Lecture 09
Lecture 09
Topics to be Covered:
- Present Worth (PW) and Annual Worth (AW) Comparisons
- Comparison of Alternatives with Unequal Lives
- Payback Period
1 2
Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)
Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)
1
Repeated indefinitely Payback Period
assumption (AW method) - It is a rough estimate of the time it takes for an investment
to pay for itself when the interest rate is assumed to be zero
z There is a more convenient approach for an annual - It should be used as a preliminary filter rather than a sole criterion
worth comparison of projects of unequal lives if it for evaluating projects.
can be assumed that the alternatives are repeated
Payback period = (first cost)/(annual savings)
indefinitely.
z Since the project would repeat indefinitely, its Example 4.8 (p. 103):
annual costs would remain the same no matter A project with initial cost $5,000 and annual savings of $2,000.
how many times it is repeated, it is not necessary to
- Assuming that the savings occur over the whole year:
determine the LCM of the service lives.
Payback period = $5,000/$2,000 = 2.5 years
z The AW can be assessed for whatever time period
is most convenient for each alternative. - Assuming that the savings occur at the end of the year:
Payback period = 3 years
5 6
Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)
Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)
2
Discounted Payback Period Recommended Problems
The present worth of each year’s savings is subtracted from
the first cost until the first cost is diminished to zero.
Problems: 4.1, 4.9, 4.13, 4.17, 4.25 & 4.42
Example (p. 104):
A project with initial cost $5000 and annual savings of $2000. If the
interest rate is 10%, the present worth of savings would be:
Year PW Cumulative
1 $2,000(P/F,10%,1)=$1,818 $1,818
2 $2,000(P/F,10%,2)=$1,653 $3,471
3 $2,000(P/F,10%,3)=$1,503 $4,974
4 $2,000(P/F,10%,4)=$1,366 $6,340
Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)