Aamonium Nitrate Production Sample Report
Aamonium Nitrate Production Sample Report
AT
VILLAGE BAGDIA, CHAUKIMATHA, RANGIAGARH
TEHSIL PARADEEP, DISTRICT JAGATSINGHPUR,
DISTRICT ODISHA
Project Proponent
M/s DEEPAK FERTILISERS &
PETROCHEMICAL CORP. LTD
Submitted to
Ministry of Environment, Forest & Climate Change
New Delhi
1
TABLE OF CONTENTS
2 INTRODUCTION Pg6
2
EXECUTIVESUMMARY
The project will consist of 900 MTPD Weak Nitric Acid plant, 1,140 MTPD Ammonium
Nitrate Solution plant and a Technical Ammonium Nitrate Prilling plant out of which
both LDAN and HDAN can be produced. The plant will be located at Paradeep, Orissa.
The plant will utilize nearly 83.26 acres of land.Ammonia plant of 380 TPD will be
relocated from Taloja to this site also.
The main raw material Ammonia will be imported through Paradeep port. Existing
Ammonia storage tanks / terminals of one of the industries, which is near of project
site, will be used on hired basis through a long-termcontract for importing and storing
Ammonia. TheAdditionally NG from Dharma pipeline Adani will be sourced from cross
country pipeline.
Water is available from Taladanda canal and will be sourced from the same
for which required applications are already submitted to concerned
departments. A dedicated power line will be installed from nearby substation
ofCESCO/GIRDCO.
Nitric Acid will be produced from Ammonia and will serve as an Intermediate
for manufacturing TAN
The Ammonium Nitrate will be trucked from the site to the customer. The
Ammonium Nitrate plant is expected to be on stream for 330 days per year.
2. INTRODUCTION
2.1. Background
Deepak Fertilizers& Petrochemicals Corporation Limited (DFPCL) is a 35-year-
old company engaged in manufacture and marketing of Ammonia/ Nitric
Acid/Sulphur based fertilizers, Formulated Nutrients based fertilizers, Technical
Ammonium Nitrate (TAN), Nitrogenous and Phosphatic Fertilizers, Methanol, Iso-
Propyl Alcohol (IPA) & other Industrial &Petrochemical products.
3
Some of the notable attributes of the company are:
A 600 plus million US$ company having over three decades of experience of
products
The only IPA and TAN manufacturer in India and the largest Nitric Acid and
4
The process plants are controlled through most modern DCS based control
systems.
DFPCL currently manufactures 410,000 MTPA of high density and low density
Ammonia Nitrate products at its Taloja complex in addition to 40,000 MTPY TAN at
Smartchem, Srikakulum which is 100 % subsidiary company of DFPCL.
The company has worked with all major technologies for Nitric Acid and Ammonium
Nitrate (M/s Uhde Germany, GPN France, Chematur Sweden, Plinke Germany,
Weatherly, Spain etc) and over years improvised the same to achieve higher
productivity, better efficiencies and lesser effluents.
5
Ammonia shall be manufactured in house having capacity of 380 TPD & balance
will be outsourced as mentioned.
The company already has the basic & detailed engineering packages ready and key
equipment are readily available from reputed manufacturers. The project is based
on the feasibility study carried out internally by the company.
This state of the art complex with fixed assets of more than 1,700 crores is
located at MIDC, Taloja near Mumbai. The company has impeccable record of
over 30 years in the industry with excellent reputation and relationship with its
Bankers, Customers, Suppliers and Shareholders. The company’s shares are
listed and traded on BSE and NSE.
DFPCL follows the best safety practices and has won British Safety Awards
multiple times. It has maintained excellent environment records.
6
The World class facilities to manufacture Nitric acid / Technical Ammonium
Nitrate along with related off-sites and utilities facilities proposed to be set up at
Paradeep,Also Ammonia Plant will be relocated from Taloja
Odisha requires apart from financial strength, project execution skills,
experience in operating large scale continuous process plants and the ability to
maintain high safety and environmental standards.
DFPCL has demonstrable experience and track record in all these areas.
7
Figure 2:Project Location (Topo Map)
The project location, in addition to proximity to major markets (Coal and Iron
Ore mining) is selected based on the following criterion.
The site is located along the Cuttack-Paradeep railway line and adjacent to
IOC Refinery township.
2. The distance from the Paradeep sea port to Plant site is a @ 10-12Km.
3. Location of plant is close to the major Mining hub especially coal i.e.
Chhattisgarh, Jharkhand, Odisha.
4. DFPCL already have possession of 340,000 Sq. Meter of prime land suitable for
industrial activities. The IOCL refinery, Paradeep Phosphates Limited (PPL),
IFFCO etc refinery/petrochemicals/Fertilizer complexes are within the radius of
10 Kms of DFPCL land
5. DFPCL Plan to capture both domestic market (eastern & central India) as well as
8
export market (Australia, SEA etc) from the aforesaid plant.
The project is proposed to be set up in a part of a total 83.26 Acre plot of land.
This area has good infrastructure of roads and good connectivity with the port.
The process plants area will be around 20 acres. The area required for
supporting facilities shall be about 20 acres more. Hence land acquired is
sufficient to accommodate the main process plants, other offsite facilities, road,
drains, green belt required for the project and most importantly to meet the
revised AN regulation related to storage and transportation of AN products.
The implementation of the project will be carried out with the Deepak Project
team and the reputed engineering company under engineering, procurement
& construction management (EPCM) Contract working in parallel and
interfacing where appropriate. The EPCM team will consist of the Technology
Provider and Engineering Contractors.
The basic process engineering for the Ammmonia, Nitric Acid plant and the
Ammonium Nitrate plant will be carried out in the office of the technology
provider.
will be carried out by the EPCM Contractor. Based on the data from the
technology suppliers, EPCM Contractor will carry out utility and infrastructure
requirements. Project construction will be carried out by construction
contractors operating under the management of Deepak and the local EPCM
contractor’s site team.
9
2.5. Capital Cost
3. PROJECTDESCRIPTION
Deepak intend to produce Ammonium Nitrate Melt and TAN Prills at Paradeep,
Odisha utilizing Imported/domestic anhydrous Ammonia and NG as feedstock.
The project will consist ofAmmonia 380 TPD and 900 MTPD Nitric Acid plant and a
total capacity of 1140 MTPD Technical Ammonium Nitrate plant. These facilities will
comprise of the following:
Kgsbags in the initial stage and 1000 Kgs and 1200 Kgs jumbo
bags(later ifrequired).
Ammonium nitrate Melt storage (2000 tonnes) and dispatch facilities for
400 MTPD;
The TAN prills will be transported from the site in enclosed trucks or by
containers using 25 Kgs, 50 Kgs bags or 1000 Kgs, 1200 Kgs Jumbo bags. The
Ammonium Nitrate Solution will be transported in Road tankers.
For the power supply to the plant, a dedicated power line from the nearest Power
substation of CESCO / GRIDCO will be erected.
Raw water will be available from Taladanda Canal via dedicated pipeline to
the site. Catalysts and chemicals will be delivered to the plant by truck via
11
3.1. General Requirements – Codes &Standards
12
3.3 General Requirements – Measuring Units
Following measuring units are to be used.
Temperature Deg C
Pressure, gauge Bar
Pressure, absolute Bar abs
Vacuum mBar
Weight Kg
Volume, liquids m3
Volume, gases (or at flow condition) Nm3
Flow rate – liquid m3 / hr
Flow rate gases Nm3/h
Flow rate steam Kg/h
Heat kJ
Power kW
Heat transfer coefficient W/m2 K
Viscosity cP
Liquid density Kg / m3
Vapor density Kg / m3
Equipment dimension mm
Piping length mm, m
Pipe diameter mm
Area m2
Tube sizes (ND) mm
Velocity m / sec
Vessel / Nozzle sizes (ND) mm
Sound pressure dB
Stresses N /mm2
Force N
Flange Rating lbs
13
areas will be segregated and disposed safely.
3.0 Gaseous Emission
Nitric Acid plant:Stack Gas vented to atmosphere after going through a
NOx Abatement Unit which brings the emission levels within norm)
14
4. PROCESSDESCRIPTION
4.1 AmmoniaPlant
Existing Ammonia plant at Taloja will be relocated to Paradeep which was based on
license provided Fish International Engineering Ltd, USA.
Original capacity of 272 MTPD has been enhanced to 380 TPD step by step.
The process conversions are based on NG/methane feedstock, are given in the following
overall chemical reaction: -
N2 + 3H2 2NH3
Gas received from battery limit is first passed through knockout drum to remove
condensate, slugs/droplets and then through a filter separator D8-0119 to eliminate dirt,
dust scales and condensate mist. The pressure of the gas to the battery limit is regulated
at 27 Bar g before metering. The total gas to the plant is metered.
4.1.3. Feedstockdesulphurization
Most of the catalysts used in the process are sensitive to sulphur and sulphur compounds.
The feedstock normally contains up to 5mg S/Nm3 as sulphur compounds. The feed-gas
is preheatedto 350-400°C, usually in the primary reformer convection section, and then
treated in a desulphurization vessel / reactor D8-0101, where the sulphur compounds are
hydrogenated to H2S, typically using a cobalt molybdenum catalyst, and then adsorbed on
pelletized zinc oxide desulphuriser D8-0102:-
R-SH + H2 H2S + RH
H2S + ZnO ZnS + H2O
In this way, the sulphur is removed to less than 0.1ppm S in the gas feed. The zinc
sulphide remains in the adsorption bed. The hydrogen for the reaction is usually recycled
from the synthesis section.
4.1.4. Primaryreforming
The gas from the desulphuriser is mixed with process steam, usually coming from an
extractionturbine, and the steam/gas mixture is then heated further to 500-600°C in the
convectionsection before entering the primary reformer. Preheated steam/gas mixture is
passed through an adiabatic pre-reformer and reheated in the convection section, before
15
entering the primary reformer). Part of the process steam is supplied by feed-gas
saturation. The amount of process steam is given by the process steam to carbon molar
ratio (S/Cratio), which should be around 3.57 for the. The optimum ratiodepends on
several factors, such as feedstock quality, purge gas recovery, primary reformer capacity,
shift operation, and the plant steam balance.
The primary reformer consists of many high–nickel chromium alloy tubes
filled with nickel-containing reforming catalyst. The overall reaction is highly endothermic
and additional heat is required to raise the temperature to 780-830°C at the reformer
outlet.
The composition of the gas leaving the primary reformer is given by close approach to the
following chemical equilibria: -
The heat for the primary reforming process is supplied by burning natural gas or other
gaseous fuel, in the burners of a radiant box containing the tubes.
The flue-gas leaving the radiant box has temperatures more than 900°C, after supplying
the necessary high level heat to the reforming process. Thus, only about 50-60% of the
fuel’s heat value is directly used in the process itself. The heat content (waste heat) of the
flue-gas is used in the reformer convection section, for various process and steam system
duties. The fuel energy requirement in the conventional reforming process is 40-50% of the
process feed gas energy.
The flue-gas leaving the convection section at 100-200°C is one of the main sources of
emissions from the plant. These emissions are mainly CO2, NOx, with small amounts of
SO2 and CO.
Only 30-40% of the hydrocarbon feed is reformed in the primary reformer because of the
chemical equilibria at the actual operating conditions. The temperature must be raised to
increase the conversion. This is done in the secondary reformer by internal combustion of
part of the gas with the process air, which also provides the nitrogen for the final synthesis
gas. In the reforming process the degree of primary reforming is adjusted so that the air
supplied to the secondary reformer meets both the heat balance and the stoichiometric
synthesis gas requirement. The process air is compressed to the reforming pressure and
heated further in the primary reformer convection section to around 600°C. The process
gas ismixed with the air in a burner and then passed over a nickel-containing secondary
reformer catalyst. The reformer outlet temperature is around 1,200°C, and up to 99% of the
hydrocarbon feed (to the primary reformer) is converted, giving a residual methane content
of 0.6% ( dry gas base) in the process gas leaving the secondary reformer. The process
gas is cooled to 350-400°C in a waste heat steam boiler or boiler/superheated
downstream from the secondary reformer.
16
The process gas from the secondary reformer contains 9.54 % CO (dry gas base) and
most of the CO is converted in the shift section per the reaction: -
CO + H2O CO2 + H2
In the High Temperature Shift (HTS) conversion, the gas is passed through a bed of iron
oxide/chromium oxide catalyst at around 360°C, where the CO content is reduced to about
1.8 % ( dry gas base), limited by the shift equilibrium at the actual operating temperature.
There is a tendency to use copper containing catalyst for increased conversion. The gas
from the HTS is cooled and passed through the Low Temperature Shift (LTS) converter.
This LTS converter is filled with a copper oxide/zinc oxide-based catalyst and operates at
about 260 °C. The residual CO content in the converted gas is about 0.1 % (dry gas base).
A low residual CO content is important for the efficiency of the process.
The process gas from the low temperature shift converter at 220 °C contains mainly H2,
N2, CO2 and the excess process steam. The gas is cooled and most of the excess steam
is condensed before it enters the CO2 removal system. This condensate normally contains
1,500-2,000ppm of ammonia 800-1,200ppm of methanol. Minor amounts of amines, formic
acid and acetic acid could be present in the condensate. All these components should be
stripped from the condensate and/or recycled in processes. The heat released during
cooling/condensation is used for: -
The amount of heat released depends on the process steam to carbon ratio. If all this low-
level heat is used for CO2 removal or absorption refrigeration, high-level heat must be
used for the feed water system. An energy-efficient process should therefore have a CO2
removal system with a low heat demand.
The CO2 is removed in a chemical or a physical absorption process. The solvents used in
chemical absorption processes are aqueous amine solutions Methyl Diethanolamine
(aMDEA.)
Residual CO2 contents are usually in the range 100-1,000ppmv, dependent on the type
and design of the removal unit. Contents down to about 100ppmv are achievable.
4.1.8. Methanation
The small amounts of CO and CO2, remaining in the synthesis gas, are poisonous for the
ammonia synthesis catalyst and must be removed by conversion to CH4 in the methanator
by following reactions: -
17
The reactions take place at around 355°C in a reactor filled with a nickel containing
catalyst. Methane is an inert gas in the synthesis reaction, but the water must be removed
before entering the converter. This is done firstly by cooling and condensation downstream
of the methanation and finally by condensation/absorption in the product ammonia in the
loop or in a make-up gas drying unit.
Centrifugal compressors for synthesis gas compression, driven by steam turbines, with the
steam being produced in the ammonia plant. The refrigeration compressor, for
condensation of product ammonia, is driven by steam turbine.
The synthesis of ammonia takes place on an iron catalyst at pressures usually in the range
310 bar g and temperatures in the range 40 °C: -
N2 + 3H2 2NH3
Only 16.5 % is reacted per pass in the converter due to the unfavorable equilibrium
conditions. The ammonia that is formed is separated from the recycle gas by
cooling/condensation, and the reacted gas is substituted by the fresh make-up synthesis
gas, thus maintaining the loop pressure. Synthesis loop arrangements differ with respect to
the points in the loop at which the make-up gas is delivered and the ammonia and purge
gas are taken out. The best arrangement is to add the make-up gas after ammonia
condensation and ahead of the converter. The loop purge should be taken out after
ammonia separation and before make-up gas addition. This configuration is dependent on
the make-up gas being treated in a drying step before entering the loop. A make-up gas
containing traces of water or carbon dioxide must be added before ammonia
condensation, with negative effects both to ammonia condensation and energy.
The size of this purge stream controls the level of inert in the loop to about 10-15%. The
purge gas is scrubbed with water to remove ammonia before being used as fuel or before
being sent for hydrogen recovery.
18
Each process is not substantially different from the others and hence there is
little difference in overall cost due to process adopted. The outline of the process
flow description and process flow diagram are given below:
The process steps involved in production of Nitric Acid plant can be divided into
(8) eight main sections described as follows:
- Air Compression
- Ammonia Evaporation
- Ammonia Oxidation
- Absorption
- Acid Bleaching
19
NH3 + 2 O2 → N2O + 3 H2O
The ammonia oxidation takes place over a set of Platinum-Rhodium gauzes at a
temperature around 890 ºC. The efficiency of this reaction varies between 96.7%
(with new gauzes, beginning of campaign) to 94-95% ( end of campaign, just
before changing the gauzes).
4.2.8 Absorption
The absorption of the nitrous dioxide and nitrous tetra oxide in water to produce
nitric acid at 60- 62 %w/w takes places in the upper trays of the Absorption
Tower. These are perforated trays with refrigeration coils to reduce the
temperature of the gases, improving the absorption process.
The nitric acid production is achieved through the following
reactions: 2 NO2 or N2O4 + H2O + HNO3 + HNO2
21
Ammonium nitrate solution preparation (wet zone)
Prilling, drying/ and cooling the product (solid zone)
The ammonium nitrate is obtained by the reaction between the gaseous
ammonia and the nitric acid per the following reaction:
NH3 + HNO3 =NO3NH4 + Heat
This reaction is exothermic. When the temperature is above 200°C the
ammonium nitrate decomposes violently per the below shown reactions:
NO3NH4 =N2O + 2 H2O + Heat
2 NO3NH4 =2 N2 + O2 + 4 H2O + Heat
b) AN Liquor Concentration
85 – 92 % Ammonium nitrate solution is pumped to the tube side of Falling Film
Evaporator. Steam is fed to the shell of evaporator to supply necessary heat to
concentrate the solution. The concentrated AN solution (96-99.8% AN) leaves the
bottom of the Falling Film Evaporator and either collected in the intermediate
22
tank or goes for prilling depending on the grade of Technical Ammonium Nitrate.
In case of former, the tank has internal coils, which are fed with LP steam to
increase the solution temperature. The concentrated AN solution/melt is pumped
to the upper part of the prilling tower.
b) Drying of theprills
The drying of the prills involves slow vaporization of most of the water of the prills
23
allowing a progressive drying which does not damage the prills and gives
hardness required to the product.
The exhausted hot air loaded with dust leaving the dryer drums is sucked into the
scrubbers by means of blower. The washing of the air is done in the Ventures
and scrubber with an AN washing solution. Clean air is then sent to the stack by
means of the air blower. From the dryer, the prills are sent to the screens through
belt conveyors.
g) AN Melt dispatch
Facilities shall be provided to load 85- 87 % concentrated AN melt by installing
loading bays for tanker. Facilities to include blast proof wall
5. TECHNOLOGIESAVAILABLE
Udhe/TKIS, Germany
Espindesa, Spain
Orica Australia
Basically, each of the technologies is not substantially different from the others
and hence there is little difference in cost due to technology adopted.
DFPCL over the years has not only absorbed but improvised these technologies
and is in position to carve out best possible process configuration towards most
cost-effective manufacture of AN- products.
For the Paradeep Project DFPCL has selected the technologies from one of the
above, and with whom DFPCL has the experience of installation, commissioning
25
& operation.
The plant is to be located at the site OFF IOCL ROAD, NEAR IOCL
OVERBRIDGE, BAGADIA- RANGIAGARH, DIST: JAGATSINGHPUR,
PARADEEP – 754141, ODISHA.
The preliminary layout of the plot is shown on end of Section 12 of this report.
The site is located along the Cuttack-Paradeep railway line and adjacent to
IOCL Refinery Township.
The existing ground level of the site is approximately 2.5 M to 3.0 M above the
Mean Sea Level. It is planned to have the Finished ground level as 5.5 M from
the Mean Sea level as per the available site conditions. Hence, filling of app. 3.00
M depth is envisaged.
Power requirement for the plant will be met through CESCO/ GRIDCO.
Depending on the voltage at which power is available, suitable step down
transformers will be provided. The app. length of power supply line will be 4 –
5 KM.
The water requirement for the Plant will be met through a water reservoir
having a storage capacity of 10 days. The source of water supply will be
from Taladanda canal. A Pump house and water supply line from Taladanda
canal will be laid up-to reservoir. The length of water supply line is estimated at
10 - 12 KM from Distributary point16.
26
Product Production
s Capacity Metric
B Utilities
Power MWh 8.5
Raw Water M3/day 15000
Steam MT/hr 55
7.3 Ammonia
Currently DFPCL sources Ammonia from Middle East. The additional requirement of
Ammonia for the Project shall be met through relocated Ammonia plant of 380 TPD which
will also cater requirement of nitric acid plant to full fill additional requirement.,.
DFPCL is in advance stage of entering long term contract with one of the
industries in Paradeep for utilizing their Ammonia receiving, storage and transfer
facility. Existing Ammonia storage tanks of this company shall be used on hired
27
basis thru a long-term contract for receiving, storage and pipe line delivery of
imported Ammonia. The Ammonia pipeline length between the nearby factory
The raw water requirement is 15000KLD which shall be supplied from the local
irrigation canal located at approx.10 - 12 Kms away from the plant site. The
water availability from this canal is restricted to 310 days in a year; hence the
average lifting/ day capacity of water shall be kept with 20% margin of normal
requirement.
Suitable water intake facilities shall be created at canal site to lift the required
volume of water through two number of pumps (one operating and one stand by)
and discharge to the raw water storage reservoir located inside the plant
premises. Water from canal intake station to plant site reservoir shall be supplied
through pipeline. Decision of underground or above ground pipeline shall be
taken during the further development stage of the project.
The requirement of water is mainly for cooling water make up. Other requirement
of process water is as make up to DM plant, utility water, etc. Water requirement
indicated above has been worked out based on recycle of majority of steam
condensate to DMplant.
28
Raw water shall be sourced from Taldanda Canal and will be stored in a
reservoir before feeding to the treatment unit.
29
7.5. Potable Water
Basis of Design
UVR unit will be provided wherever potable water shall be used for
drinking purpose.
7.6 DMWater
The DM water plant capacity has been considered as 25 m3/h without any stand
by unit. Plant shall be in line for 22 hrs. in day and remain out for 2 hrs. for resin
regeneration. Provision shall also be made for storage of DM water, process
water and steam condensate with associated pumps.
30
Design Basis
The design basis for the demineralization plant would consist of the following:
At this stage 25 m3/h unit consisting of Cation and Anion exchanges are
considered
The return condensate water from the plant could be quite hot and the ion
temperature.
The piping shall be carbon steel rubber lined or of suitable material for
All the valves and fittings shall be rubber lined or Polymer based suitable
31
The vessel and piping should can withstand a pressure of 1000 kPag and
Ejectors used to draw the dilute acid/alkali from the regeneration day tank
The neutralizing pit pump suction piping and the pumps should be
capable of pumping salt and water from the reaction of acid and alkali
7.7 Catalyst
For Ammonia plant:
Desulfurization catalyst – Cobaltmolybdenum.
Reforming catalyst- Nickel chromium alloy.
Shift conversion reaction - Iron oxide.
Methanation – Nickel.
Ammonia Synthesis – Iron.
Dynamic UPS system with Diesel Generator shall be provided for supply of
uninterrupted / emergency power. To meet the emergency power
The Nitric Acid plant is also equipped with turbo generator coupled to air
compressor and can supply 5-6 MW if required.
Firewater diesel
Emergency diesel driven generator
33
the firewater pump, an 8 hours’ storage capacity day tank or vendor standard
supply package item with the equipment should be allowed in the design.
Emergency Power
Controls;
Jockey pump;
Communication systems;
34
The entire requirement of steam in the complex will be met by this boiler.
Suitable let down station with de-superheating facilities shall be provided to cater
the steam pressure and temperature as per the requirement of downstream
process.
At peak load, Coal requirement will be around 120 TPD which will be required
only during the start-up of Nitric acid plant. Normal requirement will be 50 TPD.
Hence, eight days Coal storage capacity (1000 MT) on peak load basis shall be
installed. (FO fired Boiler is also being considered as an alternative possibility )
Boiler feed water to the plant is produced from two sources, one from the
demineralization plant and the other from condensate water polishing unit. The
filtered water from Raw Water Treatment unit is sent to the demineralization plant
whereas return condensate water from the plant is routed to condensate
polishing unit to remove the dissolved solids.
Low pressure steam from LP header would be used for stripping the dissolved
oxygen from the condensate water in the de-aerator. Oxygen scavenger dosing
35
is required to remove any residual oxygen present in the condensate water at the
outlet of the de- aerators. The condensate from the de-aerator would be
approximately 100 deg C, and routed to the Boiler Feed Water (BFW) pumps.
Since the BFW is at boiling point, the de- aerators will be elevated to avoid pump
cavitation.
The BFW pump suction piping design will also take in to account the pump
NPSH requirements, frictional losses in the suction piping, vapor pressure, high
fluid temperature and other similar requirements.
Condensate from the surface condenser in Nitric Acid plants will be recycled
back to the Waste heat boilers in those plants. Any shortfall in condensate will be
made up by DM Water
All steam lines shall be insulated with hot insulation material and cladding.
The steam header shall be designed with slight gradient towards the
steam trap.
The steam header shall be provided with steam traps at suitable location.
Proper line rating shall be considered once the P&ID’s are developed.
36
water would be used as a close loop circulating water to cool the coolers/heat
exchangers in ammonia, nitric acid and ammonium nitrate plants. The circulated
water from the outlet of the individual plant would return via a circulating water
return header back to the cooling tower.
An induced draft, cross flow type cooling tower will be used for supply of cooling
water to different section of the plant. Maximum temperature difference of 10°C is
desirable in the cooling tower. This will be associated with CW circulating pumps,
side stream filtration, chemical dosing system etc. Three cooling water pumps
(electric motor driven) will be running to meet the process requirements.
The water losses calculated from the cooling tower includes drift and
evaporation loss as well as blow down loss. The blow down rate from the
cooling tower would vary, and depend on the water quality being maintained.
Pumps Design
Design Considerations
Actual cooling water chemistry and quality will be determined upon site
selection and water source and treatment. Cooling water chemistry requires
some amounts of free chlorine, phosphate and dispersant to prevent corrosion,
scaling by keeping the impurities in suspended form.
Free chlorine also keeps bacterial and organic growth under control. Provision
of descale chemical injection point would be required in cooling water circuit.
Detail requirement of complex instrument& plant air will be freeze during detail
engineering stage of project.
System will comprise one plant air receiver and one instrument air receiver.
Instrument Air
The consumption rate for instrument air is based on all instruments operating
plus the design margin. Since P&ID’s are not available or the instrument loop
diagram, an assumption has been made to arrive at the capacity requirement.
It is important that once the details are available the capacity requirement need
38
to be revisited after detail engineering.
Plant Air
Inter-cooler and after cooler should be part of the compressor vendor skid.
39
Driers will be reactivated by desorption which is a package item
Instrument Controls
Operation and control of the compressors within the package (by the
vendor)
Start and stop of the duty compressor with the air demand (low/high
instrument air header pressure)
Failure of the duty compressor, and further fall in instrument air header
pressure, the control system should start the stand-by compressor
automatically.
The main firewater pumps (both diesel and electric drive) designed to
40
have waterwhich will be finalized during detail engineering stage of
project. The sizing of the pumps and the firewater headers assumethat at
any given time five monitors each of 55 m3/h would be required to
firefight
Firewater pumps shall be located within a safe area if possible, such that
a fire in one area will not put both the fire pumps out of action
The jockey pump should can maintain the firewater system pressure at 8
barg
Firewater tank would be designed to 3 hrs. capacity at the water flow rate of 275
m3/h
Diesel driven firewater pump will be a package item. The package should
includethe following:
3. Auxiliary system
The firewater piping design to 16 bar g and the firewater pump shutoff
head not to exceed the FW header design pressure
41
Firewater pumps should be designed to applicable NFPA / APIcodes
7.14 Manpower
The manpower required for the operation of the proposed facility will be met by
deployment of personnel with requisite experience and skill. The manpower will
beadequately trained before start of operation. Focus shall be training and
employing locals to the extent possible and based on availability of workforce
with required skill sets.
7.15 Laboratory
Adequate laboratory facility will be provided to check the all the raw materials,
products, by products, water and steam system, effluent system parameters
during day to day operation.
See Annexure-1 for Ammonia, A, ANS & TAN Process Flow Block Diagram
42
9. RAW MATERIAL & PRODUCTSPECIFICATION
Ammonia Storage
More information can be furnished after carrying out the Detail Engineering.
43
9.2.2 Technical Ammonium Nitrate Prills(LDAN)
10. ENVIRONMENTALCONSIDERATIONS
Climate and Meteorology
Meteorology plays a vital role in affecting the dispersion of pollutants into
the environment after their discharge into the atmosphere. Jagatsinghpur
District enjoys a temperate climate. Winters are cold, while summers are hot
and humid. The District is prone to cyclonic rainfalls during the monsoons.
The maximum temperature of the District is 38°C and minimum temperature
is 12°C. The average rainfall measured in the District is 1765.1-mm.
The state experiences four seasons, these are:
Winter ( December to February), Pre-monsoon (March to May), Monsoon
(June to September), Post-monsoon (October to November).
Winter Season: Occasional rains with average 40-mm rainfall is received
during this period, the average minimum temperature goes to 5°C or below
in interior districts and in coastal areas it remains around 12-15°C. Normally
44
the winter brings a clear sky, light winds and abundant sunrays during the
daytime.
Summer Season: The average temperature in the coastal districts remains
30-35°C and in interior districts remained around 35-42°C. There are some
hot pockets in the western belt, where the temperature goes as high as 45-
50°C. During March to May often a high-pressure area created over the Bay
of Bengal, forcing moisture-laden wind to the coastal districts of the State.
This situation brings thunderstorm, hail storm, dust storm and light rains to
the area.
Monsoon Season: The period mid-June to end of September or early
October is considered as monsoon season. Southwest monsoon sets in
over the State by the mid-June brining rain. About 80% of the total rainfall
(average more than 1480.0-mm) occurs during this period.
Post-monsoon Season: The monsoon usually continues up to the end of
September and to the early part of October. Then the sky becomes clear
and the day temperature starts decreasing and the night temperature drops
sharply. During the post-monsoon period, the interior parts of the State
receive about 75.0-150.0-mm rainfall and the coastal districts receive about
200 to 220-mm rainfall. Another feature of this period is occurrence of
intense low-pressure system over the Bay of Bengal creating cyclonic
storm, often striking Orissa coast.
Following waste shall be generated during the process
Environmental Sensitivity
1 Areas protected under
international conventions,
There is a Protected Forest at 5.20km,
national or local legislation for Yes
their ecological, landscape, SSW
cultural or other related value
2 Areas which are important or There is a river called Mahanadi at
sensitive for ecological 5.40km, N and Santra Nallah 1.84km,
reasons -Wetlands, SW, Antrabanki,4.18 km, SE, Mahanga
watercourses or other water Yes
Nallah,4.89km, SW
bodies, coastal zone,
biospheres, mountains, forests Bay of Bengal,6 km SE
3 Areas used by protected, There is a Protected forest present in the
important or sensitive species study area but it is an open forest and
of flora or fauna for breeding, there are no protected, important or
No
nesting, foraging, resting, over sensitive species of flora or fauna for
wintering, migration breeding, nesting, foraging, resting, over
wintering, migration
45
4 Inland, coastal, marine or There is a river called Mahanadi at
underground waters 5.40km, N and Santra Nallah 1.84km,
SW, Antrabanki,4.18 km, SE, Mahanga
Yes
Nallah,4.89km, SW
46
Oily cotton rags from maintenance activities
Filter media used for filtration of air / water / cutting or lubricating oil
The wastes indicated above are of special concern since theycould be eco-
toxic or hazardous and special attention needs to be given to their
handling, treatment and disposal.
The other generated waste is municipal solid waste, scrap –metal, paper,
plastics, waste packaging material etc. These miscellaneous wastes will also be
disposed of through local / federal approved vendors.
During the normal operation of the plant there will be no liquid effluent from
WNA plant but a smallquantity of Nitrate bearing effluent will generate from AN
wet plant. Some quantity of Nitrate and Nitric acid containing effluent from
WNA and AN wet plant will also generate during the plant upset or
startup/shutdown condition. In addition to this process effluent, blow down
water from cooling tower, boilers, backwash of DM plant resins and side
stream filters of cooling tower, domestic waste from canteen etcwillalso be
part ofmain effluent.
47
A suitable effluent treatment plant shall be installed to take care of all the
effluents. Following will be the characteristics and quantity of the liquid
effluent.
48
the effluent treatment plant.
49
Special Civil Works
The process water effluents from the Ammonia, AN, NA and Utilities area are
effluents included in the effluent plant design. The effluent water from the plant
would be segregated and routed to a holding pond or evaporation pit prior to
treatment and disposal. The holding pond or evaporation pit should be lined to
prevent soil contamination/pollution.
The composition of the pond water may change drastically during turn-around
due to the discharge of large amounts of acid or other product effluent from the
plant.
Effluent treatment plant design is based on the constituents present and the
quality of water to be achieved at the outlet of the treatment plant. The options are
a batch or continuous process.
In case RO becomes essential the reject stream from the RO unit will be further
concentrated and used as landfill unless the reject or the solid concentrate can
be suitable used for alternate application.
NOx in Tail gas from the Nitric Acid Plant: Before venting the tail gas in to
atmosphere, NOx level in the tail gas shall be reducedto the
acceptablelimit byselective catalytic reduction with ammonia in presence
of Vanadium pentoxide, platinum or iron/chromium oxides catalysts
Ammonia and ammonium nitrate laden air from the prilling scrubber: This
air is cooled and scrubbed to remove most of the ammonia and
Ammonium Nitrate from them.
Air emission from utility area is through boiler stack which will operate on
fuel oil. Dedicated stack will be attached for the service boilers.
51
The approximate quantity and quality of gaseous emission from Spent Air
and boilerstack are furnished below:
The proposed project would include site development, main process plants
along with Offsites&Utilites, Raw material and product storages, Electrical
substation, Covered Ware houses, Plant and non-plant buildings etc. The
project scope shall also include the construction of cross country facilities for
bringing Ammonia, fuel, Raw material, and Power to the site.
11.2 Location
52
Jagatsinghpur(dist), Paradeep”, East coast, Odisha State, India.
All the pre-project activities mentioned above should be completed before the
zero date of the project. It is envisaged to implement the Project through
spending equity first and then to use loans thereafter.
The project will be managed by DFPCL’s in-house PMC team to utilize the
experience obtained over 30 years and building 5 Nitric Acid and 4 Ammonium
Nitrate units. The learning from previous projects and operations over years have
been incorporated during basic and detailed design of the plants.
DFPCL has a formidable and highly dedicated project team of qualified engineers
of various disciplines and a very skilled and experienced workforce. The team
has recently executed a Rs. 600 cr brown field AN-complex at Taloja. A team
comprising of Operation group and Project group will be constituted to implement
the project and will be responsible for Overall Project Management. This team will
be composite with Engineers from various disciplines including Finance and
Accounts and Materials Management personnel.
54
11.7 Engineering:
The basic engineering is carried out by a reputed process licensor and will be
issued to the Detail Engineering Contractor to carry out the detail engineering.
The selected Detailed Engineering Contractor (DEC) shall carry out the detailed
engineering of plants and off-sites, which will form the basis for plant
construction. It will comprise all discipline design services necessary for the
procurement, construction and commissioning of the plant and associated
infrastructure including:
Prepare data sheets, standards and technical specifications and for all
materials and equipment;
Participate in HAZOPstudies;
The data provided will cover all the activities necessary for procurement of
equipment’s, plans, elevations and isometrics of different sections for civil design
55
and equipment erection etc. The Detail Engineering Contractor will require the
vendor design information from the process equipment vendors and the utilities
equipment vendors. The procurement group will expedite this vendor information
for the detail design contractor.
11.8 Procurement
The EPCM Contractor’s procurement team will provide services for the
procurement, expediting, inspection and delivery of all mechanical equipment
except for the Propriety Equipment. Orders will be placed with qualified vendors
based on technical compliance, quality, price and delivery.
Prepare tender lists for all packages and submit for Deepak approval;
Prepare and issue tender documentation, perform evaluations and
submit recommendations for award to Deepak;
Deepak shall award the purchase orders and Carry out all
management requirements, inclusive of financial guarantees,
vendor data, spares and maintenance documentation, during the
term of the order;
Review all suppliers Inspection and Test Plans (ITPs) and perform all
necessary inspection and expediting activities to ensure the specified
quality and delivery schedule requirements are met;
Receive and review all vendors invoices and prepare
recommendations for payment;
56
11.10 Project Control
11.11 Quality
It is critical that all Project documentation is clearly identified and traceable to the
end user. There will be an agreed document and drawings numbering system,
document registers maintained, protocol for revision management of drawings
and a drawing transmittal system for all external document issue.
11.13 Construction:
Construction activities for the main plants and off-sites will be grouped per the
nature of the jobs and bids invited from pre-qualified contractors. The bids will be
evaluated based on the experience of the contractors, their background, cost and
time schedule. The overall responsibility for the construction would be that of the
57
DFPCL. The chief of the construction group shall look after the co-ordination of
all the construction activities. He will be assisted by a group of Engineers,
managers and other staff.
Safety;
Contract management;
Interface management;
Survey control;
Materials management.
58
11.16 Construction Contractor’responsibilities
Construction Equipment
Contractors will furnish their own Quality Control program in accordance with
contract documents. This will include all testing requirements including
compaction, concrete strength, weld and electrical installation testing.
Construction Personnel
11.17 Commissioning
Commissioning, sustained load run and guarantee test will be under the total
responsibility of the licensor for the main plants. The owners must make
arrangement for the supply of raw materials in adequate quantities. The utility
requirements like power, water etc. would be kept ready to be supplied whenever
necessary. The owner will also supply the necessary operators, engineers and
skilled and non-skilled worker, who will be involved in the commissioning
59
activities. Commissioning spares also must be procured before the
commissioning activities start.
Scheduling and monitoring of the main plants and overall scheduling and
monitoring of entire Project will be the responsibility DFPCL project group.
PERT/CPM chart will be prepared incorporating main activities in each section
discipline wise. The activities will cover design, engineering, procurement,
transportation, civil construction etc.
Cost Control
Following confirmation of the Project capital cost estimate, the estimate will then
become the Project budget. The budget for the project will then be entered in to
database cost control system utilizing a coding structure that identifies all
equipment, materials and discipline activities. Throughout the course of the
Project all commitments and expenditure will be entered in the cost control
system. Forecasts to complete and variances will be updated monthly and
contingency drawdown will be managed. Efficient and accurate cost control will
be critical to ensure the Project is completed within budget.
Reporting
During the Project, there will be the need for on-going communication of project
status to Deepak from all parties involved. The monthly progress reports shall be
prepared and shall be circulated by DFPCL project group.
Safety;
Environmental;
60
Progress in all discipline (measurement and narrative);
Costs;
Quality;
11.19 Schedules
The project will be monitored with the help of the following schedules.
a) Overall project schedule
b) Engineering schedule
c) Procurement schedule
d) Construction Schedule.
Overalls-curve
All the networks/CPM will be computerized for working out the earliest/latest start
and finish dates and floats/slacks available in each activity.
61
11.20 Time Schedule
The overall time schedule for the proposed project including pre-project activities
is 36 months. There shall be overlap in procurement to reduce the overall time
schedule.
A preliminary bar chart showing the details of activities and their completion time is
provided on the next page.
62
52
13. PROJECT COST &FINANCIALS
Cost Estimate
The base equipment list reflects current technology offer by Grande Paroisse, France
and as presented in Section 4 of this report. Prices of proprietary equipment reflect data
base prices prepared by our internal team out of our project and operating exposure to
the relevant manufacturing set-up. For the current study, it is assumed that the balance
of the ISBL/ OSBL equipment’sis procured in India and our internal team has prepared
this pricing based on current data base pricing for Indian supply as well as capital
committed on previous projects of similar nature.
Plant Layout
The plant layout has been developed about information from previous geotechnical
investigations on this site as well as from our experience. The plant layout has been
stepped in two levels to minimize the site earthworks. The minimum elevation of the
plant is 3.2 m AMSL to remain above to the tide and storm surge water level. Refer
Infrastructure & Plant Layout (preliminary) at the end of this section.
DSCR-Avg % 2.05
The building of the Ammonium Nitrate plants being a grass root project shall
consist of the following process and non-process units/facilities:
5) DG set
15) Cooling Tower including pumps, motors / turbine and dosing system
54
a) Nitric Acid
b) Ammonia
c) Diesel
d) Furnace oil
e) Caustic soda
f) Sophoricoside
21) Weighbridges
b) Plant offices
c) Laboratory
e) Workshop
g) Security/Fire &safety
i) Restrooms
The preliminary & conceptual lay out is displayed below. The detailed layout
shall be finalized during engineering stage incorporating all statutory
regulations/ guidelines.
55
56
ANNEXURE 1:PROCESS FLOW
PDF:NITRIC ACID
57
PDF TAN UNIT AN SOLUTION AND TAN
58