2015 Contents and Preliminary Pages
2015 Contents and Preliminary Pages
Brian W. Totterdill
A catalogue record for this book is available from the British Library
This second edition of the FIDIC Users’ Guide has been extended to include
the Conditions of Contract for Plant and Design-Build, known as the
1999 Yellow Book. It also reviews the other FIDIC Contracts which have
been published since the first edition was written, together with further
discussion based on experience with the practical use of the 1999
Contracts.
During 2005 FIDIC published the Multilateral Development Banks
Harmonised Conditions of Contract for Construction, commonly known as
the MDB Edition. This Contract has been prepared in conjunction with
The World Bank and a group of Multilateral Development Banks and is
included in their procurement documents. The MDB Edition includes
some significant changes to the Conditions of Contract for Construction
and is reviewed in Part 4 of this book.
Since the publication of the first edition there has been an increased use
of the 1999 FIDIC Contracts. The Plant and Design-Build Contract has
become popular, particularly with Employers considering Contractor
design for water-related and environmental projects. This Contract is
very similar in layout and content to the Contract for Construction but
differs in detail due to the different requirements for Contractor design
rather than Employer design and the greater emphasis on electrical and
mechanical plant. These differences are extremely important and
require detailed study when deciding which Contract to use and when
preparing and administering the Contract. Hence this second edition
includes a detailed comparison between the Red and Yellow Books and
a guide to the differences at each Sub-Clause of the Plant and Design-
Build Contract.
Also, since the publication of the first edition, the European Inter-
national Contractors (EIC) have published a very useful series of EIC
Contractor’s Guides to the different FIDIC Contracts. I must acknowledge
the assistance I have received from these Guides, not just in under-
standing the Contractor’s point of view, but also from their suggestions
that potential disputes could be avoided by clarification of the meaning
iii
iv
vi
5 Flow charts 46
Fig. 1 Time periods in the Conditions of Contract 47
Fig. 2 Progress requirements 49
Fig. 3 Errors in Employer’s requirements (YB only) 51
Fig. 4 Design procedures (YB only) 52
Fig. 5 Workmanship procedures 53
Fig. 6 Procedures at Completion of Works 54
Fig. 7 Procedures during Defects Notification Period 55
Fig. 8 Procedures for advance payment 56
Fig. 9 Payment procedures 57
Fig. 10 Procedures for payment at Completion of Works 58
Fig. 11 Procedures for final payment 59
Fig. 12 Claims by the Contractor 60
Fig. 13 Claims by the Employer 62
Fig. 14 Procedures for disputes 63
6 Introduction to Part 2 67
Index 389