Chapter6 AppraisalRisk
Chapter6 AppraisalRisk
SYLLABUS
1. Describe and discuss the difference between risk and uncertainty in relation to
probabilities and increasing project life.
2. Apply sensitivity analysis to investment projects and discuss the usefulness of
sensitivity analysis in assisting investment decisions.
3. Apply probability analysis to investment projects and discuss the usefulness of
probability analysis in assisting investment decisions.
4. Apply and discuss other techniques of adjusting for risk and uncertainty in investment
appraisal, including:
(a) simulation
(b) adjusted payback
(c) risk-adjusted discount rate
1. Risk and Uncertainty (Dec 07, Jun 11, Jun 12, Jun 15)
1. Risk can be applied to a situation where there are several possible outcomes and,
on the basis of past relevant experience, probabilities can be assigned to the
various outcomes that could prevail.
2. Uncertainty can be applied to a situation where there are several possible
outcomes but there is little past relevant experience to enable the probability of
the possible outcomes to be predicted.
Statement 1 Statement 2
A True True
B True False
C False True
D False False
2. Sensitivity Analysis (Dec 07, Jun 11, Dec 11, Jun 12, Jun 15)
NPV
Sensitivity = %
PV of project variable
(b) The lower the percentage, the more sensitive is NPV to that project
variable as the variable would need to change by a smaller amount to make
the project non-viable.
2.4 EXAMPLE 1
ABC Co is considering a project with the following cash flows.
Year Initial Variable costs Cash inflows Net cash flows
investment ($000) ($000) ($000)
($000)
0 7,000
1 (2,000) 6,500 4,500
2 (2,000) 6,500 4,500
Cash flows arise from selling 650,000 units at $10 per unit. ABC Co has a cost of
capital of 8%.
Required:
Solution:
The PVs of the cash flow are as follows.
Year Discount PV of initial PV of PV of cash PV of net
factor 8% investment variable costs inflows cash flow
$000 $000 $000 $000
0 1.000 (7,000) (7,000)
NPV = 1,024
The project has a positive NPV and would appear to be worthwhile. The sensitivity
of each project variable is as follows.
The cost of capital can therefore increase by 132% [(8 – 18.56)/8] before the NPV
becomes negative.
The elements to which the NPV appears to be most sensitive are the selling price
followed by the sales volume. Management should thus pay particular attention to
these factors so that they can be carefully monitored.
$000
Present value of sales revenue 50,025
Present value of variable costs 25,475
Present value of contribution 24,550
Present value of fixed costs 18,250
Present value of operating income 6,300
Initial investment 5,000
Net present value 1,300
What is the sensitivity of the net present value of the investment project to a
change in sales volume?
A 7·1%
B 2·6%
C 5·1%
D 5·3%
(ACCA F9 Financial Management Pilot Paper 2014)
By how many units must the estimate of production and sales volume fall for the
project to be regarded as not worthwhile?
A 2,875
B 7,785
C 8,115
D 12,315
T0 Outflow $110,000
T1-4 Inflow $40,000
At the company’s cost of capital of 10% the NPV of the project is $16,800.
Applying sensitivity analysis to the cost of capital, what percentage change in the cost
of capital would cause the project NPV to fall to zero?
A 70%
B 17%
C 5%
D 41%
6. A company has a cost of capital of 10%. Project A has the following present values.
$
Initial investment 300,000
Cash inflows 600,000
Cash outflows 100,000
A 33%
B 40%
C 67%
D 300%
To manufacture the new product, equipment costing $1·5 million will be acquired
immediately. The estimated residual value of this equipment in four years’ time is $0·5
million. The company calculates depreciation on a straight-line basis.
Required:
(a) Calculate the net present value of the decision to go ahead with the project. (5 marks)
(b) Undertake sensitivity analysis to show the change needed to each of the following
before a zero NPV is achieved:
(i) discount rate;
(ii) initial outlay on equipment;
(iii) net annual operating cash flows;
(iv) residual value of the equipment. (11 marks)
(c) Evaluate briefly the information produced in your answer to (a) and (b) above and
state, with reasons, whether or not the project should go ahead. (4 marks)
(Total 20 marks)
Strengths Weaknesses
(a) No complicated theory to (a) It assumes that changes to
understand. variables can be made
(b) Information will be presented to independently, e.g. material
management in a form which prices will change independently
facilitates subjective judgement to of other variables. This is unlikely.
decide the likelihood of the If material prices went up the firm
various possible outcomes would probably increase selling
considered. price at the same time and there
(c) Identifies areas which are crucial would be little effect on NPV.
to the success of the project. If (b) It only identifies how far a
the project is chosen, those areas variable needs to change. It does
can be carefully monitored. not look at the probability of
(d) Indicates just how critical are such a change.
some of the forecasts which are (c) It is not an optimising technique.
considered to be uncertain. It provides information on the
basis of which decisions can be
made. It does not point directly to
the correct decision.
3.2.2 EXAMPLE 2
A firm has to choose between three mutually exclusive, the outcomes of which
depend on the state of the economy. The following estimates have been made:
Determine which project should be selected on the basis of expected market values.
Solution:
Project A
Project B
Project C
State of the economy Probability Project NPV EV
$000 $000
Recession 0.5 180 90
Stable 0.4 190 76
Growing 0.1 200 20
186
3.2.3 EXAMPLE 3
ABC Co is considering an investment of $460,000 in a non-current asset expected
to generate substantial cash inflows over the next five years. Unfortunately the
annual cash flows from this investment are uncertain, but the following probability
distribution has been established:
At the end of its five-year life, the asset is expected to sell for $40,000. The cost of
capital is 5%.
Solution:
NPV calculation:
Time Cash flow DF 5% PV
0 (460,000) 1.000 (460,000)
1 95,000 4.329 411,255
2 40,000 0.784 31,360
NPV = (17,385)
Even though the ENPV is negative these figures show that there is a 70% chance of
the project giving a positive NPV. Some investors may consider the project
acceptable on this basis.
services it provides. Incremental fixed costs will be $215,000 per annum. The
project has a four-year life.
Calculate the three possible NPVs and the expected NPV. Comment on your
results.
Solution:
Question 2 – ENPV
Carcross Co engages in off-shore drilling operations for oil deposits. The company has
recently spent $5 million in surveying a region in the Gulf of Mexico and has found the
existence of significant oil deposits there. The sea bed in the region, however, has a rock
formation that may make access to the oil deposits difficult. The total oil deposits in the
region have been estimated at 30 million barrels but the amount extracted will vary
according to the conditions faced when drilling operations commence. The company’s
senior geologist believes that three possible outcomes are likely from drilling operations and
has made the following estimates concerning the percentage of total oil deposits that will be
extracted under each outcome:
If the company decides to go ahead with the drilling operation, an immediate payment of
$40 million for drilling rights, along with annual payments of $5 for each barrel of oil
extracted must be made to the Mexican government. Equipment costing $125 million must
be acquired immediately but drilling will not commence until the second year of the four-
year licence period. It is expected that, whichever of the above outcomes arise, the oil will
be extracted evenly over the drilling period. Annual operating costs (excluding any
payments to the Mexican government) will be $120 million in the first year and $160
million for each of the remaining three years of the licence. At the end of the licence period,
the equipment will be sold at a price that is equal to its original cost less $8 for each barrel
of oil that has been extracted.
Oil prices over the period of the drilling licence are estimated to be as follows:
3 $75
4 $100
(a) Calculate the expected net present value (ENPV) of the investment proposal.
(10 marks)
(b) Calculate the net present value of the worst possible outcome. (5 marks)
(c) Comment on the results of your calculations in (a) and (b) above. (2 marks)
(d) Discuss the weaknesses of the ENPV approach for decision-making purposes.
(3 marks)
(20 marks)
3.2.5 EXAMPLE 4
A company is considering a project involving the outlay of $300,000 which it
estimates will generate cash flows over its two year life at the probabilities shown
in the following table.
Year 1
Annual cash flow ($) Probability
100,000 0.25
200,000 0.50
300,000 0.25
Year 2
If cash flows in Year 1 There is probability of: That the cash flow in
is: Year 2 will be:
100,000 0.25 Nil
0.50 100,000
0.25 200,000
0.25 350,000
The company’s investment criterion for this type of project is 10% DCF.
You are required to calculate the expected value of the project’s NPV and the
probability that the NPV will be negative.
Solution:
$
EV of PV of cash inflows 344,420
Less: Project cost 300,000
EV of NPV 44,420
Measure risk:
Since the EV of the NPV is positive, the project should go ahead unless the risk is
unacceptably high. The probability that the project will have a negative NPV is the
probability that the total PV of cash inflows is less than $300,000. From the column
headed ‘Total PV of cash inflows’, we can establish that this probability is 0.0625 +
0.125 + 0.0625 + 0.125 = 0.375 or 37.5%. This might be considered an
unacceptably high risk.
The company has prepared the following forecasts of net cash flows for the next two
periods, together with their associated probabilities, in an attempt to anticipate liquidity and
financing problems. These probabilities have been produced by a computer model which
simulates a number of possible future economic scenarios. The computer model has been
built with the aid of a firm of financial consultants.
Required:
3.3.1 The disadvantage of using the EV of NPV approach to assess the risk of the project is
that the construction of the probability distribution can become very complicated.
If we were considering a project over 4 years, each year have five different forecasted
cash flows, there would be 625 (5 4) NPVs to calculate. To avoid all of these
calculations, an indication of the risk may be obtained by calculating the standard
deviation of the NPV.
3.3.2 EXAMPLE 5
Frame Co is considering which of two mutually exclusive projects, A or B, to
undertake. There is some uncertainty about the running costs with each project, and
a probability distribution of the NPV for each project has been estimated, as
follows.
+ 10 0.20 + 15 0.3
+ 20 0.35 + 20 0.4
+ 40 0.30 + 25 0.1
You are required to decide which project should the company choose, if either.
Solution:
Project A has a higher EV of NPV, but what about the risk of variation in the NPV
above or below the EV? This can be measured by the standard deviation of the
NPV.
Project A, = 18 Project B, = 16
x p x- p(x - )2 x p x- p(x - )2
– 20 0.15 – 38 216.6 5 0.2 – 11 24.2
10 0.20 –8 12.8 15 0.3 –1 0.3
20 0.35 +2 1.4 20 0.4 +4 6.4
40 0.30 + 22 145.2 25 0.1 +9 8.1
376.0 39.0
Project A Project B
Although Project A has a higher EV of NPV, it also has a higher standard deviation
of NPV, and so has greater risk associated with it.
Advantages Limitations
(a) The technique recognises that (a) By asking for a series of forecasts
there are several possible the whole forecasting procedure
outcomes and is, therefore, more is complicated. Inaccurate
sophisticated than single value forecasting is already a major
forecasts. weakness in project evaluation.
(b) Enables the probability of the The probabilities used are also
different outcomes to be usually very subjective.
quantified. (b) The EV is merely a weighted
(c) Leads directly to a simple average of the probability
optimising decision rule. distribution, indicating the
(d) Calculations are relatively average payoff if the project is
simple. repeated many times.
(c) The EV gives no indication of
the dispersion of possible
outcomes about the EV. The more
widely spread out the possible
results are, the more risky the
investment is usually seen to be.
The EV ignores this aspect of the
probability distribution.
(d) The EV technique also ignores
7. A risk averse investor is considering four mutually exclusive investments, which have
the following characteristics:
Which two of the above investments will the investor immediately REJECT?
8. When using the expected value criterion, it is assumed that the individual wants to
10. Which of the following are true in respect of using expected values in net present
value calculations?
A 1, 2 and 3 only
B 3 and 4 only
C 2 and 3 only
D 1, 2 and 4
11. Sales volumes are expected to be either 20,000 units with 60% probability or they are
expected to be 25,000 units. Price will either be $10 (0.3 probability) or else $15.
Margins are expected to be 30% or 40% of sales with an even chance of each.
A $103,950
B $193,050
C $297,000
D $105,000
12. An investment project has a cost of $12,000, payable at the start of the first year of
operation. The possible future cash flows arising from the investment project have the
What is the expected value of the net present value of the investment project?
A $11,850
B $28,700
C $11,100
D $76,300
(ACCA F9 Financial Management December 2014)
(1) The sensitivity of a project variable can be calculated by dividing the project net
present value by the present value of the cash flows relating to that project
variable
(2) The expected net present value is the value expected to occur if an investment
project with several possible outcomes is undertaken once
(3) The discounted payback period is the time taken for the cumulative net present
value to change from negative to positive
A 1 and 2 only
B 1 and 3 only
C 2 and 3 only
D 1, 2 and 3
(ACCA F9 Financial Management June 2015)
Required:
(a) Explain why risk and uncertainty should be considered in the investment appraisal
process. (5 marks)
(b) Calculate and comment on the payback period of the project. (4 marks)
(c) Evaluate the sensitivity of the project’s net present value to a change in the following
project variables:
(i) sales volume;
(ii) sales price;
(iii) variable cost;
and discuss the use of sensitivity analysis as a way of evaluating project risk.
(10 marks)
(d) Upon further investigation it is found that there is a significant chance that the
expected sales volume of 20,000 units per year will not be achieved. The sales
manager of Umunat plc suggests that sales volumes could depend on expected
economic states that could be assigned the following probabilities:
Calculate and comment on the expected net present value of the project.(6 marks)
(25 marks)
(ACCA 2.4 Financial Management and Control December 2004 Q5)
4. Adjusted Payback
(Jun 09, Jun 11)
4.1.1 Payback can be adjusted for risk:
(a) Higher risk project should require shortening the payback period.
(b) It puts the focus on cash flows that are more certain (less risky) because they
are nearer in time.
4.1.2 Discounted payback:
(a) It can be adjusted for risk by discounting future cash flows with a risk-
adjusted discount rate.
(b) The normal payback period target can be applied to the discounted cash
flows, which will have decreased in value due to discounting.
(c) The overall effect is similar to reducing the payback period with
undiscounted cash flows.
5. Simulation (模擬)
5.1 Sensitivity analysis considered the effect of changing one variable at a time.
Simulation improves on this by looking at the impact of many variables changing
at the same time.
5.2 Using mathematical, it produces a distribution of the possible outcomes from the
project. The probability of different outcomes can then be calculated.
5.3 EXAMPLE 6
The following probability estimates have been prepared for a proposed project.
Year Probability
Cost of equipment 0 1.00 (40,000)
Revenue each year 1–5 0.15 40,000
0.40 50,000
0.30 55,000
0.15 60,000
The cost of capital is 12%. Assess how a simulation model might be used to assess
the project’s NPV.
Solution:
For revenue, the selection of a random number in the range 00 and 14 has a
probability of 0.15. This probability represents revenue of $40,000. Numbers have
been assigned to cash flows so that when numbers are selected at random, the cash
flows have exactly the same probability of being selected as is indicated in their
respective probability distribution above.
A computer would calculate the NPV many times over using the values established
in this way with more random numbers, and the results would be analysed to
provide the following.
The decision whether to go ahead with the project would then be made on the basis
of expected return and risk.
Advantages Drawbacks
(a) It includes all possible outcomes (a) Models can become extremely
in the decision-making process. complex and the time and costs
(b) It is a relatively easily involved in their construction can
understood technique. be more than is gained from the
(c) It has a wide variety of improved decisions.
applications (inventory control, (b) Probability distributions may be
component replacement, etc.) difficult to formulate.
15. What is the main advantage of using simulations to assist in investment appraisal?