Calibration Procedure
Calibration Procedure
CALIBRATION PROCEDURE
CALIBRATION PROCEDURE
PROCEDURE ELECTRICAL
& INSTRUMENT DEPARTEMENT
CALIBRATION PROCEDURE
1 Purpose
The purpose of this document is to describe the calibration process and required tools, drawing, material
inprovision Field Instrument at IKPT, this procedure shall be applied calibration
and ensure that each instrument is functionally correct and correctly calibrated
2 Scope Of Work
The scope of work shall be covered all calibration level switch, pressure switch, flow meter
temp switch, transmitter, etc
3 Responsibilities
3.1 Instrument Leader
Ensure relevant permits are raised and received prior to commencement of work with full
compliance by all instrument foreman, technician, and labour regarding excutions of work
in accordance with the IKPT project requirments and specification. Confirm the anailability
of the material, tools, equipment personnel who will carry out work
3.3 Safety
ensure that personal comply with all safety rulles and requipments in the conduts of all
instrument equipment installation activities performed in the project
4 Technical requirement
4,1 Tools calibration
a_ Digital multi-meter
b. DC standard voltage and current generator
c. Standard resistance box and thermocouple
d. Hand Held Communicator for Smart Transmitters and Smart
e. Hand pum
f. Pressure gauge / digital pressure gauge
g. Precision air regulator
h. Compressor / Nitrogen with air pressure
i. Connector, Tubing of various sizes
j. Others, if any
CALIBRATION PROCEDURE
Basically, calibration shall be witnessed by Owner. Contractor shall notify for the request of
witness in advance. Should any of the tests not be witnessed, Contractor can precede the test by
themselves under the confirmation of Owner's acceptance.
5,1 Control valve
5.1.1 Where specified on the Vendor's specification sheet, confirm that the material
conform to spesification,size or rating, connection type, data plate or tag plate, cable
or wiring in place and no mechanical damage.
5.1.2 Where the valve has FP positioner or E/P positioner (smart) , input the simulated
signal to the UP positioner using the "DC Standard Current Generator" or Hand held
communicator, respectively.
5.1.3 Where a valve positioner is mounted on the control valve, the stroke test shall he
performed with the positioner fitted at storage area. In this case, the supply air to be
connected to the air filter regulator mounted on the valve.
5.1.4 Before starting the stroke test, leakage test for actuator and fittings to be performed by
applying snoop from swagelok.
5.1.5 Increase the air signal pressure to load the actuator, and check the plug stem strokes at
full closing ( or full opening ) 25% opening, 50% opening, 75% opening and full
opening (or full closing) using the travel indicator mounted on the valve. Then,
decrease the air signal and check the plug stem strokes at full opening (or full
closing), 75% opening, 50% opening, 25% opening and full closing (or full opening).
Where necessary, adjust the spring tension or a positioner to obtain the correct "start
point" and "range". In case of limit switch, solenoid valve and/or booster relay are
mounted on the valve, check the action of them together with the stroke test.
5.1.6 The air failure action shall be confirmed by disconnecting either the loss of supply air
or signal function test of lock-up valve shall be performed together with this test.
5.1.7 The stroke time between full closing and full opening to be checked and confirm
which meet the specified time in the data sheets.( Note : Stroke time was specified
only which have process requirements) record stroke time.
5.1.8 Seat leakage test will not be performed unless the valve is dismantled for repair by
sheat damage.
CALIBRATION PROCEDURE
CALIBRATION PROCEDURE
General Note
a. Any adjustment for instrument shall be done in accordance with the manufacturer's
intructions, if necessary.
b. Visual check shall be performed on all instruments, before starting the procedure, to
ensure that they are not damaged or incorrectly assembled.
c. Each instrument nameplate shall be checked with the latest version of individual project
specifications and/or Vendor's specifications to confirm correct tagging.
d. All support and stuffing for shipping shall be removed from the instruments before starting the procedure
Safety precaution:
a. Make sure the PPE is use Correctly
b. Make sure all equipment before using it in good condition and has passed inspection.
c. Ensure all employees who work above the level attended training working at heigth.
d. Use acces up and down and work, with scaffolding that has been in the inspection.
e. Ensure full body harness is hung acces strong and above the head.
f. In the work place should be displayed safety sign.
g. Barricade the work place.
h. Fit to work for working at height location.
-----END-----