Removal of vegetation from the canal and its sides
BY HABTAMU M. 13
IRRIGATION STRUCTURES HANDOUT
1. Non alluvial channels: These are excavated in non-alluvial soils such as loam, clay,
moorum, boulder, etc. There is no silt problem in these channels and they are relatively
stable.
2. Rigid boundary channels: In the Rigid boundary channels, the surface of the channel is
lined. In such channels, relatively high velocity can be permitted which does not allow the
silt to get deposited; hence, the problem of silt does not exist.
3. Alluvial channels: These are excavated in alluvial soils, such as silt. In such channels, the
quantity of silt may vary from section to section along the reach. The silt content may
increase due to scouring of bed and sides of the channel and it may decrease due to silting at
some sections. If velocity is high, scouring occurs and if velocity is low, silting may occur.
Such channels should be designed for a no scouring and a non-silting velocity called the
critical velocity.
BY HABTAMU M. 14
IRRIGATION STRUCTURES HANDOUT
scoured. Moreover, the velocity is low which encourages silting. Therefore, in an alluvial
channel,
scouring and silting may occur if the channel is not properly designed. The quantity of silt
transported by water in an alluvial channel varies from section to section due to scouring of bed
and sides as well as due to Silting (or deposition). If the velocity is too high, scouring may occur.
On the other hand, if the velocity is too low, silting may occur.
The command of an irrigation channel decreases if the scouring occurs because the full supply
level falls. The discharge capacity is decreased if the silting occurs because the cross-section is
reduced. Therefore, the alluvial channel should be designed such that neither scouring nor silting
occurs. The velocity at which this condition occurs is called the critical velocity. Such an alluvial
channel is called a stable channel. Therefore, a stable channel is one in which banks and bed are
not scoured and also in which no silting occurs. Even if there is some minor scouring and silting,
the bed and banks of a stable channel remain more or less unaltered over a long period of time.
Several investigators have studied the problem and suggested various theories. These are known
as Silt theories. The most commonly used theories are:
R.G Kennedy, an executive engineer of Punjab PWD, carried out extensive investigations on
some of the canal reaches in the Upper Bari Doab canal system. He selected some straight
reaches of the canal section which had not posed any silting and scouring problems during the
previous 30 years. He considered the canal in those reaches as stable. Kennedy gave his theory,
in 1895, based on the investigations carried out on those reaches of the canal. From the
observations he concluded that the silt supporting power in a channel cross-section was mainly
dependent upon the generation of the eddies rising to the surface. These eddies are generated due
to the friction of the flowing water with the channel surface. The vertical component of these
eddies tries to move the sediment up while weight of the sediment tries to bring it down. So, if
the velocity is sufficient to generate eddies so as to keep the sediment just in suspension, silting
will be avoided based on the concept critical velocity. Eddies generated at the sides were
neglected by Kennedy because such eddies are horizontal for the greater part and therefore have
very little silt supporting power. Therefore, the eddies generated only at the bed of the channel
BY HABTAMU M. 15
IRRIGATION STRUCTURES HANDOUT
are effective for transportation of the silt. Thus, the silt supporting power is proportional to the
bed width (and not the wetted perimeter). Kennedy therefore, selected the relevant parameter as
the depth of flow D (and not the hydraulic radius R) for the critical velocity.
of flow which will just keep the channel free from silting or scouring.
0.64
V O =0.55 D
Later he recognized that the grade (or size) of silt played an important role in the silt-carrying
capacity of the channel and introduced another factor, called the critical velocity ratio (m). the
m = critical velocity ratio = 1.1 to 1.2 for coarse sand= 0.8 to 0.9 for fine sand
BY HABTAMU M. 16
IRRIGATION STRUCTURES HANDOUT
Generally, discharge Q, Manning’s coefficient N and the C.V.R (m) are given or assumed. Still
there are 4 unknowns, namely A, V, R and S. Since there are only 3 equations and 4 unknowns,
the complete solution is not possible. To obtain the complete solution, either bed slope or B/D
ratio is assumed.
Design Procedure:
Given: Q, m, N and S.
Steps:
Compute the wetted perimeter for the assumed depth and computed bed width.
P=B+2 D √ 1+ m2
V =[
1
N
+ 23+ (
0.00155
S ) ] √ RS
(
1+ 23+
S )
0.00155 N
√R
If the velocity computed now is same as found by Kennedy’s method, the design depth is correct.
Otherwise, repeat the above steps by assuming different depth of flow. If the Velocity from
BY HABTAMU M. 17
IRRIGATION STRUCTURES HANDOUT
Kennedy’s equation is less than that from Kutter’s equation, a greater value of D is assumed for
the next trial and vice versa.
BY HABTAMU M. 18
IRRIGATION STRUCTURES HANDOUT
Lacey, an eminent engineer of U.P irrigation department carried out extensive investigations
on the design of stable channel in alluviums. On the basis of his research work he found many
drawbacks in Kennedy’s theory and he put forward his new theory .He differentiated between
three
regime conditions:
True regime: A channel will be in true regime if these conditions are satisfied:
1. Discharge is constant
2. Flow is uniform
3. Silt charge is constant
4. Silt grade is constant
Initial regime: It is the first stage of regime attained by an artificial channel. The channel when
excavated has somewhat a smaller width and a flatter slope. As the channel comes in operation
and flow takes place, the bed slope of the channel is increased due to deposition of silt on the bed
of the channel when the channel throws down its incoherent silt on the bed. It increases the
velocity of flow in the channel which allows the given discharge to flow through the channel of
the smaller width. With an increase of bed slope, the depth of channel may also change.
However, the width of the channel does not change because the sides of the channel are usually
cohesive and they resist erosion. If the soil in banks is clay, the sides may resist erosion almost
indefinitely.
The channel in an alluvial soil achieves equilibrium, called the initial regime after running for
some time. This is achieved by change in bed slope and depth when discharge, silt grade, silt
charge and width remain constant. However, this stability is only temporary because the width of
the channel has so far not been adjusted to suit the requirement of a regime channel.
Final regime: It is the ultimate regime attained by an alluvial channel when in addition to bed
slope and depth, the width of the channel has also been adjusted. After a long time, because of
BY HABTAMU M. 19
IRRIGATION STRUCTURES HANDOUT
continuous action of water, the resistance of the sides of the channel is overcome and finally gets
adjusted according to discharge and silt grade, then the channel is said to have permanent
stability called final regime.
Lacey found that the silt is kept in suspension by the vertical component of eddies, but he also
considered the eddies generated at the sides of the channel which have vertical components and
hence support the silt. Lacey, therefore, considered the hydraulic radius R as the characteristic
parameter rather than the depth of flow D considered by Kennedy.
V=
√ 2
5
fR
BY HABTAMU M. 20
IRRIGATION STRUCTURES HANDOUT
2 5
A f =140 V
2/ 3 1 /3
4. Flow equation: V =10.8 R S
Lacey’s derived equations:
Following equations are derived from the Lacey’s basic or fundamental equations as:
2 5
1. Velocity equation: A f =140 V
Multiplying both sides by V: ( AV ¿ f 2=140 V 6
2 6
Q f =140V
1 /6
Or V =(Qf ¿¿ 2/ 140) ¿
2. Wetted perimeter equation:
V=
√ 2
5
fR or V =
4 4 2 2
25
5
f R
2 5 2 140 V
Also A f =140 V or f =
A
5
4 V
Eliminating f2 from above equations: V 4 = (140 ) R
2
25 A
25
Or ¿
4
√
2
2 5V
3. Hydraulic radius equation: V = fR or R=
5 2 f
2 1/ 3
2 Qf
Also V =( )
140
2 1/ 32
Qf
( )
Solving these 5 140
R=
2 f
1/ 3
Q
Or R=0.481( )
f
1 /3
Q
Generally, this constant is taken as 0.47. Therefore, R=0.47( )
f
2/ 3 1 /3
4. Slope equation: V =10.8 R S or V 3=1260 R2 S
BY HABTAMU M. 21
IRRIGATION STRUCTURES HANDOUT
3
Also V =¿
3/ 2
2 f
Therefore, 1260 R S=¿ or S= 3/ 2 ------------(a)
4980 R
3/ 2
0.0002 f
Or S= 3/2
R
Alternative equation: V=
√ 2
5
fR
1 /6
Also V =(Qf ¿¿ 2/ 140) ¿
√ 2
5
1 /2
1 /6
fR = (Qf ¿¿ 2/140) ¿
2 1/ 6 1 /6
1 /2 5 Qf Q
Or R =( ) ( ) =( )
2f 140 8.96 f
Substituting the value of R1 /2 from equation (a):
3 /2 1 /6
f Q
=( )
4980 S 8.96 f
5/ 3
0.0002 f
S= 1/ 6
Q
Design of channels by Lacey’s equation:
Procedure:
Given: Discharge Q and silt factor .
Steps:
1 /6
Determine the velocity. V =(Qf ¿¿ 2/ 140) ¿
Calculate the area of flow. A = Q/V
Compute the wetted perimeter. P = 4.75√ Q
Knowing the area of flow and wetted perimeter, determine the depth D and width B
from the geometrical relations given below, using a side slope of 0.5:1.
A = BD + 0.5 D2 and P = B+D√ 5
5/ 3
0.0002 f
Determine the bed slope: S= 1/ 6
Q
2.2.2 Design of canal in non-alluvial soils
Non-alluvial channels are considered stable as there is no silt problem in such channels.
These channels are usually designed on the basis of the maximum permissible velocity which the
channel boundary surface can resist without scouring.
BY HABTAMU M. 22
IRRIGATION STRUCTURES HANDOUT
The side slopes of the channel excavated in clay are generally kept 1:1 in cutting and 1.5:1 in
filling. For the channels in grit, soft rock and hard rock, the safe side slopes are usually taken as
0.5:1, 0.25:1 and 0.125:1 respectively. In hard rock, the sides may even be kept vertical.
The design of non- alluvial channels is done by Chezy’s equation or Manning’s formula:
i. Chezy’s equation
V =C √ RS
where C is Chezy’s coefficient, given by
87
C=
K
1+
√R
where K is Bazin’s coefficient, which depends upon the surface of the channel.
R is hydraulic radius
S is longitudinal slope.
ii. Manning’s formula
1 2/ 3 1 /2
V= R S
N
where N is Manning’s coefficient and depends upon the type of surface.
Procedure for design: The following procedure is used for the design of a non- alluvial channel
by Manning’s formula. Similar procedure can be used for the design by Chezy’s equation.
Given: Discharge (Q), maximum permissible velocity (V), Manning’s N, Bed slope (S) and the
side slope (r: 1) are given.
Steps:
1. Determine the area of cross-section from the continuity equation
Q = AV or A = Q/V
2. Determine the hydraulic radius R from the manning’s formula.
3/ 2
1 2/ 3 1 /2 VN
V= R S or R=( 1
)
N 2
S
3. Determine the wetted perimeter from the relation, P = A/R
4. Determine the depth D and bed width B from the values of A and P by solving the equations
given below
(B +r D) D = A
B + (2√ 1+r 2)D =P
BY HABTAMU M. 23
IRRIGATION STRUCTURES HANDOUT
Compacted earth linings are preferred for the canals when the earth is available near the site of
construction or In-situ. If the earth is not available near the site then it becomes costlier to
construct compacted earth lining.
BY HABTAMU M. 24
IRRIGATION STRUCTURES HANDOUT
Soil-cement linings are constructed with mixtures of sandy soil, cement and water, which harden
to a concrete-like material. The cement content should be minimum 2- 8% of the soil by volume.
However, larger cement contents are also used. In general, for the construction of soil- cement
linings following
Dry-mix method
Plastic mix method
BY HABTAMU M. 25
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 26
IRRIGATION STRUCTURES HANDOUT
Boulder Lining
This type of lining is constructed with dressed stone blocks laid in mortar. Properly dressed
stones are not available in nature. Irregular stone blocks are dressed and chipped off as per
requirement. When roughly dressed stones are used for lining, the surface is rendered rough
which may put lot of resistance to flow. Technically the coefficient of rugosity will be higher.
Thus, the stone lining is limited to the situation where loss of head is not an important
consideration and where stones are available at moderate cost.
BY HABTAMU M. 27
IRRIGATION STRUCTURES HANDOUT
Due to the presence of water at or near the land surface, evaporation takes place continuously.
Because of evaporation, there is a continuous upward flow of water from the water table if it is
high because of the capillary action. Water brings salts with it and when the water evaporates,
these salts get accumulated on the surface. These salts affect the fertility of the soil, and the soil
may become alkaline. Waterlogging can be prevented to a large extent by providing an effective
drainage system.
1. Over-Irrigation: The main cause of waterlogging is over-irrigation of the land. The excess
BY HABTAMU M. 28
IRRIGATION STRUCTURES HANDOUT
water applied to the land percolates deep into the ground and joins the water table. As the ground
water storage is augmented, the water table rises. As soon as the water table comes close to the
2. Inadequate surface drainage: Waterlogging usually occurs when there is inadequate surface
drainage of the irrigated land. Heavy precipitation along with inadequate surface drainage causes
flooding of the land. The prolonged flooding (or inundation) results in heavy percolation of
water into the ground, which causes a rise of the water table and hence waterlogging.
3. Obstruction of natural surface drainage: If a natural drainage (stream) near the irrigated
area is obstructed by constructing an embankment for a road, canal, etc., the flooding of the area
land surface at a relatively low depth, it prevents natural downward movement of water into the
subsoil which may result in the formation of perched water table that can cause waterlogging.
6. Impervious top layer: If the top layer of the land is impervious, it obstructs the flow in the
7. Seepage from canals: Water Seeps from the bed and sides of an unlined canal. It adds to the
ground water reservoir and there is a general rise in the water table, which may lead to
waterlogging.
increase in the water level on the upstream of the dam. Consequently, there is an increase in the
inflow to the groundwater storage and a decrease in the outflow from the groundwater as base
BY HABTAMU M. 29
IRRIGATION STRUCTURES HANDOUT
9. Defective methods of cultivation: If the defective methods of cultivation are used, there may
be ponding up of water on the land surface which may cause waterlogging. The defective
methods of cultivation include construction of high levees (bunds) which obstruct the natural
drainage, inadequate preparation of land, failure to smoothen the field after tillage, improper
disposal of spoil earth, improper selection or crops and growing crop which require excessive
watering.
10. Defective irrigation practice: Waterlogging may also occur due to detective irrigation
practice, such as adopting high intensity of irrigation, applying high depth of water and using
2. Difficulty in cultivation: For optimum results in crop production, the land has to be prepared.
The preparation of land in wet condition is difficult and expensive. As a result, cultivation may
upward capillary flow of water to the land surface where water gets evaporated. The upward
moving water brings with it soluble salts from the salty soil layers well below the surface. These
soluble salts carried by the upward moving water are left behind in the root zone when this water
evaporates. The accumulation of these salts in the root zone of the soil may affect the crop yield
considerably.
4. Weed growth: There are certain types of plants and grasses which grow rapidly in marshy
lands. In waterlogged lands, these plants compete with the desired useful crop. Thus, the yield of
the desired useful crop is adversely affected.
BY HABTAMU M. 30
IRRIGATION STRUCTURES HANDOUT
5. Increase in plant diseases: Because of waterlogging, various diseases occur in the plants,
which decrease their growth.
6. Lowering of soil temperature: The presence of excessive moisture content lowers the
temperature of the soil. In low temperature the bacteriological activities are retarded which
affects the crop growth badly.
7. Increase in incidence of malaria: The waterlogged land becomes a breeding place for
mosquitoes which may cause malaria. Moreover, the climate becomes damp which may affect
3. Lining the canal section: When the canal section is made fairly watertight by providing
4. By lowering the FSL of the canal: Loss may be due to percolation or absorption but when
FSL is lowered the loss is reduced to sufficient extent. The canal should be designed such that its
FSL is as low as possible, consistent with the requirements of flow irrigation for the commanded
area.
5. Improving the natural drainage of the area: Improving the natural drainage involves
removing obstruction to the flow such as weeds, bushes and other vegetations from the stream
BY HABTAMU M. 31
IRRIGATION STRUCTURES HANDOUT
section. Straightening of the streams and canalizing them into shallow wide reaches improves the
natural drainage. Increasing the bed slopes of the streams also improves the drainage. The
chances of waterlogging are considerably reduced if the natural drainage of the area is good.
6. Provision of intercepting drains: These are generally constructed parallel to the canal. The
water seeping from the unlined canal can be intercepted by providing intercepting. They give
exceptionally good results for the reach where the canal runs in high embankments.
7. Increasing outflow from the groundwater reservoir: If the well irrigation is adopted in the
area, the water table goes down and the chances of waterlogging are considerably less. In fact, a
judicious combination of the canal irrigation and the well irrigation in the same area is an ideal
solution for the waterlogging problems.
8. Changing the crop pattern: In regions susceptible to waterlogging, the crop pattern should
be changed so that the crop requiring heavy irrigation should be avoided and those requiring
light irrigation is encouraged.
9. Prevention of seepage from reservoir: The seepage from small reservoirs can be reduced by
lining the surface of the reservoirs. Also suitably designed filters should be provided so that
seepage from the reservoirs is discharged into streams.
10. Changing the assessment method: If the water supplied to the cultivators is assessed on
area basis; the cultivators have a tendency to use excess water which causes waterlogging. By
adopting the volumetric assessment of water, the excess use of water is controlled and the
chances of waterlogging are reduced.
12. Educating the cultivators to use water economically: The cultivators should be apprised of
ill effects of waterlogging. They should be trained to use water economically and avoid wasteful
use of water.
BY HABTAMU M. 32
IRRIGATION STRUCTURES HANDOUT
3 DAMS
3.1 Introduction
Dam, structure built across a stream, a river, or an estuary to retain water. Dams are built to
provide water for human consumption, for irrigating arid and semiarid lands, or for use in
industrial processes. They are used to increase the amount of water available for generating
hydroelectric power, to reduce peak discharge of floodwater created by large storms or heavy
snowmelt, or to increase the depth of water in a river in order to improve navigation and allow
barges and ships to travel more easily. Dams can also provide a lake for recreational activities
such as swimming, boating, and fishing. Many dams are built for more than one purpose; for
example, water in a single reservoir can be used for fishing, to generate hydroelectric power, and
to support an irrigation system. Water-control structures of this type are often designated
multipurpose dams.
Auxiliary works that can help a dam function properly include spillways, movable gates, and
valves that control the release of surplus water downstream from the dam. Dams can also include
intake structures that deliver water to a power station or to canals, tunnels, or pipelines designed
to convey the water stored by the dam to far-distant places. Other auxiliary works are systems for
evacuating or flushing out silt that accumulates in the reservoir, locks for permitting the passage
of ships through or around the dam site, and fish ladders (graduated steps) and other devices to
assist fish seeking to swim past or around a dam.
BY HABTAMU M. 33
IRRIGATION STRUCTURES HANDOUT
A dam can be a central structure in a multipurpose scheme designed to conserve water resources
on a regional basis. Multipurpose dams can hold special importance in developing countries,
where a single dam may bring significant benefits related to hydroelectric power
production, agricultural development, and industrial growth. However, dams have become a
focus of environmental concern because of their impact on migrating fish and riparian
ecosystems. In addition, large reservoirs can inundate vast tracts of land that are home to many
people, and this has fostered opposition to dam projects by groups who question whether the
benefits of proposed projects are worth the costs.
In terms of engineering, dams fall into several distinct classes defined by structural type and by
building material. The decision as to which type of dam to build largely depends on the
foundation conditions in the valley, the construction materials available, the accessibility of the
site to transportation networks, and the experiences of the engineers, financiers, and promoters
responsible for the project. In modern dam engineering, the choice of materials is usually
between concrete, earth fill, and rockfill. Although in the past a number of dams were built of
jointed masonry, this practice is now largely obsolete and has been supplanted by concrete.
Concrete is used to build massive gravity dams, thin arch dams, and buttress dams. The
development of roller-compacted concrete allowed high-quality concrete to be placed with the
type of equipment originally developed to move, distribute, and consolidate earth fill. Earth fill
and rockfill dams are usually grouped together as embankment dams because they constitute
huge mounds of earth and rock that are assembled into imposing man-made embankments.
BY HABTAMU M. 34
IRRIGATION STRUCTURES HANDOUT
The Assyrians, Babylonians, and Persians built dams between 700 and 250 BCE for water supply
and irrigation. Contemporary with these was the earthen Marib Dam in the southern Arabian
Peninsula, which was more than 15 meters (50 feet) high and nearly 600 meters (1,970 feet)
long. Flanked by spillways, this dam delivered water to a system of irrigation canals for more
than 1,000 years. Remains of the Maʾrib Dam are still evident in present-day Maʾrib, Yemen.
Other dams were built in this period in Sri Lanka, India, and China.
The Romans
Despite their skill as civil engineers, the Romans’ role in the evolution of dams is not particularly
remarkable in terms of number of structures built or advances in height. Their skill lay in the
comprehensive collection and storage of water and in its transport and distribution by aqueducts.
At least two Roman dams in southwestern Spain, Proserpina and Cornalbo, are still in use, while
the reservoirs of others have filled with silt. The Proserpina Dam, 12 metres (40 feet) high,
features a masonry-faced core wall of concrete backed by earth that is strengthened by buttresses
supporting the downstream face. The Cornalbo Dam features masonry walls that form cells;
these cells are filled with stones or clay and faced with mortar. The merit of curving a dam
upstream was appreciated by at least some Roman engineers, and the forerunner of the modern
curved gravity dam was built by Byzantine engineers in 550 CE at a site near the present
Turkish-Syrian border.
In East Asia, dam construction evolved quite independently from practices in the Mediterranean
world. In 240 BCE a stone crib was built across the Jing River in the Gukou valley in China; this
structure was about 30 meters (100 feet) high and about 300 meters (1,000 feet) long. Many
earthen dams of moderate height (in some cases of great length) were built by the Sinhalese in
Sri Lanka after the 5th century BCE to form reservoirs or tanks for extensive irrigation works.
The Kalabalala Tank, which was formed by an earthen dam 24 meters (79 feet) high and nearly 6
km (3.75 miles) in length, had a perimeter of 60 km (37 miles) and helped store monsoon rainfall
for irrigating the country around the ancient capital of Anuradhapura. Many of these tanks in Sri
Lanka are still in use today.
BY HABTAMU M. 35
IRRIGATION STRUCTURES HANDOUT
In Japan the Diamonike Dam reached a height of 32 metres (105 feet) in 1128 CE. Numerous
dams were also constructed in India and Pakistan. In India a design employing hewn stone to
face the steeply sloping sides of earthen dams evolved, reaching a climax in the 16-km- (10-
mile-) long Veeranam Dam in Tamil Nadu, built from 1011 to 1037 CE.
In Persia (modern-day Iran) the Kebar Dam and the Kurit Dam represented the world’s first
large-scale thin-arch dams. The Kebar and Kurit dams were built early in the 14th century by Il-
Khanid Mongols; the Kebar Dam reached a height of 26 meters (85 feet), and the Kurit Dam,
after successive heightenings over the centuries, extended 64 meters (210 feet) above its
foundation. Remarkably, the Kurit Dam stood as the world’s tallest dam until the beginning of
the 20th century. By the end of the 20th century, its reservoir had almost completely silted in,
causing floodwaters to regularly overtop the dam and cause serious erosion. A new, larger dam
was built just above the old one in order to create a new reservoir and redirect floodwaters away
from the ancient structure.
In the 15th and 16th centuries, dam construction resumed in Italy and, on a larger scale, in Spain,
where Roman and Moorish influence was still felt. In particular, the Tibi Dam across the
Monnegre River in Spain, a curved gravity structure 42 metres (138 feet) high, was not surpassed
in height in western Europe until the building of the Gouffre d’Enfer Dam in France almost three
centuries later. Also in Spain, the 23-metre- (75-foot-) high Elche Dam, which was built in the
early 17th century for irrigation use, was an innovative thin-arch masonry structure. In the
British Isles and northern Europe, where rainfall is ample and well distributed throughout the
year, dam construction before the Industrial Revolution proceeded on only a modest scale in
terms of height. Dams were generally limited to forming water reservoirs for towns, powering
water mills, and supplying water for navigation canals. Probably the most remarkable of these
structures was the 35-metre- (115-foot-) high earthen dam built in 1675 at Saint-Ferréol, near
Toulouse, France. This dam provided water for the Midi Canal, and for more than 150 years it
was the highest earthen dam in the world.
BY HABTAMU M. 36
IRRIGATION STRUCTURES HANDOUT
(a) Storage (or impounding) dam is constructed across a river to create a reservoir for storing
water during the period when the flow in the river is in excess. This stored water is then used for
irrigation, power generation and water supply when the demand exceeds the flow in the river.
(b) Detention dam is primarily constructed to detain all or part of the flood waters of a river and
released later in such a way that the region downstream of the dam is safe against flood damages.
A dam can also serve both the functions of detention as well as storage.
(c) Diversion dam is constructed for the purpose of diverting water into a canal. Such a dam is
usually called diversion weir.
(d) Coffer dam is a temporary dam constructed to keep water away from a specific area to keep
it dry for some specific purpose, such as construction of the main dam. The coffer dam too acts
like diversion dam.
(e) Debris dam is constructed across a river to trap sediments of the river.
(a) Earth and rock fill dams are constructed of loose earth (ranging from fine material to big
rock pieces) without any binding material. An earth dam having its major portion built of rocks
is called rock fill dam. Such dams are also known as non-rigid dams.
(b) Masonry dams are rigid dams constructed of either stone or brick masonry.
BY HABTAMU M. 37
IRRIGATION STRUCTURES HANDOUT
The difference between an earth and rock fill dam is that in case of rock fill dam major portion of
the dam is primarily made of rock pieces, whereas in case of the earth dam it is the soil which is
used for the construction of embankment.
Conditions favoring selection of earth and rock fill dams are as follows:
(i) Significant thickness of soil deposits overlying bedrock.
(ii) Weak or soft bedrock which would not be able to resist high stresses from a concrete dam.
(iii) Abutments of either deep soil deposits or weak rock.
(iv) Availability of a suitable location for a spillway.
(v) Availability of sufficient and suitable soils from required excavation or nearby borrow areas.
Earth dams are further divided into the following types:
(i) Homogeneous earth dam
(ii) Zoned earth dam
(iii) Diaphragm
Homogeneous earth dams are constructed entirely or almost entirely of one type of earth
material. A zoned earth dam, however, contains materials of different kinds in different parts of
the embankment. Homogeneous earth dam is usually built when only one type of material is
economically available, and/or the height of the dam is not very large.
A homogeneous earth dam of height exceeding about 6 to 8 m should always have some type of
drain [Fig. 3.1] constructed of material more pervious than the embankment soil. Such drains
reduce pore pressures in the downstream portion of the dam and, thus, increase the stability of
the downstream slope.
Besides, the drains control the outgoing seepage water in such a manner that it does not carry
away embankment soil i.e., piping does not develop. Such a dam is also categorized as
homogeneous (sometimes ‘modified homogeneous’) dam [Fig. 3.1).
BY HABTAMU M. 38
IRRIGATION STRUCTURES HANDOUT
The most common type of an earth dam usually adopted is the zoned earth dam as it leads to an
economic and more stable design of the dam. In a zoned earth dam [Fig. 3.2], there is a central
impervious core which is flanked by zones of more pervious material. The pervious zones, also
known as shells, enclose, support and protect the impervious core.
BY HABTAMU M. 39
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 40
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 41
IRRIGATION STRUCTURES HANDOUT
of masonry or concrete. However, concrete gravity dams are preferred these days and mostly
constructed. They can be constructed with ease on any dam site, where there exists a natural
foundation strong enough to bear the enormous weight of the dam. Such a dam is generally
straight in plan, although sometimes, it may be slightly curve. The line of the upstream face of
the dam, or the line of the crown of the dam if the upstream face in sloping, is taken as the
reference line for layout purposes, etc. and is known as the Base line of the dam or the 'Axis. of
the Dam'. When suitable conditions are available, such dam’s can be constructed up to great
heights. The highest gravity .dam in the world is Grand Dixence Dan:i in Switzerland (284m),
followed by ·Bhakra dam in India (226 m); both are of concrete gravity type. The ratio of base
width to height of all these structures is less than 1 : 1.
BY HABTAMU M. 42
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 43
IRRIGATION STRUCTURES HANDOUT
The following are the important factors which affect the choice of the type of dam:
(i) Topography
The topography of the site dictates the first choice of the type of dam. A Concreter dam
would be the obvious choice for a narrow stream flowing between high and rocky abutments
(i.e., deep gorges). Broad valleys in plains would suggest an embankment dam with a
separate spillway.
Geological and hydro-geological characteristics of the strata, which are to carry the weight of
the dam, determine the foundation conditions. Any type of dam can be constructed on solid
rock foundations. Well-compacted gravel foundations are suitable for concrete gravity dams
of small height, earth-fill and rock-fill dams.
However, effective water cutoffs are required to check the foundation seepage. Silt or fine
sand foundations can be used to support concrete dams of small height and earth-fill dams.
Problems of settlement, piping and the foundation seepage are associated with this type of
BY HABTAMU M. 44
IRRIGATION STRUCTURES HANDOUT
foundation. Non-uniform foundations containing different types of strata will usually require
special treatment before any type of dam is constructed on such foundation.
If the construction materials which are to be used in large quantity for the construction of
dam are available in sufficient quantity within a reasonable distance from the site, the cost of
the dam will be considerably reduced due to saving on transportation of the construction
materials.
If suitable soils for the construction of an earth-fill dam are locally available in nearby
borrow pits, choice of an earth-fill dam would be the most economical. The availability of
sand and gravel (for concrete) near the dam site would reduce the cost of a concrete dam.
Spillway is a major part of any dam and its size and type and the natural restrictions in its
location will affect the selection of the type of dam. Spillway requirements are decided by the
runoff and stream-flow characteristics.
As such, spillway on dams across streams of large flood potential can become the dominant
part of the dam and put the selection of the type of dam to a seconder position. For large
spillways, it may be desirable to combine the spillway and dam into one structure.
This is possible only in concrete dams. Earth and rockfill dams are based on more
conservative design assumptions and, hence, spillway is generally not constructed as part of
the embankment. On the other hand, excavated material from separate spillway can be
advantageously used for the construction of an embankment dam.
Nevertheless, there are some guidelines which must be followed while selecting a suitable
site for any type of dam:
(i) Availability of suitable foundation: While an earth dam can be designed for and
constructed on any type of foundation, concrete dams require relatively stronger foundation.
Foundations can be improved to some extent by taking suitable steps for foundation
treatment.
BY HABTAMU M. 45
IRRIGATION STRUCTURES HANDOUT
(ii) Considerable economy will be achieved if the dam is sited at the narrowest section in
the river valley subject to fulfillment of other requirements.
(v) The area upstream of the dam must be suitable for the requirements of a reservoir.
(vi) The environmental considerations, including displacement of local people, require that
there is minimum damage to the local environment, and minimum hardship to the local
people. At times, these become governing factors in selecting the site of a dam.
(vii) The selected site should be such that it results in overall economy in construction,
maintenance and operation of the water resource project.
BY HABTAMU M. 46
IRRIGATION STRUCTURES HANDOUT
4.1 Introduction
Any hydraulic structure which supplies water to the off-taking canal is called a headwork, or the
works which are constructed at the head of the canal, in order to divert the river water towards
the canal, so as to ensure a regulated continuous supply of silt-free water with a certain minimum
head into the canal, are known as diversion head works.
(i) It raises the water level in the river so t It raises the water level in the river so that the
hat the commanded area is increased commanded area is increased
(ii) It regulates the supply of water into the canal
(iii) It provides storage of water for a It provides storage of water for a short period short
period
(iv) It controls the entry of silt into the canal
(v) It reduces the fluctuations in the level of supply in the river.
BY HABTAMU M. 47
IRRIGATION STRUCTURES HANDOUT
Weirs are with or without gates, whereas barrages are always gate controlled.
4.3.1.2 Weirs
BY HABTAMU M. 48
IRRIGATION STRUCTURES HANDOUT
Weirs may be classified according to the material of construction and certain design features
as
- A masonry weir wall (with both upstream and downstream faces vertical; or both faces
- Block protection at upstream end of floor, and a graded inverted filter at the downstream
end of floor
- Launching aprons or pervious aprons (or floors) after block protection and inverted filters.
of:
- Dry packed boulders laid in the form of glacis or sloping aprons in the upstream and
BY HABTAMU M. 49
IRRIGATION STRUCTURES HANDOUT
The downstream slope is generally made very flat. It requires a very large quantity of stone.
It also has few intervening core walls.
The crest level is kept at a low level and the raising up of water level (or ponding) is
accomplished mainly by means of gates. During floods these gates can be raised clear off the
high flood level and thus enable the high flood to pass with minimum of afflux (or heading
up
BY HABTAMU M. 50
IRRIGATION STRUCTURES HANDOUT
of water on the upstream side). A barrage provides better control on the water level in the
river
but it is comparatively more costly. The design of a barrage involves the same procedure as a
concrete weir.
Figure 4. 5 Barrage
4.3.1.3 Divide wall
It is masonry or concrete wall with top width of 1.5 to 3m constructed at right angles to the
axis of the weir and separates the ‘weir proper’ from under sluices. The divide wall extends
on the upstream side beyond the beginning of the canal head regulator and on the
downstream side, it extends up to the end of downstream protection of the under sluices.
a) To separate the floor of the under sluices which is at lower level from the weir proper
b) To help in providing a comparatively less turbulent pocket near the canal head
regulator resulting in deposition of silt in this pocket and, thus, to help entry of silt free water
into the canal
c) To isolate the pocket upstream of the canal head regulator and facilitate scouring
operation;
BY HABTAMU M. 51
IRRIGATION STRUCTURES HANDOUT
dissipated in such a manner as to provide smooth flow at sufficiently low velocity, not
The various types of fish ladder are (i) pool type, (ii) steep channel type, (iii) fish lock type
and (iv) fish lift or elevator type. Types (iii) and (iv) are suitable for high dams only. Types (i)
and (ii) are generally provided for barrages.
Functions of Undersluices:
(i) They preserve a clear and well-defined river channel towards the canal head regulator;
BY HABTAMU M. 52
IRRIGATION STRUCTURES HANDOUT
(ii) They scour the silt deposited on the river bed in the pocket upstream of the canal head
regulator;
(iii)They pass low floods without the necessity of dropping the weir crest shutters;
(iv)They help to lower the high flood level by supplementing the discharge over the weir
Capacity of Undersluices:
(i) To ensure proper scouring, its capacity should be at least two times the maximum
(ii) It should have sufficient capacity to discharge maximum winter flood – without the
(iii) 10 to 20% of the maximum flood discharge – to supplement the discharge over the
The head regulator is generally aligned at right angle to the weir, but slightly larger angles
(between 900 and 1100) are now considered preferable for providing smooth entry of water
into the regulator. The regulation is done by means of gates.
The design principles are the same as those used in the design of barrages, except that the
regulators are a smaller version of barrages. An important consideration in designing the
regulator is silt exclusion from canals. Silt-excluder tunnels are often provided in the barrage
BY HABTAMU M. 53
IRRIGATION STRUCTURES HANDOUT
bays adjacent to the regulator, so that the heavier silt-laden bottom layers of water bypass
through the tunnels (Figure 4.7).
regulator (sill level) and the pond level. During high floods, the water level in the river will
be
much higher than the pond level. To avoid spilling of this water over the gates, a R.C. wall,
called Breast wall, is provided from pond level up-to river HFL. This wall rests over the piers
of the regulator bays.
The entry of silt into the canal is controlled by keeping the crest of the head regulator by
about
BY HABTAMU M. 54
IRRIGATION STRUCTURES HANDOUT
loose apron. In the immediate vicinity of the floor, a certain portion of the loose apron is
made
non-launching. The non-launching apron prevents the scour hole travel close to the floor or
sheet pile line; whereas launching apron is designed to launch along the slope of the scour
hole
i) By piping or undermining: If the water percolating through the foundation has sufficient
force when it emerges at the downstream end of the impervious floor it may lift up the soil
particles at the end of the floor. With the removal of the surface soil there is further
concentration of flow into the resulting depression and more soil is removed which
progressively result in subsidence of the floor in the hollows so formed.
(a) Provide sufficient length of the impervious floor (so that the path of percolation is
(b) Provide piles at upstream and downstream ends of the impervious floor
BY HABTAMU M. 55
IRRIGATION STRUCTURES HANDOUT
(ii) By uplift pressure: If the uplift pressure is not counterbalanced by the weight of the floor,
it may fail by rupture.
(b) Provide pile at the upstream end of the impervious floor so that uplift pressure is
(i) By suction due to standing wave or hydraulic jump: The standing wave or hydraulic
jump developed on the downstream side of the weir causes suction or negative pressure which
also acts in the direction of uplift pressure. If the floor thickness is insufficient it may fail by
rupture in suction.
(a) Providing additional thickness of the impervious floor to counterbalance the suction
masonry.
(ii) By scour on the upstream and downstream of the weir: Upstream and downstream
ends of the impervious floor and bed of the river may be scoured during floods. If not
Preventive measures which should be taken against failure due to scour are:
(a) Providing deep piles both at upstream and downstream ends of the impervious floor.
The piles should be driven much below the calculated scour depth.
(b) Providing launching aprons of suitable length and thickness at upstream and
BY HABTAMU M. 56
IRRIGATION STRUCTURES HANDOUT
i) Hydraulic design
ii) Structural design
The hydraulic design deals with the evaluation of the hydraulic forces acting on the structure and
the determination of the configurations of the structure which will be most economical and will
have the best functional efficiency.
The structural design consists of dimensioning the various parts of the structure to enable it to
resist safely all the forces acting on it.
The hydraulic design is treated in respect of both subsurface and surface flows. The various
aspects of design in respect of subsurface flow involves determination of;
-Uplift pressure,
-Exit gradient,
-Depth of sheet piles or cutoffs at upstream and downstream ends of the impervious
floor;
-Protection works.
On the other hand, the design in respect of surface flow involves determination of;
-Pond level;
-Afflux;
-Waterway;
-Effect of retrogression.
BY HABTAMU M. 57
IRRIGATION STRUCTURES HANDOUT
Pond level: Pond level, in the under-sluice pocket, u/s of the canal head regulator may be
obtained by adding the working head to the designed full supply level in the canal. The working
head should include the head required for passing the design discharge into the canal and the
head loss in the regulator.
Afflux: It is the rise in water level on the u/s of a weir or barrage as a result of its construction.
The value of afflux corresponding to the design flood is important for the design of the length
The u/s floor level of a weir or a barrage bays (other than under sluice bays) is fixed at the
general river bed level, at or below the level of the crest of the weir or barrage. Usually the
floor level is kept at 0.5 to 1.0 m higher than the u/s floor level of the under-sluice bays.
(i)For weirs without shutters, the crest level should be at the required pond level;
(ii) For weirs with shutters, the crest level should not be lower than 2 m below the pond
(iii) For barrages, the crest level is determined by the depth required to pass the design flood at
the desired afflux. The level of crest in this case should be fixed by adjustment of the waterway.
It should in any case be under sluice crest level. adjustment of the waterway.
A vertical drop weir is usually trapezoidal in cross section and its dimensions may be obtained on
the basis of stability considerations;
-A glacis type weir is provided with a top width of about 2.0 m, and u/s slope of 2:1 to 3:1
depending on site conditions and d/s slope as required for the glacis of stilling basin.
Waterway: The length of waterway which is equal to the length of the weir or barrage is fixed to
pass safely the maximum flood discharge. The length of the waterway should be equal to the
BY HABTAMU M. 58
IRRIGATION STRUCTURES HANDOUT
stable river width for the maximum flood discharge so that shoaling upstream is mostly
eliminated and a nearly straight and stable approach to the weir or barrage is obtained.
The clear waterway to be provided between guide banks or abutments, excluding thickness of
piers, is usually taken equal to the Lacey’s regime perimeter given by
P=4.75 √ Q
Where,
To account for the silt load carried by the alluvial rivers, the clear waterway of 1.1 to 1.25 times
Lacey’s regime perimeter is provided.
BY HABTAMU M. 59
IRRIGATION STRUCTURES HANDOUT
L = d1+ d1+ L1+ d3+ d3+ L2+ d2+ d2= (L1+ L2) + 2d1+ 2d2+ 2d3
The hydraulic gradient or the loss of head per unit length of creep is,
H H H
= =
L b +2 d 1+2 d 2+ 2 d 3 [b+2 ( d 1+d 2+ d 3 ) ]
Therefore, for any point the head loss is proportional to the creep length. As the hydraulic
gradient is constant, if L1is the creep length up to any point, then head loss up to this point will
be (H/L) L1and the residual head at this point will be (H - (H/L) L1).).
The reciprocal of the hydraulic gradient, i.e., L/H is known as Bligh’s coefficient of creep, C.
According to Bligh, the safety against piping can be ensured by providing sufficient creep length,
given by L = C.H, where C is the Bligh’s Coefficient for the soil. Bligh recommended certain
BY HABTAMU M. 60
IRRIGATION STRUCTURES HANDOUT
H 1
values of C for different soils. According to Bligh if the hydraulic gradient ≤ (for the soil)
L C
there is no danger of piping.
Table 4.1 Recommended values of Bligh coefficient of creep C and safe hydraulic gradient
ρm(for concrete, ρm = 2400 kg/m3). Downward force per unit area due to the weight of
the floor is
W= ρmgt
ρmgt = ρgh'
' ρm
h= t = Smt
ρ
BY HABTAMU M. 61
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 62
IRRIGATION STRUCTURES HANDOUT
is always required to be provided on the downstream side from the consideration of surface flow
to resist the action of fast flowing water whenever it is passed to the downstream side of t1.
BY HABTAMU M. 63
IRRIGATION STRUCTURES HANDOUT
(v) The assumption, loss of head is proportional to creep length is not true and actual
uplift
pressure distribution is not linear, but it follows a sine curve.
(vi)Bligh did not specify the absolute necessity of providing a cutoff at the downstream
end
of the floor, whereas it is absolutely essential to provide a deep vertical cutoff at the
downstream end of the floor to prevent undermining.
1
Lw = N +V
3
Where
N = sum of all the horizontal contacts and all the sloping contacts less than 450to the
horizontal.
V = sum of all the vertical contacts and all sloping contacts greater than 45 0to the horizontal.
Where H = Total seepage head (difference in in water head between upstream and
downstream)
Table 4.2. Recommended values of Lane’s coefficient of creep C1and safe hydraulic
Gradient.
BY HABTAMU M. 64
IRRIGATION STRUCTURES HANDOUT
( C1 )
1
Lane’s method for determination of the uplift pressure is criticized on the grounds that it is an
empirical method and not based on any mathematical approach. However, because of the of the
method it is also widely used.
a) The seepage water does not creep along the bottom contour of pucca-floor as stated by Bligh,
but moves along a set of streamlines. This steady seepage in a vertical plane for a homogeneous
soil can be expressed by Laplacian equation:
2 2
d φ d φ
2
= 2
d x dz
The above equation represents two sets of curves intersecting each other orthogonally. The
resultant flow diagram showing both of the curves is called a Flow Net. The streamlines
represent the paths along which the water flows through the sub-soil. Every particle entering the
soil at a given point upstream of the work will trace out its own path and will represent a
streamline. The first streamline follows the bottom contour of the works and is the same as
Bligh’s path of creep. The remaining streamlines follows smooth curves transiting slowly from
the outline of the foundation to a semi-ellipse, as shown in Figure 4.11.
BY HABTAMU M. 65
IRRIGATION STRUCTURES HANDOUT
b) The seepage water exerts a force at each point in the direction of flow and tangential to the
streamlines. This force (F) has an upward component from the point where the streamlines turn
upward. For soil grains to remain stable, the upward component of this force should be
counterbalanced by the submerged weight of the soil grain. This force has the maximum
disturbing tendency at the exit end, because the direction of this force at the exit point is
vertically upward, and hence full force acts as its upward component. For the soil grain to remain
stable, the submerged weight of soil grain should be more than this upward disturbing force. The
disturbing force at any point is proportional to the gradient of pressure of water at that point. This
gradient of pressure of water at the exit end is called the exit gradient. In order that the soil
particles at exit remain stable, the upward pressure at exit should be safe. In other words, the exit
BY HABTAMU M. 66
IRRIGATION STRUCTURES HANDOUT
gradient should be safe. This exit gradient is said to be critical, when the upward disturbing force
on the grain is just equal to the submerged weight of the grain at the exit. When a factor of safety
equal to 4 to 5 is used, the exit gradient can then be taken as safe. In other words, an exit gradient
equal to ¼ to 1/5 of the critical exit gradient is ensured, so as to keep the structure safe against
piping.
In this method, a complex profile like that of a weir is broken into a number of simple profiles;
each of which can be solved mathematically. Mathematical solutions of flow nets for these
simple standard profiles have been presented in the form of equations and curves (given in
Figure 4.18 (a), (b) and (c)), which can be used for determining the percentage pressures at the
various key points. The simple standard profiles used are:
(a) A straight horizontal floor of negligible thickness with a sheet pile at either end, i.e. at
(b) A straight horizontal floor depressed below the bed but with no vertical cut-offs.
BY HABTAMU M. 67
IRRIGATION STRUCTURES HANDOUT
(c) A straight horizontal floor of negligible thickness with a sheet pile line at some
intermediate position.
In general, the usual weir section consists of a combination of all or some of the three forms
mentioned above. Each elementary form is treated as independent of the others. The pressures as
a percentage of the water head are read from Khosla’s curves at the key points. The key points
are the junction of the floor and the pile or cut-off walls, the bottom points of the pile or walls,
and the bottom corners in the case of depressed floor. The percentage pressure observed from the
curves for the simple form into which the profile has been broken up, is valid for the profile as a
whole if corrected for:
BY HABTAMU M. 68
IRRIGATION STRUCTURES HANDOUT
C=19
√ (
D d+D
b' b )
Where b’= the distance between two pile lines
D= the depth of pile line, the influence of which has to be determined on the neighboring pile of
depth d. D is to be measured below the level at which interference is desired.
The correction is positive for points in the rear or backwater and subtractive for points forward in
the direction of flow. This equation does not apply to the effect of an outer pile on an
intermediate pile, if the intermediate pile is equal to or smaller than the outer pile and is at a
distance less than twice the length of the outer pile.
In the standard forms with cutoffs, the thickness of the floor is assumed to be negligible. Thus, as
observed from Khosla’s curves, the percentage pressures at the junction points E and C pertain to
the level at the top of the floor whereas the actual junction is with the bottom of the floor.
The percentage pressures at the actual points E and C are interpolated by assuming a straight-line
pressure variation from the hypothetical point E to D and also from D to C.
BY HABTAMU M. 69
IRRIGATION STRUCTURES HANDOUT
For pile no. 1, since the corrected pressure at E 1should be less than the calculated pressure at E,
the correction to be applied for the joint E 1shall be negative. Similarly, the pressure calculated at
C is less than the corrected pressure at C 1, and hence, the correction to be applied at point C 1is
positive.
A correction is applied for a sloping floor, and is taken as positive for the down and negative for
the up slopes following the direction of flow.
BY HABTAMU M. 70
IRRIGATION STRUCTURES HANDOUT
The correction given above is to be multiplied by the horizontal length of the slope and divided
by the distance between the two pile lines between which the sloping floor is located. This
correction is applicable only to the key points of the pile line fixed at the beginning or the ends
of the slope.
For standard form consisting of a floor length b with a vertical cutoff of depth d, the exit gradient
at its d end is given by:
H 1
G E=
d π√λ
1+ √ 1+ α 2
Where λ= , and
2
b
α=
d
The exit gradient so calculated must lie within safe limits as given in the following table (Table
4.4).
BY HABTAMU M. 71
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 72
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 73
IRRIGATION STRUCTURES HANDOUT
The sheet pile must be taken up to the level of possible deepest scour below the bed of the river.
According to Lacey the depth of scour in alluvial soils is given by
( )
2 1 /3
q
R=1.35
f
Where,
In order to ensure further safety, for the design of sheet piles the scour depth is considered as
1.25 to 2 times R given by the above equation.
Design of protection works at the u/s and d/s ends of the impervious floor
BY HABTAMU M. 74
IRRIGATION STRUCTURES HANDOUT
In order to further safeguard the impervious floor against failure due to piping certain protection
works are provided at both the u/s and d/s ends of the impervious floor. These protection works
consist of
Inverted Filter: consists of layers of materials of increasing permeability from bottom to top.
The thickness of the inverted filter varies from 0.5 to 1.25 m. To prevent the filter material from
dislocation by surface flow they are loaded with large size stones or concrete blocks. The blocks
are usually 0.9 to1.2 m thick and are placed with open joints filled with river sand or filter
material.
It is provided immediately at the d/s end of the impervious floor to relieve the uplift pressure.
The length depends on the scour depth D below the river bed and it usually varies from 1.5 D to
2 D, where D is given by
D = XR – Y
Y = depth of the river bed or impervious floor below high flood level
Block Protection: It is provided immediately at the u/s end of the impervious floor. It consists of
0.6 to 1.0 m thick stone or concrete blocks laid on 0.4 to 0.6 m thick loosely packed stone. The
length of the block protection is usually equal to the depth of scour, D, below the river bed at the
u/s end of the impervious floor.
Launching apron or pervious apron: It is an apron of loosely packed stones. Its function is to
protect the impervious floor and the pile from the scour holes progressing towards the floor
BY HABTAMU M. 75
IRRIGATION STRUCTURES HANDOUT
and the pile. The protection is provided by a launching apron by forming a protective covering of
stones over a certain slope below the bed of the river at which the apron is originally laid to the
The size of the stones (that shall not be washed away during maximum flood) is given by USBR
( )
2
VA
as d=
4.915
Where VA= average velocity of flow in m/s and d = mean diameter of stones in m.
It is generally assumed that the stones launch at a slope of 2:1. The quantity of stone in a
launching apron should be sufficient to provide about 1.0 m thick cover over a slope of 2:1 in the
launched position. Thus, if D is the depth of scour, the length of the launched apron would be
about √ 5D=2.236D Since the thickness of the launched apron is 1 m, the quantity of stone
required is 2.236D m3per m length of the apron.
BY HABTAMU M. 76
IRRIGATION STRUCTURES HANDOUT
Figure 5. 1 Aqueduct
BY HABTAMU M. 77
IRRIGATION STRUCTURES HANDOUT
(b) Syphon aqueduct: In a syphon aqueduct also, the canal is taken over the drainage, but the
flow in the drainage is pipe flow (i.e., the drainage water flows under syphonic action and there
is no atmospheric pressure in the drainage). A syphon aqueduct is constructed when the H.F.L. of
the drainage is higher than the canal bed level. When sufficient level difference is not available
between the canal bed and the H.F.L. of the drainage to pass the drainage water, the bed of the
drainage may be depressed below its normal bed level. The drainage is provided with an
impervious floor at the crossing and thus a barrel is formed between the piers to pass the
drainage water under pressure. Syphon aqueducts are preferred than Aqueducts, though costlier.
(a) Super passage: In a super passage, the canal is taken below the drainage and the flow in the
channel is open channel flow. A super passage is thus reverse of an aqueduct. A super passage is
required when canal F.S.L is below the drainage bed level. In this case, the drainage water is
taken in a trough supported over the piers constructed on the canal bed. The water in the canal
flows under gravity and possess the atmospheric pressure.
BY HABTAMU M. 78
IRRIGATION STRUCTURES HANDOUT
A canal syphon is constructed when the F.S.L. of the canal is above the drainage bed level.
Because some loss of head invariably occurs when the canal flows through the barrel of the canal
syphon, the command of the canal is reduced. Moreover, there may be silting problem in the
barrel. As far as possible, a canal Syphon should be avoided.
BY HABTAMU M. 79
IRRIGATION STRUCTURES HANDOUT
(a) Level crossing: A level crossing is provided when the canal and the drainage are practically
at the same level. In a level crossing, the drainage water is admitted into the canal at one bank
and is taken out at the opposite bank.
A level crossing usually consists of a crest wall provided across the drainage on the upstream of
the junction with its crest level at the F.S.L. of the canal. The drainage water passes over the crest
and enters the canal whenever the water level in the drainage rises above the F.S.L. of the canal.
There is a drainage regulator on the drainage at the d/s or the junction and a cross-regulator on
the canal at the d/s of the junction for regulating the outflows.
BY HABTAMU M. 80
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 81
IRRIGATION STRUCTURES HANDOUT
After the canal has mounted the watershed, no cross-drainage work will normally be required,
because all the drainage originate from the watershed and flow away from it. However, in some
cases, it may be necessary for the canal to leave the watershed and flow away from it. In that
case, the canal intercepts the drainages which carry the water of the pocket between the canal
and the watershed and hence the cross-drainage works are required. A cross-drainage work is an
expensive structure and should be avoided as far as possible. The number of cross-drainage
works can be reduced to some extent by changing the alignment of the canal. However, it may
increase the length and hence the cost of the canal. Sometimes it is possible to reduce the number
of cross-drainage works by diverting the small drainages into large drainages or by constructing
the cross-drainages work below the confluence of two drainages by shifting the alignment.
BY HABTAMU M. 82
IRRIGATION STRUCTURES HANDOUT
However, the suitability of the site for the construction of the structure should also be considered
while deciding the location of the cross-drainage works.
BY HABTAMU M. 83
IRRIGATION STRUCTURES HANDOUT
The relative levels and discharges of the canal and of the drainage mainly affect type of cross-drainage
work required. The following are the broad outlines:
1. If the canal bed level is sufficiently above the H.F.L. of the drainage, an aqueduct is selected.
2. If the F.S.L. of the canal is sufficiently below the bed level of the drainage, a super-passage is
provided.
3. If the canal bed level is only slightly below the H.F.L. of the drainage, and the drainage is small, a
siphon aqueduct is provided. If necessary, the drainage bed is depressed below the canal.
4. If the F.S.L. of the canal is slightly above the bed level of the drainage and the canal is of small
size, a canal syphon is provided.
5. If the canal bed and the drainage bed are almost at the same level, a level crossing is provided
when the discharge in the drainage is large, and an inlet-outlet structure is provided when the
discharge in the drainage is small. However, the relative levels of the canal and the drainage can
be altered to some extent by changing the canal alignment to have another crossing. In that case,
the most suitable type of the cross-drainage work will be selected depending upon the levels at
the changed crossing.
2. Performance:
As far as possible, the structure having an open channel flow should be preferred to the
structure having a pipe flow. Therefore, an aqueduct should be preferred to a syphon aqueduct.
Likewise, a super-passage should be preferred to a canal siphon. In the case of a syphon
aqueduct and a canal syphon, silting problems usually occur at the crossing. Moreover, in the
case of a canal syphon, there is considerable loss of command due to loss of head in the canal.
The performance of inlet-outlet structures is not good and should be avoided.
3. Provision of road:
An aqueduct is better than a super-passage because in the former, a road bridge can easily be
provided along with the canal trough at a small extra cost, whereas in the latter, a separate road
bridge is required.
4. Size of drainage:
When the drainage is of small size, a syphon aqueduct will be preferred to an aqueduct as the
latter involves high banks and long approaches. However, if the drainage is of large size, an
aqueduct is preferred.
BY HABTAMU M. 84
IRRIGATION STRUCTURES HANDOUT
5. Cost of earthwork:
The type of cross-drainage work which does not involve a large quantity of earthwork of the
canal should be preferred.
6. Foundation:
The type of cross-drainage work should be selected depending upon the foundation available at
the site of work.
7. Material of construction:
Suitable types of material of construction in sufficient quantity should be available near the site
for the type of cross-drainage work selected. Moreover, the soil in sufficient quantity should be
available for constructing the canal banks if the structure requires long and high canal banks.
8. Cost of construction:
The cost of construction of cross-drainage work should not be excessive. The overall cost of the
canal banks and the cross-drainage work, including maintenance cost, should be a minimum.
Sometimes, the type of cross-drainage is selected considering the permissible loss of head. For
example, if the head loss cannot be permitted in a canal at the site of cross-drainage, a canal
syphon is ruled out.
If the subsoil water table is high, the types of cross-drainage which requires excessive
excavation should be avoided, as it would involve De-watering problems.
The canal alignment is sometimes changed to achieve a better type of cross-drainage work. By
changing the alignment, the type of cross-drainage can be altered. The canal alignment is
generally finalized after fixing the sites of the major cross-drainage works.
They may be classified into three types depending on the sides of the aqueduct:
BY HABTAMU M. 85
IRRIGATION STRUCTURES HANDOUT
Type I: In this type, the cross section of the canal is not changed. The original cross section of
the canal with normal side slopes is retained. The length of the barrel through which the drainage
passes under the canal is maximum in this type of structure because the width of the canal
section is maximum. This type is suitable when the width of the drainage is small (less than 2.5
m).
Type II. In this type, the outer slopes of the canal banks are discontinued and replaced by
retaining walls. Thus, the length of the barrel is reduced, but the cost of retaining wall is added to
the overall cost. This type is suitable when the width of the drainage is moderate (2.5 to 15m).
Type III. In this type, the entire earth section of the canal is discontinued and replaced by a
concrete or masonry trough over the drainage. This type is suitable when the width of the
drainage is very large (greater than 15 m), so that the cost of the trough and canal wing walls is
BY HABTAMU M. 86
IRRIGATION STRUCTURES HANDOUT
less in comparison to the saving resulting from decreasing the length of barrel. In this type, the
canal can be easily flumed which further reduces the length of the barrel.
Selection of the Suitable Type: The selection of a particular type out of three types of aqueducts
or syphon-aqueducts lies on the considerations of economy. The cheapest of the three types at a
particular place shall be the obvious choice. In fact, in all cases, the cost of abutments and wing
walls is independent of the length of the culvert along the canal. In type 1, no canal wings are
required since the canal section is not at all changed. However, in this type, the width of the
aqueduct is the largest. Type I will, therefore, prove economical only where the length of the
aqueduct is small and where the cost of bank connections would be large in comparison to the
savings obtained from the reduction in the width of the aqueduct. In type III, the width of the
aqueduct is minimum but the cost of bank connections is maximum. This type is, therefore,
suitable where the length of the aqueduct is very large and where the cost of bank connections
would be small in comparison to the savings obtained from the reduction in the width of the
aqueduct.
On the basis of above discussion, it can be concluded that the choice of a particular type depends
mainly upon the length of the aqueduct (i.e., the width of the drainage) in relation to the size of
the canal. The exact choice of a particular type in particular case can be made by working out the
cost of all the types and then choosing the cheapest.
BY HABTAMU M. 87
IRRIGATION STRUCTURES HANDOUT
The following steps may be involved in the design of an aqueduct or a syphon-aqueduct. The
design of a super passage and a syphon is done on the same lines as for aqueducts and syphon
aqueducts, respectively, since hydraulically there is no much difference between them, except
that the canal and the drainage are interchanged by each other.
The high flood discharge for smaller drains may be worked out by using empirical formulas; and
for large drains, other reliable methods Such as Hydrograph analysis, Rational formula, etc. may
be used.
An approximate value of required waterway for the drain may be obtained by using the Lacey's
equation, given by
P=4.75 √ Q
where P is the wetted perimeter in meters and Q is the Total discharge in cumecs. For wide
drains, the wetted perimeter may be approximately taken equal to the width of the drain and
hence, equal to waterway required. For smaller drains, a smaller figure for the waterway than
that given by Lacey s regime perimeter, may be chosen. The maximum permissible reduction in
waterway from Lacey’s perimeter is 20%. Hence, for smaller drains, the width of the waterway
provided should be so adjusted as to provide this required perimeter (minimum value =0.8 P).
The decided clear water way width is provided in suitable number of bays (spans).
The velocity through syphon barrels is limited to a scouring value of about 2 to 3 m/sec. A higher
velocity may cause quick abrasion of the barrel surfaces by rolling grit, etc. and shall definitely
result in higher amount of afflux on the upstream side of the syphon or syphon aqueduct, and
thus, requiring higher and longer marginal banks. The head loss (h) through syphon barrels and
the velocity (V) through them are generally related by Unwin's formula as
BY HABTAMU M. 88
IRRIGATION STRUCTURES HANDOUT
[ ]
2 2
L V Va
h= 1+ f 1+ f 2 − (a)
R 2g 2g
f2 = is a coefficient such that the loss of head through the barrel due to surface friction
2
L V
is given by f 2 .
R 2g
After having fixed the velocity (V) through the barrels, the head (h) required to generate that
much velocity can be found by using equation (a). The d/s HFL of the drain remains unchanged
by the construction of works, and thus the u/s HFL can be obtained by adding h to the d/s HFL.
The u/s HFL, therefore, gets headed up by an amount equal to h and is known as afflux. The
amount of afflux is limited because the top of guide banks and marginal bunds, etc. are governed
by this raised HFL. So, a limit placed on afflux will limit the velocity through the barrels and
vice versa. Hence, by permitting a higher afflux and, therefore, a higher velocity through the
barrels, the cross-sectional area of syphon barrels can be reduced, but there is a corresponding
increase in the cost of guide banks and marginal bunds and also the length of d/s protection is
increased. Hence, an economic balance should be worked out and a compromise obtained
between the barrel area and afflux. Moreover, in order to reduce the afflux for the same velocity,
the entry is made smooth by providing bell mouthed piers and surface friction is reduced by
keeping the inside surface of the barrels as smooth as possible.
The contraction in the waterway of the canal (i.e., fluming of the canal) will reduce the length of
barrels or the width of the aqueduct. This is likely to produce economy in many cases. The
BY HABTAMU M. 89
IRRIGATION STRUCTURES HANDOUT
fluming of the canal is generally not done when the canal section is in earthen banks. Hence, the
canal is generally not flumed in works of Type l and Type II. However, fluming is generally done
in all the works of Type III. The maximum fluming is generally governed by the extent that the
velocity in the trough should remain subcritical (of the order of 3 m/sec). Because, if
supercritical velocities are generated, then the transition back to the normal section on the
downstream side of the work may involve the possibility of the formation of a hydraulic Jump.
This hydraulic Jump would lead to undue loss of head and large stresses on the work. The extent
of fluming is further governed by the economy and permissible loss of head. The greater is the
fluming, the greater is the length of transition wings upstream as well as downstream. This extra
cost of transition wings is balanced by the saving obtained due to the reduction in the width of
the aqueduct. Hence, an economic balance has to be worked out for any proposed design.
After deciding the normal canal section and the flumed canal section, the transition has to be
designed to avoid sudden transition and the formation of eddies, etc. For this reason, the u/s or
approach wings should not be steeper than 26.50 (i.e., 2:1 splay) and the d/s or departure wings
should not be steeper than 18.50 (i.e., 3:1 splay). Generally, the normal earthen canal section is
trapezoidal, while the flumed pucca canal section is rectangular. It is also not necessary to keep
the same depth in the normal and flumed sections. Rather, it may sometimes be economical to
increase the depth and still further reduce the channel width in cases where a channel encounters
a reach of rocky terrain and has to be flumed to curtail rock excavation. But an increase in the
water depth in the canal trough will certainly increase the uplift pressures on the roof as well as
on the floor of the culvert, thus requiring larger roof and floor sections and lower foundations.
Due to these reasons, no appreciable economy may be obtained by increasing the depth.
For an Aqueduct: In case of an aqueduct, the bottom of the canal i.e., the roof of the culvert is
subjected to the dead weight and the vertical load of water from the top.
BY HABTAMU M. 90
IRRIGATION STRUCTURES HANDOUT
Since in an aqueduct, there is no uplift from the underside acting on the bottom of the canal bed,
the canal bottom has to be designed for taking the dead weight and full water load by either
providing a thickness sufficient to take this much of load merely by gravity or by providing
reinforced concrete slab with reinforcement at its bottom. The side walls of the canal are to be
designed as retaining walls. They may be made of masonry or R.C.C. It is preferable to have an
entire R.C.C. section. The retaining walls will be designed to carry the entire horizontal force
exerted by the canal water and shall, therefore, carry reinforcement on the water face.
For an Aqueduct Syphon: In case of an aqueduct syphon, besides the vertical load of canal
water, one more force comes into action i.e., the uplift pressure exerted by the drain water. The
roof of the culvert i.e., the bottom-slab of canal should now be designed to withstand these two
forces independently. Although these two forces act in a opposition to each other but still under
the worst circumstances, there may be times when only one of them may be acting. For example,
when drainage is flowing at its maximum high flood level, canal may be empty. Similarly, there
may not be any drainage water touching the slab when the canal may be running full. Hence, the
slab should be designed for
BY HABTAMU M. 91
IRRIGATION STRUCTURES HANDOUT
When the slab is designed to counter-balance the maximum uplift, merely be gravity, it is
sometimes found that the slab thickness required is less than what is required for the first
condition i.e., when designed for full water load). But many a times, the thickness required for
balancing uplift may exceed the thickness required for balancing the water load. In that case, it is
generally not advisable to increase the thickness because any increase in thickness will result in
lowering the levels of both the roof of the culvert as well as the bottom slab of culvert. This, in
turn, will increase the uplift on the roof slab as well as on the bottom slab of culvert.
(b) Uplift due to seepage of water from the canal to the drainage: The maximum uplift due to this
seepage occurs when the canal is running full and there is no water in the drain. The
computations of this uplift, exerted by the water seeping from the canal on the bottom floor, are
very complex and difficult, due to the fact that the flow takes place in three-dimensional flow
net. The flow cannot be approximated to a two-dimensional flow, as there is no typical place
across which the flow is practically two dimensional. Hence, tor the smaller works, Bligh's Creep
theory may be used for assessing the seepage pressures. But, for the larger works, the uplift
BY HABTAMU M. 92
IRRIGATION STRUCTURES HANDOUT
pressures must be checked by model studies. The seepage pressure can be evaluated by Bligh’s
theory as explained below:
The seepage flow occurs from the beginning of pucca canal trough (point a) and reappears in the
drainage bed on either side of the impervious floor along the center of the floor of the first
culvert bay (say point c or point d) in below. Point b is the point under the center of the floor of
the first culvert bay.
The seepage path from a to b and from b to c can be known. The total creep length will then be
equal to a b + b c. If H is the total seepage head (i.e. H=FSL of canal - d/s bed level of drain), the
residual head at the point b (i.e., Hb) is then given by Bligh’s theory as equal to
H b =H−
[ H
ab+ bc
∗ab
]
Hb=
[ H
ab+bc
∗ab
]
BY HABTAMU M. 93
IRRIGATION STRUCTURES HANDOUT
The floor of the syphon-aqueduct must be designed for the total uplift which is equal to the sum
of the uplift due to seepage plus the uplift due to static head. The total uplift may be partly
resisted by the wt. of the floor and partly by bending in reinforcement.
Methods of reducing uplift on the floor: The uplift on the bottom floor may be reduced in two
ways:
(i) By extending the impervious canal trough on either side of the drainage so as to increase the
creep length ab. A puddle apron may be used in place of concrete floor, if clay is easily available.
(ii) By providing drainage holes in the culvert floor so as to release the uplift. If such relief holes
are provided in the bottom floor; an inverted filter, should also be provided below the floor. The
inverted filter would help in preventing the soil particles from getting out of the holes. The
performance of such holes may not prove very successful in actual field as it appears to be on
paper. Because, if these get choked or if there occurs some defect in filter system, there may be a
danger of failure of work by excessive uplift or by undermining.
Two set of wings are required in aqueducts and syphon-aqueducts. These are
(i) Canal wings or Land wings: These wings provide a strong connection between the masonry or
concrete sides of a canal trough and earthen canal banks. These wings are generally warped in
plan so as to change the canal section from trapezoidal to rectangular. They should be extended
up to the end of splay. These wings may be designed as retaining walls for maximum differential
earth pressure likely to come on them with no water in the canal. The foundations of these wings
should not be left on filled earth. They should be taken deep enough to give safe creep length.
(ii) Drainage wings or Water wings or River wings: These wing walls retain and protect the
earthen slopes of the canal, guide the drainage water entering and leaving the work, and join it to
guide banks and also provide a vertical cut-off for the water seeping from the canal into the
drainage bed. The foundations of these wing walls should be taken below the deepest anticipated
BY HABTAMU M. 94
IRRIGATION STRUCTURES HANDOUT
scour in the river. The sections of these wing walls should be capable of withstanding the
maximum differential earth pressure likely to come on them.
The layouts of these sets of wings depend on the extent of contraction of canal and drainage
waterways, and the general arrangement of the work.
The following methods may be used for designing the channel transitions:
(i) Mitra's method of design of transitions (when water depth remains constant).
(ii) Chaturvedi's method of design of transitions (when water depth remains constant).
(ii) Hind's method of design of transitions (when water depth may or may not vary).
Shri A.C. Mitra, Chief Engineer, U.P. Irrigation Deptt. (Retd.), has proposed a hyperbolic
transition for the design of channel transitions. According to him, the channel width at any
section X-A, at a distance x from the flumed section is given by
Bn B f L f
Bx =
Lf Bn−( B n−B f ) x
Lf = Length of transition.
(ii) Chaturvedi's Semi-Cubical Parabolic Transition when water depth remains constant:
Prof. R.S. Chaturvedi, Head of Civil Engineering Deptt. in Roorkee University (Retd.), on the
basis of his own experiments, had in 1963, proposed the following equation for the design of
channel transitions when water depth remains constant.
[ ( )]
3 /2 3 /2
L . Bn Bf
X= 1−
Bn3 /2−B f 3 /2 Bx
BY HABTAMU M. 95
IRRIGATION STRUCTURES HANDOUT
Choosing various convenient values of the corresponding distance x can be computed easily
from the above equation.
(ii) Hind's Method for the design of Transitions when water depth may also vary:
This is a general method and is applicable either when the depths in the flumed and unflumed
portions are the same, or when these depths are different. In Figure below, the contraction
transition (i.e. the approach transition) starts at section1-1 and finishes at section 2-2. The flumed
section continues from section 2-2 to section 3-3. The expansion transition starts at section 3-3
and finishes at section 4-4. From section 4-4 onwards, the channel flows in its normal cross-
section and the conditions at this section are completely known. Let V and y with appropriate
subscripts refer to velocities and depths at different sections.
BY HABTAMU M. 96
IRRIGATION STRUCTURES HANDOUT
Between section 3-3 and 4 4, there is an energy loss in the expansion, which is equal to 0.3
( )
2 2
V 3 −V 4
2g
( )
2 2
V 3 −V 4
TEL at section 3-3 = TEL at section 4-4 (known) + 0.3
2g
As the trough dimensions at section 3-3 are known, V is also known and hence, TEL at section 3-
( )
2
V3
3 can be computed. Knowing TEL at 3-3; FSL at 3-3 can be calculated by subtracting from
2g
TEL. Similarly, bed level at 3-3 can also be computed by subtracting Y3 from FSL at 3-3.
Between sections 2-2 and 3-3, the channel flows in a trough of constant cross-section. The only
loss in the trough (HL) is the friction loss which can be computed with
1 2/3 1/ 2
Q= A . R . S
n
1
Q= A . R 2/3 .
n
HL
L √
2 2
Q n L
OR H L= 2 2/ 3
A R
Adding this head loss to TEL of section 3-3, the TEL at section 2-2 is obtained. The FSL at
2
V
section 2-2 can then be obtained by subtracting from TEL of 2-2. Similarly, the bed level at
2g
section 2-2 can be easily obtained by further subtracting y2 from FSL at 2-2. Since the depth and
velocity are constant in the trough, the TEL, FSL and bed lines are all parallel to each other from
section 2-2 to 3-3. Between section 1-1 and 2-2, there is a loss of energy due to contraction. This
( )
2 2
V 2 −V 1
loss is generally taken as equal to 0.2 .
2g
( )
2 2
V 2 −V 1
Thus, the TEL at section 1-1 =TEL at section 2-2 + 0.2 = unknown
2g
BY HABTAMU M. 97
IRRIGATION STRUCTURES HANDOUT
2
V
Knowing TEL at section -1, FSL at 1-1 can be obtained by subtracting 1 from TEL at 1-1.
2g
Similarly, bed level at 1-1 can be obtained by subtracting y1 from FSL at 1-1. The bed level, FSL
and TEL having been determined at all the four sections, the total energy line may be drawn by
assuming it to be a straight line between adjacent sections. The bed line may also be drawn
straight between adjacent sections, provided the rise or fall in bed is small. However, if the
change in bed level is considerable, the bed line in the transition section should be drawn as a
smooth reverse curve, tangential to the bed lines at ends.
BY HABTAMU M. 98
IRRIGATION STRUCTURES HANDOUT
6.1 Introduction
The water which enters into· the main canal from the river has to be divided into different
Branches and Distributaries, in accordance with the relative urgency of demand on different
channels. This process of distribution is called 'Regulation'. To distribute water effectively, the
discharge has to be adjusted to any desired value. This aim is achieved by means of regulators.
The works which are constructed in order to control and regulate discharges, depths, velocities
etc. in canals, are known as canal -regulation works. These structures ensure the efficient
functioning of a canal irrigation system, by giving full control upon the canals. The important of
these structures are :
(a) regulate the discharge flowing into the off taking channel, and
A head regulator is generally aligned at an angle of 90' to 110' to the axis of the barrage in order
to minimize the entry of sediment entering into the channel, besides preventing backflow and
stagnant pools in the under-sluice pocket that lies in the vicinity of the regulator. Steel gates of
spans usually in the range of 6 to 8 m, for manual operation, are provided in the regulator to
BY HABTAMU M. 99
IRRIGATION STRUCTURES HANDOUT
control the discharge. Larger spans can be adopted for gates which are operated by electric
winches.
(a) divert (and control the supplies off taking from the main canal and entering the
distributary,
(b) restrict the silt entering the distributary canal from the main canal, and
BY HABTAMU M. 100
IRRIGATION STRUCTURES HANDOUT
Silt excluder: are constructed on the bed of the river, upstream of the head regulator. It removes
silt from the water before it enters the canal.
Silt ejectors: are constructed on the bed of the canal and a little distance downstream from the
head regulator. It extracts silt from the canal water after the silted water has travelled a certain
distance in the off-taking canals.
BY HABTAMU M. 101
IRRIGATION STRUCTURES HANDOUT
Are constructed in the form of weirs, without any gate or shutter and spills over when the water
level of the canal goes above its crest level.
The locations for providing escapes are often determined on the availability of suitable drains,
depressions or rivers with their bed level at or below the canal bed level.
Escapes may be necessary upstream of points where canals takeoff from a main canal branch.
Canal escapes may be provided at intervals of 15 to 20km for main canal and at 10 to 15km
intervals for other canals.
BY HABTAMU M. 102
IRRIGATION STRUCTURES HANDOUT
7 SPILLWAYS
7.1 Introduction
A spillway is a structure constructed at or near the dam site to dispose of surplus water from the
reservoir to the channel downstream. Spillways are provided for all dams as a safety measure
against overtopping and the consequent damage sand failure. Spillway is thus safety valve for a
dam.
5. Energy dissipater should be located in downstream side of the spillway for dissipation of
energy.
Location of Spillway
BY HABTAMU M. 103
IRRIGATION STRUCTURES HANDOUT
• Spillway capacity should be equal to the maximum outflow rate determined by flood routing.
ii) reservoir capacity curve( reservoir storage Vs reservoir water surface elevation)
iii) discharge curve( rate of outflow through spillway Vs reservoir water surface elevation)
3. Capacity of outlets
4. Gates of spillways
BY HABTAMU M. 104
IRRIGATION STRUCTURES HANDOUT
Main spillway
A main(or service) spillway is the spillway designed to pass a prefixed or the design flood.
This spillway is necessary for all dams and in most of the dams, it is the only spillway.
Auxiliary spillway
It is provided as a supplement to the main spillway and its crest is so located that it
comes into operation only after the floods for which the main spillway is designed are exceeded.
Emergency spillway
It is provided in addition to the main spillway but it comes into operation only during emergency
which may arise at any time.
Controlled spillway
A controlled spillway is one which is provided with the gates over the crest to control the
outflow from the reservoir.
In the controlled spillway, the full reservoir level (F.R.L) of the reservoir is usually kept at the
top level of the gates. Thus, the water can be stored up to the top level of the gates.
Uncontrolled spillway
In an uncontrolled spillway the gates are not provided over the crest to control the outflow from
the reservoir.
The full reservoir level(F.R.L) is at the crest level of the spillway. The water escapes
automatically when the water level rises above the crest level.
BY HABTAMU M. 105
IRRIGATION STRUCTURES HANDOUT
-In this type of spillway, the water freely drops down from the crest. It is a low weir and simple
vertical fall type structures.
-The water falls freely from the crest under the action of gravity.
-To prevent scouring at the downstream, an auxiliary dam of artificial pool is to be constructed at
the place of fall of water.
-This type of spillway is not recommended for high head since the vibrations of falling jet might
damage the structure.
-To direct the small discharge away from the face of the overfall section the crest is extended to
form an overhanging clip.
BY HABTAMU M. 106
IRRIGATION STRUCTURES HANDOUT
-It has got the advantage over other spillways for its high discharging efficiency.
-The overflow water is guided smoothly over the crest so that water do not break the contact with
the spillway surface.
-The flow in this spillway is turned 90 ̊ after passing the crest such that the flow is parallel to the
weir crest.
-It is preferred where space is not available for providing sufficient crest width for chute
spillway.
BY HABTAMU M. 107
IRRIGATION STRUCTURES HANDOUT
-For earthen and rockfill dams, spillway is to be constructed separately away from the main
valley.
-Chute Spillway is the simplest type of a spillway which can be easily provided independently
and at low costs.
BY HABTAMU M. 108
IRRIGATION STRUCTURES HANDOUT
-The water from the reservoir enters into a vertical shaft which conveys this water into a
horizontal tunnel which finally discharges the water into the river downstream.
-This type of spillway is preferred where the space is not available for providing the above type
of spillways
-If the inlet leg is provided in shape of a funnel, it is called Morning Glory Spillway.
6. Siphon
BY HABTAMU M. 109
IRRIGATION STRUCTURES HANDOUT
-It consists of a syphon pipe whose inlet leg is kept just below the normal pool level and an air
vent kept at normal pool level is connected to the crown of syphon.
-When the water raises the pool level, syphonic action starts automatically and the water
discharges to downstream side.
-When the water level falls below the pool level, air is entered through air vent and the
discharging of water stops.
Figure 7. 6 Siphon
7. conduit (or tunnel)
- A conduit Spill-way consist of a closed conduit to carry the flood discharge to the downstream
channel . It is constructed in the abutment or under the dam .
- The closed conduit may take the form of a vertical or inclined shaft, a horizontal tunnel, or a
conduit constructed in an open cut and then covered.
- To ensure the free flow in the tunnel, the ratio of flow area to total tunnel area is often limited
to 75%of air vents are provided.
- Such a spill-way is suitable for dam sites in narrow canyons with steep abutments.
BY HABTAMU M. 110
IRRIGATION STRUCTURES HANDOUT
8 ENERGY DISSIPATION
8.1 Introduction
Hydraulic jump is the jump or standing wave formed when the depth of flow of water changes
from supercritical to subcritical state.
BY HABTAMU M. 111
IRRIGATION STRUCTURES HANDOUT
The choice of the energy-dissipating device at a particular spillway is governed by the tail water
depth and the characteristics of the hydraulic jump, if formed, at the toe. If the tail water depth at
the site is not approximately equal to that required for a perfect hydraulic jump, a bucket-type
energy dissipating device is usually provided. The characteristics of the hydraulic jump are
discussed in the following section. The sequent depth (conjugate depth or post-jump depth) y2 is
determined for different values of the discharge, and a jump height curve (JHC) is plotted
between the conjugate depth y2 as ordinate and the discharge (Q) as abscissa. The tail water
rating curve (TWRC) at the spillway site is determined by stream gauging, (Q) as abscissa. As
discussed later, the correct choice of the energy-dissipating device is made after comparing the
relative positions of the jump height curve (JHC) and the tail water rating curve (TWRC). For
the design of spillways, the discharge per unit length (q) is usually taken as abscissa instead of Q.
Different types of stilling basins have been developed which are quite effective for the formation
of stable hydraulic jumps and for confining the hydraulic jump. Stilling basins are commonly
used for spillways and other hydraulic structures, such as weir and barrages. In a stilling basin,
chute blocks, basin blocks (baffle blocks) and an end sill are usually provided. Chute blocks are
triangular blocks installed at the upstream end of the basin.
An end sill is constructed at the downstream end of the basin. It may be a solid sill or a dentate
sill. Baffle blocks are installed on the basin floor between the chute blocks and the end sill. These
are also known as baffle blocks or baffle piers.
BY HABTAMU M. 112
IRRIGATION STRUCTURES HANDOUT
Hydraulic jump is a sudden and turbulent rise of water which occurs in an open channel when
the flow changes from the supercritical flow state to the subcritical state. It is accompanied by
the formation of extremely turbulent rollers and considerable dissipation of energy. Thus, a
hydraulic jump is a very effective means of dissipation of energy below spillways.
Types of jumps
The type of jump and its characteristics depend mainly upon the Froude number of the incoming
V1
flow or the initial Froude number (F1), given by F 1=
√ g y1
Where V1 is the mean velocity of flow before the hydraulic jump, g is the acceleration due to
gravity and y1 is the pre-jump depth (or the initial depth of flow).
For the formation of a hydraulic jump, the initial Froude number F 1 should be greater than unity.
Different types of hydraulic jump are as follows:
1. Undular Jump An undular jump is formed when F1 = 1.0 to 1.70. In an undular jump, the water
surface shows some undulation. The energy dissipation is about 5%.
2. Weak Jump When F1 = 1.70 to 2.50, a weak hydraulic jump occurs. In this case, a series of
small rollers develops on the surface of the jump, but the downstream water surface remains
quite smooth. The velocity is uniform throughout. The energy dissipation is about 20%.
3. Oscillating Jump An oscillating hydraulic jump occurs when F1 = 2.50 to 4.50. There is an
oscillating jet entering the jump bottom to surface and back again without any periodicity. The
energy dissipation is between 20 to 40 %.
4. Steady Jump A steady jump occurs when F1 = 4.50 to 9.0. The jump is quite stable and
balanced. This jump is not much sensitive to variations in the tail water depth. The steady jump
has very good performance, and most of the hydraulic structures utilize this type of jump for the
dissipation of energy. The energy dissipation is between 45 to 70 %.
5. Strong Jump A strong jump occurs when F1 >9.0. The jump action is quite rough but effective.
It causes a rough water surface with strong surface waves downstream. The energy dissipation is
BY HABTAMU M. 113
IRRIGATION STRUCTURES HANDOUT
BY HABTAMU M. 114
IRRIGATION STRUCTURES HANDOUT
9 OTHER STRUCTURES
9.1 Introduction
Flow measuring structures are defined as hydraulic structures, installed in open channels or in
closed conduits with a free water level where in most cases the discharge can be derived from the
measured upstream water level.
In fact, such a structure is an artificial reduction of the cross-sectional area in the channel or pipe
Which causes an increase in the upstream water level, thus creating a drop in water level over the
structure. Provided the reduction is strong enough, we have a unique relation between the
dischargeandtheupstreamwaterlevel.Andbymeasuringthiswaterlevelcontinuouslywecanalso
obtain a continuous record of discharges as a function of the time.
The relation between the discharge and the upstream water level depends primarily on the shape
and dimensions of the structure, and only slightly on the geometry of the upstream channel or
pipe. The relation can be set up from a theoretical approach which is to be supported by a
calibration, mostly carried out by a hydraulic model study.
Duringthepastcenturiesnumeroustypesofflowmeasuringstructureshavebeendesignedwhose
characteristics meet modern demands of water resources development, particularly in irrigation
schemes and hydrological studies.
BY HABTAMU M. 115
IRRIGATION STRUCTURES HANDOUT
Continuous measurements:
Stage-discharge method: Once a unique relation has been established between water level
and discharge by one of the single measurement methods, discharges are derived from the
continuously measured water levels.
slope-stage-discharge method: Firstly, a relation must be set up between water level,
water surface slope and discharge based up on the Manning equation or the Chezy
equation and calibrated by one of the single measurement methods. After these discharges
are derived from two water levels which are measured continuously.
Acoustic method:
Discharges are calculated from measurements of both the flow velocity and the water
level. The velocity is computed from the difference in running time of a sound wave
which is transmitted diagonally across the channel in upstream and downstream direction.
Electromagnetic method :the flow velocity is determined by measuring the voltage
induced by a moving conductor(streamflow) in a magnetic field.
Pumping stations: for any pumping station a relation can, be established between the
discharge and the total loss of head, supported by calibration with one of the single
measurement methods. By counting the pumping hours, the total volume of water can be
calculated.
flow measuring structures: discharges are derived from measurements of the upstream
water level which is continuously measure data certain distance upstream of the structure.
Classification of flow measuring structures
Discharge measuring structures are classified according to the shape of the crest in the flow
direction. They can further be subdivided according to the different cross-sections:
1. Broad-crested weirs
The length of the crest should be sufficient to allow straight and parallel stream lines at least
along a short distance above the crest. The crest height with respect to the bottom of the
approach channelmustcomplywithacertainminimumvalue.Thebest-knownstructures are the
following weirs
BY HABTAMU M. 116
IRRIGATION STRUCTURES HANDOUT
The length of the crest is 1to 2mm. For this reason, they are also called thin-plate weirs. The
nappe is completely free from the weir body after passing the weir, and the stream lines above
the crest are strongly curved. In the air-filled area below the underside of the outflowing jet
atmospheric pressure should prevail. Among the most used thin-plate weirs are:
We call weirs short-crested when their characteristics in some way look like those of broad
crested and sharp-crested weirs. The streamlines above the crest are curved. Well-known
examples are:
Where the bottom of the canal drops suddenly, a free overfall is created. The water level is
measured exactly above the drop(end depth or brink depth). The discharge is function of both the
end depth and the shape of the cross-section. There we can identify
BY HABTAMU M. 117
IRRIGATION STRUCTURES HANDOUT
The Parshall flume consists of a metal or concrete channel structure with three main sections: (1)
a converging section at the upstream end, leading to (2) a constricted or throat section and (3) a
diverging section at the downstream end
Depending on the flow condition (free flow or submerged flow), the water depth readings are
taken on one scale only (the upstream one) or on both scales simultaneously.
6. Cut-throat flume
The cut-throat flume is similar to the Parshall flume, but has no throat section, only converging
and diverging sections. Unlike the Parshall flume, the cut-throat flume has a flat bottom. Because
it is easier to construct and install, the cut-throat flume is often preferred to the Parshall flume.
BY HABTAMU M. 118