To Dynam C Loads: Vitelmo V. Bertero
To Dynam C Loads: Vitelmo V. Bertero
TO DYNAM~ C LOADS
by
VITELMO V. BERTERO
Ingeniero Civil
Universidad Nacional Del Litoral
R. Argentina
1947
S.M. in C.E.
Massachusetts Institute of Technology
1953
DOCTOR OF SCIENCE
at the
FEB 19 1958
IaIBRARI
To my wife, whose patience and encouragement
The lattice analogy was used for the theoretical analysis. The
simplified lattice used for the elastic behavior during a previous in-
vestigation by Mr. Finerman, was modified for the cracked range. In
order to determine the properties of the modified equivalent lattice,
several assumptions were made. Making use of these assumptions, the pro-
gramming for the WHIRLWIND I and IBM 70h digital computers was developed.
Both programs, as well as the results they yielded, are included in the
theoretical discussion.
CHAPTER I: INTRODUCTION
I. Statement of Problem
II. Previous Investigations
III. Objectives
IV. Summary of the Investigation
V. Acknowledgement
REFERENCES 8h
FIGURES 86
INTRODUCTION
I. Statement of Problem
depends on the amount of protection desired against the forces which one
load. In this sense, the shear wall structure offers one of the most
ing lateral loads from structural walls (shear walls) capable of resist-
ing lateral loads acting in their own plane, are understood to be shear
be accomplished. Since the shear wall is one of the most important com-
The shear wall is a very stiff member; that is, it has a high
in its own plane, but the analysis needed to predict its behavior is more
complicated than that of simple plates, for the following reasons. The
shear wall cannot act completely as an individual plate, but must deform
-1-
elastic and inelastic properties which are difficult to define, and which
wall. Namely:
In addition, the usual lateral loads produce dynamic effects which must
also be considered.
loads. These standards are usually based on the inertia of the entire
to each story in the form of static lateral loads. The engineer has had
to rely on judgement to decide how much of the total lateral load will be
forces created by blasts, and the increasing desire to reduce the amount
criterion necessary.
able amount of effort in the design of shear walls. A large part of their
-2-
Some experimental work has also been accomplished, yielding
I-shape.
mental testing, but since their primary goal is earthquake study, most
been done in the United States before 1949. At that time, an investiga-
gation was to obtain experimental data that would help establish design
-3-
1 2 ) ( 1 3 ) ( 14 ) ( 15 )( 16 )
published which shed some light on the subject.(11)(
(17)(18)(19)(20) However, all these investigations were made considering
only the behavior of walls under static loads, and although the results
obtained throw some light on the present problem, it is well known that
slowly applied loads, is quite different from the behavior of the same
structure under rapidly-applied loads such as those which arise from wind
attention has been paid lately to the effects of these loads, it has
reinforced concrete shear walls under dynamic loads. From the theoretical
side, its principal aim is to find a method that may allow, in the future,
-4 -
large-scale models of reinforced concrete shear walls.
to the testing of several reinforced concrete shear walls, with the ob-
ject of analyzing the behavior of the machine, and at the same time ob-
tain some data on the parameters which can affect the dynamic resistance
indicates, his work was restricted to the study of the dynamic response
that the designer must decide what point in the behavior of the structure
that only rarely may he choose this point to be within the elastic range,
assumed that the first loading on a shear wall will be resisted in part
predictable volume changes can cause cracks to develop along any section
-5-
From the above considerations it is evident that it is
III. Objectives
dynamic loads.
walls.
namic loads for the phase included between the first cracking load and
obtain theoretical load-deflection curves and the ultimate load for the
proportion. Four specimens were tested, and these were identical except
the day of the test was approximately 3,000 psi, and in the other two 5,100
-6-
and 6,300 psi respectively.
One wall was loaded by static lateral load only. This test
served to check the operation of the equipment and to establish the sta-
recorded against time, during each test, with the exception of the
VI.
V. Acknowledgment
conducting the tests. Also the work done by Shui Ho and Christopher Cal-
-7-
computers. The recording instruments were assembled and operated by
offered much practical advice and did the machine work for some of the
investigation.
-8-
CHAPTER II
FACTORS INVOLVED IN THE PROBLEM OF A SHEAR WALL UNDER
DYNAMIC LOAD
the value of a series of tests and the relation of that series to the
frames with diagonal bracing and continuous frames with masonry or re-
-9-
most satisfactory and economical choice for structures designed to
must be considered. In one case, the shear wall may belong to a one
parameters.
wall, the dynamic response of the wall can vary over a wide range,
walls only.
A. Frame Effect
- 10 -
A. Frame Effect: Ordinarily, the greatest gains in speed of construction,
cost and space usage in shear wall structures are obtained by simplify-
shear walls. Since cross walls are ordinarily well tied to face walls
and to floor and roof slabs, it is obvious the latter will impart --
as flanges with the shear wall in resisting bending moment and shear
beam practice, the allowance would be eight times the thickness of slab
or face wall on each side of the cross wall, and the maximum effective
between shear walls. This would mean that a 6" wall or roof slab is
should be noted that face walls and slabs enter into the frame action for
shear walls of any monolithic structure, whether or not there are framing
columns and beams. However, in the case where dynamic loads are applied,
frame size for a given wall, this throws little light on the actual
- 11 -
effect of face walls and slabs in a structure. It is obvious that if
the slab develops cracks (but does not fail in flexure), the horizontal
the stresses in the roof are not sufficient to cause cracking, the roof
models were carried out at Stanford University (1 3 ) but the results should
1. The relation between column and beam areas and wall panel area
will produce first cracking, by changing the stress pattern in the wall.
2. The steel ratio of the column and beam directly influence the
ultimate strength.
along the base will result as shown in Figure 3. This requires a yield-
ing of the tension column steel. If the tension column steel does not
yield and produce a failure, the ultimate load can be associated either
- 12 -
determined, reinforced concrete walls of practical proportions do not
den failure.
B. The Steel Ratio of the Wall Panel and its Distribution: The design
the mode of failure to some extent. If the percentage is small, the wall
will have an ultimate load derived from two sources -- the compression
column and the panel steel. As the panel strength increases with increas-
of the strengthening factors in the panel showed that the only important
static tests it was found that the yield point of the panel steel was a
parameter. These same tests seem to indicate that there exists a prac-
tical limit in the neighborhood of one per cent panel steel, above which
- 13 -
Standard design procedures call for equal amounts of horizon-
the panel. The practice is reasonable when the steel ratio is low and
large amounts of steel are not involved. Howrever, blast design may re-
quire large amounts of steel in the panel. Some question then arises
fective than that placed horizontally and vertically, the static test
cases the ultimate loads were smaller, in the case of a diagonal pattern
on the diagonals and in the lower corners produced early shrinkage crack-
results in slightly stronger and stiffer shear panels, provided the walls
are not subjected to a transverse load at the same time. Further studies
under static loads show that uniform vertical steel is more effective
- 14 -
zontal steel would be undesirable from a practical standpoint, since a
desired to reduce the panel steel, the horizontal wall steel in the up-
The present study only takes into account walls with uniformly
three.
mens in which the bottom beam can be considered as fixed. The analyti-
walls, the first cracking load decreases after a certain L/H, instead
of increasing.
In this first series of dynamic tests, the L/H ratio was not
eral investigation.
- 15 -
III. Construction Procedures
ing frames from sliding or rotating will act to relieve the straining
supports, except for the fact that they are not entirely rigid, but have
ing the first static test, and were found to be not negligible.
- 16 -
In a shear wall, the loads are transmitted at the bottom of
the wall through a connecting shear wall, a floor slab, or the founda-
ture.
to study the behavior of shear walls which are submitted to loads pro-
the peak pressure, the variation with time, and the duration of the
positive phase are of prime interest. These factors depend on the energy
release of the weapon, the ground zero distance, and the height of burst.
may be exposed will never be accurately known. The only thing that can
done, curves of load vs. time for most types of rectangular structures
- 17 -
may be approximated by the methods given in , Chapter XI; and(23),
Appendix 1.
the location of the wall. Figure 8 shows the typical loading on shear
wall structures.
and rear walls, the roof and shear wall are usually assumed infinitely
rigid in their own planes. Then, the reactions of the exterior walls
rather than the direct blast pressures should be used in the design of
shear wall are greatly affected by the rate at which the forces acting
on the front and rear walls and the roof are applied on it.
blast-resistant walls are allowed, the reactions of the wall will have
an impulse curve which is very different from that for the pressures act-
ing on the exposed wall at any given time, as shown in Figure 9. This
will, in most cases, reduce the strength needed for the structural ele-
system and thence to the tops of the shear walls. If walls were so
- 18
An exception would occur if large impulsive loads were applied
to very heavy face walls. However, the above conditions lead us to the
apply the load along the top of the wall. This conclusion introduces
another question: How should the load be distributed along the top of
methods cause a different crack pattern than the first. The loading in-
since face walls and floors together act as an I-beam, the floor being
the web of the beam. It would seem reasonable to believe that shear
web. However, this can only be true in the elastic range, because if
the slab develops cracks but does not fail in flexure, the load will be
is the presence of vertical forces. These forces may result from heavy
dead loads and the superimposed live load arising from vertical effects
- 19 -
magnitude of the total vertical force will be of the order of 50 to l00
of the shear load applied to the top of the wall, depending on relative
cal load may affect the response, because the moments of these loads
affect the deflections, which in turn affect the moments of the vertical
forces; but there is still another effect of the vertical load which is
one, and both the forces and the moments are independent functions of
order of magnitude as the shear load, and the initial stress pattern and
- 20 -
equivalent to the added vertical force.
concrete models geometrically scaled to 1/8, 1/4, and 3/8, were used.
of static loads -- the load will vary as the square of the scale factor,
and deflections vary directly as the scale factor, with like concrete
applied load and the internal forces are closely balanced at all times,
and continuously equal to the applied loads, and the resultant accelera-
tion of the member will not be negligible. The maximum stress and, more
- 21 -
important, the maximum displacement produced under blast loads, are a
of the force, the duration of the load, and the particular variation with
time of the applied force and the resistance. These stresses and dis-
placements are generally far different from those which would result from
a static load of equal magnitude, and the prediction of the way the load
and deflections will vary with the scale factor becomes very difficult.
of force, mass, stiffness, strength, and time. The scale factor between
the responses of model and prototype will not only depend on the dimen-
sional scale factor, but also on the rate of application of the force,
the duration of the load, and the natural vibratory frequency of the wall.
ing machine, and the other set is related to the instrumentation neces-
sary to obtain the magnitude of load and reactions, strains and deflec-
- 22 -
accuracy of the results to be obtained will depend on the errors intro-
IV.
this investigation.
- 23 -
CHAPTER III
TEST SPECIMENS
resent shear walls in a single story building, one bay wide, which was
steel distribution are illustrated in Figure l1. The four walls cast
were identical except for the compressive strength of the concrete. For
two of these walls, the compressive strength was 3,000 psi, whereas in
the other two this strength was 5,100 and 6,300 psi respectively. Table
in the places where the load was applied. As it is indicated in the same
figure, special steel plates were used where the load and reactions are
applied.
gation.
specimens. The mixes used for the concrete had the following character-
istics:
- 24 -
For wall #1 and #2
the rate of gain in strength and the strength on the day of the test
the strength was approximately that desired. This was possible in all
Reinforcing Steel
panel, and in order to maintain the separation of the bars between prac-
tical limits, it was necessary to use undeformed bars for the panel re-
- 25 -
The important characteristics of the bars used in the four
designed so that its part could be easily removed. Two walls were cast
simultaneously, The reinforcing cage and the steel plates -- where loads
the reinforcing of the frame to the plates, which were held in place by
an auxiliary steel frame. Figure 12 shows the fornmork and the rein-
forcement in place.
deflections had to be attached, and bolts were inserted for the subsequent
All the concrete was mixed for three to five minutes in a mixer
of 6 cu.ft. capacityi Each wall was cast from two batches of concrete
were also cast from each batch. The concrete was placed in the forms and
The walls and control cylinders were stored under moist condi-
tions for five days, after which they were removed from the forms and
Figure 13 shows the walls and cylinders just after being cast.
- 26 -
F-
o 0 0 0
0
I I I
Co CoCo
4
·r-l~ ·-F-
*H *H *
cc cc cx~
r-\ HH
I
0 0 O O
0 0 O0O
In I 1 tr\
I I
.~ I C Co
*H *.
COO CO
Co
0 0
F-. F--
E-4
bO
0 r- r-I H H H
0 O
O 1 ! I I
ho
o
00 .H--I
0 4 4-3
H
(D 0 H H0
4'. 4-.
tCj tC tCi
cl c MH
_ C\clJ
CN C
NC N Se -- r--
ma to~ us v
O o *H H H Hp H-
H 0 - 0 0
- 0
0
O
-) o -t o - -- --
Hr r- r- r-
. rtC
oc
E-i
0...
.
CO H c11
HCMz
t z
m .t
- 27 -
M -tC co
blE-o co
(0
o ,H
a>
*H H<
V\ - CO O
r-I
-p
0
0)0 P-
H
CO
0 0 0 0
VI) *
0 OO C.)
M
\ ED 0 0
CO
0
4,
0H a,g
0 0 *(-
O O 0
+3 ·r
V\ u\ _O
H
H
4,
0)
H-
00)
0
0j CM CJ C,j
o,
C
0)
IH C'J
rn 4 % % :1
- 28 -
0
H
H
H
H
- 29 -
CHAPTER IV
EQUIPMENT AND INSTRUMENTATION
the test setup as the specimen itself. The reliability and consistency
test program. The fact that the equipment and instrumentation necessary
for a dynamic test are infinitely more complicated than the equipment for
behavior of a test specimen under dynamic loading, which will also serve
jected to static loading. The pulse of the loads applied should be control-
lable as to magnitude and duration, and the force-time shape should follow
any desired function. The apparatus should also be able to record reac-
I. Loading equipment.
I. Loading Equipment
- 30 -
for this experimental program, under contract with the Corps of Engineers.
The supporting frame for the specimens and loading device con-
parts of the basic frame. Figure 1L is a side view of the heavy truss
feet in length.
be moved up and down by increments of five inches allowing walls from 3ft
basic trusses; therefore when the main loading device (hydraulic jack)
applies a load to the specimen, the reaction equal and opposite to the load
applied load were static, the trusses would be under loads which equili-
This is clearly shown in the sketch of Figure 15. However, since the loads
- 31 -
to be applied are dynamic ones, at any given time there may exist a con-
on beam I. This special shape was required in order that the unbalanced
and consists, essentially, of the main cylinder, main piston, and main shaft.
equal forces are applied to both faces of the main piston by the introduc-
- 32 -
tion of compressed oil into the chambers on either side of the piston, and
pressures into the two compartments are adjusted according to the area of
the piston faces (73.631 sq. in. for the push side, and 65.97h sq. in. for
the pull side) and the desired value for the dynamic load, so that no load
At the time of loading, the oil in one face of the piston (pull
side) is permitted to escape, and the piston is acted upon by the pressure
of the remaining oil on the other face (push side). This pressure is kept
The unloading process involves the flow of oil from the ten-gallon
accumulator to the pull side, and as this oil is at a higher pressure than
that in the push side, the piston is forced to move back, away from the
as it is explained below.
2. The Sequence Control System for the Automatic Control of the Loading
contact points. Each contact has its own potentiometer voltage divider, so
that the voltage on the wiper arm can be made to follow any desired function.
tenuated and sent to a summing circuit where it is combined with the signal
from the force transducer at the ram. The combined signal is the error or
the difference between the command and the load on the specimen. The error
- 33 -
signal is amplified and sent to a second summing circuit, where it is
combined with position feedback signals from the second and third stages
the first hydraulic stage. Thus, the error signal controls a feedback-
three-way valve (dump valve), which controls the flow to and from the pull
men is produced by the difference between the system pressure at the rear
the'front or pull chamber. Figure 20 shows the servo and dump valves
connected together.
panel, and the necessary piping and tubing. Figure 16 shows the disposi-
Figure 21.
piston pump, which can deliver a maximum of h8 g.p.m., the maximum operat-
ing pressure being 3000 psi. The principal purpose of this pump is to
way that it may also deliver oil to the complete system. The other pump
following:
- 34 -
The principal purpose of this unit is to feed the accumulators,
The manifold allows the delivery of oil from the pull side to the
receiver unit, or the flowing of oil from the ten-gallon accumulator to the
pull side. These two operations are made through the dump valves which are
through the dump valve -- to reduce or remove the applied load when required.
push side and their principal use is to act as a source of fluid power to
hold the pressure behind the face of the piston when it moves forward. The
compensation and to help supply the large flows required during the test.
The two one-pint accumulators are connected directly to the pull side with
the object of smoothing out pulsations, should this ever prove necessary.
phragms, one of which is connected between the pull and push sides in order
to prevent the ramming of the piston against the front side of the cylinder
failure of the specimen. The other safety head with rupture diaphragm is
connected between the ten-gallon accumulator and the push side and it will
side. This will permit a fast balance of pressure between push and pull
sides, thus preventing the ramming of the piston against the back of the
cylinder. The Barksdale valve located on the control panel may also be con-
- 35 -
sidered as a safety device, because if it is opened it will allow the rapid
draining of the push side. To open the valve it is only necessary to hit
points. One of these filters is connected to the Vickers unit, and filters
all the oil that this unit pumps into the system. Another 104 filter is
connected between the transfer unit and the Seco unit. Two 10 1 filters
are also placed in parallel just before the servo valves, with the purpose
of filtering all the oil that goes to these valves. In addition to these
filters, it was necessary to connect a unit which filters all the oil that
The transfer unit is a small pump which transfers the oil from
the tank of the Vickers unit to that of the Seco unit. The receiver unit
is a three-gallon tank into which the oil from the servo valve and the pull
side of the cylinder is drained, before it is sent back to the tank of the
Oil from any supply pump can be directed into the system through
take the following description: One starts the Vickers pump with all valves
closed, except for valves 10, 2, and the Braksdale valve. All the pressure
gage line valves (6'; 4'; 1'; 5'; and 7), are just cracked so that the pres-
sure in any line will be indicated at any moment.. In this way, it is pos-
- 36 -
operate the dump valve -- approximately 2,500 psi. The test supervisor
pressurizing system control panel, and once he has stabilized the inner
loops and has moved the dump valve to a position that will connect the pull
side of the main cylinder and the ten-gallon accumulator, he gives the
order to supply pressure to the system. At this moment the control panel
oper'ator opens valve 1, and closes valve 2. This will allow the oil to
flow to any part of the system, once the line interlock valves 6,h,5,9, are
opened. One starts opening valves 6 and h, which will allow the supply of
the pressure required for the test is smaller than 2,500 psi, this is
larger than 2,500 psi, the Vickers pump is turned off at 2,500 psi pressure,
and closing valve 10, the Seco unit is started, which can then give a maxi-
mum pressure of 10,000 psi. Once the pressure in the 10 gal. accumulator
and the pull side of the cylinder is that desired for the test, valves 6
and h are closed, and then the Barksdale valve is closed at the same time
that valve h is opened. This operation will allow the supply of pressure
to the push side. Due to the fact that the diameter of the shaft is
greater in the pull side than in the push side, the area of the pull face
of the main piston is smaller than that of the push side. Consequently,
smaller than that required in the pull chamber by a factor of 0.896. Then,
one must take the precaution that the pressure in the push side does not
When the pressure in the push chamber has reached the desired
- 37 -
and valve 9 is then opened. If the pressure desired in the 10 gal. accumu-
lator and in the chambers of the cylinder required the use of the Seco pump,
this pump must now be turned off, and the Vickers unit is to be started once
more.
The operator of the control panel gives the signal of "ready for
testing" to the test supervisor, and the test can then be performed as soon
as the supervisor brings the ram in contact with the specimen. The test
To bleed off the supply lines after the test, special precaution
has to be taken in extracting first the oil from the push chamber by open-
ing the Barksdale valve, then draining the complete system by opening valves
2, 6 and h. Servo pressure must be maintained until all push pressure has
ing the detailed shape of the mentioned quantities for force-time curves of
test program was not only the evaluation of the properties of the shear
wall, but also the evaluation of the testing machine. Since one of the most
important properties of the machine is the speed of the load build up and
the shape of the load-time curve during build up, it was decided to run this
- 38 -
Where the load-build-up time Tr was expected to be of the order of 20 to
scopes were readily available, and this would only allow the recording of
was decided to measure only load, reactions and deflections in this first
series of tests.
B. Measurements of Deflections
C. Recording Equipment
D. Timing System
E. Calibration
through the use of standard SR-h gages and strain measuring equipment. The
gages were attached to Load Cells and calibrated in terms of kips of load.
- 39 -
trol of loading and unloading processes, it is important to know the
curve, that of using sensing elements such as Baldwin SR-h strain gages
depended upon the mounting problem, and the sensitivity required. The
simplest load cell shape for use in this case. As the load cell had to be
connected to the ram (or main shaft) of the hydraulic jack and to the ele-
ment (Ram Head) which will be in direct contact with the specimen to be
from the load cell as the maximum load decreases, is through the use of
tube with reduction of the wall thickness. With this in mind, and since
it was expected for this first series of tests, that the ultimate resist-
ance of the shear wall would not be greater than 150 kips, a drawn tube
- ho -
of aluminum alloy 6062-T6, with a h in. outside diameter, and a wall thick-
Not only the stress in the load cell was checked, but also special
direct function of the area in the form fn ), does not go below certain
To obtain the output of a load cell for a given force, the follow-
GF x 1V)
o 2 2(1)
Er(r -r )
V = output voltage
o
P = applied load
V = applied voltage
1= ETE(r 2-r 2)
n 2-T 1(M + 0.33m)
- l1 -
Past work has shovwn positively that SR-h gages have little, if
any, frequency restrictions below 50,000 cycles per second. Expression (1)
imposes a limitation on the load cell sensitivity. Type C-10 or CB-10 are
the best for high sensitivity load cells for dynamic tests. However, as
they were not readily available, C-7 models with a gage factor of 3.3 were
used.instead. Four C-7 strain gages were mounted on the outer surface of
the aluminum tube in an alternating pattern. Two of the gages were placed
horizontally and parallel to the axis of the tube, and two are circumferen-
cuit is formed with the horizontal gages in opposite legs. This arrange-
the average strain output of the horizontal leg by approximately 2.6. Con-
Substituting our data into equation (1), the output of the load cell is seen
that in order to obtain better control of the loading and unloading processes
planned - for the successive tests - to use the arrangement shown in Figure
31(b).
cycles per second. If it is now considered that the wall to be tested was
- h2 -
2. Reactions: The two vertical, and the horizontal reactions of a
shear wall specimen are measured by special load cells. The shape of this
possessing great flexibility in the plane of the wall, since they also act
sist of three seven and a half inch pieces of 8 WF 48 steel. Actually the
design was made for an aluminum H-beam, with a depth of 8 in. and web thick-
ness of 0.5 in. But as this standard structural shape was not readily
strength and it became necessary to use steel. In order to obtain the sen-
sitivity required, eight SR-h, type C-7 strain gages are mounted as shown
of load and results in a signal output from the bridge equal to 2.6 times
the average of the vertical gage. These load cells have been calibrated
B. Measurement of Deflections
Company. Since previous static tests indicated that the maximum horizontal
deflection before failure would not exceed 1 in., a Schaevitz gage with a
maximum range of 1" was used. The gage used for measuring vertical deflec-
tions at the loading point had a maximum range of + 3/8", and for the one
used at the support for the vertical displacement, the range was + 1/4".
For the horizontal displacement of the support, one with a maximum range of
- 43 -
+ 1" was used. Due to the fact that the point at which the vertical deflec-
tion, a difficult alignment problem was posed. This problem was solved by
using the device that is shown in Figure 34 and which essentially consists
C. Recording Equipment:
The signals from the load, reactions, and deflections are detected
on four Du~ont type 322, Dual Beam Cathode-Ray oscilloscopes, and the perma-
nent record of the traces from the screen of the Cathode-Ray oscilloscopes
are obtained by using four DuMont Type 297 oscillograph record cameras;
D. Timing System
The number of events taking place and the short duration of the
loading period made it mandatory to adopt a triggering device such that the
with the initiation of the test. This is obtained by pressing the fire
Packard 200A audio oscillator, thus obtaining in this way a modulated wave
for the deflection signal, with a time interval equal to 2 ms. between wave
peaks.
- 44 -
As there are four deflections and four forces (one load and three
reactions) to be measured, one deflection and one force signal were recorded
E. Calibration
The load cells used to measure load and reactions were calibrated
under static loading, using a Baldwin 200,000 lbs. hydraulic testing mach-
wound resistance were placed across one leg of the bridge, so that their
the calibration trace on the screen of the oscilloscope, the zero reference
line is established first, and then the bridge is unbalanced with the
calibrated resistance.
Dial Gage.
ment used on this experimental work, there are several small devices which
are indispensable to the smooth performance of a wall test, but do not merit
E. Restraining Strut.
- 45 -
A brief description of each of these auxiliary equipment follows.
test, a lateral restraint system was devised for these tests. Figure 35
posed of two horizontal bars bolted to two poles which were fastened between
device that prevents the transmission of any large beniding moment to the
main shaft of the hydraulic jack. This bending moment can be produced by
friction between the ram head and the plate connected to the specimen.
E. Restraining Strut
In order to protect the load cells, used for reactions, and the
ram from damage caused by a specimen overriding the stroke of the ram, a
special strut of steel was placed behind the wall, limiting the total hor-
izontal deflection of the wall to two inches. Figure hO shows this strut
in place.
- 46 -
CHAPTER V
TESTS OF WALLS
tests made previously (16); but also because it would afford an opportunity
to check the correct operation of all the equipment at a loading rate slow
test would also make possible thestudy of the importance of the support
I. Wall Preparation
The preparation of the wall for testing is the same whether the
that more deflection brackets and supports for Ames dial gages were neces-
sary for the static test. Figure 42 shows schematically the location of
the gages for the static test, and Figure 43 for the dynamic tests.
Three days after the wall is cast, it is removed from the form-
work and stored in the laboratory until the tests on the corresponding cy-
-0 -
wall is moved into position on the reaction-measuring supports, which are
The wall is then bolted by means of six 7/8" Allen Socket-Head Cap Screws
per support. Then the lateral restraint mechanism is bolted on the already
cast bolts, and connected with the part attached to the frame, as shown in
Figure 35. The wall is then white washed in order to improve the detection
of the cracks. Next, the brackets for deflections are attached to the wall
on the already cast bolts. Then the frame for supporting the gages is put
in place and the last step .is the attachment of the gages and the making
the various measuring devices. A wall ready for testing is shown in Figure
S5. It must be noted that the preparation of the wall for testing requires
is read, the calibrating traces for each electronic measuring device are
IV, and the gain of each amplifier is first set so that the calibrating
The load is applied by allowing the gradual flow of oil into the
chamber behind the main piston (push side), and readings are taken for every
of 3680 lbs.
In a preliminary step, the load is increased until an oil pressure
of 300 psi is reached, and then released, with the object of checking if
- 48 -
all the measuring devices are working. The load is then increased until
the maximum resistance of the wall has been overcome and its travel is
recorded and the precharge pressure of the nitrogen in the different ac-
oil is pumped into the servo mechanism until a pressure of 2,000 psi is
reached, with the object of activating the dump valve. Then the dump valve
is set in neutral position by means of the balance control, and the two
inner-loop gains (one corresponding to the servo, and the other to the dump
valve) are set in order to obtain the stability of these two inner loops.
Next, the dump valve is moved to the closed position, which wrill allow the
pumping of oil to the pull side, and also to the ten-gallon accumulators,
because they are now interconnected through the manifold and the dump
valve. Once the pressure on the pull side and ten-gallon accumulators
reaches a value high enough to give more force on the pull side than that
which will exist on the push side under the maximum required oil pressure
for the test to be performed, the control valves to the pull side and ten-
gallon accumulators are closed, and oil is pumped to the push side of the.
loading piston. This is done until the pressure reaches the value required
Once the oil pressures in the different parts of the system are
those required for testing, the man who is operating the hydraulic system
gives the "ready" order to the man in charge of the electronic equipment;
who then, by means of the balance control moves the dump valve to the center
position (neutral), and then opens it slightly in order to move the ram
towards the wall. When the ram-head position indicator indicates that the
- 49 -
head of the ram is close to the wall, the shutters of all the oscillograph
record cameras are opened, and when the signal of the ram-head indicator
shows that the ram is practically touching the wall, the man in charge of
the function generator presses the fire button, which simultaneously re-
leases the trigger on all the oscilloscopes and sends the signal to the
This activates the whole system, producing the load desired. This load
ing to the static test - and then increasing the magnitude of the peak
load, until a value that produces the collapse of the wall is reached.
A. Static Test
1. Specimen #1: Specimen #1 was tested under lateral static load, and
the results of this test are presented in the form of curves and photographs.
Figure 46 shows the complete picture of the deflections that the wall and
its supports suffered, while Figure 47 shows the lateral movement of the
top of the shear wall with respect to the foundation (supports), which is
of primary importance.
was expected due to the special precautions .taken, such as the welding of
support B, given by curve 4, was considerable, and the same can be said
- 5o -
with respect to the horizontal displacement given by curve 3. In spite of
the special precautions taken with the connection of the supporting beam
B with the trusses, such as the introduction of shims between the gusset
plate of the supporting beam and the web of the two channels that form the
bottom chord of the two trusses, and that the nuts of the high-strength
bolts were driven in with power wrenches in order to provide a good clamp-
ing force, the large vertical displacement seems to indicate that the fric-
tion produced between the joined members was not sufficiently high to pre-
vent vertical slipping.
support in the dynamic tests, but also to include in the theoretical anal-
ysis the effect of the rotation and sliding of the shear wall as a con-
placement measured at the loading point the value obtained for the horizon-
tal movement of the support B, plus the horizontal movement due to the ro-
tation caused by the vertical movement of the supports; shows that the first
crack in the wall occurred at a load of approximately 25 Kips. This is what
actually happened during the first test, when -- in order to check the ins-
trumentation - the oil pressure in the push side was increased up to 350
psi. The first crack was that marked with number 1 in the picture of
Figure 48. The complete test was actually carried out on a cracked wall.
- 51 -
failure of the welded connection of the reinforcement of the tension column
0.12 in. With respect to these results, the following comparison should be
made:
specimen -- where the only difference lay in the strength of the concrete,
(3 vs. 5) x 103 psi, and in the modulus of elasticity, (3 vs. 4.5) x 106 psi
-- gave the following results:
47, curve (b). It should be noted that the ultimate load was associated
by shear failure at the base of the compression column.
tic relation, (i.e.) neglecting the increase of stress during strain hard-
When the results obtained are compared with those of the Stanford
holding down the tension column of the shear wall at the support. It seems
that for the test performed at Stanford University, the support of the ten-
sion column was considerably stiffer than that used in this test; and fur-
- 52 -
The discrepancy between the experimental ultimate load obtained dur-
ing the test, and that obtained analytically, can be explained by the pres-
B. Dynamic Tests
for the applied load, reactions and deflections at four points as functions
wall #4.
The results of the dynamic test on each specimen are presented in
The sharp peaks and depressions in the load-time curves were caused
and depressions are averaged and a curve is drawn through the average points,
a smooth load pulse can be obtained; however, its shape varies from one test
to another. The rise time varies from 10.0 ms. to 30.0 ms., and the total
duration from 35.0 to 75.0 msa.
- 53 -
Figures 50, 52, 54, and 56 give the value of the load and reactions
versus time, and Figures 51, 53, 55, and 57 give, respectively, the value
of the deflections vs. time obtained in these tests. As it is shown in
this last group of figures, only the data corresponding to the horizontal
deflection at the loading point, and at the support was obtained, due to
the fact that at the time the tests were started, the complete set of de-
vices necessary for holding and attaching the Shaevitz gages was not avail-
able. Consequently, it was not possible to obtain the component of the
to reach this peak load, the lateral movement of the loading point with
respect to the foundation (supports) at the time at which peak load is
reached, and the maximum value of this relative lateral movement with the
time at which it happens are shown in Table V-l, for each test. Also shown
in this table is the static deflection obtained on specimen #1 correspond-
b. For the following tests, when the peak load is smaller than 30 kips,
d. After test No. 8 the dynamic deflections are larger than the static
ones; the explanation of this result can be found in the fact that
the wall was considerably damaged (cracked) after test No. 8.
It must also be noted that the first cracking occurred during test
No. 5, at a load of 40 kips.
Because of an error when trying to precharge the ten-gallon accum-
ulator to a higher pressure, after test No. 12, the pressure in the pull
side was released without releasing that in the push side first, resulting
the tension column with the support plate. Figure 53 shows the cracks on
the wall after test No. 6, which had a peak load of 31.5 kips. However,
the cracks shown in the picture were produced by a load of 40 kips, ap-
plied during test No. 5. Figure 59 shows the wall after failure.
2. Specimen #3: Specimen #3 was submitted to several load pulses of
it can be seen that the rise time varies from 12.5 to 25.5 milliseconds
and the total duration varies from 35 to 62 milliseconds. It may also be
seen that during the first tests the load did not come back to zero. The
force-time shape varies considerably from one test to another and only
that corresponding to test 13 can be considered as triangular in shape, if
the small peaks and depressions are smoothed with an average curve. -=
- 55 -
Table V-2 gives a summary of the test results on specimen #3.
Analyzing these results and the corresponding figures, it can be seen that
when there exists a definite peak load, the maximum horizontal deflection
takes place almost simultaneously, the delay being only of a few millisec-
onds in certain cases. On the other hand, when there is.no definite peak
in the pulse, the maximum deflection may occur considerably before or
after the instant at which the peak load is reached, and more or less co-
inciding with some of the other peaks.
of 42.5 kips.
If the values of the maximum lateral deflection obtained on the tests
Because of an error during test 16, the vertical reaction at the fixed
support and the vertical displacement at the same support were not obtain-
ed.
Figure 72 shows wall #3 after failure produced by a dynamic load with
a peak value of approximately 68 kips. This failure was due to the defect-
ive welding of the reinforcement of the tension column to the support plate.
figures that:
- 56 -
a. The shape ;of the pulse load is not consistent, even if a smooth
curve is drawn through average points of the peaks and depressions.
Wall #4 failed under a dynamic load whose peak value was equal to 74
kips. Figure 85 shows the crack pattern of this wall after failure, which
the question of how much more load can the specimen withstand if this
out the concrete at the bottom of the tension column and welding again the
reinforcement to the support plate, taking special precautions to avoid -
- 57 -
The repaired wall was then submitted to a new series of tests,
Once the instrumentation was in order, two pulses with a peak load of
73 and 76 kips respectively, were applied. These peak loads were approx-
imately equal to those at which the failure of the connection occurred.
This time the wall endured the load, and when a new dynamic load with a
peak value equal to 80 kips was applied, the wall also withstood it.
The failure of the wall was produced by a load of 95 kips, with a
rise time of 21 ms. This time the failure was associated with a shearing
off of the compression column at its junction with the beam foundation.
This is the kind of failure that was expected according to the results
obtained in the static tests carried out on similar walls at Stanford
University. (16)
Figure 86 shows the wall after collapse. It is interesting to note
the local crushing of the concrete in the panel around the corner at which
failure occurred.
- 58 -
in
(1U
%,-0
co - 0 0 0 0- c 01 - 0
b o 000000000000 a4
0
a,v
H
E-1
0 v \0 co o\
m .- -tHH -t o
0 ,
H co~ H o e H ca cH om\
4
0 0
DO 0. 0
H O ·C- '
H
.H
Cd
4'
'
CO
'0 1o
ca 1-4
C~j
H 0
H j \0.o\ \ uj\ -- 54-
0 I-4
HO
to 4' C
oH o r-
U)
Ho o) Ho- HHoHHo o o oAHc H -0 cr\ 0
0 CD
F-4
Ef O E--4 *
v
0 4'
0
*1-
0
U)
U)
rd
o o o - o o 0 o oc 0. t"
r-I M
v 000
0 Cr
to)
0HOH0 0r- M-
000000000000 O,\,
IA O,
H r
OH H...
,H HH
,, H r-4
0)0 -C- J±
H
v Hoo
ýo
v
A .rd
*rI
IO
U- 0 O
H1 0\ e- tO CN
HM Ctri'r -Et- o C- mc % -
V
rl
r-t
E-., v
- 59 -
$4
a,
CiE44
C
C41240
·i
pj
Si
H 0oI!\ o 0 0C 01
O\ O O M
H>>cO~'j 0
0
E-4
0'Lr\o U
z;t -~t O
oz 00 0000 00000
0000
0 ir
Cd
edr
-q
o00 0 o~)\ ON'\
0
oL 66
00 000
0'68-
00
00 680666
00000
kWd
OS
*ri
• • 0 00 0 0 0 00 0 0 0 0 0
E-4 Nm C C'J
jA C% 0
O\ CNOt q lO \--IA
HH H N HA --- HH C\j
CHNNCM
E- -H
•dI -
'-•.,
C'j
b\ 0o 0nYU~ 0 b- r-ac 0 cc)
(0U j z .- t - cOc\O. r-
m'J At " m c C\j CUCU ---rIeO \O
E-4
zH .HH HAq
- 60 -
0)
*0
o
)d )
0)1 i-
(1) o
oz 000000O0O
0 0 0 0 04 06A 00
0 0
,O
r-
8.. A muH.H I I.J
0f
H
C cc) C~j a C'0 s cJ 0
C.j
*w-l
NI
H
E-j E 0 'lAO
0 0 0
00O
0
o
0
O
0 ^
Vi
0
*0
01 rS
-OH *0
Cl,
0 0
*8
.0
C--
co 000 0 0 0 CC)0 0 0 C\
0 0CY00\
\0
0
I
E-4
iM
'0d
0
V1
0 0 OO 00 m 0 0
*rl ,1
0
r•
O 1 O O O O1 O 0
itv
14 0 0 00 0 0 0 0 0 0o
4 rda
Cd H v o
91
.*H 4
20
ed
0
*) 0H
*H
*Pc m
CV 0 . 0A 00 I00 I0
t> *0
-
E-4
E-O OH eCm
%~d
V b
-t' LA
% V
\0 r- co a\ ,•
- 61 -
CHAPTER VI
THEORETICAL INVESTIGATION
1. Introduction
shows that its solution is complicated not only by the nature of the
shear wall itself, which can take many forms, but also by the necessity
deflection, and
- 62 -
If to this is added that the problem to be investigated is a dynamic one,
it is obvious that an exact mathematical solution is impossible and some
approximate methods must be developed to provide solutions of engineering
accuracy in a reasonable amount of time.
Figure 87. The stiffness and properties of the springs were obtained by
the lattice analogy method.
The fundamental concept involved in the lattice analogy is that
This predicted value was then corrected by the use of a closed type
formula which required a number of iterations.
tensile stress at the center of each segment. The stresses are then com-
- 63 -
pared to the cracking stress of concrete, to determine where and when
the first crack appears. Cracking may also take place in the tensile column.
The analyses were carried out until the principal tensile stress
at the center of a segment exceeded the cracking stress of concrete.
obvious that the areas determined for the equivalent lattice bars - for
the elastic phase - are no longer valid. Some further assumptions are
lamina representing the steel reinforcement, and the other two laminas or
faces being the concrete layer.
As long as the stresses acting in the plane of this laminated
plate are smaller than those which will produce cracks in the concrete,
the elastic isotropy of the laminated plate permits the substitution of a
be similar to that obtained for the case before cracking. The only dif-
ference will be that the area of the bars, instead of corresponding to
-66 -
purpose, lattices of two different sizes were investigated. (More com-
plete information is given in appendices A and B)
6. When the strain in a bar of the lattice network has reached the
value corresponding to the yield point stress, the force in that
bar should then be kept constant for any increase in strain.
ing, but also all the other bars, with the exception of the diagonal bar
in compression; although the horizontal and vertical bars have not yet
not possible and it is believed that the assumption made above will not
This is of course an arbitrary value, and does not mean in any way
- 67 -
It is evident that a better point for stopping the computations
would be the moment at which enough bars have yielded to make the struc-
ture a mechanism. However, the requirements for such a method were con-
sidered prohibitive due to their complexity.
1. Elastic Range:
A
Ki i
Eo (1)
which is the value obtained by Finerman (21); where Ati is the transformed
area of the bar, 1i is the length of the bar, and Ec is the modulus of
elasticity of concrete. This stiffness determines a curve of force vs.
Once the segment cracks, the stiffness of the bars is given by:
A
s
i
Ki = Es (2)
are smaller than the actual due to the assumption that the collaboration
of the concrete between the cracks could be neglected. Different
-68 -
methods in order to take into account the collaboration of the concrete,
after concrete has cracked. Following Brice (28), whose study seems to
be the most complete, the stiffness after crack can be obtained from:
tf li1 F c
Fi
A + nA
ci si
value in tension; from then on, the equation that governs the deflections
is given by:
Al.
1 F
fcmax
i s a
This equation is valid until the strain A li/li is such that the
- 69 -
F
s y
From then on, the force Fi will remain constant with increasing Ali/l
i.
Figure 90 shows schematically the curve F vs. deflection for the different
a bar starts to decrease, the force vs. deflection curve follows a line
parallel to the line OB, as indicated by line CD in the figure; until the
total deformation becomes zero -- point D. From then on, the F vs. /1i
program for the use of the digital computer Whirlwind I was undertaken by
Mr. Ho, while Mr. Calladine undertook the writing for the new IBM com-
puter. A complete information on the coding for these two high-speed
is shown in Figure 92. As seen from the figure, two extra dummy columns
and rows are added to the model for the convenience of programming.
- 70 -
Equivalent wall properties for the dynamic model are shown in Appendix A,
item V. 0.10 milliseconds was used as time interval in this computation.
For the IBM 704 computer, the wall was divided into a grid system 7 squares
by 5, each square being 9.2". The time interval was equal to 0.0375
milliseconds.
B. Results
1. From the Whirlwind I program. The results of the analysis are
XR= horizontal displacement of extreme right hand mass point in top row.
YL= vertical displacement of loaded mass point
YR= vertical displacement of extreme right hand mass point in top row.
in Figure 97 and 98. The nomenclature used in these figures is the same
as that used above.
- 71 -
CHAPTER VII
DISCUSSION OF RESULTS, GENERAL CONCLUSIONS, AND
RECOMMENDATIONS FOR FUTURE RESEARCH
A. Although in the function generator the rise time of the load was
set at 15 ms., this time varied considerably from test to test. For
small loads, the rise time oscillated around 12 ms., except for some of
the tests carried out on wall #4. In this case, the rise time was con-
siderably less - perhaps this can be attributed to some impact effect.
As the peak value of the load increased, the rise time also increased;
oscillating between 24 and 33.5 ms. at loads greater than 50 kips.
It is felt that these variations in rise time are due to the satura-
tion of the only dump valve used in the system, and it is hoped that with
the introduction of a new dump valve and the use of higher pressure, it
the small depressions and peaks are smoothed with an average curve - when
the load is small the shape is completely irregular, showing big oscilla-
- 72 -
the curve presents two definite peaks. When the peak load is larger
return to zero after the peak value was reached. A series of tests per-
formed on a reinforced concrete column after the four tests of the pre-
The cause for this irregularity seems to lie in the same factors
discussed above under 1 and 2. Above all, the saturation of the dump
valve seems to be the principal reason for the greater duration of the load
pulse.
larger than expected. This motion not only confuses the experimental
- 73 -
loading unit, because a larger displacement of the ram is required, and
II. Discussion of the Results Obtained from Tests Performed on the Walls
It is known that the dynamic response of a member being subjected
tion of the force, the duration of the load, and the particular variation
with time of load and resistance. Then, it is believed that in order to
get an idea of the shear wall's dynamic behavior from the data obtained,
given in Chapter V, the following comparisons have to be made.
A. The shape of the reaction vs. time and displacement vs. time
curves must be compared with the load-time curve. When this analysis is
completed it can be seen that in all cases the reaction and displacement
curves resemble the load curve. In fact, if the small peaks and depres-
sions of the load-time curve are smoothed out by an average curve; and if --
in some cases -- some time shifting which is probably due to defective
synchronization and calibration is accounted for; the agreement in shape
placement curves.
- 74 -
The conclusions arrived at can be justified by a quick analysis
according to the figures obtained by the IBM 704 computer for the dynam-
ic horizontal reaction (see Fig. 97), it can be seen that in the elastic
region this reaction ("H") vibrates about the static reaction, which is
equal to the applied load. However, the amplitude of this vibration is
load was always greater than 13 ms., (i.e.) that the rise time/natural
period of the fundamental mode, ratio was always larger than 2.6, it
series of tests.
B. When the values of the displacements obtained on specimen #2
same vertical movement of the supports occurs during the dynamic test
rather than during the static test -- it can be seen that as long as
wall #2 was not badly cracked by previous loads, the dynamic displace-
ment that the specimen undergoes practically coincides with that obtained
for similar static loads on wall #1. Considering that the modulus of
elasticity for the concrete in both specimens was approximately the same,
the reasons for this similarity follows from the former conclusion (i.e.)
- 75 -
ducted on a specimen built with concrete whose characteristics were
similar to those of the concrete used in specimens number three and
out in Chapter V, that the collapse of all four specimens was produced
by a defective welding between the reinforcement of the tension column
and the support plate. However, the failure of repaired wall #4 was
the beam. This type of failure agrees with that obtained in the static
obtained during the test conducted on the repaired wall #t, may be
- 76 -
a value which agrees closely with the results obtained at Stanford
University; where a similar specimen failed under a load of 71 kips.
able to resist a load higher than that endured by a similar wall being
considered:
1. An increase in the strength of the member due to the increase
ratio of the maximum deflection (just before collapse) to the yield deflec-
tion -- is an important influence in determining the resistance of a
member to dynamic loads.
peak ultimate strength for large plastic strains -- are capable of ab-
sorbing a greater amount of energy without failure, and are less liable
- 77 -
Consequently, the increased strength of the member under dynamic
factors of the order to 20 to 35% greater than the static strength seem
reasonable.
become evident:
tained from WHIRLWIND I's program, the first crack should occur at a load
were due to the abrupt weakening of the elements at cracking, under the
cracking hypothesis adopted. However, a second run was made by Mr. Calla-
dine, increasing the amount of steel in the wall and beams, retaining its
elastic properties but reducing its yield strength in such a way that the
ultimate strength per element was unchanged, and on the whole, this
- 78 -
second test gave results similar to those of the first.
A third test was also run by Mr. Calladine in order to check
the elastic solution would not be improved, but it was felt that the
The theoretical computations run on IBM 704 yield what seem to be sa-
tisfactory results up to a load of 23 kips, and those run on WHIRLWIND I
- 79 -
is so small, that no dynamic effect is apparent.
If the theoretical and experimental values for the horizontal dis-
placement of the loading point are compared, it may be seen that the re-
sults are inconsistent. For example; at a load of 23 kips WHIRLWIND'S I
city for the concrete in wall #1 was 4.5 x 106 p.s.i., while in the
obtained from test No. 3 on wall 3 and test No. 6 on wall 4, it can be
seen that the latter are of the order of 0.035 in., which is considerably
larger than the theoretical ones. The explanation for these inconsistent
results perhaps lies in the difficulties in obtaining a good evaluation
of the experimental value from the data, due to the complications in-
troduced by the displacement of the supports.
V. General Conclusions
The conclusions that can be drawn from the former discussion may be
summarized as follows:
of the system, aggravated by the extra oil flow required by the consider-
able displacement of the specimen's supports; the force-time shape of
the pulse, rise time of load, and duration of pulses given by the dynamic
- 80 -
loading machine differ from those set in and required by the function
generator.
Although this wall was extensively cracked, it was still able to resist
several blows with peak values larger than those endured by a similar
wall under static loading.
C. The theoretical analysis performed on WHIRLWIND I yields satis-
after which the lattice begins to vibrate. The cause of this oscillation
seems to be a mathematical error in the programming.
- 81 -
D. The theoretical and experimental results agree in showing an
almost complete lack of vibration. However, when the values for the
of tests in order to find the appropriate gain and the appropriate oil
and nitrogen pressures to be used for different values of the peak load.
wall:
1. Strength of concrete
2. Effect of frame
- 82 -
5. Variation of load pulse
6. Length/Height ratio of wall
7. Scale effect
grams already written is suggested, in order to find the cause for the
oscillation of the system.
a good approximation.
- 83 -
REFERENCES
- 84 -
14. Williams, H. A., Benjamin, J. R., "Investigations of Shear Walls,
Experimental and Mathematical Studies of the Behavior of Brick
Walled Bents under Static Shear Loading", Technical Report No. 2,
Part 4, Stanford University, August 1, 1953.
15. Williams, H. and Benjamin, J., "Investigation of Shear Walls,
Part 5, Prediction of the Behaviour of Plain Concrete, Reinforced
Concrete, and Brick-Walled Bents under Static Loadings", Stanford
University 1953.
16. Williams, H., and Benjamin, J., "Investigation of Shear Walls"
Part 6, Continued Experimental and Mathematical Studies of Rein-
forced Concrete Walled Bents under Static Shear Loading, Stanford
University, 1954.
17. Walter, J. K. et.al., "Investigation of Shear Walls", Part 7,
Continued Experimental and Mathematical Studies of the Behaviour
of Brick Walled Bents under Static Shear Loading, Stanford Univer-
sity, 1954.
18. Stivers, R., Benjamin, J. and Williams, H., "Investigation of
Shear Walls", Part 8, Stresses and Deflections in Reinforced
Concrete Shear Walls Containing Rectangular Openings, Stanford
University, August 1954.
19. Benjamin, J. and Williams, H., "Investigation of Shear Walls,"
Part 9, Continued Experimental and Mathematical Studies of Rein-
forced Concrete Walled Bents under Static Shear Loading, Stanford
University, September 1, 1955.
20. Benjamin, J., Williams, H., Erickson, R. and Campbell, R., "In-
vestigation of Shear Walls", Part 10, Limited Study of Brick and
Concrete Block Shear Walls with Steel Frame, Stanford University,
September 1956.
21. Finerman, Aaron, "The Theoretical Elastic Response of Shear Walls
Subjected to Dynamic Loads", Massachusetts Institute of Tech-
nology, August 1956.
22. Simpson, Howard, "A Dynamic Loading Machine", Massachusetts Insti-
tute of Technology, 1957.
23. Proceedings of the American Concrete Institute, Year 1955, p. 600.
24. Proceedings of the Conference on Building in the Atomic Age,
Massachusetts Institute of Technology, June 1952.
25. Newmark, Nathan M., "An Engineering Approach to Blast-Resistant
Design", Transactions of ASCE, Vol. 121, 1956, pp. 45-6h.
26. Guerin, A., "Traite' de Beton Arme" Tome I, p. 238, Tome II, p. 54.
27. Telemaco van Langendouck, "Calculo de Concreto Armado", Associacas
Brasileira de Cimento Portland, Vol. 1 (2nd Edition) Sao Paulo,
1954.
28. Brice, Louis Pierre, "Etude des Conditions de Formation des Fis-
sures de Glissement et de Decohesion dans les Solides", Travant,
June 1954, p. 475-506.
- 85 -
-j
,j I
~II
I-
86
8LAST -
-Rear Wall
SA
I
PLAN
crack caused by
BLAST ion of horizontal
c ked roof.
j.:~
N
FJ88
- 8w
'U
I-
½' -.
0
I
I>
Cr
10
IN CH
0cd
U)
a,
b4
0
to
4,
0
.r)
K-
K.LA_
4Y
7-
"0
H
r-4
0
Cd
0)
00 r,
o II
tt
*r4
4,
-d
0O
0l 0
i-1
H
0
rI
0\
3JlynSS3dId
I
7ý a;
a,
o
Cd
L- O
0
O
4o
E-
0
I H
0
1l
,.H
4.,-
N -t Cd
0
0
co
o0
H
r-t
0)
fi)
c-,
. ý11
*08(
c:
1I
N. N
-- ·
Figure 12 - F.ormwork and Reinforcement in Place for the
Shear Wall Specimen
7 97
Figure 13 - Walls and Cylinder, after being Cast
98
O
Q) Od
.H
-• 0) 0
-tP O G 0
4-Q3
-p
q; liw10(1)
0 0
-)0 to-I -C,
a~ 6-
) -0) 0
+3 o
'o4
ed
O mdO_C m
.H U)
LD
0 c0
cHi
+3
0
4.•- i1
-o I
-P
O
43
0
E 0
O I
Sco
catJo
,oe,
-4
99,
L
c a
V. >
-r IL
ICL
~P; 0 a
0P 35
0 0
w0 3 0 1 OCL
_143
E 0 0
C)
U) 0 U 1-
":I "'
w
Cz
00 o .,-
o oo
cc
= -a c €
E
;, -
E > 0) 0
Qu,
- , •
~0 CL
LL j0
r•• ,• :0
i
I • I,_
.. (j
i,7_° ...
-u I II ,I -
3•,"
', I II.,.
,. I - Ico _
--
4-'-- .....
v0,1'91
_ _ -_-_, - _ I
0 13
r.4.
•,OO•
4, I~
Figure 19 - View of ýontroi ranel of the Function Generator
reO3~
Figure 21 - General View of Pump Setup
1'04 'a
Figure 23 - General View of the Filter Unit
T7ME
I-C
418
toi
Ac Q siz
LL R
K
Figure 29 - General View of Instruments
I II - 11I
r-7 k
i~LiJ
Lu
41U-r Lu
& (0
U)e
t-. Z
~------c
CL
C)
0u N 0
U,
'U
-----------
-------'
'-----'
"I
LL 4 1j
1-
CL
a.~
S
LUL"
-5ý0
N,
i,
izz
Lu
I,, (,j
& I
Ltj
LIJ
LU
(LU
,,•L
/ 1 f -1-40 (
I
f-l I
JA
'~..-,
i
Y
Figure 31-(a)
H4 H2
V
H3
I
H4 SH3 V H2
I I
I I
N...~-'
Figure 31-(b)
EJ0
1111
Figure 34 - View of the Device used to Connect the
L.V.D.T. with the Specimen
i iý2
I
01
,·
a
a
Q
--
LAJ
I'M~c
Figure 37 - View of Indicator of the Ram Head Position
Id4
O
LLi
Lu
-i
CI)
5t
Lu~
U)
__
// 3 7! Fi
---
Figure 40 - View of the Restraining Strut
Figure h2 - Arrangement of Gages for LMeasuring
Deflections Under Static Load
S DIAL - DEFLECTION
SES
AR VARIABLE DIFFERENTIAL
4NSFORMER
. /
Figure 44 - Setup of Load Cells for Reactions
73.60
66.24
58.88
51.52
44.16
36.80
29.44
22.08
/4.72
7.36
;I
U)
7.36
.02 .04 .06 .08 .10 .12 .14 .16 .18 .20 .22 .24 .26
LATERAL DEFLECTION (in.)
i21
A 8
C
Figure 49 - Example of a Complete Record of a Test
(Test 6 on Wall #4)
A- Load and vertical deflection C-Vertic al reaction at support
at loading point C an d vert. def I. at support 8
B- Horizontal reaction and hori- D-Vertical reaction at support
zontal deflec. at loading pt. 8 and horiz. deflec. at sup-
port 8
L2O2
24
22
2C
18
016
10 20 30 40 50
o TIME (ms.)
- Load
-- Lc*#3
-- Lc#2
........ Lc# I
Figure 50 - Observed Load and Reactions vs Time
for Test No. 2 on Wall #2
S23
.030
.028
.026
.024
.022
.02C
I
//
.016
I
iI II
.014 IIA
II
.012
.010
.008
.006
I/-__ ___
__ _ _ I
_ /__
__
.004
.00;
TIME (milliseconds)
- HORIZONTAL DEFLECTION AT
LOADING POINT
-- HORIZONTAL DEFLECTION AT
SUPPORTS
-24
32
30
26
24
22
20
18
16
L&j
14
12
-0
-2
TIME (ms.)
.w.
.080
.076
.0 72
.068
.064
.060
.056
.052
U,
.048
.044
o .040
LU .036
.032
.028
.024
.020
.016
.012
.008
.004
.000
0
TIME (milliseconds)
- HORIZONTAL DEFLECTION AT LOADING
-- HORIZONTAL DEFLECTION AT SUPPORT
50
45
40
35
15
00
10 20 30 40 50 60 70 80 90 100
o TIME (ms.)
Load
---
-- Reactlon No. 3
.......... Reaction No. I
Figure 5h - Observed Load and Reactions vs Time for Test No. 11
on Wall #2
-27
0.
0.
0.
0.
0.
0A
0.
0.(
0 10 20 30 40 50 60 70 80
TIME (milliseconds)
-2S
60
55
50
45
40
30
25
20
15
10
10 20 30 40 50 60 70 80 90 I00
TIME (ms.)
--- Load
- Reaction No. 3
........ Reaction No. I
Figure 56 - Observed Loads and Reactions for Test No. 12 on
Wall #2
`29
0.24
0.22
0.20
0-- -
0.18
0.16
2
- Of
0.14
-t--
0.12
0.10 o-- -
0.08
0.06
0.04
-- /
--I /-
-I-!I
\N
- a
/
I
0.02
0 I o 30
a
4
TlI s 07
04E (ms o 6
-o0.02
/:23 0
t!r3O
Figure 58 - Crack Pattern of Wall #2 After a
Dynamic Load with a Peak Value
of 31,5 kips was Applied
0~
TIME (ms.)
-0 02
0.17
0.16
SVRTICof
-- V"RTICAL DEF ECTIOV AT ýUPPOAT
0.15
- RIZONTAL
0.14
0.13
0.12
0.11
0.10
0.09
0.08
0.07
r-IF--- -x - - -
0.06
0.05 --
1-.1---
0.04 I .
i-k
0.03
0.02
0.01
_ I --.
_
-
_
2*--'
S1 409 50 60 7 a
TIME (ms.)
433
15
I0
10 20 30 40
0
TIME (ms.)
4/34
0.090
0.080
0.070
0.060
0.050
Laj
_l
L4 Q040
0.030
0.020
0.010
0 /0 20 30 40 50 60
TIME (ms.)
- HORIZONTAL DEFLECTION AT LOADING POINT
VERTICAL
---- VERTICAL DEFLECTION AT SUPPORT
--- HORIZONTAL
"p.q I .1 1 b-
%ft
yj SI f-I-I ?--1-I--tI--l-II I I
(3
Lu
La
TIME (ms.)
0.15
0.14
0.13
0.12
0.11
0. 10
L 0.09
0.08
,-J 0.07
0.06
0.05
0.04
0.03
0.02
0.01
TIME (ms.)
r!37
(I)
(V)
LW I I f I ! i Ii I
Q
h
5J
rr I· * I
0-
TIME (ms.)
.19
.18
.17
.16
.15
.14
.13
.12
.11
.09
.08
.07
.06
.05
.04
.03
.02
.01
TIME (ms.)
Figure 67 - Observed Deflections vs Time for Test No. 13 on Wall #3
i3/9
__
68
64
60
56
52
48
36
32
g 28
" 24
20
16
12
o TIME (ms.)
---- Load
---- Lc No. 3
--- LcNo. 2
....-. LcNo. I
Figure 68 - Observed Load and Reactions vs Time for
Test No. 15 on Wall #3
0..
0.O
0.1
0.1
0.;
0.1
O.
0.
0.
0.
0.
0.
0.(
0(
0.4
0.4
- 0.4
- 0.(
-0.
- HORIZ. DEFLECTION AT LOADING POINT
--- VERTICAL " i t
. . ...... VERTICAL DEFLECTION AT SUPPORT
--.-- HORIZ.
ye'
- Load
--- Lc No. 3
.......... Lc No. I
Figure 70 - Observed Load and Reactions vs
Time for Test No. 16 on Wall #3
2
14
_ __
0.42
0.40
0.38
0.36
0.34
0.32
0.30
0.28
0.26
0.24
0.22
0.20
S0.18
0.16
L&J 0.14
S0.12
0.10
0.08
0.06
0.04
0.02
0 10 20 30 40 50
TIME (m s.) - HORIZ. DEFLEC. AT LOADING POINT
-----VERT. " I o
--- HORIZ. DEFLEC. AT SUPPORT
?1 43
. _|-
rr
7" A
E-4
0
,o
OO
Cd
0
*r8
(X)
C)
L
0=
0)
rrx-
Fr
- Load
Lc No. 3
---- Lc No. 2
- I .......... Lc No. I
-2
-3
-4
45
0.12
0.11
o.IQ
0.09
0.08
0.07
0.06
0.05
O
•, 0.04
0.03
LL&
0.02
0.01
- 0.01
- 0.02
- 0.03
- nn
26
24
22
20
/B
16
'
L14
c 12
00
8
-2
TIME (ms.)
.97?
1-47
0.19
0.18
0.17
0.16
0./15
0.14
0.13
0.12
0.11
0.10
0.09
I 0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
- 0.01
-n fl
38
36
34
32
30
28
26
24
22
20
18
16
12
10
- 2
- 4
i141'
O.l9
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
O. 10
0.09
0.08
Lai
S0.06
0.05
0.04
0.03
0.02
0.01
TIME (ms.)
- HORIZ. DEFLECTION AT LOADING POINT
........ VERTICAL DEFLECTION AT LOADING POINT
HORIZ. DEFLECTION AT SUPPORT
--- VERTICAL DEFLECTION AT SUPPORT
-"` 150
50
47.5
45
42.5
40
375
35
32.5
30
25
22.5
L15
20
Q S17.5
15
IO
75
2.5
- 2.5
-5
Ql
Lt
TIME (ms.)
- HORIZ. DEFLECTION AT LOADING POINT
........ VERTICAL It to ot
•-•- HORIZ. DEFLECTION AT SUPPORT
--- VERTICAL
°° .
60
56
52
48
44
40
36
32
28
24
20
16
12
-4
-8
Figure 81 - Observed Load and Reactions vs Time for Test No. 7 on Wall #4
/ -3
All
0. 3
0.31
0.31,
0.3(
0.21
0.24
0.2,
0.2,
0.2(
O.11
O. IE
0.10
0.I'
0.11
0.1(
0.0ý
0.01
0.04
0.0'
10 20 30 40 50 60 80
TIME (ms.)
- HORIZ. DEFLECTION AT LOADING POINT
........ VERTICAL
-- HORIZ. DEFLECTION AT SUPPORT
---- VERTICAL
-54
__
elu
76
72
68
64
60
56
52
48
44
40
S36
Q 32
Q 28
-J 24
20
16
12
-4
-8
- 10
O 10 20 30
TIME (ms.)
1 L
3
Figure 7(a) - Actual Wall
H L
1I
!
L---------
K
I I
S59
a,
a,
(o
0
-d
0
a,
D)
0cd 0
00oH
o0
H
o)l O C
z 0)
0
OH,
Q: 0)
*H r-t -)
o0
O
* COS
(A- k
*Hjc
* ." /
P (Kips)
53
t {ms.)
O0
I lx\
/ / \
I
\/ /\LV \I/
i X\
\/
7 /V• I
""-7.
0
.H
q) 04,
O
0
-Hl
0 tO
0 0 0 0
(001)) dPUO H3
(sd.I) A c A
U)
6
;'16
Vj
*...
IGG•
46
44
42
40
38
36
34
32
0 3C
224
I(
I
I1
167
340
320
300
280
260
240
220
200
180
160
140
120
100
80
60
40
20
0
TIME (each interval = .0375 ms.)
(I
APPENDIX A
NOMENCLATURE
direction, etc.
qn = displacement at time tn .
qn+l =
displacement at time tn+ '
1
qn-1 =
displacement at time tn-l'
- 169 -
4n+1 velocity of the mass point at time tn+1 in that direction, etc.
qn+l = acceleration of the mass point at time tn+1 in that direction, etc.
A. Dynamic Analogy
According to the lattice analogy method, the wall is replaced
1) The deformations of the units must be the same under direct uniform
stress.
2) The deformation must be the same under the Poisson's ratio effect.
3) The deformation must be the same under a pure shear loading condition.
4) The deformation must be the same under a pure moment loading condition.
- 17 -
was shown in Figure 87(b). The continuous distribution of the actual
Ki = 3/4-t. Ec (A-1)
,e
K (3/8 t +-
a
) Ec (A-2)
Kd = 3/8 t. Ec (A-3)
B. Equation of Motion
The equation of motion for each mass point can be developed from
the dynamic equilibrium as:
P + R - m(' (A-3)
bar forces at the mass point can be derived as follows and according to
Figure A-2. +X
I0
tS
y Figure A-2 Typical Interior Mass.
- i 71 -
= K1
x - x d] (A-4)
= K2 (A-5)
-K 3 (xi - xa) + (Yi - Ya)] (A-6)
K4
[(x - xf) + (Yf - Yl (A-7)
= K5
= K (x - xi ) + (Yl - Yc) (A-8)
half the actual stiffness) is implied and only components of force rather
than total force are considered. The two equations defining the horizon-
tal and vertical motion of the interior mass point are:
Px + Rx -m(c) = 0 (A-12)
P + R -m() = 0 (A-13)
Y Y
where
R = - Fl + F2 - F3 - F4 + + F6 (A-14)
R = - F + F - F + F4 - + F6
y 7 8 3 h
C. Numerical Integration
The open type formula used to predict the value in the succeed-
- 172 -
2
= displacement at time t
displacement at time t
n
= displacement at time t
n-1
be expressed as
3E
rx 8- (3Ex + C ) (A-19)
3E
yl -- (3 E + 6x )
(A-20)
3E
(A-21)
-173--
0~ rb
a b
C
r+y
Figure A-3. Typical Plate Segment
x 2a S(axb 1 - ) +
a) · (x-~
(xd X )(A-22)
[(x
X -x) + (X- Xb) + (yb Ya
+ (Y - Yc)] (A-2h)
In general the first crack may occur at the center of any segment or in
the most highly stressed tension column. The stresses at the tensile column
ing has occurred, assuming 450 crack, all bars except the diagonal which
of the wall unless the bar is subjected to compressive force. For the
diagonal which is parallel to the crack, bar area will be reduced only
- 174 -
The major operations of the program are as follows.
A). "Compute load P for use in acceleration impulse equation"
n
decided to store the value of load for each time interval in the computer
memories. Instead of computing the load from formulas, the computer will
pick up the proper value of the applied load from the memories at each
time interval.
B). "Predict the deflection qn+1 for each mass point from the accelera-
where
an
Pn Rn
n M M
For the loaded mass point, Pn can be picked up from the computer memories
while for all other mass points Pn will be equal to zero. At the first
compute the value qn+l for each mass point in the y direction.
C). "From the predicted values of n+l calculate the resistances Rn+1 for
The spring forces between the masses are calculated from the
for each mass point can be obtained from equations (A-14) and (A-15).
- 175 -
The analysis involved is rather tedious after cracking has
occurred. For convenience in programming, the analysis is broken down
segment.
plastic shortening.
-. 176 -
FORCE
LONGATION
Aflwtr
I
I
I
I
I
I b'
IA
ELONGATION
- 177 -
ij - represents the force-elongation curve of the cracked bar. The
If plastic shortening has occurred before cracking starts, the force elon-
gation curves will have the same shape except that the origin "a" will
move to point fal" as shown in Figure A-5. For the diagonal which is
parallel to the crack, the cracking state (bc) in Figure A-h) will depend
on the tensile force at the bar instead of the stress at the center of
the segment.
For lattice bar at the edge, the outer spring will represent
the equivalent resistance force of the bounding beam. For each lattice
bar, the following storages are required from the computer memories.
lattice bar.
d - storage to store the index for the edge spring indicating whether
- 178 -
In the following discussion tensile forces are taken as posi-
a) Assuming no crack has occurred compute bar force between the two
horizontal masses from the equation
F = KL xb - a - "Kink" (compression)
required.
2) If newly plastic, reduce the bar force to the allowable value.
"kink" (compression).
sary. For edge spring, compare the spring force with the
able value.
iii) if already plastic since the last time interval, reduce
lattice bar except that the system concerned is in the vertical direction.
a) Assuming no crack has occurred compute the diagonal bar force from
the equation (see Figure A-6)
- 1 80- -
U-
- 181 -
F [xd - Xa) (y -a) -"kink" (compression)
required.
ii) If newly plastic, reduct the bar force to the allowable value.
iii) If already plastic since the last time interval, reduce the
"kink" (compression).
d) If the bar force is in tension and crack has occurred in the seg-
bar force with the cracking tensile force for the bar.
- 182--
(1) If still remains in elastic condition, no further
correction is required.
value.
lattice bars.
qn+1 for each mass point from the linear acceleration equation."
2
qn+l = n + b (2
+ +" +l)
P R
n + n and
Pn+1nl Rn+1
qn+1 M M
F). "Calculate the new values of resistance Rn+ 1 for each mass point from
G). "To store the values qn+l' +1'' n+l for use in the next time interval."
- 183--
H). "Determine the stresses at the center of all segments: Compare these
1 t -1 xy where + 90
2 an 0o- 0
y x
I). "Compute the stresses at the tensile column and compare these values
with the cracking stress of concrete".
J). 'With the values of resistance R+ 1 and load P predict the deflec-
tion qn+2 for each mass point from the acceleration impulse equation."
i.e., start a new cycle of the above operations for the next
time interval.
K). "Repeat the above operations until computer stops at certain specified
1) Time
2) Applied Load
- 184-.
The direction and location of the cracks are also printed out at the last
time interval to give a general picture of the cracked wall.
A. General
Two systems of instructions are involved in the present high
speed digital computer, Whirlwind I.
1) Whirlwind System. This system consists of the fundamental
instructions to the computer. It is generally used in the counting system
and used as index (e.g. indicating crack or plastic condition, etc.)
B. Storage Arrangement
Comprehensive System
Registers xl Horizontal displacements x
yl Vertical displacements y
R
rl Horizontal resistances _x
R
r2 Vertical resistances -Z
d3 )
"kink" (compression) for diagonals (8 = -645
q3 Applied loads
Whirlwind System
Registers e4 Crack indexes for segments and bounding beams
a4 Plastic indexes for lower springs
- 186-
O 2 4 0 2
24 26 28 30
l I'l A 10 12 14
1]2 22
32 34 36 38
18 20 22
rl, r2, x1,x2, yl, y2 40 42 zl,z2 44 46
6 8 /0
12 14 16
e2, e3 e5, al, a2, a3
4 8 12
6 /0 14
0 2 41 M
CCj
1"c
It
6 B 0/0
d2, d4
n-2 =I h columns
- 187 -
0 I 3 4
6 7 8 9
1L3 4 5
t0 II 12 13 14
15 16 17 18 19
6 7 8
e4 ah, a5
2 4 6
3 5 7
bh, b5 d6, d8
\2
, d7
3 K4 5
d~, d7
- 188 -
d7 Crack indexes for diagonals (0 = -45c)
d8 Crack indexes for diagonals ( 8 = +459 )
C. Field Arrangement
The computer core memory consists of six fields each of 1024
the Auxiliary Drum and will be distributed into six fields in the follow-
ing order:
Step A
- 189- .
START
STOP
- 190 -
Step B
Integration Routine. Predict qn+l for each mass point from the
acceleration impulse equation. Proceed to Step C.
step C
Resistance Routine. Calculate Rn+1 from the predicted values
each mass point from the linear acceleration equation. Proceed to Step
C to recorrect qn+l" After performing this complete operation four times
proceed to Step F.
Print Out Subroutine. Print out the results of this time inter-
val on the oscilloscope. Return to Step F.
StepH
Tensile Stress Computation. Compute the stresses at center of
all segments. If cracking has taken place compute direction of the crack.
Proceed to Step I.
- ,191- -
Step I
stop the computer and print out results. Otherwise, proceed to Step B.
1) Load Computation
P
ml Compute - for next time interval. Print out results and stop the
m2 Compute
4 P
m3 Compute P ( = -).
1 Used in the first time interval only.
2) Integration Routine
n3 A simplified routine for the first time interval to skip the un-
necessary operations.
-192 -
nl Reset n2.
n16 Obtain resistance from the resistance routine.
n18 Used in the fourth iteration only. Store n+1 (h) and "+1I
n19 Used in the fourth iteration only. Additional instructions for
3) Resistance Routine
a) Horizontal Bar
b) Vertical Bar
- 193 --
bll Reset for next interior column.
bl3 Reset the whole operation. Change field and proceed to compute forces
dl2 Counter for the bar, check column and row. After completing
dl5 Reset the whole operation. Change field and proceed to compute
resistances.
d) Resistance Computation
R R
k2 Compute x and - at left upper corner.
M M
k3 Compute __ and a for interior mass point at upper edge.
M M
kh Counter for mass point at upper edge.
R
k5 Compute Rx and at right upper corner.
M M
k6 Reset k3 for next mass point.
uM M
- 194--
k10 Counter for the typical interior mass point, check column.
kl9 Reset the whole operation. Change field and leave the resistance
routine.
- 195--
h3 Reset the whole routine.
pl LSR OS4 SCOPE MRA DECIMAL FOMAT SUBROUTINE.
6) Stopping Device
glO Stop the computer when deflection exceeds the specified value.
F. Preparation of Tapes
of Mr. Shui Ho, "The Theoretical Analysis for the Dynamic Behavior of
- 196--
V. EQUIVALENT WALL PROPERTIES FOR THE DYNAMIC MODEL
- 197--
E = 3000 k.s.i.
n = 10
tw = t 1 + (n-1) Pw = 2 1 + 9 x 0.00255102 = 2.0459184 in
Bar areas:
Al (interior) = 3/8 x a x tw
Interior bar = 2A1 = 3/4 x a x tw
- 19 0-1.
Effective stiffnesses (concrete):
Stiffnesses (steel):
= 1090.9091 k/in
Edge spring 22 x 4 x 0.2 x 30000
-=
= 4 k.s.i.
Allowable compressive forces (concrete(: fc' -- 000 p.s.i.
= 3 x 22 x 2.0559184
= 135.0306144 k
Exterior bar = 67.5153072 + 39.585203 x L
= 225.8561192 k
= 0.4 k.s.i.
Allowable tensile forces (concrete): ft'
= 15.8340812 k
- 199--
Bottom edge - 87.2261477 x 0.4
= 34.8904591 k
Effective diagonal bar = (3/8 x a x tw) x 0.4
= 6.7515307 k
= 39-3 x 1.33 = 52.229 k.s.i.
Allowable tensile forces (steel): Panel - f'
Y
Frame - f' = 47 x 1.33 = 62.51 k.s.i.
y
Edge spring = 4 x 0.2 x 62.51
= 5o.008 k
Bottom spring = 50.008 k
The general programming and coding for IBM 704 was undertaken
previously.
NOMENCLATURE
n Es
E
= Young Modulus for Steel/ Y.M. for Concrete.
c
- 201 -
bAS
Figure B-1
d2at dld2t 2
2
-- + (A+ As2) a (m-
A. Uncracked Wall
from the predicted values of qn+1 (see item II, part C of Appendix A)
the operator technique was used. This technique basically consists in
the following:
- 209 -
9--
I
I
.@ y
8
X X x
2a
7
X
m M
X b '1*
Figure B-2
Ad E in direction 7-9
xg9 /a
x 9 /a
Al E in direction 8-9
A E+ 9 - in direction 9-8
fJa1 Ad E
1 + 3/16 x Et 9 3/16 x 9 Et - - X9 B
3 3/16 x Et = + x9 + 3/16 x Et SX9+
4 3/4 x9 Et = + 2x a
3/1 6 X9 Et = + x 9 - 3/16 x 9 Et S- x9
5
3/16 x 9 Et = + x9 + 3/16 x9 Et
7
8 3/h x 9 Et = + 2x9 a
9 -9/h x9 Et = x9
where a "3/8 Et, PB 3/16 Et, (a+ P)
X= .- - 9/16 Et.
- 203 -
A similar set of reactions can be found for a displacement of point (9)
in the y-direction.
The whole wall system may now be analyzed by superimposing
at each mass point can be built up by the use of the above operation
Figure B-3 and B-4 show the complete operations for displace-
ments in the x and y directions. The forces computed are divided by
the corresponding masses to give the desired accelerations.
mass of the central element MN, thus giving the accelerations directly.
MN
the mass of the cor-
responding element
B. Cracked Wall
0 crack across an element has
The effect of a 45 already been
discussed in Chapter VI and Appendix A.
mass points, the system is first analyzed as if there were no cracks, and
computed in the bars by the forces resulting from an analysis of the bars
that are assumed to be cracked.
- 204 -
S=O +d 6 AEE
- 206 -
d =bar
dp =plo,
dy =defi
de = d-
p = elo1
del
(contraction) (extension)
(no plastic
set)
No (some
plasticprevious
set)
(no more
yield: bar yielding)
elastic)
yield)
COMPUTE
i --crs x dp
ADD TO COMPUTED
ELASTIC FORCE
OUT
Figure B-5 Flow diagram for the programme which computes the
difference in force due to cracking
- 207 -
is shown in Figure B-5 and the following is a brief explanation of the
.vigure Bt-o
force assuming the bar was elastic, the value obtained would be that
- 208 -
F~IC(S
EFLECTION
Figure B-7
Figure B-8
- 209--
b)If[ ce - y] ispositive we have to consider two new
possibilities, depending on whether ce is positive or negative.
i) If 6( is negative, we have the situation shown in Figure
Pe = (-a
s
x 6 y ) it is necessary to add to the computed
Id I- c3
Figure B-9
to obtain the value of the plastic set for the next step
- 210 -
it is necessary to add to cp the value [IeI - Sy]
Figure B-10
II. THE ITERATIVE SOLUTION OF THE EQUATIONS OF MOTION OF THE POINT MASSES
q+i = 2% - %- + hi n (B-1)
Linear Acceleration Equation.
2
= +'qn+1) (B-2)
qn+l n n+ h + (2 B
Velocity Equation.
- 21- -
is then used to compute the accelerations qn+l by use of the processes
are used.
Compute
h/2 "-1n+ + n- n
(B-3)
Compute
2qn 1 n-1 + h2
n n+l
(B-i)
Compute
h2
3T 4 +4n h +qn
h2 ..
%+L 6 %+i =b
AZ I
Jrom Deflections
qn+1 compute acceler-
3 times
ations q'n+l
Compute
b + h2 /6 n+l =n+ out
Figure B-11
- 212 -
III. PROGRAM FOR THE IBM 704 BASED ON SCHEMATIC FLOW DIAGRAM
A. Key to the Overall Flow Diagr
Dump Stop.
Num 1 : Reserves all storage space used: the size of the matrices being
Orig.: Fills in with -0 the blocks which will contain the amounts of
Rout : Computes n+l from qn, assuming the wall uncracked and of uni-
CF1 : Checks for the last iteration of the current time interval. If
the iterative procedure is over, control is transferred to CF2.
- 213--
Bound : Modifies qn+l to take account of the additional mass of the
Stres : Computes the principal tensile stress in each panel of the wall
and in the edge beams. If the breaking stress is reached, a
Mast : Master control. Sets the force for the next time interval.
PRO : Prints out the sequence of cracking and the angles of the wall
cracks.
CATCH Current results are printed out when CATCH = 1. Any new crack
puts CATCH = 1.
CUT Results are printed out when CUT = 0. Each successive time in-
TEST +1 or -1. When positive, the routines deal with forces, velo-
cities and accelerations in the x-direction; when negative, in
the y-direction.
the computations of the first time interval, +2 during the second, etc.
TCO +1 or -1. When TIM is odd, TCO is +1
- 215--