BMS-21-RoofingMethod Statement
BMS-21-RoofingMethod Statement
METHOD STATEMENT
FOR
ROOFING
If, despite best endeavours, a conflict should arise between this Method Statement and the Project
Specification the requirements of the latter shall be observed and this document revised, accordingly.
Prepared Checked
Authorised
Issue Date Senior Site
HSE (PSM) Quality (PQM) (Project Manager)
Engineer
00 DD MMM YY
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref BMS-21 Rev 00
ROOFING Date DD MMM YY Page 2 of 16
CONTENTS
CONTENTS................................................................................................................................ 2
1.0 SCOPE............................................................................................................................. 4
2.0 RESPONSIBILITIES........................................................................................................ 4
3.0 INTERFACING................................................................................................................. 5
4.0 SEQUENCING..................................................................................................................5
5.0 METHODOLOGY............................................................................................................. 5
6.0 EQUIPMENT.................................................................................................................. 12
7.0 MATERIALS...................................................................................................................12
10.0 ATTACHMENTS......................................................................................................... 12
Attachment 1: Key to Safety Symbols.......................................................................................................................13
Amendments History
Rev Clause Changes Made
00 Original issue of document
01
02
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref BMS-21 Rev 00
ROOFING Date DD MMM YY Page 4 of 16
1.0 Scope
This method statement covers the practices applicable for built-up roofing systems.
This method statement excludes:
Sheet metal roofing
Shingle roofing
Note: Emphasis of required safety measures will be inserted throughout, generally in the
following format, pictograms are to be found in Attachment 1:
2.0 Responsibilities
Site Manager:
Site Engineers:
o Continuous monitoring of all aspects of roofing works, i.e. cleaning and prep of receiving surface,
the placement of the low Density Concrete, membrane placement and water testing.
o Liaising with QC Engineers regarding works progression and availability for hold point
inspections.
o Ensuring that the Project Inspection Plan (PIP) has been briefed to and is then followed by the
construction team.
3.0 Interfacing
Site Manager:
Coordination with Technical Office Manager to ensure timely availability and approval of materials in
collaboration with Quality Manager.
o Liaison with Technical Office Manager for advice required regarding changes, missing
information, clarifications.
Site Engineers:
QC Engineers:
o Ongoing liaison with Site Engineers concerning waterproofing/roofing progression and adherence
to stipulated requirements of method statements, approved materials and PIP.
4.0 Sequencing
< INSERT DETAILS OF WORKS SEQUENCE OR INCLUDE PROGRAMME EXCERPT OR
CROSS-REFERENCE PROGRAMME CONCERNED >
5.0 Methodology
5.1 Structural Concrete Roof Slab EPDM (Ethylene Propylene Diene Monomer)
The roofing system is based upon the use of large size (up to 30’x100’ Rolls) EPDM rubber elastomeric
waterproofing membrane, loose laid over lightweight concrete laid to falls, thermally insulated with
extruded polystyrene boards, protected with Geotextile fibermat, and ballasted by loose laid concrete
tiles, giving the following inverted (traditionally the insulation was placed under the EPDM) built-up
section from roof slab upwards:
Introduction:
The lightweight thermal insulating concrete is a foam cellular screeding material when applied over
a structural concrete deck, it forms a strong continuous, fireproof lightweight screed with
considerable thermal insulation properties, and provides effective slopes for proper drainage.
The finished surface of the lightweight concrete is smooth, strong and easily repairable in case of
any crack development. However, due to its relatively higher shrinkage factor, in comparison to
normal concrete or screed, the development of hair and minor surface cracks is an unavoidable
phenomenon.
Mix Design:
For an average dry density of 480 Kg/m3, the following (approximate) mix design is to be
implemented per cubic meter:
Cement Consumption 400 Kg.
Water Consumption 200 Kg.
Foaming water Consumption 60 Litres
Foaming agent Consumption 1.1 Litres
Method Of Application:
Set the foam machine on deck. The mixing and casting of the light weight concrete is done with
an automated machine mainly composed of a mixer, aerator, pump, water reservoir, electric
panel board and related accessories all set on special trailer.
Sweep deck surface clean of standing water, dirt, construction debris and other foreign
materials.
The foam concrete is cast in multiple layers procedure. As the multiple density casting is an
accepted method of placing, provided each layer thickness is not less than that of the
minimum accepted of 50 mm and not more than the maximum accepted of 100 mm
Prior to initiating casting, the deck slope and levels are set using metal guideline bars and chalk-
line marks on upstands, to create placement bays. Immediately before casting the lightweight
concrete, the concrete deck surface shall be moistened. The first casted foam layer shall be
left for 12 hours to set, during this setting period, no traffic is allowed. The same will be
repeated for the subsequent layers until reaching the finished upper layer, which finishing is
done by using straight edge aluminium finishing bar. After 12 hours from casting, the finished
level surface of the lightweight concrete shall be water cured, two or three times a day,
(depending on prevailing weather condition), during which it will be covered with either jute or
polyethylene sheet. Afterwards, it will be left for two or three days to dry up. Finally, damages
to the lightweight concrete surface shall be repaired with sand cement mortar mix with suitable
bonding agent (SBR (Styrene-Butadiene-Rubber) or Acrylic based) added to the mix. The
various components of lightweight cellular concrete are introduced into the cement mixer as
follows:
While the cement mixer is in motion, the water and cement are introduced, subsequently the
right quantity of foam is automatically injected, which is directly related to the quantity of
cement. The mixing process must then continue until all the foam is completely mixed with the
liquid mortar, whereby white foaming will appear on top face of the mixer.
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref BMS-21 Rev 00
ROOFING Date DD MMM YY Page 7 of 16
It is advisable to complete the three operations: Mixing, transportation and casting as quickly
as practical in order to ensure successful results.
o Foaming Agent:
Extruded polystyrene thermal insulation rigid boards, 2.0” thick, in one layer, loose laid, applied
staggered usually has an R-10 value
Single layer of non-woven, needle punched geotextile fibermat, 120 - 140 gm / m 2 loose laid,
overlapping adjoining sheets 4.0” (10 cm). The mat shall be extended around roof parapet/
upstands up to the ballast finished level.
5.1.9 Ballast:
Precast concrete pavers 400 x 400 x 40 mm applied loose laid, with gravel bed ballast at border line
and around roof details, at strip width not exceeding 400 mm. Calculate uplift and make sure that
weight of pavers will resist the uplift.
Internal / External corners shall be suitably dressed with EPDM membrane, and reinforced with extra
piece layer of Elastoform Flashing of uncured “EPDM”, 0.060” thick, sealed around with lap
sealant.
Roof rain water outlets, scupper type, shall be dressed with Elastoform Flashing of uncured EPDM,
0.060” thick, sealed with lap sealant.
EPDM membrane laps shall be minimum 3.0” wide, first cleaned with primer (or Splice Cleaner),
seamed with EP-95 Splicing cement, sealed at internal edge with In-Seam sealant and at the
external edge with Lap Sealant.
Duct penetration through roof slab: Its concrete upstand shall be flashed with EPDM membrane,
0.060” thick, fully adhered and terminated by termination bar.
The Electro-mechanical contractor must ensure that the gap line between the upstand top face and
the duct body shall be sealed by reliable multipart sealant and protected by shop-fabricated
watertight metal cap properly sealed.
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref BMS-21 Rev 00
ROOFING Date DD MMM YY Page 11 of 16
6.0 Equipment
Torch
Bee mixer
Hand tools
7.0 Materials
Geotextile Fiber Mat
EPDM
elastomeric flexible cementitious coating
polypropylene protection boards
needle punched geotextile fibermat
APP modified, torch applied bituminous waterproofing membrane
primer
10.0 Attachments
Key to Safety Symbols
Risk Assessment
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref BMS-21 Rev 00
ROOFING Date DD MMM YY Page 13 of 16
Use respirators
< INSERT PROJECT REF # & TITLE HERE >
Ref BMS-21 Rev 00
METHOD STATEMENT: ROOFING
Date DD MMM YY Page 14 of 16
roofing Falling while getting on Applicators 3 5 9 a secure way to enter and exit the roof is essential 1 5 5
and off the roof
roofing Falling Material Applicators 2 5 10 Conduct safety meeting to instruct the donning of hard hats and safety 2 2 4
shoes.
roofing Roofers may sustain Applicators 2 5 10 Conduct safety meetings to instruct the donning of protective clothing 2 2 4
serious burns from the
torch or the asphalt
being applied
< INSERT PROJECT REF # & TITLE HERE >
Ref BMS-21 Rev 00
METHOD STATEMENT: ROOFING
Date DD MMM YY Page 15 of 16