100% found this document useful (1 vote)
368 views

Overhead Water Intze Tank Design

1) The document determines the height of stagging for a water tank foundation to be 25 meters based on calculations of total head, hydrostatic pressure, and minor head losses. 2) Dimensions are provided for the cylindrical tank wall, top and bottom domes, and various ring beams based on structural analysis and design considerations. 3) Reinforcement is designed for the tank components to resist stresses from water pressure and self-weight, with rebar sizes and spacing specified for the domes, wall, and ring beams.

Uploaded by

iqramoyale022
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
368 views

Overhead Water Intze Tank Design

1) The document determines the height of stagging for a water tank foundation to be 25 meters based on calculations of total head, hydrostatic pressure, and minor head losses. 2) Dimensions are provided for the cylindrical tank wall, top and bottom domes, and various ring beams based on structural analysis and design considerations. 3) Reinforcement is designed for the tank components to resist stresses from water pressure and self-weight, with rebar sizes and spacing specified for the domes, wall, and ring beams.

Uploaded by

iqramoyale022
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 19

DETERMINATION OF FOUNDATION

-From testing of soil sample

For clay =12˚

r = density of soil

= 1.76 gm/cm3

= 17.6 KN/m3

p = 100 KN/m3

1
9. DETERMINATION OF HEIGHT OF STAGGING

We know turbulent flow occurs in a pipe

So Re 4000

L = length of pipe,

v = mean velocity in pipe of flow

d = diameter of pipe

The kinematic viscosity of water ( ) = 0.01×10-4 m2/s

Assume diameter of pipe = 15 cm

Volume (V) = 350 m3

Only for one hour maximum velocity occurs in the pipe so the discharge during that period

0.097 0.0176

m/sec.

Maximum velocity =5.52 m/sec.

(O.K.)

2
Minimum length of pipe requirement

= 2 × height of building up to 3 storeys from the level + lateral distance up to the centre of tank

= 2 × 15.6 + 18

= 49.2 m

≈ 50 m

Head loss

= 5.40 m

HEIGHT OF STAGGING

Total hydrostatic pressure on tank P = ρgh

Total head =

Minor loss (assume) = 1 m.

Using total head = 29.5

Height of stagging = 29.5 – 4.5

= 25 m

3
DESIGN OF TOP DOME

Assume thickness of top dome = 100 mm.

Meridional thrust at edges

Dead load of top dome = 0.100 × 25 = 2.5 KN/m2

Live load on top dome = 0.75 KN/m2 (assume)

Total load P = 3.25 KN/m2

N/m

Meridional stress = MPa < 5 MPa (OK)

Maximum hoop stress occurs at the centre and its magnitude

0.30 N/mm2 0.3 MPa < 5MPa (OK)

Provide nominal reinforcement of 0.24%.

Use 8 mm bars.

Spacing

205 mm c/c.

Provide 8 mm bars @ 205 mm c/c radially and circumtentially as shown in figure.

4
The 205 mm c/c for radial bar is provided at the springing of the dome.

At the crown the spacing reduces to zero.

Hence the curtailment of radial bars may be carried out at the appropriate distance.

5
DIMENSION OF TANK

Inner diameter of cylindrical portion D = 12 m

Rise of top dome h1 = 1 m

Rise of bottom dome h2 = D/8 = 1.5 m (centre)

Free board = 0.15 m

Diameter of ring beam Do = 5/8 D = 7.5 = 8 m

Rise of bottom dome (side) ho = 3/16 × D

= 2.25 m

= 2.5 m

Capacity of tank:-

Radius of bottom circular dome:-

1.5 × (2R2 – 1.5) = 42

2R2 – 1.5 = 10.67

R2 =6 m

Sin Ɵ2 =

Ɵ2 = 41.8o

Radius of top circular dome:-

6
1 × (2R1-1) = 6 × 6

R1 = 18.5 m

Sin Ɵ1 = 6/18.5

Ɵ1 = 18.92o

Design of top ring beam:-

A ring beam is provided at the junction of top dome and the vertical wall to resist hoop tension
induced by the top dome.

Horizontal component of meridional thrust P1 = T1 cos Ɵ1

= 30897.15 cos 18.92o

= 29227.8 N/m.

Total hoop tension tending to rupture of beam =

Permissible stress in HYSD bars = 150 N/m2

Ash = 175366.8/150 = 1170 mm2

Provide 20 mm bars (314.15) as hoop.

Number of 12 mm bars = 1170 / 314.15

= 3.72

=4

Actual Ash = 4 × /4 × 202 = 1256.63 mm2

= 1257 mm2

Provide 4-20 mm ø hoop and 8 mm bars tie @ 205 mm c/c.

Hence the cross sectional area of concrete

1.3

Ac = 124841.53

Provide ring beam of 320 mm × 400 mm.

7
Design of cylindrical wall:-

In the membrane analysis the tank wall is assumed to be free at top and bottom maximum hoop
tension occurs at the base of the wall and its magnitude:-

Hoop tension at any depth x from the top

X (m) Hoop tension (N/m)


0 0
1 58800
2 117600

Minimum thickness of cylindrical wall = 3 H + 5

=3×2+5

= 11 cm.

Provide 20 cm at the bottom and taper it to 12 cm at top.

At x = 1 m.

Area of steel Ash = 58800/150

= 392 mm2

Provide 8 mm bars.

Aø = 50.26 mm2

Spacing = (1000 × 50.26) / 392

= 130 mm c/c.

At x = 2 m.

Area of steel Ash = 117600/150

= 784 mm2

Provide 10 mm bars.

Aø = 78.53 mm2

Spacing = (1000 × 78.53) / 784

8
= 100 mm c/c.

The hoop steel may be curtailed according to hoop tension at different height along the wall
provided 0.24% of minimum vertical reinforcement.

Average thickness of wall = (120+200) / 2 = 160 mm.

Ash = mm2

Provide 8 mm ø.

Aø = 50.26 mm2

Spacing = mm c/c.

Design of ring beam B3:-

Thickness =100 mm

Rise = 1.5 m (centre)

Base dia. = 8 m

Raidus of curvature = 6 m

Cos 41.8o = 0.745

The ring beam connect the tank wall within conical dome. The vertical load at the junction of the
wall with conical dome is transferred to the ring beam B3 by horizontal thrust. In the conical dome
the horizontal component of thrust causes hoop tension at the junction.

W = Load transferred through the tank wall at the top of conical dome / unit length.

Øo = Inclination of conical dome.

9
T = Meridional thrust in conical dome at the junction.

tan Øo = 2/2.5

Øo = 38.65

10
= 30897.15 sin 18.92

= 10018.32 N/m

(ii) Load due to ring beam B1 = 320 mm depth

= 400 mm width

= 0.32×(0.4-0.1)×1×25000

= 2400 N/m

(iii) Load due to tank wall =

= 8000 N/m

(iv) Seif load of beam B3 (1m × 0.6m say)

=(1-0.3) ×0.6×25000

= 10500 N/m

Total W = 10018.32 + 2400 + 8000 + 10500

= 30918.32 N/m

Sin Øo = sin 38.65 = 0.62 , cos 38.65 = 0.78

Force Pw due to load Pw1 = W tan Øo

= 30918.32 tan 38.65

= 24725.97 N/m

Force Pw caused due to water pressure at top of conical dome

Pw2 = rw × hd3

h = depth of water upto centre of ring beam

d3 = depth of ring beam

Pw2 = 9800 × 2 × 0.6

= 11760 N/m

Hence hoop tension in the ring beam is given by :-

P=

11
=

This is to be resisted by steel hoops the area of which is

Ash =

= 1460 mm2

Use 20 mm bars = 314.15

Number of 20 mm bars =

= 5 bars

Hence provide 5 ring of 20 mm dia bars.

Actual area As = π/4 × 20 × 5

= 1570 mm2

Stress in equivalent section =

= 0.35 N/mm2 < 1.2 N/mm2 (SAFE) (OK)

The 10 mm diameter distribution bara (vertical bars) provided in the wall@ 100 mm c/c should be
taken round the above ring to act as stirrups.

Design of conical dome :-

12
(a)Meridional thrust :-

Ww = Total weight of water on the conical dome

W = Weight of top dom, cylindrical wall etc.

Ws = Self weight of conical dome

Ww =

=3920098 N

Let the thickness of conical slab = 400 mm

Ww =

l=

= 3.2 m

Ws =

= 1005309.649 N

Weight W at B3 = 30918.32 N/m.

Hence vertical load W2 per metre run is given by

W2 =

=242353.22 N/m

Meridional thrust To in the conical dome

13
To = W2 / cos Øo

= 242353.22 / cos 38.65

= 310321.06 N/m.

Meridional stress = 310321.06 / (1000×400)

= 0.775 N/mm2 < 5 N/mm2 (Safe).

(b) Hoop stress

Diameter of conical dome at any height h’ above base is

D’ = 8 + (12-8)/2 × h’ = 8 + 2h’

Intensity of water pressure P = [(4+2)-h’]×9800

= [6-h’]9800 N/mm2

Self weight q = 0.4 × 25000

= 10000 N/mm2

Hoop tension

Po’= 333150.48 + 12548.4 h’2 + 12548.4h’2

h’ Hoop Tension
0 333150.48 N
1 353695.41 N
2 349144.86 N
2.5 337457.95 N

14
For maximum

33093.99 – 25096.8 h’= 0

h’= 1.31 m.

Maximum Po’ = 354969.2977 N

(c) Design of walls:-

Meridional stress = 0.775 N/mm2

Maximum hoop stress = 354969.29 N

Which is to be resisted by steel

As = 354969.29/150

= 2366.46 mm2

Area of each face = 1183.23 mm2

Spacing of 16 mm dia bars = (1000 × 201)/1183.23

= 170 mm c/c

Hence provide 16 mm dia hoops @170 mm c/c on each face.

Actual As = (1000 × 201)/170

= 1182 mm2

Maximum tensile stress in composite section =

=0.83 N/mm2 < 1.2 N/mm2 (Safe) (OK)

In the meridional direction the reinforcement = = 840 mm2

Or 420 mm2 on each face

Use 10mm diameter bars A = 78.53 mm2

Spacing = = 180 mm c/c

15
Hence provide 10 mm bars @ 180 mm c/c on each face with a clear cover 20 mm

DESIGN OF BOTTOM DOME


R2= 6 m

Ɵ2= 41.8

Weight of water on w0 on the dome is given by

W0= ϒw

D0=8,H0 =2.5 ,R2=6,h2=1.5,

W0=850471.35N

Let the thickness of bottom dome =250mm

Self Weight Ws =2πR2h2t2×25000

R2=6, h2=1.5, t2=0.25

Ws=353429.17N

Total Weight=1203900.52N

Meridional thurst=T2=

D0=8

T2=71866.98N/m

Meridional Stress=

=0.287N/mm2 <5N/mm2 safe o.k.

Intensity of load per unit area

P2=

R2 =6,h2=1.5

P2=21289.63N/m2

Max hoop stress at centre of dome

16
=255475.625N/mm2

=0.25N/mm2 <5MPa O.K.

Area of min steel=

=650 mm2in each direction

Use 10 mm Ɵbars

Spacing= =120mm

Hence provide 10mm ᶲ bars @ 120mm c/c in both direction also provide 16mm ø meridoinal bars
@170mm c/c near water face.

Design of bottom circular Beam B2

Inward thrust from conical dome =T0Sinøo

=310321.06 Sin38.65

=193814.5 N/m

Outward thrust from bottom dam=T2cosƟ2

=7866.98cos41.8

=56126.36N/m

Net inward thrust=137688.14N/m

Hoop compression in beam =137688.14×8/2

=550752.56N

Vertical load on beam ,per meter run=T0Cosø0+T2SinƟ2

=310321.06 Cos 38.6 +71866.98 Sin 41.8

=290423.93 N/m

Self weight of beam=0.6×1.2×25000

=18000N/m

Total load on beam=290423.93+18000=308423.90N/m

Let us support the beam on 8 equally spaced column at a mean dia 8m

Mean radius of curved beam R=4m

17
For support 8:-coefficient of B.H.& twisting moment in circular beam

2Ɵ=45o C1=0.066,C2=0.030,C3=0.005

Øm=9.5o ,Ɵ=π/4=22.5=π/8 Radius

wR2Ɵ=308423.9×42×π/4

=3875769.4

Max –ve B.M.at support M0=C1wR22Ɵ

=255800.78N.m

Max +ve B.M. at support Mc=C2wR22Ɵ

=116273.08N.m

Max torsional moment =C3 wR22Ɵ

=19378.84Nm

For σ cbc=8.5

Hysd bars σst=150 N/mm2

Neuteral axis depth factor (K)

K= m= = =10.98

=0.383

Lever Arm

J=1-K/3=0.872

R=1/2×σcbc×J×k=1/2×8.5×0.872×0.383

1.41

Mr=Rbd2

Req eff. Depth (d)-

255800.78=1.41×600×d2

d=550mm

18
However keep total depth =700mm from shear point of view.

Max shear force at support Fo=WRƟ

=308423.9×4×π/8

=484471.12N

S.F. at any point F=WR(Ɵ-φ)

=308423.9×4×(22.5-9.5) ×π/180

=279916.6N

B.M. at the pointy of max torssional moment φm=9.50

Mφ=WR2(ƟSinφ+ƟCosƟCosφ-1) sagging

=308423.9×42×(π/8×sin9.5+π/8×cot22.5×cos9.5-1)

=4934.78Nm sagging

The torsion moment at any point-

Mpt=WR2[Ɵcosφ-Ɵcosφsinφ-(Ɵ-φ)]

At the support φ=0 M0t=WR2 (Ɵ-φ)=0

At the mid span φ=Ɵ=22.5=π/8 radian

Mφt= WR2[ƟcosƟ]- =0

Hence we have the following combination of B.M. & torsional moment:-

(a)at the support

M0 =255800.78 NM(hogging or negative)

M0t=0

19

You might also like