Label Control SOP
Label Control SOP
PROCEDURES MANUAL
Issue & Update : 01 (05/12/2023)
Responsible:
Store Issue Girl, Sewing Issue Boy, Line chief & Supervisor .
01. Procedure:
1.1 Labels on receipt at main store with proper inventory, get inspected as per the Trims
& Accessories inspection SOP and stored in controlled manner in order to avoid theft,
misplace & damage.
1.2 If required, Sub-store will (For Sewing and Finishing Accessories) receive required
quantity as per the production plan from Main-store and ensure that the storage
system is maintain as per Style & Customer in secured manner with bin card update
system. On the other hand Main store will kept Pass labels as per Style & Customer
in secured manner with bin card update system
1.3 When needed for the use in line, Line Issue boy will receive the required labels from
sub- store/ Main store as per the cut quantity mentioned in the cutting challan and
handover to Line chief.
1.4 Line chief issues the label to the operator as per the bundle in process to ensure the
correct size and correct number of labels are issued and take sign from the operators
on the label issue, receive and return format.
1.5 Operators are not allowed to keep various sizes of labels to avoid incorrect attaching
and extra labels in their custody.
1.6 Operators attach the label as per mock-up card information as required for the style in
production.
1.7 Line chief and Issue boy is responsible for exchange reject / damage (if any) quantity
from sub-store/Main store and issue to operator.
1.8 After style production is over, Line chief and Issue boy will hand over all kinds of
labels to main store with proper Challan. A copy of the Challan is given to the Store
Document Number : PM / PR / 06
PROCEDURES MANUAL
Issue & Update : 01 (05/12/2023)
Quarantined area:
1.10 All reject/damage labels will be kept carefully quarantined area in every
stage. (Main & sub-store)
PROCEDURES MANUAL
Issue & Update : 01 (05/12/2023)