2011 ASAP Annual Report
2011 ASAP Annual Report
Pursuant to Section 106(b) of the National Aeronautics and Space Administration Authorization Act of 2005 (P.L. 109-155),
the Aerospace Safety Advisory Panel (ASAP) is pleased to submit the ASAP Annual Report for 2011 to the U.S. Congress
and to the Administrator of the National Aeronautics and Space Administration (NASA).
This report is based on the Panel’s 2011 fact-finding and quarterly public meetings; “insight” visits and meetings; direct
observations of NASA operations and decision-making; discussions with NASA management, employees, and contractors;
and the Panel members’ past experiences.
In our report we highlight issues on cost, schedule, resources, requirements and acquisition strategy that impact safety. Further,
we again note the uncertainty regarding goals and objectives and the need for clarity and constancy of purpose. Importantly,
we also acknowledge several of NASA’s many accomplishments during calendar year 2011. We observe that transparency, the
evolution of a safe and open culture, and key process advances have all significantly improved under your leadership.
A key and honest question that we pose is: “How safe is safe enough?” The pursuit of great reward often comes hand in hand
with great risk—so it has always been with explorers. The answer to the question must come from a balance between risk
and reward and should reflect a consensus among the American people, the White House, the Congress, and NASA. It is not
our intent or purpose to answer the question; however, we point to areas where we believe the stated requirement may not
produce the requisite safety. We especially invite your attention to the section “Reassessment of Space Shuttle Risks” and
the historical gap between anticipated and deployed systems risk.
In this report, we have assumed that the purpose of the commercial crew initiative is to facilitate the near-term development
of a U.S. commercial space transportation capability to achieve safe, reliable, and cost-effective access to and from low-
Earth orbit (LEO). However, some among the stakeholders believe human transport to LEO is not the primary intent of the
commercial crew initiative. They believe the intent is, instead, to foster a domestic U.S. space industry over a longer time
horizon. We note that attention to and investment in safety are critical in developing near-term transport to LEO but may not
be as significant in seeding a future industry. Some of the funding decisions and the resultant shifts in acquisition strategy
give credence to those who believe the objective has indeed changed. We believe clarity is needed, and constancy of purpose
must follow in either regard. We strongly believe those setting national strategy, providing resources, and planning for
execution must all share in acknowledging and shouldering the risk. To speak more plainly, if NASA attempts to execute an
underfunded program to an unrealistic schedule, the accountability for accepting the associated risk must be shared.
NASA’s senior leaders and staff members offered significant cooperation to support the completion of this document. I
therefore submit the ASAP Annual Report for 2011 with respect and appreciation.
Sincerely,
Enclosure
NASA AEROSPACE SAFETY ADVISORY PANEL
National Aeronautics and Space Administration
Washington, DC 20546
VADM Joseph W. Dyer, USN (Ret.), Chair
Pursuant to Section 106(b) of the National Aeronautics and Space Administration Authorization Act of 2005 (P.L. 109-155),
the Aerospace Safety Advisory Panel (ASAP) is pleased to submit the ASAP Annual Report for 2011 to the U.S. Congress
and to the Administrator of the National Aeronautics and Space Administration (NASA).
This report is based on the Panel’s 2011 fact-finding and quarterly public meetings; “insight” visits and meetings; direct
observations of NASA operations and decision-making; discussions with NASA management, employees, and contractors;
and the Panel members’ past experiences.
In our report we highlight issues on cost, schedule, resources, requirements and acquisition strategy that impact safety.
Further, we again note the uncertainty regarding goals and objectives and the need for clarity and constancy of purpose.
Importantly, we also acknowledge several of NASA’s many accomplishments during calendar year 2011. We observe that
transparency, the evolution of a safe and open culture, and key process advances have all significantly improved under
NASA Administrator Charles F. Bolden, Jr.’s leadership.
A key and honest question that we pose is: “How safe is safe enough?” The pursuit of great reward often comes hand in hand
with great risk—so it has always been with explorers. The answer to the question must come from a balance between risk
and reward and should reflect a consensus among the American people, the White House, the Congress, and NASA. It is not
our intent or purpose to answer the question; however, we point to areas where we believe the stated requirement may not
produce the requisite safety. We especially invite your attention to the section “Reassessment of Space Shuttle Risks” and
the historical gap between anticipated and deployed systems risk.
In this report, we have assumed that the purpose of the commercial crew initiative is to facilitate the near-term development
of a U.S. commercial space transportation capability to achieve safe, reliable, and cost-effective access to and from low-
Earth orbit (LEO). However, some among the stakeholders believe human transport to LEO is not the primary intent of the
commercial crew initiative. They believe the intent is, instead, to foster a domestic U.S. space industry over a longer time
horizon. We note that attention to and investment in safety are critical in developing near-term transport to LEO but may not
be as significant in seeding a future industry. Some of the funding decisions and the resultant shifts in acquisition strategy
give credence to those who believe the objective has indeed changed. We believe clarity is needed, and constancy of purpose
must follow in either regard. We strongly believe those setting national strategy, providing resources, and planning for
execution must all share in acknowledging and shouldering the risk. To speak more plainly, if NASA attempts to execute an
underfunded program to an unrealistic schedule, the accountability for accepting the associated risk must be shared.
NASA’s senior leaders and staff members offered significant cooperation to support the completion of this document. I
therefore submit the ASAP Annual Report for 2011 with respect and appreciation.
Sincerely,
Enclosure
NASA AEROSPACE SAFETY ADVISORY PANEL
National Aeronautics and Space Administration
Washington, DC 20546
VADM Joseph W. Dyer, USN (Ret.), Chair
Pursuant to Section 106(b) of the National Aeronautics and Space Administration Authorization Act of 2005 (P.L. 109-155),
the Aerospace Safety Advisory Panel (ASAP) is pleased to submit the ASAP Annual Report for 2011 to the U.S. Congress
and to the Administrator of the National Aeronautics and Space Administration (NASA).
This report is based on the Panel’s 2011 fact-finding and quarterly public meetings; “insight” visits and meetings; direct
observations of NASA operations and decision-making; discussions with NASA management, employees, and contractors;
and the Panel members’ past experiences.
In our report we highlight issues on cost, schedule, resources, requirements and acquisition strategy that impact safety.
Further, we again note the uncertainty regarding goals and objectives and the need for clarity and constancy of purpose.
Importantly, we also acknowledge several of NASA’s many accomplishments during calendar year 2011. We observe that
transparency, the evolution of a safe and open culture, and key process advances have all significantly improved under
NASA Administrator Charles F. Bolden, Jr.’s leadership.
A key and honest question that we pose is: “How safe is safe enough?” The pursuit of great reward often comes hand in hand
with great risk—so it has always been with explorers. The answer to the question must come from a balance between risk
and reward and should reflect a consensus among the American people, the White House, the Congress, and NASA. It is not
our intent or purpose to answer the question; however, we point to areas where we believe the stated requirement may not
produce the requisite safety. We especially invite your attention to the section “Reassessment of Space Shuttle Risks” and
the historical gap between anticipated and deployed systems risk.
In this report, we have assumed that the purpose of the commercial crew initiative is to facilitate the near-term development
of a U.S. commercial space transportation capability to achieve safe, reliable, and cost-effective access to and from low-
Earth orbit (LEO). However, some among the stakeholders believe human transport to LEO is not the primary intent of the
commercial crew initiative. They believe the intent is, instead, to foster a domestic U.S. space industry over a longer time
horizon. We note that attention to and investment in safety are critical in developing near-term transport to LEO but may not
be as significant in seeding a future industry. Some of the funding decisions and the resultant shifts in acquisition strategy
give credence to those who believe the objective has indeed changed. We believe clarity is needed, and constancy of purpose
must follow in either regard. We strongly believe those setting national strategy, providing resources, and planning for
execution must all share in acknowledging and shouldering the risk. To speak more plainly, if NASA attempts to execute an
underfunded program to an unrealistic schedule, the accountability for accepting the associated risk must be shared.
NASA’s senior leaders and staff members offered significant cooperation to support the completion of this document. I
therefore submit the ASAP Annual Report for 2011 with respect and appreciation.
Sincerely,
Enclosure
.
Aerospace Safety Advisory Panel
I. Introductory Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
A. The Aerospace Safety Advisory Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
B. ASAP Observations on NASA Accomplishments in 2011 . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1. Shuttle Program Completion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2. International Space Station (ISS) Assembly Complete . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
3. Noteworthy Launches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
4. Public Communications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
5. Progress on ASAP Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
III. Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Appendix: Summary and Status of ASAP 2011 Recommendations . . . . . . . . . . . . . . . . . . . . 19
CD Table of Contents
Attachment 1: Charter of the Aerospace Safety Advisory Panel
Attachment 2: ASAP 2011 Recommendations, NASA Responses, and Status
Attachment 3: ASAP 2011 Quarterly Meeting Minutes
Attachment 4: 2011 Activities of the Aerospace Safety Advisory Panel
Attachment 5: Aerospace Safety Advisory Panel Members and Staff
I. Introductory Remarks
A. The Aerospace Safety Advisory Panel (ASAP)
The ASAP was established by Congress in 1968 to provide advice and make recommendations to the
NASA Administrator on safety matters.1 The Panel holds quarterly fact-finding and public meetings and
makes one or more “insight” visits per year to NASA Field Centers or other related sites. It reviews safety
studies and operations plans and advises the NASA Administrator and Congress on hazards related to
proposed or existing facilities and operations, safety standards and reporting, safety and mission assurance
aspects on ongoing or proposed programs, and NASA management and culture related to safety. Although
the Panel may perform other duties and tasks as requested by either the NASA Administrator or Congress,
the ASAP members normally do not engage in specialized studies or detailed technical analyses.
This report highlights the issues and concerns that were identified or raised by the Panel during its activities
over the past year. The Panel recommendations submitted to the Administrator during 2011 are summarized
in the Appendix at the end of this report.2 They are based upon the ASAP fact-finding and quarterly public
meetings; “insight” visits and meetings; direct observations of NASA operations and decision-making;
discussions with NASA management, employees, and contractors; and the Panel members’ expertise.
3. Noteworthy Launches
NASA safely and successfully launched several important robotic missions in 2011:
• Aquarius was launched on June 9 from Vandenberg Air Force Base (AFB) on a Delta II. The joint
U.S.-Argentine mission will map ocean surface salinity, which is critical to understanding the
water cycle and ocean circulation—two major components of Earth’s climate system.
• The Juno probe to Jupiter, the second mission in NASA’s New Frontiers Program, was launched
on August 5 from Cape Canaveral on an Atlas V. Juno will take 5 years to reach the planet and
will be the first spacecraft to orbit Jupiter since the Galileo probe was de-orbited in 2003.
• The Gravity Recovery and Interior Laboratory (GRAIL), a two-spacecraft Discovery mission, was
launched on September 10 from Cape Canaveral on a Delta II. GRAIL will be used to study the
Moon’s gravitational field and learn more about its internal structure and thermal evolution.
• The National Polar-orbiting Operational Environmental Satellite System (NPOESS) Preparatory
Project (NPP) was launched on October 28 from Vandenberg AFB on a Delta II. NPP is the first of
a new generation of satellites that will observe many facets of our changing Earth.
• The Mars Science Laboratory, with the Curiosity Rover, was launched on November 26 from Cape
Canaveral on an Atlas V on its quest to determine if Mars is, or ever was, capable of supporting
microbial life. Curiosity is scheduled to arrive at Mars in August 2012.
4. Public Communications
Public communications on two potentially negative events were handled very well. In March, the Glory
spacecraft failed to reach orbit after launch on a Taurus XL from Vandenberg AFB. NASA’s Office of
Communications released a thorough message very quickly; several NASA personnel were on television
and radio discussing the mishap scenario and presenting the information that was available at that time.
There were frequent updates throughout the day. In September, 6 years after the end of its productive
scientific life, the Upper Atmosphere Research Satellite (UARS) broke into pieces during reentry, and
most of it burned up in the atmosphere. NASA’s chief scientist for orbital debris discussed the reentry
process and status on NASA’s website, and NASA’s Office of Communications was in close contact with
the media. From the time that it appeared that UARS would be de-orbiting, NASA did an outstanding
job of keeping the public informed on the satellite’s status and associated risks in an exemplary manner
that has not always been the case with other programs. This was done by not only supplying very
technical numerical analyses, but also by providing comparative real-life analogies to other risks to
which people are exposed in their everyday life; thus, people could make meaningful comparisons.
A. Human Spaceflight
Calendar year 2011 saw the Space Shuttle era draw to a close with the successful completion of the
STS-135 mission. The human spaceflight safety issues that were related to the Space Shuttle Program
are now no longer NASA’s most pressing concerns; however, there still are a number of areas related
to the ISS, Soyuz, the Commercial Crew Program (CCP), and potentially the Space Launch System
(SLS) that require continuing attention. The areas of particular interest include Micro-Meteoroid and
Orbital Debris (MMOD) risk to the ISS, plans regarding ground impact risks after de-orbit at the end
of the ISS’s useful life, and the risks of inadequate resources for programs under development. Risk is an
unavoidable component of any program. A critical characteristic of a successful program is the ability
to identify hazards and their risk of causing harm; comparing that to the level of risk allowable by the
program, the Agency, and the Congress; and prioritizing the work to mitigate the known risks to an
acceptable level.
In this Report, the ASAP provides specific comments on the ISS, Soyuz, the CCP, and the SLS/Multi-
Purpose Crew Vehicle (MPCV).
outcome. This can occur in either a controlled or an uncontrolled manner, with the latter clearly the
more dangerous. While this possibility has been known for some time, NASA has not yet shared with
the Panel an explicit plan to deal with this situation. ISS End of Life (EOL) is inevitable, and the ISS
will ultimately de-orbit; therefore, it is not too soon for EOL planning to begin in earnest and its
consequences to be understood by all stakeholders. Action plans, contingent on various circumstances,
should be created and shared with all agencies responsible for executing some part of that plan. This
would especially be true should resources (such as Soyuz) be required to complete the action plan.
The lack of advanced planning was illustrated by the activities surrounding the Russian Progress failure
that is described more fully in the next section of this report. This failure necessitated major schedule
changes due to the delay of Soyuz launches to the ISS. While NASA had always recognized a possible
interruption of scheduled Soyuz availability and, from a safety perspective, there was no immediate
impact on the crew, the subsequent flurry of activity showed a lack of maturity in the planning to
handle this eventuality. The potential loss of Soyuz availability—to bring new crew to the ISS as well
as to provide vehicles to be available 24/7 as potential “lifeboats”—raised the very real potential that
the ISS may have had to be abandoned. Fortunately, in this instance, time was available to create the
required plan; however, had this been an MMOD hit or other more immediate hazard, there may not
have been this luxury of time.
It is a foregone conclusion that at some time in the future, the ISS will have to be de-orbited. This fact
strongly supports the argument that NASA should have detailed plans already worked out with the
international partners on how this de-orbit will be accomplished. The hazards and risk implications
for those on the ground must be analyzed, and the resulting conclusions and plans must be available to
mitigate those risks.
(JSC). Following the detailed discussion on the Russian investigation and its conclusions, the MSFC
team then explained its independent Risk/Failure Tree analysis and computer modeling. This was very
thorough, especially considering the fact that the team’s knowledge of the system and its history is not as
detailed as the Russian Commission’s. However, regardless of some obvious differences in background
on the system, they were able to replicate all of the critical Russian results.
Both teams concluded that the most likely event was a “quality escape” resulting in debris entering
and clogging the fuel system. This result was based on the investigation and considerable history of
this engine (some 2,000 engine runs) without ever seeing this failure before. This conclusion was also
supported by audits on the assembly, build, and test process. In short, the MSFC team agreed with the
conclusions of the Russian team and felt that the failure scenario was plausible. MSFC was able to reach
its conclusions independently and also felt that a quality escape was the most probable cause. The MSFC
team concluded that the Russians were on track to put into place measures to mitigate any recurrence.
In the ASAP’s view, the two teams did an exemplary job examining the cause of the Progress accident.
The Russians treated this incident very seriously and put the kind of expertise on the team that had
technical knowledge and background as well as the seniority in the Russian system to act and speak
independently. The MSFC team’s work was very impressive, both its analysis of the Russian work and
its independent work.
While no absolutely definitive physical evidence is available to prove the failure cause, the completeness
and competence with which this investigation took place gave the confidence in the subsequent return
to flight decision. The successful Soyuz mission commencing November 14, 2011, took place without
incident. NASA should continue to closely examine Soyuz operations so as to be alert to any information
that might bear on future operational decisions.
It is well to remember that the Soyuz spacecraft, an evolutionary vehicle that has been flying since
1967, currently provides the sole transportation to and from the ISS for the Expedition crews.
Equally important to know is that since Soyuz has the capability to remain docked to the Station for
6-month periods, it provides a “lifeboat” function. This supports the crew by providing an on-orbit
rescue capability in the event of a contingency aboard the ISS. It has been long-standing ISS policy
that the Station can host six crewmembers on long-duration missions only with the availability of
immediate de-orbit capability for the entire on-board crew. Therefore, two Soyuz spacecraft are
required to be docked at Station for the six-person ISS crew. In September of this year, when one of
the docked Soyuz vehicles reached the end of its on-orbit certified life, NASA and Russia made the
decision to return three crewmembers to Earth on Soyuz 26. It must be recognized that there could
be circumstances where the Soyuz 6-month on-orbit limit could result in a de-crewing of the ISS. In
addition, recently projected slippages in the Commercial Crew Program will require renegotiation
with the Russians to provide Soyuz transportation beyond the currently agreed 2016 deadline. Such
renegotiations could be problematic. Failure to renegotiate the agreement could result in a period of
time without U.S. access to the Station. The ASAP will continue its focus on these issues and NASA’s
plans over the next year.
3. Commercial Crew
We believe the objective of the commercial crew initiative is to facilitate the development of a U.S.
commercial space transportation capability with the goal of achieving safe, reliable, and cost-effective
astronaut access to and from low-Earth orbit (LEO) and the ISS. (We do not believe the objective is
just to fund and develop a commercial space industry; however, we note that some stakeholders would
debate this.) Once that capability has matured, NASA plans to purchase commercial services to meet
the ISS crew transportation needs. To take maximum advantage of the limited funding available, and
in recognition of the urgent need for this capability, NASA is using nontraditional acquisition and
partnering approaches during the early phases of the program and had planned to switch to a more
standard acquisition process during later (post–critical design review) program phases. Competition is
considered to be a fundamental aspect of the strategy in order to incentivize performance, support cost
effectiveness, and eliminate dependence on a single provider.
Because the 2010 NASA Authorization Act stated that commercially provided services should be used
as the means for ISS crew transportation to the maximum extent practicable, the ASAP has been closely
following NASA’s progress on this program and has requested status updates at each quarterly meeting.
Some program challenges that have been identified to date include making sure that the available funds
are appropriate to the objectives, working toward a realistic schedule, developing the safety certification
processes that will be used, and selecting the proper design targets for safety and reliability.
NASA has recently baselined and published the design requirements in its 1100-series documents.
It has also defined a streamlined control board process that should contribute to expedited decision-
making. To increase its insight into the commercial development efforts, NASA has put in place
Partner Integration Teams that will have the ability to work side by side with the various partners to
understand their approaches and progress. Although such an approach can certainly be beneficial, it will
be important to ensure that the tendency to “over-identify” with the contractor does not result in a lack
of objectivity by the NASA representatives.
According to NASA program managers, the top program risk is inadequate budget; however, without
an accurate NASA estimate of how much it will cost to develop and test a system, it is not possible to
precisely know the program’s budgetary requirements or if there is a risk of underfunding. In this case,
the difficulty is compounded by the fact that the vehicles are being developed by commercial entities,
using nontraditional procurement strategies. It is not surprising that when NASA asked proposers on
the second phase of the Commercial Crew Development (CCDev) Program for rough estimates of
the funds needed to complete the development of a commercial crew system, it received a wide range
of figures from the various companies. NASA is understandably reluctant to publicize the details of
those estimates due to the proprietary nature of the figures in the ongoing competition. Nevertheless, it
appears to the ASAP that the fiscal year (FY) 2012 funding level approved by Congress, which was less
than half of what was requested by the Administration, will not allow commercial crew transportation
to the ISS by 2016. In fact, if the new funding level continues into the future, it is the ASAP’s belief that
the program is in jeopardy, thus extending the current lack of a U.S. human spaceflight capability and
resulting in no alternative to reliance on Russia to obtain access to the ISS.
The ASAP considers the lack of a credible and appropriately funded plan to develop a U.S. capability to
launch its astronauts to the ISS to be an issue with significant safety implications. If the development
program is continued without adequate funding, it will increase the likelihood that safety-related testing
and modifications to correct any design deficiencies would not be made. Alternatively, terminating the
development program would result in continued reliance on the Russian Soyuz, a system with an
uncertain long-term future.
In mid-December, however, just before this report went to publication, NASA announced plans to
change its acquisition strategy for the integrated design phase of the CCP from a fixed-price, Federal
Acquisition Regulation (FAR)-based contracting approach to one utilizing Space Act Agreements
(SAAs). Previously, NASA had made a strong safety case for using conventional contracting on the
next phase of the CCDev Program, an approach that was viewed as well reasoned and appropriate by
the ASAP. The ASAP acknowledges NASA’s assertion that the change is primarily driven by funding
uncertainties and the need to maintain more than one provider for commercial crew transportation
services. However, we believe that the sudden change in acquisition strategy in an effort to salvage the
CCP may have significantly increased the risk to safety that the previous plan had begun to address. The
lack of the ability to incorporate firm safety requirements using an SAA procurement exposes NASA to
new risks if, at the conclusion of the developmental phase, the proposed designs do not meet minimum
safety requirements. In that event, NASA will have to either (1) expend additional time and money
having the designs modified and retested or (2) accept the risk associated with flying its astronauts on
systems that do not meet the currently articulated minimum safety requirements. If NASA is deciding
to take on more risk because the cost is otherwise prohibitive, then the Agency should be clear about
that increased level of risk acceptance and develop approaches to manage that risk. While it is possible
that NASA can find a way to accomplish the assigned mission with the available budget, at this point in
time the Panel has serious concerns about the likelihood of such an outcome. The ASAP plans to closely
examine the SAA approach in 2012 and will be most interested in the plan for transitioning the designs
into certified systems before their use as crew transport.
and Constellation Programs. The ASAP plans to review the SLS and Orion MPCV programs during
the coming year.
A key question involves the selection of an appropriate mission. For the purposes of determining risk,
should NASA assume the vehicles will be used in a mission to the Moon, to an asteroid, to a Lagrange
point, or to some other destination? Or should the vehicles be designed for all of those missions? Other
areas of interest include reexamining the design targets and thresholds for LOM and Loss of Crew
(LOC), the plan for program control boards, the appropriate magnitude of needed budget margins,
and the potential impacts of a decline in the U.S. aerospace industrial base on long-term logistics and
support. NASA will need to give each of these questions due consideration in 2012. This is not a new
challenge. Prior ASAP reports have highlighted the requirement for clarity and constancy of purpose
regarding goals and objectives for NASA.
B. Risk Management
At least in our lifetime, travel by humans to orbital velocity and beyond and returning to Earth
through our atmosphere will always entail significant risks. The sheer amount of energy required
to reach these velocities and the space environment’s unforgiving nature dictate that extraordinary
efforts must be expended to identify potential hazards and either design them out or provide positive
measures to minimize the probability of their occurrence and control the results if they do occur.
The residual risk that remains is measured by the probability of the various failure scenarios and the
severity of their outcomes. The most serious of these outcomes is known as LOC (loss of crew). In
using a variety of analytical tools to identify, assess, and manage these risks, NASA remains at the
forefront of organizations conducting high-consequence operations. The ASAP feels that the risk
targets must be prudently selected, based on past experience, and explicitly articulated. The foundation
upon which the ultimate assessment must be made is the acceptable level of risk. In other words—how
safe is safe enough?
RESULTS SUMMARY
• SSME risk increase due to higher power level
• APU risk reduction post STS-9 (process improvement) • MMOD risk reduction due to addition of late inspection
• Orbiter flight software using OI-2 • Ascent debris risk reduction improved debris
• Ejection Seats Disabled
environment and improved repair
• APU risk reduction post STS-9 (re-design) • SSME uncontained risk reduction with Block II engine
0.12 • Orbiter flight software using OI -7 with AHMS
• Orbiter flight software using OI-21 • SSME risk slight increase with
• Risk reductions due to IAPU Block II engines
0.04 • Orbiter flight software using OI-29
1:36 1:37 1:38
1:47 1:47
0.02 • SSME Risk reduction with
Block I & IA engines 1:73 1:90
• Orbiter flight software
using OI-24
0
1 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130
STS-1 STS-41B STS-51L, STS-26 and STS-49 STS-77 STS-86 STS-103 STS-110 STS-114 STS-133
STS-5 STS-29 STS-89
Flight Sequence #
The ASAP is very pleased with NASA’s work in this area. Many things were learned through this
analysis. One key finding was that the risk on a new system that has not been flown before and thus
has not been through the rigors of real-life flight is probably much higher than what the initial risk
assessments show. The reason for this difference is that at the beginning of operations, all the failure
mechanisms are not fully known. In the language of risk analysis, such unknown failure mechanisms
are often called “unknown-unknowns.” In the Shuttle’s case, the first flight risk as now retrospectively
calculated was in actuality 1 in 12 for LOC, yet at least one analysis that existed at the time of the
initial launch estimated the risk to be 1 in 1,000 or better. In other words, the system was almost 100
times more dangerous than the early analysis indicated. This type of disparity must be remembered
when future targets for reliability and LOC numbers are chosen for new programs. One thing that has
always been said in the design business is that engineering design standards take care of the “knowns”;
factors of safety take care of the “known-unknowns”; and margin is what takes care of the “unknown-
unknowns.” A significant margin for error should be allowed for the unknown-unknowns as well as to
create a robust design.
In any discussion of spaceflight risk, the perceived versus actual risks experienced by the Space Shuttle
clearly should be taken into account. As already mentioned, the Space Shuttle, unbeknownst to the
team at the time, started at a LOC risk level of 1 in 12, and there was a 92-percent chance that a crew
would be lost in the first 25 missions. By constant improvements, that risk was lowered to 1 in 90 by the
last flight, which is still a high number compared to many endeavors.
In order for risk to be managed appropriately at any level, but especially at a programmatic level, the
various component risks and their overall impact must be clearly communicated. A critical question
involves not only what technical information should be communicated, but also what entities need
to receive this communication and the manner in which the information is communicated. If this
clear communication of risk is not accomplished, then safety, appropriate use of resources, and overall
confidence and support of programs and NASA can be negatively impacted.
Examples— UARS and ISS
There are examples where this has been done in productive and less than productive ways. As noted in
Section I of this Report, NASA communicated the UARS reentry hazard in a multipronged manner
and did a very good job in communicating the level of risk and explaining that real damage or injury
could result. The proactive, well-thought-out and -executed communication of risk was accomplished
well in advance of the actual reentry event and ultimately resulted in an appropriate public response
rather than an emotional alarmist response.
In the case of the ISS, however, ASAP feels this level of proactive, clear communication of risk has
not been accomplished. As noted earlier, NASA provided information to ASAP regarding the risk of
LOM for ISS at a level of 1 in 55 for a single, 180-day mission. The ASAP thinks that it would be more
informative to state the risk as a greater-than-30-percent chance that the ISS could sustain a LOM
sometime during its projected operating life. LOM is not an inconsequential risk, and it has not been
openly communicated either inside or outside of NASA. The point here is not the 1 in 55 number,
but that it may not be understood in the same manner as expressing it as an approximately 30-percent
chance of LOM during the ISS’s currently projected life. Failure to clearly communicate this level of risk
in a manner that the various stakeholders conceptually understand can result in an inappropriate loss of
support and confidence in NASA in the event that an ISS LOM occurs. For example, it could be argued
that in the case of the Challenger mishap, the failure to communicate openly and effectively about risk
undercut the confidence and support for NASA that might otherwise have been present.
Attempting to execute programs with insufficient funding often leads to compromise detrimental to
safety. Therefore, we believe transparency is essential if NASA, the Congress, and the White House are
to collectively shoulder the risk and the responsibility.
4. Knowledge Management
Knowledge management is the collection of processes that govern the creation, dissemination, and
utilization of knowledge. In this discussion, the ASAP is using the following definition of “knowledge”:
the ability, capability, and willingness to assemble information in such a way as to advance learning,
improve on current mechanisms, and advance civilization. Knowledge management takes time, effort,
expertise, and the willingness to be curious, search, think, and experiment. It is a nontrivial, critical
task that must be undertaken by serious personnel who are competent in the process. The ASAP has
observed such personnel within the NASA Centers and compliments the personnel and the programs at
JSC and Goddard Space Flight Center, for example. In these locations (and perhaps others), competent
and enthusiastic personnel are making excellent progress at both cataloging and managing NASA
critical knowledge. We have also seen excellent examples in regard to specific programs; for example, the
Constellation Program just published a two-volume report on lessons learned, and the Shuttle Program
has an equivalent program in process.
These examples, while excellent and laudable, do not constitute an approach that ensures the
identification and capture of critical NASA implicit and explicit knowledge Agency-wide in a manner
that would allow any NASA employee (or, under some circumstances, NASA partners and contractors)
a single process or tool to locate and then access all of the information resources.
The ASAP has recommended that NASA establish a single focal point—a “Chief Knowledge Officer”—
within the Agency to develop the policy and requirements necessary to integrate knowledge capture
across programs, projects, and Centers. Additionally, the ASAP has recommended that NASA consider
establishing Chief Knowledge Officer positions at all NASA Centers and in all Mission Directorates to
ensure standardization of programs and lessons learned as we move forward. A single focal point within
the Agency provides clear responsibility and authority to ensure an integrated Agency-wide process and
archive for knowledge capture. A similar focal point at each NASA Center and each Mission Directorate
would facilitate this function at the local level.
The ASAP believes that one overarching and fundamental purpose of NASA is to create knowledge.
The Agency remains the sole repository within the U.S. for a rich history of knowledge on human
spaceflight. Its Centers contain much of the world’s information on planetary science, knowledge of the
cosmos, and many related scientific fields. Ensuring that this knowledge is captured and available to
future generations is more than an obligation; it is a sacred trust.
5. Facilities
For the past 3 years, the ASAP has been monitoring the condition of NASA facilities and infrastructure
with an eye toward safety and mission accomplishment. In this regard, during each Center or
installation visit, a facilities tour is performed to derive a sense of the changes that have occurred since
the last visit and to gain an appreciation of the general condition of the facilities’ components. This is
not a detailed engineering inspection or assessment, nor is it a comprehensive review, covering every
facility or all areas of the Center; rather, it is an overall impression of the facilities’ condition, including
pressure vessels, boilers, hoists and lifts, hangars, test stands, electrical systems, etc.
The Panel has noted in past annual reports and continues today to believe that, considering their
age, most NASA facilities are in relatively acceptable condition. However, during each visit we have
observed firsthand or have identified areas where the infrastructure or a particular condition could have
an undesirable mission effect. Worse yet, it could present a safety hazard that, if not addressed, could
result in NASA or contractor personnel injury. Regretfully, but not surprisingly, the number of such
conditions or infrastructures is on the rise, and the overall facility condition-index trend is downward.
In light of this downward trend, for the past 2 years, the ASAP has asked NASA to identify the process
used Agency-wide to identify, characterize, and prioritize facilities or infrastructure requiring critical
repair or replacement. The response thus far is that the burden of such characterization and repairs is the
responsibility of each Center’s engineering organizations, using standardized codes to identify the most
critical repair or replacement. Funding to address these needs routinely is provided by project funds, if
available. For those Centers well endowed with an abundance of projects, this approach has been, for
the short term, satisfactory; however, for Centers not so fortunate, this methodology has been less than
successful. In some cases, instead of repairs, the Agency has earmarked facilities for replacement. This
approach has resulted in a significant near-term request for construction that even under the best of
circumstances is not likely to be funded.
Considering the current and anticipated budget environment, the ASAP believes that NASA must
develop and implement a process that compares risk at each Center, then integrates, prioritizes, and
allocates dollars for facility repairs Agency-wide for the most critical areas. To do otherwise will allow
further deterioration of critical facilities at some Centers while possibly over-improving facilities or
infrastructure at other Centers. Both results are undesirable. In other words, these decisions need to be
made from the perspective of what is best for NASA overall rather than what is best for an individual
NASA Center.
The ASAP continues to believe that it is critical for the Agency to constantly evaluate its transparency
and culture. In this context, “transparency” means open access to information, participation, and
decision-making, which ultimately creates a higher level of trust among stakeholders; “culture” is a
collection of values and norms that are shared by people in the organization and that control the way
they interact with each other and with stakeholders outside the organization. An open culture makes
it easier to identify risk and perform insight and oversight; it will also improve communication within
the Agency and with key partners and contractors. The ASAP has addressed culture frequently since
the Columbia Accident Investigation Board (CAIB) report and will continue to do so. With respect to
transparency and culture, this past year the ASAP made recommendations on insight/oversight, timely
and accurate communication, and development of a NASA alcohol use and testing policy.
1. Insight/Oversight
As NASA transitions into utilizing commercial services for both cargo and crew transportation to LEO
destinations while developing a new SLS for exploration, both insight and oversight will be essential to
maintaining the safety of various systems and the crew that occupy them.
The ASAP has been monitoring the transition to commercially based programs for the delivery of cargo
and eventually crew to the ISS and other LEO destinations and has discussed the type of information
that is needed to provide additional insight. In accordance with our recommendations from prior
reports, we are pleased to note that NASA has recently baselined and published technical requirements
for any provider interested in offering transportation for NASA astronauts to LEO. This publication is
fundamental to establishing transparency in the relationship between the Agency and its suppliers. The
ASAP believes it will be equally helpful for NASA to provide oversight to a validation and verification
matrix that outlines how each provider will provide assurance that the design meets those requirements.
Establishing requirements to guide the design and then overseeing the process that validates that the
intent is being met is fundamental to being able to certify these systems upon entering into follow-on
development phases after the SAA design phase.
The ASAP feels that oversight must continue to be provided in order to ensure that the vehicle is
manufactured, is assembled, and will be operated in accordance with the requirements and the design
constraints. Any manufacturer that is involved in producing or providing systems where human safety
is a critical concern should expect that a level of oversight is a necessary requirement and take the
appropriate steps to integrate this oversight into the program plans.
Even though the SAA prevents NASA from issuing requirements directly under a contract-type
arrangement, there should be no restriction on NASA seeking assurance information to make certain
that the provider designs to meet the human rating requirements, validates the design, builds to the
design, operates the build within the design limits, and maintains it to ensure that no degradation
takes place.
Another related area where insight must be provided is risk. Technical risk represents perhaps the most
controllable risk. NASA is providing a set of requirements that list the objectives that must be achieved
as well as any known approach for achieving them; in addition, all of NASA’s engineering standards are
being provided. While technical risk can never be fully eliminated, this approach mitigates such risk to
the extent possible. We believe that NASA should seek the maximum opportunity to closely oversee what
the contractors are developing during the SAA phase of the CCP. Schedule risk is a more difficult risk
to mitigate because, like cost, it tends to be a “victim” of whatever else goes wrong. The ASAP believes
that the best approach to handling this risk is to develop an agreed-to integrated plan and schedule that
calls out specific, measurable events that are easily discernable by all parties so that progress is clearly
measurable and evident. Financial risk is, without a doubt, the most contentious risk category, from
both the funder’s perspective and the performer’s perspective. The funding uncertainty makes this risk
more difficult to manage. The tendency to “promise beyond ability” and to “expect beyond capability”
is strong in the program culture. Under the recently announced change from traditional contracts to
SAAs, the ASAP continues to stress that insight and oversight into program execution are essential to
ensuring that the SAA phase of the program yields designs that can be ultimately certified as meeting
safety criteria.
Several things can ease the ASAP’s concerns regarding the programmatic and thus the safety risk
associated with developing the commercial space transportation system and any future space launch
system for NASA astronauts:
1. An independent and credible cost estimate;
2. A realistic schedule based on the resources made available;
3. Sufficient resources to fund the acquisition approach, with historically realistic management reserve;
4. Completion of NASA’s safety certification requirements and process; and
5. Provisions in the SAAs negotiated with suppliers that provide NASA access to and insight into the
design and validation of the vehicles under development.
Transparent communication, constructive feedback, professional trust, and flexibility will be necessary
to assure all stakeholders that these programs are on a path to success. The insight/oversight process
must revolve around the development of a long-standing, mutually trusting relationship between all
stakeholders. It is essential to the safe and efficient execution of any programs or partnerships. When
issues arise, they need to be openly and thoroughly discussed. Withholding information, hiding
concerns, and keeping secrets are clearly signs of trouble in any relationship, but especially one in
which the end product is designed for human transport to space, which is a very hazardous endeavor.
The ASAP believes this must be worked on by both sides until an open and transparent relationship
is established. While the SAAs pose the potential for increased risk, this can be partially overcome by
making sure that both sides of the process are fully knowledgeable about the ability of the design to
meet NASA’s human rating requirements.
• What is the mission? We must clearly articulate the goals and objectives of the U.S. human
spaceflight program, both within and beyond LEO.
• What will it cost? We must measure the risk in both resources and human lives to reach the goal.
Said another way—Is what we will get worth what it may cost?
• Whom will you tell? The risk must be made fully transparent to the stakeholders and the
American people.
The time for either unfounded pessimism or unbridled optimism is over. Human space exploration,
should we choose to pursue it, is expensive, time-consuming, demanding of the highest levels of
technology, and inherently dangerous. If we cannot accept these fundamental facts, then we must
consider whether or not we should go. It is a choice, and that choice should not be postponed.
Expanded commercial activities and how best to acquire them remains a topic of importance. The
ASAP had previously noted that fixed-price contracting potentially sets up a conflict between cost,
schedule, and performance that can affect safety. Significant insight and oversight by NASA will be
required to ensure that this inherent conflict is appropriately managed. NASA’s very recently announced
plan to change the acquisition approach for commercial crew transportation services from FAR-based
contracting to SAAs may have negative implications for the safety of NASA crew. The ASAP plans to
closely examine this approach and its safety issues in 2012.
In our current media environment, NASA needs to work harder to clearly express more complex
scientific information, relative risk, and test results. When working through and with commercial
entities, it becomes more critical for NASA to effectively communicate to all external stakeholders.
The ASAP believes that one overarching and fundamental purpose of NASA is to create knowledge.
Public information, no matter how skillfully done, does not ensure the identification and capture of
critical NASA knowledge. The Agency remains the sole U.S. repository for a rich history of knowledge
on human spaceflight, and its Centers contain much of the world’s information on space science and
related scientific fields. Ensuring that this knowledge is captured, retained, and available to future
generations is essential. Therefore, the ASAP has recommended that NASA establish a single focal
point—a “Chief Knowledge Officer”—within the Agency to develop the policy and requirements
necessary to integrate knowledge capture across programs, projects, and Centers.
NASA has now announced that, to provide the future capability for human exploration beyond Earth
orbit, it plans to develop the SLS and the Orion MPCV. Since these systems will be NASA’s primary
vehicles for carrying out its exploration mission over the next several decades, it is essential that they be
designed to be as safe and reliable as possible. The ASAP plans to initiate a more detailed review of these
programs during the coming year.
19
Aerospace Safety Advisory Panel
2011-01-01 NASA Alcohol Use and Testing Policy. NASA should NASA response
implement a post-mishap alcohol and drug testing program and updates
for all personnel in sensitive positions that are involved in received;
Class A and B mishaps. That includes NASA contractors, civil OPEN pending
servants, political appointees, and all affected visitors. schedule with
completion and
implementation
dates
2011-01-02 Safety and Mission Assurance Role Descriptions. NASA NASA response
should begin to draft a role description as well as some key job received 6/27/11;
requirements, such as educational background and experience, OPEN pending
for the personnel who have to specify, manage, and assure the briefing on study
S&MA activities under the new program direction. findings
2011-01-03a Safety Metrics. The NSC should expand mishap analysis NASA response
to include all types of mishaps. As this process develops received 6/27/11;
and matures, and as the comparisons make the data more CLOSED,
meaningful, the NSC should brief the senior leadership of the with quarterly
Centers and the Agency on the results. monitoring
2011-01-03b IRIS Support. NASA should describe how the IRIS supports NASA response
causal analysis and include the causations in the periodic received 6/27/11;
reports together with their associated mitigation actions and OPEN, with
schedules for completion to management. NASA should progress report at
take steps to have the system do the analysis and reporting 1st qtr. mtg. in
automatically. 2012
2011-02-02 Space Shuttle Launch and Re-entry Risk Study. NASA NASA response
should perform an analytical study on the Space Shuttle received
launch and re-entry risk to both crew and public safety. This 8/8/11; briefing
study should be done using a consistent set of assumptions 10/20/11;
over the total launch history. CLOSED
2011-03-02 Partner Integration Team Rotation. The CCP should develop NASA response
a written policy specifying team rotation schedules based on received 10/6/11;
tour of duty, milestones, or other appropriate criteria, to ensure OPEN, pending
a fresh set of eyes are always protecting the government’s interest receipt of policy
for the insight portion of the acquisition strategy. or procedure