Truss Install
Truss Install
;
˜12"
One
brace
requir
ed on
each
of the
se tw
o webs
.
i
BCSI 1-03
BCSI 1-03
GUIDE TO GOOD PRACTICE
FOR HANDLING, INSTALLING & BRACING
OF METAL PLATE CONNECTED
WOOD TRUSSES
JOINTLY PRODUCED BY
WOOD TRUSS COUNCIL OF AMERICA
AND
TRUSS PLATE INSTITUTE
PUBLISHED - OCTOBER 1, 2003
EFFECTIVE DATE
01/01/04
Copyright © 2003
WOOD TRUSS COUNCIL OF AMERICA
and TRUSS PLATE INSTITUTE
All rights reserved. This book or any part thereof
may not be reproduced in any form without the
written permission of the publisher.
Printed in the United States of America.
iii
BCSI 1-03
ACKNOWLEDGEMENTS
The thoughts, ideas and hard work of many have brought the
Building Component Safety Information (BCSI 1-03) document to
press.
Special thanks to WTCA's membership in its entirety for perspec-
tive and feedback in guiding the creation of this work, under the
leadership of Scott Arquilla, WTCA 2003 President; Mike Ruede,
Immediate Past President; Dan Holland, President Elect; and
Kendall Hoyd, Secretary. Special thanks are also due to each of
the TPI Member Companies: Alpine Engineered Products,
Cherokee Metal Products, CompuTrus, Eagle Metal Products,
MiTek Industries, Robbins Manufacturing Company, TeeLok
Corporation, and Truswal Systems Corporation, and in particular
TPI's President Charles C. Hoover, Jr., P.E., for his leadership in
creating the cooperative spirit that is the key to any successful
endeavor where two organizations are involved in a project as
substantial as this.
Certain individuals have been especially dedicated to making this
document possible: Scott Arquilla, Clyde Bartlett, David
Brakeman, Steve Cabler, Steve Cramer, Bob Dayhoff, Dave
Denoncourt, James Gingrich, Kirk Grundahl, Kelly Gutting, Joe
Heinsman, Dan Holland, Ted Kolanko, Mike Kozlowski, Stu Lewis,
Mike Magid, John Meeks, Joe Michels, Carl Schoening, Marvin
Strzyzewski, Gary Sweatt, and Ken Watters II.
WTCA would like to thank those who serve on its Engineering &
Technology and Marketing Committees, and TPI would like to
thank those who serve on its Technical Advisory Committee
(TAC) for their continued dedication to advancing our industry's
work on safety and technology.
Finally, a key thank you must go to those that tended to all the
details in the background, without which this document would not
yet be completed. This group includes Dave Brakeman, TPI-TAC
Chairman; Kelly Gutting, TPI Technical Director; Ryan Dexter,
Lora Gilardi, Libby Maurer, Anita Meredith, Stan Sias, Rachel
Smith, Barb Speer, and Richard Zimmermann, of WTCA staff.
iv
CONTENTS
v
CONTENTS
vi
CONTENTS
SCREWS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .88
BOLTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .89
BCSI-B10 POST FRAME TRUSS INSTALLATION AND BRACING . . . 91
GENERAL WARNING NOTES . . . . . . . . . . . . . . . . . . . . . . . . . . . .91
MECHANICAL INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . .93
IMPORTANT NOTES ON LIMITATIONS . . . . . . . . . . . . . . . . . . . .95
TEMPORARY BRACING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .96
STABLE BASE UNIT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .97
BRACING THE BASE UNIT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .99
TEMPORARY TOP CHORD LATERAL BRACING SCHEDULE . . .100
TOP CHORD LATERAL BRACING . . . . . . . . . . . . . . . . . . . . . . . .101
BOTTOM CHORD BRACING . . . . . . . . . . . . . . . . . . . . . . . . . . . .102
TOP CHORD DIAGONAL BRACING . . . . . . . . . . . . . . . . . . . . . .103
WEB MEMBER BRACING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .104
WARNINGS AND RESPONSIBILITIES . . . . . . . . . . . . . . . . . . . .105
BCSI-B11 FALL PROTECTION AND WOOD TRUSSES . . . . . . . . . . 107
GENERAL NOTES AND RESOURCE INFORMATION . . . . . . . . . .107
FALL PROTECTION DOS AND DON’TS . . . . . . . . . . . . . . . . . . .108
SAFE INSTALLATION OPTIONS . . . . . . . . . . . . . . . . . . . . . . . . .110
WARNING SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .110
GLOSSARY OF TERMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
REFERENCED INDUSTRY ASSOCIATIONS AND
GOVERNMENTAL AGENCIES . . . . . . . . . . . . . . . . . . . . . . . . . . 129
REFERENCED INDUSTRY STANDARDS, GUIDELINES
AND RECOMMENDATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
SUPPLEMENTAL INFORMATION TAGS . . . . . . . . . . . . . . . . . . . . . .135
QUICK REFERENCE TO BCSI-B SERIES DOCUMENTS . . .BACK COVER
vii
CONTENTS
viii
BCSI 1-03
INTRODUCTION
PUBLICATIONS BACKGROUND
The WTCA and TPI have developed the BCSI 1-03 booklet to
replace the HIB-91, Commentary and Recommendations for
Handling, Installing and Bracing Metal Plate Connected Wood
Trusses. The BCSI 1-03 booklet was developed using DSB-89,
Recommended Design Specification for Temporary Bracing of
Metal Plate Connected Wood Trusses; HIB-91; HIB-91 (Summary
Sheet); HIB-98, Recommendations for Handling, Installing and
Temporary Bracing of Metal Plate Connected Wood Trusses
Used in Post-Frame Construction; and several existing bracing,
warning and safety documents (for a complete list, see refer-
ences on page 131-134). The consistent message throughout all
of these documents is that proper truss handling, installing and
bracing are crucial for consistent jobsite safety and acceptable
structural performance. More information regarding the design
and manufacturing of metal plate connected wood trusses can be
found in ANSI/TPI 1-2002, National Design Standard for Metal
Plate Connected Wood Trusses.
ix
BCSI 1-03
x
BCSI 1-03
xi
BCSI 1-03
xii
BCSI-B1
BCSI-B1
GUIDE FOR HANDLING, INSTALLING
AND BRACING OF METAL PLATE
CONNECTED WOOD TRUSSES
GENERAL NOTES
Familiarity with the Building Structural System Design
Documents (BSSDD), Truss Design Drawings (TDD),
Truss Placement Diagrams (if/when required by the
BSSDD), this BCSI document and specific site conditions
is required to properly receive, store, erect, brace and
connect the trusses to the building system.
All of the care and quality involved in the design and
manufacture of wood trusses can be jeopardized if the
trusses are not properly handled, erected, and braced.
PHOTO B1-1
1
BCSI-B1
FIGURE B1-1
2
BCSI-B1
3
BCSI-B1
JOBSITE HANDLING
PHOTO B1-4
PHOTO B1-5
PHOTO B1-6
5
BCSI-B1
HAND ERECTION
FIGURE B1-6
FIGURE B1-7
10' 10'
10'
.
ax
3"m
10'
.
ax
FIGURE B1-8
3"m
20'
.
ax
6"m
HOISTING
FIGURE B1-9
7
BCSI-B1
FIGURE B1-10A
60° or less
Approx. 1/2
truss length
Tagline
For trusses up to 30'
FIGURE B1-10B
60° or less
Approx. 1/2
truss length
Tagline
For trusses up to 30'
Spreader bar
Toe-in Toe-in
8
BCSI-B1
FIGURE B1-12
Spreader bar
Toe-in Toe-in
FIGURE B1-13
Locate Spreader bar
10' o.c.
above or stiffback
max.
mid-height
FIGURE B1-14
Spreader bar
or stiffback 10' o.c.
max.
9
BCSI-B1
45°
FIGURE B1-16
FIGURE B1-17
FIGURE B1-18
Ground brace
diagonals
Ground brace strut
End brace
First floor
Second floor
Second floor system must have adequate capacity to support ground braces
11
BCSI-B1
Out of Plumb
D/50 D (ft.)
1/4" 1'
Depth, D
BRACING WARNINGS
DIAGONAL BRACING IS
VERY IMPORTANT!
FIGURE B1-21
FIGURE B1-22
DIAGONAL BRACING IS
VERY IMPORTANT!
SEE BCSI-B2 TRUSS INSTALLATION AND
TEMPORARY BRACING (PAGES 21-50) FOR
ADDITIONAL BRACING OPTIONS.
13
BCSI-B1
FIGURE B1-24
|45°
*Spacing of temporary
continuous lateral bracing 10 truss spaces
per Table B1-4 (20' max)
This top chord bracing approach applies to all sloping chord trusses,
scissors trusses and 2x_ parallel chord trusses.
FIGURE B1-25
Continuous lateral bracing
Diagonal bracing
Bottom
chord
FIGURE B1-26
2x4x12' length lapped
over two trusses.
Bottom chords
Repeat diagonals
every 10 truss
*10'-15' spaces (20' max)
max
This bracing approach apples to all truss types except 3x2 and
4x2 parallel chord trusses.
15
BCSI-B1
ery
g ev Web members
n )
ci ax
bra 20' m
FIGURE B1-28
a l
on s(
d iag pace
at ss s
pe
Re 0 tru
1
Bottom
chords
16
BCSI-B1
DIAGONAL BRACING IS
VERY IMPORTANT!
SEE BCSI-B2 TRUSS INSTALLATION AND
TEMPORARY BRACING (PAGES 21-50)
FOR ADDITIONAL BRACING OPTIONS.
Ribbon Board
FIGURE B1-31
17
BCSI-B1
CONSTRUCTION LOADING
FIGURE B1-33
FIGURE B1-34
FIGURE B1-35
Cantilever
18
BCSI-B1
FIGURE B1-36
FIGURE B1-37
FIGURE B1-39
19
BCSI-B1
CAUTION NOTES
20
BCSI-B2
BCSI-B2
TRUSS INSTALLATION
AND TEMPORARY BRACING
21
BCSI-B2
PHOTO B2-1
PHOTO B2-2
22
BCSI-B2
; 4. Are the tops of all bearing walls flat, level and at the
same elevation? Are the walls straight in their length,
and parallel where they should be parallel? Uneven
bearing surfaces are a major cause of truss uneven-
ness, and may cause costly delays and/or repairs.
Check and correct bearing wall deficiencies prior to
starting the truss erection process.
23
BCSI-B2
; 10. Is the roof a hip style? Can the crane lift and hold
the girder truss while the end jacks are installed to
brace the girder? This could eliminate the need for
ground bracing the first truss assuming all hardware
and hangers are installed prior to the crane releasing
the girder. Sheathing this assembly would assure a
rigid framework to which subsequent trusses could be
braced.
24
BCSI-B2
Exterior
; STEP 3. Set first truss (or gable end frame) and fas-
ten securely to ground braces using minimum 2-16d
(0.135x3.5'') nails clinched at each junction, and to
the wall, or as directed by the Building Designer.
25
FIGURE B2-3 - EXTERIOR GROUND BRACING TO FIRST TRUSS INSTALLED (SEE GROUND BRACING PAGE 117)
Typical attachment of
Typical attachment
vertical, diagonal and lateral
of vertical brace
braces to truss First truss (or gable to end wall
Ground brace diagonal end frame) of braced
group of trusses Blocking
Ground brace
Lateral diagonal
brace
Ground brace
vertical
26
BCSI-B2
Truss Ground
brace
Driven ground lateral
Ground brace vertical
stake End wall
Side View Elevation View Strut
Ground brace vertical
Backup ground
NOTE! BRACING MATERIAL MUST BE
stake End brace Side Elevation
MIN. 2X4 STRESS-GRADED LUMBER
Horizontal tie member View View
CONNECTED WITH MIN. 2-16D
(0.135x3.5") NAILS AT EACH JUNCTION. with multiple stakes
FIGURE B2-4 - INTERIOR GROUND BRACING TO FIRST TRUSS INSTALLED (SEE GROUND BRACING PAGE 117)
Typical attachment of
vertical, diagonal and lateral
braces to truss
First truss of
Ground brace diagonal
braced group of
trusses
Lateral
brace Ground brace
vertical
27
Ground brace
BCSI-B2
diagonal
End brace
Truss
FIGURE B2-5
28
BCSI-B2
29
BCSI-B2
FIGURE B2-6
Truss Span
Truss span
Bearing wall Bearing wall
Ground brace typical
FIGURE B2-7 ” 12
6’-2 6
” 18’-
6’-2 6”
”
6’-2
33’-0” Span
The 33' truss above will require TCTLB at not more than 8'
on-center per Table B2-1. Measure the top chord length
from the peak to truss heel. The sloping length will be
roughly 18'-6". One TCTLB would divide the 18'-6" in half,
or two sections. Half of 18'-6" is 9'-3" which exceeds the 8'
on-center maximum in Table B2-1. Therefore, the chord
segment needs to be divided into three sections 18'-6''÷3
= 6'-2''. TCTLB will be 6'-2'' on-center along the slope.
30
BCSI-B2
10" or greater
Truss attachment
required at support(s)
FIGURE B2-9 *
Under 8’ Over 8’ (add
add aabrace
brace)
= Pitch break
*
* * * *
5’-6” 5’-6” 5’-6” 8’-10” 3’-4” 4’-4”
33’-0” Span
FIGURE B2-10
31
BCSI-B2
10'
o.c. 8' o
max .c. m
.* ax.*
|45°
Trus Typical
s spa
ns u up t
p to o 45
30' '
Flat Truss
FIGURE B2-12
Gambrel Truss
FIGURE B2-13
32
BCSI-B2
FIGURE B2-11
4' o
.c. m
6' o ax.*
.c. m
ax.*
up t
o 80
up t '
o 60
'
Mono Truss
FIGURE B2-14
Scissors Truss
FIGURE B2-15
33
BCSI-B2
; Set up the ground bracing for the first truss from the
building interior or exterior.
34
BCSI-B2
X Truss height
FIGURE B2-19
35
BCSI-B2
FIGURE B2-20
FIGURE B2-21
FIGURE B2-22
36
BCSI-B2
22½''
27''+
1½'' minimum
end distance 22½''
Use of longer spacers
will reduce splitting potential.
Do not use split spacer pieces.
22½''
Use 2-16d
deformed shank
nails minimum at
each spacer to
truss connection.
Do not use split spacer pieces.
22½''
FIGURE B2-26
FIGURE B2-27
PHOTO B2-4
PHOTO B2-5
38
BCSI-B2
FIGURE B2-28
FIGURE B2-29
FIGURE B2-30
39
BCSI-B2
40
BCSI-B2
ery
g ev ) Web members
in x
rac ma
a l b (20'
n es
go
t dia spac
a
pe uss
Re 10 tr
Bottom
chords
41
BCSI-B2
FIGURE B2-33
Approx. 45°
42
BCSI-B2
Diagonal bracing
required at each
FIGURE B2-34
end of truss row
and every 10 truss
spaces.
10 truss
spaces max.
4 truss spaces max.
10 truss
spaces max.
˜12"
FIGURE B2-35
43
BCSI-B2
FIGURE B2-36
Temporary diagonal
bracing repeated entire
See details page 37. length of building.
44
BCSI-B2
PHOTO B2-8
45
BCSI-B2
46
BCSI-B2
Field splices
Temporary scaffold
47
BCSI-B2
FIGURE B2-39
48
BCSI-B2
FIGURE B2-40
49
BCSI-B2
50
BCSI-B3
BCSI-B3
WEB MEMBER PERMANENT
BRACING/WEB REINFORCEMENT
FIGURE B3-1
51
BCSI-B3
FIGURE B3-2
One brace
required on
this web
Two braces
required on
this web
FIGURE B3-3
52
BCSI-B3
FIGURE B3-4
FIGURE B3-5
Note: Some
chord and web
members not
shown, for clarity.
Always Diagonally Brace the
Permanent Continuous Lateral Bracing!
FIGURE B3-6
53
BCSI-B3
Truss member
Truss member
Reinforcement
FIGURE B3-8
on one edge
54
BCSI-B3
Truss member
FIGURE B3-9
FIGURE B3-10
55
BCSI-B3
Specially
designed metal
reinforcement
FIGURE B3-11
Truss member
Stacked web
reinforcement
plated to truss
member
FIGURE B3-12
Truss member
56
BCSI-B4
BCSI-B4
CONSTRUCTION LOADING
; DO stack a reasonable
amount of material that
will not overload the FIGURE B4-1
trusses.
57
BCSI-B4
FIGURE B4-2
; DO stack materials
along outside supports
or directly over inside
supports of properly
braced structures.
FIGURE B4-4
FIGURE B4-5
58
BCSI-B4
FIGURE B4-7
PHOTO B4-1
FIGURE B4-8
FIGURE B4-9
cantilever
WARNING! Stacking excessive construction loads on
floor or roof trusses is an unsafe act. Failure to follow
these recommendations could lead to property dam-
age, or worse, serious personal injury or death.
59
BCSI-B4
60
BCSI-B5
BCSI-B5
TRUSS DAMAGE, JOBSITE MODIFICATIONS
AND INSTALLATION ERRORS
FIGURE B5-1
PHOTO B5-2
Do not cut truss webs. This condition needs a repair.
61
BCSI-B5
62
BCSI-B5
FIGURE B5-2
Cracked web
Damaged plate
FIGURE B5-3
; Truss ID mark.
63
BCSI-B5
PHOTO B5-2
FIGURE B5-4
64
BCSI-B6
BCSI-B6
GABLE END FRAME BRACING
FIGURE B6-2
65
BCSI-B6
Exposure
distance to terrain obstructions
Ridge
½h
h
Mean ½h
Roof
Eave
Height
Ground
d
ee
Sp
d
in
W
FIGURE B6-3
L E O N LY
SAMP
FIGURE B6-4
67
BCSI-B6
FIGURE B6-5
68
BCSI-B6
Roof diaphragm
Gable end frame
WIND
FORCE
Sheathing
Ceiling diaphragm
End wall
FIGURE B6-6
HIGH Excessive
WIND bow in gable
FORCE end frame
Connection failure
between top of
wall and bottom of Ceiling and finish cracking and
gable end frame related serviceablity issues (i.e.
construction defects).
FIGURE B6-7
69
BCSI-B6
FIGURE B6-8
T-reinforcement
L-reinforcement
Scab reinforcement
on one face
FIGURE B6-9
Truss member
70
BCSI-B6
Gable end
Roof
diaphragm
blocking
Horizontal L
reinforcement
71
BCSI-B6
BLOCK BETWEEN
OUTLOOKERS.
FASTEN TO GABLE TOP
CHORD W/ 10d TOE-NAILS
@ 8" O.C.
GABLE TOP CHORD
2X4 NO.2 SYP X-BRACING L-BRACE ON GABLE VERTS
AT MID-SPAN AND AT 48" AS SPECIFIED BY TRUSS
O.C. RUN BACK 8' FROM MANUFACTURER.
GABLE. ATTACH TO
GABLE AND TRUSS
GABLE TRUSS
VERTICALS W/(3) 16d.
IF VERTICAL IS NOT PRESENT,
SCAB FULL HEIGHT VERTICAL
FROM BOTTOM CHORD TO
TOP CHORD W/(4) 10d EACH
END. (TYP)
FIGURE B6-13
72
FIGURE B6-14
NOTE! ALL BRACING MATERIAL MUST BE A ;
MINIMUM OF 2x4 STRESS-GRADED LUM-
BER (AS SPECIFIED BY THE TDD OR
BUILDING DESIGNER).
73
BCSI-B6
LEGEND:
Diagonal bracing
74
BCSI-B7
BCSI-B7
TEMPORARY AND PERMANENT BRACING
FOR PARALLEL CHORD TRUSSES
75
BCSI-B7
FIGURE B7-4
FIGURE B7-5
FIGURE B7-6
76
BCSI-B7
Rim board
FIGURE B7-10
FIGURE B7-11
FIGURE B7-12
FIGURE B7-13
78
BCSI-B7
FIGURE B7-14
CONSTRUCTION LOADING
FIGURE B7-15
FIGURE B7-16
79
BCSI-B7
80
BCSI-B8
BCSI-B8
TOE-NAILING FOR UPLIFT REACTIONS
FIGURE B8-1
FIGURE B8-2
INSTALLATION GUIDELINES
81
BCSI-B8
; 1. Proper Installation
To get the most out of a toe-nailed connection, it is
important to toe-nail correctly. The figure below illus-
trates proper toe-nailing. The dimensions shown are
only meant to serve as a rough guide. Toe-nailing
through truss plates does not affect the uplift capaci-
ty of the connection provided the truss plate is not
damaged during installation.
FIGURE B8-4
30°
; 3. Type of Nails
The type of nail used in a toe-nailed connection also
influences its uplift capacity. When installing toe-nails,
use care to avoid splitting of bottom chord lumber.
The Building Designer should provide nail spacing
and minimum end and edge distances. In lieu of such
guidance, a rule-of-thumb is to limit the total number
of toe-nails to three for a 2x4 top plate and five for a
2x6 top plate.
82
BCSI-B8
FIGURE B8-6
FIGURE B8-7
FIGURE B8-8
TYPICAL
LOAD DURATION CD
DESIGN LOAD
Permanent 0.9 Dead Loads
10 Years (Normal) 1.0 Floor Live Loads
2 Months 1.15 Snow Loads
7 Days 1.25 Construction Loads
10 Minutes/Impact 1.33/1.6* Wind/Earthquake
*Check with local code. TABLE B8-2
84
BCSI-B9
BCSI-B9
MULTI-PLY GIRDERS
PHOTO B9-1
85
BCSI-B9
; Check the TDD for the nailing schedule for each multi-
ply girder.
For example, the nailing schedule for this three-ply
girder is:
FIGURE B9-1
86
BCSI-B9
Spreader bar/stiffback
THI
S IS
NOT A SING
AS
A MU
TO
BE LE PLY
LTI-
USED
PLY
TRU
SS
RE
HE
E
AT
PL
FIGURE B9-2
FIGURE B9-3
87
BCSI-B9
FASTENER GUIDELINES
NAIL FASTENERS
FIGURE B9-4
Girder trusses up to three plies can be fastened together with
nails. Nail each additional ply with the specified schedule.
SCREW FASTENERS
Install per screw manufacturer and Truss Designer require-
ments and specifications.
FIGURE B9-8
FIGURE B9-13
FIGURE B9-11
FIGURE B9-12
BOLT FASTENERS
FIGURE B9-16
FIGURE B9-17 FIGURE B9-18
90
BCSI-B10
BCSI-B10
POST FRAME TRUSS INSTALLATION
AND BRACING
Recommendations for Handling, Installing and
Temporary Bracing of Metal Plate Connected Wood
Trusses in Post-Frame Construction
PHOTO B10-1
TRUSS STORAGE
FIGURE B10-1
91
BCSI-B10
FIGURE B10-2
92
BCSI-B10
FIGURE B10-4
MECHANICAL INSTALLATION
FIGURE B10-5
93
BCSI-B10
60° or less
Approx. 1/2
truss length
Tagline
For trusses up to 30'
TRUSSES UP TO 60'
FIGURE B10-7
Spreader bar
Toe-in Toe-in
95
BCSI-B10
Figure A Bracing
Diagonal Wall-Ground
FIGURE A (B10-9)
(Diagonal Wall Ground Bracing)
96
BCSI-B10
Figure
Column C
Connection
(Column Connection)
FIGURE C (B10-11)
97
BCSI-B10
8'
16d nails
Column-Truss Bracing
FIGURE D (B10-12)
base unit
PURLINS, TRUSS WEB BRACING & SOME NAILERS
OMITTED FOR CLARITY, SEE SECTION 3 FOR
BRACING REQUIREMENTS!!
Column Chaining
FIGURE E (B10-13)
98
BCSI-B10
Figure F
End Wall Chaining
(End Wall Chaining)
FIGURE F (B10-14)
2x6 n/a n/a 62' n/a 25' 81' n/a 42' 81'
2x8 n/a 27' 81' n/a 43' 81' 22' 61' 81'
2x10 n/a 40' 81' 24' 57' 81' 35' 78' 81'
2x12 21' 53' 81' 34' 74' 81' 48' 81' 81'
TABLE 1, (B10-1)
100
BCSI-B10
101
BCSI-B10
Top
Top Chord
chord temporary braces
Section A-A Cemporary B races
Bottom Chord
Temporary braces
A A
bay
Truss bay
bay
102
BCSI-B10
o
45
typical
Di
ag
on
ridge
Trusses
al
Br
length of building
a cin
g
purlins
Top view of the roof
Note: Diagonal braces run to the fourth truss on 48' & wider build-
ings. Braces lap two purlins if diagonal brace is spliced. Use 2-16d
(0.135x3.5") nails at each diagonal brace to purlin connection.
Diagonal Wood Bracing
FIGURE J B10-18
o
45
typical strapping
length of building
ridge
Trusses bay
bay
purlins
top view of the roof
Note: Metal strap cross bracing is typically used when purlins are
mounted flush between trusses.
103
BCSI-B10
Figure L
Cross Bracing
FIGURE L (B10-20)
(Cross Bracing)
4. ERECT THE ADDITIONAL ROOF TRUSSES
4.1 Install top chord temporary bracing at the spac-
ings indicated in Table 1, B10-1.
4.2 Install bottom chord temporary bracing as indi-
cated in Figure I, B10-17.
4.3 Provide additional diagonal temporary bracing in
the plane of the top chord approximately equal to
the bracing described in 3.4 at intervals not to
exceed 100' or 12 truss spaces, whichever is
less.
104
BCSI-B10
WARNINGS
AND RESPONSIBILITIES
It is the responsibility of the Erection/Installation Contractor
to properly receive, unload, store, handle, install, and
brace metal plate connected wood trusses to protect life
and property. The Erection/Installation Contractor must
exercise the same high degree of safety awareness as
with any other structural material. It is the responsibility of
the Erection/Installation Contractor to determine if the
installation crew has the needed equipment and training to
safely erect the proposed roof construction, and to deter-
mine that the trusses to be installed are undamaged.
Temporary bracing schedules in Table 1, B10-1 were
developed for an assumed load of the truss weight, plus
two workers and their equipment at a given time assumed
to weigh 250 lbs. each. Bracing schedules do not provide
for wind loads or for accidental overload, materials
stacked on trusses during erection, or loads due to misuse
or negligence.
These recommendations are based upon the collective
experience of leading technical personnel in the wood
truss and post frame industry, but must, due to the nature
of responsibilities involved, be presented only as a guide
for use by a qualified Building Designer or Erection/
Installation Contractor. It is not intended that these recom-
mendations be interpreted as superior to the project
Architect's or Engineer's design specification for handling,
installing and bracing wood trusses and it does not pre-
clude the use of other equivalent methods for bracing and
providing stability for the walls and columns as may be
determined by the Contractor. Thus, WTCA and TPI
expressly disclaim any responsibility for damages arising
from the use, application, or reliance on the recommenda-
tions and information contained herein.
105
BCSI-B10
106
BCSI-B11
BCSI-B11
FALL PROTECTION AND WOOD TRUSSES
107
BCSI-B11
WARNING!
Use of a single truss
as anchorage point
for any type of personal
fall arrest system
IS DANGEROUS
DANGER
PHOTO B11-1
108
BCSI-B11
PHOTO B11-2
FIGURE B11-4
FIGURE B11-5
FIGURE B11-6
109
BCSI-B11
; Option 1: Scaffolding
Use a scaffolding system with personal fall arrest sys-
tem, following OSHA’s guidelines.
FIGURE B11-7
FIGURE B11-8
110
BCSI-B11
! WARNING SUMMARY:
! A single truss is NOT designed to withstand loads
from a falling person.
PHOTO B11-7
112
GLOSSARY OF TERMS
113
GLOSSARY OF TERMS
114
GLOSSARY OF TERMS
116
GLOSSARY OF TERMS
119
GLOSSARY OF TERMS
120
GLOSSARY OF TERMS
121
GLOSSARY OF TERMS
122
GLOSSARY OF TERMS
123
GLOSSARY OF TERMS
124
GLOSSARY OF TERMS
125
GLOSSARY OF TERMS
127
GLOSSARY OF TERMS
128
REFERENCE
INDUSTRY ASSOCIATIONS
AND GOVERNMENTAL AGENCIES
AF&PA/American Wood Council
1111 19th St NW Ste 800 • Washington, DC 20036
202/463-4713 • 202/463-2791 fax
www.awc.org
American Institute of Architects (AIA)
1735 New York Ave NW • Washington, DC 20006-5292
202/626-7300 • 202/626-7547 fax
www.aia.org
American National Standards Institute (ANSI)
11 W 42nd St • New York, NY 10036
212/642-4900 • 212/398-0023 fax
www.ansi.org
American Society of Agricultural Engineers (ASAE)
2950 Niles Rd • St Joseph, MI 49085-9659
616/429-0300 • 616/429-3852 fax
www.asae.org
American Society of Civil Engineers (ASCE)
1801 Alexander Bell Dr • Reston, VA 20191
703/295-6000 • 703/295-6333 fax
www.asce.org
Association of Crane & Rigging Professionals
P.O. Box 87907 • Vancouver, WA 98687-7907
800-690-3921 • Voice: 360-834-3805 • 360-834-3507 fax
www.arcp.net
National Association of Home Builders (NAHB)
15th & M St NW • Washington, DC 20005
202/822-0401 • 202/822-0374 fax
www.nahb.org
National Frame Builders Association (NFBA)
4840 W 15th St Ste 1000 • Lawrence, KS 66049-3876
800/557-6957 • 785/843-7555 fax
www.nfba.org
Occupational Safety and Health Administration (OSHA)
US Department of Labor
200 Constitution Ave NW • Washington, DC 20210
202/523-1452 • 202/523-3573 fax
www.osha.gov
Truss Plate Institute (TPI)
583 D'Onofrio Dr Ste 200 • Madison, WI 53719
608/833-5900 • 608/833-4360 fax
www.tpinst.org
129
REFERENCE
130
REFERENCE
131
REFERENCE
132
REFERENCE
133
REFERENCE
134
REFERENCE
135
REFERENCE
136
IMPORTANT SAFETY INFORMATION