Diavik Mining
Diavik Mining
)
© 2022 Australian Centre for Geomechanics, Perth, ISBN 978-0-6450938-3-4
doi:10.36487/ACG_repo/2205_98
Abstract
Sublevel retreat (SLR) and sublevel cave (SLC) production levels require an initial void for production drifts to
begin blasting into. Slot drifts are commonly developed perpendicular to production drifts and used to
establish a free face using uphole drilling and blasting. Unlike in open stoping, these openings are filled with
caved or blasted material, requiring choke blasting. The overall approach of establishing these slot drifts is
relatively straightforward from a high level, operationally there are many options to achieve this. It is
important to understand the impact these options have on safety, ore recovery, and production rates.
Diavik Diamond Mine uses SLR/SLC methods to mine two ore bodies. During the last 10 years of production,
seven different methods have been used to open and establish slots in SLR/SLC levels. This paper examines
the various methods used and their suitability to different situations. The methods used at Diavik are heavily
dependent on ground conditions and what the ore quality will allow. The work completed at Diavik may offer
a starting point for other mines beginning or changing an SLR or SLC.
Keywords: sublevel cave, sublevel retreat, slot, blasting
1 Introduction
Diavik Diamond Mine is located on Lac de Gras in the Northwest Territories, Canada. It is accessible only by
air for most of the year and by winter road for two months of the year. Operations began in 2003, initially
mining kimberlite pipes using open pit methods, three of which have transitioned to underground mining
upon completion of the pits. All kimberlite pipes that have been mined at Diavik were located under the lake;
water retention dykes were constructed and the pools that remained inside dyke enclosures dewatered to
allow mining of the pipes. The full transition to underground mining occurred in 2012; a fourth pipe
subsequently began open pit production in 2018. Mining is planned to complete in 2025 (Yip & Pollock 2017).
Initial studies for underground mining selected blasthole open stoping (BHS) and underhand cut-and-fill
(UCAF) to be used as mining methods. During open pit mining and underground construction, the methods
were re-evaluated, and BHS was maintained for the A154N orebody while sublevel retreat (SLR) was selected
for the A418 and A154S ore bodies (Lewis et al. 2018).
Given the extremely good quality granite host rock, as the SLR front is drawn deeper, the granite has not
substantially caved, leaving a crater exposed to surface with unsupported high walls of over 300 m in height.
Over time, relatively minor sloughing (compared with the overall opening) of the highwall has caused broken
waste to overlay the ore blanket (Jakubec et al. 2004). This has necessitated the use of draw control methods
similar to what is used in a sublevel cave (SLC) to regulate grade. For this reason, Diavik could be considered
both an SLR and SLC mine.
Drilling into or in proximity to previously blasted ground introduces the risk of drilling into misfired explosives
and causing an unintended detonation. To protect underground operators, remote controlled drilling is
carried out at Diavik using multiple cameras, allowing the operator to control the drilling from a safe distance
in an enclosed, moveable cabin (Lewis et al. 2018). This remote drilling process requires exclusion zones to
be established, closing, and barricading of sections of the level.
Drilling through previously blasted ground creates an additional safety risk which must be managed. It
requires area closures and additional work to set up remote drilling causing substantial delays in the mining
cycle. When recovery drilling is required, production rates are reduced, and ore release may be delayed.
Figure 2 Layout of intersection mass blast plan view and section view
Figure 3 Sequence of intersection mass blast plan view and section view
A slight variation of this method was also used, where the slot drift was developed from the two outer drifts
and then production drifts broken through once the slot drift was complete. The resulting smaller
intersection from developing the production drifts into an existing slot drift require fewer rings firing in the
intersection blast as the intersection was smaller (generally closer to 7 m in diameter). These were slightly
more effective; they were less likely to bridge and when they did bridge would require less recovery drilling.
Larger intersections would typically require blasting 4–5 rings at once where the smaller intersections would
typically require blasting 2–3 rings at once. The difference in intersection size is illustrated in Figures 4 and 5.
While the difference appears minimal, it did allow at least one less ring to be required in the mass blast. The
smaller intersections had the added benefit of reduced long support and reduced risk associated with larger
intersections in weak ground.
Figure 4 Larger intersection examples in plan view with slot drift rings
Figure 5 Smaller intersection examples in plan view with slot drift rings
Given the inconsistency in block size and jointing in kimberlite, unconfined compressive strength (UCS) is
used at Diavik to differentiate kimberlite strength (Diavik Diamond Mine 2021). The ground in the A418 is
poorer quality than in the A154S (Table 1). Low stress conditions in weak kimberlite have been found to cause
rock to slough away around rockbolts at Diavik. Due to the low stress conditions near open brows, it was felt
that long support would be ineffective in preventing localised failures near brows in the A418 orebody. For
this reason, intersection ring-by-ring was never attempted in the A418 orebody but is the preferred method
in the A154S orebody.
Figure 7 Layout of slot drift, non-breakthrough plan view and section view
Figure 8 Sequence of slot drift, non-breakthrough plan view and section view
While this method was more successful at establishing the slot drift, it introduced additional recovery blasting
at the beginning of the production drift mining. The fan blast was using the slot drift as void; however, the
blasting direction of the initial ring was toward the pillar between the drifts. Insufficient void propagated for
the entire blast. This method was found to be ineffective and was discontinued.
Figure 9 Layout of slot drift, post-breakthrough plan view and section view
Figure 10 Sequence of slot drift, post-breakthrough plan view and section view
This method has proven effective in opening the slot drift and establishing production drifts and has become
the standard method used in the A418 orebody.
Figure 11 Layout of individual full width plan view and section view
3.6 Individual
In an attempt to reduce bridging and recovery drilling, vertical individual slots were used (Figure 12). This
type blasted with 25–30% void ratios and would generally pull to full length. However, they did not open the
slot to full width. In order to open production drifts to full width, production rings were designed to gradually
widen from 5 to 15 m over multiple rings. This method reduced recovery drilling, however there was poor
ore recovery on the far side of the orebody. In the SLR method, this ore could potentially be draw on the next
level, however there was a delay in draw, uncertainty, and potential for increased dilution to recover this
ore.
3.7 Hammerhead
To reduce the requirement for recovery drilling and recover as much ore as possible, the hammerhead
method has been proposed. Production drifts are slashed and developed either side. An uphole raise is drilled
with vertical rings; the entire hammerhead is then blasted in a single shot (Figures 13 and 14). This method
produces adequate void for the individual full width using additional development. It has similarities with the
intersection mass blast method, however it slowly opens using the initial void from reamers rather than
blasting choked into a muckpile.
At the time of writing, the hammerhead method was planned for a level in the A418 as well as for a single
heading in the A154S. These locations had not been drilled or blasted so no results are available yet.
4 Discussion
Slot drift methods are used to establish levels efficiently, allowing for maximum ore recovery. Safety of
operators is paramount, and methods are not considered if undue risk to personnel is anticipated. A summary
of the methods used at Diavik is illustrated in Table 2.
Intersection ring-by-ring proved to satisfy safety concerns, ore recovery, and ease of opening, only where
ground conditions allowed adequate support to protect workers. Compared against the slot drift,
post-breakthrough method, was also generally easier from an operational perspective as development could
be completed ahead of time, and remote development drilling not required for the post-breakthrough round.
Where ground conditions do not allow an intersection ring-by-ring method, Hammerhead may offer a simple
alternative, however it was unproven at Diavik at the time of writing. While the slot drift, post-breakthrough
method required additional operational delays and effort, it still produced a safe and predictable method.
5 Conclusion
Diavik’s path to optimising its slot drift opening kept safety as the principal value. An iterative approach was
then taken trialling and refining various methods. Multiple methods are available depending on local
conditions to maximise ore recovery and reduce production disruptions. The most successful methods used
were intersection ring-by-ring and slot drift, post-breakthrough; results of the hammerhead method were
pending at time of writing.
The purpose of this paper has been to share the lessons learned at Diavik to provide options, ideas, and a
starting point for other SLR and SLC mines. When beginning a new SLR or SLC, other mines may use
experience gained at Diavik as a starting point for slot drift opening methods. Every orebody and mine will
encounter unique situations and challenges, however the experience gained at Diavik may allow other
operations the ability to skip unsuccessful methods and focus on those which have shown more successful.
References
Bull, G & Page, CH 2000, ‘Sublevel caving - today’s dependable low-cost ‘ore factory’’, Proceedings of 3rd International Conference
and Exhibition on Mass Mining 2000, The Australasian Institute of Mining and Metallurgy, Melbourne, pp. 537–556.
Di Giovinazzo, M & Singh, U 2010, ‘Instrumentation and monitoring of cave initiation at Telfer Mine’, in Y Potvin (ed.), Caving 2010:
Proceedings of the Second International Symposium on Block and Sublevel Caving, Australian Centre for Geomechanics, Perth,
pp. 145–155, https://doi.org/10.36487/ACG_rep/1002_7_Digiovinazzo
Diavik Diamond Mine 2021, Ground Control Management Plan, Diavik Diamond Mines, Yellowknife.
Jakubec, J, Page C & Harvey, P 2004, ‘Mining method selection for diamond mines - challenges in the arctic’, in A Karzulovic
& MA Alfaro (eds), Proceedings of MassMin 2004, Instituto de Ingenieros de Chile, Santiago.
Kosowan, MI 1999, Design and Operational Issues for Increasing Sublevel Cave Intervals at Stobie Mine, MSc thesis, Laurentian
University, Sudbury.
Lewis, PA, Clark, LM, Rowles, SJ, Auld, CP, Petryshen, CM & Elderkin, AP 2018, ‘Sublevel retreat mining in the subarctic: a case study
of the Diavik Diamond Mine’, in Y Potvin & J Jakubec (eds), Caving 2018: Proceedings of the Fourth International Symposium
on Block and Sublevel Caving, Australian Centre for Geomechanics, Perth, pp. 57–72, https://doi.org/10.36487/ACG_rep
/1815_02_Lewis
Page, CH & Bull, G 2001, ‘Sublevel caving: a fresh look at this bulk mining method’, in WA Hustrulid & RL Bullock (eds), Underground
Mining Methods: Engineering Fundamentals and International Case Studies, Society for Mining, Metallurgy, and Exploration,
Englewood, pp. 385–394.
Power, G & Just, GD 2008, ‘A review of sublevel caving current practice’, in H Schunnesson & E Nordlund (eds.), Proceedings of the
5th International Conference and Exhibition on Mass Mining 2008, Luleå University of Technology, Luleå, pp. 155–166.
Yip, CG & Pollock, KS 2017, Diavik Diamond Mine NI 43-101 Technical Report, Diavik Diamond Mines, Yellowknife.