Item Description Unit Quantity Unit Rate USD VAT USD Amount USD TTC
CIVIL WORKS
A Site Mobilization
Site Mobilization including : the cleaning of the site, the removal of the dirt and debris
1 to a municipality approved dump site, the levelling of the site, the equipment and Lot 1
tools mobilization on site,etc.
B Fence Works (Item 6) (Details as per the plan A5-R01)
The supply & installation of door of Height=1.8 to 1.9 m & Width= 4m (Gate A & B).
The rectangular door frames & accessories will be made of the same material of the
7 6.2cm galvanized steel bars, the door surface will be made of the same material of No 2
the stainless steel fence net. The price should include the hinges, locks, knobs and
all the needed accessories for a complete door.
All required earth & civil works for the casting of the fence concrete foundations. The
price will include the digging of 45x45x50cm fence foundation holes, removal of the
debris to approved dump sites, compaction of holes if needed, the supply of all filling
8 materials, the formwork, the concrete supplying, mixing and casting. The concrete No 43
would be class B that is dosed at 350 Kg of cement/m³ with a minimum compressive
strength of 28 Mpa. Aggregates will be used up to 20mm in size.The Ratio Water /
Cement = 0.45.
Supply & installation of galvanized steel goal bar (schedule 40) of total length of 9m
9 No 2
& of Diam=6.2cm as per the drawings & details
All required earth & civil works for the casting of the goal bar concrete foundations.
The price will include the digging of 45x45x50cm goal foundation holes, removal of
the debris to approved dump sites, compaction of holes if needed, the supply of all
10 filling materials, the formwork, the concrete supplying, mixing and casting. The No 4
concrete would be class B that is dosed at 350 Kg of cement/m³ with a minimum
compressive strength of 28 Mpa. Aggregates will be used up to 20mm in size.The
Ratio Water / Cement = 0.45.
The construction of reinforced concrete slab on grade of 45cm with stairs (as per
drawings), with two layers of reinforcement steel bars of 12mm(20cm spacing) at low
level and two layers of reinforcement steel bars of 10mm(20cm spacing). The price
will include the formwork,bar chairs, the concrete supplying and mixing and the
11 m3 16
supply of all materials, labor, tools, machines and all necessary equipment for
casting the slab.The concrete would be class B that is dosed at 350 Kg of
cement/m³ with a minimum compressive strength of 28 Mpa. Aggregates will be used
up to 20mm in size.The Ratio Water / Cement = 0.45.
The construction of the masonry wall of hollow block (Hordi) of 10cm width on the
12 stage as per the drawings. The price will include the supply of the blocks, the cement m2 15.5
for mortar, labors and all necessary material and tools to build the wall.
Cement plastering of the two sides of the masonry wall and the stage façade & back
wall and stair suraces as per the drawings & details. The price should include the
13 supply, transportation, storing and placing plaster on 3 layer 16mm thick, labor, m2 43
cement mortar furnishing and placing, providing scaffolds, tools, accessories and all
necessary materials.
External painting of the two sides of the masonry wall and the stage façade & back
wall and stair surfaces as per the drawings & details. The price will include the
14 supply, transportation, storing and placing of paint including labor, paint material, all m2 43
needed mixing materials and placing, providing scaffolds, tools, accessories and all
necessary materials where needed and as directed by the project manager.
The finishing works on the concrete stage floor. The price will include labor, cement
15 mortar polishing, tools, accessories and all necessary materials where needed and m2 35
as directed by the project manager.
E Playground Center Civil Works (Item 3) (Details as per the plan A4-R01)
The construction of reinforced concrete slab on grade of 10cm, with two layers of
reinforcement steel bars of 10mm(20cm spacing) as per the drawings & details. The
price will include the formwork,bar chairs, the concrete supplying and mixing and the
16 supply of all materials, labor, tools, machines and all necessary equipment for m3 8
casting the slab. The concrete would be class B that is dosed at 350 Kg of
cement/m³ with a minimum compressive strength of 28 Mpa. Aggregates will be used
up to 20mm in size.The Ratio Water/Cement = 0.45.
F Seater Rocker Civil Works (Item 4) (Details as per the plan A4-R01)
The construction of reinforced concrete slab on grade of 10cm, with two layers of
reinforcement steel bars of 10mm (20cm spacing) as per the drawings & details. The
price will include the formwork,bar chairs, the concrete supplying and mixing and the
17 supply of all materials, labor, tools, machines and all necessary equipment for m3 1
casting the slab. The concrete would be class B that is dosed at 350 Kg of
cement/m³ with a minimum compressive strength of 28 Mpa. Aggregates will be used
up to 20mm in size.The Ratio Water/Cement = 0.45.
All required earth & civil works for the casting of the trampoline bars concrete
foundation. The price will include the digging of 45x45x50cm bar foundation holes,
removal of the debris to approved dump sites, compaction of holes if needed, the
18 supply of all filling materials, the formwork, the concrete supplying, mixing and No 8
casting. The concrete would be class B that is dosed at 350 Kg of cement/m³ with a
minimum compressive strength of 28 Mpa. Aggregates will be used up to 20mm in
size.The Ratio Water / Cement = 0.45.
H Swing Set Civil Works (Item 2) (Details as per the plan A3-R01)
All required earth & civil works for the casting of the swing set bars concrete
foundation. The price will include the digging of 60x30x60cm bar foundation holes,
removal of the debris to approved dump sites, compaction of holes if needed, the
19 supply of all filling materials, the formwork, the concrete supplying, mixing and No 4
casting. The concrete would be class B that is dosed at 350 Kg of cement/m³ with a
minimum compressive strength of 28 Mpa. Aggregates will be used up to 20mm in
size.The Ratio Water / Cement = 0.45.
Note: For the line items 16,17,18 & 19, the contractor should coordinate with
World Vision/Items Suppliers before implementation of work.
I Site Demobilization
Lead Time:
Payment Terms:
Company Name:
Email Address: