0% found this document useful (0 votes)
63 views

09 Project Risk Management

The document discusses project risk management and the importance of planning for risk management. It describes the inputs, tools and techniques, and output of the plan risk management process. Key aspects covered include defining risk management procedures and approaches, and developing a risk management plan.

Uploaded by

BJ Swamy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views

09 Project Risk Management

The document discusses project risk management and the importance of planning for risk management. It describes the inputs, tools and techniques, and output of the plan risk management process. Key aspects covered include defining risk management procedures and approaches, and developing a risk management plan.

Uploaded by

BJ Swamy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 117

®

PMP Exam Preparation Course

Project Risk Management

1
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Project Risk Management


 Risk is everywhere !!!
 From driving a car to parachuting, its’ inherent in the activities
we choose.
 Within a project, risk are unplanned events or conditions
that can have a positive or negative effect on its success.
 Not all risks are bad, but almost all are seen as threat.

2
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Project Risk Management


 Positives risks are called opportunities.

 For project managers, risk can mean failure, but the reward
can mean a time or cost savings, as well as other benefits.

 Risk management is the process in which the project


manager and project team identify project risks, analyze and
rank them, and determine what actions, if any, need to be
taken to avert these threats.
3
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

The Importance of Project Risk Management

 Project risk management is the art and science of identifying,


analyzing, and responding to risk throughout the life of a project and
in the best interests of meeting project objectives

 Risk management is often overlooked in projects, but it can help


improve project success by helping select good projects, determining
project scope, and developing realistic estimates

4
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Project Risk Management Processes


1. Plan Risk Management : deciding how to approach and plan the risk
management activities for the project
2. Identify Risks : determining which risks are likely to affect a project and
documenting the characteristics of each
3. Perform Qualitative risk analysis: prioritizing risks for further analysis or action
based by assessing and combining their probability of occurrence and impact
4. Perform Quantitative risk analysis: numerically estimating the effects of the
identified risks on overall project objectives
5. Plan Risk Responses: taking steps to enhance opportunities and reduce
threats to meeting project objectives
6. Monitor and Control Risks : the process of implementing risk response plans ,
monitoring identified and residual risks, identifying new risks, and evaluating the
effectiveness of risk strategies throughout the life of the project

5
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Project Risk Management Processes


Risk Management
Planning
Risk
Identification

Risk Response Risk


Monitoring and Analysis
Control

Risk Response
Planning
6
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.1 Plan Risk Management

 The main output of risk management planning is a risk management


plan—a plan that documents the procedures for managing risk
throughout a project

 The project team should review project documents and understand


the organization’s and the sponsor’s approaches to risk

 The level of detail will vary with the needs of the project

7
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.1 Plan Risk Management

Inputs Tools & Techniques Outputs

1. Project scope statement 1. Planning meetings and 1. Risk management plan


2. Cost management plan analysis
3. Schedule Management Plan
4. Communications
Management Plan
5. Enterprise environmental
factors
6. Organizational process assets

8
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Plan Risk Management Data Flow Diagram

9
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Planning for Risk Management


 Risk management planning is about making decisions.

 The risk management process is related to the scope of the


project, the priority of the project within the performing
organization, and the impact of the project deliverables.

 It’s important to complete risk management planning in order


to successfully manage, plan for, analyze, and react to
identified risks.

10
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.1 Plan Risk Management : Inputs


1. Project Scope Statement : provides a clear sense of the range of possibilities
associated with the project and its deliverables and establishes the framework
for how significant the risk management effort may ultimately become

2. Cost Management Plan : defines how risk budgets , contingencies , and


management reserves will be reported and accessed .

3. Schedule Management Plan : defines how schedule contingencies will be


reported and assessed .

4. Communications Management Plan : defines the interactions that will occur


on the project, and determines who will be available to share information on
various risks and responses at different times ( and locations )

11
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.1 Plan Risk Management : Inputs


5. Enterprise Environmental Factors : That can influence this process
include, but are not limited to risk attitudes and tolerances that describe the
degree of risk that an organization will stand
 Examining Stakeholder Tolerance : Depending on the project, the
conditions, and the potential for loss or reward, stakeholders will have
differing tolerances for risk.

 Consider a project to install new medical equipment in a hospital; there’s


little room for acceptance of errors because life and death are on the line.

 A person’s willingness to accept risk is known as the utility function (Risk


Tolerance).
12
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.1 Plan Risk Management : Inputs


6. Organizational Process Assets : that might be useful in this process include ,
but are not limited to :
 Risk Categories
 Common Definitions of concepts and terms
 Risk statement formats
 Standard templates
 Roles and responsibilities , authority levels for decision making
 Lessons learned and stakeholder registers .

Relying on Risk Management Policies :


 Organizations often have a predefined approach to risk management.
 The policies can define the activities to initiate, plan, and respond to risk.
 Risk management policies are considered part of the organizational
process assets. 13
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.1 Plan Risk Management : Tools & Techniques


1. Planning Meetings and Analysis
 Through planning meetings, the risk management plan is created.

 Risk Management plan templates, performing organization policies,


and the risk tolerance level of the stakeholders aid the creation of
the risk management plan.

 Attendees should include:


 The project manager, project team leaders, key stakeholders,
personnel specific to risk management or any other person or
authority involved or who have input required for the risk
management processes.
14
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.1 Plan Risk Management : Output

1. Risk Management Plan

 Methodology

 Roles and responsibilities

 Budget and schedule

 Risk categories

 Risk probability and impact

 Risk documentation : revised stakeholder’s tolerances, reporting formats and


tracking 15
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Examining the Risk Management Plan


 The risk management plan is responsible for
determining:
 How risk will be identified
 How quantitative analysis will be completed
 How qualitative analysis will be completed
 How risk response planning will happen
 How risks will be monitored
 How ongoing risk management activities will happen throughout
the project life cycle

16
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Methodology
 The methodology is concerned with how the risk
management processes will take place. The methodology
asks the following:
 What tools are available to use for risk management?
 What approaches are acceptable within the performing organization?
 What data sources can be accessed and used for risk management?
 What approach is best for the project type, and the phase of the project,
and which is most appropriate given the conditions of the project?
 How much flexibility is available for the project given the conditions, the
timeframe, and the project budget?

17
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Roles and Responsibilities


 The roles and responsibilities identify the groups and
individuals that will participate in the leadership and
support of each of the risk management activities within
the project plan.

 In some instances, risk management teams outside of


the project team may have a more realistic, unbiased
approach to the risk identification, impact, and overall
risk management needs than the actual project team.

18
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Budgeting

 Based on the size, impact, and priority of the project, a budget may
need to be established for the project’s risk management activities.

 A project with high priority and no budget allotment for risk


management activities may face uncertain times ahead.

 A realistic dollar amount is needed for risk management activities if


the project is to be successful.

19
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Timing /Scheduling
 The risk management process needs a schedule to
determine how often and when risk management
activities should happen throughout the project.
 If risk management activities should happen throughout
the project, then the project could be delayed because
of the time needed to identify, assess, and respond to
the risks.
 A realistic schedule should be developed early in the
project to accommodate risks, risk analysis, and risk
reaction.
20
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Analysis Scoring - Definitions of risk


probability and impact & probability impact matrix
 Prior to beginning quantitative and qualitative analysis, a
clearly defined scoring system and interpretation of the
scoring system must be in place.

 Altering the scoring process during risk analysis – or


from analysis to analysis – can skew the seriousness of
a risk, its impact, and the effect of the risk on the
project.

21
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Categories
 Based on the nature of the work, there should be
identified categories of risks within the project.
 RBS is one approach to identifying the risk categories.

22
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Sample RBS

23
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.2 Identify Risks


 Risk identification is the process of identifying the risks
and then documenting how their presence can affect the
project.
 Risk identification is an iterative process and can be
completed by the project manager, the project team,
and a risk management team.
 In some instances, stakeholders and even people
outside of the project can complete additional waves of
risk identification.
24
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.2 Identify Risks

Inputs Tools & Techniques Outputs

1. Risk management plan 1. Documentation reviews 1. Risk register


2. Activity Cost Estimates 2. Information gathering techniques
3. Activity Duration Estimates 3. Checklist analysis
4. Scope baseline 4. Assumptions analysis
5. Stakeholder register 5. Diagramming techniques
6. Cost management Plan 6. SWOT analysis
7. Schedule management plan 7. Expert Judgement
8. Quality management plan
9. Project documents
10. Enterprise environmental factors
11. Organizational process assets

25
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Identify Risks Data


Flow Diagram

26
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.2 Identify Risks : Inputs


1. Risk Management Plan :The risk management plan is one of the key
inputs to the risk identification process.
2. Activity Cost Estimates
3. Activity Duration Estimates
4. Scope Baseline
5. Stakeholder Register
6. Cost Management Plan
7. Schedule Management Plan
8. Quality Management Plan

27
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.2 Identify Risks : Inputs

9. Project Documents : that can be useful in this process, include , but are not
limited to :
 Assumptions Log

 Work performance reports

 Earned value reports

 Network diagrams, baselines and other project information proven to be valuable in


identifying risks

10. Enterprise Environmental Factors : include, but are not limited to :


 Published information, academic studies, published checklists ,benchmarking, industry
studies, and risk attitudes

11. Organizational Process Assets : Project files ,organizational and project


process controls, Risk statement templates, and lessons learned .
28
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.2 Identify Risks – Tools & Techniques


 Risk identification should be a methodical, planned
approach.
 A systematic, scientific approach is best.
1. Reviewing Project Documents
 The project plan, scope, and other project files should be reviewed.
 Constraints and assumptions should be reviewed, considered, and
analyzed for risks.
 This structure review takes a very broad look at the project plan,
the scope, and the activities defined within the project.

29
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.2 Identify Risks – Tools & Techniques

2. Information Gathering Techniques

 Brainstorming

 Delphi Technique

 Interviewing

 Root Cause Analysis

30
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Brainstorming the Project


 Brainstorming is likely the most common approach to risk
identification.
 It’s usually completed together as a project team to identify
the risks within the project.
 A multidisciplinary team, hosted by a project facilitator, can
also complete brainstorming.
 This approach can include subject matter experts, project
team members, customers, and other stakeholders who
contribute to the risk identification process.

31
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Using the Delphi Technique


 The Delphi Technique is an anonymous method to query experts
about foreseeable risks within a project, phase, or component of a
project.

 The result of the survey are analyzed by a third party, organized,


and then circulated to the experts.

 There can be several rounds of anonymous discussion with the


Delphi Technique – without fear of backlash or offending other
participants in the process.

32
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Identifying Risks Through Interviews


 Interviewing subject-matter experts and project stakeholders is an
excellent approach to identifying risks on the current project based
on the interviewee’s experience.

 The interviewee, through questions and discussion, shares his


insight on what risks he perceives within the project.

 The goal of the process is to learn from the expert what risks may
be hidden within the project, what risks this person has
encountered on similar work, and what insight the person has into
the project work.
33
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Root Cause Analysis

 Root cause analysis is a specific technique to identify a


problem, discover the underlying causes that lead to it,and
develop a preventive action

34
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

3. Checklists Analysis :
1. Risk checklists can be developed based on historical information
and knowledge that has been accumulated from previous similar
projects and from other sources of information .

2. The lowest level of RBS can also be used as a checklist

35
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

4. Examining the Assumptions


 Assumption analysis is the process of examining the
assumptions to see what risk may stem from false
assumptions.

 Examining assumptions is about finding the validity of the


assumptions.

36
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

5. Diagramming Techniques
 There are several diagramming techniques that can be
utilized by the project team to identify risks:
 Ishikawa
 Flow charts
 Influence diagrams

37
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

6. Analyzing SWOT
SWOT means strengths, weaknesses, opportunities, and threats.
 Strengths : the technology to be installed in the project has been installed
by other large companies in our industries

 Weaknesses: we have never installed this technology before.

 Opportunities: the new technology will allow us to reduce our cycle time
for time-to-market on new products.

 Threats: the time to complete the training and simulation may overlap with
product updates, new versions, and external changes to our technology
portfolio.

38
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.2 Identify Risks - Output


Risk Register

 The main output of the risk identification process is a list


of identified risks and other information needed to begin
creating a risk register

 The risk register is a project plan component that


contains all the information related to the risk
management activities.

39
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Register Contents


 List of identified risks

 List of Potential Responses

40
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.3 Perform Qualitative Risk Analysis


 The Qualitative Risk Analysis process involves determining
what impact the identified risks will have on the project
objectives and the probability they’ll occur.

 It also ranks the risks in priority order according to their effect


on the project objectives.

 This helps the team determine if Quantitative Risk Analysis


should be performed or if you can skip right to developing
response plans.
41
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.3 Perform Qualitative Risk Analysis

Inputs Tools & Techniques Outputs

1. Risk register 1. Risk probability and impact 1. Risk register (updates)


2. Risk management plan assessment
3. Project scope statement 2. Probability and impact matrix
4. Organizational process assets 3. Risk data quality assessment
4. Risk categorization
5. Risk urgency assessment
6. Expert Judgement

42
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.3 Perform Qualitative Risk Analysis

43
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.3 Perform Qualitative Risk Analysis - Inputs


 The Qualitative Risk Analysis process has four inputs:
 Organizational process assets

 Project scope statement

 Risk management plan

 The risk register

44
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.3 Perform Qualitative Risk Analysis – Tools &


Techniques

 The Qualitative Risk Analysis process includes the following


tools and techniques:
 Risk probability and impact assessment

 Probability and impact matrix

 Risk data quality assessment

 Risk categorization

 Risk urgency assessment

45
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Probability and Impact Assessment

 This tool and technique assess the


probability that the risk events you’ve
identified will occur and it determines the
effect their impacts have on the project
objectives, including time, scope, quality, and
cost.

 Analyzing risks in this way allows you to


determine which risks require the most
aggressive management.

46
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Probability and Impact Assessment


 Probability
 Probability is the likelihood that an event will occur. The classic example is flipping a
coin.
 There is a .50 probability of getting heads and a .50 probability of getting tails on the
flip.

 Impact
 Impact is the amount of pain (or the amount of gain) the risk event poses to the
project.
 The risk impact scale can be a relative scale that assigns values such as high-
medium-low (or some combination of these) or a numeric scale known as a cardinal
scale.
 Cardinal scale values are actual numeric values assigned to the risk impact. Cardinal
scales are expressed as values from 0.0 to 1.0 and may be stated in equal (linear) or
unequal (nonlinear) increments.

47
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Impact Scale

48
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Assessing Probability and Impact


 The idea behind both probability and impact values is to
develop predefined measurements that describe what value
to place on a risk event.

 During the Qualitative Risk Analysis process, you’ll determine


and assess probability and impact for every risk identified
during the Risk Identification process.

49
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Probability and Impact Matrix


 A probability and impact matrix assigns an overall risk rating to
each of the project’s identified risks.

 The combination of probability and impact results in a classification


usually expressed as high, medium, or low.

 According to A Guide to the PMBOK, high risks are considered a


red condition, medium risks are considered a yellow condition, and
low risks are considered a green condition.

 This type of ranking is known as an ordinal scale because the


values are rank-ordered from high to low.

50
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Sample Probability and Impact Matrix

51
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Data Quality Assessment


 The data quality assessment involves determining the usefulness of
the data gathered to evaluate risk. Most importantly, the data must
be unbiased and accurate.

 You will want to examine elements like the following when


performing this tool and technique:
 The quality of the data used

 The availability of data regarding the risks

 How well the risk is understood

 The reliability and integrity of the data

 The accuracy of the data


52
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Categorizations

 This tool and technique is used to determine the effects risk


has on the project.

 You can examine not only the categories of risk determined


during the Risk Management Planning process (and
described in the RBS) but also the project phase and the
WBS to determine the elements of the project that are
affected by risk.

53
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk Urgency Assessment


 Using this tool you’ll determine how soon the potential risks
may occur and quickly determine responses for those risks
that could occur soon.

 You should consider the risk triggers, the time to develop and
implement a response, and the overall risk rating when
determining how quickly responses are needed.

54
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.3 Perform Qualitative Risk Analysis - Output


Risk Register (update)
 The goal of the Qualitative Risk Analysis process is to rank the
risks and determine which ones need further analysis and,
eventually, risk response plans.

 You’ll update the register with the following information:


 Risk ranking (or priority) for the identified risks

 Risks grouped by categories

 List of risks requiring near-term responses

 List of risks for additional analysis and response

 Watch list of low-priority risks

 Trends in Qualitative Risk Analysis results


55
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.4 Perform Quantitative Risk Analysis


 The Quantitative Risk Analysis process evaluates the
impacts of risk prioritized during the Qualitative Risk Analysis
process and quantifies risk exposure for the project by
assigning numeric probabilities to each risk and their impacts
on project objectives.

 This quantitative approach is accomplished using techniques


like Monte Carlo simulation and decision tree analysis.

56
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Quantifying Risk
 To paraphrase A Guide to the PMBOK, the purpose of this
process is to perform the following:
 Quantify the project’s possible outcomes and probabilities.

 Determine the probability of achieving the project objectives.

 Identify risks that need the most attention by quantifying their


contribution to overall project risk.

 Identify realistic and achievable schedule, cost, or scope targets.

 Determine the best project management decisions possible when


outcomes are uncertain.

57
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.4 Perform Quantitative Risk Analysis


 Quantitative Risk Analysis—like Qualitative Risk Analysis—
examines each risk and its potential impact on the project
objectives.

 You may choose to use both of these processes to assess risk or


only one of them, depending on the complexity of the project and
the organizational policy regarding risk planning.

 The Quantitative Risk Analysis process can follow either the Risk
Identification process or the Qualitative Risk Analysis process.

58
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.4 Perform Quantitative Risk Analysis

Inputs Tools & Techniques Outputs

1. Risk register 1. Data gathering and 1. Risk register (updates)


2. Risk management plan representation techniques
3. Cost management plan 2. Quantitative risk analysis and
4. Schedule management plan modelling techniques
5. Organizational process assets 3. Expert Judgement

59
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.4 Perform Quantitative Risk Analysis

60
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.4 Perform Quantitative Risk Analysis - Inputs

1. Organizational process assets

2. Project scope statement

3. Risk management plan

4. Risk register

5. Project management plan : Cost management plan and


schedule management plan

61
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.4 Perform Quantitative Risk Analysis – Tools &


Techniques
1. Data Gathering and Representation Techniques
 The data gathering techniques includes interviewing techniques,
probability distributions, and expert judgment. Let’s look at each of
them.

 Interviewing
 Project team members, stakeholders, and subject matter experts
are prime candidates for risk interviews.

 Ask them about their experiences on past projects and about


working with the types of technology or processes you’ll use during
this project.
62
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Data Gathering and Representation Techniques


 Probability Distributions
 According to A Guide to the PMBOK, continuous probability
distributions include normal, lognormal, triangular, beta, and
uniform distributions.

 Distributions are graphically displayed and represent both the


probability and time or cost elements

 Triangular distributions use estimates based on the three-point


estimate (the pessimistic, most likely, and optimistic values).

 This means that during your interviews, you’ll gather these pieces
of information from your experts. Then you’ll use them to quantify
risk for each WBS element.
63
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Quantitative Risk Analysis and Modeling Techniques


 There are four techniques encompassed in this tool and
technique:
1. Sensitivity Analysis,

2. Expected Monetary Value Analysis,

3. Decision Tree Analysis, &

4. Modeling And Simulation.

64
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Sensitivity Analysis

 Sensitivity analysis is a quantitative method of analyzing the


potential impact of risk events on the project and determining
which risk event (or events) has the greatest potential for
impact by examining all the uncertain elements at their
baseline values.

 One of the ways sensitivity analysis data is displayed is a


tornado diagram.

65
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Tornado Diagram

66
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Expected Monetary Value (EMV) Analysis

 Expected monetary value (EMV) analysis is a statistical technique


that calculates the average, anticipated impact of the decision.

 EMV is calculated by multiplying the probability of the risk times its


impact and then adding them together.

 For example, one risk may cost the project an additional $10,000 if
it occurs, but there’s only a 20-percent chance of the event
occurring.

 In the simplest form, the expected monetary value of this individual


risk impact is thus $2,000. Project managers can also find the
expected monetary value of a decision by creating a decision tree.

67
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Expected Monetary Value (EMV) Example

68
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis


 Decision trees are diagrams that show the sequence of
interrelated decisions and the expected results of choosing
one alternative over the other.

69
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis an Example

70
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis an Example

71
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis an Example

72
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis an Example

73
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis an Example

74
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis an Example

75
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Decision Tree Analysis an Example

76
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Modeling and Simulation


 Project simulations allow the project team to play “what-if” games
without affecting any areas of production. The Monte Carlo
technique is the most common simulation.

 Monte Carlo, typically completed through a computer software


program, completely simulates a project with values for all possible
variables to predict the most likely model.

 For the exam, remember that simulation techniques are used to


predict schedule or cost risks. Schedule simulations are usually
performed using the precedence diagramming method, while cost
simulation typically uses the WBS as its basis.

77
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Expert Judgment
 Experts can come from inside or outside the organization and
should have experience that’s applicable to your project.

 For example, if your project involves manufacturing a new product


or part, you might want to consider experts like engineers or
statisticians.

 If you’re dealing with sensitive data in an information technology


project, consider bringing on a security expert.

78
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.4 Perform Quantitative Risk Analysis Outputs

1. Risk Register (Updates)

 Probabilistic analysis of the project

 Probability of achieving cost and time objectives

 Prioritized list of quantified risks

 Trend in Quantitative risk analysis results

79
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses


 Risk response planning is all about options and actions.

 It focuses on how to decrease the possibility of risks from


adversely affecting the project’s objectives, and on how to
increase the likelihood of positive risks that can aid the
project.

 Risk response planning assigns responsibilities to people


and groups close to the risk event.

 Risks will increase or decrease based on the effectiveness of


risk response planning.
80
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses

Inputs Tools & Techniques Outputs


1. Risk management plan 1. Strategies for negative risk or 1. Risk register (updates)
2. Risk register threats 2. Risk-related contractual
2. Strategies for positive risk or agreements
Opportunities 3. Project management plan
3. Contingent response (updates)
strategies 4. Project Document Updates
4. Expert Judgment

81
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses

82
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses : Inputs


 The risk management plan is needed during the risk response planning,
but the risk register is also needed to provide the following:
 A list of prioritized risks

 A risk ranking

 A prioritized list of quantified risk

 A probabilistic analysis of the project

 The probability of the project meeting the cost and schedule goals

 The list of potential responses decided upon when risks were first identified

 Any risk owners that have been identified

 A list of risks with common causal factors

 Trends from qualitative and quantitative analysis

83
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses– Tools & Techniques


 Strategies for Negative Risks or Threats

 After identifying and quantifying risks, you must decide


how to respond to them

 Four main response strategies for negative risks:

 Avoid

 Transfer

 Mitigate

 Accept

84
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses– Tools & Techniques


 Strategies for Negative Risks or Threats

 Avoiding the Negative Risks and Threats


 Avoidance is simply avoiding the risk.

 Examples of avoidance include the following:


 Changing the project plan to eliminate the risk

 Clarifying project requirements to avoid discrepancies

 Hiring additional project team members that have experience with the
technology that the project deals with

 Using a proven methodology rather than a new approach

85
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Strategies for Negative Risks or Threats


 Transferring the Negative Risk

 Transference is the process of transferring the risk (and the


ownership of the risk) to a third party. The risk doesn’t disappear,
it’s just someone else’s problem. Transference of a risk usually
costs a premium for the third party to own and manage that risk.
Common examples of risk transference include
 Insurance

 Performance bonds

 Warrantees
Most Effective in dealing with Financial Risk
 Guarantees

 Fixed-priced contracts
86
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Strategies for Negative Risks or Threats


 Mitigating the Negative Risk
 Mitigating risks is an effort to reduce the probability and/or impact
of an identified risk in the project. Mitigation is done—based on the
logic—before the risk happens.

 The cost and time to reduce or eliminate the risks is more cost
effective than repairing the damage caused by the risk. The risk
event may still happen, but hopefully the cost and impact of the risk
will both be very low.

87
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Mitigating the Negative Risk


 Examples of mitigation include:
 Adding activities to the project to reduce the risk probability or
impact

 Simplifying the processes within the project

 Completing more tests on the project work before implementation

 Developing prototypes, simulations, and limited releases

88
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Accepting the Negative Risk


 Acceptance indicates a decision not to make any changes to the project
plan to deal with a risk or that a suitable response strategy cannot be
identified. This strategy can be used for both negative and positive risks

 There are two types of acceptance:

Active acceptance: may include developing a contingency plan to


execute should a risk occurs.

Passive acceptance: requires no action. The project team will deal


with the risk as it occurs.

89
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Response Strategies for Positive Risks

 Exploit

 Share

 Enhance

 Acceptance

90
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Managing the Positive Risk and Opportunities

 Exploiting the Positive Risk or Opportunities

 When an organization would like to ensure that a positive risk


definitely happens, it can exploit the risk.

 Positive risk exploitation can be realized by adding resources to


finish faster than what was originally planned, increasing quality to
recognize sales and customer satisfaction, utilizing a better way of
completing the project work—or any other method that creates the
positive outcomes of the identified risk.

91
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Managing the Positive Risk and Opportunities


 Sharing the Positive Risk
 The idea of sharing a positive risk really means sharing a mutually
beneficial opportunity between two organizations or projects, or
creating a risk-sharing partnership.

 When a project team can share the positive risk, ownership of the
risk is given to the organization that can best capture the benefits
from the identified risk.

92
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Managing the Positive Risk and Opportunities

 Enhancing the Positive Risks


 This risk response seeks to modify the size of the identified
opportunity. The goal is to strengthen the cause of the opportunity
to ensure that the risk event does happen.

 Enhancing a project risk looks for solutions, triggers, or other drives


to ensure that the risk does come to fruition so the rewards of the
risk can be realized by the performing organization.

93
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Accepting the Risks

 Risk acceptance is the process of simply accepting the risks


because no other action is feasible; or the risks are deemed to be
of small probability, impact, or both and that a formal response is
not warranted.

 Passive acceptance requires no action; the project team deals with


the risks as they happen.

 Active acceptance entails developing a contingency plan should the


risk occur. Acceptance may be used for both positive and negative
risks.

94
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Accepting the Risks

 A contingency plan is a predefined set of actions the project


team will take should certain events occur. Events that trigger
the contingency plan should be tracked.

 A fallback plan is a reaction to a risk that has occurred when


the primary response proves to be inadequate.

95
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Contingency Response Strategies


 A contingency allowance is the amount of money the project
will likely need in the contingency reserve based on the
impact, probability, and expected monetary value of a risk
event.

96
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses- Output


 The major output of risk response planning is the risk register
updates. These risk responses are documented in the risk register
and guide the reaction to each identified risk.

 They include the following:

 A description of the risk, what area of the project it may affect, the
causes of the risk, and its impact on project objectives

 The identities of the risk owners and their assigned


responsibilities

 The outputs of qualitative and quantitative analysis


97
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses- Output


 Risk strategies and the specific actions necessary to implement
those strategies

 Symptoms and warning signs, sometimes called triggers, of each


risk event

 A description of the response to each risk, such as avoidance,


transference, mitigation, or acceptance

 The actions necessary to implement the responses

 The budget and schedule for risk responses

 Both the contingency and fallback plans

98
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Working with Residual Risks


 The risk response plan also acknowledges any residual risks that
may remain after planning, avoidance, transfer, or mitigation.

 Residual risks are typically minor and have been acknowledged


and accepted. Management may elect to add both contingency
costs and time to account for the residual risks within the project.

99
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Accounting for Secondary Risks


 Secondary risks are risks that stem from risk responses.

 For example, transference may elect to hire a third party to


manage an identified risk.

 A secondary risk caused by the solution is the failure of the


third party to complete their assignment as scheduled.

 Secondary risks must be identified, analyzed, and planned


for, just as any another identified risk.

100
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Risk related contract decisions


 When multiple entities are involved in a project, contractual
agreements may be necessary to identify the responsible parties for
identified risks.

 The contract may be needed for insurance purposes, customer


acceptance, or the acknowledgement of responsibilities between
the entities completing the project.

 Transference is an example of contractual agreements for the


responsibility of risks within a project.

101
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Updating the Project Plan

 The risk reactions, contingency plans, and fallback plans


should all be documented and incorporated into the project
plan—for example, updating the schedule, budget, and WBS
to accommodate additional time, money, and activities for
risk responses.

102
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.5 Plan Risk Responses– Outputs

Project Document Updates :

 Project documents that may get updated , include, but are not
limited to :
 Assumptions Log Updates

 Technical documentation updates

103
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks


 Risks must be actively monitored and new risks must be responded
to as they are discovered.

 Risk monitoring and control is the process of monitoring identified


risks for signs that they may be occurring, controlling identified risks
with the agreed responses, and looking for new risks that may
creep into the project.

 Risk monitoring and control also is concerned with the


documentation of the success or failure of risk response plans, and
keeping records of metrics that signal risks are occurring, fading, or
disappearing from the project.

104
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks


 There are several goals to risk monitoring and control:
 To confirm risk responses are implemented as planned

 To determine if risk responses are effective or if new responses are


needed

 To determine the validity of the project assumptions

 To determine if risk exposure has changed, evolved, or declined due to


trends in the project progression

 To monitor risk triggers

 To confirm policies and procedures happen as planned

 To monitor the project for new risks

105
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks

Inputs Tools & Techniques Outputs

1. Risk register 1. Risk reassessment 1. Risk register (updates)


2. Project Management Plan 2. Risk audits 2. Change Requests
3. Work performance 3. Variance and trend analysis 3. Organizational process assets
information 4. Technical performance (updates)
4. Performance reports measurement 4. Project management plan
(updates)
5. Reserve analysis
5. Project Document Updates
6. Status meetings

106
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks

107
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks : Inputs


 The risk register The risk register is central repository for all
project risk information. It includes the identified risks, the potential
responses, the root causes of risks, and any identified categories of
risk.

 Project Management Plan : contains risk management plan : that


defines the organization’s approach to risk management. It is not
the strategy for specific risks within a project, but the overall
strategy for risk analysis and planning.

 Project performance Project performance focuses on the balance


of the project schedule, costs, and scope. Should any of these
factors suffer, new risks are likely to enter the project.
108
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks : Inputs


 Work performance information :
 The results of project work can inform the project manager and the project team of new
and pending risks. In addition, project team members may create reports to monitor or
document risks. These reports are known as issue logs, action items, jeopardy
warnings, and escalation notices.

 Deliverables status

 Schedule progress

 Costs incurred

 Performance Reports : These reports take information from performance


measurements and analyze it to provide project work performance
information including variance analyses, earned value data , and forecasting
data
109
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks – Tools &


Techniques
 Risk Reassessment
 Identification of new risk, reassessment of current risk etc…

110
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks – Tools &


Techniques
 Risk Response Audits
 A risk response audit examines the planned risk response, how
well the planned actions work, and the effectiveness of the risk
owner in implementing the risk response.

 The audits happen throughout the project to measure the


effectiveness of mitigating, transferring, and avoiding risks.

 The risk response audit should measure the effectiveness of the


decision and its impact on time and cost.
111
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks – Tools &


Techniques

 Periodic Risk Reviews


 The periodic risk review is a regularly scheduled discussion
throughout the project to ascertain the level of foreseeable risks,
the success of risk responses in the project to date, and a review of
pending risks.

112
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks – Tools &


Techniques

 Earned Value Analysis


 Earned value analysis measures project performance. When
project performance is waning, the project is likely missing targeted
costs and schedule goals.

 The results of earned value analysis can signal that risks are
happening within the project—or that new risks may be developing.

113
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks – Tools &


Techniques

 Technical Performance Measurement


 Throughout the project, the project team’s technical competence
with the technology being used in the project should increase.

 The level of technical achievement should be in proportion to the


expected level of technical performance within the project.

114
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks – Tools &


Techniques
 Additional Risk Planning
 Most likely, new risks will become evident during the project
implementation.

 The project team, project manager, and key stakeholders that


discover the risks should communicate the risk.

 The risk must then be acknowledged, documented, analyzed, and


planned for. The project team must be encouraged to communicate
the discovery of new risks.

115
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

11.6 Monitor and Control Risks - Outputs

1. Risk register updates

2. Change Requests : recommended corrective actions or


recommended preventive actions

3. Organizational process assets updates

4. Project management plan updates

5. Project Document Updates

116
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved
®
PMP Exam Preparation Course

Results of Good Project Risk Management

 Unlike crisis management, good project risk management


often goes unnoticed

 Well-run projects appear to be almost effortless, but a lot of


work goes into running a project well

 Project managers should strive to make their jobs look


easy to reflect the results of well-run projects

117
Madras Management Training W.L.L Email: [email protected] www.mmt-institute.com ©2008 All Rights Reserved

You might also like