CHulter Hammer Power Distribution Systems Book
CHulter Hammer Power Distribution Systems Book
June 2006
Sheet 0019
1.0-1
Index
Master TOC
Contents
Power Distribution Systems System Design Basic Principles. . . . . . . . . . . 1.1-1 Modern Electric Power Technologies . . . . . . . . . . . 1.1-1 Goals of System Design . . . 1.1-2 Voltage Classications; BILs Basic Impulse Levels . . . . . 1.1-4 3-Phase Transformer Winding Connections . . . . 1.1-5 Types of Systems Radial, Loop, Selective, Two-Source, Sparing Transformer, Spot Network, Distribution . . . . 1.1-6 Health Care Facility Design Considerations . . . 1.1-14 Generator Systems . . . . . . 1.1-17 Generator System Design Types of Generators . . . . . . . 1.2-1 Generator Systems . . . . . . . 1.2-2 Generator Grounding. . . . . . 1.2-3 Generator Controls. . . . . . . . 1.2-4 Generator Short Circuit Characteristics . . . . . . . . . . 1.2-4 Generator Protection . . . . . . 1.2-5 System Analysis Systems Analysis . . . . . . . . . 1.3-1 Short Circuit Currents . . . . . 1.3-2 Fault Current Waveform Relationships . . . . . . . . . . . 1.3-3 Fault Current Calculations and Methods Index . . . . . . 1.3-4 Determine X and R from Transformer Loss Data . . . 1.3-19 Voltage Drop Considerations . . . . . . . . . . 1.3-23 System Application Considerations Capacitors/Power Factor. . . 1.4-1 Overcurrent Protection and Coordination . . . . . . . . 1.4-3 Protection of Conductors . . . 1.4-5 Circuit Breaker Cable Temperature Ratings . . . . . 1.4-5 Zone Selective Interlocking . 1.4-5 Ground Fault Protection . . . 1.4-6 Suggested Ground Fault Settings . . . . . . . . . . . . . 1.4-6 Grounding/Ground Fault Protection Grounding Equipment, System, MV System, LV System . . . . . . . . . . . . . . 1.4-6 Ground Fault Protection . . . . 1.4-11 Lightning and Surge Protection . . . . . . . . . . . . . . 1.4-14 Grounding Electrodes. . . . . . 1.4-14 Power Quality Terms, Technical Overview . . 1.4-15 TVSS . . . . . . . . . . . . . . . . . . . 1.4-16 Harmonics and Nonlinear Loads . . . . . . . . . 1.4-18 UPS . . . . . . . . . . . . . . . . . . . . 1.4-22 Other Application Considerations Secondary Voltage . . . . . . . . 1.4-28 Energy Conservation . . . . . . 1.4-29 Building Control Systems . . 1.4-30 Cogeneration. . . . . . . . . . . . . 1.4-30 Emergency Power. . . . . . . . . 1.4-30 Peak Shaving. . . . . . . . . . . . . 1.4-31 Sound Levels. . . . . . . . . . . . . 1.4-32 Reference Data IEEE Protective Relay Numbers . . . . . . . . . . . . . . . 1.5-1 Codes and Standards . . . . . . 1.5-6 Motor Protective Device Data . . . . . . . . . . . . . 1.5-7 Chart of Short Circuit Currents for Transformers . . 1.5-9 Transformer Full Load Amperes and Impedances . . . . . . . . . 1.5-10 Transformer Losses, TP-1 Losses . . . . . . . . . . . . . 1.5-12 Power Equipment Losses . . . 1.5-13 NEMA Enclosure Denitions . . 1.5-13 Cable R, X, Z Data . . . . . . . . . 1.5-15 Conductor Ampacities . . . . . 1.5-16 Conductor Temperature Ratings . . . . . . . . . . . . . . . . 1.5-16 Formulas and Terms . . . . . . . 1.5-18 Seismic Requirements . . . . . 1.5-19
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
21
CA08104001E
1.0-2
June 2006
Sheet 0020
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
June 2006
Sheet 0021
TOC
Index
1.1-1
Master TOC
Basic Principles
The best distribution system is one that will, cost effectively and safely, supply adequate electric service to both present and future probable loads this section is included to aid in selecting, designing and installing such a system. The function of the electric power distribution system in a building or installation site is to receive power at one or more supply points and deliver it to the individual lamps, motors, and all other electrically operated devices. The importance of the distribution system to the function of a building makes it almost imperative that the best system be designed and installed. In order to design the best distribution system, the system design engineer must have information concerning the loads and a knowledge of the various types of distribution systems that are applicable. The various categories of buildings have many specic design challenges, but certain basic principles are common to all. Such principles, if followed, will provide a soundly executed design.
The basic principles or factors requiring consideration during design of the power distribution system include:
s s s
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
s s
s s s s s s s s s
Functions of structure, present and future. Life and exibility of structure. Locations of service entrance and distribution equipment, locations and characteristics of loads, locations of unit substations. Demand and diversity factors of loads. Sources of power; including normal, standby and emergency (see Section 42). Continuity and quality of power available and required (see Section 41). Energy efciency and management. Distribution and utilization voltages. Bus and/or cable feeders. Distribution equipment and motor control. Power and lighting panelboards and motor control centers. Types of lighting systems. Installation methods. Power monitoring systems. Electric utility requirements.
Power monitoring and control. Building management systems interfaces. Lighting control. Automated energy management. Predictive diagnostics.
Various sections of this guide cover the application and selection of such systems and components that may be incorporated into the power equipment being designed. See Sections 2, 3, 4, 23 and 43.
CA08104001E
1.1-2
TOC
Index
June 2006
Sheet 0022
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
2. Minimum Initial Investment: The owners overall budget for rst cost purchase and installation of the electrical distribution system and electrical utilization equipment will be a key factor in determining which of various alternate system designs are to be selected. When trying to minimize initial investment for electrical equipment, consideration should be given to the cost of installation, oor space requirements and possible extra cooling requirements as well as the initial purchase price. 3. Maximum Service Continuity: The degree of service continuity and reliability needed will vary depending on the type and use of the facility as well as the loads or processes being supplied by the electrical distribution system. For example, for a smaller commercial ofce building a power outage of considerable time, say several hours, may be acceptable, whereas in a larger commercial building or industrial plant only a few minutes may be acceptable. In other facilities such as hospitals, many critical loads permit a maximum of 10 seconds outage and certain loads, such as real-time computers, cannot tolerate a loss of power for even a few cycles. Typically, service continuity and reliability can be increased by: A. Supplying multiple utility power sources or services. B. Supplying multiple connection paths to the loads served. C. Using short-time rated power circuit breakers. D. Providing alternate customerowned power sources such as generators or batteries supplying uninterruptable power supplies. E. Selecting the highest quality electrical equipment and conductors. F. Using the best installation methods. G. Designing appropriate system alarms, monitoring and diagnostics. H. Selecting preventative maintenance systems or equipment to alarm before an outage occurs.
4. Maximum Flexibility and Expendability: In many industrial manufacturing plants, electrical utilization loads are periodically relocated or changed requiring changes in the electrical distribution system. Consideration of the layout and design of the electrical distribution system to accommodate these changes must be considered. For example, providing many smaller transformers or loadcenters associated with a given area or specic groups of machinery may lend more exibility for future changes than one large transformer; the use of plug-in busways to feed selected equipment in lieu of conduit and wire may facilitate future revised equipment layouts. In addition, consideration must be given to future building expansion, and/or increased load requirements due to added utilization equipment when designing the electrical distribution system. In many cases considering transformers with increased capacity or fan cooling to serve unexpected loads as well as including spare additional protective devices and/ or provision for future addition of these devices may be desirable. Also to be considered is increasing appropriate circuit capacities or quantities for future growth. Power monitoring communication systems connected to electronic metering can provide the trending and historical data necessary for future capacity growth.
CA08104001E
June 2006
Sheet 0023
TOC
Index
1.1-3
Master TOC
5. Maximum Electrical Efciency (Minimum Operating Costs): Electrical efciency can generally be maximized by designing systems that minimize the losses in conductors, transformers and utilization equipment. Proper voltage level selection plays a key factor in this area and will be discussed later. Selecting equipment, such as transformers, with lower operating losses, generally means higher rst cost and increased oor space requirements; thus, there is a balance to be considered between the owners utility energy change for the losses in the transformer or other equipment versus the owners rst cost budget and cost of money. 6. Minimum Maintenance Cost: Usually the simpler the electrical system design and the simpler the electrical equipment, the less the associated maintenance costs and operator errors. As electrical systems and equipment become more complicated to provide greater service continuity or exibility, the maintenance costs and chance for operator error increases. The systems should be designed with an alternate power circuit to take electrical equipment (requiring periodic maintenance) out of service without dropping essential loads. Use of drawout type protective devices such as breakers and combination starters can also minimize maintenance cost and out-of-service time.
7. Maximum Power Quality: The power input requirements of all utilization equipment has to be considered including the acceptable operating range of the equipment and the electrical distribution system has to be designed to meet these needs. For example, what is the required input voltage, current, power factor requirement? Consideration to whether the loads are affected by harmonics (multiples of the basic 60 cycle per second sine wave) or generate harmonics must be taken into account as well as transient voltage phenomena. The above goals are interrelated and in some ways contradictory. As more redundancy is added to the electrical system design along with the best quality equipment to maximize service continuity, exibility and expandability, and power quality, the more initial investment and maintenance are increased. Thus, the designer must weigh each factor based on the type of facility, the loads to be served, the owners past experience and criteria.
Summary
It is to be expected that the engineer will never have complete load information available when the system is designed. The engineer will have to expand the information made available to him on the basis of experience with similar problems. Of course, it is desirable that the engineer has as much denite information as possible concerning the function, requirements, and characteristics of the utilization devices. The engineer should know whether certain loads function separately or together as a unit, the magnitude of the demand of the loads viewed separately and as units, the rated voltage and frequency of the devices, their physical location with respect to each other and with respect to the source and the probability and possibility of the relocation of load devices and addition of loads in the future. Coupled with this information, a knowledge of the major types of electric power distribution systems equips the engineers to arrive at the best system design for the particular building. It is beyond the scope of this guide to present a detailed discussion of loads that might be found in each of several types of buildings. Assuming that the design engineer has assembled the necessary load data, the following pages discuss some of the various types of electrical distribution systems that can be utilized. The description of types of systems, and the diagrams used to explain the types of systems on the following pages omits the location of utility revenue metering equipment for clarity. A discussion of short circuit calculations, coordination, voltage selection, voltage drop, ground fault protection, motor protection, and other specic equipment protection is also presented.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
1.1-4
TOC
Index
June 2006
Sheet 0024
Master TOC
i ii 1 2 3 4 5 6 7
Voltage Classications
ANSI and IEEE standards dene various voltage classications for single-phase and 3-phase systems. The terminology used divides voltage classes into:
s
Table 1.1-2. Metal-Clad Switchgear Voltage and Insulation Levels (From ANSI/IEEE C37.20.2-1999)
Rated Maximum Voltage (kV rms) 4.76 8.25 15.0 27.0 38.0 Impulse Withstand (kV) 60 95 95 125 150
Low voltage. Medium voltage. s High voltage. s Extra-high voltage. s Ultra-high voltage.
s
Table 1.1-3. Metal-Enclosed Switchgear Voltage and Insulation Levels (From ANSI C37.20.3-1987)
Rated Maximum Voltage (kV rms) 4.76 8.25 15.0 15.5 25.8 38.0 Impulse Withstand (kV) 60 75 95 110 125 150
Table 1.1-1 presents the nominal system voltages for these classications. Table 1.1-1. Standard Nominal System Voltages and Voltage Ranges (From IEEE Standard 141-1993)
Voltage Class Low Voltage Nominal System Voltage 3-Wire 4-Wire 208Y/120 240/120 480Y/277
Motor, motor starter and cable rst cost. Motor, motor starter and cable installation cost. Motor and cable losses. Motor availability. Voltage drop. Qualications of the building operating staff; and many more.
The following table is based in part on the above factors and experience. Since all the factors affecting the selection are rarely known, it is only an approximate guideline. Table 1.1-5. Selection of Motor Horsepower Ratings as a Function of System Voltage
Motor Voltage Motor (Volts) hp Range 460 2,300 4,000 4,600 13,200 125 350 450 550 up to 500 250 to 2000 250 to 3000 250 to 3000 above 2000 System Voltage 480 2,400 4,160 4,800 13,800
240/120 240 480 600 2,400 4,160 4,800 6,900 13,200 13,800 23,000 34,500 46,000 69,000 115,000 138,000 161,000 230,000
Medium Voltage
8 9 10
High Voltage
4160Y/2400 8320Y/4800 12000Y/6930 12470Y/7200 13200Y/7620 13800Y/7970 20780Y/12000 22860Y/13200 24940Y/14400 34500Y/19920
Table 1.1-4. Liquid-Immersed Transformers Voltage and Basic Lightning Impulse Insulation Levels (BIL) (From ANSI/IEEE C57.12.00-2000)
Application Nominal BIL System (kV Crest) Voltage (kV rms) 1.2 2.5 5.0 8.7 15.0 25.0 34.5 46.0 69.0 Power 1.2 2.5 5.0 8.7 15.0 25.0 34.5 46.0 69.0 115.0 138.0 161.0 230.0 345.0 500.0 765.0 30 45 60 75 95 150 200 250 350 45 60 75 95 110 150 200 250 350 550 650 750 125 150 200 250 30 45 60 75 95 200 250 450 550 650
Distribution
Table 1.1-6. Dry-Type Transformers Voltage and Basic Lightning Impulse Insulation Levels (BIL) From ANSI/IEEE C57.12.01-1989)
Nominal System Voltage (kV rms) 1.2 2.5 5.0 8.7 15.0 25.0 34.5 BIL (kV Crest)
11 12 13 14 15 16 17 18 19 20 21
Extra-High Voltage
Ultra-High Voltage
95
10 20 30 45 60 110 125
20 30 45 60 95 125 150
900 825 750 650 1,175 1,050 900 1,675 1,550 1,425 1,300 2,050 1,925 1,800
BIL values in bold typeface are listed as standard. Others listed are in common use. Optional higher levels used where exposure to overvoltage occurs and higher protection margins are required. Lower levels where surge arrester protective devices can be applied with lower spark-over levels.
BIL values in bold typeface are listed as standard. Others listed are in common use.
CA08104001E
June 2006
Sheet 0025
TOC
Index
1.1-5
Master TOC
Notes 1. Suitable for both ungrounded and effectively grounded sources. 2. Suitable for a 3-wire service or a 4-wire service with a mid-tap ground.
i ii 1
H1
H3
X1
X3
2
1. Suitable for both ungrounded and effectively grounded sources. 2. Suitable for a 3-wire service or a 4-wire grounded service with XO grounded. 3. With XO grounded, the transformer acts as a ground source for the secondary system. 4. Fundamental and harmonic frequency zero-sequence currents in the secondary lines supplied by the transformer do not ow in the primary lines. Instead the zero sequence currents circulate in the closed delta primary windings. 5. When supplied from an effectively grounded primary system does not see load unbalances and ground faults in the secondary system. 1. Suitable for both ungrounded and effectively grounded sources. 2. Suitable for a 3-wire service or a 4-wire delta service with a mid-tap ground. 3. Grounding the primary neutral of this connection would create a ground source for the primary system. This could subject the transformer to severe overloading during a primary system disturbance or load unbalance. 4. Frequently installed with mid-tap ground on one leg when supplying combination 3-phase and single-phase load where the 3-phase load is much larger than single-phase load. 5. When used in 25 kV and 35 kV 3-phase 4-wire primary systems, ferroresonance can occur when energizing or de-energizing the transformer using single-pole switches located at the primary terminals. With smaller kVA transformers the probability of ferroresonance is higher. 1. Suitable for both ungrounded and effectively grounded sources. 2. Suitable for a 3-wire service only, even if XO is grounded. 3. This connection is incapable of furnishing a stabilized neutral and its use may result in phase-to-neutral overvoltage (neutral shift) as a result of unbalanced phase-to-neutral load. 4. If a 3-phase unit is built on a three-legged core, the neutral point of the primary windings is practically locked at ground potential.
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
X1 H1 H3 X3
X0 H1 H3 X1 X3
H0 H1 H3 X1
X0 X3
1. Suitable for 4-wire effectively grounded source only. 2. Suitable for a 3-wire service or for 4-wire grounded service with XO grounded. 3. 3-phase transformers with this connection may experience stray ux tank heating during certain external system unbalances unless the core conguration (four or ve legged) utilized provides a return path for the ux. 4. Fundamental and harmonic frequency zero-sequence currents in the secondary lines supplied by the transformer also ow in the primary lines (and primary neutral conductor). 5. Ground relay for the primary system may see load unbalances and ground faults in the secondary system. This must be considered when coordinating overcurrent protective devices. 6. 3-phase transformers with the neutral points of the high voltage and low voltage windings connected together internally and brought out through an HOXO bushing should not be operated with the HOXO bushing ungrounded (oating). To do so can result in very high voltages in the secondary systems. 1. Suitable for both ungrounded and effectively grounded sources. 2. Suitable for a 3-wire service or a 4-wire service with a mid-tap ground. 3. When using the tap for single-phase circuits the single-phase load kVA should not exceed 5% of the 3-phase kVA rating of the transformer. The 3-phase rating of the transformer is also substantially reduced.
H1
H3
X1
X3
CA08104001E
1.1-6
TOC
Index
June 2006
Sheet 0026
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Types of Systems
In many cases, power is supplied by the utility to a building at the utilization voltage. In these cases, the distribution of power within the building is achieved through the use of a simple radial distribution system. In cases where the utility service voltage is at some voltage higher than the utilization voltage within the building, the system design engineer has a choice of a number of types of systems which may be used. This discussion covers several major types of distribution systems and practical modications of them. 1. Simple Radial. 2. Loop-Primary System Radial Secondary System. 3. Primary Selective System Secondary Radial System. 4. Two-Source Primary Secondary Selective System. 5. Sparing Transformer System. 6. Simple Spot Network. 7. Medium Voltage Distribution System Design.
Low voltage feeder circuits run from the switchgear or switchboard assemblies to panelboards that are located closer to their respective loads as shown in Figure 1.1-1. Each feeder is connected to the switchgear or switchboard bus through a circuit breaker or other overcurrent protective device. A relatively small number of circuits are used to distribute power to the loads from the switchgear or switchboard assemblies and panelboards. Since the entire load is served from a single source, full advantage can be taken of the diversity among the loads. This makes it possible to minimize the installed transformer capacity. However, the voltage regulation and efciency of this system may be poor because of the low voltage feeders and single source. The cost of the low voltagefeeder circuits and their associated circuit breakers are high when the feeders are long and the peak demand is above 1000 kVA.
A fault on the secondary low voltage bus or in the source transformer will interrupt service to all loads. Service cannot be restored until the necessary repairs have been made. A low voltage feeder circuit fault will interrupt service to all loads supplied over that feeder. A modern and improved form of the conventional simple radial system distributes power at a primary voltage. The voltage is stepped down to utilization level in the several load areas within the building typically through secondary unit substation transformers. The transformers are usually connected to their associated load bus through a circuit breaker, as shown in Figure 1.1-2. Each secondary unit substation is an assembled unit consisting of a 3-phase, liquid-lled or air-cooled transformer, an integrally connected primary fused switch, and low voltage switchgear or switchboard with circuit breakers or fused switches. Circuits are run to the loads from these low voltage protective devices.
Distribution Dry-Type Transformer Distribution Panel MCC Distribution Panel Lighting Panelboard
Primary Cables
June 2006
Sheet 0027
TOC
Index
1.1-7
Master TOC
Since each transformer is located within a specic load area, it must have sufcient capacity to carry the peak load of that area. Consequently, if any diversity exists among the load area, this modied primary radial system requires more transformer capacity than the basic form of the simple radial system. However, because power is distributed to the load areas at a primary voltage, losses are reduced, voltage regulation is improved, feeder circuit costs are reduced substantially, and large low voltage feeder circuit breakers are eliminated. In many cases the interrupting duty imposed on the load circuit breakers is reduced. This modern form of the simple radial system will usually be lower in initial investment than most other types of primary distribution systems for buildings in which the peak load is above 1000 kVA. A fault on a primary feeder circuit or in one transformer will cause an outage to only those secondary loads served by that feeder or transformer. In the case of a primary main bus fault or a utility service outage, service is interrupted to all loads until the trouble is eliminated. Reducing the number of transformers per primary feeder by adding more primary feeder circuits will improve the exibility and service continuity of this system; the ultimate being one secondary unit substation per primary feeder circuit. This of course increases the investment in the system but minimizes the extent of an outage resulting from a transformer or primary feeder fault. Primary connections from one secondary unit substation to the next secondary unit substation can be made with double lugs on the unit substation primary switch as shown, or with separable connectors made in manholes or other locations. Depending on the load kVA connected to each primary circuit and if no ground fault protection is desired for either the primary feeder conductors and transformers connected to that feeder or the main bus, the primary main and/or feeder breakers may be changed to primary fused switches. This will signicantly reduce the rst cost, but also decrease the level of conductor and equipment protection. Thus, should a fault or overload condition occur, downtime increases signicantly and higher costs associated with increased damage levels and the need for fuse replacement is typically encountered.
CA08104001E
In addition, if only one primary fuse on a circuit opens, the secondary loads are then single phased, causing damage to low voltage motors. Another approach to reducing costs is to eliminate the primary feeder breakers completely, and utilize a single primary main breaker or fused switch for protection of a single primary feeder circuit with all secondary unit sub-stations supplied from this circuit. Although this system results in less initial equipment cost, system reliability is reduced drastically since a single fault in any part of the primary conductor would cause an outage to all loads within the facility.
break switches with load side bus connection) sectionalizing switches and primary load break fused switch as shown in Figure 1.1-4. When pad-mounted compartmentalized transformers are utilized, they are furnished with loop feed oil immersed gang operated load break sectionalizing switches and drawout current limiting fuses in dry wells as shown in Figure 1.1-5. By operating the appropriate sectionalizing switches, it is possible to disconnect any section of the loop conductors from the rest of the system. In addition, by opening the transformer primary switch (or removing the load break drawout fuses in the pad-mounted transformer) it is possible to disconnect any transformer from the loop. A key interlocking scheme is normally recommended to prevent closing all sectionalizing devices in the loop. Each primary loop sectionalizing switch and the feeder breakers to the loop are interlocked such that to be closed they require a key (which is held captive until the switch or breaker is opened) and one less key than the number of key interlock cylinders is furnished. An extra key is provided to defeat the interlock under qualied supervision.
i ii 1 2 3 4 5 6 7 8 9 10
11 12 13
Tie Breaker
52
52
14 15 16
NC
NC
NO
NC
NC
NC
17 18 19
Secondary Unit Substations Consisting of: Duplex Primary Switches/Fused Primary Switches/ Transformer and Secondary Main Feeder Breakers
20 21
1.1-8
TOC
Index
June 2006
Sheet 0028
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Loop Feeder
When a primary feeder conductor fault occurs, the associated loop feeder breaker opens and interrupts service to all loads up to the normally open primary loop load break switch (typically half of the loads). Once it is determined which section of primary cable has been faulted, the loop sectionalizing switches on each side of the faulted conductor can be opened, the loop sectionalizing switch which had been previously left open then closed and service restored to all secondary unit substations while the faulted conductor is replaced. If the fault should occur in a conductor directly on the load side of one of the loop feeder breakers, the loop feeder breaker is kept open after tripping and the next load side loop sectionalizing switch manually opened so that the faulted conductor can be sectionalized and replaced.
Note: Under this condition, all secondary unit substations are supplied through the other loop feeder circuit breaker, and thus all conductors around the loop should be sized to carry the entire load connected to the loop. Increasing the number of primary loops (two loops shown in Figure 1.1-6) will reduce the extent of the outage from a conductor fault, but will also increase the system investment.
52
Loop A
Loop A
In cases where only one primary line is available, the use of a single primary breaker provides the loop connections to the loads as shown here.
Figure 1.1-6. Single Primary Feeder Loop System A basic primary loop system which utilizes a single primary feeder breaker connected directly to two loop feeder switches which in turn then feed the loop is shown in Figure 1.1-6. In this basic system the loop may be normally operated with one of the loop sectionalizing switches open as described above or with all loop sectionalizing switches closed. If a fault occurs in the basic primary loop system, the single loop feeder breaker trips, and secondary loads are lost until the faulted conductor is found and eliminated from the loop by opening the appropriate loop sectionalizing switches and then reclosing the breaker.
Figure 1.1-5. Pad-Mounted Transformer Loop Switching In addition, the two primary main breakers which are normally closed and primary tie breaker which is normally open are either mechanically or electrically interlocked to prevent paralleling the incoming source lines. For slightly added cost, an automatic throw-over scheme can be added between the two main breakers and tie breaker. During the more common event of a utility outage, the automatic transfer scheme provides signicantly reduced power outage time. The system in Figure 1.1-3 has higher costs than in Figure 1.1-2, but offers increased reliability and quick restoration of service when 1) a utility outage occurs, 2) a primary feeder conductor fault occurs, or 3) a transformer fault or overload occurs. Should a utility outage occur on one of the incoming lines, the associated primary main breaker is opened and the tie breaker closed either manually or through an automatic transfer scheme.
When a transformer fault or overload occurs, the transformer primary fuses open, and the transformer primary switch manually opened, disconnecting the transformer from the loop, and leaving all other secondary unit substation loads unaffected.
Primary Metal-Clad Switchgear Lineup Bus A
52
52
52
52
52
52
52
Feeder A1
Feeder B1
Feeder B2 Feeder A2
To Other Substations
NO
NC
NO
NC NO
Typical Secondary Unit Substation Duplex Primary Switch/Fuses Transformer/600 V Class Secondary Switchgear
NC
June 2006
Sheet 0029
TOC
Index
1.1-9
Master TOC
designed so that when one primary circuit is out of service, the remaining feeder or feeders have sufcient capacity to carry the total load. Half of the transformers are normally connected to each of the two feeders. When a fault occurs on one of the primary feeders, only half of the load in the building is dropped. Duplex fused switches as shown in Figure 1.1-7 and detailed in Figure 1.1-8 are the normal choice for this type of system. Each duplex fused switch consists of two (2) load break 3-pole switches each in their own separate structure, connected together by bus bars on the load side. Typically, the load break switch closest to the transformer includes a fuse assembly with fuses. Mechanical and/or key interlocking is furnished such that both switches cannot be closed at the same time (to prevent parallel operation) and interlocking such that access to either switch or fuse assembly cannot be obtained unless both switches are opened.
Primary Feeders
Primary Feeders
or most of the loads, may more than offset the greater cost. Having twosources allows for either manual or automatic transfer of the two primary main breakers and tie breaker should one of the sources become unavailable. The primary selective-secondary radial system, however, may be less costly or more costly than a primary loop secondary radial system of Figure 1.1-3 depending on the physical location of the transformers while offering comparable downtime and reliability. The cost of conductors for the two types of systems may vary greatly depending on the location of the transformers and loads within the facility and greatly override primary switching equipment cost differences between the two systems.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Fuses
Figure 1.1-9. Fused Selector Switch in One Structure This means limited cable space especially if double lugs are furnished for each line as shown in Figure 1.1-7 and should a faulted primary conductor have to be changed, both lines would have to be deenergized for safe changing of the faulted conductors. In Figure 1.1-7 when a primary feeder fault occurs the associated feeder breaker opens, and the transformers normally supplied from the faulted feeder are out of service. Then manually, each primary switch connected to the faulted line must be opened and then the alternate line primary switch can be closed connecting the transformer to the live feeder, thus restoring service to all loads. Note that each of the primary circuit conductors for Feeder A1 and B1 must be sized to handle the sum of the loads normally connected to both A1 and B1. Similar sizing of Feeders A2 and B2, etc., is required. If a fault occurs in one transformer, the associated primary fuses blow and interrupts the service to just the load served by that transformer. Service cannot be restored to the loads normally served by the faulted transformer until the transformer is repaired or replaced. Cost of the primary selective secondary radial system is greater than that of the simple primary radial system of Figure 1.1-1 because of the additional primary main breakers, tie breaker, two-sources, increased number of feeder breakers, the use of primary-duplex or selector switches, and the greater amount of primary feeder cable required. The benets from the reduction in the amount of load lost when a primary feeder is faulted, plus the quick restoration of service to all
Fuses
Figure 1.1-8. Duplex Fused Switch in Two Structures As an alternate to the duplex switch arrangement, a non-load break selector switch mechanically interlocked with a load break fused switch can be utilized as shown in Figure 1.1-9. The non-load break selector switch is physically located in the rear of the load break fused switch, thus only requiring one structure and a lower cost and oor space savings over the duplex arrangement. The non-load break switch is mechanically interlocked to prevent its operation unless the load break switch is opened. The main disadvantage of the selector switch is that conductors from both circuits are terminated in the same structure.
CA08104001E
TOC
Index
June 2006
Sheet 0030
Master TOC
i ii 1 2 3
secondary emergency transfer. If the loss of voltage was due to a failure of one of the transformers in the doubleended unit substation, then the associated primary fuses would open taking only the failed transformer out of service, and then only the secondary loads normally served by the faulted transformer would have to be transferred to the opposite transformer.
In either of the above emergency conditions, the in-service transformer of a double-ended unit substation would have to have the capability of serving the loads on both sides of the tie breaker. For this reason, transformers utilized in this application have equal kVA rating on each side of the doubleended unit substation and the normal operating maximum load on each transformer is typically about 2/3 base
nameplate kVA rating. Typically these transformers are furnished with fancooling and/or lower than normal temperature rise such that under emergency conditions they can carry on a continuous basis the maximum load on both sides of the secondary tie breaker. Because of this spare transformer capacity, the voltage regulation provided by the double-ended unit substation system under normal conditions is better than that of the systems previously discussed. The double-ended unit substation arrangement can be utilized in conjunction with any of the previous systems discussed which involve two primary sources. Although not recommended, if allowed by the utility, momentary re-transfer of loads to the restored source may be made closed transition (anti-parallel interlock schemes would have to be defeated) for either the primary or secondary systems. Under this condition, all equipment interrupting and momentary ratings should be suitable for the fault current available from both sources. For double-ended unit substations equipped with ground fault systems special consideration to transformer neutral grounding and equipment operation should be made see Grounding and Ground Fault Protection in Section 1.4. Where two single-ended unit substations are connected together by external tie conductors, it is recommended that a tie breaker be furnished at each end of the tie conductors.
52
52 52
4 5 6 7 8 9 10 11 12 13
K K Primary Fused Switch Transformer To Other Substations Typical Double-Ended Unit Substation 52 52
52
52
To Other Substations
Tie Breaker
14 15 16
K K Sparing Transformer
17 18 19
K K Typical Single-Ended Substation Typical Secondary Busway Loop
The sparing transformer system concept came into use as an alternative to the capital cost intensive double-ended secondary unit substation distribution system (see Two-Source Primary Secondary Selective System). It essentially replaces double-ended substations with single-ended substations and one or more sparing transformer substations all interconnected on a common secondary bus (see Figure 1.1-11).
Generally no more than 3 to 5 singleended substations are on a sparing loop. The essence of this design philosophy is that conservatively designed and loaded transformers are highly reliable electrical devices and rarely fail. Therefore, this design provides a single common backup transformer for a group of transformers in lieu of a backup transformer for each and every transformer. This system design still maintains a high degree of continuity of service.
CA08104001E
20 21
Figure 1.1-11. Sparing Transformer System
June 2006
Sheet 0031
TOC
Index
1.1-11
Master TOC
Referring to Figure 1.1-11, it is apparent that the sparing concept backs up primary switch and primary cable failure as well. Restoration of lost or failed utility power is accomplished similarly to primary selective scheme previously discussed. It is therefore important to use an automatic throwover system in a two source lineup of primary switchgear to restore utility power as discussed in the Two-Source Primary scheme see Figure 1.1-10. A major advantage of the sparing transformer system is the typically lower total base kVA of transformation. In a double-ended substation design, each transformer must be rated to carry the sum of the loads of two busses and usually requires the addition of cooling fans to accomplish this rating. In the sparing concept, each transformer carries only its own load, which is typically not a fan-cooled rating. Major space savings is also a benet of this system in addition to rst cost savings. The sparing transformer system operates as follows: All main breakers, including the sparing main breaker are normally closed; the tie breakers are normally open. s Once a transformer (or primary cable or primary switch/fuse) fails, the associated secondary main breaker is opened. The associated tie breaker is then closed, which restores power to the single-ended substation bus. s Schemes which require the main to be opened before the tie is closed (open transition), and which allow any tie to be closed before the substation main is opened, (closed transition) are possible.
s
In facilities with no qualied electrical power operators, an open transition with key interlocking is often a prudent design.
Note: Each pair of main breaker/tie breaker key cylinders should be uniquely keyed to prevent any paralleled source operations.
Careful sizing of these transformers as well as careful specication of the transformers is required for reliability. Low temperature rise specied with continuous overload capacity or upgraded types of transformers should be considered. One disadvantage to this system is the external secondary tie system, see Figure 1.1-11. As shown, all singleended substations are tied together on the secondary with a tie busway or cable system. Location of substations is therefore limited because of voltage drop and cost considerations. Routing of busway, if used, must be carefully layed out. It should also be noted, that a tie busway or cable fault will essentially prevent the use of the sparing transformer until it is repaired. Commonly, the single-ended substations and the sparing transformer must be clustered. This can also be an advantage, as more kVA can be supported from a more compact space layout.
The major advantage of the secondary network system is continuity of service. No single fault anywhere on the primary system will interrupt service to any of the systems loads. Most faults will be cleared without interrupting service to any load. Another outstanding advantage that the network system offers is its exibility to meet changing and growing load conditions at minimum cost and minimum interruption in service to other loads on the network. In addition to exibility and service reliability, the secondary network system provides exceptionally uniform and good voltage regulation, and its high efciency materially reduces the costs of system losses. Three major differences between the network system and the simple radial system account for the outstanding advantages of the network. First, a network protector is connected in the secondary leads of each network transformer in place of, or in addition to, the secondary main breaker, as shown in Figure 1.1-12. Also, the secondaries of each transformer in a given location (spot) are connected together by a switchgear or ring bus from which the loads are served over short radial feeder circuits. Finally, the primary supply has sufcient capacity to carry the entire building load without overloading when any one primary feeder is out of service. A network protector is a specially designed heavy duty air power breaker, spring close with electrical motor-charged mechanism, with a network relay to control the status of the protector (tripped or closed). The network relay is usually a solid-state microprocessorbased component integrated
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
With a closed transition scheme it is common to add a timer function that opens the tie breaker unless either main breaker is opened within a time interval. This closed transition allows power to be transferred to the sparing transformer without interruption, such as for routine maintenance, and then back to the substation. This closed transition transfer has an advantage in some facilities, however, appropriate interrupting capacities and bus bracing must be specied suitable for the momentary parallel operation.
Typical Feeder Primary Circuit Network Transformer Network Protector Fuses Optional Main, 50/51 Relaying and/or Network Disconnect To Other Networks
Tie NC
18 19
LV Feeder
Customer Loads
Customer Loads
Customer Loads
20 21
CA08104001E
TOC
Index
June 2006
Sheet 0032
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
into the protector enclosure which functions to automatically close the protector only when the voltage conditions are such that its associated transformer will supply power to the secondary network loads, and to automatically open the protector when power ows from the secondary to the network transformer. The purpose of the network protector is to protect the integrity of the network bus voltage and the loads served from it against transformer and primary feeder faults by quickly disconnecting the defective feeder-transformer pair from the network when backfeed occurs. The simple spot network system resembles the secondary-selective radial system in that each load area is supplied over two or more primary feeders through two or more transformers. In network systems, the transformers are connected through network protectors to a common bus, as shown in Figure 1.1-12, from which loads are served. Since the transformers are connected in parallel, a primary feeder or transformer fault does not cause any service interruption to the loads. The paralleled transformers supplying each load bus will normally carry equal load currents, whereas equal loading of the two separate transformers supplying a substation in the secondary-selective radial system is difcult to obtain. The interrupting duty imposed on the outgoing feeder breakers in the network will be greater with the spot network system. The optimum size and number of primary feeders can be used in the spot network system because the loss of any primary feeder and its associated transformers does not result in the loss of any load even for an instant. In spite of the spare capacity usually supplied in network systems, savings in primary switchgear and secondary switchgear costs often result when compared to a radial system design with similar spare capacity. This occurs in many radial systems because more and smaller feeders are often used in order to minimize the extent of any outage when a primary fault event occurs. In spot networks, when a fault occurs on a primary feeder or in a transformer, the fault is isolated from the system through the automatic tripping of the primary feeder circuit breaker and all of the network protectors associated
with that feeder circuit. This operation does not interrupt service to any loads. After the necessary repairs have been made, the system can be restored to normal operating conditions by closing the primary feeder breaker. All network protectors associated with that feeder will close automatically. The chief purpose of the network bus normally closed ties is to provide for the sharing of loads and a balancing of load currents for each primary service and transformer regardless of the condition of the primary services. Also, the ties provide a means for isolating and sectionalizing ground fault events within the switchgear network bus, thereby saving a portion of the loads from service interruptions, yet isolating the faulted portion for corrective action. The use of spot network systems provides users with several important advantages. First, they save transformer capacity. Spot networks permit equal loading of transformers under all conditions. Also, networks yield lower system losses and greatly improve voltage conditions. The voltage regulation on a network system is such that both lights and power can be fed from the same load bus. Much larger motors can be started acrossthe-line than on a simple radial system. This can result in simplied motor control and permits the use of relatively large low voltage motors with their less expensive control. Finally, network systems provide a greater degree of exibility in adding future loads; they can be connected to the closest spot network bus. Spot network systems are economical for buildings which have heavy concentrations of loads covering small areas, with considerable distance between areas, and light loads within the distances separating the concentrated loads. They are commonly used in hospitals, high rise ofce buildings, and institutional buildings where a high degree of service reliability is required from the utility sources. Spot network systems are especially economical where three or more primary feeders are available. Principally, this is due to supplying each load bus through three or more transformers and the reduction in spare cable and transformer capacity required.
They are also economical when compared to two transformer doubleended substations with normally opened tie breakers. Emergency power should be connected to network loads downstream from the network, or upstream at primary voltage, not at the network bus itself.
52 Main Bus
52
52
Figure 1.1-13. Single Bus This conguration is the simplest system, however, outage of the utility results in total outage. Normally the generator does not have adequate capacity for the entire load. A properly relayed system equipped with load shedding, automatic voltage/ frequency control may be able to maintain partial system operation. Any future addition of breaker sections to the bus will require a shutdown of the bus, since there is no tie breaker.
CA08104001E
June 2006
Sheet 0033
TOC
Index
1.1-13
Master TOC
Utility #1
Utility #2
Normal
Standby
Again, the closing of the tie breaker can be manual or automatic. The statements made for the retransfer of scheme B apply to this scheme also.
Utility #1 Utility #2
The third tie breaker allows any bus to be fed from any utility source. Caution for Figures 1.1-14, 1.1-15 and 1.1-16: If continuous paralleling of sources is planned, reverse current, reverse power and other appropriate relaying protection should be added. When both sources are paralleled for any amount of time, the fault current available on the load side of the main device is the sum of the available fault current from each source plus the motor fault contribution. It is required that bus bracing, feeder breakers and all load side equipment is rated for the increased available fault current.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
52 NC
Figure 1.1-14. Single Bus with Two-Sources Retransfer to the Normal can be closed transition subject to the approval of the utility. Closed transition momentarily (5 10 cycles) parallels both utility sources. Caution: when both sources are paralleled, the fault current available on the load side of the main device is the sum of the available fault current from each source plus the motor fault contribution. It is recommended that the short circuit ratings of the bus, feeder breakers and all load side equipment are rated for the increased available fault current. If the utility requires open transfer, the disconnection of motors from the bus must be ensured by means of suitable time delay on reclosing as well as supervision of the bus voltage and its phase with respect to the incoming source voltage. This busing scheme does not preclude the use of cogeneration, but requires the use of sophisticated automatic synchronizing and synchronism checking controls, in addition to the previously mentioned load shedding, automatic frequency and voltage controls. This conguration is more expensive than the scheme shown in Figure 1.1-13, but service restoration is quicker. Again, a utility outage results in total outage to the load until transfer occurs. Extension of the bus or adding breakers requires a shutdown of the bus. If paralleling sources, reverse current, reverse power, and other appropriate relaying protection should be added as requested by the utility.
52 52
Summary
The medium voltage system congurations shown are based on using metalclad drawout switchgear. The service continuity required from electrical systems makes the use of single source systems impractical. In the design of a modern medium voltage system the engineer should: 1. Design a system as simple as possible. 2. Limit an outage to as small a portion of the system as possible. 3. Provide means for expanding the system without major shutdowns. 4. Relay the system so that only the faulted part is removed from service, and damage to it is minimized consistent with selectivity. 5. Specify and apply all equipment within its published ratings and national standards pertaining to the equipment and its installation.
Load
Load
Figure 1.1-15. Two-Source Utility with Tie Breaker If looped or primary selective distribution system for the loads is used, the buses can be extended without a shutdown by closing the tie breaker and transferring the loads to the other bus. This conguration is more expensive than B. The system is not limited to two buses only. Another advantage is that the design may incorporate momentary paralleling of buses on retransfer after the failed line has been restored to prevent another outage. See the Caution for Figures 1.1-14, 1.1-15 and 1.1-16. In Figure 1.1-16, closing of the tie breaker following the opening of a main breaker can be manual or automatic. However since a bus can be fed through two tie breakers the control scheme should be designed to make the selection.
Utility #1
Utility #2
Utility #3
16 17
52 NC NO 52 52 NC NO 52 52 NC
18 19
C. Multiple Sources with Tie Breaker, Figure 1.1-15 and Figure 1.1-16
This conguration is similar to conguration B. It differs signicantly in that both utility sources normally carry the loads and also by the incorporation of a normally open tie breaker. The outage to the system load for a utility outage is limited to half of the system.
CA08104001E
Bus #1
Bus #2
Bus #3
52
52
52 NO
20 21
TOC
Index
June 2006
Sheet 0034
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11
NFPA 101 Life Safety Code. NFPA 110 Standard for Emergency and Standby Power Systems. s NFPA 111 Standard on Stored Electrical Energy Emergency and Standby Power Systems.
s s
These NFPA guidelines represent the most industry recognized standard requirements for health care electrical design. However, the electrical design engineer should consult with the authorities having jurisdiction over the local region for specic electrical distribution requirements.
The electrical system requirements for the Essential Electrical System (EES) vary according to the type of health care facility. Health care facilities are categorized by NFPA 99 as Type 1, Type 2 or, Type 3 facilities. Some example health care facilities, classied by Type, are summarized in the following Table 1.1-8. Table 1.1-8. Health Care Facilities
Description Denition EES Type Hospitals NFPA 99 Chap. 13 Type 1 Nursing Homes NFPA 99 Chap. 17 Type 2 Limited Care Facilities NFPA 99 Chap. 18 Type 2 Ambulatory Surgical Facilities NFPA 99 Chap. 14 Type 3 Other Health Care Facilities NFPA 99 Chap. 14 Type 3 If electrical life support or critical care areas are present then facility is classied as Type 1.
Normal Source
Normal Source
Normal Source
12 13 14 15 16
Non-Essential Loads Non-Essential Loads
17 18 19 20 21
Manual Transfer Switch Delayed Automatic Transfer Switch Automatic (Non-Delaying) Transfer Switch Equipment System Life Safety Critical Branch Branch Emergency System Essential Electrical System
CA08104001E
June 2006
Sheet 0035
TOC
Index
1.1-15
Master TOC
Sources: Type 1 systems are required to have a minimum of two independent sources of electrical power. A normal source that generally supplies the entire facility and one or more alternate sources that supply power when the normal source is interrupted. The alternate source(s) must be an on-site generator driven by a prime mover unless a generator(s) exists as the normal power source. In the case where a generator(s) is utilized as the normal source, it is permissible for the alternate source to be a utility feed. Alternate source generators must be classied as Type 10, Class X, Level 1 gensets per NFPA 110 2-2 capable of providing power to the load in a maximum of 10 seconds. Typically, the alternate sources of power are supplied to the loads through a series of automatic and/or manual transfer switches. (See Section 25.) The transfer switches can be non-delayed automatic, delayed automatic, or manual transfer depending on the requirements of the specic branch of the EES that they are feeding. It is permissible to feed multiple branches or systems of the EES from a single automatic transfer switch provided that the maximum demand on the EES does not exceed 150 kVA. This conguration is typically seen in smaller health care facilities that must meet Type 1 EES requirements. (See Figure 1.1-18.)
Normal Source Alternate Source G
4 4.4.2 517-30
Systems and Branches of Service: The Type 1 EES consists of two separate power systems capable of supplying power considered essential for life safety and effective facility operation during an interruption of the normal power source. They are the Emergency System and the Equipment System. 1. Emergency System consists of circuits essential to life safety and critical patient care. The Emergency System is an electrical sub-system that must be fed from an automatic transfer switch or series of automatic transfer switches. This Emergency System consists of two mandatory branches that provide power to systems and functions essential to life safety and critical patient care. A. Life Safety Branch supplies power for lighting, receptacles, and equipment to perform the following functions: 1. 2. 3. 4. Illumination of means of egress. Exit signs and exit direction signs. Alarms and alerting systems. Emergency communications systems. 5. Task illumination, battery chargers for battery powered lighting, and select receptacles at the generator. 6. Elevator lighting control, communication and signal systems. 7. Automatic doors used for egress. These are the only functions permitted to be on the life safety branch. Life Safety Branch equipment and wiring must be entirely independent of all other loads and branches of service. This includes separation of raceways, boxes or cabinets. Power must be supplied to the Life Safety Branch from a non-delayed automatic transfer switch.
B. Critical Branch supplies power for task illumination, xed equipment, selected receptacles and selected power circuits for areas related to patient care. The purpose of the critical branch is to provide power to a limited number of receptacles and locations to reduce load and minimize the chances of fault conditions. The transfer switch(es) feeding the critical branch must be automatic type. They are permitted to have appropriate time delays that will follow the restoration of the life safety branch but should have power restored within 10 seconds of normal source power loss. The critical branch provides power to circuits serving the following areas and functions: 1. Critical care areas. 2. Isolated Power Systems in special environments. 3. Task illumination and selected receptacles in the following patient care areas: infant nurseries, medication prep areas, pharmacy, selected acute nursing areas, psychiatric bed areas, ward treatment rooms, nurses stations. 4. Specialized patient care task illumination, where needed. 5. Nurse call systems. 6. Blood, bone and tissue banks. 7. Telephone equipment rooms and closets. 8. Task illumination, selected receptacles, and selected power circuits for the following: general care beds (at least one duplex receptacle), angiographic labs, cardiac catheterization labs, coronary care units, hemodialysis rooms, selected emergency room treatment areas, human physiology labs, intensive care units, selected postoperative recovery rooms. 9. Additional circuits and singlephase fraction motors as needed for effective facility operation.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Figure 1.1-18. Small Hospital Electrical System Single EES Transfer Switch
CA08104001E
TOC
Index
June 2006
Sheet 0036
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14
The following equipment must be arranged for delayed automatic or manual transfer to the emergency power supply: 1. Select heating equipment. 2. Select elevators. 3. Supply, return and exhaust ventilating systems for surgical, obstetrical, intensive care, coronary care, nurseries, and emergency treatment areas. 4. Supply, return and exhaust ventilating systems for airborne infectious/isolation rooms, labs and medical areas where hazardous materials are used. 5. Hyperbaric facilities. 6. Hypobaric facilities. 7. Autoclaving equipment. 8. Controls for equipment listed above. 9. Other selected equipment in kitchens, laundries, radiology rooms, and central refrigeration as selected. Table 1.1-11. Type 1 Equipment System Applicable Codes
Description General Equipment Standard NFPA 99 NEC NFPA 99 NEC Section 4.4.2.2.3 517-34 4.4.2.2.3 (3-5) 517-34(a)-(b)
must be congured such that the loads will not cause the generator to overload and must be shed in the event the generator enters an overload condition. Ground Fault Protection per NFPA 70 NEC article 230-95, ground fault protection is required on any feeder or service disconnect 1000 A or larger on systems with line to ground voltages of 150 volts or greater and phase-to-phase voltages of 600 volts or less. For health care facilities (of any type), a second level of ground fault protection is required to be on the next level of feeder downstream. This second level of ground fault is only required for feeders that serve patient care areas and equipment intended to support life. 100% selective coordination of the two levels of ground fault protection must be achieved with a minimum six-cycle separation between the upstream and downstream device. NEC 517-17 prohibits the installation of ground fault protection between the on-site generator(s) and any EES transfer switch or on the load side of a transfer switch feeding EES circuits. (See Figure 1.1-19 Additional Level of Ground Fault). The intent of this code section is to prevent a ground fault that causes a trip on the normal system to also cause a trip on the emergency system. Such an event could result in complete power loss of both normal and emergency power sources and could not be recovered until the source of the ground fault was located and isolated from the system. To prevent this condition, NEC 700-26 removes the
2. Equipment System consists of major electrical equipment necessary for patient care and Type 1 operation. The Equipment System is a subsystem of the EES that consists of large electrical equipment loads needed for patient care and basic hospital operation. Loads on the Equipment System that are essential to generator operation are required to be fed by a non-delayed automatic transfer switch. The following equipment must be arranged for delayed automatic transfer to the emergency power supply: 1. Central suction systems for medical and surgical functions. 2. Sump pumps and other equipment required for the safe operation of a major apparatus. 3. Compressed air systems for medical and surgical functions. 4. Smoke control and stair pressurization systems. 5. Kitchen hood supply and exhaust systems, if required to operate during a re.
Normal Source
Any loads served by the generator that are not approved as outlined above as part of the Essential Electrical System must be connected through a separate transfer switch. These transfer switches
Normal Source(s)
G Generator Breakers are Typically Supplied with Ground Fault Alarm Only. (NEC 700-26) Additional Level of Ground Fault is not Permitted Between Generator and EES Transfer Switches. (NEC 517-17a(1))
480/277 V
15 16 17 18 19 20
GF GF GF GF GF
GF GF GF
GF GF GF
Non-Essential Loads
Non-Essential Loads
Additional Level of Ground Fault is not Permitted on Load Side of EES Transfer Switches. (NEC 517-17a(2))
21
Ground fault protection is required for service disconnects 1000 amperes and larger or systems with less than 600 volts phase-to-phase and greater than 150 volts to ground per NEC 230-95.
CA08104001E
June 2006
Sheet 0037
TOC
Index
1.1-17
Master TOC
ground fault protection requirement for the emergency system source. Typically, the emergency system generator(s) are equipped with ground fault alarms that do not automatically disconnect during a ground fault. Table 1.1-12. Ground Fault Protection Applicable Codes
Description Services Feeders Additional Level Alternate Source Standard NEC NEC NEC NFPA 99 NEC NEC Section 230-95 215-10 517-17 4.3.2.5 700-26 700-7 (d)
trained in development and execution of annual preventative maintenance procedures of health care facility electrical distribution systems.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Wet Locations A wet location in a health care facility is any patient care area that is normally subject to wet conditions while patients are present. Typical wet locations can include operating rooms, anesthetizing locations, dialysis locations, etc. (Patient beds, toilets, sinks, are not considered wet locations.) These wet locations require special protection to guard against electric shock. The ground fault current in these areas must be limited not to exceed 6 mA. In areas where the interruption of power is permissible, ground fault circuit interrupters (GFCI) can be employed. GFCIs will interrupt a circuit when ground fault current exceeds the present level (typically 2-5 mA). In areas where the interruption of power cannot be tolerated, protection from ground fault currents is accomplished through the use of an Isolated Power System. Isolated Power Systems provide power to an area that is isolated from ground (or ungrounded). This type of system limits the amount of current that ows to ground in the event of a single line-to-ground fault and maintains circuit continuity. Electronic Line Isolation Monitors (LIM) are used to monitor and display leakage currents to ground. When leakage current thresholds are exceeded, visible and/or audible alarms are initiated to alert occupants of a possible hazardous condition. This alarm occurs without interrupting power to allow for the safe conclusion of critical procedures. Table 1.1-13. Wet Location Applicable Codes
Description General Isolated Power Systems Standard NFPA 99 NEC NFPA 99 NEC Section 4.3.2.2.9 517-20 4.3.2.6 517-160
Routine maintenance should be performed on circuit breakers, transfer switches, switchgear, generator equipment, etc. by trained professionals to ensure the most reliable electrical system possible. See Section 43 for Eaton - Electrical Services & Systems E-ESS), which provides engineers,
CA08104001E
TOC
Index
June 2006
Sheet 0038
Master TOC
i ii 1 2 3 4 5 6 7
b. As each automatic transfer switch transfers back to utility power, it removes its run request from the generator plant. c. When the last automatic transfer switch has retransferred to the utility and all run requests have been removed from the generator plant, all generator circuit breakers are opened. d. The generators are allowed to run for their programmed cool- down period. e. The system is now back in Automatic/Standby Mode.
Many health care facilities are taking advantage of these utility incentives by adding generator capacity over and above the NFPA requirements. Figure 1.1-21 on Page 1.1-19 shows an example one-line of a health care facility with complete generator backup and utility interconnect. NFPA 110 requirements state that the normal and emergency sources must be separated by a re rated wall. The intent of this requirement is so that a re in one location cannot takeout both sources of power. To meet this requirement, the Paralleling Switchgear must be split into separate sections with a tie bus through a re rated wall. For more information on Generator Paralleling Switchgear, see Section 43.
Utility Transformer
8 9 10 11 12 13 14 15 16 17
Non-Essential Loads
Service Main
Emergency Bus Optional Electrically Operated Stored Energy Breakers F1 F2 Fx EF1 EF2 EFx
Equipment ATS # 1
Critical ATS # X
EP1
EP2
Typical Panelboards
EPX
Figure 1.1-20. Typical One-Line for a Paralleling Switchgear Line-up Feeding the Essential Electrical System (EES)
18 19 20 21
For more information visit: www.EatonElectrical.com CA08104001E
June 2006
Sheet 0039
TOC
Index
1.1-19
Master TOC
Utility Transformer
i ii 1 2 3
Emergency Bus
Utility Metering Utility Protective Relay Service Main Normal Bus Closed Transition Paralleling of Generators and Utility, Plus Soft Loading/ Unloading TIE Optional Electrically Operated Stored Energy Breakers Typical Generator Breaker
G1
G2
Gx
Optional TIE Electrically Operated Stored Energy Breakers EF1 EF2 EFx
4 5 6
F1
F2
Fx
Equipment ATS # 1
Critical ATS # X
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
EP2
EPX
Typical Panelboards
Figure 1.1-21. Typical One-Line Health Care Facility with Complete Generator Backup and Utility Interconnect
CA08104001E
June 2006
Sheet 0040
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
June 2006
Sheet 0041
TOC
Index
1.2-1
Master TOC
Types of Engines
Many generator sets are relatively small in size, typically ranging from several kilowatts to several megawatts. These units are often required to come on line and operate quickly. They need to have the capacity to run for an extended period of time. The internal combustion engine is an excellent choice as the prime mover for the majority of these applications. Turbines may also be utilized. Diesel fueled engines are the most common, but other fuels used include natural gas, digester gas, landll gas, propane, biodiesel, crude oil, steam and others. Some campuses and industrial facilities use and produce steam for heating and other processes. These facilities may nd it economically feasible to produce electricity as a by-product of the steam production. These installations would typically be classied as a cogeneration facility producing a fairly constant power output and operating in parallel with the electric utility system.
Types of Generators
Generators can be either synchronous or asynchronous. Asynchronous generators are also referred to as induction generators. The construction is essentially the same as an induction motor. It has a squirrel-cage rotor and wound stator. An induction generator is a motor driven above its designed synchronous speed thus generating power. It will operate as a motor if it is running below synchronous speed. The induction generator does not have an exciter and must operate in parallel with the utility or another source. The induction generator requires vars from an external source for it to generate power. The induction generator operates at a slip frequency so its output frequency is automatically locked in with the utility's frequency. An induction generator is a popular choice for use when designing cogeneration systems, where it will operate in parallel with the utility. This type of generator offers certain advantages over a synchronous generator. For example, voltage and frequency are controlled by the utility; thus voltage and frequency regulators are not required. In addition, the generator construction offers high reliability and little maintenance. Also, a minimum of protective relays and controls are required. Its major disadvantages are that it requires vars from the system and it normally cannot operate as a standby/emergency generator. Synchronous generators, however, are the most common. Their output is determined by their eld and governor controls. Varying the current in the dc eld windings controls the voltage output. The frequency is controlled by the speed of rotation. The torque applied to the generator shaft by the driving engine controls the power output. In this manner, the synchronous generator offers precise control over the power it can generate. In cogeneration applications, it can be used to improve the power factor of the system.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Introduction
The selection and application of generators into the electrical distribution system will depend on the particular application. There are many factors to consider including code requirements, environmental constraints, fuel sources, control complexity, utility requirements and load requirements. The Health Care Requirements for legally required emergency standby generation systems are described starting on Page 1.1-14. Systems described in this section are applicable to Health Care requirements, as well as other facilities that may require a high degree of reliability. The electrical supply for data centers, nancial institutions, telecommunications, government and public utilities also require high reliability. Threats of disaster or terror attacks have prompted many facilities to require complete self-sufciency for continuous operation.
CA08104001E
1.2-2
TOC
Index
June 2006
Sheet 0042
Master TOC
i ii 1 2 3 4 5 6 7 8
Generator Systems
Emergency Standby Generator System
There are primarily three types of generator systems. The rst and simplest type is a single generator that operates independently from the electric utility power grid. This is typically referred to as an Emergency Standby Generator System. Figure 1.2-1 shows a single standby generator, utility source and a transfer switch. In this case, the load is either supplied from the utility or the generator. The generator and the utility are never continuously connected together. This simple radial system has few requirements for protection and control. It also has the least impact on the complete electric power distribution system. It should be noted that this type of generator system improves overall electrical reliability but does not provide the redundancy that some facilities require if the generator fails to start or is out for maintenance.
Multiple generator systems have a more complex control and protection requirement as the units have to be synchronized and paralleled together. The generators are required to share the load proportionally without swings or prolonged hunting in voltage or frequency for load sharing. They may also require multiple levels of load shedding and/or load restoration schemes to match generation capacity.
Utility G1 G2
Switchgear
ATS-1
ATS-2
Load 1
Load 2
Utility
9 10 11
ATS
G1
Figure 1.2-2. Multiple Isolated Set of Standby Generators In an N system, where N is the number of generators required to carry the load; if a generator fails or is out for maintenance, then the load may be dropped. This is unacceptable for most critical 24/7 operations. In an N + 1 system, N is the number of generators needed to carry the load and 1 is an extra generator for redundancy. If one generator fails to start or is out for maintenance, it will not affect the load. In a 2N system, there is complete 100% redundancy in the standby generation system such that the failure of one complete set of generators will not affect the load.
Switchgear
12 13 14 15 16 17 18 19 20 21
Load
Load 1
Load 2
Load 3
CA08104001E
June 2006
Sheet 0043
TOC
Index
1.2-3
Master TOC
Generator Fundamentals
A generator consists of two primary components, a prime mover and an alternator. The prime mover is the energy source used to turn the rotor of the alternator. It is typically a diesel combustion engine for most emergency or standby systems. In cogeneration applications, the prime mover may come from a steam driven turbine or other source. On diesel units, a governor and voltage regulator are used to control the speed and power output. The alternator is typically a synchronous machine driven by the prime mover. A voltage regulator controls its voltage output by adjusting the eld. The output of a single generator or multiple paralleled generator sets is controlled by these two inputs. The alternator is designed to operate at a specied speed for the required output frequency, typically 60 or 50 hertz. The voltage regulator and engine governor along with other systems dene the generators response to dynamic load changes and motor starting characteristics. Generators are rated in power and voltage output. Most generators are designed to operate at a 0.8 power factor. For example, a 2000 kW generator at 277/480 V would have a kVA rating of 2500 kVA (2000 kW/ 08 pf) and a continuous current rating of 3007 A ( 2500 kVA 480V 3 ). Typical synchronous generators for industrial and commercial power systems range in size from 100 to 3,000 kVA and from 208 V to 13,800 V. There are other ratings available and these discussions are applicable to those ratings as well. Generators must be considered in the short circuit and coordination study as they may greatly impact the rating of the electrical distribution system. This is especially common on large installations with multiple generators and systems that parallel with the utility source. Short circuit current contribution from a generator typically ranges from 8 to 12 times full load amperes.
The application of generators requires special protection requirements. The size, voltage class, importance and dollar investment will inuence the protection scheme associated with the generator(s). Mode of operation will inuence the utility company's interface protection requirements. Paralleling with the electric utility is the most complicated of the utility inter-tie requirements. IEEE ANSI 1547 provides recommended practices.
need to be switched for 4-wire loads or ground fault relays could misoperate and unbalanced neutral current may be carried on ground conductors. An IEEE working group has studied the practice of low resistance grounding of medium voltage generators within the general industry. This working group found that, for internal generator ground faults, the vast majority of the damage is done after the generator breaker is tripped off-line and the eld and the turbine is tripped. This is due to the stored energy in the generator ux that takes several seconds to dissipate after the generator is tripped offline. It is during this time that the Low Resistance Ground contributes huge energy over time into the generator ground fault. One of the solutions set forth by this working group is a Hybrid High Resistance Grounding (HHRG) scheme as shown in Figure 1.2-4. In the HHRG scheme, the Low Resistance Ground (LRG) is quickly tripped off-line when the generator protection senses the ground fault. The LRG is cleared at the same time that the generator breaker clears leaving the High Resistance Ground portion connected to control the transient overvoltages during the coast-down phase of the generator thereby all but eliminating generator damage.
i ii 1 2 3 4 5 6 7 8 9 10 11
Generator Grounding
Generator grounding methods need to be considered and may affect the distribution equipment and ratings. Generators may be connected in delta or wye but wye is the most typical connection. A wye-connected generator can be solidly grounded, low impedance grounded, high impedance grounded or ungrounded. Section 1.4 discusses general grounding schemes, benets of each and protection considerations. A solidly grounded generator may have a lower zero sequence impedance than its positive sequence impedance. In this case, the equipment will need to be rated for the larger available ground fault current. The generator ground can be the same as the system ground or it could be a separate ground. If they are separate grounds, then the neutral will
12 13 14 15
16 17 18 19 20 21
CA08104001E
1.2-4
TOC
Index
June 2006
Sheet 0044
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Generator Controls
The engine generator set has controls to maintain the output frequency (speed) and voltage. These controls consist of a governor and voltage regulator. As loads change on the system the frequency and voltage will change. The speed control will then adjust the governor to correct for the load (kW) change. The voltage regulator will change the eld current to adjust the voltage to the desired voltage value. These are the basic controls found on all synchronous generators. Multiple generator systems require more sophisticated controls. Generators are paralleled in a multi-generator system and they must share the load. These systems often have a load shed scheme, which adds to the complexity. Multiple generator schemes need a master controller to prevent units from being connected out of phase. The sequence of operation is to send a start signal to all generators simultaneously. The rst unit up to frequency and voltage will be permitted to close its respective breaker and energize the paralleling bus. Breakers for the other generators are held open, not permitted to close, until certain conditions are met. Once the paralleling bus is energized the remaining generators must be synchronized to it before the generators can be paralleled. Synchronization compares the voltage phasors angle and magnitude. Both generators must be operating at the same frequency and lined up within typically 5 to 10 degrees with each other. The voltage magnitude typically must be within 20 to 24%. A synch-scope is typically supplied on paralleling gear. The synch-scope displays the relative relationship between voltage phasors on the generator to be paralleled and the bus. If the generator is running slower than the bus (less than 60 Hz) then the needle on the scope will spin in the counterclockwise direction. If it is running faster then it will rotate in the clockwise direction. The greater the frequency difference, the faster is the rotation. It is important that the generators are in phase before they are paralleled. Severe damage will occur if generators are paralleled out-of-phase.
Subtransient reactance Xd which is used to determine the fault current during the rst 1 to 5 cycles. s Transient reactance Xd which is used to determine the fault current during the next 5 to 200 cycles. s Synchronous reactance Xd which is used to determine the steady state fault current. The subtransient reactance Xd will range from a minimum of approximately 9% for a two pole round rotor machine to approximately 32% for a low speed salient pole hydro-generator. The initial symmetrical fault current can be as much as 12 times full load current. Depending on the generator type, the zero sequence impedance may be less than the subtransient reactance and the ground fault current substantially higher than the three phase short circuit current. For example, a 2500 kVA, 480/277 V, 4 pole, 2/3rds pitch stand-by generator has a 0.1411 per unit subtransient reactance Xd and a 0.033 per unit zero sequence Xo reactance. The ground current is approximately a third larger than the three-phase fault current. The ground fault current can be reduced to the three-phase level by simply adding a small reactance between the generator neutral and ground while still being considered solidly grounded. The electric power system analysis must be performed based on the worst case operating conditions. Typically this is when all sources are paralleled. If the system can operate with both the utility supply and generators in parallel then the equipment must be rated for the combined fault current plus motor contribution. If the generator and utility will not be paralleled, then both cases will need to be looked at independently and the worst case used for selecting the equipment ratings.
CA08104001E
June 2006
Sheet 0045
TOC
Index
1.2-5
Master TOC
Generator Protection
Generator protection will vary and depend on the size of the generator, type of system and importance of the generator. Generator sizes are dened as: small 1000 kVA maximum up to 600 V (500 kVA maximum when above 600 V); medium over 1000 kVA to 12,500 kVA maximum regardless of voltage; large from 12,500 50,000 kVA. The simplest is a single generator system used to feed emergency and/or standby loads. In this case, the generator is the only source available when it is operating and it must keep operating until the normal source returns. Figure 1.2-5 Part (A) shows minimum recommended protection for a single generator used as an emergency or standby system. Phase and ground time overcurrent protection (Device 51 and 51G) will provide protection for external faults. For medium voltage generators, a voltage controlled time overcurrent relay (Device 51V) is recommended for the phase protection as it can be set more sensitive than standard overcurrent relays and is less likely to false operate on normal overloads. This scheme may not provide adequate protection for internal generator faults when no other power source exists. Local generator controllers may offer additional protection for voltage and frequency conditions outside the generators capabilities. Figure 1.2-5 Part (B) shows the recommended protection for multiple isolated medium voltage small generators. Additional protection may be desired and could include generator differential, reverse power and loss of eld protection. Differential protection (Device 87) can be accomplished with either a self-balancing set of CTs as in Figure 1.2-6 or with a percentage differential scheme as in Figure 1.2-7 on Page 1.2-6. The percentage differential scheme offers the advantage of reducing the possibility for false tripping due to CT saturation. The self-balancing scheme offers the advantages increased sensitivity; needing three current transformers in lieu of six and the elimination of current transformer external wiring from the generator location to the generator switchgear location.
Generator Protection ANSI/IEEE Std 242-1986
i ii
1 51 Alternate Location
1 51V
1 32
1 40
1 2
3 87
3 4 5
1 51G
(A)
(A) Single Isolated Generator on Low Voltage System (B) Multiple Isolated Generator on Medium Voltage System
(B)
6 7
8
R
9 10 11 12 13 14
50/5A
87-1
50/5A
87-2
50/5A
87-3
Gen
15 16
Figure 1.2-6. Self-Balancing Generator Differential Relay Scheme
17 18 19 20 21
CA08104001E
1.2-6
TOC
Index
June 2006
Sheet 0046
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Reverse power protection (Device 32) is used to prevent the generator from being motored. Motoring could damage (with other hazards) the prime mover. A steam turbine could overheat and fail. A diesel or gas engine could either catch re or explode. A steam turbine can typically withstand approximately 3% reverse power where a diesel engine can withstand up to 25% reverse power. Loss of eld protection (Device 40) is needed when generators are operating in parallel with one another or the power grid. When a synchronous generator loses its eld, it will continue to generate power as an induction generator obtaining its excitation from the other machines on the system. During this condition, the rotor will quickly overheat due to the slip frequency currents induced in it. Loss of excitation in one machine could jeopardize the operation of the other machines beyond their capability and the entire system.
87 01 PC R1 R1 02 Gen OC R2 03 87G R3 R3 R2
52
To Main Bus
Figure 1.2-7. Generator Percentage Differential Relay (Phase Scheme) and Ground Differential Scheme Using a Directional Relay
CA08104001E
June 2006
Sheet 0047
TOC
Index
1.2-7
Master TOC
Typical protection for larger generators is shown in Figure 1.2-8. It adds phase unbalance and eld ground fault protection. Phase unbalance (Device 46) or negative sequence overcurrent protection prevents the generators from rotor overheating damage. Unbalanced loads, fault conditions or open phasing will produce a negative sequence current to ow. The unbalanced currents induce double system frequency currents in the rotor, which quickly causes rotor overheating. Serious damage will occur to the generator if the unbalance is allowed to persist.
3 1 87
i
3 87B 81U/O
ii 1
27/59
2
3 51V 1 40 1 32 1 46
3 4
Other protection functions such as under/over voltage (Device 27/59) could be applied to any size generator. The voltage regulator typically maintains the output voltage within its desired output range. This protection can provide backup protection in case the voltage regulator fails. Under/over frequency protection (Device 81U/81O) could be used for backup protection for the speed control. Synch check relays (Device 25) are typically applied as a breaker permissive close function where generators are paralleled. Many modern protective relays are microprocessor-based and provide a full complement of generator protection functions in a single package. The cost per protection function has been drastically reduced such that it is feasible to provide more complete protection even to smaller generators. IEEE ANSI 1547 provides recommended practices for utility inter-tie protection. If the system has closed transition or parallel capability, additional protection may be required by the utility. Typically, no additional protection is required if the generator is paralleled to the utility for a maximum of 100 msec or less. Systems that offer soft transfer, peak shaving or co-generation will require additional utility inter-tie protection. The protection could include directional overcurrent and power relays and even transfer trip schemes. Please consult your local utility for specic requirements.
87G
5 6 7
Gen E
8
51G
9 10 11
12 13 14 15 16 17 18 19 20 21
CA08104001E
1.2-8
TOC
Index
June 2006
Sheet 0048
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Typical rating denitions for diesel gensets are: standby, prime plus 10, continuous and load management (paralleled with or isolated from utility). Any diesel genset can have several electrical ratings depending on the number of hours of operation per year and the ratio of electrical load/genset rating when in operation. The same diesel genset can have a standby rating of 2000 kW at 0.8 power factor (pf) and a continuous rating of 1825 kW at 0.8 pf. The lower continuous rating is due to the additional hours of operation and higher load that the continuous genset must carry. These additional requirements put more stress on the engine and generator and therefore the rating is decreased to maintain longevity of the equipment. Different generator set manufacturers use basically the same diesel genset electrical rating denitions and these are based on international diesel fuel stop power standards from organizations like ISO, DIN and others. A standby diesel genset rating is typically dened as supplying varying electrical loads for the duration of a power outage with the load normally connected to utility, genset operating < 100 hours per year and no overload capability. A prime plus 10 rating is typically dened as supplying varying electrical loads for the duration of a power outage with the load normally connected to utility, genset operating 500 hours per year and overload capability of 10% above its rating for one hour out of twelve. A continuous rating is typically dened as supplying unvarying electrical loads (i.e., base loaded) for an unlimited time. The load management ratings apply to gensets in parallel operation with the utility or isolated/islanded from utility and these ratings vary in usability from < 200 hours per year to unlimited usage. Refer to generator set manufacturers for further denitions on load management ratings, load factor or average power consumption, peak demand and how these ratings are typically applied. Even though there is some standardization of these ratings across the manufacturers, there also exists some uniqueness with regards to how each manufacturer applies their generator sets.
Electrical rating denitions for natural gas powered gensets are typically dened as standby or continuous with denitions similar to those mentioned above for diesels. Natural gas gensets recover more slowly than diesel gensets when subjected to block loads. Diesel engines have a much more direct path from the engine governor and fuel delivery system to the combustion chamber and this results in a very responsive engine-generator. A natural gas engine is challenged with air-fuel ow dynamics and a much more indirect path from the engine governor (throttle actuator) and fuel delivery system (natural gas pressure regulator, fuel valve and actuator, carburetor mixer, aftercooler, intake manifold) to the combustion chamber and this results in a less responsive engine-generator. Diesel gensets recover about twice as fast as natural gas gensets. For the actual calculations involved for sizing a genset, there are readily accessible computer software programs which are available on the genset manufacturer's Internet sites or from the manufacturer's dealers or distributors. These programs are used to quickly and accurately size generator sets for their application. The programs take into consideration the many different parameters discussed above including the size and type of the electrical loads (resistive, inductive, SCR etc.), reduced voltage soft starting devices (RVSS), motor types, voltage, fuel type, site conditions, ambient conditions and other variables. The software will optimize the starting sequences of the motors for the least amount of voltage dip and determine the starting kVA needed from the genset. It also provides transient response data including voltage dip magnitude and recovery duration. If the transient response is unacceptable, then design changes can be considered including oversizing the generator to handle the additional kvar load, adding RVSS devices to reduce the inrush current, improving system power factor and other methods. The computer software programs are quite exible in that they allow changes to the many different variables and parameters to achieve an optimum design. The software allows, for example, minimizing voltage dips or using paralleled gensets vs. a single genset.
CA08104001E
June 2006
Sheet 0049
TOC
Index
1.2-9
Master TOC
s s s s
s s s s s
Foundation type (crushed rock, concrete, dirt, wood, separate concrete inertia pad etc.). Foundation to genset vibration dampening (spring type, cork and rubber etc.). Noise attenuation (radiator fan mechanical noise, exhaust noise, air intake noise). Combustion and cooling air requirements. Exhaust backpressure requirements. Emissions permitting. Delivery and rigging requirements. Genset derating due to high altitudes or excessive ambient temperatures.
s s
Hazardous waste considerations for fuel, antifreeze, engine oil. Meeting local building and electrical codes. Genset exposure (coastal conditions, dust, chemicals etc.). Properly sized starting systems (compressed air, batteries and charger). Allowing adequate space for installation of the genset and for maintenance (i.e., air lter removal, oil changing, general genset inspection etc). Flex connections on all systems that are attached to the genset and a rigid structure (fuel piping, foundation vibration isolators, exhaust, air intake, control wiring, power cables, radiator anges/duct work etc.). Diesel fuel day tank systems (pumps, return piping). Fuel storage tank (double walled, re codes) and other parameters.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Please see the generator set manufacturers Application and Installation Guidelines for proper application and operation of their equipment.
Running kVA = (445 A x 480 V x 1.732)/ 1000 = 370 kVA s Starting kVA = (516 A x 480 V x 1.732)/ 1000 = 428 kVA
Solution Generator must have a minimum starting capability of 428 kVA and minimum running capability of 370 kVA.
Also, please see Section Factors Governing Voltage Drop on Page 1.3-21 for further discussion on generator loading and reduced voltage starting techniques for motors.
19 20 21
CA08104001E
June 2006
Sheet 0050
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
June 2006
Sheet 0051
TOC
Index
1.3-1
Master TOC
Systems Analysis
A major consideration in the design of a distribution system is to ensure that it provides the required quality of service to the various loads. This includes serving each load under normal conditions and, under abnormal conditions, providing the desired protection to service and system apparatus so that interruptions of service are minimized consistent with good economic and mechanical design. Under normal conditions, the important technical factors include voltage prole, losses, load ow, effects of motor starting, service continuity and reliability. The prime considerations under faulted conditions are apparatus protection, fault isolation and service continuity. During the system preliminary planning stage, before selection of the distribution apparatus, several distribution systems should be analyzed and evaluated including both economic and technical factors. During this stage if system size or complexity warrant, it may be appropriate to provide a thorough review of each system under both normal and abnormal conditions.
The principal types of computer programs utilized to provide system studies include:
s
Short circuit identify 3-phase and line-to-ground fault currents and system impedances. Arc ash calculates arc ash energy levels which lead to the selection of personal protective equipment (PPE). Circuit breaker duty identify asymmetrical fault current based on X/R ratio. Protective device coordination determine characteristics and settings of medium voltage protective relays and fuses, and entire low voltage circuit breaker and fuse coordination. Load ow simulate normal load conditions of system voltages, power factor, line and transformer loadings. Motor starting identify system voltages, motor terminal voltage, motor accelerating torque, and motor accelerating time when starting large motors.
Short circuit calculations dene momentary and steady-state fault currents for LV and MV breaker and fuse duty and bus bracings at any selected location in the system and also determine the effect on the system after removal of utility power due to breaker operation or scheduled power outages. Computer software programs can identify the fault current at any bus, in every line or source connected to the faulted bus, or to it and every adjacent bus, or to it and every bus which is one and two buses away, or currents in every line or source in the system. The results of these calculations permit optimizing service to the loads while properly applying distribution apparatus within their intended limits. The following additional studies should be considered depending upon the type and complexity of the distribution system, the type of facility and the type of loads to be connected to the system:
s s s s s
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Harmonic Analysis Transient Stability Insulation Coordination Grounding Study Switching Transient
CA08104001E
1.3-2
TOC
Index
June 2006
Sheet 0052
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
The ac component is not constant if rotating machines are connected to the system because the impedance of this apparatus is not constant. The rapid variation of motor and generator impedance is due to these factors: Subtransient Reactance (x d ), deter" mines fault current during the rst cycle, and after about 6 cycles this value increases to the transient reactance. It is used for the calculation of the momentary interrupting and/or momentary withstand duties of equipment and/or system. Transient Reactance (x d), which deter' mines fault current after about 6 cycles and this value in 1/2 to 2 seconds increases to the value of the synchronous reactance. It is used in the setting of the phase OC relays of generators and medium voltage circuit breakers. Synchronous Reactance (xd ), which determines fault current after steady state condition is reached. It has no effect as far as short circuit calculations are concerned but is useful in the determination of relay settings. Transformer Impedance, in percent, is dened as that percent of rated primary voltage that must be applied to the transformer to produce rated current owing in the secondary, with secondary shorted through zero resistance. Therefore, assuming the primary voltage can be sustained (generally referred to as an innite or unlimited supply), the maximum current a transformer can deliver to a fault condition is the quantity of (100 divided by percent impedance) times the transformer
rated secondary current. Limiting the power source fault capacity will thereby reduce the maximum fault current from the transformer. The electric network which determines the short circuit current consists of an ac driving voltage equal to the prefault system voltage and an impedance corresponding to that observed when looking back into the system from the fault location. In medium and high voltage work, it is generally satisfactory to regard reactance as the entire impedance; resistance may be neglected. However, this is normally permissible only if the X/R ratio of the medium voltage system is equal to or more than 25. In low voltage (1000 volts and below) calculations, it is usually worthwhile to attempt greater accuracy by including resistance with reactance in dealing with impedance. It is for this reason, plus ease of manipulating the various impedances of cables and buses and transformers of the low voltage circuits, that computer studies are recommended before nal selection of apparatus and system arrangements. When evaluating the adequacy of short circuit ratings of medium voltage circuit breakers and fuses, both the rms symmetrical value and asymmetrical value of the short circuit current should be determined. For low voltage circuit breakers and fuses, the rms symmetrical value should be determined along with either: the X/R ratio of the fault at the device or the asymmetrical short circuit current.
Total Current - A Wholly Offset Asymmetrical Alternating Wave 3.0 2.5 2.0 Scale of Curent Values 1.5 1.0 0.5 1 0 0.5 -1.0 -1.5 -2.0 Direct Component - The Axis Time in Cycles of of Symmetrical Wave a 60 Hz Wave 2 3 4 rms Value of Total Current Alternating Component Symmetrical Wave rms Value of Alternating Component
June 2006
Sheet 0053
TOC
Index
1.3-3
Master TOC
i
2 60 --------------120 --------------- 1 + e X R = ---------
ii
1
2 ----------XR
1.
Ip = I 2
( 2 ) ( 2 60 ) -----------------------------120 -----------------------------XR
2 3 4
1 + 2e
2.5612
I = Symmetrical rms current Ip = Peak current e = 2.718 =2f f = Frequency in Hz t = Time in seconds rms mf = 1 + 2e
2 ---------15
5
1.5217
6 7 8 9
2.8 PEAK MAXIMUM ASYMMETRICAL 2.7 2.6 2.5 2.4 2.3 2.2 2.1 PEAK MULTIPLICATION FA L LT A AT FACTOR = 2.0 1.9 1.8 1.7 1.6 1.5
OR CT FA
Based Upon:
RMS SYMMETRICAL
RMS SYMMETRICAL
10 11 12 13 14 15 16 17 18 19 20
CA TI O N
FA CT
O R
SM RM
L TIP UL
TI ICA
ON
1.5
2.5
8 9 10
15
20
25
30
40
50
60 70 80 90 100
PE A
U LT IP LI
21
CA08104001E For more information visit: www.EatonElectrical.com
1.3-4
TOC
Index
June 2006
Sheet 0054
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Synchronous Motors Use 5.0 times motor full load current (impedance value of 20%). When the motor load is not known, the following assumptions generally are made:
Calculation Methods
The following pages describe various methods of calculating short circuit currents for both medium and low voltage systems. A summary of the types of methods and types of calculations is as follows:
s s s
208Y/120 V Systems
s
or
s
Assume motor feedback contribution of four times full load current of transformer. Assume 50% induction motor load. or
s s s s
Assume motor feedback contribution of two times full load current of transformer or source.
Medium Voltage Switchgear exact method . . . . . . . . . Page 1.3-5 Medium Voltage Switchgear quick check table . . . . . . Page 1.3-7 Medium Voltage Switchgear Example 1 Verify ratings of breakers . . . . . . . . . . . . . Page 1.3-8 Medium Voltage Switchgear Example 2 Verify ratings of breakers with rotating loads . . . . . . . . . . . . . . . . Page 1.3-9 Medium Voltage Switchgear Example 3 Verify ratings of breakers with generators . . . . . . . . . . . Page 1.3-10 Medium Voltage Fuses exact method . . . . . . . . . Page 1.3-11 Power Breakers Asymmetry derating factors . . . . . . . Page 1.3-11 Molded Case Breakers asymmetry derating factors . . . . . . . Page 1.3-12 Short Circuit Calculations Short cut method for a system . . . . . . . . . . . . . Page 1.3-13 Short Circuit Calculations Short cut method for end of cable . . . . . . . . . . Page 1.3-15 Short Circuit Calculations Short cut method for end of cable chart method . . . . Page 1.3-16 Short Circuit Currents Chart of transformers 300 to 3750 kVA . . . . . . . . . . . . . Page 1.5-9
CA08104001E
June 2006
Sheet 0055
TOC
Index
1.3-5
Master TOC
a voltage = maximum rated voltage divided by K (for example, 4.76/1.24 = 3.85). If this breaker is applied in a system rated at 2.4 kV the calculated fault current must be less than 36 kA.
greater than the available system fault current of 20,000 amperes, the breaker is acceptable (assumes the breakers momentary and fault close rating is also acceptable).
Note: If the system available fault current were 22,000 amperes symmetrical, this breaker could not be utilized even though the Maximum Symmetrical Interrupting Capability is greater than 22,000 since Test 1 calculation is not satised.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
For approximate calculations, Table 1.3-1 provides typical values of % reactance (X) and X/R values for various rotating equipment and transformers. For simplication purposes, the transformer impedance (Z) has been assumed to be primarily reactance (X). In addition, the resistance (R) for these simplied calculations has been ignored. For detailed calculations, the values from the IEEE Red Book Standard 141, for rotating machines, and ANSI C57 and/or C37 for transformers should be utilized.
Reactance X Used for Typical Values and Range Short Circuit Close and Latch on Component Base Duty (Momentary) % Reactance X/R Ratio X X X .75X 1.5X 1.5X X X X .75X 1.0X 1.0X 1.2X Neglect X X 9 (7 14) 15 (12 17) 20 (13 32) 16 (16 50) 20 (13 35) 17 (15 25) 17 (15 25) 80 (40 120) 80 (40 120) 30 (10 60) 30 (10 60) 30 (10 60) 30 (15 40) 15 (2 40)
Note: Interrupting capabilities of some of todays vacuum breakers may have K = 1, whereby the interrupting current is constant across its entire operating range.
Transformers
OA to 10 MVA, 69 kV OA to 10 MVA, above 69 kV FOA 12 to 30 MVA FOA 40 to 100 MVA X X X X X X X X 18 (7 24) 8.0 to 10.5 Depends on 20 (7 30) Primary Windings BIL 38 (32 44) Rating
Table 1.3-2. Typical System X/R Ratio Range (for Estimating Purposes)
Type of Circuit Remote generation through other types of circuits such as transformers rated 10 MVA or smaller for each 3-phase bank, transmission lines, distribution feeders, etc. Remote generation connected through transformer rated 10 MVA to 100 MVA for each 3-phase bank, where the transformers provide 90 percent or more of the total equivalent impedance to the fault point. Remote generation connected through transformers rated 100 MVA or larger for each 3-phase bank where the transformers provide 90 percent or more of the total equivalent impedance to the fault point. Synchronous machines connected through transformers rated 25 to 100 MVA for each 3-phase bank. Synchronous machines connected through transformers rated 100 MVA and larger. Synchronous machines connected directly to the bus or through reactors. X/R Range 15 or less 15 40
30 50
30 50 40 60 40 120
1.3-6
TOC
Index
June 2006
Sheet 0056
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10
impedances and their X/R ratios are given in Table 1.3-1. The ANSI Standard C37.010 allows the use of the X values only in determining the E/X value of a fault current. The R values are used to determine the X/R ratio, in order to apply the proper multiplying factor, to account for the total fault clearing time, asymmetry, and decrement of the fault current. The steps in the calculation of fault currents and breaker selection are described hereinafter: Step 1: Collect the X and R data of the circuit elements. Convert to a common kVA and voltage base. If the reactances and resistances are given either in ohms or per unit on a different voltage or kVA base, all should be changed to the same kVA and voltage base. This caution does not apply where the base voltages are the same as the transformation ratio. Step 2: Construct the sequence networks and connect properly for the type of fault under consideration. Use the X values required by ANSI Standard C37.010 for the interrupting duty value of the short circuit current.
Step 3: Reduce the reactance network to an equivalent reactance. Call this reactance XI. Step 4: Setup the same network for resistance values. Step 5: Reduce the resistance network to an equivalent resistance. Call this resistance RI. The above calculations of XI and RI may be calculated by several computer programs. Step 6: Calculate the E/XI value, where E is the prefault value of the voltage at the point of fault nominally assumed 1.0 pu. X Step 7: Determine X/R = ------I as RI previously calculated. Step 8: Go to the proper curve for the type of fault under consideration (3-phase, phase-to-phase, phase-toground), type of breaker at the location (2, 3, 5 or 8 cycles), and contact parting time to determine the multiplier to the calculated E/XI. See Figures 1.3-3, 1.3-4 and 1.3-5 for 5-cycle breaker multiplying factors. Use Figure 1.3-5 if the short circuit is fed predominantly from generators removed from the fault by two or more
130
11 12 13 14
Ratio X/R
12
10
90 80 Ratio X/R 70 60 50 40 30
5-CYCLE BREAKER
70 60 50 40
NT AC T P ART ING
17
30
CO
18 19 20 21
5-CYCLE BREAKER
20 10
20 10
5-CYCLE BREAKER
1.0
1.1
CO
1.2
NT AC
16
PA RT IN
1.3 1.4
15
TIME
Figure 1.3-3. 3-phase Fault Multiplying Factors Which Include Effects of ac and dc Decrement
Figure 1.3-4. Line-to-Ground Fault Multiplying Factors Which Include Effects of ac and dc Decrement
For more information visit: www.EatonElectrical.com
Figure 1.3-5. 3-phase and Line-to-Ground Fault Multiplying Factors Which Include Effects of dc Decrement Only
CA08104001E
GT IME
90
100
8 6
100
June 2006
Sheet 0057
TOC
Index
1.3-7
Master TOC
transformations or the per unit reactance external to the generation is 1.5 times or more than the subtransient reactance of the generation on a common base. Also use Figure 1.3-5 where the fault is supplied by a utility only. Step 9: Interrupting duty short circuit current = E/XI x MFx = E/X2. Step 10: Construct the sequence (positive, negative and zero) networks properly connected for the type of fault under consideration. Use the X values required by ANSI Standard C37.010 for the Close and Latch duty value of the short circuit current. Step 11: Reduce the network to an equivalent reactance. Call the reactance X. Calculate E/X x 1.6 if the breaker close and latch capability is given in rms amperes or E/X x 2.7 if the breaker close and latch capability is given in peak or crest amperes. Step 12: Select a breaker whose: a. Maximum voltage rating exceeds the operating voltage of the system: b.
V max E ------ I -------------- KI X2 Vo
Section 5 of ANSI C37 provides further guidance for medium voltage breaker application.
i ii 1 2 3
Reclosing Duty
ANSI Standard C37.010 indicates the reduction factors to use when circuit breakers are used as reclosers. CutlerHammer VCP-W breakers are listed at 100% rating factor for reclosing.
3,300 (1,006) (and Below) 1.00 5,000 (1,524) 0.99 10,000 (3,048) 0.96
4 5 6 7
12
13.8
8
50 VCP-W 250 10.1 kA 150 VCP-W 500 23 kA 150 VCP-W 500 22.5 kA 150 VCP-W 500 19.6 kA
9 10 11
See Table 6.0-1, Section 6. Where: I = Rated short circuit current Vmax = Rated maximum voltage of the breaker VD KI = Actual system voltage = Maximum symmetrical interrupting capacity
75 VCP-W 500 41.3 kA 150 VCP-W 750 35 kA 150 VCP-W 1000 46.3 kA 150 VCP-W 750 30.4 kA 150 VCP-W 1000 40.2 kA
12 13 14 15 16 17 18 19 20 21
c. E/X x 1.6 rms closing and latching capability of the breaker and/or E/X x 2.7 Crest closing and latching capability of the breaker. The ANSI standards do not require the inclusion of resistances in the calculation of the required interrupting and close and latch capabilities. Thus the calculated values are conservative. However, when the capabilities of existing switchgears are investigated, the resistances should be included. For single line-to-ground faults the symmetrical interrupting capability is 1.15 x the symmetrical interrupting capability at any operating voltage but not to exceed the maximum symmetrical capability of the breaker.
Transformer impedance 6.5% or more, all other transformer impedances are 5.5% or more.
CA08104001E
1.3-8
TOC
Index
June 2006
Sheet 0058
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
4.76 ---------- (29) = 33.2 kA I1 4.16 LG Symmetrical Interrupting Capability 36 kA 1.15 (33.2) = 38.2 kA I2
Note: Interrupting capabilities I1 and I2 at operating voltage must not exceed maximum symmetrical interrupting capability Kl.
Check capabilities I1, I2 and I3 on the following utility system where there is no motor contribution to short circuit.
24,200 Watts Load Losses
13.8 kV X R 375 MVA Available
On 13.8 kV System, 3.75 MVA Base 3.75 MVA Z = -------------------------------- = .01 pu or 1% 375 MVA
2 2 2 2 2X Z = X + R = R ------- + 1 2 R
= 15
50VPC-W250
Answer
Figure 1.3-6. Example 1 One-Line Diagram
The 50VCP-W250 breaker capabilities exceed the duty requirements and may be applied. 24.2 kW R = ------------------------------- = .0065 pu or .65% 3750 kVA With this application, short cuts could have been taken for a quicker check of the application. If we assume unlimited short circuit available at 13.8 kV and that Trans. Z = X I B .52 Then I 3-Phase = ----- = ------------- = 9.5 kA Sym. X .055 X/R ratio 15 or less multiplying factor is 1.0 for short circuit duty. The short circuit duty is then 9.5 kA Sym. (I1, I2) and momentary duty is 9.5 x 1.6 kA = 15.2 kA (I3).
For more information visit: www.EatonElectrical.com CA08104001E
(5.09) (.65) =
25.91 .42 =
25.48
X = 5.05% X .99% 5.05% 6.04% .0604 pu R X/R .066% 15 .65% 8 .716 % 9 .00716 pu
June 2006
Sheet 0059
TOC
Index
1.3-9
Master TOC
i ii 1 2 3
Z = 5.53%
6.9 kV 1
4 5 6 7
3000 hp Synchronous Motor X = .20 (.628) = .638 pu at 7.5 MVA base -----------------.197 2500 hp Ind. Motor (.628) X = .25 ------------------ = .908 pu at 7.5 MVA base (.173) E IB I 3-Ph = ---- = ----- where X on per unit base X X Table 1.3-6. Multiplying Factor for E/X Amperes (ANSI C37.010, 1979, Figures 1.1-8, 1.1-9 and 1.1-10)
System X/R Type VCP-W Vacuum Circuit Breaker Rated Interrupting Time, 5 Cycle Type of Fault Ratio 3-Phase Local 1 15 20 25 30 36 40 45 50 55 60 65 70 75 80 85 90 95 100 100 120 130 1.00 1.00 1.00 1.00 1.04 1.06 1.08 1.12 1.13 1.14 1.16 1.17 1.19 1.20 1.21 1.22 1.23 1.24 1.24 1.24 1.00 1.00 1.02 1.06 1.10 1.14 1.16 1.19 1.22 1.25 1.26 1.28 1.29 1.30 1.31 1.32 1.33 1.34 1.35 1.35 LG 3-Phase & LG Remote 1.00 1.00 1.05 1.10 1.13 1.17 1.22 1.25 1.27 1.30 1.32 1.33 1.35 1.36 1.37 1.38 1.39 1.40 1.41 1.42 1.43 1.43 Source of Short Circuit 3000 hp 1.0 PF Syn. 2500 hp Ind.
8 9 10 11 12 13 14
15 16 17 18 19 20 21
8.25 kV 33 kA 15 kV 18 kA
Answer
Either breaker could be properly applied, but price will make the type 150VCP-W500 the more economical selection.
CA08104001E
TOC
Index
June 2006
Sheet 0060
Master TOC
i ii 1 2 3 4 5 6 7 8
Answer
The 50VCP-W250 breaker could be applied.
G1
G2
G3
4.16 kV
9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
June 2006
Sheet 0061
TOC
Index
1.3-11
Master TOC
Step 4 Construct the sequence networks using resistances and connect properly for the type of fault under consideration and reduce to a single equivalent resistance. Step 5 Calculate the E/XI value, where E is the prefault value of the voltage at the point of fault normally assumed 1.0 in pu. For 3-phase faults E/XI is the fault current to be used in determining the required interrupting capability of the fuse.
Note: It is not necessary to calculate a single phase-to-phase fault current. This current is very nearly 3 /2 x 3-phase fault. The line-to-ground fault may exceed the 3-phase fault for fuses located in generating stations with solidly grounded neutral generators, or in delta-wye transformers with the wye solidly grounded, where the sum of the positive and negative sequence impedances on the high voltage side (delta) is smaller than the impedance of the transformer.
includes induction and synchronous motor loads. The assumption is made that in 208Y/120-volt systems the contribution from motors is 2 times the full load current of step-down transformer. This corresponds to an assumed 50% motor aggregate impedance on a kVA base equal to the transformer kVA rating or 50% motor load. For 480-, 480Y/277- and 600-volt systems the assumption is made that the contribution from the motors is four times the full load current of the step-down transformer which corresponds to an assumed 25% aggregate motor impedance on a kVA base equal to the transformer kVA rating or 100% motor load. In low voltage systems which contain generators the subtransient reactance should be used. If the X/R to the point of fault is greater than 6.6, a derating multiplying factor (MF) must be applied. The X/R ratio is calculated in the same manner as that for medium voltage circuit breakers. Calculated symmetrical amperes x MF breaker interrupting rating. The multiplying factor MF can be calculated by the formula: ( ) ( X/R ) 2 [ 1 + 2.718 ] MF = 2.29 If the X/R of system feeding the breaker is not known, use X/R = 15. For fused breakers by the formula: 1 + 2 ( 2.718 ) MF = 1.25
( 2 ) ( X/R )
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
For single line-to-ground fault; X I = X I (+) + X I () + X I (0) E I f = ------ 3 XI Step 6 Select a fuse whose published interrupting rating exceeds the calculated fault current. Figure 1.3-2 should be used where older fuses asymmetrically rated are involved. The voltage rating of power fuses used on 3-phase systems should equal or exceed the maximum line-to-line voltage rating of the system. Current limiting fuses for 3-phase systems should be so applied that the fuse voltage rating is equal to or less than 1.41 x nominal system voltage.
If the X/R of the system feeding the breaker is not known, use X/R = 20. Refer to Table 1.3-8 for the standard ranges of X/R and Power Factors used in testing and rating low voltage breakers. Refer to Table 1.3-9 for the circuit breaker interrupting rating multiplying factors to be used when the calculated X/R ratio or power factor at the point the breaker is to be applied in the power distribution system falls outside of the Table 1.3-8 X/R or power factors used in testing and rating the circuit breakers. MF is always greater than 1.0.
CA08104001E
TOC
Index
June 2006
Sheet 0062
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Molded Case Breakers and Insulated Case Circuit Breakers Fault Calculations
The method of fault calculation is the same as that for low voltage power circuit breakers. Again the calculated fault current x MF breaker interrupting capacity. Because molded case breakers are tested at lower X/R ratios the MFs are different than those for low voltage power circuit breakers.
X 2 R 2 1 + 2.718
MF = --------------------------------------------------X 1 R 1 1 + 2.718
For distribution systems where the calculated short circuit current X/R ratio differs from the standard values given in the above table, circuit breaker interrupting rating derating factors from Table 1.3-9 table should be applied.
Note: These are derating factors applied to the breaker and are the inverse of MF.
CA08104001E
June 2006
Sheet 0063
TOC
Index
1.3-13
Master TOC
i ii 1 2
(pu impedance on kVA base 1)
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
3.
(ohms impedance) (kVA base) (a) Per unit impedance = pu Z = percent = 2 impedance ( kV ) ( 1000 ) 100 (b) % impedance = % Z = (c) Ohms impedance = (ohms impedance) (kVA base) 2 ( kV ) ( 10 ) ( kV )2
4.
Change power-source impedance to per-unit or percent impedance on kVA base as selected for this study:
(a) if utility fault capacity given in kVA kVA base in study Per-unit impedance = pu Z = -----------------------------------------------------------------------------------------power-source kVA fault capacity (b) if utility fault capacity given in rms symmetrical short circuit amperes kVA base in study Per-unit impedance = pu Z = --------------------------------------------------------------------------------------------------------------(short-circuit current) ( 3 )(kV of source)
5.
motor kVA ( 3 ) (kV) (I) where I = motor nameplate full-load amperes if 1.0 power factor synchronous motor kVA = (0.8) (hp) if 0.8 power factor synchronous motor kVA = (1.0) (hp) if induction motor kVA = (1.0) (hp) 3-phase kVA or 1-phasekVA ( 3 ) ( kV )
6.
kV line-to-neutral
(c) rms Symmetrical current = ISC = (pu ISC) (IBase Amperes) 3-phase kVA base 1-phase kVA base (d) rms Symmetrical current = Amperes = ------------------------------------------------- or ------------------------------------------------( puZ ) ( kV ) ( puZ ) ( 3 ) ( kV ) (e) (g) (3-phase kVA base) (100) 1-phase kVA base (100) = --------------------------------------------------------------------- or ----------------------------------------------------------------(%Z) ( kV ) (%Z) ( 3 ) ( kV ) (kV) (1000) = ---------------------------------3 (ohms Z)
7.
( kV )2 ( 1000 ) (a) Symmetrical short circuit kVA = kVA base = (kVA base) (100) = ----------------------------------------------------------------------------------------------------( puZ ) %Z ohms Z (b) 3(line-to-neutral kV)2 ( 1000 ) = ---------------------------------------------------------------------------(ohms Z)
8.
(a) from 3-phase transformer approx. 86% of 3-phase current (b) three single-phase transformers (e.g., 75 kVA, Z = 2%) calculate same as one 3-phase unit (i.e., 3 x 75 kVA = 225 kVA, Z = 2%). (c) from single-phase transformer see Page 1.3-15. (a) synchronous motor 5 times motor full load current (impedance 20%) See IEEE Standard No. 141 (b) induction motor 4 times motor full-load current (impedance 25%) (c) motor loads not individually identied, use contribution from group of motors as follows: on 208Y/120 volt systems 2.0 times transformer full-load current on 240-480-600 volt 3-phase, 3-wire systems 4.0 times transformer full-load current on 480Y/277 volt 3-phase, 4-wire systems In commercial buildings, 2.0 times transformers full-load current (50% motor load) In industrial plants, 4.0 times transformer full-load current (100% motor load)
9.
CA08104001E
TOC
Index
June 2006
Sheet 0064
Master TOC
i ii 1
Example Number 1
How to Calculate Short Circuit Currents at Ends of Conductors
A. System Diagram B. Impedance Diagram (Using Short Cut Method for Combining Impedances and Sources).
A Utility Source 500 MVA V VA Utility Major Contribution B C
2
Transformer Cables Switchboard Fault 1,000 kVA V VA 5.75% 480 Volts Cable
3 4
Cables Fault
Switchboard Fault
5 6 7 8 9 10 11 12 13 14
2 4(a)
A B C 100 Feet (30 m) 3 350 kcmil Cable in Steel Conduit
.002 pu
1.00 pu
1.00 pu
1.00 pu
.0575 pu
.027 pu
.027 pu
Mixed Load Motors and Lighting Each Feeder 100 Feet (30 m) of 3 350 kcmil Cable in Steel Conduit Feeding Lighting and 250 kVA of Motors Cable Fault Combining Series Impedances: ZTO
L
C. Conductor impedance from Table 1.5-20, Page 1.5-14. Conductors: 3 350 kcmil copper, single conductors Circuit length: 100 feet (30 m), in steel (magnetic) conduit Impedance Z = 0.00619 ohms/100 feet (30 m). ZTOT = 0.00619 ohms (100 circuit feet) D. Fault current calculations (combining impedances arithmetically, using approximate Short Cut method see Note 4, Page 1.3-13)
Step 1 Equation (See)
1 ZTOTAL
1 + 1 + ... 1 Z1 Z2 Zn
.0595 pu
.342 pu
.0507 pu E .0777 pu
.027 pu
.027 pu
Calculation Select 1000 kVA as most convenient base, since all data except utility source is on secondary of 1000 kVA transformer. kVA base 1000 Utility per unit impedance = Z pu = ------------------------------------------ = -------------------- = 0.002 pu utility fault kVA 500.000 %Z Transformer per unit impedance = Z pu = --------- = 5.75 = 0.0575 pu ---------100 100 kVA base 1000 Motor contribution per unit impedance = Z pu = --------------------------------------- = ------------------- = 1.00 pu 4 x motor kVA 4 x 250 Cable impedance in ohms (see above) = 0.00619 ohms (ohms)(kVA base) Cable impedance per unit = Z pu = ------------------------------------------------- = (0.00619)(1000) = 0.027pu -----------------------------------------2 2 (0.480) (1000) (kV) (1000)
15 16 17 18
3(a)
6(d)
Total impedance to switchboard fault = 0.0507 pu (see diagram above) 3-phase kVA base Symmetrical short circuit current at switchboard fault = = = 23,720 amperes rms 1000 ( Z pu ) ( 3 ) ( kV ) ( 0.0507 ) ( 3 ) ( 0.480 )
19 20 21
7 6(d)
Total impedance to cable fault = 0.0777 pu (see diagram above) Symmetrical short circuit current at cable fault = 3-phasebase = = 15, 480 amperes rms kVA 1000 ( Z pu ) ( 3 ) ( kV ) ( 0.0777 ) ( 3 ) ( 0.480 )
June 2006
Sheet 0065
TOC
Index
1.3-15
Master TOC
Example Number 2
Fault Calculation Secondary Side of Single-Phase Transformer
A. System Diagram
R = 0.1498 Z 480-Volt 3-Phase Switchboard Bus at 50,000 Amp Symmetrical, X/R = 6.6 X = 0.9887 Z
i
Deriving Transformer R and X:
ii 1
X = 6.6 R Z=
2
X = 6.6 R
2
X +R =
44.56R = 6.6753R
100 Ft. Two #2/0 Copper Conductors, Magnetic Conduit R = 0.0104 Ohms X = 0.0051 Ohms
R=
75 kVA Single-Phase 480-120/240 Volts; Z = 2.8%, R = 1.64%, X = 2.27% V VA
2 3 4 5 6 7 8 9
= 0.00054 pu = 0.00356 pu = 0.00677 pu
6.6753
X = 6.6R
120 Volts F2 240 V F1
75
RSyst = 2 (0.1498 x Z) XSyst = 2 (0.9887 x Z) 0.0104 75 RCond = 2 2 0.48 1000 0.0051 75 XCond = 2 ( 0.48 ) 2 1000 1.64 RTfmr = 100 2.27 XTfmr = 100
10 11
ZCond =
2 ( kV ) 1000
12 13 14
( 2.27 )
100
2 2
= 0.0272 pu
2 2
Impedance to Fault F1 Full Winding Impedance to Fault F2 Half Winding Short circuit current F1 = 75 (0.03791 x 0.240 kV) = 8,243 Ampere Symmetrical Short circuit current F2 = 75 (0.04669 x 0.120 kV) = 13,386 Ampere Symmetrical
Z= Z=
= 0.03791 pu = 0.04669 pu
15 16 17 18 19 20 21
of the conductors can be calculated as follows. 277 volts/30,000 amperes = 0.00923 ohms (source impedance) Conductor ohms for 500 kcmil conductor from reference data in this section in magnetic conduit is 0.00551 ohms per 100 feet (30 m). For 100 feet (30 m) and 2 conductors per phase we have: 0.00551/2 = 0.00273 ohms (conductor impedance)
For more information visit: www.EatonElectrical.com
Add source and conductor impedance or 0.00923 + 0.00273 = 0.01196 total ohms
Next, 277 volts/0.01196 ohms = 23,160 amperes rms at load side of conductors X 30,000 amperes available 100 feet (30 m) 2 500 kcmil per phase X If = 23,160 amperes
TOC
Index
June 2006
Sheet 0066
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Step Five
Enter the chart along the bottom horizontal scale with the distance (in feet) from the transformer to the fault point. Draw a vertical line up the chart to the point where it intersects the selected curve. Then draw a horizontal line to the left from this point to the scale along the left side of the chart.
Motor Contribution
For system voltages of 120/208 volts, it is reasonable to assume that the connected load consists of 50% motor load, and that the motors will contribute four times their full load current into a fault. For system voltages of 240 and 480 volts, it is reasonable to assume that the connected load consists of 100% motor load, and that the motors will contribute four times their full load current into a fault. These motor contributions have been factored into each curve as if all motors were connected to the transformer terminals.
Step Six
The value obtained from the left-hand vertical scale is the fault current (in thousands of amperes) available at the fault point. For a more exact determination, see the formula method. It should be noted that even the most exact methods for calculating fault energy use some approximations and some assumptions. Therefore, it is appropriate to select a method which is sufciently accurate for the purpose, but not more burdensome than is justied. The charts which follow make use of simplications which are reasonable under most circumstances and will almost certainly yield answers which are on the safe side. This may, in some cases, lead to application of circuit breakers having interrupting ratings higher than necessary, but should eliminate the possibility of applying units which will not be safe for the possible fault duty.
Feeder Conductors
The conductor sizes most commonly used for feeders from molded case circuit breakers are shown. For conductor sizes not shown, the following table has been included for conversion to equivalent arrangements. In some cases it may be necessary to interpolate for unusual feeder ratings. Table 1.3-10 is based on using copper conductor. Table 1.3-10. Conductor Conversion (Based on Using Copper Conductor)
If Your Conductor is: 3 No. 4/0 Cables 4 No. 2/0 Cables 3 2000 kcmil Cables 5 400 kcmil Cables 6 300 kcmil Cables 800 Ampere Busway 1000 Ampere Busway 1600 Ampere Busway Use Equivalent Arrangement 2 500 kcmil 2 500 kcmil 4 750 kcmil 4 750 kcmil 4 750 kcmil 2 500 kcmil 2 500 kcmil 4 750 kcmil
UTILITY KVA V VA
12.5
7.5
5.0
2.5
100
200
500
1000 2000
5000
Step Two
Select the applicable chart from the following pages. The charts are grouped by secondary system voltage which is listed with each transformer. Within each group, the chart for the lowest kVA transformer is shown rst, followed in ascending order to the highest rated transformer.
Step Three
Select the family of curves that is closest to the available source kVA. The black line family of curves is for a source of 500,000 kVA. The lower value line (in red) family of curves is for a source of 50,000 kVA. You may interpolate between curves if necessary, but for values above 100,000 kVA it is appropriate to use the 500,000 kVA curves.
10
Step Four
Select the specic curve for the conductor size being used. If your conductor size is something other than the sizes shown on the chart, refer to the conductor conversion Table 1.3-10.
100
200
500
1000 2000
5000
CA08104001E
June 2006
Sheet 0067
TOC
Index
1.3-17
Master TOC
i ii 1 2 3
#4 AWG A AW
15 4 2 10
60
40
20
4
0 0 2 5 10 20 50 Distance in Feet from T 100 200 500 1000 2000 5000 0 0 2 5 10 20 50 Distance in Feet from T 100 200 500 1000 2000 5000
5 6
7 8 9 10 11
50,000
20 4 10 kcmil
40
20
100
200
500
1000 2000
5000
100
200
500
1000 2000
5000
12 13
60 B 50
kcmil kcmil
A 12
14 15
10 B 8 F 50,000
F 40 F
50,000
16
4 2
30
17 18
20
W WG
10
100
200
500
1000 2000
5000
19
0 2 5 10 20 50 Distance in Feet from T 100 200 500 1000 2000 5000
20 21
CA08104001E
TOC
Index
June 2006
Sheet 0068
Master TOC
i
A Fault Current in Thousands of Amperes (Sym.) A Fault Current in Thousands of Amperes (Sym.) 60
ii 1 2 3 4
30
50
kcmil F 50,000
40
#4 AW A AWG B
30
10
20
750 kcmil
10
5 6
Fault Current in Thousands of Amperes (Sym.) 30
100
200
500
1000 2000
5000
100
200
500
1000 2000
5000
7 8 9 10 11 12 13 14
A 60 4 kcmil
25
50
W WG F 50,000
20
B F
40 F 30
15
10
kcmil
20
#4 A 5
10
100
200
500
1000 2000
5000
100
200
500
1000 2000
5000
15 16 17 18 19 20 21
15 4 750 kcmil 2 10
100
200
500
1000 2000
5000
CA08104001E
June 2006
Sheet 0069
TOC
Index
1.3-19
Master TOC
Method 2:
Refer to Page 1.5-9 in the Reference section, and use appropriate row of data based on transformer kVA and primary short circuit current available. This will yield more accurate results and allow for including motor short circuit contribution.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
where %Z is the transformer impedance in percent, from Tables 1.5-6 through 1.5-11, Page 1.5-11. This is the maximum 3-phase symmetrical bolted-fault current, assuming sustained primary voltage during fault, i.e., an innite or unlimited primary power source (zero source impedance). Since the power source must always have some impedance this a conservative value; actual fault current will be somewhat less.
Note: This will not include motor short circuit contribution.
Method 2:
Using same values above. I R Losses %R = 10 kVA 7300 = 1.46 10 500 %X = 5.5 1.46 = 5.30%
2 2 2
See Tables 1.5-12 through 1.5-15 on Page 1.5-12 for loss data on transformers.
CA08104001E
TOC
Index
June 2006
Sheet 0070
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Computer Equipment: With the proliferation of data-processing and computer- or microprocessor-controlled manufacturing, the sensitivity of computers to voltage has become an important consideration. Severe dips of short duration can cause a computer to crash shut down completely, and other voltage transients caused by starting and stopping motors can cause data-processing errors. While voltage drops must be held to a minimum, in many cases computers will require special power-conditioning equipment to operate properly. Industrial Plants: Where large motors exist, and unit substation transformers are relatively limited in size, voltage dips of as much as 20% may be permissible in some cases, if they do not occur too frequently. Lighting is often supplied from separate transformers, and is minimally affected by voltage dips in the power systems. However, it is usually best to limit dips to between 5 and 10% at most. One critical consideration is that a large voltage dip can cause a dropout (opening) of magnetic motor contactors and control relays. The actual dropout voltage varies considerably among starters of different manufacturers. The only standard that exists is that of NEMA, which states that a starter must not drop out at 85% of its nominal coil voltage, allowing only a 15% dip. While most starters will tolerate considerably more voltage dip before dropping out, limiting dip to 15% is the only way to ensure continuity of operation in all cases. X-Ray Equipment: Medical x-ray and similar diagnostic equipment, such as CAT-scanners, are extremely sensitive to low voltage. They present a small, steady load to the system until the instant the x-ray tube is red. This presents a brief but extremely high instantaneous momentary load. In some modern x-ray equipment, the ring is repeated rapidly to create multiple images. The voltage regulation must be maintained within the manufacturers limits, usually 2 to 3%, under these momentary loads, to ensure proper x-ray exposure.
Motor Starting
Motor inrush on starting must be limited to minimize voltage dips. Table 1.3-11 on the next page will help select the proper type of motor starter for various motors, and to select generators of adequate size to limit voltage dip. See Section 30 for additional data on reduced voltage motor starting.
Utility Systems
Where the power is supplied by a utility network, the motor inrush can be assumed to be small compared to the system capacity, and voltage at the source can be assumed to be constant during motor starting. Voltage dip resulting from motor starting can be calculated on the basis of the voltage drop in the conductors between the power source and the motor resulting from the inrush current. Where the utility system is limited, the utility will often specify the maximum permissible inrush current or the maximum hp motor they will permit to be started across-the-line.
Transformer Considerations
If the power source is a transformer, and the inrush kVA or current of the motor being started is small compared to the full-rated kVA or current of the transformer, the transformer voltage dip will be small and may be ignored. As the motor inrush becomes a signicant percentage of the transformer full-load rating, an estimate of the transformer voltage drop must be added to the conductor voltage drop to obtain the total voltage drop to the motor. Accurate voltage drop calculation would be complex and depend upon transformer and conductor resistance, reactance, and impedance, as well as motor inrush current and power factor. However, an approximation can be made on the basis of the low power-factor motor inrush current (30 40%) and impedance of the transformer. For example, if a 480 V transformer has an impedance of 5%, and the motor inrush current is 25% of the transformer full-load current (FLC), then the worst case voltage drop will be 0.25 x 5%, or 1.25%. The allowable motor inrush current is determined by the total permissible voltage drop in transformer and conductors.
CA08104001E
June 2006
Sheet 0071
TOC
Index
1.3-21
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Design B
Normal
Low
Design C
High
Low
Wound Rotor
High
Low
Secondary Controller 100% current for 100% Torque Across-the-Line Across-the-Line Autotransformer 300 450 550 288 350
40% Starting, 40% Pull-In 60% Starting, 110% Pull-In 38% Starting, 110% Pull-In
Consult NEMA MG-1 sections 1 and 12 for the exact denition of the design letter. In each case, a solid-state reduced voltage starter can be adjusted and controlled to provide the required inrush current and torque characteristics. Where accuracy is important, request the code letter of the the motor and starting and breakdown torques from the motor vendor. Using 80% taps.
From the nameplate data on the motor the full-load amperes of a 7-1/2 hp. 220-volt, 1750 rpm, 3-phase, squirrelcage motor is 19.0 amperes. Therefore: Starting current (%F.L.) = 10 100 1000 = 3.45 or 345%. 19.0 220 3 0.40 From Table 1.3-11, a NEMA design C or NEMA design D motor with an autotransformer starter gives approximately this starting ratio. It could also be obtained from a properly set solid-state adjustable reduced voltage starter. The choice will depend upon the torque requirements of the load since the use of an autotransformer starter reduces the starting torque in direct proportion to the reduction in starting current. In other words, a NEMA design C motor with an autotransformer would have a starting torque of approximately full-load (see Table 1.3-11) whereas the NEMA design D motor under the same conditions would have a starting torque of approximately 1-1/2 times full-load.
Note: If a resistance starter were used for the same motor terminal voltage, the starting torque would be the same as that obtained with autotransformer type, but the starting current would be higher, as shown.
Example:
Assuming a project having a 1000 kVA generator, where the voltage variation must not exceed 10%. Can a 75 hp, 1750 rpm, 220-volt, 3-phase, squirrel-cage motor be started without objectionable lamp icker (or 10% voltage drop)? From tables in the circuit protective devices reference section the full-load amperes of this size and type of motor is 158.0 amperes. To convert to same basis as column 7, 158 amperes must be divided by the generator capacity and % voltage drop, or: 158 = 0.0158 amperes per kVA per 1% voltage drop 1000 10 Checking against the table, 0.0158 falls within the .0170 .0146 range. This indicates that a general-purpose motor with autotransformer starting can be used.
Note: Designers may obtain calculated information from engine generator manufacturers.
Short-Cut Method
Column 7 in Table 1.3-11 has been worked out to simplify checking. The gures were obtained by using the formula above and assuming 1 kVA generator capacity and 1% voltage drop.
For more information visit: www.EatonElectrical.com
The calculation results in conservative results. The engineer should provide to the engine-generator vendor the starting kVA of all motors connected to the generator and their starting sequence. The engineer should also specify the maximum allowable drop. The engineer should request that the engine-generator vendor consider the proper generator size when closed-transition autotransformer reduced voltage starters, and soft-start solid-state starter are used; so the most economical method of installation is obtained.
CA08104001E
TOC
Index
June 2006
Sheet 0072
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
If the receiving end voltage, load current and power factor (PF) are known. E VD = ( E R cos + I R ) + ( E R sin + I X ) E R ER is the receiving end voltage. Exact Method 2 If receiving or sending mVA and its power factor are known at a known sending or receiving voltage.
2 2 ( ZMVA R ) E S = E R + --------------------------------- + 2ZMVA R cos ( R ) 2 ER 2 2 2 2
Exact Methods
Voltage Drop Exact Method 1 If sending end voltage and load PF are known. E VD = E S + IR cos + IX sin E S ( IX cos IR sin ) where: EVD = Voltage drop, line-to-neutral, volts ES I R X = Source voltage, line-to-neutral, volts = Line (Load) current, amperes = Circuit (branch, feeder) resistance, ohms = Circuit (branch, feeder) reactance, ohms
2
or
2 2 2 ( ZMVA R ) E R = E S + --------------------------------- 2ZMVA S cos ( S ) 2 ES
cos = Power factor of load, decimal sin = Reactive factor of load, decimal
MVAR = Receiving 3-phase mVA MVAS = Sending 3-phase mVA Z R S = Impedance between and receiving ends = The angle of impedance Z = Receiving end PF = Sending end PF, positive when lagging
CA08104001E
June 2006
Sheet 0073
TOC
Index
1.3-23
Master TOC
Voltage Drop
Voltage Drop Tables
Note: Busway voltage drop tables are shown in Section 23 of this catalog.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Tables for calculating voltage drop for copper and aluminum conductors, in either magnetic (steel) or nonmagnetic (aluminum or non-metallic) conduit, appear on Page 1.3-24. These tables give voltage drop per ampere per 100 feet (30 m) of circuit length. The circuit length is from the beginning point to the end point of the circuit regardless of the number of conductors.
Calculations
To calculate voltage drop:
1. Multiply current in amperes by the length of the circuit in feet to get ampere-feet. Circuit length is the distance from the point of origin to the load end of the circuit. 2. Divide by 100. 3. Multiply by proper voltage drop value in tables. Result is voltage drop.
Example:
A 3-phase, 4-wire lighting feeder on a 208-volt circuit is 250 feet (76.2 m) long. The load is 175 amperes at 90% PF. It is desired to use aluminum conductors in aluminum conduit. What size conductor is required to limit the voltage drop to 2% phase-to-phase? 2 1. VD = 208 = 4.16 volts 100 2. 3. = 0.0000951 4.16 175 250 0.0000951 100 = 0.00951
Example:
A 460-volt, 100-hp motor, running at 80% PF, draws 124 amperes full-load current. It is fed by three 2/0 copper conductors in steel conduit. The feeder length is 150 feet (46 m). What is the voltage drop in the feeder? What is the percentage voltage drop? 1. 124 amperes x 150 feet (46 m) = 18,600 ampere-feet 2. Divided by 100 = 186 3. Table: 2/0 copper, magnetic conduit, 80% PF = 0.0187 186 x 0.0187 = 3.48 volts drop 3.48 x 100 = 0.76% drop 460 4. Conclusion: .76% voltage drop is very acceptable (See NEC 2005 Article 215, which suggests that a voltage drop of 3% or less on a feeder is acceptable.)
4. In table, under Aluminum Conductors, nonmagnetic conduit, 90% PF, the nearest lower value is 0.0091. Conductor required is 500 kcmil. (Size 4/0 THW would have adequate ampacity, but the voltage drop would be excessive).
3. Voltage drops are for a conductor temperature of 75C. They may be used for conductor temperatures between 60C and 90C with reasonable accuracy (within 5%). However, correction factors in the table below can be applied if desired. The values in the table are in percent of total voltage drop. For conductor temperature of 60C SUBTRACT the percentage from Table 1.3-12. For conductor temperature of 90C ADD the percentage from Table 1.3-12.
CA08104001E
TOC
Index
June 2006
Sheet 0074
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Table 1.3-13. Voltage Drop Volts per Ampere per 100 Feet (30 m); 3-Phase, Phase-to-Phase
Conductor Size AWG or kcmil Magnetic Conduit (Steel) Load Power Factor, % 60 .3390 .2170 .1390 .0905 .0595 .0399 .0275 .0233 .0198 .0171 .0148 .0130 .0122 .0111 .0104 .0100 .0088 .0084 .0080 .3296 .2133 .1305 .0898 .0595 .0403 .0332 .0286 .0234 .0209 .0172 .0158 .0137 .0130 .0112 .0101 .0095 .0085 70 .3910 .2490 .1590 .1030 .0670 .0443 .0300 .0251 .0211 .0180 .0154 .0134 .0124 .0112 .0104 .0091 .0086 .0081 .0077 .3811 .2429 .1552 .1018 .0660 .0443 .0357 .0305 .0246 .0220 .0174 .0163 .0139 .0133 .0111 .0106 .0094 .0082 80 .4430 .2810 .1790 .1150 .0742 .0485 .0323 .0267 .0222 .0187 .0158 .0136 .0124 .0111 .0102 .0087 .0082 .0077 .0072 .4349 .2741 .1758 .1142 .0747 .0483 .0396 .0334 .0275 .0231 .0179 .0162 .0143 .0128 .0114 .0097 .0090 .0078 90 .4940 .3130 .1980 .1260 .0809 .0522 .0342 .0279 .0229 .0190 .0158 .0133 .0120 .0106 .0096 .0080 .0074 .0069 .0063 .4848 .3180 .1951 .1254 .0809 .0523 .0423 .0350 .0284 .0241 .0177 .0159 .0144 .0131 .0099 .0090 .0084 .0071 100 .5410 .3410 .2150 .1350 .0850 .0534 .0336 .0267 .0213 .0170 .0136 .0109 .0094 .0080 .0069 .0053 .0046 .0040 .0035 .5330 .3363 .2106 .1349 .0862 .0535 .0428 .0341 .0274 .0217 .0170 .0145 .0122 .0100 .0076 .0063 .0056 .0043 Nonmagnetic Conduit (Aluminum or Nonmetallic) Load Power Factor, % 60 .3370 .2150 .1370 .0888 .0579 .0384 .0260 .0218 .0183 .0156 .0134 .0116 .0107 .0097 .0090 .0078 .0074 .0069 .0064 .3312 .2090 .1286 .0887 .0583 .0389 .0318 .0263 .0227 .0160 .0152 .0138 .0126 .0122 .0093 .0084 .0081 .0069 70 .3900 .2480 .1580 .1010 .0656 .0430 .0287 .0238 .0198 .0167 .0141 .0121 .0111 .0099 .0091 .0077 .0072 .0067 .0062 .3802 .2410 .1534 .1011 .0654 .0435 .0349 .0287 .0244 .0171 .0159 .0144 .0128 .0123 .0094 .0085 .0080 .0068 80 .4410 .2800 .1780 .1140 .0730 .0473 .0312 .0256 .0211 .0176 .0147 .0124 .0112 .0099 .0091 .0075 .0070 .0064 .0058 .4328 .2740 .1745 .1127 .0719 .0473 .0391 .0322 .0264 .0218 .0171 .0147 .0133 .0119 .0094 .0085 .0078 .0065 90 .4930 .3120 .1970 .1250 .0800 .0513 .0333 .0270 .0220 .0181 .0149 .0124 .0110 .0096 .0087 .0070 .0064 .0058 .0052 .4848 .3052 .1933 .1249 .0800 .0514 .0411 .0337 .0274 .0233 .0179 .0155 .0132 .0120 .0091 .0081 .0072 .0058 100 .5410 .3410 .2150 .1350 .0849 .0533 .0335 .0266 .0211 .0169 .0134 .0107 .0091 .0077 .0066 .0049 .0042 .0035 .0029 .5331 .3363 .2115 .1361 .0849 .0544 .0428 .0339 .0273 .0222 .0172 .0138 .0125 .0101 .0072 .0060 .0051 .0038
Copper Conductors
14 12 10 8 6 4 2 1 1/0 2/0 3/0 4/0 250 300 350 500 600 750 1000
Aluminum Conductors
12 10 8 6 4 2 1 1/0 2/0 3/0 4/0 250 300 350 500 600 750 1000
CA08104001E
June 2006
Sheet 0075
TOC
Index
1.4-1
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Capacitor selection. Where to install capacitors in a plant distribution system. Locating capacitors on reduced voltage and multi-speed starters. Harmonic considerations. Eliminating harmonic problems. National Electrical Code requirements.
CA08104001E
1.4-2
TOC
Index
June 2006
Sheet 0076
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
% AR percent reduction in line current due to the capacitor. A capacitor located on the motor side of the overload relay reduces line current through the relay. Therefore, a different overload relay and/or setting may be necessary. The reduction in line current may be determined by measuring line current with and without the capacitor or by calculation as follows: (Original PF) % AR = 100 100 (Improved PF) If a capacitor is used with a lower kvar rating than listed in tables, the % AR can be calculated as follows: Actual kvar % AR = Listed % AR kvar in Table The tables can also be used for other motor ratings as follows: A. For standard 60 Hz motors operating at 50 Hz: kvar = 1.7 1.4 of kvar listed % AR = 1.8 1.35 of % AR listed B. For standard 50 Hz motors operating at 50 Hz: kvar = 1.4 1.1 of kvar listed % AR = 1.4 1.05 of % AR listed C. For standard 60 Hz wound-rotor motors: kvar = 1.1 of kvar listed % AR= 1.05 of % AR listed
Note: For A, B, C, the larger multipliers apply for motors of higher speeds; i.e., 3600 rpm = 1.7 mult., 1800 rpm = 1.65 mult., etc.
To derate a capacitor used on a system voltage lower than the capacitor voltage rating, such as a 240-volt capacitor used on a 208-volt system, use the following formula:
Actual kvar =
( Applied Voltage ) Nameplate kvar --------------------------------------------------------------------2 ( Nameplate Voltage )
2
For the kVAC required to correct the power factor from a given value of COS 1 to COS 2, the formula is: kVAC = KW (tan phase1 tan phase2) Capacitors cause a voltage rise. At light load periods the capacitive voltage rise can raise the voltage at the location of the capacitors to an unacceptable level. This voltage rise can be calculated approximately by the formula MVA r % VR = MVA SC MVAR is the capacitor rating and MVASC is the system short circuit capacity. With the introduction of variable speed drives and other harmonic current generating loads, the capacitor impedance value determined must not be resonant with the inductive reactances of the system.
Denitions
kvar rating of the capacitor in reactive kilovolt-amperes. This value is approximately equal to the motor no-load magnetizing kilovars.
CA08104001E
June 2006
Sheet 0077
TOC
Index
1.4-3
Master TOC
i ii 1 2 3 4 5 6 7
4.16 kV
250 MVA
8 9 10 11 12 13 14 15 16 17
B A C D D
300
200
200
100 90 80 70 60 50 40 30 20
250 Amperes 1000 kVA 5.75% ANSI 3-Phase Thru Fault Protection Curve (More Than 10 in Lifetime) 4,160 V 480/277 V 19,600 Amperes
100 90 80 70 60 50 40 30
20
TIME IN SECONDS
10 9 8 7 6 5 4 3
B M
10 9 8 7 6 5 4 3
TIME IN SECONDS
1 .9 .8 .7 .6 .5 .4 .3
1 .9 .8 .7 .6 .5
.4 .3
.2
.2
18 19 20 21
.02
.5 .6 .7 .8 .9 1
6 7 8 9 10
20
30
40 50 60
Figure 1.4-1. Time-Current Characteristic Curves for Typical Power Distribution System Protective Devices Coordination Analysis
For more information visit: www.EatonElectrical.com
2000
3000
4000
5000
70 80 90 100
200
300
400
500
.01
.01
1.4-4
TOC
Index
June 2006
Sheet 0078
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
In a fully rated system, all circuit breakers must have an interrupting capacity adequate for the maximum available fault current at their point of application. All breakers are equipped with long-time-delay (and possibly short delay) and instantaneous overcurrent trip devices. A main breaker may have short time-delay tripping to allow a feeder breaker to isolate the fault while power is maintained to all the remaining feeders. A selective or fully coordinated system permits maximum service continuity. The tripping characteristics of each overcurrent device in the system must be selected and set so that the breaker nearest the fault opens to isolate the faulted circuit, while all other breakers remain closed, continuing power to the entire unfaulted part of the system. The 2005 National Electrical Code (NEC) has added specic requirements for designing certain circuits with selective coordination. Article 100 has added, under Coordination (Selective), the following denition: Localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished by the choice of overcurrent protective devices and their ratings or settings.
NEC 2005 NFPA 70: National Electrical Code International Electrical Code Series.
for L-L and L-G faults. For line-to-line fault the secondary (low voltage) side fault current is 0.866 x I 3-phase fault current.
However the primary (high voltage) side fault is the same as if the secondary fault was a 3-phase fault. Therefore in coordination studies, the knee of the short-time pickup setting on the secondary breaker should be multiplied by 1 or 1.1547 0.866 before it is compared to the minimum melting time of the upstream primary fuse curve. In the example shown, the knee is at 4000 amperes 30 sec., and the 30-sec. trip time should be compared to the MMT (minimum melt time) of the fuse curve at 4000 x 1.1547 = 4619 amperes. In this case there is adequate clearance to the fuse curve.
Article 620.62 (Elevators, Dumbwaiters, Escalators, Moving Walks, Wheelchair Lifts, and Stairway Chair Lifts) requires Where more than one driving machine disconnecting means is supplied by a single feeder, the overcurrent protective devices in each disconnecting means shall be selectively coordinated with any other supply side overcurrent protective device. A similar requirement under Article 700.27 is as follows; Emergency system(s) overcurrent devices shall be selectively coordinated with all supply side overcurrent protective devices. Also Article 701.18, added Legally required standby system(s) overcurrent devices shall be selectively coordinated with all supply side overcurrent devices. In addition, for health care facilities, Article 517.26, Application of Other Articles requires that The essential electrical system shall meet the requirements of Article 700, except as amended by Article 517.
In the example shown, the ANSI 3-phase through fault protection curve must be multiplied by 0.577 and replotted in order to determine the protection given by the primary for a single line to ground fault in the secondary.
CA08104001E
June 2006
Sheet 0079
TOC
Index
1.4-5
Master TOC
All breakers must have an interrupting capacity not less than the maximum available short circuit current at their point of application. A selective system is a fully rated system with tripping devices chosen and adjusted to provide the desired selectivity. The tripping characteristics of each overcurrent device should not overlap, but should maintain a minimum time interval for devices in series (to allow for normal operating tolerances) at all current values. Generally, a maximum of four low voltage circuit breakers can be operated selectively in series, with the feeder or branch breaker downstream furthest from the source. Specify true rms sensing devices in order to avoid false trips due to rapid currents or spikes. Specify tripping elements with I2t or I4t feature for improved coordination with other devices having I2t or I4t (such as OPTIM trip units) characteristics, and fuses. In general for systems such as shown in the example: 1. The settings or ratings of the primary side fuse and main breaker must not exceed the settings allowed by NEC Article 450. 2. At 12 x IFL the minimum melting time characteristic of the fuse should be higher than 0.1 second. 3. 4. The primary fuse should be to the left of the transformer damage curve as much as possible. The correction factor for a single lineto-ground factor must be applied to the damage curve. 5. The setting of the short-time delay element must be checked against the fuse MMT after it is corrected for line-to-line faults. 6. The maximum fault current must be indicated at the load side of each protective device. 7. The setting of a feeder protective device must comply with Article 240 and Article 430 of the NEC. It also must allow the starting and acceleration of the largest motor on the feeder while carrying all the other loads on the feeder.
E. Tap Conductors. Tap conductors shall be permitted to be protected against overcurrent in accordance with the following: 1. 210-19(A)(3) and (A)(4) Household Ranges and Cooking Appliances and Other Loads. 2. 240.5(B)(2) Fixture Wire. 3. 240.21 Location in Circuit. 4. 368.17(B) Reduction in Ampacity Size of Busway. 5. 368.17(C) Feeder or Branch Circuits (busway taps). 6. 430.53(D) Single Motor Taps.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
B. Devices Rated 800 Amperes or Less. The next higher standard overcurrent device rating (above the ampacity of the conductors being protected) shall be permitted to be used, provided all of the following conditions are met. 1. The conductors being protected are not part of a multi-outlet branch circuit supplying receptacles for cord- and plug-connected portable loads. 2. The ampacity of the conductors does not correspond with the standard ampere rating of a fuse or a circuit breaker without overload trip adjustments above its rating (but that shall be permitted to have other trip or rating adjustments). 3. The next higher standard rating selected does not exceed 800 amperes. C. Devices Rated Over 800 Amperes. Where the overcurrent device is rated over 800 amperes, the ampacity of the conductors it protects shall be equal to or greater than the rating of the overcurrent device as dened in Section 240.6. D. Small Conductors. Unless specically permitted in 240.4(E) or 240.4(G), the overcurrent protection shall not exceed 15 amperes for 14 AWG, 20 amperes for 12 AWG, and 30 amperes for 10 AWG copper; or 15 amperes for 12 AWG and 25 amperes for 10 AWG aluminum and copper-clad aluminum after any correction factors for ambient temperature and number of conductors have been applied.
CA08104001E
1.4-6
TOC
Index
June 2006
Sheet 0080
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Any of these current-limiting devices fuses, fused breakers, or currentlimiting breakers cannot only clear these large faults safely, but also will limit the Ip and I2t let-through signicantly to prevent damage to apparatus downstream, extending their zone of protection. Without the current limitation of the upstream device, the fault current could exceed the withstand capability of the downstream equipment. Underwriters Laboratories tests and lists these series combinations. Application information is available for combinations which have been tested and UL -listed for safe operation downstream from MDSL, TRI-PAC, and Current Limit-R, or Series C breakers of various ratings, under high available fault currents. Protective devices in electrical distribution systems may be properly coordinated when the systems are designed and built, but that is no guarantee that they will remain coordinated. System changes and additions, plus power source changes, frequently modify the protection requirements, sometimes causing loss of coordination and even increasing fault currents beyond the ratings of some devices. Consequently, periodic study of protective-device settings and ratings is as important for safety and preventing power outages as is periodic maintenance of the distribution system.
It is recommended that in solidly grounded 480/277-volt systems where main breakers are specied to be equipped with ground fault trip elements that the feeder breakers be specied to be equipped with ground fault trip elements as well.
CA08104001E
June 2006
Sheet 0081
TOC
Index
1.4-7
Master TOC
Grounding
Grounding encompasses several different but interrelated aspects of electrical distribution system design and construction, all of which are essential to the safety and proper operation of the system and equipment supplied by it. Among these are equipment grounding, system grounding, static and lightning protection, and connection to earth as a reference (zero) potential.
i ii 1 2 3 4 5 6 7 8 9 10 11 12
1. Equipment Grounding
Equipment grounding is essential to safety of personnel. Its function is to ensure that all exposed noncurrentcarrying metallic parts of all structures and equipment in or near the electrical distribution system are at the same potential, and that this is the zero reference potential of the earth. Equipment grounding is required by both the National Electrical Code (Article 250) and the National Electrical Safety Code regardless of how the power system is grounded. Equipment grounding also provides a return path for ground fault currents, permitting protective devices to operate. Accidental contact of an energized conductor of the system with an improperly grounded noncurrent-carry metallic part of the system (such as a motor frame or panelboard enclosure) would raise the potential of the metal object above ground potential. Any person coming in contact
2. System Grounding
System grounding connects the electrical supply, from the utility, from transformer secondary windings, or from a generator, to ground. A system can be solidly grounded (no intentional impedance to ground), impedance grounded (through a resistance or reactance), or ungrounded (with no intentional connection to ground.
13 14 15 16 17 18 19 20 21
Maximum value rarely Cannot satisfactorily be higher than 3-phase short reduced below one-half circuit current or one-third of values for solid grounding
(3) Stability
Usually unimportant
Lower than with other methods but can be made satisfactory by use of high-speed breakers
(4) Relaying
Difcult
Satisfactory
Satisfactory
Satisfactory
Likely
Unlikely
Possible if reactance is excessive Effect of faults localized to system or part of system where they occur unless reactance is quite high Unlikely unless reactance is quite high and insulation weak
Unlikely Effect of faults transmitted as excess voltage on sound phases to all parts of conductively connected network Unlikely unless resistance is quite high and insulation weak
Effect of fault transmitted Effect of faults localized as excess voltage on to system or part of sound phases to all system where they occur parts of conductively connected network Likely Likely
CA08104001E
1.4-8
TOC
Index
June 2006
Sheet 0082
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12
D Resistance Grounded Arresters for ungrounded, neutral service usually must be applied at sacrice in cost and efciency Will be reduced from solidly grounded values
E Resonant Grounded Ungrounded neutral service arresters must be applied at sacrice in cost and efciency Will be low in magnitude except in cases of double faults or series resonance at harmonic frequencies, but duration may be great May be high during faults
Ungrounded neutral Highest efciency and service arresters must be lowest cost applied at sacrice in cost and efciency Will usually be low except in cases of double faults or electrostatic induction with neutral displaced but duration may be great Will be greatest in magnitude due to higher fault currents but can be quickly cleared particularly with high speed breakers
May be quite high during Minimum faults or when neutral is displayed Will inherently clear Must be isolated for themselves if total length each fault of interconnected line is low and require isolation from system in increasing percentages as length becomes greater
Greater than for solidly grounded, when faults occur Must be isolated for each fault
Greater than for solidly grounded, when faults occur Must be isolated for each fault
Need not be isolated but will inherently clear itself in about 60 to 80 percent of faults
Cannot be interconnected Satisfactory indenitely Satisfactory indenitely unless interconnecting with reactance-grounded with solidly-grounded system is ungrounded systems systems or isolating transformers are used
Cannot be interconnected unless interconnected system is resonant grounded or isolating transformers are used. Requires coordination between interconnected systems in neutralizer settings Interrupting capacity determined by 3-phase fault conditions
Same interrupting capacity as required for 3-phase short circuit will practically always be satisfactory Simple
Ordinarily simple but possibility of double faults introduces complication in times of trouble
Simple
Simple
Taps on neutralizers must be changed when major system switching is performed and difculty may arise in interconnected systems. Difcult to tell where faults are located Highest unless the arc suppressing characteristic is relied on to eliminate transmission circuits when it may be lowest for the particular types of service
13 14 15 16 17 18 19 20 21
High, unless conditions Lowest are such that arc tends to extinguish itself, when transmission circuits may be eliminated, reducing total cost
Intermediate
Intermediate
Because the method of grounding affects the voltage rise of the unfaulted phases above ground, ANSI C62.92 classies systems from the point of view of grounding in terms of a coefcient of grounding
Highest Power Frequency rms Line Ground Voltage COG = -------------------------------------------------------------------------------------------rms Line Line Voltage at Fault Location with the Fault Removed
This same standard also denes systems as effectively grounded when COG .8 such a system would have X0 /X1 3.0 and R0 /X1 1.0. Any other grounding means that does not satisfy these conditions at any point in a system is not effectively grounded.
The aforementioned denition is of signicance in medium voltage distribution systems with long lines and with grounded sources removed during light load periods so that in some locations in the system the X0 /X1, R0 /X1 may exceed the dening limits. Other standards (cable and lightning arrester) allow the use of 100% rated cables and arresters selected on the basis of an effectively grounded system only where the criteria in the above are met. In effectively grounded system the line-to-ground fault current is high and there is no signicant voltage rise in the unfaulted phases. With selective ground fault isolation the fault current should be at least 60%
of the 3-phase current at the point of fault. Damage to cable shields must be checked. Although this fact is not a problem except in small cables, it is a good idea to supplement the cable shields returns of ground fault current to prevent damage, by installing an equipment grounding conductor. The burdens on the current transformers must be checked also (for saturation considerations), where residually connected ground relays are used and the current transformers supply current to phase relays and meters. If ground sensor current transformers (zero sequence type) are used they must be of high burden capacity.
CA08104001E
June 2006
Sheet 0083
TOC
Index
1.4-9
Master TOC
Table 1.4-2 taken from ANSI-C62.92 indicates the characteristics of the various methods of grounding.
Grounding Point
The most commonly used grounding point is the neutral of the system or the neutral point created by means of a zigzag or a wye-broken delta grounding transformer in a system which was operating as an ungrounded delta system.
In general, it is a good practice that all source neutrals be grounded with the same grounding impedance magnitude. However, neutrals should not be tied together to a single resistor. Where one of the medium voltage sources is the utility, their consent for impedance grounding must be obtained. The neutral impedance must have a voltage rating at least equal to the rated line-to-neutral voltage class of the system. It must have at least a 10-second rating equal to the maximum future line-to-ground fault current and a continuous rating to accommodate the triple harmonics that may be present.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Reactance Grounding
It is generally used in the grounding of the neutrals of generators directly connected to the distribution system bus, in order to limit the line-to-ground fault to somewhat less than the 3-phase fault at the generator terminals. If the reactor is so sized, in all probability the system will remain effectively grounded.
Resistance Grounded
Medium voltage systems in general should be low resistance grounded. The ground fault is typically limited to about 200 400 A but less than 1000 amperes (a cable shield consideration). With a properly sized resistor and relaying application, selective fault isolation is feasible. The fault limit provided has a bearing on whether residually connected relays are used or ground sensor current transformers are used for ground fault relaying. In general, where residually connected ground relays are used (51N), the fault current at each grounded source should not be limited to less than the Table 1.4-2. Characteristics of Grounding
Grounding Classes and Means A. Effectively 1. Effective 2. Very effective B. Noneffectively 1. Inductance a. Low Inductance b. High Inductance 2. Resistance a. Low Resistance b. High Resistance 3. Inductance and Resistance 4. Resonant 5. Ungrounded/Capacitance a. Range A b. Range B
Ratios of Symmetrical Component Parameters X0/X1 0-3 0-1 R0/X1 0-1 0-0.1 R0/X0
>60 >95
2 <1.5
0-1 >100
- to -40 -40 to 0
N
Grounded Wye
Values of the coefcient of grounding (expressed as a percentage of maximum phase-to-phase voltage) corresponding to various combinations of these ratios are shown in the ANSI C62.92 Appendix gures. Coefcient of grounding affects the selection of arrester ratings. Ground-fault current in percentage of the 3-phase short circuit value. Transient line-to-ground voltage, following the sudden initiation of a fault in per unit of the crest of the prefault line-to-ground operating voltage for a simple, linear circuit. In linear circuits, Class A1 limits the fundamental line-to-ground voltage on an unfaulted phase to 138% of the prefault voltage; Class A2 to less than 110%. See ANSI 62.92 para. 7.3 and precautions given in application sections. Usual isolated neutral (ungrounded) system for which the zero-sequence reactance is capacitive (negative). Same as NOTE (6) and refer to ANSI 62.92 para. 7.4. Each case should be treated on its own merit. Under restriking arcing ground fault conditions (e.g., vacuum breaker interrupter operation), this value can approach 500%. Under arcing ground fault conditions, this value can easily reach 700% but is essentially unlimited.
17 18
19 20 21
Corner-Grounded Delta
TOC
Index
June 2006
Sheet 0084
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12
Ungrounded Delta
With one phase grounded, the voltage to ground of the other two phases rises 73%, to full phase-to-phase voltage. In low voltage systems this is not important, since conductors are insulated for 600 V. A low voltage resistance grounded system is normally grounded so that the single line-to-ground fault current exceeds the capacitive charging current of the system. If data for the charging current is not available use 40 50 ohm resistor in the neutral of the transformer. In commercial and institutional installations, such as ofce buildings, shopping centers, schools, and hospitals, lighting loads are often 50% or more of the total load. In addition, a feeder outage on rst ground fault is seldom crucial even in hospitals, which have emergency power in critical areas. For these reasons, a solidly grounded wye distribution, with the neutral used for lighting circuits, is usually the most economical, effective, and convenient design. In some instances it is an NEC requirement. In industrial installations, the effect of a shutdown caused by a single ground fault could be disastrous. An interrupted process could cause the loss of all the materials involved, often ruin the process equipment itself, and sometimes create extremely dangerous situations for operating personnel. On the other hand, lighting is usually only a small fraction of the total industrial electrical load. A solidly grounded neutral circuit conductor is not imperative and, when required, can be obtained from inexpensive lighting transformers. Because of the ability to continue in operation with one ground fault on the system, many existing industrial plants use ungrounded delta distribution. Today, new installations can have all the advantages of service continuity of the ungrounded delta, yet minimize the problems of the system, such as the difculty of locating the rst ground fault, risk of damage from a second ground fault, and damage transient overvoltages. A high-resistance grounded wye distribution can continue in operation with a ground fault on the system, will not develop transient overvoltages, and, because the ground point is established, locating a ground fault is less difcult than on an ungrounded system especially when a pulsing contactor design is applied. When combined with sensitive ground-fault protection, damage
CA08104001E
N
Ungrounded Wye
Figure 1.4-3. Ungrounded Systems Resistance-grounded systems (Figure 1.4-4) are simplest with a wye connection, grounding the neutral point directly through the resistor. Delta systems can be grounded by means of a zig-zag or other grounding transformer. Wye broken delta transformer banks may also be used.
Phase A Phase B Phase C
N R
Resistance-Grounded Wye
Phase A
Phase B Phase C
13 14 15 16 17 18 19 20 21
Delta With Derived Neutral ResistanceGrounded Using Zig-Zag Transformer
Figure 1.4-4. Resistance-Grounded Systems This derives a neutral point, which can be either solidly or impedancegrounded. If the grounding transformer has sufcient capacity, the neutral created can be solidly grounded and used as part of a 3-phase, 4-wire system. Most transformer-supplied systems are either solidly grounded or resistance grounded. Generator neutrals are often grounded through a reactor, to limit ground fault (zero sequence) currents to values the generator can withstand.
June 2006
Sheet 0085
TOC
Index
1.4-11
Master TOC
from a second ground fault can be nearly eliminated. Ungrounded delta systems can be converted to highresistance grounded systems, using a zig-zag or other grounding transformer to derive a neutral, with similar benets, see Section 38. While the majority of manufacturing plants use solidly grounded systems, in many instances, the high-resistance grounded distribution will be the most advantageous.
Main
i
Neutral
Service Transformer Sensor GFR Ground Bus Main Bonding Jumper Grounding Electrode Conductor Equipment Grounding Conductor Typical 4W Load Typical Feeder
ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Figure 1.4-5. Ground Return Sensing Method When an energized conductor faults to grounded metal, the fault current returns along the ground return path to the neutral of the source transformer. This path includes the main bonding jumper as shown in Figure 1.4-5. A current sensor on this conductor (which can be a conventional bar-type or window type CT) will respond to ground fault currents only. Normal neutral currents resulting from unbalanced loads will return along the neutral conductor and will not be detected by the ground return sensor.
This is an inexpensive method of sensing ground faults where protection per NEC (230-95) is desired. For it to operate properly, the neutral must be grounded in only one place as indicated in Figure 1.4-5. In many installations, the servicing utility grounds the neutral at the transformer and additional grounding is required in the service equipment per NEC (250-24(a)(2)). In such cases, and others including multiple source with multiple, interconnected neutral ground points, residual or zero sequence ground sensing methods should be employed.
A second method of detecting ground faults involves the use of a zero sequence sensing method, as illustrated in Figure 1.4-6. This sensing method requires a single, speciallydesigned sensor either of a toroidal or rectangular shaped conguration. This core balance current transformer surrounds all the phase and neutral conductors in a typical 3-phase, 4-wire distribution system. The sensing method is based on the fact that the vectorial sum of the phase and neutral currents in any distribution circuit will equal zero unless a ground fault condition exists downstream from the sensor. All currents that ow only in the circuit conductors, including balanced or unbalanced phase-to-phase and phaseto-neutral normal or fault currents, and harmonic currents, will result in zero
CA08104001E
TOC
Index
June 2006
Sheet 0086
Master TOC
i ii 1 2 3
neutral. In a residual sensing scheme, the relationship of the polarity markings as noted by the X on each sensor is critical. Since the vectorial sum of the currents in all the conductors will total zero under normal, nonground faulted conditions, it is imperative that proper polarity connections are employed to reect this condition.
Sensor Polarity Marks Main
or in multi-tier schemes where additional levels of ground fault protection are desired for added service continuity. Additional grounding points may be employed upstream of the residual sensors but, not on the load side. Both the zero sequence and residual sensing methods have been commonly referred to as vectorial summation methods. Most distribution systems can utilize either of the three sensing methods exclusively or a combination of the sensing methods depending upon the complexity of the system and the degree of service continuity and selective coordination desired. Different methods will be required depending upon the number of supply sources and the number and location of system grounding points. As an example, one of the more frequently used systems where continuity of service to critical loads is a factor is the dual source system illustrated in Figure 1.4-8. This system utilizes tie-point grounding as permitted under NEC Sec. 250-24(a)(3). The use of this grounding method is limited to services that are dual fed (double-ended) in a common enclosure or grouped together in separate enclosures and employing a secondary tie. This scheme utilizes individual sensors connected in ground return fashion. Under tie breaker closed operating conditions either the M1 sensor or M2 sensor could see neutral unbalance currents and possibly initiate an improper tripping operation. However, with the polarity arrangements of these two sensors along with the tie breaker auxiliary switch (T/a) and interconnections as shown, this possibility is
Residual Sensors
Neutral
4
GFR
Neutral
Typical Feeder
GFR
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Typical 4W Load
Typical Feeder
Typical 4W Load
Figure 1.4-6. Zero Sequence Sensing Method Zero sequence sensors are available with various window openings for circuits with small or large conductors, and even with large rectangular windows to t over bus bars or multiple large size conductors in parallel. Some sensors have split cores for installation over existing conductors without disturbing the connections. This method of sensing ground faults can be employed on the main disconnect where protection per NEC (230-95) is desired. It can also be easily employed in multi-tier systems where additional levels of ground fault protection are desired for added service continuity. Additional grounding points may be employed upstream of the sensor but, not on the load side. Ground fault protection employing ground return or zero sequence sensing methods can be accomplished by the use of separate ground fault relays (GFRs) and disconnects equipped with standard shunt trip devices or by circuit breakers with integral ground fault protection with external connections arranged for these modes of sensing. In some cases, a reliable source of control power is needed. The third basic method of detecting ground faults involves the use of multiple current sensors connected in a residual sensing method as illustrated in Figure 1.4-7. This is a very common sensing method used with circuit breakers equipped with electronic trip units, current sensors and integral ground fault protection. The 3-phase sensors are required for normal phase overcurrent protection. Ground fault sensing is obtained with the addition of an identically rated sensor mounted on the
Figure 1.4-7. Residual Sensing Method As with the zero sequence sensing method, the resultant residual sensor output to the ground fault relay or integral ground fault tripping circuit will be zero if all currents ow only in the circuit conductors. Should a ground fault occur, the current from the faulted conductor will return along the ground path, rather than on the other circuit conductors, and the residual sum of the sensor outputs will not be zero. When the level of ground fault current exceeds the pre-set current and time delay settings, a ground fault tripping action will be initiated. This method of sensing ground faults can be economically applied on main service disconnects where circuit breakers with integral ground fault protection are provided. It can be used in protection schemes per NEC (230-95)
Power Transformer
Power Transformer
A, B, C Neutral
A, B, C Neutral
Neutral Sensor Tie Bkr. 52-T
M1N M1G
M2G M2N
TG
TN
( )B5 ( )B4
52-T a
( )B5 ( )B4
4-Wire Load
B4 B5 Digitrip
June 2006
Sheet 0087
TOC
Index
1.4-13
Master TOC
eliminated. Selective ground fault tripping coordination between the tie breaker and the two main circuit breakers is achieved by pre-set current pickup and time delay settings between devices GFR/1, GFR/2 and GFR/T. The advantages of increased service continuity offered by this system can only be effectively utilized if additional levels of ground fault protection are added on each downstream feeder. Some users prefer individual grounding of the transformer neutrals. In such cases a partial differential ground fault scheme should be used for the mains and tie breaker. An example of a residual partial differential scheme is shown in Figure 1.4-9. The scheme typically relies upon the vector sum of at least two neutral sensors in combination with each breakers 3-phase sensors. To reduce the complexity of the drawing, each of the breakers 3-phase sensors have not been shown. It is absolutely critical that the sensors polarities are supplied as shown, the neutral sensor ratings of the mains and tie are the same, and that there are no other grounds on the neutral bus made downstream of points shown. An innite number of ground fault protection schemes can be developed depending upon the number of alternate sources, the number of grounding points and system interconnections involved. Depending upon the individual system conguration, either mode of sensing or a combination of all
GFR next upstream from the fault and that device will operate instantaneously to clear the fault with minimum damage and maximum service continuity. This operating mode permits all GFRs to operate instantaneously for a fault within their zone and still provide complete selectivity between zones. The National Electrical Manufacturers Association (NEMA) states, in their application guide for ground fault protection, that zone interlocking is necessary to minimize damage from ground faults. A 2-wire connection is required to carry the restraining signal from the GFRs in one zone to the GFRs in the next zone. Circuit breakers with integral ground fault protection and standard circuit breakers with shunt trips activated by the ground fault relay are ideal for ground fault protection. Many fused switches over 1200 A, and CutlerHammer Type FDP fusible switches in ratings from 400 A to 1200 A, are listed by UL as suitable for ground fault protection. Fusible switches so listed must be equipped with a shunt trip, and be able to open safely on faults up to 12 times their rating. Power distribution systems differ widely from each other, depending upon the requirements of each user, and total system overcurrent protection, including ground fault currents, must be individually designed to meet these needs. Experienced and knowledgeable engineers must consider the power sources (utility or on-site), the effects of outages and costs of downtime, safety for people and equipment, initial and lifecycle costs, and many other factors. They must apply protective devices, analyzing the time-current characteristics, fault interrupting capacity, and selectivity and coordination methods to provide the most safe and cost-effective distribution system.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Power Transformer
Further Information
s
52-1 a
52-T a
52-2 a
X X
s s 4-Wire Load
4-Wire Load Trip Unit Main Breaker 52-1 Trip Unit Trip Unit Tie Breaker Main Breaker 52-T 52-2
PRSC-4E System Neutral Grounding and Ground Fault Protection (ABB Publication). PB 2.2 NEMA Application Guide for Ground Fault Protective Devices for Equipment. IEEE Standard 142 Grounding of Industrial and Commercial Power Systems (Green Book). IEEE Emerald Book (Standard 1100). UL 96A, Installation Requirements for Lightning Protection Systems.
TOC
Index
June 2006
Sheet 0088
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
The electrical distribution system and equipment ground must be connected to this grounding electrode system by a grounding electrode conductor. All other grounding electrodes, such as those for the lightning protection system, the telephone system, television antenna and cable TV system grounds, and computer systems, must be bonded to this grounding electrode system.
Grounding Electrodes
At some point, the equipment and system grounds must be connected to the earth by means of a grounding electrode system. Outdoor substations usually use a ground grid, consisting of a number of ground rods driven into the earth and bonded together by buried copper conductors. The required grounding electrode system for a building is spelled out in the NEC Article 250. The preferred grounding electrode is a metal underground water pipe in direct contact with the earth for at least 10 feet (3 m). However, because underground water piping is often plastic outside the building, or may later be replaced by plastic piping, the NEC requires this electrode to be supplemented by and bonded to at least one other grounding electrode, such as the effectively grounded metal frame of the building, a concrete-encased electrode, a copper conductor ground ring encircling the building, or a made electrode such as one or more driven ground rods or a buried plate. Where any of these electrodes are present, they must be bonded together into one grounding electrode system. One of the most effective grounding electrodes is the concrete-encased electrode, sometimes called the Ufer ground, named after the man who developed it. It consists of at least 20 feet (6 m) of steel reinforcing bars or rods not less than 1/2 inches (12.7 mm) in diameter, or at least 20 feet (6 m) of bare copper conductor, size No. 4 AWG or larger, encased in at least 2 inches (50.8 mm) of concrete. It must be located within and near the bottom of a concrete foundation or footing that is in direct contact with the earth. Tests have shown this electrode to provide a low-resistance earth ground even in poor soil conditions.
Motors
Surge capacitors and, where appropriate, surge arresters should be applied at the motor terminals.
Generators
Surge capacitors and station class surge arresters at the machine terminals.
Further Information
IEEE/ANSI Standard 142 Grounding Industrial and Commercial Power Systems (Green Book). s IEEE Standard 241 Electric Power Systems in Commercial Buildings (Gray Book). s IEEE Standard 141 Electric Power Distribution for Industrial Plants (Red Book).
s
CA08104001E
June 2006
Sheet 0089
TOC
Index
1.4-15
Master TOC
Another option is to buy power conditioning equipment to correct any and all perceived power quality problems without any on-site investigation.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Power quality surveys, analysis and studies. Power monitoring. Grounding products and services. Surge protection. Voltage regulation. Harmonic solutions. Lightning protection (ground rods, hardware, etc.). Uninterruptible Power Supply (UPS) or Motor-Generator (M-G) set.
Sometimes this approach is not practical because of limitations in time; expense is not justied for smaller installations; monitoring for power disturbances may be needed over an extended period of time to capture infrequent disturbances; the exact sensitivities of the load equipment may be unknown and difcult to determine; and nally, the investigative approach tends to solve only observed problems. Thus unobserved or potential problems may not be considered in the solution. For instance, when planning a new facility, there is no site to investigate. Therefore, power quality solutions are often implemented to solve potential or perceived problems on a preventive basis instead of a thorough on-site investigation.
CA08104001E
TOC
Index
June 2006
Sheet 0090
Master TOC
i ii 1 2 3 4 5
The benet of implementing cascaded network protection is shown in Figure 1.4-11. Combined, the two stages of protection at the service entrance and branch panel locations reduce the IEEE 62.41 recommended test wave (C3 20 kV, 10 kA) to less than 200 V voltage, a harmless disturbance level for 120 V rated sensitive loads. If only building entrance feeder protection were provided, the let-through voltage will be approximately 950 V in a 277/480 V system exposed to induced lightning surges. This level of let-through voltage can cause degradation or physical damage of most electronic loads. Wherever possible, consultants, speciers and application engineers should ensure similar loads are fed from the same source. In this way, disturbancegenerating loads are separated from electronic circuits affected by power disturbances. For example; motor loads, HVAC systems and other linear loads should be separated from the sensitive process control and computer systems. The most effective and economic solution for protecting a large number of loads is to install parallel SPDs at the building service entrance feeder and panelboard locations. This reduces the cost of protection for multiple sensitive loads.
2. Surge Protection
Surge Protection Devices (SPDs) are recommended as the next stage power quality solutions. NFPA, UL 96A, IEEE Emerald Book and equipment manufacturers recommend the use of surge protectors. The transient voltage surge suppressors (also called TVSS) shunt short duration voltage disturbances to ground, thereby preventing the surge from affecting electronic loads. When installed as part of the facility-wide design, SPDs are cost-effective compared to all other solutions (on a $/kVA basis). The IEEE Emerald book recommends the use of a two-stage protection concept. For large surge currents, diversion is best accomplished in two stages: the rst diversion should be performed at the service entrance to the building. Then, any residual voltage resulting from the action can be dealt with by a second protective device at the power panel of the computer room (or other critical loads).
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Cost Per kVA 5. Uninterruptible Power Supply (UPS, Gen. Sets, etc.) 4. Harmonic Distortion 3. Voltage Regulation 2. Surge Protection 1. Grounding
1. Grounding
480 V 120/208 V
CP
TVSS
20,000 V
Input - high energy transient disturbance; IEEE Category C3 Impulse 20,000 V; 10,000 A
Grounding represents the foundation of a reliable power distribution system. Grounding and wiring problems can be the cause of up to 80% of all power quality problems. All other forms of power quality solutions are dependent upon good grounding procedures.
PEAK VOLTAGE
Best achievable performance with single TVSS at main panel (950 V, at Stage 1)
800 V 400 V 0
System Test Parameters: IEEE C62.41[10] and C62.45 [10] test procedures using category; 480 V main entrance panels; 100 feet (30 m) of 3-phase wire; 480/208 V distribution transformer; and 208 V branch panel.
= SPD or TVSS
25 uS 50 uS TIME (MICROSECONDS)
Two stage (cascade approach) achieves best possible protection (less than 200 V at Stage 2)
CA08104001E
June 2006
Sheet 0091
TOC
Index
1.4-17
Master TOC
The recommended system approach for installing SPDs is summarized in Figure 1.4-12.
1. Identify Critical Loads 2. Identify Non-Critical Loads 3. Identify Noise and Disturbance Generating Loads 4. Review Internal Power Distribution Layout 5. Identify Facility Exposure to Expected Levels of Disturbance 6. Apply Mitigating Equipment to: a) Service Entrance Main Panels b) Key Sub-Panels c) Critical Loads d) Data and Communication Lines
tion wires, the area between wires is reduced and the mutual inductance affect minimized.
i ii 1 2 3 4 5 6 7 8 9 10 11 12
Increasing the diameter of the installation wires is of negligible benet. Inductance is a skin effect phenomenon and a function of wire circumference. Since only a marginal reduction in inductance is achieved when the diameter of the installation conductors is increased, the use of large diameter wire results in only minimal improvement (see Figure 1.4-14).
Further benets provided by integrated surge suppression designs are the elimination of eld installation costs and the amount of expensive outboard wall space taken up by side mounted SPD devices.
208Y/120 Panelboard (integrated versus side mounted SPD) 1000 Let-Through Voltage at Bus Bar Side Mounted SPD used for Retrofit Applications SPD Integrated into Panelboards, Switchboards, MCCs 800 600 400 200 0 -200 -2.00 Surge Event 0.00 2.00 4.00 6.00 8.00 10.00 Integrated SPD (direct bus bar connection) Side Mounted SPD Device (assuming 14-inch (355.6 mm) lead length to bus)
13 14 15 16 17 18 19
SPD SPD
GRO UND
G RO UND
G N
Microseconds
20 21
CA08104001E For more information visit: www.EatonElectrical.com
TOC
Index
June 2006
Sheet 0092
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Additional Let-Through Voltage Using IEEE C1(6000V, 3000A)[3] Waveform (UL 1449 Test Wave)[12]
900 800 700 600 500 400 300 200 100 0
3. Voltage Regulation
Voltage Regulation (i.e., sags or overvoltage) disturbances are generally site- or load-dependent. A variety of mitigating solutions are available depending upon the load sensitivity, fault duration/magnitude and the specic problems encountered. It is recommended to install monitoring equipment on the ac power lines to assess the degree and frequency of occurrences of voltage regulation problems. The captured data will allow for the proper solution selection.
The size or capacity of a suppressor is measured in surge current per phase. Larger suppressors rated at approximately 250 kA per phase should be installed at the service entrance to survive high-energy surges associated with lightning. A 250 kA per phase surge rating allows for over a 25 year life expectancy assuming an IEEE dened high exposure environment. Lower surge rating devices may be utilized; however, device reliability and long-term performance may be compromised. For aerial structures, the 99.8 percentile recorded lightning stroke current is less than 220 kA. The magnitude of surges conducted or induced into a facility electrical distribution system is considerably lower given the presence of multiple paths for the surge to travel along. It is for this reason that IEEE C62.41 recommends the C3 (20 kV, 10 kA) test wave for testing SPDs installed at building entrance feeders. SPDs with surge ratings greater than 250 kA are not required, however, higher ratings are available and may provide longer life.
switch is about 50 to 60 V. This increase in disturbance voltage can result in process disruption and downtime.
4. Harmonics Distortion
Harmonics and Nonlinear Loads
Until recently, most electrical loads were linear. Linear loads draw the full sine wave of electric current at its 60 cycle (Hz) fundamental frequency Figure 1.4-15 shows balance single-phase, linear loads. As the gure shows, little or no current ows in the neutral conductor when the loads are nonlinear and balanced. With the arrival of non-linear electronic loads, where the ac voltage is converted to a dc voltage, harmonics are created because of the use of only part of the ac sine wave. In this conversion from ac to dc, the electronics are turned on in the 60 cycle wave at a given point in time to obtain the required dc level. The utilization of only part of the sign wave causes harmonics. It is important to note that the current distortion caused by loads such as rectiers or switch mode power supplies causes the voltage distortion. That voltage distortion is caused by distorted currents owing through an impedance. The amount of voltage distortion depends on:
s s
Devices that can cause harmonic disturbances include rectiers, thrusters and switching power supplies, all of which are non-linear. Further, the proliferation of electronic equipment such as computers, UPS systems, variable speed drives, programmable logic controllers, and the like: non-linear loads have become a signicant part of many installations. Other types of harmonic-producing loads include arcing devices (arc furnaces, uorescent lights) and iron core storable devices (transformers, especially during energization).
CA08104001E
June 2006
Sheet 0093
TOC
Index
1.4-19
Master TOC
Non-linear load currents vary widely from a sinusoidal wave shape; often they are discontinuous pulses. This means that non-linear loads are extremely high in harmonic content. Triplen harmonics are the 3rd, 9th, 15th,...harmonics. Further, triplen harmonics are the most damaging to an electrical system because these harmonics on the A-phase, B-phase and C-phase are in sequence with each other. Meaning, the triplen harmonics
Harmonic Issues
Harmonic currents perform no work and result in wasted electrical energy that may over burden the distribution system. This electrical overloading may contribute to preventing an existing electrical distribution system from serving additional future loads. In general, harmonics present on a distribution system can have the following detrimental effects: 1. Overheating of transformers and rotating equipment.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
60 Hz Fundamental
2. Increased hysteresis losses. 3. Decreased kVA capacity. 4. Overloading of neutral. 5. Unacceptable neutral-to-ground voltages.
A Phase
120 Lagging
7. Failed capacitor banks. 8. Breakers and fuses tripping. 9. Double or ever triple sized neutrals to defy the negative effects of triplen harmonics.
120 Lagging
C Phase
In transformers, generators and uninterruptible power supplies (UPS) systems, harmonics cause overheating and failure at loads below their ratings because the harmonic currents cause greater heating than standard 60 Hz current. This results from increased eddy current losses, hysteresis losses in the iron cores, and conductor skin effects of the windings. In addition, the harmonic currents acting on the impedance of the source cause harmonics in the source voltage, which is then applied to other loads such as motors, causing them to overheat. The harmonics also complicate the application of capacitors for power factor correction. If, at a given harmonic frequency, the capacitive impedance equals the system reactive impedance, the harmonic voltage and current can reach dangerous magnitudes. At the same time the harmonics create problems in the application of power factor correction capacitors, they lower the actual power factor. The rotating meters used by the utilities for watthour and various measurements do not detect the distortion component caused by the harmonics. Rectiers with diode front ends and large dc side capacitor banks have displacement power factor of 90% to 95%. More recent electronic meters are capable of metering the true kVA hours taken by the circuit. Single-phase power supplies for computer and xture ballasts are rich in third harmonics and their odd multiples.
120 Lagging
B Phase
120 Lagging
C Phase
TOC
Index
June 2006
Sheet 0094
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Table 1.4-6. Current Distortion Limits for General Distribution Systems (120 V Through 69000 V)
Maximum Harmonic Current Distortion in Percent of IL Individual Harmonic Order (Odd Harmonics) ISC /IL <11 11 17 23 35 TDD <h <h <h <h <17 <23 <35 2.0 3.5 4.5 5.5 7.0 1.5 2.5 4.0 5.0 6.0 .6 1.0 1.5 2.0 2.5 .3 .5 .7 1.0 1.4 5.0 8.0 12.0 15.0 20.0
All power generation equipment is limited to these values of current distortion, regardless of actual ISC/IL where: ISC = Maximum short circuit current at PCC. IL = Maximum demand load current (fundamental frequency component) at PCC.
Special systems are those where the rate of change of voltage of the notch might mistrigger an event. AN is a measurement of notch characteristics measured in voltmicroseconds, C is the impedance ratio of total impedance to impedance at common point in system. DF is distortion factor.
TDD = Total Demand Distortion. Even harmonics are limited to 25% of the odd harmonic limits above. Current distortions that result in a dc offset, e.g., half-wave converters, are not allowed.
Harmonic Solutions
In spite of all the concerns non-linear loads cause, these loads will continue to increase. Therefore, the design of non-linear loads and the systems that supply them will need design so adverse harmonic effects are greatly reduced. Table 1.4-7 and depicts many harmonic solutions along with their advantages and disadvantages.
5.0%
2.5%
1.5%
= h max h = 2
2 V h
It is important for the system designer to know the harmonic content of the utilitys supply voltage because it will affect the harmonic distortion of the system.
CA08104001E
June 2006
Sheet 0095
TOC
Index
1.4-21
Master TOC
Disadvantages
s May require additional compensation.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
reduce harmonic current distortion from 80% down to about 35 40%. K-Rated/Drive Isolation Transformer dc Choke 12-Pulse Convertor
s Offers series reactance (similar to line s No advantage over reactors for
on load balance.
s Must have even multiples of
of 18-pulse.
s Excellent harmonic control for drives
above 100 hp. s IEEE 519 compliant. Active Filters Computers/ Switch-Mode Power Supplies Neutral Blocking Filter
s Handles load/harmonic diversity. s Complete solution up to 50th harmonic. s Eliminates the 3rd harmonic from load. s Relieves system capacity. s Possible energy savings. s 3rd harmonic recalculated back to the load. s When used as phase-shifted transformers, s High cost. s High cost. s May increase voltage distortion. s Requires fully rated circuits and
reduces other harmonics. s Reduces voltage at-topping. Oversized Neutral/Derated Transformer K-Rated Transformer Fluorescent Lighting Harmonic Mitigating Transformers
s Tolerate harmonics rather than correct. s Typically least expensive. s Tolerate harmonics rather than correct. s 3rd harmonic recalculated back to the load. s When used as phase-shifted transformers, s Upstream and downstream equipment
s Tolerate harmonics rather than correct them. s Does not reduce system harmonics. s Reduce harmonics at the source. s Fast response and broadband s Additional cost and typically more
harmonic correction.
s Reduces voltage icker.
Tuned Filters System Solutions Tuned Filters Harmonic Mitigating Transformers Active Filters
or upgrade.
s Ideal solution and
CA08104001E
TOC
Index
June 2006
Sheet 0096
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
The normal power source supplied by the local utility or provider is not stable enough over time to continuously serve these loads without interruption. It is possible that a facility outside a major metropolitan area served by the utility grid will experience outages of some nature 15 20 times in one year. Certain outages are caused by the weather, and others by the failure of the utility supply system due to equipment failures or construction interruptions. Some outages are only several cycles in duration, while others may be for hours at a time. In a broader sense, other problems exist in the area of power quality, and many of those issues also contribute to the failure of the supply to provide that narrow range of power to the sensitive loads mentioned above. Power Quality problems take the form of any of the following: power failure, power sag, power surge, undervoltage, overvoltage, line noise, frequency variations, switching transients, and harmonic distortion. Regardless of the reason for outages and power quality problems, the sensitive loads can not function normally without a backup power source and in many cases the loads must be isolated from the instabilities of the utility supply and power quality problems and given clean reliable power on a continuous basis, or be able to switch over to reliable clean electrical power quickly.
Uninterruptible Power Supply (UPS) systems have evolved to serve the needs of sensitive equipment and can supply a stable source of electrical power, or switch to backup to allow for an orderly shutdown of the loads without appreciable loss of data or process. In the early days of mainframe computers, motor-generator sets provide isolation and clean power to the computers. They did not have deep reserves, but provided extensive ride-through capability while other sources of power (usually standby emergency engine generator sets) were brought to bear to serve the motor-generator sets while the normal source of power was unstable or unavailable. UPS systems have evolved along the lines of rotary types and static types of systems, and they come in many congurations, and even hybrid designs having characteristics of both types. The discussion that follows attempts to compare and contrast the two types of UPS systems, and give basic guidance on selection criteria. This discussion will focus on the medium, large and very large UPS systems required by users who need more than 10 kVA of clean reliable power.
CA08104001E
June 2006
Sheet 0097
TOC
Index
1.4-23
Master TOC
Each of these categories is arbitrary because manufacturers have many different UPS offerings for the same application. The choice of UPS type and the conguration of UPS modules for a given application depends upon many factors, including how many Power Quality problems the UPS is expected to solve, how much future capacity is to be purchased now for future loads, the nature of the sensitive loads and load wiring, which type of UPS system is favored, rotary or static, choices of battery or dc storage technology considered, and a host of other application issues.
low rotational speeds. These legacy types of hybrid UPS systems are not the focus of this discussion, since only one or two vendors offer these hybrid types of rotary UPS systems, although admittedly they continue to be used in very large-scale data center applications. See Figure 1.4-17 for the modern high speed Rotary UPS systems discussed in this section of the guide. These types of modern Rotary UPS systems are advanced, integrated designs utilizing scalable congurations of high-speed ywheel, motor and generator in one compact UPS package. The new rotary technologies have the potential to replace battery backup systems, or at least reduce the battery content for certain applications. The appeal of rotary systems is the avoidance of the purchase, maintenance, and facility space required by dc battery based backup systems.
system checks are performed then the input Contactor is closed. The Static Disconnect Switch is turned on and the conduction angle is rapidly increased from zero to an angle that causes the dc bus voltage between the Utility Converter and the Flywheel Converter to reach approximately 650 volts through the rectifying action of the freewheeling diodes in the Utility Converter. As soon as this level of dc voltage is reached the Static Disconnect turns on fully. The next steps involved the Utility Converter IGBTs to start ring which allows the converter to act as a Rectier, a regulating voltage source and an active harmonic lter. As the IGBTs begin to operate, the dc bus is increased to a normal operating voltage of approximately 800 volts, and the output bus is transferred from Bypass to the output of the power electronics module. The transfer from Bypass is completed when the Output Contactor is closed and the Bypass Contactor opened in a make-before-break manner. The ring of the SCRs in the Static Disconnect Switch is now changed so that each SCR in each phase is only turned on during the half-cycle, which permits real power to ow from the utility supply to the UPS. This ring pattern at the Static Disconnect Switch prevents power from the Flywheel from feeding backwards into the utility supply and assures that all of the Flywheel energy is available to support the Load.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Startup Mode
The UPS output is energized on Bypass as soon as power is applied from the Source to the system input. The UPS continues the startup procedure automatically when the front panel controls are placed into the Online position. Internal UPS
Static Bypass Option It = Input Current Ir = Real Load Current Ic = Charging Current Ig = Voltage Regulation Current Bypass Contactor It = Ir + Ic + Ig Source Flywheel Converter Ix Field Coil Driver ac dc Ih Integrated Motor/Flywheel/ and Generator dc ac Utility Converter Ic Inverter Fuse Ig Output Transformer Id = Output Current Ih = Harmonic Current Ix = Reactive Load Current Ir = Real Load Current Id = Ih + Ix + Ir Line Inductor Output Contactor Load
15 16 17 18 19 20 21
Input Contactor
Filter Inductor
CA08104001E
TOC
Index
June 2006
Sheet 0098
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Immediately after the output is transferred from Bypass to the power electronic module, the Flywheel Field is excited which also provides magnetic lift to unload the Flywheel bearings. The Flywheel Inverter is turned on and gradually increases frequency at a constant rate to accelerate the Flywheel to approximately 60 RPM. Once the Flywheel reached 60 RPM, the Flywheel Inverter controls the acceleration to keep currents below the maximum charging and the maximum input settings. Once the Flywheel reaches 4000 RPM, the UPS is fully functional and capable of supporting the Load during a power quality event. Flywheel acceleration continues until the Flywheel reaches full charge at 7,700 RPM. The total time to complete startup is less than 5 minutes.
nominal output voltage, just enough reactive current ows through the line inductor to make up the difference between the input voltage and the output voltage. The Load current consists of three components: the harmonic current required by the load, the reactive load current, and the real current, which does the work. The Utility Converter supplies both the harmonic and reactive currents. Since these currents supply no net power to the load, the Flywheel supplies no energy for these currents. They circulate between the Utility Converter and the Load. The power stage controls analyze the harmonic current requirements of the load and set the ring angle of the inverter IGBTs to make the Utility Converter a very low impedance source to any harmonic currents. Thus, non-linear load currents are supplied almost entirely from the Utility Converter with little effect on the quality of the UPS output voltage waveform and with almost no transmission of load harmonics currents to the input of the UPS.
nominal levels. Recharging the Flywheel is accomplished by controlling the Utility and Flywheel Converter in a similar manner as is used to maintain full charge in the Normal Operation Mode, however the IGBT gating points are changed to increase current into the Flywheel.
s s
Addresses all power quality problems. Battery systems are not required or used. No battery maintenance required. Unlimited discharge cycles. 150 second recharge time available. Wide range of operating temperatures can be accommodated (-20 to 40 degrees C). Small compact size and less oor space required (500 kW systems takes 20 sq.ft.). N+1 reliability available up to 900 kVA maximum. No disposal issues. Flywheel does not have deep reserve capacity rides through for up to 13 seconds at 100% load. Some enhanced ywheel systems may extend the ride through to 30 seconds at 100% load. Mechanical ywheel maintenance required every 2 3 years, and oil changes required every year. Recharge fast rates require the input to be sized for 125% of nominal current. Flywheels failures in eld not understood. Requires vacuum pumps for high speed ywheels. Limited number of vendors and experience.
Discharge Mode
The UPS senses the deviation of the voltage or frequency beyond programmed tolerances and quickly disconnects the supply source by turning off the Static Disconnect Switch and opening the Input Contactor. The disconnect occurs in less than one-half cycle. Then the Utility Converter starts delivering power from the dc bus to the Load, and the Flywheel Converter changes the ring point of its IGBTs to deliver power to the dc bus. The UPS maintains a clean output voltage within 3% or nominal voltage to the Load when input power is lost.
s
s s s
Recharge Mode
When input power is restored to acceptable limits, the UPS synchronizes the output and input voltages, closes the Input Contactor and turns on the Static Disconnect Switch. The Utility Converter then transfers power from the Flywheel to the input source by linearly increasing the real input current. The transfer time is programmable from 1 to 15 seconds. As soon as the load power is completely transferred to the input source, the Utility Converter and Flywheel Converter start to recharge the Flywheel and return to Normal Operation Mode. The Flywheel recharge power is programmable between a slow and fast rate, and using the fast rate results in an increase of UPS input current over
CA08104001E
June 2006
Sheet 0099
TOC
Index
1.4-25
Master TOC
2. The Rectier/Charger function converts the normal ac power to dc power to charge the Battery and power the Inverter. The Load is isolated from the normal input Source. 3. The Battery stores dc energy for use when input power to the UPS fails. The amount of power available from the dc Battery system and time to discharge voltage is a function of the type of Battery selected and the amperehour sized used. Battery systems should be sized for no less than 5 minutes of clean power usage from a fully charged state, and in many cases are sized to provide more time on Battery power. 4. The dc link connects the output of the Rectier/Charger to the input of the Inverter and to the Battery. Typically the Rectier/Charger is sized slightly higher than 100% of UPS output since it must power the Inverter and supply charger power to the Battery.
When the UPS recognizes a requirement to transfer to the Bypass mode it simultaneously turns the Static Switch ON, the Output Breaker to OPEN, and the Bypass Breaker to CLOSE. The Output Breaker opens and the Bypass Breaker closes in about 50 milliseconds. The restoration of normal conditions at the UPS results in the automatic restoration of the UPS module powering the Load through the Rectier/ Charger and Inverter with Load isolation from power quality problems, and the opening of the Bypass circuit.
i ii 1 2 3 4 5 6 7 8 9 10 11 12
5. The Bypass circuit provides a path for unregulated normal power to be routed around the major electronic sub-assemblies of the UPS to the Load so that the Load can continue to operate during maintenance, or when the UPS electronics fails. The Bypass Static Switch can switch to conducting mode in 150 120 milliseconds.
Addresses all power quality problems. Suitable for applications from 5 kVA to over 2500 kVA. Simple battery systems are sized for application. Long battery backup times and long life batteries are available. Higher reliability is available using redundant UPS modules.
UPS Module
13 14
Bypass Static Switch Source Normal Rectifier/Charger Breaker ac dc Inverter dc ac Battery Breaker Output Breaker Load
15 16 17
Battery
18
Figure 1.4-18. Typical Static UPS, Double Conversion Type with Battery Backup
19 20 21
CA08104001E For more information visit: www.EatonElectrical.com
TOC
Index
June 2006
Sheet 0100
Master TOC
i ii 1 2 3 4
s s s
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
s s s s
Battery systems, battery maintenance, and battery replacement are required. Large space requirement for battery systems (higher life takes more space, e.g., 500 kW takes 80 to 200 sq.ft. depending upon the type of battery used, VRLA 10 year, VRLA 20 year or ooded). Limited discharge cycles of battery system. Narrow temperature range for application. Efciencies are in the 90 94% range, which is lower than some line interactive congurations. Bypass mode places load at risk unless bypass has UPS backup. Redundancy of UPS modules results in higher costs. Output faults are cleared by the bypass circuit. Output rating of the UPS is 150% for 30 seconds. Battery disposal and safety issues exist.
3. The Battery stores dc energy for use by the Inverter when input power to the UPS fails. The amount of power available from the dc Battery system and time to discharge voltage is a function of the type of Battery selected and the ampere-hour sized used. Battery systems should be sized for the anticipated outage. 4. The dc link connects the output of the Rectier/Charger to the input of the Inverter and to the Battery. Typically the Rectier/Charger is sized only to supply charger power to the Battery, and is rated far lower than in the Double Conversion UPS. 5. The Bypass circuit provides a direct connection of input source to the Load. The Load operates from unregulated power. The Bypass Static Switch can switch to non-conducting mode in 150 120 milliseconds. When the UPS recognizes the loss of normal input power it transfers to Battery / Inverter mode by simultaneously turning the Inverter ON and the Static Switch OFF.
C. Static Line Interactive UPS Concept of Operation The basic operation of the Line Interactive UPS is: 1. The Line Interactive type of UPS has a different topology than the Static Double Conversion and Standby systems. The normal input power is connected to the Load in Parallel with a Battery and bi-directional Inverter/Charger assembly. The input source usually terminates at a line inductor and the output of the inductor is connected to the Load in parallel with the Battery and Inverter/ Charger circuit. See Figure 1.4-20 for further details. 2. The traditional Rectier circuit is eliminated and this results in a smaller footprint and weight reduction. However, line conditioning is compromised. 3. When the input power fails, the Battery/Inverter Charger circuit reverses power and supplies the Load with regulated power.
B. Standby UPS Concept of Operation The basic operation of the Standby UPS is: 1. The Standby UPS topology is similar to the Double Conversion type, but the operation of the UPS is different in signicant ways. Normal power is connected to the UPS input through the facility electrical distribution system. This usually involves two input circuits that must come from the same Source. See Figure 1.4-19 for details. 2. The Rectier/Charger function converts the normal ac power to dc power to charge the Battery only and does not simultaneously power the Inverter. The Load is connected to the input source through the Bypass static switch. The Inverter is in the standby mode ready to serve the load from Battery power if the input power source fails.
s s s s
Impractical over 2 kVA. Little to no isolation of load from power quality disturbances. Standby power is from battery alone. Battery systems, battery maintenance, and battery replacement are required. Limited discharge cycles of battery system. Narrow temperature range for application. Output faults are cleared by the bypass circuit. Battery disposal and safety issues exist.
s s s
Impractical over 5 kVA. Not as good conditioning as double conversion. Standby power is from battery alone. Battery systems, battery maintenance, and battery replacement are required. Limited discharge cycles for the battery system. Narrow temperature range for application. Battery disposal and safety issues exist.
CA08104001E
June 2006
Sheet 0101
TOC
Index
1.4-27
Master TOC
UPS Module
i ii 1 2
Source Normal Breaker Rectifier/ Charger ac dc Battery Breaker Inverter dc ac Output Breaker
Load
3 4 5 6 7
Battery
Figure 1.4-19. Typical Static UPS, Standby Type with Battery Backup
8
UPS Module
9
Source Inductor Load
10 11 12 13
Bidirectional Inverter/Charger dc ac
14
Battery
15 16
Figure 1.4-20. Typical Static UPS, Line Interactive Type with Battery Backup
17 18 19 20 21
CA08104001E
TOC
Index
June 2006
Sheet 0102
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Secondary Voltage
The choice between 208Y/120 V and 480Y/277 V secondary distribution for commercial and institutional buildings depends on several factors. The most important of these are size and types of loads (motors, uorescent lighting, incandescent lighting, receptacles) and length of feeders. In general, large motor and uorescent lighting loads, and long feeders, will tend to make the higher voltages, such as 480Y/277 V, more economical. Very large loads and long runs would indicate the use of medium voltage distribution and loadcenter unit substations close to the loads. Conversely, small loads, short runs, and a high percentage of incandescent lighting would favor lower utilization voltages such as 208Y/120 V. Industrial installations, with large motor loads, are almost always 480 V, often ungrounded delta or resistance grounded delta or wye systems (see section on ground fault protection).
Technical Factors
The principal advantage of the use of higher secondary voltages in buildings is that for a given load, less current means smaller conductors and lower voltage drop. Also, a given conductor size can supply a large load at the same voltage drop in volts, but a lower percentage voltage drop because of the higher supply voltage. Fewer or smaller circuits can be used to transmit the power from the service entrance point to the nal distribution points. Smaller conductors can be used in many branch circuits supplying power loads, and a reduction in the number of lighting branch circuits is usually possible. It is easier to keep voltage drops within acceptable limits on 480-volt circuits than on 208-volt circuits. When 120-volt
loads are supplied from a 480-volt system through step-down transformers, voltage drop in the 480-volt supply conductors can be compensated for by the tap adjustments on the transformer, resulting in full 120-volt output. Since these transformers are usually located close to the 120-volt loads, secondary voltage drop should not be a problem. If it is, taps may be used to compensate by raising the voltage at the transformer. The interrupting ratings of circuit breakers and fuses at 480 volts have increased considerably in recent years, and protective devices are now available for any required fault duty at 480 volts. In addition, many of these protective devices are current limiting, and can be used to protect downstream equipment against these high fault currents.
Practical Factors
Since most low voltage distribution equipment available is rated for up to 600 volts, and conductors are insulated for 600 volts, the installation of 480-volt systems uses the same techniques and is essentially no more difcult, costly, or hazardous than for 208-volt systems. The major difference is that an arc of 120 volts to ground tends to be selfextinguishing, while an arc of 277 volts to ground tends to be self-sustaining and likely to cause severe damage. For this reason, the National Electrical Code requires ground fault protection of equipment on grounded wye services of more than 150 volts to ground but not exceeding 600 volts phase-to-phase (for practical purpose, 480Y/277 V services), for any service disconnecting means rated 1000 amperes or more. The National Electrical Code permits voltage up to 300 volts to ground on circuits supplying permanently installed electric discharge lamp xtures, provided the luminaires do not have an integral manual switch and are mounted at least 8 feet (2.4 m) above the oor. This permits a 3-phase, 4-wire, solidly grounded 480Y/277-volt system to supply directly all of the uorescent and high-intensity discharge (HID) lighting in a building at 277 volts, as well as motors at 480 volts.
480Y/277 208Y/120 V Panel Panel Dry Ty 480-208Y/120 V (Typical Every Floor) T Ty V VA HVAC Feeder Busway Riser Emergency Lighting Riser
T Ty Typical
Elevator Riser
T Ty Typical
Typical
T Ty Typical
T Ty Typical Spare
Typical
Utility Service
Figure 1.4-21. Typical Power Distribution and Riser Diagram for a Commercial Ofce Building
Include ground fault trip.
CA08104001E
June 2006
Sheet 0103
TOC
Index
1.4-29
Master TOC
Economic Factors
Utilization equipment suitable for principal loads in most buildings is available for either 480-volt or 208-volt systems. 3-phase motors and their controls can be obtained for either voltage, and for a given horsepower are less costly at 480 volts. Fluorescent and HID lamps can be used with either 277- or 120-volt ballasts. However, in almost all cases, the installed equipment will have a lower total cost at the higher voltage.
rise, with no more than 80C (or sometimes 115C) average winding temperature rise at full load. A better method would be to evaluate transformer losses, based on actual loading cycles throughout the day, and consider the cost of losses as well as the initial cost of the transformers in purchasing. NEMA standard TP-1 is being adopted by many states and is another method of energy efcient design. NEMA TP-1 establishes minimum operating efciencies for each distribution transformer size at a loading equal to 35% of the transformer full load kVA. The 35% loading value in the NEMA standard reects eld studies conducted by the U.S. Department of Energy which showed that dry-type transformers installed in commercial facilities are typically loaded at an average of 35% of their full load capacity over a 24 hour time period. Table 1.4-8 compares losses for both low temperature rise and TP-1 transformers using a 75 kVA design. Table 1.4-8. Load Losses
Temp. Load Losses in Watts Rise C No 25% 35% 50% 75% Full Loss Load Load Load Load Load 150 115 80 TP-1 150 360 420 500 230 490 480 535 310 620 610 615 480 885 805 730 745 1,535 2,450 1,170 1,950 945 1,410 1,235 2,280
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Energy Conservation
Because of the greatly increased cost of electrical power, designers must consider the efciency of electrical distribution systems, and design for energy conservation. In the past, especially in commercial buildings, design was for lowest rst cost, because energy was inexpensive. Today, even in the speculative ofce building, operating costs are so high that energy-conserving designs can justify their higher initial cost with a rapid payback and continuing savings. Buildings that must meet LEED certications may require energy saving designs. There are four major sources of energy conservation in a commercial building the lighting system, the motors and controls, the transformers, and the HVAC system. The lighting system must take advantage of the newest equipment and techniques. New light sources, familiar light sources with higher efciencies, solid-state ballasts with dimming controls, use of daylight, environmental design, efcient luminaires, computerized or programmed control, and the like, are some of the methods that can increase the efciency of lighting systems. They add up to providing the necessary amount of light, with the desired color rendition, from the most efcient sources, where and when it is needed, and not providing light where or when it is not necessary. Using the best of techniques, ofce spaces that originally required as much as 3.5 watts per square foot have been given improved lighting, with less glare and higher visual comfort, using as little as 1.0 to 2.0 watts per square foot. In an ofce building of 200,000 square feet (60,960 m), this could mean a saving of 400 kW, which, at $.05 per kWh, 250 days per year, 10 hours per day, could save $50,000 per year in energy costs. Obviously, efcient lighting is a necessity.
HVAC systems have traditionally been very wasteful of energy, often being designed for lowest rst cost. This, too, is changing. For example, reheat systems are being replaced by variable air volume systems, resulting in equal comfort with substantial increases in efciency. While the electrical engineer has little inuence on the design of the HVAC system, he/she can specify that all motors with continuous or long duty cycles are specied as energy efcient types, and that the variable-air-volume fans do not use inlet vanes or outlet dampers, but are driven by variablespeed drives. Variable-speed drives can often be desirable on centrifugal compressor units as well. Since some of these requirements will be in HVAC specications, it is important for the energy-conscious electrical engineer to work closely with the HVAC engineer at the design stage.
CA08104001E
TOC
Index
June 2006
Sheet 0104
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Because building design and control for maximum energy saving is important and complex, and frequently involves many functions and several systems, it is necessary for the design engineer to make a thorough building and environmental study, and to weigh the costs and advantages of many systems. The result of good design can be economical, efcient operation. Poor design can be wasteful, and extremely costly.
One reason is that most cogenerators are connected to feeders serving other customers. Utilities desire to reclose the feeder after a transient fault is cleared. Reclosing in most cases will damage the cogenerator if it had remained connected to their system. Islanding is another reason why the utility insists on the disconnection of the cogenerator. Islanding is the event that after a fault in the utilitys system is cleared by the operation of the protective devices, a part of the system may continue to be supplied by cogeneration. Such a condition is dangerous to the utilitys operation during restoration work. Major cogenerators are connected to the subtransmission or the transmission system of a utility. Major cogenerators have buy-sell agreements. In such cases utilities use a trip transfer scheme to trip the cogenerator breaker. Guidelines that are given in ANSI Guide Standard 1001 are a good starting point, but the entire design should be coordinated with the utility.
Cogeneration
Cogeneration is another outgrowth of the high cost of energy. Cogeneration is the production of electric power concurrently with the production of steam, hot water, and similar energy uses. The electric power can be the main product, and steam or hot water the by-product, as in most commercial installations, or the steam or hot water can be the most required product, and electric power a by-product, as in many industrial installations. In some industries, cogeneration has been common practice for many years, but until recently it has not been economically feasible for most commercial installations. This has been changed by the high cost of purchased energy, plus a federal law (Public Utility Regulatory Policies Act, known as PURPA) that requires public utilities to purchase any excess power generated by the cogeneration plant. In many cases, practical commercial cogeneration systems have been built that provide some or all of the electric power required, plus hot water, steam, and sometimes steam absorption-type air conditioning. Such cogeneration systems are now operating successfully in hospitals, shopping centers, high-rise apartment buildings and even commercial ofce buildings. Where a cogeneration system is being considered, the electrical distribution system becomes more complex. The interface with the utility company is critical, requiring careful relaying to protect both the utility and the cogeneration system. Many utilities have stringent requirements that must be incorporated into the system. Proper generator control and protection is necessary, as well. An on-site electrical generating plant tied to an electrical utility, is a sophisticated engineering design. Utilities require that when the protective device at their substation opens that the device connecting a cogenerator to the utility open also.
Emergency Power
Most areas have requirements for emergency and standby power systems. The National Electrical Code does not specically call for any emergency or standby power, but does have requirements for those systems when they are legally mandated and classed as emergency (Article 700), legally required standby (Article 701) by municipal, state, federal, or other codes, or by any governmental agency having jurisdiction. Optional standby systems, not legally required, are also covered in the NEC (Article 702). Emergency systems are intended to supply power and illumination essential for safety to human life, when the normal supply fails. NEC requirements are stringent, requiring periodic testing under load and automatic transfer to emergency power supply on loss of normal supply. See Figure 1.4-22 on Page 1.4-31. All wiring from emergency source to emergency loads must be kept separate from all other wiring and equipment, in its own distribution and raceway system, except in transfer equipment enclosures and similar locations. The most common power source for large emergency loads is an engine-generator set, but the NEC also permits the emergency supply (subject to local code requirements) to be storage
CA08104001E
June 2006
Sheet 0105
TOC
Index
1.4-31
Master TOC
Utility Source
i
Typical Application: Three engine generator sets serve the load, plus one additional engine generator set for redundancy to achieve N+1 level of performance. Open or Closed transition is available.
ii
G1 Revenue Metering HMI Touchscreen 52G1 Main Service 52G2 52G3 52G4 D1 D2 D3 D4 G2 G3 G4 Paralleling Switchgear with Distribution
1 2 3 4 5
To Emergency Circuits
ATS1
ATS2
ATS3
ATS4
6 7
EDP1
EDP2
EDP3
EDP4
8
Optional Remote PC with Software LP1 BP1 LP2 BP2 LP3 BP3 LP4 BP4
9 10
Figure 1.4-22. Typical Emergency Power System batteries, uninterruptible power supplies, a separate emergency service, or a connection to the service ahead of the normal service disconnecting means. Unit equipment for emergency illumination, with a rechargeable battery, a charger to keep it at full capacity when normal power is on, one or more lamps, and a relay to connect the battery to the lamps on loss of normal power, is also permitted. Because of the critical nature of emergency power, ground fault protection is not required. It is considered preferable to risk arcing damage, rather than to disconnect the emergency supply completely. For emergency power, ground fault alarm is required by NEC 700.7(D) to indicate a ground fault in solidly grounded wye emergency systems of more than 150 volts to ground and circuit-protective devices rated 1000 amperes or more. Legally required standby systems, as required by the governmental agency having jurisdiction, are intended to supply power to selected loads, other than those classed as emergency systems, on loss of normal power. These are usually loads not essential to human safety, but loss of which could create hazards or hamper rescue
CA08104001E
or re-ghting operations. NEC requirements are similar to those for emergency systems, except that wiring may occupy the same distribution and raceway system as the normal wiring if desired. Optional standby systems are those not legally required, and are intended to protect private business or property where life safety does not depend on performance of the system. Optional systems can be treated as part of the normal building wiring system. Both legally required and optional standby systems should be installed in such a manner that they will be fully available on loss of normal power. It is preferable to isolate these systems as much as possible, even though not required by code. Where the emergency or standby source, such as an engine generator or separate service, has capacity to supply the entire system, the transfer scheme can be either a full-capacity automatic transfer switch, or, less costly but equally effective, normal and emergency main circuit breakers, electrically interlocked such that on failure of the normal supply the emergency supply is connected to the load. However, if the emergency or standby source does not have capacity for the
For more information visit: www.EatonElectrical.com
full load, as is usually the case, such a scheme would require automatic disconnection of the nonessential loads before transfer. Simpler and more economical in such a case is a separate emergency bus, supplied through an automatic transfer switch, to feed all critical loads. The transfer switch connects this bus to the normal supply, in normal operation. On failure of the normal supply, the engine-generator is started, and when it is up to speed the automatic switch transfers the emergency loads to this source. On return of the normal source, manual or automatic retransfer of the emergency loads can take place.
11 12 13 14 15 16 17 18 19 20 21
Peak Shaving
Many installations now have emergency or standby generators. In the past, they were required for hospitals and similar locations, but not common in ofce buildings or shopping centers. However, many costly and unfortunate experiences during utility blackouts in recent years have led to the more frequent installation of engine generators in commercial and institutional systems for safety and for supplying important loads. Industrial plants, especially in
TOC
Index
June 2006
Sheet 0106
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Some reduction or attenuation takes place through building walls, the remainder may be reected in various directions, resulting in a build-up or apparent higher levels, especially if resonance occurs because of room dimensions or material characteristics.
Area Consideration
In determining permissible sound levels within a building, it is necessary to consider how the rooms are to be used and what levels may be objectionable to occupants of the building. The ambient sound level values given in Table 1.4-9 are representative average values and may be used as a guide in determining suitable building levels. Decrease in sound level varies at an approximate rate of 6 decibels for each doubling of the distance from the source of sound to the listener. For example, if the level 6 feet (1.8 m) from a transformer is 50 dB, the level at a distance of 12 feet (3.7 m) would be 44 dB and at 24 feet (7.3 m) the level decreases to 38 dB, etc. However, this rule applies only to equipment in large areas equivalent to an outof-door installation, with no nearby reecting surfaces. Table 1.4-9. Typical Sound Levels
Description Average Decibel Level (dB)
Sound Levels
Sound Levels of Electrical Equipment for Ofces, Hospitals, Schools and Similar Buildings
Insurance underwriters and building owners desire and require that the electrical apparatus be installed for maximum safety and the least interference with the normal use of the property. Architects should take particular care with the designs for hospitals, schools and similar buildings to keep the sound perception of such equipment as motors, blowers and transformers to a minimum. Even though transformers are relatively quiet, resonant conditions may exist near the equipment which will amplify their normal 120 Hz hum. Therefore, it is important that consideration be given to the reduction of amplitude and to the absorption of energy at this frequency. This problem begins in the designing stages of the equipment and the building. There are two points worthy of consideration: 1) What sound levels are desired in the normally occupied rooms of this building? 2) To effect this, what sound level in the equipment room and what type of associated acoustical treatment will give the most economical installation overall? A relatively high sound level in the equipment room does not indicate an abnormal condition within the apparatus. However, absorption may be necessary if sound originating in an unoccupied equipment room is objectionable outside the room. Furthermore, added absorption material usually is desirable if there is a build-up of sound due to reections.
Radio, Recording and TV Studios 25 30 Theatres and Music Rooms 30 35 Hospitals, Auditoriums and Churches 35 40 Classrooms and Lecture Rooms 35 40 Apartments and Hotels 35 45 Private Ofces and Conference Rooms 40 45 Stores Residence (Radio, TV Off) and Small Ofces Medium Ofce (3 to 10 Desks) Residence (Radio, TV On) Large Store (5 or More Clerks) Factory Ofce Large Ofce Average Factory Average Street 45 55 53 58 60 61 61 64 70 80
CA08104001E
June 2006
Sheet 0107
TOC
Index
1.4-33
Master TOC
Since values given in Table 1.4-10 are in general higher than those given in Table 1.4-9, the difference must be attenuated by distance and by proper use of materials in the design of the building. An observer may believe that a transformer is noisy because the level in the room where it is located is high. Two transformers of the same sound output in the same room increase the sound level in the room approximately 3 dB, and three transformers by about 5 dB, etc.
Sounds due to structure-transmitted vibrations originating from the transformer are lowered by mounting the transformers on vibration dampeners or isolators. There are a number of different sound vibration isolating materials which may be used with good results. Dry-type power transformers are often built with an isolator mounted between the transformer support and case members. The natural period of the core and coil structure when mounted
on vibration dampeners is about 10% of the fundamental frequency. The reduction in the transmitted vibration is approximately 98%. If the oor or beams beneath the transformer are light and exible, the isolator must be softer or have improved characteristics in order to keep the transmitted vibrations to a minimum. (Enclosure covers and ventilating louvers are often improperly tightened or gasketed and produce unnecessary noise). The building structure will assist the dampeners if the transformer is mounted above heavy oor members or if mounted on a heavy oor slab. Positioning of the transformer in relation to walls and other reecting surfaces has a great effect on reected noise and resonances. Often, placing the transformer at an angle to the wall, rather than parallel to it, will reduce noise. Electrical connections to a substation transformer should be made with exible braid or conductors; connections to an individually mounted transformer should be in exible conduit.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
June 2006
Sheet 0108
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
June 2006
Sheet 0109
TOC
Index
1.5-1
Master TOC
i ii 1 2 3 4 5
A device which functions to give a desired amount Used for providing a time-delay for of time delay before or after any point of operation re-transfer back to the normal source in a switching sequence or protective relay system, in an automatic transfer scheme. except as specically provided by device functions 48, 62 and 79 described later. A device whose principal function is to connect a machine to its source of starting voltage. A device which operates to initiate or cause the automatic transfer of a machine from the starting to the running power connection. A device which functions when the circuit admittance, impedance or reactance increases or decreases beyond predetermined limits. A device which functions to raise or to lower the temperature of a machine or other apparatus, or of any medium, when its temperature falls below or rises above, a predetermined level. A device that operates when the ratio of voltage to frequency is above a preset value or is below a different preset value. The relay may have any combination of instantaneous or time delayed characteristics. A device which operates when two ac circuits are within the desired limits of frequency, phase angle or voltage, to permit or cause the paralleling of these two circuits. A device which functions on a given value of undervoltage. Used to transfer a reduced voltage starter from starting to running.
6 19
21
Distance relay
23
24
6
In a closed transition breaker transfer, a 25 relay is used to ensure two-sources are synchronized before paralleling. Cutler-Hammer FP-5000 feeder protective relay. Used to initiate an automatic transfer when a primary source of power is lost. Cutler-Hammer FP-5000/ FP-4000/MP-4000 protective relays. Used to remotely indicate that a protective relay has functioned, or that a circuit breaker has tripped. Typically, a mechanical drop type annunciator panel is used. Used to prevent reverse power from feeding an upstream fault. Often used when primary backup generation is utilized in a facility. CutlerHammer FP-5000 protective relay. Used to indicate the position of a drawout circuit breaker (TOC switch).
25
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
27
Undervoltage relay
30
Annunciator relay
A non-automatically reset device that gives a number of separate visual indications upon the functioning of protective devices, and which may also be arranged to perform a lockout function. A relay which functions on a desired value of power ow in a given direction, or upon reverse power resulting from arc back in the anode or cathode circuits of a power rectier. A device which makes or breaks contact when the main device or piece of apparatus, which has no device function number, reaches a given point.
32
33
Position switch
34
A device such as a motor-operated multi-contact switch, or the equivalent, or a programmable device, that establishes or determines the operating sequence of the major devices in equipment during starting and stopping or during sequential switching operations. A relay which functions when the current or power ow decreases below a predetermined value. Cutler-Hammer MP-3000/MP-4000 motor protective relays.
37 38
A device which functions on excessive bearing Cutler-Hammer MP-3000/MP-4000 temperature, or on other abnormal mechanical motor protective relays. conditions, such as undue wear, which may eventually result in excessive bearing temperature. A device that functions on a given or abnormally high or low value or failure of machine eld current, or on an excessive value of the reactive component of armature current in an ac machine indicating abnormally high or low eld excitation. A device which functions to apply, or to remove, the eld excitation of a machine. A device whose function is to connect a machine to its source of running or operating voltage. This function may also be used for a device, such as a contactor, that is used in series with a circuit breaker or other fault-protecting means, primarily for frequent opening and closing of the circuit.
40
Field relay
41 42
CA08104001E
1.5-2
TOC
Index
June 2006
Sheet 0110
Master TOC
i ii 1 2 3 4 5 6 7 8
Typical Uses
44
46
Reverse-phase, or phase balance, current relay A relay which functions when the polyphase currents are of reverse-phase sequence, or when the polyphase currents are unbalanced or contain the negative phase-sequence components above a given amount. Phase-sequence voltage relay A relay which functions upon a predetermined value of polyphase voltage in the desired phase sequence.
Cutler-Hammer FP-5000/FP-4000 feeder protective relays and MP-3000/ MP-4000 motor protective relays.
47
Cutler-Hammer FP-5000/FP-4000 feeder protective relays and MP-3000/ MP-4000 motor protective relays.
48
A relay that generally returns the equipment to the normal, or off, position and locks it out of the normal starting, or operating or stopping sequence is not properly completed within a predetermined amount of time. If the device is used for alarm purposes only, it should preferably be designated as 48A (alarm). A relay that functions when the temperature of a machine armature, or other load carrying winding or element of a machine, or the temperature of a power rectier or power transformer (including a power rectier transformer) exceeds a predetermined value. Cutler-Hammer MP-3000/MP-4000 motor protective relays.
49
50
9 10 11 12 13 14
52 51
Instantaneous overcurrent, or rate-of-rise relay A relay that functions instantaneously on an excessive value of current, or an excessive rate of current rise, thus indicating a fault in the apparatus of the circuit being protected.
Used for tripping a circuit breaker instantaneously during a high level short circuit. Can trip on phasephase (50), phase-neutral (50N), phase-ground (50G) faults. Cutler-Hammer Digitrip 3000, FP-5000/FP-4000 protective relays, MP-3000/MP-4000 motor protective relays. Used for tripping a circuit breaker after a time delay during a sustained overcurrent. Used for tripping a circuit breaker instantaneously during a high level short circuit . Can trip on phase (51), neutral (51N) or ground (51G) overcurrents. Cutler-Hammer Digitrip 3000, FP-5000/FP-4000 protective relays, MP-3000/MP-4000 motor protective relays. A term applied typically to medium voltage circuit breakers, or low voltage power circuit breakers. Cutler-Hammer VCP-W Vacuum Circuit Breaker, Magnum DS Low Voltage Power Circuit Breaker
A relay with either a denite or inverse time characteristic that functions when the current in an ac circuit exceeds a predetermined value.
ac circuit breaker
15 16 17 18 19 20 21
60 Voltage or current balance relay 53 Exciter or dc generator relay
A device that is used to close and interrupt an ac power circuit under normal conditions or to interrupt this circuit under fault or emergency conditions.
A device that forces the dc machine eld excitation to build up during starting or that functions when the machine voltage has built up to a given value. A relay that operates when the power factor in an ac circuit rises above or below a predetermined value.
55
Cutler-Hammer FP-5000/FP-4000 feeder protective relays and MP-4000 motor protective relay.
56
A device that automatically controls the application of the eld excitation to an ac motor at some predetermined point in the slip cycle. A relay that functions on a given value of overvoltage. Used to trip a circuit breaker, protecting downstream equipment from sustained overvoltages. Cutler-Hammer FP-5000/FP-4000 feeder protective relays and MP-4000 motor protective relay.
59
Overvoltage relay
A relay that operates on a given difference in voltage, or current input or output of two circuits.
CA08104001E
June 2006
Sheet 0111
TOC
Index
1.5-3
Master TOC
Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
Device Number 62 Function Time-delay stopping or opening relay Denition A time-delay relay that serves in conjunction with the device that initiates the shutdown, stopping, or opening operation in an automatic sequence. A switch which operates on given values or on a given rate of change of pressure. Typical Uses Used in conjunction with a 27 device to delay tripping of a circuit breaker during a brief loss of primary voltage, to prevent nuisance tripping. Used to protect a transformer during a rapid pressure rise during a short circuit. This device will typically act to open the protective devices above and below the transformer. Typically used with a 63-X auxiliary relay to trip the circuit breaker.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14
63
Pressure switch
64
A relay that functions on a failure of the insulation Used to detect and act on a groundof a machine, transformer, or of other apparatus to fault condition. In a pulsing high ground, or on ashover of a dc machine to ground. resistance grounding system, a 64 device will initiate the alarm. A device consisting of an assembly of uid, electrical or mechanical control equipment used for regulating the ow of water, steam, or other media to the prime mover for such purposes as starting, holding speed or load, or stopping. A device that functions to allow only a specied Cutler-Hammer MP-3000/MP-4000 number of operations of a given device, or motor protective relays. equipment, or a specied number of successive operations within a given time of each other. It also functions to energize a circuit periodically or for fractions of specied time intervals, or that is used to permit intermittent acceleration or jogging of a machine at low speeds for mechanical positioning. A relay that functions on a desired value of ac overcurrent owing in a predetermined direction. Cutler-Hammer FP-5000 feeder protective relay.
65
Governor
66
67 69
A device that is generally a two-position manually Used as a remote-local switch for operated switch that in one position permits the circuit breaker control. closing of a circuit breaker, or the placing of equipment into operation, and in the other position prevents the circuit breaker to the equipment from being operated. A switch that operates on given values, or on a given rate of change of level. Used to indicate a low liquid level within a transformer tank in order to save transformers from loss-ofinsulation failure. An alarm contact is available as a standard option on a liquid level gauge. It is set to close before an unsafe condition actually occurs.
71
Level Switch
72
dc circuit breaker
A device that is used to close and interrupt a dc power circuit under normal conditions or to interrupt this circuit under fault or emergency conditions. A device that is used to shunt or insert a step of load limiting, shifting or indicating resistance in a power circuit; to switch a space heater in circuit; or to switch a light or regenerative load resistor of a power rectier or other machine in and out of circuit. A device other than an annunciator, as covered under device number 30, which is used to operate, or to operate in connection with, a visible or audible alarm.
73
Load-resistor contactor
15
74
Alarm relay
16 17 18 19 20 21
78
A device that functions at a predetermined phase angle between two voltages, between two currents, or between voltage and current. A relay that controls the automatic closing and locking out of an ac circuit interrupter. Used to automatically reclose a circuit breaker after a trip, assuming the fault has been cleared after the power was removed from the circuit. The recloser will lock-out after a predetermined amount of failed attempts to reclose.
79
ac reclosing relay
CA08104001E
1.5-4
TOC
Index
June 2006
Sheet 0112
Master TOC
i ii 1 2 3 4 5 6 7 8
Typical Uses Used to trip a generator circuit breaker in the event the frequency drifts above or below a given value. Cutler-Hammer FP-5000/FP-4000 feeder protective relays and MP-4000 motor protective relay. Used to transfer control power sources in a double-ended switchgear lineup.
83
A relay that operates to select automatically between certain sources or conditions in equipment, or performs a transfer operation automatically. A device that is operated or restrained by a signal transmitted or received via any communications media used for relaying. An electrically operated hand, or electrically, reset relay that functions to shut down and hold an equipment out of service on the occurrence of abnormal conditions.
85
86
Locking-out relay
Used in conjunction with protective relays to lock-out a circuit breaker (or multiple circuit breakers) after a trip. Typically required to be manually reset by an operator before the breaker can be reclosed.
87
A protective relay that functions on a percentage or Used to protect static equipment, phase angle or other quantitative difference of two such as cable, bus or transformers, currents or of some other electrical quantities. by measuring the current differential between two points. Typically the upstream and/or downstream circuit breaker will be incorporated into the zone of protection. Cutler-Hammer FP-5000 feeder protective relay (87B) and MD-3000 protective relay. A device that functions to regulate a quantity or quantities, such as voltage, current, power, speed, frequency, temperature and load, at a certain value or between certain (generally close) limits for machines, tie lines or other apparatus. A device that operates when the voltage across an open circuit breaker or contactor exceeds a given value in a given direction. A relay that functions to trip a circuit breaker, contactor, or equipment, or to permit immediate tripping by other devices, or to prevent immediate reclosure of a circuit interrupter, in case it should open automatically even though its closing circuit is maintained closed.
90
Regulating device
9 10 11 12 13 14 15 16 17 18 19 20 21
91 Voltage directional relay
94
CA08104001E
June 2006
Sheet 0113
TOC
Index
1.5-5
Master TOC
Main Device
The following letters denote the main device to which the numbered device is applied or is related: A AC BP BT C DC E F G M MOC S T TOC Alarm/auxiliary power Alternating current Bypass Bus tie Capacitor Direct current Exciter Feeder/eld Generator/ground Motor/metering Mechanism operated contact Synchronizing/secondary Transformer Truck-operated contacts
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CS D L O OP
PB R U X Y Z
Actuating Quantities
These letters indicate the condition or electrical quantity to which the device responds, or the medium in which it is located, such as the following: A C F I0 I-, I2 I+, I1 P PF S T V VAR VB W Amperes/alternating Current Frequency/fault Zero sequence current Negative sequence current Positive sequence current Power/pressure Power factor Speed Temperature Voltage/volts/vacuum Reactive power Vibration Watts
CA08104001E
1.5-6
TOC
Index
June 2006
Sheet 0114
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
testing laboratories have been recognized and accepted. The Institute of Electrical and Electronic Engineers (IEEE) publishes a number of books (the color book series) on recommended practices for the design of industrial buildings, commercial buildings, emergency power systems, grounding, and the like. Most of these IEEE standards have been adopted as ANSI standards. They are excellent guides, although they are not in any way mandatory.
A design engineer should conform to all applicable codes, and require equipment to be listed by UL or another recognized testing laboratory wherever possible, and to meet ANSI or NEMA standards. ANSI/IEEE recommended practices should be followed to a great extent. In many cases, standards should be exceeded to get a system of the quality required. The design goal should be a safe, efcient, long-lasting, exible, and economical electrical distribution system.
Professional Organizations
Operations:
25 West 43rd Street 4th Floor New York, NY 10036 212-642-4900 www.ansi.org
Operations:
445 Hoes Lane Piscataway, NJ 08854-1331 732-981-0060 www.ieee.org
CA08104001E
June 2006
Sheet 0115
TOC
Index
1.5-7
Master TOC
Motor Protection
In line with 2005 NEC 430.6(A) circuit breaker, HMCP and fuse rating selections are based on full load currents for induction motors running at speeds normal for belted motors and motors with normal torque characteristics using data taken from NEC Table 130.250 (3-phase). Actual motor nameplate ratings shall be used for selecting motor running overload protection. Motors built special for low speeds, high torque characteristics, special starting conditions and applications will require other considerations as dened in the application section of the NEC. These additional considerations may require the use of a higher rated HMCP, or at least one with higher magnetic pickup settings. Circuit breaker, HMCP and fuse ampere rating selections are in line with maximum rules given in NEC 430.52 and Table 430.250. Based on known characteristics of Eatons Cutler-Hammer type breakers, specic units are recommended. The current ratings are no more than the maximum limits set by the NEC rules for motors with code letters F to V or without code letters. Motors with lower code letters will require further considerations. In general, these selections were based on: 1. Ambient Outside enclosure not more than 40C (104F). 2. Motor starting Infrequent starting, stopping or reversing. 3. Motor accelerating time 10 seconds or less. 4. Locked rotor Maximum 6 times motor FLA. Type HMCP motor circuit protector may not set at more than 1300% of the motor full-load current to comply with NEC 430.52. (Except for NEMA Design B energy high-efciency motors which can be set up to 1700%.) Circuit breaker selections are based on types with standard interrupting ratings. Higher interrupting rating types may be required to satisfy specic system application requirements. For motor full load currents of 208 and 200 volts, increase the corresponding 230-volt motor values by 10 and 15% respectively.
i ii 1 2 3 4 5 6 7
8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E
1.5-8
TOC
Index
June 2006
Sheet 0116
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Recommended Cutler-Hammer: Circuit Breaker Amperes Type 30 35 40 50 70 100 150 15 20 25 30 40 60 80 ED ED ED ED ED ED ED ED ED ED ED ED ED ED 2-Pole Device Not Available Motor Circuit Protector Type GMCP/HMCP Amperes Adjustable Range
.50 (12.7) 45 .50 (12.7) 60 .75 (19.1) 100 1.00 (25.4) 150 .50 (12.7) .50 (12.7) .50 (12.7) .50 (12.7) .50 (12.7) .50 (12.7) .50 (12.7) 15 15 20 25 30 50 70
Consult fuse manufacturers catalog for smaller fuse ratings. Types are for minimum interrupting capacity breakers. Ensure that the fault duty does not exceed breakers I.C.
CA08104001E
June 2006
Sheet 0117
TOC
Index
1.5-9
Master TOC
i ii 1
6400 6700 6800 6800 6900 7000 9900 10,600 10,900 11,200 11,300 11,500 12,900 14,000 14,500 14,800 15,100 15,500 16,300 18,200 18,900 19,500 20,100 20,600 22,300 25,800 27,200 28,500 29,700 30,900 27,500 32,600 35,000 37,200 39,100 41,300 32,000 38,800 42,000 45,200 48,100 51,400 36,100 44,500 48,800 53,000 57,000 61,700 41,600 52,400 58,100 64,200 69,900 77,200
14,900 15,700 16,000 16,300 16,500 16,700 21,300 25,200 26,000 26,700 27,200 27,800 28,700 32,000 33,300 34,400 35,200 36,200 35,900 41,200 43,300 45,200 46,700 48,300 47,600 57,500 61,800 65,600 68,800 72,500
1700 1700 1700 1700 1700 1700 2800 2800 2800 2800 2800 2800 4200 4200 4200 4200 4200 4200 5600 5600 5600 5600 5600 5600 8300 8300 8300 8300 8300 8300
12,900 13,600 13,900 14,100 14,300 14,400 20,000 21,900 22,500 23,100 23,600 24,100 24,900 27,800 28,900 29,800 30,600 31,400 31,000 35,600 37,500 39,100 40,400 41,800 41,200 49,800 53,500 56,800 59,600 62,800
2900 2900 2900 2900 2900 2900 4800 4800 4800 4800 4800 4800 7200 7200 7200 7200 7200 7200 9800 9800 9800 9800 9800 9800 14,400 14,400 14,400 14,400 14,400 14,400
15,800 16,500 16,800 17,000 17,200 17,300 24,800 26,700 27,300 27,900 28,400 28,900 32,100 35,000 36,100 37,000 37,800 38,600
6400 6800 6900 7000 7100 7200 10,000 10,900 11,300 11,600 11,800 12,000 12,400 13,900 14,400 14,900 15,300 15,700 15,500 17,800 18,700 19,600 20,200 20,900 20,600 24,900 26,700 28,400 29,800 31,400 24,700 31,000 34,000 36,700 39,100 41,800 28,000 36,500 40,500 44,600 48,100 52,300 30,700 41,200 46,600 51,900 56,800 62,800 34,000 47,500 54,700 62,200 69,400 78,500
1400 1400 1400 1400 1400 1400 2400 2400 2400 2400 2400 2400 3600 3600 3600 3600 3600 3600 4800 4800 4800 4800 4800 4800 7200 7200 7200 7200 7200 7200 9600 9600 9600 9600 9600 9600 12,000 12,000 12,000 12,000 12,000 12,000 14,000 14,000 14,000 14,000 14,000 14,000 18,000 18,000 18,000 18,000 18,000 18,000
7800 8200 8300 8400 8500 8600 12,400 13,300 13,700 14,000 14,200 14,400 16,000 17,500 18,000 18,500 18,900 19,300 20,300 22,600 23,500 24,400 25,000 25,700
5200 5500 5600 5600 5700 5800 8000 8700 9000 9300 9400 9600 10,000 11,100 11,600 11,900 12,200 12,600 12,400 14,300 15,000 15,600 16,200 16,700 16,500 20,000 21,400 22,700 23,900 25,100 19,700 24,800 27,200 29,400 31,300 33,500 22,400 29,200 32,400 35,600 38,500 41,800 24,600 33,000 37,300 41,500 45,500 50,200 27,200 38,000 43,700 49,800 55,500 62,800
1200 1200 1200 1200 1200 1200 1900 1900 1900 1900 1900 1900 2900 2900 2900 2900 2900 2900 3900 3900 3900 3900 3900 3900 5800 5800 5800 5800 5800 5800 7800 7800 7800 7800 7800 7800 9600 9600 9600 9600 9600 9600 11,500 11,500 11,500 11,500 11,500 11,500 14,400 14,400 14,400 14,400 14,400 14,400
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
25,900 1203 28,000 1203 28,800 1203 29,500 1203 30,000 1203 30,600 1203 32,900 1804 36,200 1804 37,500 1804 38,600 1804 39,400 1804 40,400 1804 41,500 2406 46,800 2406 48,900 2406 50,800 2406 52,300 2406 53,900 2406 55,900 3609 65,800 3609 70,100 3609 73,900 3609 77,100 3609 80,800 3609
250,000 1388 500,000 1388 Unlimited 1388 750 5.75% 50,000 100,000 150,000 2080 2080 2080
250,000 2080 500,000 2080 Unlimited 2080 1000 5.75% 50,000 100,000 150,000 2776 2776 2776
40,600 1203 45,200 1203 47,100 1203 48,700 1203 50,000 1203 51,400 1203 55,600 1804 64,200 1804 57,900 1804 71,200 1804 74,000 1804 77,200 1804 2406 2406 2406 2406 2406 2406 3008 3008 3008 3008 3008 3008 3609 3609 3609 3609 3609 3609 4511 4511 4511 4511 4511 4511
250,000 2776 500,000 2776 Unlimited 2776 1500 5.75% 50,000 100,000 150,000 4164 4164 4164
27,800 1444 32,100 1444 33,900 1444 35,600 1444 37,000 1444 38,600 1444 34,300 1924 40,600 1924 43,600 1924 46,300 1924 48,700 1924 51,400 1924 40,000 2405 48,500 2405 52,500 2405 56,600 2405 60,100 2405 64,300 2405 44,700 2886 55,200 2886 60,600 2886 65,900 2886 70,800 2886 76,800 2886 52,000 3608 65,500 3608 72,700 3608 80,200 3608 87,400 3608 96,500 3608
250,000 4164 500,000 4164 Unlimited 4164 2000 5.75% 50,000 100,000 150,000
Short circuit capacity values shown correspond to kVA and impedances shown in this table. For impedances other than these, short circuit currents are inversely proportional to impedance. The motors short circuit current contributions are computed on the basis of motor characteristics that will give four times normal current. For 208 volts, 50% motor load is assumed while for other voltages 100% motor load is assumed. For other percentages, the motor short circuit current will be in direct proportion.
CA08104001E
TOC
Index
June 2006
Sheet 0118
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
13,800 1.26 1.88 3.14 4.71 6.28 9.41 12.6 20.9 31.4 41.8 62.8 83.7 105 126 157 209 314 418
22,900 0.75 1.13 1.89 2.84 3.78 5.67 7.56 12.6 18.9 25.2 37.8 50.4 63.0 75.6 94.5 126 189 252
34,400 0.50 0.76 1.26 1.89 2.52 3.78 5.04 8.39 12.6 16.8 25.2 33.6 42.0 50.4 62.9 83.9 126 168
30 45 75 112-1/2 150 225 300 500 750 1000 1500 2000 2500 3000 3750 5000 7500 10,000
CA08104001E
June 2006
Sheet 0119
TOC
Index
1.5-11
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
150C Rise
15 30 45 75 112.5 150 225 300 500 750
150C Rise
3 6 9 15 30 45 75 112.5 150 225 300 500 750 1000
115C Rise
15 30 45 75 112.5 150 225 300 500
115C Rise
15 30 45 75 112.5 150 225 300 500 750
80C Rise
65C Rise
112.5 150 225 300 500 750 1000 1500 2000 2500
80C Rise
15 30 45 75 112.5 150 225 300 500
Table 1.5-10. 600 Volt Primary Class NEMA Type TP-1 Dry-Type Transformers
kVA 300 300 300 500 500 Temperature Rise 80 115 150 115 150 115 150 Impedance 3.16 at 100C 3.03 at 135C 7.06 at 170C 5.97 at 135C 6.04 at 170C 7.21 at 135C No Test
Note: K factor rated distribution dry-type transformers may have signicantly lower impedances.
150C Rise
300 500 750 1000 1500 2000 2500
750 750
80C Rise
300 500 750 1000 1500 2000 2500
CA08104001E
TOC
Index
June 2006
Sheet 0120
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
150C Rise
3 6 9 15 30 45 75 112.5 150 225 300 500 750 1000
65C Rise
112.5 150 225 300 500 750 1000 1500 2000 2500
115C Rise
15 30 45 75 112.5 150 225 300 500 750
150C Rise
300 500 750 1000 1500 2000 2500
80C Rise
300 500 750 1000 1500 2000 2500
80C Rise
15 30 45 75 112.5 150 225 300 500
Table 1.5-15. 600-Volt Primary Class Dry-Type Distribution Transformers NEMA TP-1 2002
kVA No Load Losses in Watts N.L. 15 30 45 75 112.5 150 225 300 500 80 100 170 230 360 480 565 730 1350 Full Load Losses in Watts Total 822 1674 1885 2534 3290 3552 6783 7477 8031 TP-1% Efciency at 75C and 35% Load Minimum Required 97 97.5 97.7 98 98.2 98.3 98.5 98.6 98.7
Note: Loss and efciency data shown are based on transformers that meet NEMA optional standard TP-1 2002 for energy savings. NEMA TP-1 establishes minimum operating efciencies for each transformer size at reduced loading equal to 35% of the transformer base kVA. The 35% loading value in the NEMA standard reects eld studies which show that installed dry-type transformers are actually loaded far below base kVA most of the time.
CA08104001E
June 2006
Sheet 0121
TOC
Index
1.5-13
Master TOC
Enclosures
The following are reproduced from NEMA 250. Table 1.5-17. Comparison of Specic Applications of Enclosures for Indoor Nonhazardous Locations
Provides a Degree of Protection Against the Following Environmental Conditions Incidental Contact with the Enclosed Equipment Falling Dirt Falling Liquids and Light Splashing Circulating Dust, Lint, Fibers, and Flyings Settling Airborne Dust, Lint, Fibers, and Flyings Hosedown and Splashing Water Oil and Coolant Seepage Oil or Coolant Spraying and Splashing Corrosive Agents Occasional Temporary Submersion Occasional Prolonged Submersion Type of Enclosures 1 2 4 4X 5 X X X X X X X X X X X X X X X X X X X X X X 6 X X X X X X X 6P X X X X X X X X X 12 X X X X X X 12K 13 X X X X X X X X X X X X X
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
These enclosures may be ventilated. These bers and ying are nonhazardous materials and are not considered the Class III type ignitable bers or combustible yings. For Class III type ignitable bers or combustible yings see the National Electrical Code, Article 500.
Table 1.5-18. Comparison of Specic Applications of Enclosures for Outdoor Nonhazardous Locations
Provides a Degree of Protection Against the Following Environmental Conditions Incidental Contact with the Enclosed Equipment Rain, Snow and Sleet Sleet Windblown Dust Hosedown Corrosive Agents Occasional Temporary Submersion Occasional Prolonged Submersion Type of Enclosures 3 3R 3S X X X X X X X X X 4 X X X X 4X X X X X X 6 X X X X X 6P X X X X X X X
These enclosures may be ventilated. External operating mechanisms are not required to be operable when the enclosure is ice covered. External operating mechanisms are operable when the enclosure is ice covered.
Table 1.5-19. Comparison of Specic Applications of Enclosures for Indoor Hazardous Locations
Provides a Degree of Protection Against Atmospheres Typically Containing (For Complete Listing, See NFPA 497M) Acetylene Hydrogen, Manufactured Gas Diethyl Ether, Ethylene, Cyclopropane Gasoline, Hexane, Butane, Naphtha, Propane, Acetone, Toluene, Isoprene Metal Dust Carbon Black, Coal Dust, Coke Dust Flour, Starch, Grain Dust Fibers, Flyings Methane with or without Coal Dust Class Enclosure Types 7 and 8, Class I Groups A I I I I II II X B X C X D X Enclosure Type 9, Class II Groups E X F X G X X 10 X
II III MSHA
For Class III type ignitable bers or combustible yings see the National Electrical Code, Article 500. Due to the characteristics of the gas, vapor, or dust, a product suitable for one Class or Group may not be suitable for another Class or Group unless so marked on the product.
Note: If the installation is outdoors and/or additional protection is required by Tables 1.5-17 and 1.5-18, a combination-type enclosure is required.
Note: The information provided on power equipment losses is generic data intended to be used for sizing of HVAC equipment.
CA08104001E
TOC
Index
June 2006
Sheet 0122
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
diameters, and the like. Therefore, data for medium voltage cables should be obtained from the manufacturer of the cable to be used.
For interlocked armored cable, use magnetic conduit data for steel armor and non-magnetic conduit data for aluminum armor.
2 2
Application Notes
Resistance and reactance are phaseto-neutral values, based on 60 Hz ac, 3-phase, 4-wire distribution, in ohms per 100 feet (30 m) of circuit length (not total conductor lengths). s Based upon conductivity of 100% for copper, 61% for aluminum. s Based on conductor temperatures of 75C. Reactance values will have negligible variation with temperature. Resistance of both copper and aluminum conductors will be approximately 5% lower at 60C or 5% higher at 90C. Data shown in tables may be used without signicant error between 60C and 90C.
s
Z = X +R s For busway impedance data, see Section 21 of this catalog. s For PF (power factor) values less than 1.0, the effective impedance Z e is calculated from Z e = R PF + X sin (arc cos PF)
s
For copper cable data, resistance based on tinned copper at 60 Hz; 600V and 5 kV nonshielded cable based on varnished cambric insulation; 5 kV shielded and 15 kV cable based on neoprene insulation. s For aluminum cable data, cable is cross-linked polyethylene insulated.
s
Table 1.5-20. 60 Hz Impedance Data for 3-Phase Copper Cable Circuits, in Approximate Ohms per 1000 Feet (305 m) at 75C (a) Three Single Conductors
Wire Size, AWG or kcmil 8 8 (Solid) 6 6 (Solid) 4 4 (Solid) 2 1 1/0 2/0 3/0 4/0 250 300 350 400 450 500 600 750 In Magnetic Duct 600 V and 5 kV Nonshielded R X Z .811 .786 .510 .496 .321 .312 .202 .160 .128 .102 .0805 .0640 .0552 .0464 .0378 .0356 .0322 .0294 .0257 .0216 .0754 .0754 .0685 .0685 .0632 .0632 .0585 .0570 .0540 .0533 .0519 .0497 .0495 .0493 .0491 .0490 .0480 .0466 .0463 .0495 .814 .790 .515 .501 .327 .318 .210 .170 .139 .115 .0958 .0810 .0742 .0677 .0617 .0606 .0578 .0551 .0530 .0495 5 kV Shielded and 15 kV R X Z .811 .786 .510 .496 .321 .312 .202 .160 .128 .103 .0814 .0650 .0557 .0473 .0386 .0362 .0328 .0300 .0264 .0223 .0860 .0860 .0796 .0796 .0742 .0742 .0685 .0675 .0635 .0630 .0605 .0583 .0570 .0564 .0562 .0548 .0538 .0526 .0516 .0497 .816 .791 .516 .502 .329 .321 .214 .174 .143 .121 .101 .0929 .0797 .0736 .0681 .0657 .0630 .0505 .0580 .0545 In Nonmagnetic Duct 600 V and 5 kV Nonshielded R X Z .811 .786 .510 .496 .321 .312 .202 .160 .127 .101 .0766 .0633 .0541 .0451 .0368 .0342 .0304 .0276 .0237 .0194 .0603 .0603 .0548 .0548 .0506 .0506 .0467 .0456 .0432 .0426 .0415 .0398 .0396 .0394 .0393 .0392 .0384 .0373 .0371 .0356 .813 .788 .513 .499 .325 .316 .207 .166 .134 .110 .0871 .0748 .0670 .0599 .0536 .0520 .0490 .0464 .0440 .0405 5 kV Shielded and 15 kV R X Z .811 .786 .510 .496 .321 .312 .202 .160 .128 .102 .0805 .0640 .0547 .0460 .0375 .0348 .0312 .0284 .0246 .0203 .0688 .0688 .0636 .0636 .0594 .0594 .0547 .0540 .0507 .0504 .0484 .0466 .0456 .0451 .0450 .0438 .0430 .0421 .0412 .0396 .814 .789 .514 .500 .326 .318 .209 .169 .138 .114 .0939 .0792 .0712 .0644 .0586 .0559 .0531 .0508 .0479 .0445
CA08104001E
June 2006
Sheet 0123
TOC
Index
1.5-15
Master TOC
Table 1.5-21. 60 Hz Impedance Data for 3-Phase Copper Cable Circuits, in Approximate Ohms per 1000 Feet (305 m) at 75C (b) Three Conductor Cable
Wire Size, AWG or kcmil 8 8 (Solid) 6 6 (Solid) 4 4 (Solid) 2 1 1/0 2/0 3/0 4/0 250 300 350 400 450 500 600 750 In Magnetic Duct and Steel Interlocked Armor 600 V and 5 kV Nonshielded 5 kV Shielded and 15 kV R X Z R X Z .811 .786 .510 .496 .321 .312 .202 .160 .128 .102 .0805 .0640 .0552 .0464 .0378 .0356 .0322 .0294 .0257 .0216 .0577 .0577 .0525 .0525 .0483 .0483 .0448 .0436 .0414 .0407 .0397 .0381 .0379 .0377 .0373 .0371 .0361 .0349 .0343 .0326 .813 .788 .513 .499 .325 .316 .207 .166 .135 .110 .0898 .0745 .0670 .0598 .0539 .0514 .0484 .0456 .0429 .0391 .811 .786 .510 .496 .321 .312 .202 .160 .128 .103 .0814 .0650 .0557 .0473 .0386 .0362 .0328 .0300 .0264 .0223 .0658 .0658 .0610 .0610 .0568 .0508 .0524 .0516 .0486 .0482 .0463 .0446 .0436 .0431 .0427 .0415 .0404 .0394 .0382 .0364 .814 .789 .514 .500 .326 .317 .209 .168 .137 .114 .0936 .0788 .0707 .0640 .0576 .0551 .0520 .0495 .0464 .0427 In Nonmagnetic Duct and Aluminum Interlocked Armor 600 V and 5 kV Nonshielded 5 kV Shielded and 15 kV R X Z R X Z .811 .786 .510 .496 .321 .312 .202 .160 .127 .101 .0766 .0633 .0541 .0451 .0368 .0342 .0304 .0276 .0237 .0197 .0503 .0503 .0457 .0457 .0422 .0422 .0390 .0380 .0360 .0355 .0346 .0332 .0330 .0329 .0328 .0327 .0320 .0311 .0309 .0297 .812 .787 .512 .498 .324 .315 .206 .164 .132 .107 .0841 .0715 .0634 .0559 .0492 .0475 .0441 .0416 .0389 .0355 .811 .786 .510 .496 .321 .312 .202 .160 .128 .102 .0805 .0640 .0547 .0460 .0375 .0348 .0312 .0284 .0246 .0203 .0574 .0574 .0531 .0531 .0495 .0495 .0457 .0450 .0423 .0420 .0403 .0389 .0380 .0376 .0375 .0366 .0359 .0351 .0344 .0332 .813 .788 .513 .499 .325 .316 .207 .166 .135 .110 .090 .0749 .0666 .0596 .0530 .0505 .0476 .0453 .0422 .0389
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Table 1.5-22. 60 Hz Impedance Data for 3-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 Feet (305 m) at 90C (a) Three Single Conductors
Wire Size, AWG or kcmil 6 4 2 1 1/0 2/0 3/0 4/0 250 300 350 400 500 600 700 750 1000 In Magnetic Duct 600 V and 5 kV Nonshielded R X Z .847 .532 .335 .265 .210 .167 .133 .106 .0896 .0750 .0644 .0568 .0459 .0388 .0338 .0318 .0252 .053 .050 .046 .048 .043 .041 .040 .039 .0384 .0375 .0369 .0364 .0355 .0359 .0350 .0341 .0341 .849 .534 .338 .269 .214 .172 .139 .113 .0975 .0839 .0742 .0675 .0580 .0529 .0487 .0466 .0424 5 kV Shielded and 15 kV R X Z .532 .335 .265 .210 .167 .132 .105 .0892 .0746 .0640 .0563 .0453 .0381 .0332 .0310 .0243 .068 .063 .059 .056 .055 .053 .051 .0495 .0479 .0468 .0459 .0444 .0431 .0423 .0419 .0414 .536 .341 .271 .217 .176 .142 .117 .102 .0887 .0793 .0726 .0634 .0575 .0538 .0521 .0480 In Nonmagnetic Duct 600 V and 5 kV Nonshielded R X Z .847 .532 .335 .265 .210 .167 .133 .105 .0894 .0746 .0640 .0563 .0453 .0381 .0330 .0309 .0239 .042 .040 .037 .035 .034 .033 .037 .031 .0307 .0300 .0245 .0291 .0284 .0287 .0280 .0273 .0273 .848 .534 .337 .267 .213 .170 .137 .109 .0945 .0804 .0705 .0634 .0535 .0477 .0433 .0412 .0363 5 kV Shielded and 15 kV R X Z .532 .335 .265 .210 .167 .132 .105 .0891 .0744 .0638 .0560 .0450 .0377 .0326 .0304 .0234 .054 .050 .047 .045 .044 .042 .041 .0396 .0383 .0374 .0367 .0355 .0345 .0338 .0335 .0331 .535 .339 .269 .215 .173 .139 .113 .0975 .0837 .0740 .0700 .0573 .0511 .0470 .0452 .0405
Table 1.5-23. 60 Hz Impedance Data for 3-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 Feet (305 m) at 90C (b) Three Conductor Cable
Wire Size, AWG or kcmil 6 4 2 1 1/0 2/0 3/0 4/0 250 300 350 400 500 600 700 750 1000 In Magnetic Duct and Steel Interlocked Armor 600 V and 5 kV Nonshielded 5 kV Shielded and 15 kV R X Z R X Z .847 .532 .335 .265 .210 .167 .133 .106 .0896 .0750 .0644 .0568 .0459 .0388 .0338 .0318 .0252 .053 .050 .046 .048 .043 .041 .040 .039 .0384 .0375 .0369 .0364 .0355 .0359 .0350 .0341 .0341 .849 .534 .338 .269 .214 .172 .139 .113 .0975 .0839 .0742 .0675 .0580 .0529 .0487 .0466 .0424 .335 .265 .210 .167 .133 .105 .0895 .0748 .0643 .0564 .0457 .0386 .0335 .0315 .0248 .056 .053 .050 .049 .048 .045 .0436 .0424 .0418 .0411 .0399 .0390 .0381 .0379 .0368 .340 .270 .216 .174 .141 .114 .100 .0860 .0767 .0700 .0607 .0549 .0507 .0493 .0444 In Nonmagnetic Duct and Aluminum Interlocked Armor 600 V and 5 kV Nonshielded 5 kV Shielded and 15 kV R X Z R X Z .847 .532 .335 .265 .210 .167 .133 .105 .0894 .0746 .0640 .0563 .0453 .0381 .0330 .0309 .0239 .042 .040 .037 .035 .034 .033 .037 .031 .0307 .0300 .0245 .0291 .0284 .0287 .0280 .0273 .0273 .848 .534 .337 .267 .213 .170 .137 .109 .0945 .0804 .0705 .0634 .0535 .0477 .0433 .0412 .0363 .335 .265 .210 .167 .132 .105 .0893 .0745 .0640 .0561 .0452 .0380 .0328 .0307 .0237 .045 .042 .040 .039 .038 .036 .0349 .0340 .0334 .0329 .0319 .0312 .0305 .0303 .0294 .338 .268 .214 .171 .138 .111 .0959 .0819 .0722 .0650 .0553 .0492 .0448 .0431 .0378
CA08104001E
TOC
Index
June 2006
Sheet 0124
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Current Carrying Capacities of Copper and Aluminum and Copper-Clad Aluminum Conductors From National Electrical Code (NEC), 2005 Edition (NFPA70-2005)
Table 1.5-24. Allowable Ampacities of Insulated Conductors Rated 0 2000 Volts, 60C to 90C (140F to 194F). Not more than three current-carrying conductors in raceway, cable or earth (directly buried), based on ambient temperature of 30C (86F)
Size AWG or kcmil Temperature Rating of Conductor (See Table 310.16) 60C (140F) Types TW, UF RHW, THHW, THW, THWN, XHHW, USE, ZW TBS, SA, SIS, FEP, FEPB, MI, RHH, RHW-2, THHN, THHW, THW-2, THWN-2, USE-2, XHH, XHHW, XHHW-2, ZW-2 75C (167F) 90C (194F) 60C (140F) Types TW, UF RHW, THHW, THW, THWN, XHHW, USE TBS, SA, SIS, THHN, THHW, THW-2, THWN-2, RHH, RHW-2, USE-2, XHH, XHHW, XHHW-2, ZW-2 75C (167F) 90C (194F) Size AWG or kcmil
Copper 18 16 14 12 10 8 6 4 3 2 1 1/0 2/0 3/0 4/0 250 300 350 400 500 600 700 750 800 900 1000 1250 1500 1750 2000 20 25 30 40 55 70 85 95 110 125 145 165 195 215 240 260 280 320 355 385 400 410 435 455 495 520 545 560 20 25 35 50 65 85 100 115 130 150 175 200 230 255 285 310 335 380 420 460 475 490 520 545 590 625 650 665 14 18 25 30 40 55 75 95 110 130 150 170 195 225 260 290 320 350 380 430 475 520 535 555 585 615 665 705 735 750
Aluminum or Copper-Clad Aluminum 20 25 30 40 55 65 75 85 100 115 130 150 170 190 210 225 260 285 310 320 330 355 375 405 435 455 470 20 30 40 50 65 75 90 100 120 135 155 180 205 230 250 270 310 340 375 385 395 425 445 485 520 545 560 25 35 45 60 75 85 100 115 135 150 175 205 230 255 280 305 350 385 420 435 450 480 500 545 585 615 630 12 10 8 6 4 3 2 1 1/0 2/0 3/0 4/0 250 300 350 400 500 600 700 750 800 900 1000 1250 1500 1750 2000 Ambient Temperature F 1.04 1.00 .96 .91 .87 .82 .76 .71 .58 .41 70 77 78 86 87 95 96 104 105 113 114 122 123 131 132 140 141 158 159 176
Correction Factors
Ambient Temperature C 21 25 26 30 31 35 36 40 41 45 46 50 51 55 56 60 61 70 71 80 For ambient temperatures other than 30C (86F), multiply the allowable ampacities shown above by the appropriate factor shown below. 1.08 1.00 .91 .82 .71 .58 .41 1.05 1.00 .94 .88 .82 .75 .67 .58 .33 1.04 1.00 .96 .91 .87 .82 .76 .71 .58 .41 1.08 1.00 .91 .82 .71 .58 .41 1.05 1.00 .94 .88 .82 .75 .67 .58 .33
Note: For complete details of using Table 1.5-24, see NEC Article 310 in its entirety.
CA08104001E
June 2006
Sheet 0125
TOC
Index
1.5-17
Master TOC
Ampacities for Conductors Rated 0 2000 Volts (Excerpts from NEC 310-15)
(A) General.
(1) Tables or Engineering Supervision. Ampacities for conductors shall be permitted to be determined by tables as provided in 310.15(B) or under engineering supervision, as provided in 310.15(C).
Note: FPN No. 1: Ampacities provided by this section do not take voltage drop into consideration. See 210.19(A), FPN No. 4, for branch circuits and 215.2(A), FPN No. 2, for feeders. Note: FPN No. 2: For the allowable ampacities of Type MTW wire, see Table 13.5.1 in NFPA 79-2002, Electrical Standard for Industrial Machinery.
(1) Each cable has not more than three current-carrying conductors. (2) The conductors are 12 AWG copper. (3) Not more than 20 current-carrying conductors are bundled, stacked, or supported on bridle rings. A 60 percent adjustment factor shall be applied where the current-carrying conductors in these cables that are stacked or bundled longer than 24 inches (600 mm) without maintaining spacing exceeds 20. (b) More Than One Conduit, Tube, or Raceway. Spacing between conduits, tubing, or raceways shall be maintained.
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Table 1.5-25. NEC (2005) Table 310.15(B)(2)(a) Adjustment Factors for More than Three CurrentCarrying Conductors in a Raceway or Cable
Number of Current-Carrying Conductors 46 79 10 20 21 30 31 40 41 and Above Percent of Values in Tables as Adjusted for Ambient Temperature if Necessary 80 70 50 45 40 35
(2) Selection of Ampacity. Where more than one calculated or tabulated ampacity could apply for a given circuit length, the lowest value shall be used. Exception: Where two different ampacities apply to adjacent portions of a circuit, the higher ampacity shall be permitted to be used beyond the point of transition, a distance equal to 10 feet (3.0 m) or 10 percent of the circuit length gured at the higher ampacity, whichever is less.
Note: FPN: See 110.14(C) for conductor temperature limitations due to termination provisions.
(B) Tables. Ampacities for conductors rated 0 to 2000 volts shall be as specied in the Allowable Ampacity Table 310.16 through Table 310.19, and Ampacity Table 310.20 and Table 310.21 as modied by (B)(1) through (B)(6).
Note: FPN: Table 310.16 through Table 310.19 are application tables for use in determining conductor sizes on loads calculated in accordance with Article 220. Allowable ampacities result from consideration of one or more of the following:
Exception No. 1: Where conductors of different systems, as provided in 300.3, are installed in a common raceway or cable, the derating factors shown in Table 1.5-25 shall apply only to the number of power and lighting conductors (Articles 210, 215, 220 and 230). Exception No. 2: For conductors installed in cable trays, the provisions of 392.11 shall apply. Exception No. 3: Derating factors shall not apply to conductors in nipples having a length not exceeding 24 inches (600 mm). Exception No. 4: Derating factors shall not apply to underground conductors entering or leaving an outdoor trench if those conductors have physical protection in the form of rigid metal conduit, intermediate metal conduit, or rigid nonmetallic conduit having a length not exceeding 3.05 m (10 ft) and if the number of conductors does not exceed four. Exception No. 5: Adjustment factors shall not apply to Type AC cable or to Type MC cable without an overall outer jacket under the following conditions:
For more information visit: www.EatonElectrical.com
(3) Bare or Covered Conductors. Where bare or covered conductors are used with insulated conductors, their allowable ampacities shall be limited to those permitted for the adjacent insulated conductors. (4) Neutral Conductor. (a) A neutral conductor that carries only the unbalanced current from other conductors of the same circuit shall not be required to be counted when applying the provisions of 310.15(B)(2)(a). (b) In a 3-wire circuit consisting of 2-phase wires and the neutral of a 4-wire, 3-phase, wye-connected system, a common conductor carries approximately the same current as the line-to-neutral load currents of the other conductors and shall be counted when applying the provisions of 310.15(B)(2)(a). (c) On a 4-wire, 3-phase wye circuit where the major portion of the load consists of nonlinear loads, harmonic currents are present in the neutral conductor; the neutral shall therefore be considered a currentcarrying conductor. (5) Grounding or Bonding Conductor. A grounding or bonding conductor shall not be counted when applying the provisions of 310.15(B)(2)(a).
(1) Temperature compatibility with connected equipment, especially the connection points. (2) Coordination with circuit and system overcurrent protection. (3) Compliance with the requirements of product listings or certications. See 110.3(B). (4) Preservation of the safety benets of established industry practices and standardized procedures.
CA08104001E
TOC
Index
June 2006
Sheet 0126
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11
I E 2 % eff pf I E % eff pf I E 3 % eff pf 746 746 746 For 2-phase, 3-wire circuits the current in the common conductor is 2 times that in either of the two other conductors.
Note: Units of measurement and denitions for E (volts), I (amperes), and other abbreviations are given below under Common Electrical Terms.
1. 1. From watthour meter. Watts = rpm of disc x 60 x Kh Where Kh is meter constant printed on face or nameplate of meter. If metering transformers are used, above must be multiplied by the transformer ratios. 2. Directly from wattmeter reading. Where: Volts = line-to-line voltage as measured by voltmeter. Amperes = current measured in line wire (not neutral) by ammeter. Table 1.5-27. Temperature Conversion
(F to C) (C to F) C -15 F 5 C 25 F 77 C 65 F 149 -10 14 30 86 -5 23 C = 5/9 (F-32) F = 9/5(C)+32 0 32 5 41 10 50 15 59 20 68 60 140 100 212
Kilovolt Amperes (kVA) = 1000 volt-amperes Watt (W) = unit of true power = VA pf = .00134 hp = 1000 watts = ratio of true to apparent power W kW = -------- ----------VA kVA = unit of electrical work = one watt for one hour = 3.413 Btu = 2,655 foot. lbs. = 1000 watthours = measure of time rate of doing work = equivalent of raising 33,000 lbs. one foot. in one minute = 746 watts = ratio of maximum demand to the total connected load = ratio of the sum of individual maximum demands of the various subdivisions of a system to the maximum demand of the whole system = ratio of the average load over a designated period of time to the peak load occurring in that period
Kilowatt (kW)
12 13 14 15 16 17 18 19 20 21
Watthour (Wh)
35 40 45 95 104 113
Load Factor
1 Inch = 2.54 centimeters 1 Kilogram = 2.20 lbs. 1 Square Inch = 1,273,200 circular mills 1 Circular Mill = .785 square mil 1 Btu = 778 foot. lbs. = 252 calories 1 Year = 8,760 hours
CA08104001E
June 2006
Sheet 0127
TOC
Index
1.5-19
Master TOC
Seismic Requirements
General
Starting more than 15 years ago, Eaton embarked on a comprehensive program centered around designing and building electrical distribution and control equipment capable of meeting and exceeding the seismic load requirements of the Uniform Building Code (UBC ) and California Building Code (CBC). The entire program has been updated to also meet the Year 2003 International Building Code (IBC) unied seismic requirements. These codes emphasize building design requirements. Electrical equipment and distribution system components are considered attachments to the building. The equipment is acceptable if it can withstand the seismic event and perform its function immediately afterwards. A cooperative effort with the equipment user, the building designer and the equipment installer ensures that the equipment is correctly mounted to a foundation that can withstand the effects of an earthquake. Cutler-Hammer electrical distribution and power control equipment has been tested and seismically proven for requirements exceeding the UBC, CBC and the IBC. Over one hundred different assemblies representing all product lines have been successfully tested and veried to seismic levels higher than the maximum seismic requirements specied in the UBC, CBC and the IBC. The equipment maintained structural integrity and demonstrated the ability to function before and immediately after the seismic tests. A technical paper, Earthquake Requirements and Cutler-Hammer Distribution and Control Equipment Seismic Capabilities (SA.125.01.S.E), provides a detailed explanation of the applicable seismic codes and the Cutler-Hammer program to qualify equipment. The paper may be found at www.EatonElectrical.com. Type in SA12501SE in document search.
i ii 1 2 3 4 5
Uniform Building Code Seismic Zones
0 1 2A 2B 3 4 Those areas within Zone 3 determined by the proximity to certain major faults
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No damage
Minor damage
Moderate damage
Moderate damage
Major damage
States is shown in Figure 1.5-1 (Figure 16-3 of the UBC, Chapter 16). Ca is taken equal to the maximum of 0.44 x 1.5 = 0.66. Ip: Is the Seismic Importance Factor (Table 16-K, page 2-30). It is taken as maximum and equal to 1.5. Wp: Is the Equipment Operating Weight. Therefore, the maximum theoretical static seismic loads (including all the conservatism possible) are: F p = 4.0 ( .44 1.5 ) 1.5 W p The codes state that the design lateral accelerations and resultant loads, determined above, are static loads to be distributed in proportion to the mass distribution of the element or component. Therefore, assuming a uniformly distributed mass, the static loads computed in the above formula are imposed at the C.G. or at conservatively one half the height of the equipment from its base. The complete Response Spectrum Curve starts at 0.33g at 1.0 Hz, linearly increases to 2.15g at 2.15 Hz (Ts ). The peak spectral accelerations then covers a wide band of frequencies up to 11 Hz (To) then gradually decreases to 0.86 g (ZPA) at 33 Hz. This curve represents the complete 1997 UBC Design Response Spectrum.
Where:
Ca: Is the Seismic Coefcient for Zone 4, Table 16-Q. It is equal to a maximum of 0.44 Na where Na is Near Source Factor and is equal to a maximum of 1.5 (see Table 16-S, page 2-35). The Seismic Zone Map of the United
CA08104001E For more information visit: www.EatonElectrical.com
TOC
Index
June 2006
Sheet 0128
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A. Ground Motion
According to the code, the rst and most important step in the process is to determine the Maximum Considered Earthquake Spectral Response Acceleration at short periods of 0.2 seconds (SS) and at a period of 1.0 second (S1). These values are determined from a set of 24 Spectral Acceleration Maps which include numerous contour lines indicating the severity of the earthquake requirements at a particular location in the country.
ANSI C37.81
The seismic requirements for Class 1E switchgear in nuclear power plants are dened in ANSI C37.81. Eaton elected to test the equipment to 2/3 of the nuclear requirements.
CA08104001E
June 2006
Sheet 0129
TOC
Index
1.5-21
Master TOC
The maps indicate low to moderate seismic requirements for the entire country, with the exception of two particular areas; the West Coast (the State of California) and the Midwest (the New Madrid areas). Areas with the seismic requirements at the New Madrid are approximately 40% higher than the maximum requirements of the West Coast. The Design Response Spectrum/ Spectral accelerations are equal to 0.68g at zero period (ZPA), increase linearly to a peak acceleration of 1.7g at 0.146 seconds (or 6.9 Hz) and stay constant to 0.73 seconds (or 1.37 Hz) then gradually decrease to 1.24g at 1 second (or 1 Hz).
i ii 1 2 3 4 5
Seismic Zones
0 1 2A 2B 3 4 Those areas within Zone 3 determined by the proximity to certain major faults
6 7 8 9
Bellcore Requirements
The Bellcore Generic Requirements (GR-63-CORE, Issue 1, dated 1995) for the Network Equipment-Building System (NEBS) (Reference 10), and the Physical Protection Section 5.4 of the code includes a map of the seismic zones (Figure 1.5-2), as well as a proposed Response Spectrum Curve for testing communication equipment. Descriptions of the test requirements and test levels of equipment are also included.
No damage
Minor damage
Moderate damage
Moderate damage
Major damage
Where:
Fp : Seismic design force imposed at the components C.G. and distributed relative to component mass distribution. Component amplication factor that varies from 1.00 to 2.50.
10 11 12 13 14 15 16 17 18 19 20 21
ap :
s s s
SDS: Spectral acceleration, short period, as determined in the previous section. Wp: Component operating weight. Rp: Component response modication factor that varies from 1.0 to 5.0. Ip : Z: Component importance factor that is either 1.0 or 1.5. Highest point of equipment in a structure relative to grade elevation. Average roof height of structure relative to grade elevation.
Z is taken equal to H (equipment on roof). Ip is taken equal to 1.5. Ap is taken equal to 2.5. Rp is taken equal to 2.5. SDS is equal to 1.7g as computed in previous section.
The acceleration at C.G. of equipment is then computed equal to: Acceleration = 0.4 x 2.5 x 1.7g (1 + 2) / (2.5/1.5) = 3.06g For equipment on grade, the acceleration at C.G. is then computed equal to: Acceleration = 0.4 x 2.5 x 1.7g (1 + 0) / (2.5 /1.5) = 1.02g The base forces associated with the static loads at the C.G. of the equipment could be computed as 3.06/1.5 = 2.04g. Finally ASCE7 Section 9.6.1.3 provides for FP is not required to be taken as greater than FP = 1.6 SDS IP WP When IP = 1.5
h:
CA08104001E
TOC
Index
June 2006
Sheet 0130
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14
To better compare all seismic levels and determine the nal envelope seismic requirements, the UBC, CBC, Y2K IBC for California, Y2K IBC for New Madrid area, and Bellcore nal seismic requirements are plotted in Figure 1.5-3. All curves are plotted at 5% damping. An envelopment of the seismic levels in the frequency range of 3.2 Hz to 100 Hz is also shown. This level is taken as Cutler-Hammer generic seismic test requirements for all certications. Eaton performed additional seismic test runs on the equipment at approximately 120% of the generic enveloping seismic requirements (see Figure 1.5-4). The testing is designed to establish additional margin and prepare for future changes in the codes.
10 9 8 7 6 5 4 3
Equiv. Bellcore
2
1.0 .9 .8 .7 .6 .5 .4 .3
.2
.1 1 2 3 4 5 6 7 8 9 10 10 2 3 4 5
Frequency Hz
6 7 8 9 10 100
6 7 8 9 10 1000
Acceleration (g peak)
1.0 .9 .8 .7 .6 .5 .4 .3
.2
.1
15 16 17 18 19 20 21
6 7 8 9 10 10
Frequency Hz
6 7 8 9 10 100
6 7 8 9 10 1000
CA08104001E
June 2006
Sheet 0131
TOC
Index
1.5-23
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13
Figure 1.5-5. Sample Seismic Certicate
Cutler-Hammer is a federally registered trademark of Eaton Corporation. National Electrical Code and NEC are registered trademarks of the National Fire Protection Association, Quincy, Mass. NEMA is the registered trademark and service mark of the National Electrical Manufacturers Association. UL and CUL are federally registered trademarks of Underwriters Laboratories Inc. Uniform Building Code (UBC) is a trademark of the International Conference or Building Ofcials (ICBO). BOCA is a registered trademark of Building Ofcials and Code Administrators International, Inc. SBCCI is a registered trademark of Southern Building Code Congress International.
14 15 16 17 18 19
20 21
CA08104001E
June 2006
Sheet 0132
Master TOC
i ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CA08104001E