Risk Model For Energy Performance Contracting in Correctional Facilities
Risk Model For Energy Performance Contracting in Correctional Facilities
George H. Berghorn, Ph.D., LEED AP BD+C1 and Matt Syal, Ph.D., LEED AP2
ABSTRACT
Energy performance contracting provides guaranteed minimum energy savings to
KEYWORDS
energy performance contracting (EPC), energy efficient building practices, building
retrofits, project performance risks, risk modeling, scenario failure mode and effect
analysis (SFMEA)
INTRODUCTION
Commercial buildings account for nearly half of the primary energy consumption in the United
States. Although correctional facilities (prisons and jails) account for less than 1.5% of the overall
commercial building stock floor space, they are in the upper half of all commercial building
1. Assistant Professor of Construction Management, Michigan State University School of Planning, Design, and Construction
(corresponding author)—[email protected]
2. Professor of Construction Management, Michigan State University School of Planning, Design, and Construction—[email protected]
METHODS
Figure 1 depicts the steps involved with developing the approach used for developing the risk
model. The model utilizes expert knowledge and project-specific quantitative data, as described
by Duah (2014). Therefore, a method that combines both types of information must be con-
sidered in developing an EPC contractor’s risk model. Since all levels of project decisions have
a greater impact on overall project design and performance at the lowest overall cost, informa-
tion availability and quality during the project is also critical. This is premised on the notion
that risks can best be controlled during the earliest project phases, when the costs of change are
lowest and the potential impact of those changes is the greatest (Horsley et al. 2003; Kishk et
al. 2003). As a result, the presented model utilizes a risk analysis and evaluation framework that
incorporates multiple sources of information (quantitative, expert knowledge, probabilistically
generated data).
of either “1” or “2,” indicating the top two ranks, across all three score types. One panelist
referred to these as the risks that “keep me awake at night.” Additionally, panelists agreed that
since the investment grade audit (IGA) establishes the energy baseline for the project, as well
as the basis of design for the project, the quality of this analysis can disproportionately impact
actual savings.
These varied and significant risks highlight the need to develop a comprehensive frame-
work for addressing all of the elements of risk that impact specific project objectives. Syal et al.
(2014) and Duah (2014) emphasized the need to capture expert knowledge and judgements
related to the energy retrofit process; in this paper, that is applied within the context of a risk
management system. While this research uses an expert-based risk evaluation and analysis
process, the following studies were considered to guide method development:
ECt
ECPV =
(1+ d)t
where ECPV = the present value of the EC, ECt = the future expected cost at time t, d = the
discount rate, and t = the time in years when the risk is realized.
Step 4: Recommend and Evaluate Mitigation Strategies
The EPC risk framework completed by Berghorn and Syal (2016) included control measures
and mitigation strategies for many potential risk causes. The primary focus of the paper was
the development of the model framework. Mitigation, while important, was not the main
goal, therefore a separate ESCO expert with significant risk management experience was asked
to provide mitigation strategies for each risk scenario. An efficacy score was assigned to each
mitigation strategy, which is a measure of the amount of the initial risk that is controlled by
investing in a given mitigation strategy.
( ) ( )
Risk remaining = 1− Efficacy mitigation × EC or Risk remaining = 1− Efficacy mitigation × ECPV
Potential values of ELCV or ELCVPV are variable within the upper limit of the EC and the
lower limit of the cost of risk remaining after mitigation, therefore values approaching zero are
desirable; negative values indicate a poor cost-benefit relationship between mitigation costs
and net benefits.
Project Variables: Variables related to ECM service life-related costs were generated
from a probability density function (PDF) that was generated based on ECM-specific
service life values using the “Service Life Data Query” feature of the ASHRAE Service
Life and Maintenance Cost Database (ASHRAE 2014).
Facility Variables: Cause probabilities were developed through expertise elicited from
SFMEA panelists.
IF (gross floor area) built or renovated after 1980 THEN Pcause = 0.0 × area
Calculation of Risk Scenario Costs: As with the calculation of probabilities, costs for
each scenario are derived from SFMEA panelist-assigned values, user inputs, or exter-
nally-derived data.
In cases where risk causes were “Misunderstanding Facility Conditions” and “Facility Age and
Current Code Requirements,” construction estimates were used whenever possible to determine
risk costs, utilizing industry standard cost databases such as those developed by RS Means (RS
Means 2017). Data for asbestos abatement costs per building square foot were derived from
Azen et al. (1992) and Whitestone Research (2009), with costs converted to present year dollars
using consumer product indices.
Framework Database
The database providing facility-, probability-, and cost-related data utilizes data sources in
four primary sub-databases: (1) IGA data, (2) cost data, (3) climate data, and (4) equipment
replacement and maintenance life/cost. Relevant IGA data is provided directly by the model
user through the interface. Cost data was derived from industry standard construction cost
estimating databases (RS Means 2017) and research that has been directed to defining asbestos
remediation costs per square foot of building area. Equipment service life data was obtained
from the ASHRAE Service Life and Maintenance Cost Database combined with cost data from
the IGA.
Climate data consisted of annual normal HDD and CDD values as well as 62 years of
CDD and HDD data. These data were then used to calculate probabilistic energy savings in
the case of extreme climate conditions (e.g., ≥95th percentile climate years). Each model run
selected an input value of HDD or CDD from the climate PDF; if a value from the 95th per-
centile or above was chosen, that value was retained and its impact on the project was calculated
using the results of the multivariate regression model developed by Griffin (2008). Griffin’s
model found that for every one unit increase in HDD, energy consumption per square foot
increases by 0.032 thousand BTUs (KBTUs) (or 0.00032 therms). He also observed a 1:0.007
relationship for CDD and KBTUs. While developed for Air Force installations, and thus not
specific to correctional facilities, Griffin’s work was useful in preliminary model development
due to similarities between military installations and correctional facilities (government owner-
ship, large multi-building campuses, wide variation in building ages, and high security opera-
tional profiles).
• Highly experienced key informants (ESCO and correctional facility staff); and
• Locations were sought that recently (i.e., within the past five years) entered the energy
savings phase of an EPC project, such that data would be readily available and key
informants would have recent knowledge of project characteristics.
• Capacity and willingness of ESCO and corrections staff to participate in the study.
Sensitivity Analysis
Sensitivity analysis was conducted to determine the impact of inputs on the results of the life
Recommendations
The model determined the ten most critical risks for the case study project to be related to five
root causes discussed briefly, below: (1) reduced availability of “low-hanging fruit” ECMs, (2)
work scopes based on traditional DBB procurement, (3) unavailable or inaccurate facility infor-
mation, (4) facility age and current code requirements, and (5) conducting the IGA too quickly.
These root causes point to the need for ESCOs to expand ECMs beyond traditionally
deployed technologies such as lighting retrofits and water conservation measures. This includes
continuing the trend to increase use of non-energy benefits in EPC retrofits (Stuart et al. 2016).
Moving away from DBB procurement models will require institutional commitment to adopt
design-build or integrated project delivery procurement methods, in order to integrate retrofit
contractors into early phase engineering decisions during the RD phase. Additionally, reliance
on standardized fees for engineering and architectural design, often found in DBB contracts,
may lead to artificially increasing the cost of an EPC retrofit to the ESCO, thus eroding the
potential energy savings scope of work. Incomplete and inaccurate facility information, as well
as age and code update requirements highlight the need for ESCOs to clearly and appropriately
allocate responsibility for risks that may arise from these root causes. Finally, great care should
be taken during the IGA, particularly when focusing on information needs to address critical
risks identified through the model (e.g., facility condition information, establishment of the
energy baseline, and modeled performance in light of climate extremes).
Despite the maturity of state and federal EPC markets, making these recommended
changes, particularly for correctional projects, can be difficult due to the nature of these facili-
ties and the complex political and regulatory environments in which they exist (Stuart et al.
SUMMARY
This paper introduced a risk analysis and evaluation framework and risk model for EPC contrac-
tors undertaking correctional facility retrofit projects. The framework of the model was built
on SFMEA (Kmenta and Ishii 2000; Kmenta and Ishii 2004) which uses expected cost as the
measure of risk criticality. This represents a methodological improvement over the reliance on
REFERENCES
ASHRAE (2014). “ASHRAE: Service life and maintenance cost database.” <http://xp20.ashrae.org/publicdatabase/
default.asp> (March 14, 2014).
Azen, S.P., Niland, J., Hayward, S.B., Liu, K-S., Redinger, C., and Porter, P. (1992). “Estimation of the cost
of asbestos abatement in public buildings in the state of California: an application of the bootstrap.”
Environmetrics, 3(2), 193–209.
Berghorn, G.H. (2014). Life cycle cost-based risk model for energy performance contracting retrofits. PhD Dissertation.
Michigan State University. East Lansing, MI.
Berghorn, G.H. and Syal, M.G.M. (2016) “Risk framework for energy performance contracting building retrofits.”
Journal of Green Building, 11(2) 93–115.
Bharvirkar, R., Goldman, C., Gilligan, D., Singer, T.E., Birr, D., Donahue, P., and Serota, S. (2008). Performance
contracting and energy efficiency in the state government market. LBNL-1202E, Ernest Orlando Lawrence
Berkeley National Laboratory. Berkeley, CA.
Bhattacharjee, S., Ghosh, S., and Young-Corbett, D. (2010). “Energy service performance contracting in construc-
tion.” Proc., 46th Annual International Conference of Associated Schools of Construction, Boston, MA.
Bolstad, W.M. (2013). Introduction to Bayesian statistics, 2nd ed. Wiley: New York, USA.
Bowles, J.B. (2004). “An assessment of RPN prioritization in a failure modes effects and criticality analysis.” Journal
of the Institute of Environmental Sciences and Technology, 47(1), 51–56.
Chen, C-C. and Zhang, H. (2012). “A FMEA-aided equipment life-cycle-cost measurement system.” Proc.,
3rd International Asia Conference on Industrial Engineering and Management Innovation, Chinese Industrial
Engineering Institution, Beijing, China.