We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 7
‘213123, 1:21 PM 2.2 INTRODUCTION OF ESTIMATES: CEM 303-CE41S2 - Construction Cost Engineering
2.2 INTRODUCTION OF ESTIMATES
Preliminary Cost Estimate
Introduction to the Topic:
Hello Future Engineers! In every construction project, budgets are used to anticipate all costs and
expenses of the building process. There are two main parts of the budget - quantity and cost. Let's,
discuss!
Intended Learning Outcomes:
At the end of the session the students should be able to:
4. Lear and understand the different types of Estimates;
2. Acknowledge the purpose of Preliminary estimates.
QUANTITY SURVEYING
hntps:tip.instructure,comicoursesi¢6527/pages!2-dot2-itroduction-t-etimates ?module_em_a=4532618 wr127928, 1:21 PM 22 INTRODUCTION OF ESTIMATES: CEM 303-CE4182- Constucton Cost Engineering
This is originated from the combination of two words - Quantity means “number or amount of
material" and Surveying means “act of looking carefully at something"
Quantity Surveying is the estimation of the quantity of materials for a certain construction project
such as the volume of concrete, weight of steel, and other amounts of building materials. This
estimation will be used to determine the total project cost.
QUANTITY SURVEYOR
Quantity Surveyor is the "cost manager’ of a construction project. A quantity surveyor job is not
limited to the creation of a bill of materials and budget preparation, but also performs other vital roles
in a construction project such as contract procurement, tender evaluation, and value engineering.
The main objective of a quantity surveyor is to ensure the efficient and effective utilization of
resources (materials, manpower, money).
Types of Estimate
Acost estimate is predicted expenditure of a project which is generally prepared before the project is
taken up. It is prepared in different types based on the requirement of project.
The construction cost estimates can be prepared either in a detailed manner by taking into
consideration item by item or can be calculated approximately without going much into the details
Based on these criteria's, there are mainly 8 cost estimates followed in construction:
. Preliminary Cost Estimate
Plinth Area Cost Estimate
. Cube Rate Cost Estimate
Approximate Quantity Method Cost Estimate
. Detailed Cost Estimate
Revised Cost Estimate
. Supplementary Cost Estimate
Annual Repair Cost Estimate
SPNOAEYNS
Preliminary Cost Estimate
The preliminary cost estimate is also called an abstract cost estimate or approximate cost
estimate or budget estimate. This estimate is generally prepared in initial stages to know the
approximate cost of the project. By this estimate, the competent sanctioning authority can decide the
financial position and policy for the administration section.
ntps:hipnstructure.com/courses/46527 pages!2-dot-2-ntroducton-o-estimates?module_tem _j6°4532818 2‘aa, 11:21 Pm 22 INTRODUCTION OF ESTIMATES: CEM 303-CE4182- Constucton Cost Engineering
Preliminary estimates are prepared with reference to the cost of similar type projects in a practical
manner. In this estimate, the approximate cost of each important item of work is displayed individually
to know the necessity and utility of each item of work. The items of work include the cost of lands,
cost of roads, electrification, water supply costs, cost of each building, etc.
Plinth Area Cost Estimate
Plinth area cost estimate is prepared on the basis of plinth area of building which is the area covered
by external dimensions of building at the floor level and plinth area rate of building which is the cost
of similar building with specifications in that locality,
Plinth area estimate is obtained by multiplying plinth area of building with plinth area rate. For
‘example if we require plinth area estimate of 100 sq.m in a particular locality and plinth area rate of a
building in same locality is 2000 per sq.m then plinth area estimate is 100 X 2000 = 200000.
Open areas, courtyards, etc. are not included in the plinth area. If the building is multi-storied, the
plinth area estimate is prepared separately for each floor level.
Cube Rate Cost Estimate
Cube rate cost estimate of a building is obtained by multiplying plinth area with the height of building
Height of building should be considered from floor level to the top of the roof level. It is more suitable
for multi storied buildings.
This method of estimation is accurate than plinth area method. The rate per cubic meter is taken into
consideration based on the costs of similar type of buildings situated in that location. Foundation,
plinth and parapet above the roof level are not considered in this type of estimate
Approximate Quantity Method Cost Estimate
In approximate quantity method cost estimate, the total wall length of the structure is measured, and
this length is multiplied by the rate per running meter which gives the cost of the building. The rate
per running meter is calculated separately for the foundation and superstructure.
In case of foundation, rate per running meter is decided by considering quantities such as excavation
cost, brick work cost up to plinth. While in case of superstructure quantities like brickwork for wall,
wood works, floor finishing etc, are considered for deciding rate per running meter.
Detailed Cost Estimate
nitps:hipnstructure.comicourses/46527 pages!2-dot-2-ntroducton-o-estimates?module_tem _l6=4532818, a7‘aa, 11:21 Pm 22 INTRODUCTION OF ESTIMATES: CEM 303-CE4182- Constucton Cost Engineering
Detailed cost estimate is prepared when competent administrative authority approved the preliminary
estimates. This is very accurate type of estimate. Quantities of items of work are measured and the
cost of each item of work is calculated separately.
The rates of different items are provided according to the current workable rates and total estimated
cost is calculated. 3 to 5 % of estimated cost is added to this for contingencies as miscellaneous
expenditure,
The detailed Estimated should consist following details and documents.
+ Report
+ General Specifications
+ Detailed Specifications
+ Drawings/plans — layout plans, elevation, sectional views, detailed drawings etc.
+ Designs and calculations — In case of buildings design of foundations, beams, slab ete.
+ Schedule of rates
Revised Cost Estimate
Revised cost estimate is a detailed estimate and it is prepared when the original sanctioned estimate
value is exceeded by 5% or more,
The increase may be due to sudden increase in cost of materials, cost of transportation etc. The
reason behind the revision of estimate should be mentioned on the last page of revised estimate.
Supplementary Cost Estimate
Supplementary cost estimate is a detailed estimate and it is prepared freshly when there is a
requirement of additional works during the progress of original work, The estimate sheet should
consists of cost of original estimate as well as the total cost of work including supplementary cost of
work for which sanction is required
Annual Repair Cost Estimate
The annual repair cost estimate is also called as annual maintenance estimate which is prepared to
know the maintenance costs of the building which will keep the structure in safe condition.
Whitewashing, painting, minor repairs, etc. are taken into consideration while preparing annual repair
estimate for a building.
nitps:hipnstructure.comicourses/46527 pages!2-dot-2-ntroducton-o-estimates?module_tem _l6=4532818, anPurpose of Preliminary Estimate
You can get a preliminary estimate at the concept stage of your construction project, during the
initial design phase. The purpose is to provide you with an introductory cost of your project. Yours
can be done prior to the availability of detailed drawings. We are highly skilled in estimating at this,
stage of a project. Count on our state of the art systems to make your bids as accurate and timely as
possible.
Your preliminary estimate will give you insight into the cost of your project before detailed plans are
drawn up. You will be provided with a cost that you can present with confidence to your client, based
on our 30 years of estimating experience, using calculations determined on the latest software. You
can expect to receive a projected cost that is as accurate as possible based on the information you
provide,
We can use a building information model (BIM) to determine many factors of the preconstruction
plan just by using our point and click measuring system. Your bill of materials will be based on a
variety of measurements:
+ The square footage of each area
+ The square footage of your total project
+ The linear footage of each structure
As the concept changes, the BIM can also be changed and the new model can be viewed by all
parties. The bill of materials for your proposed project can be imported onto an Excel spread sheet to
be sent out for pricing. These prices can be used to further ensure accuracy. Of course, the more
information you provide, the greater the accuracy of the estimate.
The benefits of your having a preliminary estimate
made include:
- Increasing awareness of probable costs, in order to gain early financial commitment
-To determine costs for budget control
~To inform the architects and engineers of the cost of the project and the commitments you require
The information in the preliminary estimate will include:
- The date of the estimate and the expected tender date
- The drawings and brief specification details
- The expected variation from the estimate to the actual construction costs
- The more information provided, the narrower the variation will be.
nitps:hipnstructure.comicourses/46527 pages!2-dot-2-ntroducton-o-estimates?module_tem _l6=4532818, 87127928, 1:21 PM 2.2 INTRODUCTION OF ESTIMATES: CEM 303-CE41S2 - Construction Cost Engineering
preliminary estimate is often based on templates and information from past projects. This is why
you will benefit from an experienced estimating team like ours. We can draw upon the history of
comparable projects. These may be based on factors that can include project type, geographical
region and methods of construction. Very often, they are based on building type multiplied by the
square foot cost. For example, a school is estimated at so much per square foot multiplied by the
total square footage of the particular project. The same may be applied to office buildings of a few
floors. High rise projects may be calculated by a floor cost x the number of floors.
With the advantage of a highly experienced estimation team, the calculation of costs for your
estimate can help you to avoid strain on your builder/client relationship. There is no substitute, in any
stage of the estimating process, for a seasoned professional providing the most precise projection
possible. Let us show you how we can lead you from concept to completion with the latest
technology available in the industry today.
END OF DISCUSSION-——
Reference:
Fajardo, Max (2000). Simplified Estimates. 5138 Merchandising
Other Reference:
Pellicer, Eugenio (2014). Construction management. West Sussex, United Kingdom: John Wiley &
Sons
Godwin, William (2013). Intemational construction contracts: a handbook with commentary on the
FIDIC design-build forms. West Sussex, United Kingdom: Wiley-Blackwell
Ritz, George J. (2013). Total construction project management. New York, New York: McGraw-Hill
Education
Proprietary Clause
Property of the Technological Institute of the Philippines (T.I.P.). No part of the
materials made and uploaded in this learning management system by T.I.P. may
be copied, photographed, printed, reproduced, shared, transmitted, translated,
nitps:hipnstructure.comicourses46527 pages!2-dot-2-ntroducton-o-estimates?module_tem._|6=4532818 8712923, 1:21 PM 2.2 INTRODUCTION OF ESTIMATES: CEM 303-CE41S2 - Construction Cost Engineering
jor reduced to any electronic medium or machine-readable form, in whole or in
part, without prior consent of T.I.P.
“Many are the plans in a person's heart, but it is
the lord's purpose that prevails.’
-Proverbs 19:21
CLICK "NEXT" FOR THE NEXT MODULE.
RETURN TO HOME PAGE? CLICK BELOW.
Home Page (Construction Methods and Project Management)
(http: instructure.com/courses/13359)
nitps:hipnstructure.com/courses!46527 pages!2-dot-2-ntroducton-o-estimates?module_tem _|6=4532818,