We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 12
Doc Number ISECC-MOS-0513
Method Statement
Rev A01| Sheet 14 of 21 |
| Client: ZAID AL HUSSAIN & BROTHERS GROUP | Project: RM-25 KING ABDULLAH INTERNATIONAL
GARDEN
| Contract No: 12104580 Location: Riyadh, K.S. A |
414
Grind the above area to remove the topcoat and surface layer of the pipes until the
pipes glass fibers are exposed.
Clean this area by dry clean cloth or by blowing or paintbrush and ensure that it is
fully dry.
Use rotary disc: grinder/sander to grind the area. This procedure shall remove the
shiny surface of the pipe. Grinding should not be done more than 2 hours in advance
of lamination. After 2 hours, if lamination has not begun, touch up grinding procedure
shall be repeated.
If it was grinded already, then no need to grind again, rather it should be clear with
dry rag and by touch up grinding.
Wipe the ground areas with clean solvent/by blowing/cloth to remove the collected
dust and any surface moisture. If solvent is used, it must be allowed to evaporate
completely. If the prepared surface is contaminated prior to the start of work, it
should be cleaned first with a clean dry rag and by touch up grinding.
Application of Cab-o-Sil Putty/Bonding Paste
Fill the gap if any between the two pipes with cab-o-sil putty or bonding paste.
Atter applied putty/paste has cured (10-15 Min), touch up grinding shall be
performed prior to the application of laminate layers.
Field Joint Kits
Do not use kits that have been previously opened or has been damaged. Do not use
any glass reinforcement that are wet or may have been previously exposed to
moisture.
Each supplied joint kit contains the required number of plies of chopped mat and
Multi Axial fabric according to the manufacturer specification.
Each layer is consisted of one or more sections to make up the complete layers
around the pipe circumference.
These sections are pre-cut to a specific length that can be handled easily.
Re-check the applicable layers configuration from the process sheets provided
The total numbers of plies are divided into the layers with the same number of plies
and that each layer begins and ends with chopped mat plies.Doc Number ISECC-MOS-0513
Method Statement
Rev A01| Sheet 15 of 21
Client: ZAID AL HUSSAIN & BROTHERS GROUP Project: RM-25 KING ABDULLAH INTERNATIONAL |
GARDEN
Contract No: 12104580 Location: Riyadh, K.S. A
Application of the layers
Before commencing the lamination procedure, polyethylene sheet or wood shall be
placed beneath the joint so that the ground shall not be contaminated from the
chemicals (resin, catalyst, etc.)
Thoroughly clean the pipe ends that are to be jointed
Prepare enough resin for approximately 20-30 minutes gel time by adding proper
amount of catalyst in the one-gallon half cut plastic pot.
Mix the resin along with the catalyst in percentage of 1-3%. For e.g. If we take resin
100 gms then the catalyst volume should range between 1-3 ml
Mix the catalyzed resin through mixing tongue to make it homogenous. Mix by stirring
continuously for at least 1 minute. The Pipe surface to be laminated shall be “clean,
not contaminated” and spread a thin layer of mixed resin on the pipe surface over
an area large enough to include the largest piece of chopped mat.
Lay a piece of chopped mat on the applied layer of resin
Dip the paint wooly roller into the resin (not very deeply) and apply it on the layer
mat smoothly all over the surface to wet out well.
Now lay out a piece of multi axial over the wet mat and apply the paint roller over
to it complete wet out. (It is to be noted that mat plies are always longer than glass
fabric so short of length in glass fabric shall be distributed equally over the mat).
Continue building up by mat and glass fabric plies as per the recipe provided by the
manufacturer.
Too many plies may not allow proper heat dissipation when the resin is under curing
process and could cause blistering in small dimension laminates.
Use the steel grooved roller slightly pressed to remove out the air bubbles. The angle
of groove roller shall be changed time to time in order to remove the air bubbles in
all directions.
Keeping in consideration that very limited time has left for the resin to start getting
gel, make sure all air bubbles have been taken out prior to start of the plies to
become hard.
Stop rolling as soon as the resin starts to gel.
Continue this procedure until all the sections of the first layer have beerrapisie
Make sure that each section overlaps with the other by minimum fitty eae yDoc Number ISECC-MOS-0513 |
Method Statement
Rev AO01| Sheet 16 of 21
Client: ZAID AL HUSSAIN & BROTHERS GROUP Ce AG AED U EHR anon ay
Contract No: 12104580 Location: Riyadh, KS. A
Allow this lay-up round to cure and cool (until it is comfortable to touch with the bare
hands) prior fo application of another round of plies. After proper curing on the
previous round, remove the shiny surface of the lay-up by scuff grinding as needed.
Always remove dust and restart lamination on a clean surface.
Complete the supplied number of plies application with the same procedure.
As per standard procedure of Amiantit Fiberglass industries, a full rich resin coating
shall be applied on the joint by using a paint roller. Final resin coating will be applied
only after completion of all required joint inspections, which includes thickness and
hardness of lamination.
Apply the layers in the sequence as supplied in the packet of each kit.
Lamination kits will be supplied in different widths creating a natural slope on both
edges of the joint after all the required number of plies have been applied on the
pipe.
The above procedure shall be same for both internal and external laminations.
Before Lamination
After Lamination
ill with putty I
Bonding paste
LaminationDoc Number ISECC-MOS-0513
Method Statement
Rev A01| Sheet 17 of 21
Client: ZAID AL HUSSAIN & BROTHERS GROUP Project: RM-25 KING ABDULLAH INTERNATIONAL
GARDEN
Contract No: 12104580 Location: Riyadh, K.S. A
4.1.6
Field Lamination Recipe
Refer Atfachment# 1 for Field Lamination Recipe.
5. Determination of Hardness Using Barcol Impressor
This test method covers the determination of hardness of the field joint using Barcol
Impresser.
$.1.1
5.1.2
5.1.3
Test Specimen
The test specimen can be a pipe, tank, end cap or a repair section free from
mechanical damage.
The specimen dimensions shall be large enough to ensure a minimum Smm in any
direction from the impresser point to the edge of the specimen.
Test Procedure
After proper curing of the laminate proceed for barcol hardness.
QC shall take at different locations ensuring the hardness as per the manufacturer
recommendations are achieved.
Installation of insulation and Jacket Pipe
After successful lamination and curing of the carrier pipe as per above explained
procedure contractor shall proceed with the installation of the PU Foam.
The PU foam shall be wrapped around the field joint acting as a intermediated
between the GRP cartier and Jacket pipe.
The PU foam in the liquid form shall be allowed to harden and segments of it shall
be used to wrap around the joint at site.
At the interface of the hardened segments of the PU foam same liquid can be
allowed to join and gel accordingly.
The PU foam can be either installed in segment as explained above or it can be
also injected on the area to achieve the profile and then leave it to cure.
Contractor shall follow best practice at site for this activity. cee
After proper hardening of PU foam and curing, contractor can then ts
installation of the jacket pipes. ?Doc Number ISECC-MOS-0513
Method Statement
Rev A01| Sheet 18 of 21
Client: ZAID AL HUSSAIN & BROTHERS GROUP. | Prolect: RM-25 KING ABDULLAH INTERNATIONAL|
GARDEN
Contract No: 12104580 Location: Riyadh, K.S. A
+ The jacket pipe will be supplied by the vendor in 2 parts which shall be assembled
and joint at site.
= Contractor to refer the drawings for the required no of plies and dimensions to joint
the two halves of the jacket pipe.
+ Belowis the pictorial representation (Fig B) of the field joint assembly for the jacket
pipes.
FIELD LAMINATIONS
ART WILL BE SUPPLIED IN TO TWO HALVES
AND WILL BE INSTALLED ABOVE THE PIPE JONT
(CONNECTION DETAIL BY BUTT & WREP LAVINATION,
FigB
6. Usage of Materials
The promoted resin is used by mixing it with catalyst with an appropriate ratio. This ratio
varies as per weathering condition, the hotter the weather less the amount of catalyst to
be added. On extreme hot weather condition, less than 1% catalyst mixed with resin to
achieve faster curing time.
Minimum amount of 1% (hot weather) it may even be less
—
catalyst required than 1% sometimes
Maximum amount of 3% (cold weather) it may be even more
o_—
catalyst required than 3% sometimes
Note: Above is based on the manufacture recommendation.Doc Number ISECC-MOS-0513
Method Statement
Rev A01| Sheet 19 of 21
Client: ZAID AL HUSSAIN & BROTHERS GROUP Project: RM-25 KING ABDULLAH INTERNATIONAL |
GARDEN
Contract No: 12104580 Location: Riyadh, K.S. A
+ Mix the catalyst as per the ratio described above and mix it through mixing tongue
or use a longer straight, clean wooden stick. The resin should be stirred for 1 minute
before use to have a good mixing before laminate layup.
+ At this stage, temperature will rise progressively (color change as well) until it reaches
to a peak signifying an end to the reaction
+ This temperature peak is accompanied by a rapid gelling of the materials.
+ Gradually it cools to a hard mass.
+ The gel time varies depending on the amount catalyst mixed with resin.
6.1 Catalyst Addition Chart
‘% of Catalystto Resin 3% Catalyst. 2% Catalyst 1% Catalyst
Temperature 13.46 °C 16-20°C 20.35 °C
RESIN CATALYST CATALYST CATALYST
500g 15 mi 40 mi 5 ml
kg 30 mil 20 mi 40 mi
2k 60 ml 40 mi 20 mil
3kg 90 mil 60 mil 30 ml
4k 120 mi 80 ml 40 ml
5k 150 mi 400 mi 50 ml
kg 4180 mi 120 mi 60 mil
Tks 210 ml 140 mi 70 mil
Bkg 240 ml 160 mi 80 mi
akg 270 ml 180 mi 90 mi
10 kg 300 mi 200 mil 100 mi
7. Safety Precaution
The chemical components required for the butt-strap joints present certain safety and
health hazards if not handled well. Following are the recommendations:
7.1 Hazards
Resin: Liquid resin contains styrene which is flammable. Its vapors may cause irritation of the
eyes, nose, and throat. Excessive inhalation may cause dizziness, drowsiness, or loss of
consciousness.
Catalyst: Methyl ethyl ketone peroxide is a strong oxidizing agent and is a fire and explosion
hazard. Its iritant to eyes, skin, and mucous membranes, and is known as sensitizer. It shall
be stored in original containers and only small quantity shall be taken to the workplace as
per site activities’ requirement.Doc Number ISECC-MOS-0513
Method Statement
Rev A01) Sheet 20 of 21
Client: ZAID AL HUSSAIN & BROTHERS GROUP | Project: RM-25 KING ABDULLAH INTERNATIONAL
GARDEN
Contract No: 12104580 Location: Riyadh, K.S. A
7.2 Precautionary Measures
+ Workin adequate ventilation. Wear dust/vapor mask while mainly working inside the
pipes.
+ All crew members shall use protective/safety glasses and rubber gloves.
+ Long sleeved shirts, long pants, and hats are recommended.
+ "NO SMOKING" sign in all lamination material storage and working area shall be
displayed.
+ All materials and chemicals shall be away from heat source, sparks, and open
flames.
7.3 First Aid Procedure
Inhalation: Move the victim to fresh air. The victim must inhale fresh air, without fresh air the
victim will be suffocated, and fatality may happen.
Eyes: Flush exposed eye with large amount of flowing water. In case of severity,
immediately obtain medical aid from nearest hospital.
Skin: Wash skin with soap using enough volume of water.
8. Personal Protective Equipment (PPE)
+ FRC Coveralls
+ Hard hat
+ Safety boots
+ Gloves (rubber and cotton)
+ Safety glass
+ Paper mask
+ Respirator with cartridge filters (for internal lamination works)
+ Full body harness (working at height)
+ Face shield to use during the grinding works.
+ Access fo suitable fire extinguishers tor intemal and external work faces.
oo ene
ak
44MIANTIT
4
ae,
Arey —
“TaianDoc Number ISECC-MOS-0513
Method Statement
Rev A01| Sheet 21 of 21
i Tec RIG
Client: ZAID AL HUSSAIN & BROTHERS GROUP Project: RM-25 KING ABDULLAH INTERNATIONAL}
GARDEN
Contract No: 12104580 Location: Riyadh, K.S. A
9
Quality Control for GRP Works
* Approved project ITP shall be referenced while inspection of piping activities
+ QC Inspector shall perform visual inspection for the laminated joints for
external/internal works. Hardness shall be checked using Barcol Tester.
* QC Inspector shall check the thickness using the P! Tape. Lamination width shall also
be measured.
+ QC Inspector shall keep all record of laminated joints as per approved ITP.
* Only Laminators certified by AMIANTIT shall perform lamination.
10.Notes
+ The above procedure are the minimum guidelines from the manufacturer to cary
out the Field lamination at site, in addition to this all the guidelines related to the
project must be adhered.
+ Refer to AFIL underground installation Guide Attachment#2 for more information and
details regarding Underground Installation of the GRP pipes.
+ Allthe safety and quality requirements relevant to the project must be adhered.
+ Incase of any critical challenges occurring during the site installation contractor to
contact vendor to provide suitable solutions.
11.Attachments
+ Attachment#1- Field joint Recipe for Carrier Pipes
+ Atfachment#2- Underground installation guide from the manufacturer
serio g
eesTACHMENT
/AMIANTIT 4
FIELD JOINT LAMINATION
(Process Sheet - z
Al External Lay-up)
For ND350-PN(ATM)-SN2500-UG
CUSTOMER : Zaid Al-Hussain & Brothers Group
PROJECT —: RM-25-King Abdullah International Garden
Order No. : 12104580
Wrap Dimensions
3 plies 800 gi? roving fabric"
1 ply 450 gim chop strand mat
a
SAMIANTIT
% cmon.
cae
“Reese
Confidential 5-Mar-2023
‘Amiantit FIBERGLASS Ind. Ltd Rev.0JAMIANTIT
FIELD JOINT LAMINATION
(Process Sheet —
Balance Lay-up)
For ND600-PN(ATM)-SN2500-UG
CUSTOMER : Zaid Al-Hussain & Brothers Group
PROJECT: RM-25-King Abdullah International Garden.
Order No. : 12104580
Wrap Dimensions
1 ply 450 gim? chop strand mat 3 plies 800 gi? roving fabric
Gin roving fabric™
100_gim® roving fabric*
800 gim* roving fabric*
850 gim® chop strand mat 200 200 mm
ts!
oe
ey goat 8
sages
Confidential 5-Mar-2023
Amiantit FIBERGLASS Ind, Ltd Rev.0AMIANTIT
FIELD JOINT LAMINATION
(Process Sheet — Balance Lay-up)
For ND1400-PN(ATM)-SN2500-UG
CUSTOMER : Zaid Al-Hussain & Brothers Group
PROJECT : RM-25-King Abdullah International Garden
Order No. : 12104580
Wrap Dimensions
1 ply 450 gim? chop strand mat
5 plies 800 gim? roving fabric*
|
—-
=e
oo
SS
‘Mat [450 gim? chop strand mat 267 267
Confidential 5-Mar-2023
Amiantit FIBERGLASS Ind. Ltd. Rev.0AMIANTIT
FIELD JOINT LAMINATION
(Process Sheet ~ Balance Lay-up)
For ND1700-PN(ATM)-SN2500-UG
CUSTOMER : Zaid Al-Hussain & Brothers Group
PROJECT — : RM-25-King Abdullah International Garden
Order No. — : 12104580
Wrap Dimensions
1 ply 450 gim? chop strand mat
6 plies 800 gim? raving fabric"
00. g/t roving fabrc™
500_gim™ roving fabric" 200 200
[800 gim* roving fabric
B00 9)
[B00 gi roving fabric
800 g/m® roving fabric’ 133, 4133
850 gim® chop strand mat 300. 300
i.
gS tS
epeon
Confidential 5-Mar-2023
Amiantit FIBERGLASS Ind. Ltd, Rev.0