CMA Job Order Costing Compiled
CMA Job Order Costing Compiled
Q.1. ABC Company incurred the following costs to produce. Job No.586 which consisted of 1000 units of
product ‘A’.
Direct materials:
Direct labour:
Time card No.72 500 hours at Rs.13 per hour.
Manufacturing overhead:
Required:
a) Prepare a job order cost sheet and record the information given above.
b) Pass journal entries to record all transactions.
Q.2. Pakistan Engineering Works uses a job-cost system. Consider the following data:
Required:
(i) Compute the cost of:
(ii) Overheads are applied to jobs at Rs. 25 per direct labour hour. Under/over applied
overheads are transferred to cost of sales.
(iii) Job 101 was completed during the month and the goods were sent to the warehouse for
delivery to the customer. During the transfer to the warehouse, 160 units were damaged.
Net realizable value of the damaged units was Rs.500,000. Remaining units were
transferred to the customer.
(iv) Job 202 is in process; however, 2,000 units are fully complete and were transferred to the
warehouse during the month while 3,000 units are 70% complete as at 30 June 2014.
(v) Actual overheads for the month of June 2014 amounted to Rs. 4,000,000.
Required:
Prepare journal entries to record the above transactions.
Q.4. The following information has been taken from the job order cost system, used by Jahangeer Sons:
During July job no.23, 24 and 25 were completed and job no.21, 22 and 23 were sold on account at
25% above cost.
Required:
(I) Cost of finished goods inventory – beginning.
(II) Cost of goods in process inventory beginning
(III) Cost of finished goods inventory – ending
(IV) Cost of goods in process inventory – ending
(V) Cost of goods manufactured
(VI) Cost of goods sold
(VII) Sale revenue.
Q.6. RI Limited (RIL) is engaged in the manufacturing of spare parts for industrial machines. RIL
receives bulk orders from its customers and follows job order costing. Following data pertains to two
of the jobs which were started in the month of February 2018:
Q.7. Gulshan Enterprises Limited (GEL) is engaged in the manufacturing of specialized drilling
equipment for the oil and gas industry. The following data pertains to the jobs undertaken by GEL
during the month of August 2023:
On 16 August 2023, a special machine was hired on rent for three months, exclusively for use on
Job C528. A rent of Rs. 4.8 million was paid in advance, while the remaining amounting to Rs.
2.4 million will be paid at the end of the three-month period. The transportation cost incurred in
bringing the machine to the site amounted to Rs. 0.3 million. The costs incurred in respect of this
machine have not been included in the factory overheads amount.
Additional information:
(i) Job A227 was completed on 25 August 2023. Upon completion, unused materials
costing Rs.5 million were transferred to Job B391. All 20 units were transferred to the
finished goods store, from which 14 units were transported to the client on 31 August
2023. The remaining 6 units were transported on 2 September 2023.
(ii) On 31 August 2023, 16 units from Job B391 were completed and transferred to the finished
goods store. It is estimated that the further cost required to complete the job will amount to
Rs. 95 million.
(iii) In a fire on 10 August 2023, some of the materials issued on Job C528 having a cost of
Rs.18 million was destroyed. 80% of the materials were insured, and GEL received a claim
for those materials. The remaining materials were sold as scrap for Rs. 1 million.
Required:
Prepare journal entries to record the transactions for the month of August 2023. (16)