Overhead Water Intze Tank Design
Overhead Water Intze Tank Design
r = density of soil
= 1.76 gm/cm3
= 17.6 KN/m3
p = 100 KN/m3
1
9. DETERMINATION OF HEIGHT OF STAGGING
So Re 4000
L = length of pipe,
d = diameter of pipe
Only for one hour maximum velocity occurs in the pipe so the discharge during that period
0.097 0.0176
m/sec.
(O.K.)
2
Minimum length of pipe requirement
= 2 × height of building up to 3 storeys from the level + lateral distance up to the centre of tank
= 2 × 15.6 + 18
= 49.2 m
≈ 50 m
Head loss
= 5.40 m
HEIGHT OF STAGGING
Total head =
= 25 m
3
DESIGN OF TOP DOME
N/m
Use 8 mm bars.
Spacing
205 mm c/c.
4
The 205 mm c/c for radial bar is provided at the springing of the dome.
Hence the curtailment of radial bars may be carried out at the appropriate distance.
5
DIMENSION OF TANK
= 2.25 m
= 2.5 m
Capacity of tank:-
R2 =6 m
Sin Ɵ2 =
Ɵ2 = 41.8o
6
1 × (2R1-1) = 6 × 6
R1 = 18.5 m
Sin Ɵ1 = 6/18.5
Ɵ1 = 18.92o
A ring beam is provided at the junction of top dome and the vertical wall to resist hoop tension
induced by the top dome.
= 29227.8 N/m.
= 3.72
=4
= 1257 mm2
1.3
Ac = 124841.53
7
Design of cylindrical wall:-
In the membrane analysis the tank wall is assumed to be free at top and bottom maximum hoop
tension occurs at the base of the wall and its magnitude:-
=3×2+5
= 11 cm.
At x = 1 m.
= 392 mm2
Provide 8 mm bars.
Aø = 50.26 mm2
= 130 mm c/c.
At x = 2 m.
= 784 mm2
Provide 10 mm bars.
Aø = 78.53 mm2
8
= 100 mm c/c.
The hoop steel may be curtailed according to hoop tension at different height along the wall
provided 0.24% of minimum vertical reinforcement.
Ash = mm2
Provide 8 mm ø.
Aø = 50.26 mm2
Spacing = mm c/c.
Thickness =100 mm
Base dia. = 8 m
Raidus of curvature = 6 m
The ring beam connect the tank wall within conical dome. The vertical load at the junction of the
wall with conical dome is transferred to the ring beam B3 by horizontal thrust. In the conical dome
the horizontal component of thrust causes hoop tension at the junction.
W = Load transferred through the tank wall at the top of conical dome / unit length.
9
T = Meridional thrust in conical dome at the junction.
tan Øo = 2/2.5
Øo = 38.65
10
= 30897.15 sin 18.92
= 10018.32 N/m
= 400 mm width
= 0.32×(0.4-0.1)×1×25000
= 2400 N/m
= 8000 N/m
=(1-0.3) ×0.6×25000
= 10500 N/m
= 30918.32 N/m
= 24725.97 N/m
Pw2 = rw × hd3
= 11760 N/m
P=
11
=
Ash =
= 1460 mm2
Number of 20 mm bars =
= 5 bars
= 1570 mm2
The 10 mm diameter distribution bara (vertical bars) provided in the wall@ 100 mm c/c should be
taken round the above ring to act as stirrups.
12
(a)Meridional thrust :-
Ww =
=3920098 N
Ww =
l=
= 3.2 m
Ws =
= 1005309.649 N
W2 =
=242353.22 N/m
13
To = W2 / cos Øo
= 310321.06 N/m.
D’ = 8 + (12-8)/2 × h’ = 8 + 2h’
= [6-h’]9800 N/mm2
= 10000 N/mm2
Hoop tension
h’ Hoop Tension
0 333150.48 N
1 353695.41 N
2 349144.86 N
2.5 337457.95 N
14
For maximum
h’= 1.31 m.
As = 354969.29/150
= 2366.46 mm2
= 170 mm c/c
= 1182 mm2
15
Hence provide 10 mm bars @ 180 mm c/c on each face with a clear cover 20 mm
Ɵ2= 41.8
W0= ϒw
W0=850471.35N
Ws=353429.17N
Total Weight=1203900.52N
Meridional thurst=T2=
D0=8
T2=71866.98N/m
Meridional Stress=
P2=
R2 =6,h2=1.5
P2=21289.63N/m2
16
=255475.625N/mm2
Use 10 mm Ɵbars
Spacing= =120mm
Hence provide 10mm ᶲ bars @ 120mm c/c in both direction also provide 16mm ø meridoinal bars
@170mm c/c near water face.
=310321.06 Sin38.65
=193814.5 N/m
=7866.98cos41.8
=56126.36N/m
=550752.56N
=290423.93 N/m
=18000N/m
17
For support 8:-coefficient of B.H.& twisting moment in circular beam
2Ɵ=45o C1=0.066,C2=0.030,C3=0.005
wR2Ɵ=308423.9×42×π/4
=3875769.4
=255800.78N.m
=116273.08N.m
=19378.84Nm
For σ cbc=8.5
K= m= = =10.98
=0.383
Lever Arm
J=1-K/3=0.872
R=1/2×σcbc×J×k=1/2×8.5×0.872×0.383
1.41
Mr=Rbd2
255800.78=1.41×600×d2
d=550mm
18
However keep total depth =700mm from shear point of view.
=308423.9×4×π/8
=484471.12N
=308423.9×4×(22.5-9.5) ×π/180
=279916.6N
Mφ=WR2(ƟSinφ+ƟCosƟCosφ-1) sagging
=308423.9×42×(π/8×sin9.5+π/8×cot22.5×cos9.5-1)
=4934.78Nm sagging
Mpt=WR2[Ɵcosφ-Ɵcosφsinφ-(Ɵ-φ)]
Mφt= WR2[ƟcosƟ]- =0
M0t=0
19