ITR-MRE (Rotating Equip.)

The document is an inspection and test report for equipment foundation. It includes checks of the foundation elevation and location, bolt positions, and pad levels. Measurement data is presented in tables. The inspection found the results to be acceptable.

Uploaded by

mahmoud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
93 views25 pages

ITR-MRE (Rotating Equip.)

The document is an inspection and test report for equipment foundation. It includes checks of the foundation elevation and location, bolt positions, and pad levels. Measurement data is presented in tables. The inspection found the results to be acceptable.

Uploaded by

mahmoud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 25

INSPECTION AND TEST REPORT REPORT. NO.

:
FOR PAD LEVEL PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ FOUNDATION CHECK
Projection DWG:
Elevation Actual:
DWG:

Actual:

UNIT : mm
No. Elevation No. Elevation
1 16
2 17
3 18
4 19
5 20
6 21
7 22
8 23
9 24
10 25
11 26
12 27
13 28
14 29
15 30

Tolerance :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject


Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-001
INSPECTION AND TEST REPORT REPORT. NO. :
FOR EQUIPMENT FOUNDATION PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ EQUIPMENT LOCATION CHECK (BOX TYPE)

DIS. CENTER

SUC. CENTER

Tolerance :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject


Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-002
INSPECTION AND TEST REPORT REPORT. NO. :
FOR PAD PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

Bolt No. "A" Pad "B" Pad Result Remarks

Equipment "A" (Running) Equipment "A"


1 2 3 1
2
3
4
4 5 6 5
6

Equipment "B" (Stand-by) Equipment "B"


1 2 3 1
2
3
4
4 5 6 5
6

Unit : mm

Elevation : See table


Tolerance : ±3mm

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-003
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF ROTATING
EQUIPMENT(1ST, 2ND) PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ COUPLING ALIGNMENT (1st, 2nd) UNIT : mm

90

TOLERANCE : ±0.05mm

POSITION AXIAL RIM

90

180

270

◎ COUPLING DISTANCE

DWG : ACTUAL :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-004A
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF ROTATING
EQUIPMENT(FINAL) PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ COUPLING ALIGNMENT (FINAL) UNIT : mm

90

BEFORE PIPING TOLERANCE : ±0.05mm AFTER PIPING

POSITION AXIAL RIM POSITION AXIAL RIM

0 0

90 90

180 180

270 270

◎ COUPLING DISTANCE

DWG : ACTUAL :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-004B
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF COMPRESSOR &
TURBINE(1ST, 2ND) PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ COUPLING ALIGNMENT (1st, 2nd) UNIT : mm

TOLERANCE : ±0.05mm
COMPRESSOR TURBINE
POSITION
DWG ACTUAL DWG ACTUAL

90

180

270

◎ COUPLING DISTANCE

DWG : ACTUAL :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-005A
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF COMPRESSOR &
TURBINE(FINAL) PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ COUPLING ALIGNMENT (FINAL) UNIT : mm

BEFORE PIPING TOLERANCE : ±0.05mm AFTER PIPING


COMPRESSOR TURBINE COMPRESSOR TURBINE
POSITION POSITION
DWG ACTUAL DWG ACTUAL DWG ACTUAL DWG ACTUAL

0 0

90 90

180 180

270 270

◎ COUPLING DISTANCE

DWG : ACTUAL :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-005B
INSPECTION AND TEST REPORT REPORT. NO. :
FOR GROUTING WORK PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev. No. :


Results
No Items to be Checked Remarks
Accept Reject
1 Foundation Chipping Condition

2 Foundation Chipping Condition

3 Formworks

4 Foundation Wet Condition

5 Grouting Works

a.) Grout Material and Water Ratio

b.) Mixed Grout Temperature

c.) Casting Method

d.) Finishing Works

6 Curing of Grout at site

7 Cube sample

a.) 3 Days

b.) 7 Days

c.) 28 Days

Tolerance :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject


Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-006
INSPECTION AND TEST REPORT REPORT. NO. :
FOR HORIZONTAL CENTRIFUGAL
COMPRESSOR(LEVELING WORK) PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ LEVELING WORK UNIT : mm

Tolerance :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-007
INSPECTION AND TEST REPORT REPORT. NO. :
FOR MULTIPLE OR SKID WITH
LOCATION PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

Location
Elevation
North ( N-S ) East ( E - W )

Drawing Actual Drawing Actual Drawing Actual

1)

2)

3)

Tolerance : UNIT : mm

Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-008
INSPECTION AND TEST REPORT REPORT. NO. :
FOR SETTING INSPECTION OF
HORIZONTAL PUMP PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

◎ ELEVATION CHECK UNIT : mm

X Elevation DWG :

Actual :
(Tolerance ±3mm)

(Allowable ±3mm)

◎ LEVELING WORK

Allowable : 0.05mm

Tolerance :

Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-009
INSPECTION AND TEST REPORT REPORT. NO. :
FOR COUPLING ALIGNMENT PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

Date & Time :

Ambient Temperature(°C) :

Dial "B"

Dial "A"

*1 "C"

Alignment
Description Gap "C" Result
Dial "A" Dial "B"

90°

180°

270°
*1. See the Anchor Bolt Check List
Tolerance :

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-010
INSPECTION AND TEST REPORT REPORT. NO. :
FOR FINAL INSPECTION PAGE : OF

PROJECT: JOB NO.:

Area / Unit : Date :

Location : Subcon. Name :

Equipment Name : Equipment No. :

Ref. Dwg. : Rev No. :

Result
No. Items to be Checked Remarks
Accept Reject

. Check the name plate is properly attached to the equipment.

. Check the foundation bolts are securely tightened.

. Check the insulation condition.

. Check the equipment for internal cleanliness before final sealing.

Check whether the lubrication system has been properly flushed and is
.
clean.

Check the direction of rotation. An arrow, indicating the direction of


.
rotation.

. Check the shaft alignment between driving and driven unit.

. Check cold setting position of spring hanger.

. Check whether coupling is clean and lubricated.

. Check coupling guard and flexible connections.

Note :

Inspection Result : □ Accept □ Conditionally Accept □ Reject

Inspection by Subcontractor Contractor Client

Name

Signature

Date
Form No. : ITR-MRE-011