Project Report
Project Report
On
Submitted by
Guided by
Prof.Vinayak Kale
CERTIFICATE
This is to certify that the following student has satisfactorily carried out the seminar
work entitled “ ”. This work is being submitted for the award of degree of Master of
Civil Engineering (Construction & Management). It is submitted in the partial
fulfillment of the prescribed syllabus of Savitribai Phule Pune University, Pune for
the academic year 2023 – 2024.
Examination Seat No. Name of the Student
Vasudha Ninad Jadhav
Prof.Vinayak Kale
(Guide)
Dr. Shruti Wadalkar Dr. Deepa A. Joshi Dr. Lalit Kumar Wadhwa
(P.G. Coordinator) (H.O.D.) (Principal)
External Examiner
ACKNOWLEDGEMENT
I hereby take this opportunity to express my profound thanks and deep sense of
gratitude towards my guide, Prof.Vinayak Kale Associate Professor, Department of
Civil Engineering. He gave me a precious time from his busy schedule & his valuable
guidance has been a constant encouragement.
I would also like to thank Dr. Lalit Kumar Wadhwa , Principal, Dr. Deepa A. Joshi,
Head of the Department of Civil Engineering, and the faculty of the Department of
Civil Engineering, whose constant encouragement and expert guidance was
instrumental in the completion of this seminar work.
Let me, at the end, express gratitude to all those from whom I received co-operation,
help & motivation during seminar work.
Name of student
Vasudha Jadhav
ACKNOWLEDGEMENT iii
SYNOPSIS iv
NOTATIONS vi
LIST OF TABLES vii
LIST OF FIGURES viii
LIST OF GRAPHS ix
CONTENTS
2. LITERATURE REVIEW
4. CASE STUDY
5. CONCLUSIONS
LIST OF FIGURES
Literature Review
A) Aibinu, A. A. and Jagboro, G. O. ,
G) N.Hamzah, M. A. Khoiry,
Arshad, W. H. W. Badaruzzaman, and N. M. Tawil“
Identification of the causes of construction delay in
Malaysia ”.International journal of civil,
environmental, structural, construction and
architectural engineering , Vol. 6, No. 12, 2012. N.
Hamzahet. al. was identified 34 causes of construction
delay have been determined and 24 have been selected
using rasch model analysis. He was identify causes of
delay in Malaysian construction industries based on
previous research also to illuminate unwanted factors
on the basis of rasch model method.He was concluded
that the improvement of delay factors is not only
limited to technical factors, but also factors from the
project management perspective.Both from the
processes involved and influence of human attitudes,
mentality, skills and behaviour.
CONSTRUCTION DELAYS
TYPES OF DELAYS:
Compensable Delays
A compensable delay is one where there’s going to be some
compensation involved for the delay to the project. That means that
the owner or contractor is liable for a extension of time or cost
compensation or both. The cost compensation is to account for
damages or extra costs associated with the delay.
Concurrent Delays
There are many moving parts between an owner and a contractor
(and subs or suppliers) on a construction project and, at times, a
concurrent delay can occur. This type of schedule delay happens
when 2 or more parties are at fault. The complexity here lies in
determining to what extent each party contributed to the delay.
CAUSES OF DELAYS
Effects of Delay
With the help of MSP schedule that will be prepare for the
project according to the information collected from
the organization. Before preparing the schedule initially different
activities are identified with the help of data given by the
organization and resources required for the project by rate
analysis.