Cost Engineering Lecture Note
Cost Engineering Lecture Note
0
1. Fundamental Principles of Cost Engineering
1.1 Introduction
Before taking up any construction work for its execution, the owner or
builder should have a thorough knowledge about the volume of work that
can be completed within the limits of his fund or the probable cost that may
be required to complete the contemplated work. It is therefore necessary to
prepare the probable cost or estimate for the intended work from its design
plan and specifications. Otherwise it may so happen that the work has to be
stopped before its completion due to shortage of funds and or materials.
There are many costs associated with construction projects. Some are not
directly associated with the construction itself but are important to quantify
because they can be a significant factor in whether or not the project goes
forward and feasible. These include the initial capital cost and the
subsequent operation and maintenance costs. Each of these major cost
categories consists of a number of cost components:
Land acquisition, including assembly, holding and improvement
Planning and feasibility studies
Architectural and engineering design
Construction, including materials, equipment and labor
Field supervision of construction
Construction financing including overhead costs
Insurance and taxes during construction
Owner's general office overhead
Equipment and furnishings not included in construction
Inspection and testing
The operation and maintenance cost in subsequent years over the project life
cycle includes the following expenses:
Land rent, if applicable
Operating staff
Labor and material for maintenance and repairs
Periodic renovations
Insurance and taxes
Financing costs
Utilities
Owner's other expenses
1
It is important for design professionals and construction managers to realize
that while the construction cost may be the single largest component of the
capital cost, other cost components are not insignificant. Early on, the owner
wants to understand the nature of these costs as well as have some indication
of what the construction itself will cost in order to analyze the life cycle
costs and determine the worthy fullness of the investment. The Cost-Benefit
Analysis can serve as a decision making tool to address all the costs and the
corresponding associated benefits worth to the owner.
Cost Engineering is a dynamic process that begins in the very early stages of
a project and ends when the project is turned over to the owner. As a project
moves along time, the amount of information generated increases. The
information improves an estimate’s accuracy but also costs more to develop
and takes more time. Cost estimating is critical in the development of the
project because it informs the owner of costs, which in turn guide design
decisions.
Cost Engineers consider past projects while anticipating new factors. Some
of these factors include:
Current technologies ,
Market demand and supply of material and labor,
Quantities of materials,
Collective bargaining agreements of suppliers and buyers,
Level of quality,
Requirements for completion.
A good database of actual costs from past project experiences facilitate the
preparation of a quick and accurate cost estimate. Cost Engineers spent
considerable time and resources developing and protecting this database.
Each new project provides a clearer picture of the actual cost of construction
and adds to the value of the data. Larger design and construction companies
maintain their own databases. Smaller companies may rely on the data
developed from independent cost consultants and cost data suppliers.
2
reference and common understanding as they are used in the Construction
Industry.
Construction Costs: valued consumption of goods /material/
and performance /labor work/ of different kind and amount for
the purpose of the production.
Depreciation/ Depletion Costs: Costs of goods/equipment/ or
plant distributed for the whole useful life to compensate its
deterioration to the work. Although a nonlinear relationship
exists, a linear or a straight-line
Average method is often preferred.
Original Value
100%
Depreciation Value
Full Depreciation
Residual Value
Residual Value
4
Cost Estimating and Cost Budgeting processes that develop the costing
documents will help obtain ones goal.
Cost Estimating is the process of developing an approximation of the cost
of the resources needed to complete project activities including the
consideration of the possible fluctuations and other variances such as risk.
Throughout the Cost Estimating process various alternatives are considered
to assure accurate and effective estimates. This process is conjoined with the
Activity Resource Estimating process and is foundational work necessary
for Cost Budgeting.
The inputs to the cost estimating process are outputs from the
other planning processes. These include the project scope
statement, the project management plan, the work breakdown
structure, staffing management plan, and organizational process
assets. The main outputs of the cost estimating process are the
Activity Cost Estimates and the Activity Cost Estimate
Supporting Detail.
The end result of the Cost Budgeting process is a Cost Baseline, which is a
time-phased budget that will be used to measure and monitor overall cost
performance on the project—usually displayed in the form of an S-curve.
Additionally, the Cost Budgeting process will produce Project Funding
Requirements, including a management reserve amount that is included
along with the cost baseline to compensate for either early progress or cost
overruns.
The Figure illustrates subjective estimates attempting to hit the target, which
is the actual cost. The subjective value chosen by each estimator was
considered to represent the resources required by each firm to complete an
example office-building project. We can see that the estimates are all
scattered around the target of actual cost. Hitting the target is not a common
occurrence and is an inbuilt problem of estimating.
Briefly, let us consider an estimator pricing a brickwork item.
What are the difficulties presented? They are as follows:
1. Choice of work method.
2. Output of crew (given the firm’s unique efficiency).
3. Cost of labor
4. Cost of material and selection of an appropriate wastage
allowance.
5. Addition of overheads and profit
6
Choice of work Method
There may be many or only a few work methods available. For instance,
should the estimator assume a three-man or a four-man crew, composed of
two or three bricklayer with either one or two laborers? Will there be central
mortar mixing or individual mixers for each crew? How will the brickwork
be constructed? Will trestles or proper standing scaffolding be used? Where
will work commence from? What restrictions will the other trades impose
on the masonry work?
All possibilities must be investigated, and the most economical possibility
should be chosen.
Output of crew
The output chosen will be based on past performance, since the estimator
will assume that this performance will be repeated in the future. As will be
explained later, recording and properly documenting job site performance is
helpful to the estimator when he or she considers future projects.
Manipulation of these historical data may occur; for example, decreasing
output to allow for restricted working condition. Whatever manipulation
occurs, the estimator is faced with the difficulty of trying to assess what
output will be achieved.
Cost of labor
How much will the contractor be required to pay for labor? The estimator
must predict this cost. The labor cost will vary depending on job location,
availability of skilled labor, contract wage regulations, union or open shop
labor requirements, general market conditions, and so on.
Cost of Material
This can be predicted with a fair degree of accuracy if the material in
question is in ready supply and is frequently purchased. The quantity of
material required must be accurately measured from the drawing and is not
dependent on the crew performance or work method adopted. Although
the estimator must not only consider the finished in -place quantity of
material, but also must allow for a wastage factor, this factor can vary
dramatically and is highly dependent on the performance and work
procedures adopted by the crew.
7
Addition for overheads and profit
This amount will depend on company policy, market condition, and many
other variables that will be discussed later. It is, as you can imagine, very
important to incorporate overhead and profit into the final estimate.
Variability of Estimates
The following are where cost variances between one estimate and another
can occur:
1. Quantity take off.
2. Material Costs.
3. Labor Costs.
4. Labor productivity forecasts.
5. Work Methods.
6. Construction equipment costs.
7. Indirect Job costs.
8. Subcontractor quotations.
9. Quotations from material suppliers.
10. Unknown site conditions.
11. Locational Factors.
12. Cost associated with the time element of the construction project and
escalation costs.
13. Staging and project start up costs.
14. Overheads.
15. Profit element.
16. Contingency and risk allocation.
17. Errors in estimate formulation.
18. Basis of information used to formulate estimate.
19. Market forces.
8
The total cost estimate is made up of numerous smaller cost estimates for
each activity required to complete the overall project. The estimating
equation is therefore composed of a series of calculations, the estimator has
to assess and propose a monetary solution. The total cost estimate is the
total of all the minor monetary solutions.
Each assessment the estimator performs is based on:
Previously recorded data (historical data)
The estimators own past experience.
Previous experience of others.
Hunches/intuition.
The final assessment is subjective. The estimator will decide what
productivity to allow, or what birr allowance or unit price to use. This
subjective act is the main reason why estimates vary. If you give identical
drawings and specifications to 100 estimators, you will get 100 different cost
estimates.
Figure below indicates the factors influencing variance in an estimate.
Variance
Information provided
Estimating experience
by others
Basic reasons for variances being introduced into cost estimates – the
subjective assessment.
9
Conflicting Issues of quality, size, performance and cost: As
projects develop, there is continual competition among issues of
quality, size, performance and cost. Owners want to have the biggest
facility with the best finishes and systems that will perform over time
with least possible amount of money. With these criteria, it is likely
that conflicts are bound to arise.
Owner
Need
Decision on
quality & Cost
Designer/
Constructor
Cost Information
Project Information
Cost Engineers
The design and construction team uses estimates to ensure that good
cost information developed and a feedback loop established so that
these conflicts can be addressed as quickly as possible. As project
information becomes available, it is passed through a costing exercise.
The owner can then decide to proceed based on this information or
ask for some alteration in the design. The designer can then devise
ways to meet the cost targets. Through this feedback loop, conflicting
demands of cost versus performance can be resolved.
Cost Engineering combines both science and art: Cost estimates are
a product of information supplied by the designer, the owner and the
suppliers. Experienced Cost Engineers use much judgment in
interpreting and configuring this information.
Cost Engineering does not offer guarantees of costs: Used properly,
however, can be important tool in bringing a project under or at
10
budget. The costs developed during design and even at the bidding
stage are almost never the final and complete costs of the project.
Costing can only be as accurate as the information upon which it is
based: Cost accuracy depends on many factors. Document
completeness, data base accuracy, the skill and judgment of the Cost
Engineer.
Cost estimate accuracy increases as the design becomes more
precisely defined: A normal feature of the design process is that
earlier stages of design are less precise than later stages. Cost
information provided at schematic and preliminary design will by
nature be less accurate than the ones provided at design developments.
Inputs
Scope
Definition
Time to
Prepare Costing
Accuracy
Quality of
Cost Data
Cost
Engineers
Skill
Learning Curve
Number of Units
As operations continue, crews learn so that the time required to complete the
next like unit is less. In general for buildings built to the same specification
13
in the same locality, the larger building will have the lower unit area cost.
This is mainly to the decreasing contribution of the exterior walls plus the
economy of scale usually achievable in larger buildings. As an example, the
area conversion scale shown below will give a factor to convert costs for the
typical size building to an adjusted cost for the particular project.
14
2. Project Quality
An owner may require a high quality project to create a specific image or
may need facilities for a specific use. Whatever the reason, the consequences
are always the same: an increase in costs. Early in the project, the Cost
Engineer must discuss expectations of quality with the users, the designers
and applicable government agencies.
3. Project Location
Constructing a facility in a locality is very different from constructing one
on other areas. The differences are in labor costs, the availability of
materials and equipment, delivery logistics, local regulations, and climate
conditions. Material costs are a factor of availability, competition, and
access to efficient methods of transportation. Labor costs, particularly
unionized labor, are a factor of the strength of the local bargaining unit. The
cost of labor is also a factor the degree of sophistication and level of training
found at the project location. On some projects the numbers and the skill
levels of workers required are not available locally and must be imported.
Understanding the need for such importation adds significantly to the
accuracy of an estimate.
Local conditions can influence the costs of the project. The need for citizen
involvement, local taxes or fees, and government requirements all can cost
the project money. Extreme climatic conditions, political instability, and
earthquake zones all add to the cost in ways that may not be entirely obvious
without some investigation.
The cost of labor and material in different locations can be predicted by
establishing location indices for different cities and parts of the country. An
index is created for a particular city by comparing the cost of labor,
equipment and material for that city to the national average. This allows an
estimator using national average costs to adjust the estimate to a particular
location. Most design and construction companies have developed an
accurate record of location indices, which they use for their pricing, or they
buy this cost data from national pricing suppliers. To predict the costs of
other local factors, such as political instability, a company either uses its
own experience in the locale or teams up with a local partner who knows
how the local atmosphere can affect project costs.
15
Various locational difficulties are described:
1. Remoteness
2. Confined sites
3. Labor availability
4. Weather
5. Design considerations (related to location).
6. Vandalism and site security
Remoteness
A remote construction site, for example, a project site located in valleys of
Gibe River, poses a contracting organization with a difficult set of problems
to cope with.
Communication Problems
If adequate communications such as telephone are not available, then a
radio or cellular-type installation is required. A telephone is a requisite to
any construction project: lack of communication during the construction
process can result in major, costly errors. In addition, because the project
location is further away from the head office, additional long-distance
telephone charges will be incurred.
Transportation Problems
All material and labor must be transported to the building site. If the
transport route is poor (if, indeed, any route exists at all), then delays in
material deliveries may occur; large vehicles may damage narrow bridges
(case of Gilgel Gibe Hydro-power project) or other items of property,
whose replacements costs must be borne by the contractor.
It may be necessary for the contractor to widen the existing route or
construct a bridge to allow material trailers access into the job site. The
route that is proposed should be studied carefully by the estimator.
Existing capacity of existing bridges on route should be established to
verify if equipment loads can be accommodated of if the bridge needs to
be strengthened by the contractor. Finally, the cost of hauling items of
equipment to the job site increases as the distance increases. Given these
considerations, the requirement for management to make the correct
equipment selections becomes very important.
16
Increased Material Cost
Increased material cost is primarily due to increased transport charges
such as when distance for haulage from the depot to a remote job site is
longer than the haulage associated with other construction projects the
estimator has previously worked on. Avery4 found that if the material
was fragile or hazardous, then transport costs fluctuated widely depending
on distance. He also discovered that the bulk materials with low initial
cost, such as sand and gravel, tend to be the most adversely affected by
distance and difficult transport conditions. Ferry crossing or bridges with
tolls increase the basic cost of materials.
Power and Water
Power and water are a necessity for building construction. Water is
needed for materials such as concrete, for cleaning the building, and for
many other uses. Salt water is not acceptable in most specifications for
concrete or mortar mixing, so remote projects without a convenient
domestic water supply, even if the site has access to thousands of gallon of
seawater; require water to be trucked to the job site. The cost of water
depends on the hauling costs. In some instances wells can be dug to pump
water to the surface; of course, the costs involved must be considered in
the estimate.
If no power source is available, then power must be provided by
generators.
Confined Sites
The problems associated with confined sites generally take the form of
congestion resulting in restricted working areas resulting in low productivity
from labor and equipment. These difficulties are generally associated with
downtown sites, but this need not always be the case.
In extreme cases, congestion can limit the choice of work methods, types of
equipment used, and size of crew to be employed. Careful investigation of
the problems likely to be associated with each particular site will allow a
realistic assessment of factors such as productivity to be made. Project
startup requires a careful utilization of resources in order to provide
production outputs that maximize profits. Confined sites create logistical
problems. Material movement should be minimized: each time an item of
17
material is moved, its cost to install in place increases. When materials are
delivered to a confined site, the material should be used immediately. If this
is not possible, a storage area should be available to receive the material, or,
if possible, the material should be offloaded directly at its intended
utilization point.
The estimator needs to consider the unique logistical problems associated
with each job site. These problems, including restricted access, restricted
material lay down area, restricted equipment storage areas, and restricted
location for site trailers, affect the type of equipment that can be used, the
effective management of the job, the worker productivity, and the amount of
labor involved in handling material. Since confined sites nearly always pose
logistical problems, the unit prices used by the estimator must account for
the increased costs.
Labor Availability
Each location has varying amount of available skilled and unskilled labor,
depending on the condition of the local economy. If labor of any kind is not
available locally (as may be the case in remote areas), then labor must be
imported from other location. In order to move labor from one area to
another, a financial incentive is usually required. The magnitude of this
incentive will vary depending on the state of the labor market. If labor is
imported, accommodations may have to be provided. Labor camps
comprising full time kitchen staff, dormitories, leisure facilities, etc., have
been set up on major construction project to house the contractor’s labor
force. The leisure facilities keep the labor force relaxed and occupied during
any rest periods. Living and working on a remote construction site can be
very demoralizing, after a while, and by keeping the morale level high, labor
turnover is reduced. Generally, the cost of importing labor will follow the
laws of supply and demand.
Weather
4. Construction Time
A project is estimated at a given point in time, but usually the actual
procurement and field construction occur at some point in the future.
Sometimes this future can be years away, especially in the case of a very
large or phased project. The estimate, then, must take into consideration
when the actual project will be built. Labor and material costs usually
escalate in time; so by examining past and current trends, the estimator can
predict where these costs will be at the time of actual construction.
Other:
An estimator who accurately incorporates project size, project quality,
location, and time has an estimate that reflects the fair value for the project.
20
In a normal market without any unusual circumstances, this estimate should
reflect the price that is paid.
Market conditions, however, shift; and owners, designers, and contractors all
look at a given project from different perspectives. In a market without much
work, contractors may bid a project at cost or with little profit to cover their
overhead and keep their staff employed. On complicated projects,
contractors may bid the work low in hopes of making significant profit on
future changes. Conversely, they may bid a work high to cover the increased
risks of a complex project. It is not unusual for contractors to offer very
competitive prices when they hope to enter a new market or establish a
relationship with a new owner. Such issues are very difficult to quantify but
should be considered in the preparation of the estimate. They are usually
treated as a percentage applied at the end of the estimate, included in either
overhead or profit or in a final contingency.
21
2. Construction Pricing and Contracting
Financial Proposal
Financial Pr.
Financial Proposal
23
In practice, because of contractor’s marketing policies, a contractor will find
he is in competition with a limited number of firms for any project in the
locality. A bidding pattern could be worked out for his major competitors.
If the contractor were able to identify the competition, an optimum bid could
be ascertained by combining the probability curves (the Z-distribution) and
developing a bidding curve using a linear regression line for this situation.
The following steps shall be followed by a competing firm to assume a
bidding strategy.
i) Preparation of a database of price quotations offered by competing
bidders. One has to collect and record the tender sum of each competitor
from the tender opening sessions. At least the winning price and the tender
sum of the contractor under consideration have to be recorded and put in a
database file for further undertakings.
Example:
Contract Contractor’s Least Bidder’s
No. Quotation Quotation
(Birr) (Birr)
1 500,000 450,000
2 750,000 750,000
3 1,000,000 800,000
4 625,000 600,000
5 850,000 800,000
6 250,000 250,000
7 400,000 350,000
8 1,200,000 1,000,000
9 900,000 875,000
10 1,100,000 950,000
ii) After having sufficient records of the respective bid prices, one could
plot the information on a scattered diagram.
X-axis: Contractor’s own tender prices
Y-axis: The least bidder and most responsive bidder’s price
For the example in (i), the scattered diagram looks the following:
24
1,200,000
1,000,000
800,000
600,000 Series1
Scattered Diagram
Winner’ Price
400,000
200,000
0
0 200,000 400,000 600,000 800,000 1,000,000 1,200,000 1,400,000
iii) Draw the most likely curve referred as a regression line. The simplest to
draw is a linear regression line that can be represented by:
Y = mX + b
Where: Y: refers to the most likely winning price,
X: refers to contractor’s tender prices
m & b are coefficients of the regression line.
m: The slope of the line
b: The intercept of the line.
n : number of samples.
b
y x x xy
2
n x x 2 2
n 1 2
VARIANCE
n2
s y m 2 sx2
25
Alternatively, Using The Microsoft Excel:
iv) The final step is to decide the probability of winning a tender using
the normal distribution. The chance of winning the tender by offering the
most likely price is 50%. A contractor can increase or decrease the
probability of winning the tender using the Z-normal distribution theory of
statistics.
Example: For the example in (i), suppose the contractor’s tender sum
amounts to 675,000 Birr. Determine the rebate to be improvised with 95 %
probability of winning the tender.
The most likely winning price, Y = 0.813(675,000) + 66476.91 = Birr
615,251,91 :- taken as the mean value (µ) with a winning chance of 50%.
The Z-values of 95% probability, from the table = 1.645. The relation
between Z, and probability in this case is inverse. Higher probability is
achieved by reducing the bid price and hence we need to use the negative
value of what we read from the table.
Yi
Z
Z= -1.645, µ = 615,251.91 and δ = 55509.2,
Yi = Birr 523,939.28
Rebate (R) = 100% -- (523,939.28/675,000) x100%
= 22.38 % (95% probability of wining)
= 8.9% (50% probability of winning)
26
2.1.2 Tendering Procedure
In order that the tendering policy of the firm be maintained it is necessary
that a procedure for the preparation of all tenders be established. This will
vary with different contractors, depending on size and personnel, but a basis
could follow the stages set out by the Ministry of Infrastructure.
Decision to Tender:
A management decision based on the firm’s position at the time of invitation
in relation to:
Production workload,
Future commitments,
Market,
Capital,
Associated risk,
Prestige, reputation
Estimating workload,
Time for preparation of tender,
Collection of Information:
If management decides to tender for the project, the estimating staff should
assemble information about project costs. An accurate estimate can only be
produced when each element is broken down into its simplest terms and the
cost estimated on factual information.
Some of the factors required include:
Time scale for tendering with key dates as mentioned in the invitation
to bid,
Examination of contract documents, with preliminaries attached with
the tender,
Assessment of client and design team,
Enquiries to suppliers and sub-contractors with a time scale,
Site and locality visit,
Discussion with site management, plant and planning department,
Evaluation of alternatives
Preparation of detailed construction method statement and pre-tender
programme, developed to include production outputs, gang sizes,
plant details, etc.
27
Preparation of estimate:
Having assembled all the information, the next task of the estimating staff is
to build the cost of the unit rates. This requires the calculation of all-in rates
for labor, plant, materials and extending these, using the production details
from the pre-tender programme. The cost of any on site administration and
services, known as project overheads is also calculated. These net
production costs, together with a project appraisal report are then submitted
to management for adjudication.
The tender:
The management of the firm would consider the mark-up required on the
estimated production costs, to cover the firm’s overheads, profit and risk of
the tender. These additional costs included, the tender figure can then be
determined and submitted.
Action with tender results:
An analysis of tenders and a comparison of results should be completed for
each project to provide a basis for future bidding strategy. With a successful
tender, cost information during the progress of the work and a final
reconciliation of estimated and final account costs should be made.
28
ii) Annual Turnover on contracts. This can be obtained from the firm’s
short term plan committed or planned for execution in the current
year.
iii) General overhead costs (off-site administration): can be identified
within a company’s accounts by items such as rent, telephone charges,
electric bills, office equipment hire charges, payment to staff directors
etc. Often it is established in relation with the total turnover planned
in the trading year.
Example for determination of firm’s mark-up:
Assumptions
Capital Employed: Birr 2,000,000
Turnover on contracts for year: Birr 4,000,000
General overheads: Birr 160,000
Return on Capital Employed 17%
Target: Contracts must contribute (Head office Mark-up)
General overheads Birr 160,000
Return ( ROCE) 17% ( 2,000,000 ) Birr 340,000
Head office Mark-up = Birr 500,000
29
Insurances on office and staff
Interest on capital borrowed
Each contract must contribute towards these costs; the usual method of
recovery is to express them in terms of a percentage of a previous year’s
turnover. For example, if last year’s turnover was Birr 2,000,000 and the
fixed costs Birr 160,000 then:
The general overhead cost used = 160000/ 2000000 = 8%
All owners want quality construction with reasonable costs, but not all are
willing to share risks and/or provide incentives to enhance the quality of
construction. In recent years, more owners recognize that they do not get the
best quality of construction by squeezing the last cash of profit from the
contractor, and they accept the concept of risk sharing/risk assignment in
principle in letting construction contracts. However, the implementation of
such a concept in the past decade has received mixed results.
Those public and private owners have found that while initial bid prices may
have decreased somewhat, claims and disputes on contracts are more
frequent than before, and notably more so in public than in privately funded
construction. Some of these claims and disputes can no doubt be avoided by
improving the contract provisions.
Since most claims and disputes arise most frequently from lump sum and
unit price contracts for both public and private owners, the following factors
are particularly noteworthy:
unbalanced bids in unit prices on which periodic payment estimates
are based.
change orders subject to negotiated payments
changes in design or construction technology
incentives for early completion and penalties of damage for late
completion,
31
Exceptional climatic condition or physical obstruction beyond the
capacity of an experienced contractor.
An unbalanced bid refers to raising the unit prices on items to be completed
in the early stage of the project and lowering the unit prices on items to be
completed in the later stages. The purpose of this practice on the part of the
contractor is to ease its burden of construction financing. It is better for
owners to offer explicit incentives to aid construction financing in exchange
for lower bid prices than to allow the use of hidden unbalanced bids.
Unbalanced bids may also occur if a contractor feels some item of work was
underestimated in amount, so that a high unit price on that item would
increase profits. Since lump sum contracts are awarded on the basis of low
bids, it is difficult to challenge the low bidders on the validity of their unit
prices except for flagrant violations. Consequently remedies should be
sought by requesting the contractor to submit pertinent records of financial
transactions to substantiate the expenditures associated with its monthly
billings for payments of work completed during the period.
In some projects, the contract provisions may allow the contractor to provide
alternative design and/or construction technology. The owner may impose
different mechanisms for pricing these changes. For example, a contractor
may suggest a design or construction method change that fulfills the
performance requirements. Savings due to such changes may accrue to the
contractor or the owner, or may be divided in some fashion between the two.
The contract provisions must reflect the owner’s risk-reward objectives in
calling for alternate design and/or construction technology. While
32
innovations are often sought to save money and time, unsuccessful
innovations may require additional money and time to correct earlier
misjudgment. At worse, a failure could have serious consequences.
36
3. Cost Estimating Approach
B) Detailed Estimate
37
same format facilitates the development of a cost database for use in
planning future projects.
Estimating Methods
There are four primary methods used to estimate construction costs. Those
methods are known as:
Project Comparison Estimating or Parametric Cost Estimating,
Area & Volume Estimating,
Assembly & System Estimating, and
Unit Price & Schedule Estimating.
Each method of estimating offers a level of confidence that is directly
related to the amount of time required to prepare the estimate: fig A
Square Foot & Cubic Foot Estimates are another method of developing
both preliminary and intermediate budgets based on historical data. This
method is effective in preparing fairly accurate estimates if the design is
developed enough to allow measurement and calculation of floor areas and
volumes of the proposed spaces. There are several historical databases
available to support this method of estimating providing unit costs that are
adjusted annually and many of the large estimating firms maintain their own
39
databases. More accurate estimates made with this method make
adjustments and additions for regional cost indices, local labor market rates,
and interpolation between available cost tables. Further adjustments may be
made to account for other unique aspects of the design such as special site
conditions or design features being planned. In addition, the estimate can
develop overall "core and shell" costs along with build-out costs of different
space types, allowing for relative ease of determining the impact of changes
to the program. Estimates made with this method can be expected to be
within 5% to 15% of accurate.
Assembly & Systems Estimates are intermediate level estimates performed
when design drawings are between 50% and 75% complete. Assemblies or
systems group the work of several trades or disciplines and/or work items
into a single unit for estimating purposes. For example, a foundation usually
requires excavation, formwork, reinforcing, and concrete— including
placement and finish— and backfill. An Assembly & Systems estimate
prices all of these elements together by applying values available in
assemblies cost data guides. Estimates made with this method can be
expected to be within 10% of accurate.
Unit Price and Schedule Estimating, the work is divided into the smallest
possible work increments, and a "unit price" is established for each piece.
That unit price is then multiplied by the required quantity to find the cost for
the increment of work. This calculation is often called "extending". Finally,
all costs are summed to obtain the total estimated cost. For example, the cost
to erect a masonry wall can be accurately determined by finding the number
of bricks required and estimating all costs related to delivering, storing,
staging, cutting, installing, and cleaning the brick along with related units of
accessories such reinforcing ties, weep-holes, flashings and the like. This
method of estimating provides the most accurate means of projecting
construction costs, beyond which accuracy is more likely to be affected by
supply and demand forces in the current market.
41
From these approximate comparative estimates, a decision is made to select
the sketch for preparation of its detailed design and estimate.
v) To obtain administrative approval: For government or public body
projects approximate estimate with a brief report and site plan has to be
submitted to obtain administrative approval to proceed with detailed with
detailed investigation and preparation of detailed estimate.
vi) For insurance and tax schedule: For insurance and tax schedule, the
value of a property or a project is drawn up from the approximated cost
estimate.
42
3.3 Detailed Cost Estimates
It is the task of the estimator to predict the cost of construction for the items
of finished works presented in the bill of quantities. An accurate cost
prediction can only take place when each item has been analyzed into its
simplest element and the cost methodology estimated on the basis of factual
information.
TENDER PRICE
INCLUDES
PRICED
PRELIMINARIES
UNLOADING
WASTE ALLOWANCE
NOMINATED
SUB-
CONTRACTORS
WORK
DOMESTIC LABOR ONLY
OVERHEADS
AND PROFIT
MARKET
ASSESSEMENT
43
The planning department of the firm does the analysis of the physical
resources required for the project and the deployment of these resources.
Pre-tender program will be prepared after consultation with other relevant
departments and evaluation of alternate construction methods and sequences.
The program would be presented as a network or bar chart to show
deployment of resources to constructional elements on a time scale. The
amount of detail developed would depend on the complexity of the project
and the time available for preparation. It should show the detailed labor and
plant requirements for each operation and the production outputs anticipated
for these resources. A schedule of labor and plant requirements is sometimes
prepared to amplify the program.
The task of the estimator is to evaluate the cost of the resources from the
program and to build up a unit rate for each finished work item. A
fundamental principle is that unit rates should be prepared net. A unit rate
prepared on this methodology will take into account methods of construction
and all circumstances which may affect the execution of work on the project.
It will consist of a prediction of the cost of the physical resources and mark-
up by management. These physical resources are: Labor, materials, and
plant.
labor and equipment costs. These are the categories of construction expense
44
that are inherently variable and the most difficult to estimate accurately
production rates from past projects (historical data), and obtain advance
45
The diagram below summarizes the components of unit rate build-ups.
46
47
d. Costs for sub-constructor:- If the work is to be subletted to a
nominated sub-contractor, the cost shall be determined and separately
established as a sub-contractor fee.
Ex. –Marble cladding
-Supply and fix items (aluminum frames)
-Furniture etc.
II. Indirect Costs
The project overheads are the cost of administering a project and
providing the general plant, facilities and site based services. They
consist of the items that cannot be satisfactorily allocated to individual
unit rates of finished work. The cost of some of the project are time
related and will be estimated in terms of the contract period or length
of time on site and the all-in rate for a unit of time, the information on
time being obtained from the pre-tender program. Other project
overheads are value related and will not be able to be evaluated until
after the adjudication process by management.
a. Site over head costs
Time-independent costs
Costs for site plant/ site installations
Cost for site facilities
Engineering and controlling
Operation risks
Special costs
Time-dependent costs
Commissioning /holding costs
Operating costs
Costs for contractor’s agent
b. General overhead costs
48
c. Risks and profit
b) Labor Costs
All costs, which result from the building /construction works of the
employees on site include:-
- Standard wages
- Extra and supplementary pay for
Production bonus
Long continuity of Service (permanent laborer)
Over time pay
Merit increase
Property creating performance
Less favorable condition /allowances
-Social Service payments
Holiday pay if any
50
Health insurance
Unemployment insurance
Payment during sickness
Required information for the calculation of labor cost
Number and type of skilled and unskilled manpower for a
particular type of work, (Crew)
Performance of crew per hour for a unit amount of work
Indexed hourly cost of the workman ship.
Utilization factor of the workmanship. Share of a particular
personal per hour for the specified work.
Example: Calculation of indexed hourly cost for carpenter
Standard wage:- 40 birr /day
Extra pay (for long continuity of service)
1Birr /hr for 60 % of the carpenters
Over time
50 weekly working hours / 44 weekly working hours/
6 overtime hours with 25% increment
Property- Creating performance
For 80% of the employees 0.25birr /hr
Supplements: 10% of wage
Solution:
Standard wage..........................................5 Birr /hr
Extra pay = 0.6 (1) ...................................0.6 birr/hr
Over time 6x0.25 x 5...............................0.15 birr/hr
50
Property creating performance 0.86(0.25) = 0.2 birr/hr
Supplements= 0.1(5) ..............................…..0.5birr/hr
Total..................................................…….. 6.45 b/hr.
c) Equipment cost
Required information
Type of equipment for a particular item of work.
Performance of equipment per hour for a unit amount of work
(production rate)
Two methods of calculation are followed.
I) With charges accounted for depreciation, interest return and monthly
repair costs
II) With monthly rental charges.
Example: Calculation of equipment cost for m3 of concrete
Mixer - Original cost = 50.000 Birr
Assume 8 working hours per
Useful life = 3yrs day and 22 days per month
Interest rate=6.5%
Monthly repair cost with supplies: - 700 Birr
Virbrator- Original cost = 5.000 Birr
Useful life = 7yrs
Repair cost monthly = 50 Birr
Hourly equipment cost
i) Mixer
Depreciation (d)
50,000 Birr = 7.89 Birr/hr
3x12(22x8) hr
52
Interest of return (i)
1/3 [50,000 (1+0.0665)3 - 50,000] Birr /year = 3465.83 Birr/year
Hourly cost 3465.88/(12x8x22) = 1.641 Birr/hr
Hourly repair cost = 700/8x22 = 3.98 Birr/hr
Hourly Mixer cost = 7.89 + 1.641+ 3.98 = 13.511 Birr/hr
ii) Virbrator
Depreciation (d)
5000/(7x12x8x22) = 0.338 Birr/hr
Interest return (i)
1/7 [ (5000 (1+0.065)7 - 5000] = 395.7 Birr/hr
395.7/(12x8x22) = 0.187 Birr /hr
Repair cost
50/(8x22) = 0.284 Birr /hr
Hourly virbrator cost = 0.338+0.187+0.284= 0.81 Birr/hr
Type of Hourly
equipment No UF Hourly rental rate Cost
Mixer 1 1 1 13.51 13.51
Virbrator 1 1 0.81 0.81
Total hourly cost
(Birr) 14.32
Example
2) Costs For Formwork
Two methods of calculation to be accounted
i) With monthly rental charges
Ex. Steel form works
ii) With charges according to the number of uses
54
3. Two approaches for cost calculation
i/ Cost Calculation with predetermined charges
Unit prices
(Rate)
Bid Sum
56
3 Concrete for tie beam M3 425
4 Dia 14 dc formed ban Kg 5
5 Dia 8 stirrups Kg 4.5
6 Formwork tie beam M2 45
7 20cm thick HCB wall M2 52
Direct cost 14,374 birr
Question: Establish bid sum and unit prices for the itemized works.
Step 1: Establish production cost. (Direct cost + Site overhead cost)
Direct cost :- 14,374 birr
Site overhead cost:- 5,600 birr
Production cost 19,974 birr
Step 2: Establish bid sum [production cost + General overhead cost + risk &
profit]
Production cost -------------------------------- 19,974 birr
General overhead cost = 10%(14,374)= 1,437.40 birr
Risk & profit ---------------7 %(14374)= 1,006.18 birr
Bid sum without vat = 22417.58 birr
vat 15% = 3362.64
Bid sum with vat = 25780.22 birr
Step 3: Surcharge on direct itemized cost
Surcharge = Bid sum without vat
57
Direct itemized cost
= 22417.58 = 1.5596 = 1.56
14374
Step 4: Establishing unit prices
Unit price = Surcharge x direct itemized cost
Item of work Unit Quantity Unit price Amount
1. Excavation m3 40 9.36 374.40
2. masonry wall m 3 25 288.53 7213.25
3. Concrete m3 5 662.83 3314.15
4. dia 4 bar kg 242 7.798 1887.116
5. dia 8 bar kg 132 7.018 926.376
2
6. formwork m 20 70.18 1403.6
2
7. HCB wall m 90 81.099 7298.91
58
4.0 VALUE ENGINEERING
Value Engineering is a systematic and organized effort to identify the
functions of a product, system or procedure and to attain that function with
minimum cost without jeopardizing quality, aesthetics, appearance etc. It is
an organized creative approach which has for its purpose the efficient
identification of unnecessary cost without scarifying reliability, performance
or maintainability.
59
Provides a method of generating ideas and alternatives for possible
solution to a problem,
Provides a vehicle for dialogue,
Documents the rationale for decisions,
Improves the value of goods and services.
60
functional requirements and provide more value to the completed
project.
4) Development of Technical Solutions:
The development phase involves creating design concepts for the
alternatives identified during the evaluation phase. This involves
developing detailed functional and economic data for each alternative.
Estimated Life-Cycle cost data is developed for each alternative and
compared with the estimated life-cycle cost of the components under
study. The advantages and disadvantages of each alternative are
identified. Alternatives are compared, and the ones representing the
best value are selected for presentation to the designer and the owner.
5) Presentation of Alternative Options:
The final step is the preparation of the value engineering proposals, in
which detailed technical and cost data are developed to support the
recommendations. The advantages and disadvantages of each
recommendation are described. The proposals are submitted to the
designer and the owner for proposal. If approved, the proposals are
incorporated into the design. If not approved, the design is not
changed.
61