Chap 2
Chap 2
LITERATURE REVIEW
concrete, and large-panel formwork. The selection of tower cranes and their
appropriate positioning can significantly affect the costs and overall productivity of
the construction operation (Hasan et al. 2013; Tam and Tong 2003).
location of tower cranes and material supply points on the construction site to
minimize the costs of lifting operations (Lien and Cheng 2014; Tam et al. 2001;
Huang et al. 2011). The demand points on a construction site are usually dictated
by the location and shape of the building. The tower crane location determines the
travel time of materials between the supply and demand points and thus the
operating costs.
additionally account for the vertical displacement due to vertical hook movement
(Lien and Cheng 2014). Minimizing the operation time of the tower crane, which
directly affects its operating costs, has been extensively studied in the literature.
Zhang et al. developed an analytical model that considered tower crane hooks' travel
3
4
time and adopted a Monte Carlo simulation to optimize tower crane location (Zhang
et al. 1999).
a developed model on a residential project. Come out with the result, a 31.9%
Crane lift capacity is determined from a radius-load curve where the greater
the load, the smaller the crane’s operating radius. Assuming a load at the supply
point (S), its corresponding crane radius is r. Therefore, a crane is unable to lift a
load unless it is located within a circle with radius r [Picture 2.1(a)]. To deliver a
load from (S) to demand point (D), the crane has to be positioned within an elliptical
area enclosed by two circles, shown in [Picture 2.1(b)]. This is called a feasible task
area. The area's size is related to the distance between S and D, the weight of the
load, and crane capacity. The larger the feasible area, the more easily the task can
Three geometric relationships exist for any two feasible task areas, as
illustrated in Picture 2.2; namely, (a) one fully enclosed by another (tasks 1 and 2);
(b) two areas partly intersected (tasks 1 and 3); (c) two areas separated (tasks 2 and
3). As indicated in cases (a) and (b), by being located in area A, a crane can handle
both tasks 1 and 2, and similarly, within B, tasks 1 and 3. However, case (c) shows
that tasks 2 and 3 are so far from each other that a single tower crane is unable to
handle both without moving location, so more than one crane or greater lifting
5
capacity is required. The closeness of tasks can be measured by the size of the
overlapping area, e.g., task 2 is closer to task 1 than task 3 because the overlapping
area between tasks 1 and 2 is larger than that for 1 and 3. This concept can be
extended to measure the closeness of a task to a task group. For example, area C in
picture 2..2(b) is a feasible area of a task group consisting of three tasks, where task
5 is said to be closer to the task group than task 4 since the overlapping area between
C and D is larger than that between C and E. If task 5 is added to the group, the
feasible area of the new group would be D, shown in Figure 2.2.(c). (Zhang et al.
1999)
Tower Crane has many models that are adapted to the conditions project.
types of crane. The mast of the self-supporting tower crane must be firmly
special mast base section cast into a foundation. They are particularly
suitable for confined sites and should be positioned in front or to one side
coverage of the new structure. Generally, these cranes have a static tower,
but types with a rotating or slewing tower and luffing jib are also available.
The details and overview of this crane can be seen in figure 2.3.
are used for lifting to a height over that possible with self-supporting or
traveling tower cranes. The tower or mast is fixed or tied to the structure
using single or double steel stays to provide the required stability. This tying
back will induce stresses in the supporting structure, which must therefore
because a luffing jib mast's rotation renders it unsuitable for this application.
traveling crane could be used. The crane travels on heavy wheeled bogies
1 in 200 and curves not less than 11.000 m radius depending on mast height.
The base for the railway track sleepers must be accurately prepared, well-
crane reverses to reduce the risk of the cable becoming cut or trapped by the
capacities and jib arrangements as given for static cranes. The complete
4. Climbing Cranes
These are designed for tall buildings, being located within and
steel collars, frames, and wedges. The raising of the static mast is carried
out using a winch that is an integral part of the system. Generally, this form
construction area than a static or similar tower crane. The jib is made from
small, easy-to-handle sections, which are lowered down the face of the
attached to one section of the crane. The winch is finally lowered to ground
level by hand when the crane has been dismantled. Figure 2.6 show the
The parts of tower crane are shown in picture 2.7, the detail as follows:
1. Jib
A jib is the longest part and can rotate by 360 ° with a function to lift the
material.
2. Counter Jib
The extension part of the jib to maintain the jib stay balance, usually
3. Counter Weight
4. Pendant/Tie rod
The wire that hold the jib in a 90o condition with the tower.
5. Cat Head
Center of cable ties from jib and counter jib. It is located on the top of the
TC.
6. Trolley
7. Hook
8. Operator Cabin
9. Slewing Ring
11. Mast
12. Base
The Mechanism movement can be seen in figure 2.7, with the detail as
follows.
1. Hoisting
2. Trolleying
jib.
12
3. Slewing
4. Traveling
5. Luffing
Luffing is a horizontal jib movement. The jib can move more than 90o.