Lift Plan Requirements
Lift Plan Requirements
Operation needing assistants to guide the load during the load setting
excavator)
5
STEP: 1
Know the detail of the job from
the drawing.
a) Identify Size, Shape and Weight of
6
CG of Load
CG
UNSAFE
CG IS HIGHER THAN LIFT POINTS
CG
CG
CG
Get stability when the sling angle (A) Get an unstable load when the
is much larger than angle (B). sling angle (A) is less than (B).
STEP: 2
(2) Make sure the operator can see you and acknowledges the signal
given
(3) Signalperson must watch the load – the operator is watching you
(4) Don’t swing the load over other workers; warm them to keep out
of the way
FOLLOW MY STOP EMERGENCY STOP
INSTRUCTION
HOIST LOWER SLOWLY LOWER
Clench and Unclench
Fingers to “inch” load
JIB UP JIB DOWN
STEP: 8
Clear site.
Clean the lifting tackles and check it.
Store the lifting tackle on racks correctly.
Tandem Lift :
Any lift involving more than 2 cranes is a Tandem or
Critical Lift. Tandem Lifts are complex and dangerous as
crane capacities are based on freely suspended and
balanced load. The use of two, often more cranes, May
introduce side loading of the boom not normally
encountered with one crane. The load must be divided as
planned and the rigging so arranged.
Requirements of a Tandem Lift :
1) The ground must be levelled & compacted (especially so if one or
more the cranes must travel with the load).
2) The load and crane position during the lift must be determined.(so
that load calculation can be done).
The net load weight must be calculated, after the crane
types have been selected, the gross weight of the load can be
worked out, including the crane hook blocks and rigging
components.
3) All cranes must have their capacity calculated for the lift. None
of the cranes should have more than a 75 % load.
4) If different crane models are used, the operators will have to
match the line, boom and swing speed.
5) All swing and boom motions , and crane travel must be kept to
a minimum.
(An equaliser beam is recommended if hoist line speeds are
difficult to match ).
6) Operators, riggers and signalpersons must know exactly what
the entire operation is, step by step.
7) At least one dry run should be mode. All
communication should be made by radio.
8) There must be one person co-ordinating the lift.
9) The operators must maintain jerk-free movements. Hoisting,
booming, or swinging requires smooth start and stops.
10)All cranes on a multi-crane lift must lift the load off the
ground simultaneously. If not, one of the cranes will be
overloaded.
TANDEM LIFT (Unequal Loading)
1)When two cranes lift a load
determination must be made on the
location of the lift points for each crane.
This must be calculated to properly distribute the load
according to the capacities of each crane.
2) If load is non-symmetrical as in
illustration, the center of gravity will be
closer to one end.
Therefore it is likely that one crane will be positioned to lift
over half of the load weight.
What to do & What not to do.
(Do’s & Don’ts)
DO’S DON’TS
• Always fallow safety
policy,rules,guide lines, • Don’t violate any