Iw Rules July 2023-Edition
Iw Rules July 2023-Edition
July 2023
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
General Information
1. This consolidated version of the ‘Rules and Regulations for the Construction and Classification of
Inland Waterways Vessels’ (July 2023) supersedes the July 2022 edition of the Rules and includes
the amendments published in the following :
2. For ease of reference by the users, a summary of additions and amendments incorporated in the
various Rule Change Notices (issued since July 2022) along with their effective dates are indicated
in the respective tables.
3. This edition of the Rules also consists of amendments carried out subsequent to the publication of
Rules Change Notice No.3 of March 2023. Such amendments are included in Table 1.
a) Part 1 – Regulations
b) Part 2 – Inspection and Testing of Materials
(This part is same as Part 2 of ‘Rules and Regulations for the Construction
and Classification of Steel Ships’)
c) Part 3 – General Hull Requirements
d) Part 4 – Main and Auxiliary Machinery
e) Part 5 - Special Ship Types
The amendments are applicable to vessels contracted for construction on or after 1 January 2023
Amendments are made to modify the formulation related to grab loading such
4/ 4.2.3 that it can be applied to cases where mass of un-laden grab is more than 7
tonnes.
Part 5 Chapter 1: Dry Bulk Cargo Carriers
The amendments are applicable to vessels contracted for construction on or after 1 January 2023
Suitable cross-reference is provided to the revised requirements for ships
2/ 2.3.3
discharged by grabs in Pt.3, Ch. 6.
RULES AND REGULATIONS FOR THE CONSTRUCTION AND CLASSIFICATION
OF INLAND WATERWAYS VESSELS – July 2022
The amendments are applicable to vessels contracted for construction on or after 1 January 2023
More clarity is provided on requirements for anchoring and mooring
1/ 1.1.4 equipment for vessels assigned notation INDIAN INSHORE TRAFFIC
CORRIDOR VESSEL.
RULES AND REGULATIONS FOR THE CONSTRUCTION AND CLASSIFICATION
OF INLAND WATERWAYS VESSELS – July 2022
The amendments are applicable to vessels contracted for construction on or after 1 July 2023
Applicable class notations and construction requirements for high-speed
2/ 2.8 (new)
vessels operating in Inland Waterways are specified.
Clause addressing ‘Certificate of Compliance’ for IW vessels not intended to
2/ 2.18.5 (new)
be retained under Classification after construction is introduced.
Part 1
Regulations
Contents
Chapter 1 General
Contents
Chapter 1
General
2.10 Materials
General Information
2.11 Request for Surveys
Chapter 2
Periodical Surveys
General Requirements
Section 3
Section 5
Section 2
Surveys – Liquefied Gas Carriers
Hull Surveys
5.1 General
End of Contents
Chapter 1
General
Contents
Section
1 General Information
2 Classification Regulations
3 Classification of Vessels not built under the Supervision of
Indian Register of Shipping
Section 1
General Information
1.1.2 The management of the affairs of IRS are 3 Directors being persons of eminence
carried out by the Managing Director (MD) and from any industry allied with maritime
Jt. Managing Director (JMD), under the direction activities
and control of the Board of Directors (hereinafter
referred to as the 'Board'), in accordance with 1 Managing Director being full-time
the provisions of its Memorandum and Articles employee appointed by the Board of
of Association. Directors
1.1.3 The Board of Directors shall consist of 1 Jt. Managing Director, where so
representative of the interests of various appointed, being full-time employee,
members of the Company and those concerned appointed by the Board of Directors.
with shipping in general as under:
The composition of the Board as above is to be
3 Directors representing Indian in accordance with the Articles of Association of
Shipowners IRS (as may be amended from time to time).
2 Directors representing Indian 1.1.4 The Board shall consist of not less than six
Shipbuilders and not more than fifteen Directors. If the actual
representation on the Board of Directors exceeds
1 Director representing General Insurance 15 Directors, the provisions of the Indian
Corporation of India and other Indian Companies Act would apply to approve the
underwriters increase in the sanctioned strength of the Board
beyond the limit specified in the Articles of
Indian Register of Shipping
Chapter 1 Part 1
Page 2 of 17 General
Association of IRS. The Board of Directors shall 1.3.3 The Technical Committee to be constituted
elect one of its members to be Chairman of the as follows:
Board of Directors. The reference to Chairman
shall include Executive Chairman, where so Number of
appointed by the Board of Directors. Members Nominees/Representatives of
powers to act on its behalf, and all such actions caused in any information or advice given in any
being reported to the Board at its subsequent way whatsoever by or on behalf of the Society,
meeting. even if held to amount to a breach of warranty.
Nevertheless, if any person uses services of the
1.4.2 The reports of the Surveyors shall, subject Society, or relies on any information or advice
to the approval of the Managing Director/Jt. given by or on behalf of the society and suffers
Managing Director, be open to inspection of the loss damage or expenses thereby which is
Owner and any other person authorised in proved to have been due to any negligent act
writing by the Owner. Copies of the reports will, omission or error of the Society its servants or
subject to the approval of the Managing agents or any negligent inaccuracy in
Director/Jt. Managing Director, be supplied to information or advice given by or on behalf of
Owners or their representatives. the Society then the Society will pay
compensation to such person for his proved loss
1.5 Register of Ships up to but not exceeding the amount of the fee
charged by the Society for that particular
1.5.1 A Register of Ships is available on-line on service, information or advice.
IRCLASS Website which contains the names of
ships, character of class and notations assigned 1.6.2 Any notice of claim for loss, damage or
together with other relevant useful information expense as referred to in 1.6.1 shall be made in
for ships classed with IRS. writing to Head Office within six months of the
date when the service, information or advice
1.6 Liability was first provided, failing which all the rights to
any such claim shall be forfeited and the Society
1.6.1 Whilst Indian Register of Shipping, a shall be relieved and discharged from all
Classification Society, along with its subsidiaries liabilities.
and associates (hereinafter referred to as the
Society) and its Committees use their best 1.7 Access of Surveyor to vessels, shipyards
endeavours to ensure that the functions of the or works
Society are properly carried out, in providing
services, information or advice neither the 1.7.1 The Surveyors are to be given free access
Society nor any of its servants or agents to vessels classed with IRS as well as to
warrants the accuracy of any information or shipyards, works, etc. so as to perform their
advice supplied. Except as set out herein neither duties, and are to receive adequate assistance
the Society nor any of its servants or agents (on for this purpose.
behalf of each of whom the Society has agreed
this clause) shall be liable for any loss damage 1.8 Requirements for service suppliers
or expense whatever sustained by any person
due to any act or omission or error of 1.8.1 For requirements of approval of applicable
whatsoever nature and howsoever caused of service suppliers, refer to Part 1, Chapter 1, 1.9
the Society its servants or agents or due to any of the IRS Rules and Regulations for the
inaccuracy of whatsoever nature and howsoever Construction and Classification of Steel Ships.
Section 2
Classification Regulations
2.1.4 When a vessel is assigned a specific 2.2.2 Unless directed otherwise by IRS, all new
Character of Class in Indian Register of Rules and Regulations or amendments to the
Shipping, it implies that IRS has been satisfied existing Rules & Regulations become applicable
that the said vessel meets, for this particular 6 months after the date of issue. Where it is
class, with these Rules and Regulations or proposed to use existing previously approved
requirements equivalent thereto. The vessel will plans for a new contract, written application is to
continue to be classed with IRS so long as she be made to IRS.
is found, upon examination at the prescribed
annual and periodical surveys, to be maintained 2.3 Scope and process of classification
in a fit and efficient condition and in accordance
with the Periodical Survey requirements of these 2.3.1 Classification covers vessel's hull,
Rules. In general, classification will be appendages and machinery including electrical
conditional upon compliance with IRS systems to the extent as specified in these
requirements and assignment of character of Rules & Regulations. Classification does not
class for both hull and machinery. guarantee the design or performance of a vessel
except for those aspects covered by the Rule
2.1.5 The Rules are framed on the under- requirements and subject to the conditions of
standing that vessels will be properly loaded and operation of the vessel mentioned in 2.1.5.
handled and that vessels will not be operated in
environmental conditions more severe than 2.3.2 The classification process consists of:
those agreed for design basis and approval.
They do not, unless stated in the class notation, A technical review of the design plans and
provide for special distributions or concen- related documents for a new vessel to verify
trations of loading. compliance with the applicable Rules;
2.1.9 It is the responsibility of the Owners to Upon satisfactory completion of the above,
ensure that the operating and maintenance the builder’s/ owner’s request for the
instructions/manuals for the vessel machinery issuance of a class certificate will be
equipment essential to the safe operation of the considered by IRS and, if deemed
vessel are available in a language satisfactory, the assignment of class may be
understandable by those officers and crew approved and a certificate of classification
members who are required to understand such issued;
information/ instructions in the performance of
their duties.
Once in service, the owner is to submit the Zone 2 : A zone where the significant
vessel to a clearly specified programme of wave height does not exceed
periodical class surveys, carried out 1.2 [m].
onboard the vessel, to verify that the vessel
continues to meet the relevant Rule Zone 3 : A zone where the significant
requirements for continuation of class. A wave height does not exceed
classification survey is a visual examination 0.6 [m].
that normally consists of an overall
examination of the items identified in the 2.5.4 Description: A ‘description’ may be
Rules for survey, detailed check of selected assigned to indicate the purpose or role of a
parts on a sampling basis and witnessing vessel. In general, there would be no specific
tests, measurements and trials where rule requirements to be complied with for
applicable. assignment of a description. E.g. “Cutter Suction
Dredger” can be assigned to describe the vessel
When a Surveyor identifies corrosion, type dredger.
structural defects or damage to hull,
machinery and/ or equipment which, based 2.6 Character of classification
on the Rules and in the opinion of the
Surveyor, affects the Ship’s class, remedial 2.6.1 The following Characters and symbols are
measures and/ or appropriate conditions of assigned by IRS to indicate classification of
class are specified in order to retain class. Inland Waterways Vessels. (For explanation of
Conditions of class are requirements to the abbreviations, see Appendix I).
effect that specific measures, repairs,
surveys etc. are to be carried out within a 2.6.2 Character IWL indicates that the hull and
specified time limit in order to retain class. its appendages and equipment (i.e. anchors,
chain cable and hawsers) meet the Rule
2.3.3 On application by Builder or Owner, requirements for assignment of this Character of
certain installation, e.g. refrigerating machinery Class.
may be classed by IRS.
Guidance Note : Appendages to the hull referred
2.4 Interpretation of the Rules to in 2.6.2, 2.6.3 and 2.6.4 means the rudder &
rudder stock, rudder horn, sole pieces, propeller
2.4.1 The correct interpretation of the nozzles, shaft brackets, skeg etc. which are
requirements contained in the Rules and other covered by the rule requirements.
Regulations is the sole responsibility and at the
sole discretion of IRS. 2.6.3 Character IW (-) indicates that the hull and
its appendages meet the Rule requirements but
2.5 Definitions equipment (i.e. anchors, chain cable and
hawsers) is not supplied or maintained as per
2.5.1 Type Notation : A notation indicating that the relevant Rules but is considered by IRS to
the vessel has been designed and constructed be acceptable for particular service.
with applicable Rules to that type of vessel, e.g.
FERRY, BULK CARRIER , etc. 2.6.4 Character IW indicates that the hull and its
appendages meet the Rule requirements but
2.5.2 Cargo Notation : A notation indicating that where special consideration has been given for
the vessel has been designed, modified or reason of particular purpose of service and
arranged to carry one or more particular normal equipment may be unnecessary. In such
cargoes, e.g. "Phosphoric Acid". Vessels with cases letter 'L' is omitted from the Character
one or more particular cargo notations are not IWL.
thereby prevented from carrying other cargoes
for which they are suitable. 2.6.5 Character IY assigned to self-propelled
vessels indicates that the machinery meets the
2.5.3 Zone Notation : A notation indicating that rule requirements for assignment of this
a vessel has been classed on the understanding Character of Class.
that it will be operated in one of the zones
described below : 2.6.6 The distinguishing mark inserted before
Characters of Class (IWL, IW (-), IW, IY as
Zone 1 : A zone where the significant appropriate) is assigned to new vessels where
wave height does not exceed the hull and its appendages, equipment and the
2.0 [m]. machinery, as appropriate are constructed
2.6.7 The distinguishing mark inserted 2.8.3 Requirements in the following Chapters of
before a Character of Class (IWL, IW (-), IW, IY the HSC & LC Rules may be applied to such
vessels, as relevant and applicable:
as appropriate), is assigned to vessels admitted
into IRS Class during the course of construction
and surveyed by an IACS Society. a) Chapter 3: Materials of Construction
recognized by IRS. Alternatively, tests to the 2.12.2 Where a vessel is damaged to an extent
satisfaction of IRS will be required to resulting in towage outside port limits, it shall be
demonstrate the suitability of the steel. the Owners' responsibility to notify IRS at the
first practicable opportunity.
Consideration may be given by IRS to accept the
works approved by IACS Member Societies with 2.12.3 Where such repairs are effected at a port
whom IRS currently has Cooperation Agreements where there is no Surveyor of IRS, the vessel is
for this purpose. to be surveyed by one of its Surveyors at the
earliest opportunity.
2.10.2 Certification of materials, components,
equipment and machinery is carried out on basis 2.12.4 Where repairs to hull, machinery or
of the following: equipment, which affect or may affect
classification, are to be carried out by a riding
a) Type approval carried out by IRS. crew, they are to be planned in advance. A
complete repair procedure including the extent
b) Unit certification by IRS. of proposed repairs and the need for Surveyor's
attendance during the voyage is to be submitted
c) Alternative Certification Scheme by to and agreed upon by the Surveyor reasonably
IRS (see Pt. 1, Ch.1 Sec. 4 of the Rules in advance. Failure to notify IRS, in advance of
and Regulations for the Construction the repairs, may result in suspension of the
and Classification of Steel Ships). vessel's class.
2.16.1 The date of completion of the special 2.18.4 It is the responsibility of the owner to
survey inspection will normally be taken as the ensure that the validity of class and statutory
date of build to be entered in the Register Book. certificates is maintained.
Where there is a substantial delay between 2.18.5 IRS may consider requests for new
completion of construction survey and the construction vessels of less than 24 m in length
vessel commencing service, the date of for certification of compliance with the Rules
commissioning may be specified on the without assignment and maintenance of
classification certificate. classification. In such cases, IRS may issue a
certificate of compliance (valid for one year from
When modifications are carried out on a vessel, the date of issue) with the applicable design and
the initial date of build remains assigned to the construction requirements of the Rules, instead
vessel. of a Class certificate. Such vessels would not be
subjected to periodical surveys after
2.16.2 When a complete replacement or construction.
addition of a major portion of the vessel (e.g.
fwd. section, midship section or aft section) is 2.19 Suspension / withdrawal and deletion of
involved, the following applies: class
2.17.1 If the recommendations of the Surveyors 2.19.1.2 The class of a vessel will also be
are considered in any case to be unnecessary automatically suspended if the annual,
or unreasonable, appeal may be made to IRS, intermediate survey become overdue unless the
who may direct a special examination to be vessel is under attendance by the surveyor for
held. completion of survey. (See Ch.2, Table 1.1.1 for
class will be withdrawn and the notation "Class grounding or due to structural failure or due to
withdrawn" (with date) will be made in the actions of war or sabotage.
Supplement and the notation "IRS Class
withdrawn" (with date) will be made in the next 2.20.3 Vessel’s class will be deleted when it
reprint of the Register of Ships.. This entry will ceases to exist.
continue till the vessel’s class is reinstated or
deleted. 2.21 Reclassification of vessels
2.19.2.4 Procedure for withdrawal of class may 2.21.1 When Owners request for reclassification
be initiated if the vessel is found to be in breach of a vessel for which the class previously
of international sanctions or engaged in unlawful assigned has been withdrawn, IRS will require a
trading activities. Special Survey for Reclassification to be held by
the IRS Surveyors. The extent of the survey will
2.19.2.5 The withdrawal of a vessel will be depend upon the age of the vessel and the
confirmed in writing to the Owner and the circumstances of each case.
statutory authority, where applicable.
2.21.2 If the vessel is found or placed in good
2.20 Deletion of Class and efficient condition in accordance with the
requirements of the Rules and Regulations at
2.20.1 A vessel will be considered to “cease to the Special Survey for Reclassification, IRS may
exist” when it is destroyed by recycling or by decide to reinstate her original class or assign
sinking to unsalvageable depths or abandoned such other class as considered appropriate.
by the owner.
2.21.3 The date of reclassification will appear in
2.20.2 A vessel can also be considered to the supplement to the Register of Ships and the
“cease to exist” when it is broken up either by subsequent issue of Register of Ships.
Section 3
3.1 General procedure for classification of equipment showing the main scantling and
vessels not built under survey of IRS arrangements of the actual vessel and any
proposed alterations are to be submitted.
3.1.1 Plans of hull and machinery, as listed in
3.2.1 to 3.2.5 or equivalent, together with For approval
torsional vibration calculations, where
applicable, are to be submitted for approval. Loading Manual, where required
Alternative technical data in lieu of specific plans Midship section
or items may be accepted. It is preferable to Longitudinal section and decks
have the plans approved before the Shell expansion plan
classification survey is commenced. In case of Transverse Bulkheads
transfer of class from an IACS member society/ Sternframe
adding dual class with an IACS member society, Rudder and Rudder Stock
only copies of plans or equivalent (as listed in
Hatch Covers
3.2.1 to 3.2.5) are to be submitted to IRS
Fire detection, fighting and extinction
and such other plans as may be
3.1.2 Full special classification surveys would
requested.
require to be carried out by IRS Surveyors in
order to satisfy themselves regarding the Loading instrument details
workmanship and to verify the approved Stability booklet
scantlings and arrangements. The scope of Damage stability calculations, where
these surveys may, however, be modified in the required.
case of vessels built under the Special Survey
and holding valid certificates of class of For information
established classification societies, if prior to
commencement of survey by IRS, documentary General arrangement
evidence of all hull and machinery classification Capacity plan
surveys held by the other society subsequent to Hydrostatic Curves.
last special survey carried out by them could be
produced. In such cases, a special survey 3.2.2 It would normally be expected that
notation will not be assigned in conjunction with particulars of the process of manufacture and
the classification survey. The next special testing of material of construction are furnished.
survey therefore would become due five years Consideration will however be given to waiving
from the special survey held by the other society this where such particulars are not readily
and not five years from classification with IRS. available, provided it can be established that the
relevant vessel has been originally built under
3.1.3 When the required reports on completion special survey of an established classification
of such surveys have been received from the society and continues to be so classed with an
Surveyors and thereafter approved by IRS, they established classification society. In the case of
will be classed. Certificates of Class will be vessels which have been originally built under
issued and entered in the Register of Ships with the special survey of an established
the relevant characters of class and notation, classification society but subsequently not
but the mark signifying the survey during maintaining class, it should additionally be
construction will be omitted. possible to reasonably ascertain that no
changes that would significantly affect the
3.1.4 Once a vessel has been taken into IRS material specifications have taken place.
class, periodical surveys are subsequently to be
held as per these rules. 3.2.3 Following machinery plans together with
the particulars of the materials used in the
3.2 Plans and data to be furnished construction of the boilers, air receivers and
important forgings should be furnished:
3.2.1 Generally following plans of hull and
Appendix 1
Table of Characters Class and Type Notations of IRS, their Expanded Form and Significance
Abbreviation Significance
Characters Of Class
Denotes vessels which are classed with Indian Register of Shipping for
IWL operation in Inland Waterways where the hull and its appendages and
equipment (i.e. anchors, chain cables, hawsers) meet the Rule requirements.
Denotes vessels which are classed with IRS for operation in Inland Waterways
where the hull and its appendages meet the Rule requirements but the
IW (-)
equipment of vessel is not supplied or maintained as per the relevant Rules but
is considered by IRS to be acceptable for particular service.
Denotes vessels which are classed with IRS for Inland Waterways but where for
IW reason of their particular purpose or service normal equipment may be
unnecessary
Denotes that for self-propelled vessels the machinery installation complies with
IY
the applicable requirements of Indian Register of Shipping
This distinguishing mark inserted before a Character of Class is assigned to
new vessels where the hull and its appendages, equipment and the machinery
as appropriate, are constructed under special survey of IRS in compliance with
the Rules to the satisfaction of IRS.
The distinguishing mark inserted before a Character of Class (IWL, IW (-), IW,
IY as appropriate), is assigned to vessels admitted into IRS Class during the
course of construction and surveyed by an IACS Society
The distinguishing mark inserted before a Character of Class (IWL, IW (-), IW,
IY as appropriate), is assigned to vessels admitted into IRS Class at the time of
delivery of the vessel and constructed under the survey of an IACS Society
When a Class Notation is enclosed within brackets, it indicates that applicable
[ ]
arrangements exist on board but the notation has been temporarily suspended.
Appendix 1 – (Contd.)
Abbreviation Significance
Class Notations - Hull
Zone 1 A zone where the significant wave height does not exceed 2.0 [m].
Zone 2 A zone where the significant wave height does not exceed 1.2 [m].
Zone 3 A zone where the significant wave height does not exceed 0.6 [m].
Specified Operating Service within one or more geographical area(s) which will form part of the
Area Service Class Notation.
This will be entered in the Register of Ships where the scantlings and
"Strengthened for arrangements have been approved for heavier cargo loadings in any hold filled
heavy cargoes" up to the top of the hatch coaming with bulk cargo of density of at least upto 1.0
[t/m3].
Denotes that the examination of the ship's bottom and related items may be
INWATER SURVEY carried out while the ship is afloat in accordance with the applicable
requirements indicated in Pt.1, Ch.2.
This additional class notation will be assigned to a vessel having a class notation
TANK DESIGN 1
“TANKER” and using pressure tank for carrying cargo.
This additional class notation will be assigned to a vessel having a class notation
TANK DESIGN 2
“TANKER” and using closed tank for carrying cargo.
This additional class notation will be assigned to a vessel having a class notation
TANK DESIGN 3
“TANKER” and using open tank with flame arresters for carrying cargo.
This additional class notation will be assigned to a vessel having a class notation
TANK DESIGN 4
“TANKER” and using open tank for carrying cargo.
This additional class notation will be assigned to a vessel having a class notation
TANK TYPE 1
“TANKER” and using independent tank for carrying cargo.
This additional class notation will be assigned to a vessel having a class notation
TANK TYPE 2
“TANKER” and using integral tank for carrying cargo.
This additional class notation will be assigned to a vessel having a class notation
TANK TYPE 3 “TANKER” and using tanks whose walls are distinct from outer hull of the vessel
for carrying cargo.
Denotes that the vessel/ structure complies with the requirements of the IRS
EDD (X) Classification Note “Extended Dry-Docking Scheme”, and is fit for service with
an extended interval of ‘X’ years between successive dry-dockings.
Class Notations – Vessel Type and System
This notation will be assigned to vessels designed for the carriage of dry cargo
BULK CARRIER in bulk and built in accordance with the applicable requirements of Pt.5, Ch.1 of
the Rules for carriage of cargoes of density of at least 0.8 [t/m3].
This notation will be assigned to vessels specially designed for the carriage of
ORE CARRIER Ore and built in accordance with applicable requirements of Pt.5, Ch.1 of the
Rules.
This notation will be assigned to vessels intended for carriage of bulk cargo in
TANKER tanks built in accordance with applicable requirements of Pt.5, Ch.2 of the
Rules.
This additional class notation will be assigned to a vessel having a class notation
“TANKER” complying with the requirements of Part 5 Chapter 2, Section 5, 5.4 and
TYPE N
other relevant rule requirements. In general, TYPE N tankers are intended for the
carriage of flammable liquid and chemical cargoes in bulk.
This additional class notation will be assigned to a vessel having a class notation
“TANKER” complying with the requirements of Part 5 Chapter 2, Section 5, 5.5 and
TYPE C
other relevant rule requirements. In general, TYPE C tankers are intended for the
carriage of flammable liquid and chemical cargoes in bulk.
Appendix 1 – (Contd.)
Abbreviation Significance
This additional class notation will be assigned to a vessel having a class notation
“TANKER” complying with the requirements of Part 5 Chapter 2, Section 6 and other
TYPE G
relevant rule requirements. In general, TYPE G tankers are intended for the carriage
of gases in bulk.
PASSENGER This notation will be assigned to vessels intended for the carry more than 12
VESSEL passengers and built in accordance with Pt.5, Ch.3 of the Rules.
This additional notation will be assigned to vessels on regular scheduled
FERRY
service.
This additional notation will be assigned to a vessel having a class notation
RO-RO PAX “PASSENGER VESSEL” intended for carriage of passengers and vehicles and
built in accordance with Pt.5, Ch.3, Sec 6 of the Rules
This additional notation will be assigned to a vessel having a class notation
PRM “PASSENGER VESSEL” in which areas are provided for use by persons with
reduced mobility, according to the provisions of Pt.5, Ch.3, Sec 7 of the Rules.
This notation will be assigned to all vessels built in accordance with applicable
TUG
requirements of Pt.5, Ch.4 of the Rules.
This notation will be assigned to non-self- propelled, manned or unmanned
vessels carrying dry cargo in cargo holds and built in accordance with
BARGE
applicable requirements of Pt.5, Ch.5 of the Rules. For special purpose vessels,
the Notation will be suitably modified, e.g. Shipborne Barge
This notation will be assigned to non-self- propelled, manned or unmanned
vessels designed specifically for the carriage of non-perishable cargo or
PONTOON equipment on deck and built in accordance with the applicable requirements of
Pt.5, Ch.5 of the Rules. For special purpose vessels, the Notation will be
suitably modified, e.g. Crane Pontoon
This additional class notation would be assigned, where the vessel is designed and
constructed primarily for using natural gas as fuel, and complying with the
requirements of IRS Classification Note “Natural Gas Fueled Vessels for Coastal
LFPF(NG)(SFE) and Inland Waters”.
LFPF(NG)(DFE) An additional qualifier will be assigned to identify the engine type used as follows:
(SFE) – Single Fuel Engine
(DFE) – Dual Fuel Engine
This additional class notation would be assigned, where the vessel is designed and
constructed primarily for using methanol as fuel, and complying with the
LFPF(ML)(SFE) requirements of IRS “Guidelines on Methanol Fueled Vessels”
An additional qualifier will be assigned to identify the engine type used as follows:
LFPF(ML)(DFE) (SFE) – Single Fuel Engine
(DFE) – Dual Fuel Engine
The additional notation BATTERY PROP will be assigned to vessels where the
BATTERY PROP battery systems are used for propulsion and are in accordance with the ‘Guidelines
on Battery Powered Vessels’.
This notation will be assigned to Inland vessels engaged in operations in fair
INDIAN INSHORE weather season during the fair weather; within 5 nautical miles from the base
TRAFFIC line or upto 2 meters of significant wave height condition, whichever is less.
CORRIDOR Such Inland vessels are to comply with the DGS Order 08 of 2018. The DGS
VESSEL Order 08 of 2018 stipulates minimum compliance criteria for issuance of
“Statement of Compliance” (SOC).
This additional notation will be assigned to vessels engaged in ship-to-shore
operations at Indian ports beyond inland water limits of the said port, provided
that such operation is carried out in fair weather and against a favorable
INDIAN RIVER SEA
weather forecast. Vessels falling under this Type, while engaged in ship-to-
VESSEL-TYPE 1
shore operations at an Indian port, shall operate within territorial waters of India.
These vessels are covered by and are to comply with the DGS Order No.18 of
2013.
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 17 of 17
___________________________________________________________________________________
Appendix 1 – (Contd.)
Abbreviation Significance
This additional notation will be assigned to vessels engaged in operations
between Indian ports in which the sea passage does not exceed that can be
covered by a fully loaded vessel at the vessel’s optimum speed in daylight
INDIAN RIVER SEA
hours, provided that such operation is carried out in fair weather and against a
VESSEL-TYPE 2
favorable weather forecast. Vessels falling under this Type shall, at all times,
operate within the territorial waters of India. These vessels are covered by and
are to comply with the DGS Order No.18 of 2013.
This notation will be assigned to self-elevating platforms operating in inland
water ways, which are normally used for assisting in construction projects. The
leg structure and associated items of these platforms are to comply with the
SELF ELEVATING
requirements for Rules and Regulations for the Construction and Classification
PLATFORM
of Mobile Offshore Drilling Units. Self-elevating platforms that are self-propelled
would be assigned additional qualifier ‘SELF PROPELLED’ and are to comply
with the relevant requirements of these Rules.
The notation ‘Hopper Barge’ will be assigned to non-self-propelled vessels
operating in Inland Waterways designed and constructed for the carriage and
discharge of rocks, sand, spoil in the hopper. The notation ‘Split Hopper Barge’
HOPPER BARGE/ will be assigned to vessels which are similar to hopper barges but with
SPLIT HOPPER arrangements for discharging the spoil through the bottom of the ship by means
BARGE of split hull, separated at the hinges using actuating devices. Requirements of
Pt.5, Ch. 10 of the Rules and Regulations for the Construction and
Classification of Steel Ships with appropriate reductions in external loads, as
applicable to the vessel operating in Inland Waterways; are to be complied with.
End of Chapter
Chapter 2
Periodical Surveys
Contents
Section
1 General Requirements
2 Hull Surveys
3 Machinery Surveys
4 Surveys – Dredgers
5 Surveys – Liquefied Gas Carriers
Section 1
General Requirements
1.1 General
Table 1.1.1 : Periodical Survey intervals for
1.1.1 All vessels are to be subjected to Main class notations
Periodical Surveys for the purpose of
maintenance of class. Survey notations and Survey Main class Survey
Survey intervals are given in Table 1.1.1 for Survey interval in
main class Surveys. Notation years
Special Survey; SSH 5
1.1.2 Vessels with additional class notations for Hull
which there are no specific Survey requirements Special Survey; SSM 5
in this Chapter are to have the equipment and/or Machinery
construction related to this additional class Intermediate IS 2.51
notation examined to the Surveyor's satisfaction Survey
at each Special Survey. Annual Survey AS 12
re-activation. Humidity levels in machinery other equipment in use depending on the type of
spaces are to be recorded on a regular basis lay-up.
during the lay-up period, together with
scheduled equipment maintenance and 1.2.3 Survey at re-activation
operation.
1.2.3.1 Vessels are to be surveyed and tested
1.2.1.6 The requirements of flag Administrations before re-entering service. On completion of the
and port or maritime authorities regarding lay-up lay-up period, all outstanding class and statutory
are also to be complied with surveys are to be completed before the vessel
returns to normal operation.
1.2.1.7 During lay-up, the vessel is also to
comply with the following: 1.2.3.2 For vessels in hot lay-up, the scope of
the reactivation survey is to include:
a) The vessel is to be adequately manned in
accordance with the statutory requirements - a general examination of the hull, deck
prevailing at the location of lay-up. fittings, safety systems, machinery
installations (including boilers whose survey
b) Adequate power is to be available on board is not due) and steering gear;
to meet the following requirements, as
applicable: - - all periodical surveys due at the date of re-
activation or which became overdue during
- firefighting; the lay-up period;
- bilge pumping;
- lighting; - dealing with the Conditions of Class due at
- communication with shore; the date of re-activation or which became
- needs of crew on board, and due during the lay-up period.
- operating anchor and mooring winches
within a reasonable time. Function testing of equipment would be specially
considered.
The listed items are generally applicable for hot
lay-up. For cold lay-up, arrangements may be 1.2.3.3 The extent of the surveys and tests for
specially considered. vessels in cold lay-up will be considered in each
case by IRS depending upon the time out of
1.2.2 Surveys during lay-up service, the maintenance and preservative
measures taken during lay-up and the extent of
1.2.2.1 Lay-up survey surveys carried out during this time but, will at
least include a sea trial for function testing of the
.1 A lay-up survey is to be carried out at the machinery installation.
beginning of the lay-up period to verify that the
safety conditions, preservation measures, lay-up 1.2.3.4 Upon satisfactory completion of the re-
site and mooring arrangements are in activation survey, the Class of the vessel will be
accordance with the lay-up program approved revalidated.
by IRS.
1.3 Surveys for damage or alterations
.2 On successful completion of the survey, a lay-
up status will be assigned by IRS. 1.3.1 At any time when a ship is undergoing
alterations or damage repairs, any exposed
1.2.2.2 Annual lay-up condition surveys parts of the structure normally difficult to access
are to be specially examined, e.g. if any part of
.1 A general examination of the hull and the propulsion or auxiliary machinery, including
machinery is to be carried out in lieu of annual boilers, insulation or fittings, and tanks not
survey. An underwater examination is to be forming part of the ship’s structure, is removed
carried out in lieu of docking survey coinciding for any reason, the steel structure in way is to be
with special survey. carefully examined by the Surveyor, or when
cement in the bottom or covering on decks is
The purpose of the annual lay-up condition removed, the plating in way is to be examined
survey is to ascertain that the lay-up before the cement or covering is relaid.
maintenance program is being continuously
complied with and recorded in the lay-up record. 1.4 Unscheduled Surveys
.2 The annual lay-up condition survey is to cover
examination of hull integrity, firefighting 1.4.1 In the event that IRS has reason to believe
arrangements, mooring arrangements, and that its Rules and Regulations are not being
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 3 of 17
___________________________________________________________________________________
complied with, IRS reserves the right to perform (e) Portable ladders may be used, at the
unscheduled surveys of the hull or machinery. discretion of the Surveyor.
1.5 Provision for surveys 1.5.7 Where soft coatings have been applied,
safe access is to be provided for the Surveyor to
1.5.1 The Surveyors are to be provided with verify the effectiveness of the coating and to
necessary facilities for a safe execution of carry out an assessment of the conditions of
survey. In order to enable the attending internal structures which may include spot
surveyors to carry out the survey, provisions for removal of the coating. When safe access
proper and safe access, are to be agreed cannot be provided, the soft coating is to be
between the owner and IRS in accordance with removed.
confined space safe entry procedure of IRS and
IMO Resolution A1050(27) ‘Revised 1.5.8 A survey planning meeting is to be held
recommendations for entering enclosed spaces prior to the commencement of Intermediate
abroad ships’, as amended. Details of the Survey and Special Survey.
means of access are to be provided in the
survey planning questionnaire. In cases where 1.6 Repairs
the provisions of safety and required access are
judged by the attending surveyor(s) as not 1.6.1 Any damage in association with wastage
adequate, the survey of the spaces concerned over the allowable limit (including buckling,
would not be carried out. grooving, detachment or fracture), or extensive
areas of wastage over the allowable limits,
1.5.2 Tanks and spaces are to be safe for which affects or, in the opinion of the Surveyor,
access, i.e. gas freed, ventilated and will affect the ship's structural, watertight or
illuminated. weathertight integrity, is to be promptly and
thoroughly repaired. Areas to be considered
1.5.3 In preparation for survey and thickness include (where fitted):
measurements, all spaces are to be cleaned
including removal from surfaces of all loose • side shell frames, their end
accumulated corrosion scale. Spaces are to be attachments and adjacent shell plating;
sufficiently clean and free from water, scale, dirt,
oil residues, etc. to reveal corrosion, • deck structure and deck plating;
deformation, fractures, damages or other
structural deterioration. However, those areas of • bottom structure and bottom plating;
structure whose renewal has already been
decided by the owner need only be cleaned and • side structure and side plating;
descaled to the extent necessary to determine
the limits of renewed areas. • inner bottom structure and inner
bottom plating;
1.5.4 Sufficient illumination is to be provided to
reveal corrosion, deformation, fractures, • inner side structure and inner side
damages or other structural deterioration. plating;
1.5.6 For surveys, including close-up survey For locations where adequate repair facilities
where applicable, in cargo spaces and ballast are not available, consideration may be given to
tanks, one or more of the following means of allow the ship to proceed directly to a repair
access is to be provided: facility. This may require discharging the cargo
and/or temporary repairs for the intended
(a) Permanent staging and passages voyage.
through structures.
1.6.2 Additionally, when a survey results in the
(b) Temporary staging and passages identification of structural defects or corrosion,
through structures. either of which, in the opinion of the Surveyor,
will impair the ship's fitness for continued
(c) Lifts and movable platforms. service, remedial measures are to be
implemented before the ship continues in
(d) Boats or rafts. service.
Section 2
Hull Surveys
2.1 Special surveys (hull) completed. In the case where a Special Survey
is spread over a period and is not carried out at
2.1.1 All ships classed with IRS are to undergo one time the date assigned for such a Survey
Special Surveys at 5 yearly intervals. The first will correspond to the date when the principal
Special Survey becomes due five years after the part of the Survey has been completed. IRS will
date of build or date of Special Survey for decide when the principal part of the Survey is
classification and the subsequent Special deemed to have been completed. Record of
Surveys become due 5 years after the assigned Special Survey will not be assigned until the
date of the previous Special Survey. engine Survey has been completed.
2.1.2 The interval between the Special Surveys 2.1.8 IRS may, at the request of the Owners,
may be reduced at the request of the parties accept a Special Survey of hull on a continuous
concerned or by IRS if deemed appropriate. basis spread over a period of 5 years. Proposals
for such continuous Surveys are to be submitted
2.1.3 For surveys completed within 3 months for the consideration of IRS. In general,
before expiry date of Special Survey, the next approximately one fifth of the Special Survey is
period of class will start from the expiry date of to be completed every year. All compartments of
the Special Survey. For surveys completed the hull should be opened for survey and testing
more than 3 months before the expiry date of in rotation such that not more than 5 years
the Special Survey, the period of class will start elapse between consecutive examination of
from the survey completion date. each part.
2.1.4 The Special Survey may be commenced 2.2 Requirements of special surveys
at the 4th Annual Survey and be progressed
with a view to completion by the 5th Annual 2.2.1 General
Survey.
2.2.1.1 Survey requirements
2.1.5 Record of Special Survey will not be
assigned until the Machinery Survey has been 2.2.1.1.1 The requirements of intermediate
completed. survey are to be complied with as applicable.
The ship is to be placed in drydock or on a
2.1.6 As part of the preparation for Special slipway, cleaned and be at a sufficient height
Survey, the thickness measurement and Survey above the dockfloor or the ground for
Programme should be dealt with, in advance of examination of shell plating, sternframe,
the Special Survey. The thickness measurement rudders, etc. If necessary, proper staging is to
is not to be held before the 4th Annual Survey. be erected for this examination. Each rudder is
to be lifted for examination of pintles if
2.1.7 Upon satisfactory completion of a Special considered necessary by the Surveyor.
Survey a record will be entered in the
supplement to the Register of Ships indicating 2.2.1.1.2 The holds, tween decks, deep tanks,
the month and the year in which the Survey is peaks, bilges and drain wells, engine and boiler
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 5 of 17
___________________________________________________________________________________
spaces, coal bunkers and other spaces are to special attention being paid to the tanks under
be cleared out and cleaned as necessary and boiler spaces.
examined. Floor plates in engine and boiler
spaces are to be lifted as may be necessary for Tanks, other than the peak tanks, which are
examination of the structure underneath. used exclusively for oil fuel or freshwater or
lubricating oil in ships less than 15 years old
Where necessary close and spar ceiling, lining need not be examined internally provided upon
and pipe casings are to be removed for external examination and testing of the tanks,
examination of the structure. the Surveyor finds their condition to be
satisfactory.
2.2.1.1.3 In ships with single bottom, a sufficient
amount of close ceiling is to be lifted to enable 2.2.1.1.10 Spaces which are inaccessible for
examination of the structure below. The ceiling examination, e.g. low double bottom tanks,
to be lifted is to comprise of at least two strakes boxed in web frames, spaces under tanks not
on each side of centreline fore and aft and one forming part of the ship’s structure are to be
of these strakes is to be in way of the bilges. examined externally and gauged as necessary.
In case of doubt, openings are to be made in the
2.2.1.1.4 In ships having double bottom, a structure for examination of the interior so that
sufficient amount of ceiling is to be lifted from the Surveyor can satisfy himself as to the
the tank top and the bilges to enable the efficient condition of the structure.
condition of plating underneath to be
ascertained. If the condition of the plating is 2.2.1.1.11 All decks, casings and
found to be satisfactory, lifting of the remainder superstructures are to be examined. Attention is
of the ceiling may be dispensed with. All bilges to be given to the corners of openings and other
are to be cleaned for examination. discontinuities in way of the strength decks and
top sides.
Where the inner bottom plating is covered with
cement or asphalt the removal of such covering Wooden decks or sheathings are to be
may be dispensed with provided it is found to be examined and if decay or rot is found or the
adhering properly to the plating when carefully wood is excessively worn, the wood is to be
examined by hammering and chipping. renewed.
2.2.1.1.5 All watertight bulkheads are to be Attention is to be given to the condition of the
examined. plating under wood decks, sheathing or other
deck coverings. If it is found that such coverings
2.2.1.1.6 The steelwork is to be exposed and are broken, or are not adhering closely to the
cleaned as may be required for its proper plating, sections are to be removed, as
examination by the Surveyor and close attention necessary, to ascertain the condition of the
is to be paid to the parts of the structure which plating.
are particularly liable to excessive corrosion or
to deterioration due to other causes. 2.2.1.1.12 Where holds are insulated for the
carriage of refrigerated cargoes and the hull in
2.2.1.1.7 The Surveyor may require to way was examined by IRS Surveyors prior to
determine thickness of the material where the fitting of the insulation, it will be sufficient to
wastage is evident. Any parts of the structure remove the limbers and hatches for examination
which are found defective or materially reduced of the structure in way. In all other cases
in scantlings are to be made good by materials additional insulation will require to be removed
of approved scantlings and quality. Particular as considered necessary to enable the Surveyor
attention is to be paid to structure in way of to satisfy himself regarding condition of the
discontinuities. Surfaces are to be re-coated as structure.
necessary.
2.2.1.1.13 The masts, standing rigging and
2.2.1.1.8 Double bottom compartments, peak anchors are to be examined. Chain cables are
tanks and all other tanks are to be tested to be ranged for examination. Chain cables
hydrostatically by a head sufficient to give the which are worn to 12 per cent or more of the
maximum pressure that can be experienced in original rule diameter are to be renewed.
service.
The Surveyor should satisfy himself that there
2.2.1.1.9 Tanks, forming part of the main are appropriate mooring ropes on board and
structure, except as stated below, are to be also that a towline is provided when this is a
thoroughly cleaned and examined internally, Rule requirement.
2.2.1.1.14 The steering gear, and its gratings are to be examined. The clearance in
connections and control systems (main and each sternbush or the efficiency of each
alternative) are to be examined. The various sterngland is to be ascertained.
parts of the auxiliary steering gear are to be
assembled, examined and tested. The helm 2.2.1.1.18 Where any alterations are made to a
indicator is to be examined and tested. vessel, which materially affect the stability, the
vessel is to be re-inclined.
2.2.1.1.15 The windlass, hand pumps and
suctions, watertight doors, air and sounding 2.2.1.1.19 At special surveys, a lightweight
pipes are to be examined. Whilst examining the survey is to be carried out on all passenger
tanks internally, the Surveyors are to ensure that vessels to verify and record any changes in
striking plates are fitted under the sounding lightship displacement and longitudinal centre of
pipes . gravity.
2.2.1.1.16 The Surveyor should satisfy himself 2.2.1.1.20 The vessel is to be re-inclined
regarding the efficient condition of the following. whenever, in comparison with the approved
stability information, a deviation from the
Means of escape from machinery lightship displacement exceeding 2% or a
spaces, crew and passenger spaces and deviation of the longitudinal centre of gravity
spaces in which crew are normally exceeding 1% of the rule length is found, or
employed; anticipated.
Special Survey No. I Special Survey No. II Special Survey No. III Special Survey No. IV
(Age ≤ 5 years ) (5 < Age ≤ 10 years) (10 < Age ≤ 15 years) (Age > 15 years)
Critical areas, as Within the cargo area Within the cargo area Within the cargo area
required by the or 0.5L amidships: or 0.5L amidships: or 0.5L amidships:
Surveyors
‐ Selected deck ‐ Each exposed deck ‐ Each deck plate
plates plate ‐ Three transverse
‐ One transverse ‐ Two transverse sections 3
section sections ‐ Each bottom / inner
‐ Selected bottom / ‐ Selected tank top bottom / tank top
inner bottom plates plates plate
‐ Selected side shell ‐ Each bottom / inner ‐ All side shell plates
plates bottom plates ‐ All transverse and
‐ Selected hatch ‐ All side shell plates longitudinal cargo
covers and ‐ Selected hold bulkheads1
coamings1 transverse and ‐ All hatch covers
‐ Critical areas, as longitudinal cargo and coamings1
required by the hold bulkheads1 ‐ Critical areas, as
Surveyor ‐ All hatch covers required by the
and coamings1 Surveyor
‐ Critical areas, as
required by the
Surveyor
Special Survey No. I Special Survey No. II Special Survey No. III Special Survey No. IV
(Age ≤ 5 years ) (5 < Age ≤ 10 years) (10 < Age ≤ 15 years) (Age > 15 years)
Outside the cargo area: Outside the cargo area:
‐ Selected side shell ‐ Each deck plate
plates ‐ Each side shell
‐ Selected bottom plate
plates ‐ Each bottom plate
‐ Nozzle plating in ‐ Nozzle plating in
way of transverse way of transverse
thrust units thrust units
2.2.1.2.3 In areas where substantial corrosion 2.2.1.2.6 Where a 10 per cent area reduction of
(defined as wastage of individual plates and deck plating and longitudinals is exceeded, a
stiffeners in excess of 75 per cent of allowable check of the buckling capacity of the upper deck
margins, but within acceptable limits) has been is to be carried out for all tankers.
noted, additional measurements are to be
carried out, as deemed necessary by the 2.2.2 Special survey of ships over 15 years
attending Surveyor. old
The lifting of the ceiling is to comprise of at least be examined together with their attachments to
three strakes all fore and aft on each side and the structure. The condition of internal coatings,
one such strake on each side to be in way of the if applied, is to be examined.
bilges. Where the ceiling is fitted in hatches, the
whole of the hatches and at least one strake of 2.2.3.7 All cargo tanks are to be tested at
planks in way of the bilges on each side are to Special Surveys by filling the tanks with liquid to
be lifted. If the Surveyor considers it necessary the top of the hatch coaming. Tanks may be
the whole of the ceiling and the limber boards tested when the ship is afloat provided the
are to be lifted. internal examination of the bottom is also carried
out afloat.
2.2.2.3 In ships with double bottom, sufficient
amount of ceiling is to be lifted for the 2.2.3.8 Where extensive repairs have been
examination of the inner bottom plating, pillar effected to the shell plating or bulkheads, the
feet bottom plating of bulkheads, tunnel side tanks should be tested to Surveyor's
plating and the structure in way of the bilges. If satisfaction.
the Surveyor considers it necessary the whole of
the ceiling is to be lifted. 2.2.3.9 Where corrosion control arrangements
have been adopted, satisfactory evidence of
2.2.2.4 Chain locker is to be cleaned and continued effectiveness is to be verified.
examined internally.
2.2.4 Tankers with cargo tanks independent
2.2.2.5 The thickness of bottom plating in way of from the ship’s structure
cement is to be ascertained unless the
Surveyor, after an internal and external 2.2.4.1 The requirements of 2.2.1, 2.2.2, 2.2.3.3,
examination, is entirely satisfied that this is 2.2.3.6 and 2.2.3.7 are to be complied with so
unnecessary. Selected portions of cement are to far as applicable.
be removed from the bottom and bilge if
required by the Surveyor. 2.2.4.2 Special attention is to be paid to the
ship’s structure underneath the cargo tanks and
2.2.3 Tankers the supports, securing arrangements, etc. of
these tanks.
2.2.3.1 The requirements of 2.2.1 and 2.2.2 are
to be complied with as applicable. 2.2.4.3 All cargo tanks are to be tested by filling
the tanks with liquid to the top of the hatch
2.2.3.2 The survey is to include the inspection of coaming. Cofferdams and cargo tanks of
pump-rooms, cargo, bunker and vent piping tankers of Type G, C and N, are to be pressure
systems on deck and in pumprooms, and also tested with liquid to the top of the hatch
pressure/vacuum valves and flame arresters coaming.
2.2.3.3 All cargo tanks and cofferdams are to be 2.2.4.4 The requirements of 2.2.1.2 are to be
thoroughly cleaned and cleared of gas at each complied with for the hull structure at Special
Special Survey before inspection and every Survey II (ships 10 years old) and at each
precaution is to be taken to ensure safety during Special Survey thereafter. In order to determine
inspection. Access is to be arranged to any part the general diminution in thickness, cargo tanks
of the tank as considered necessary by the independent from the ship’s structure are to be
Surveyor to enable him to ascertain the gauged.
condition of the structure within the tanks.
The gauging is to be done in at least one place
2.2.3.4 Attention is to be given to the inside of on each tank (in two places on each tank over
the bottom plating for excessive pitting and 20 [m] in length) in each strake of bottom,
where extensive pitting is found requisite forward and aft, side and top plating. The
renewals or repairs are to be carried out to remainder of the plating is to be gauged as
preserve the longitudinal strength of the bottom. deemed necessary by the Surveyor, taking into
account the results of gauging already carried
2.2.3.5 The strums of the cargo suction pipes out.
are to be removed to facilitate examination of
the shell plating and bulkheads in that vicinity, 2.3 Intermediate surveys
unless other means for visual inspection of
these parts are provided. 2.3.1 Preparations for Survey
2.2.3.6 Where fitted, anodes in tanks and 2.3.1.1 The ship is to be brought in to light
cofferdams within the cargo tank spaces are to condition for internal and external examination
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 9 of 17
___________________________________________________________________________________
afloat. All ships operating at sea ports and other damage by contact with other vessels, quay
ships over 20 years of age are to be examined walls or from causes such as chafing, touching
in drydock or on a slipway. In the case of ships or lying on the ground and to any undue
over 20 years old and not operating at sea ports unfairness of bottom plating, especially in
this requirement may be waived, if following an transversely framed ships.
internal examination, the Surveyor is satisfied as
to the efficient condition of the underwater part 2.3.2.4 The Surveyor is to thoroughly examine
of the shell. the following parts and also ensure the efficient
condition of their respective closing appliances:-
2.3.1.2 When the ship is in dry dock or on a
slipway, it is to be at a sufficient height above a) Inert gas plant overboard discharge
the dock floor or the ground for examination of when passing through the shell, so far
shell plating, sternframe, rudder(s), etc. If as practicable.
necessary proper staging is to be erected for
this examination. Each rudder is to be lifted for b) Vent piping, including that of inert gas
examination of pintles if considered necessary installation, where applicable, within
by the Surveyor. cargo tank area together with
associated flame arresters and
2.3.1.3 The decks, hatchways with beams and pressure/vacuum valves and cargo and
covers are to be cleared for examination. bunker deck piping of tankers.
2.3.1.4 The steering gear and auxiliary steering c) Watertight bulkhead penetrations as
gear are to be prepared for examination and far as practicable.
testing.
d) Hatchways with beams and covers,
2.3.1.5 Tankers of Type G, C and N, when deck houses and companionways
submitted for the survey are to be thoroughly together with any closing appliances.
cleared of gas.
e) Scuppers and sanitary discharges so
2.3.1.6 Stream anchor, when provided, is to be far as practicable, bulwarks and guard
prepared for examination and testing. rails.
2.3.2.3 When the ship is placed in dry dock or 2.3.2.10 The various parts of the auxiliary
on a slipway, the Surveyor is to examine the steering gear are to be assembled to ascertain
shell plating, the sternframe, rudder(s), etc. and that the gear is in good and workable condition.
attention is to be given to those underwater Auxiliary steering gear of the mechanically
parts of the ship particularly liable to driven type is to be examined and tested to
deterioration due to excessive corrosion or to demonstrate that, if the power for the main
Indian Register of Shipping
Chapter 2 Part 1
Page 10 of 17 Periodical Surveys
steering gear fails, the auxiliary gear can be put a) Hatchways on freeboard and superstructure
into operation immediately. decks, ventilator and air pipe coamings,
exposed casings, skylights, deckhouses and
2.3.2.11 The Surveyor is to examine and test companionways, superstructure bulkheads,
bow rudder installations when they are an side scuttles and deadlights, together with
essential part of the steering arrangement. all closing appliances.
Opening up the gear may be required if deemed
necessary by the Surveyor in view of the b) Means of ensuring weathertightness of steel
condition or the testing of the gear. hatch covers by hose test if deemed
necessary.
2.3.2.12 Where rod and chain steering gear is
fitted, attention is to be paid to all parts of rod c) Scuppers and sanitary discharges with
and chain gears. All pins are to be examined valves; guard rails and bulkwarks; freeing
and the chain in the vicinity of the blocks is to be ports, gangways and lifelines.
cleaned and examined for wear and tear. Any
length of chain so worn that its mean diameter d) Freeboard marks.
at its most worn part is reduced by 12 per cent
or more from its Rule diameter, is to be e) General examination of machinery and
renewed. All replacements of chains are to be steering gear.
subjected, at approved Works, to the proof tests
required for short link cables by the Rules and f) Vent piping, including that of inert gas
the certificates are to be produced. It is installations, where applicable, within cargo
recommended that, in addition, a breaking test tank area, together with associated flame
be applied to these chains. arresters and pressure/vacuum valves, also
cargo and bunker deck piping of tankers.
2.3.2.13 It is recommended that repaired chains
be tested by the repairers and a certificate to 2.4.1.2 Additionally, following is to be examined
that effect produced. in case of tankers :
2.3.2.14 All the means of communication a) The efficiency of any safe type equipment
between the navigating bridge and the fiited.
machinery control positions, as well as the
bridge and the alternative steering position, if b) The insulation resistance.
fitted, are to be tested.
c) Effectiveness of earth bonding straps,
2.3.2.15 On tankers of type G, C and N Closed where fitted.
and N Open with flame arrestors, pump rooms,
cargo, bunker and vent piping systems on deck d) General examination of inert gas system;
and in pump rooms, pressure/vavuum valves flame arresters, pressure/vacuum valves;
and flame arresters and electrical installations cargo and bunker piping.
are also to be inspected including verification of:
2.4.2 Passenger Ships
a) The efficiency of any safe type equipment
fitted; 2.4.2.1 The ship is to be examined afloat in light
condition internally and externally, as far as
b) Insulation resistance. practicable.
c) Tests are to be carried out to demonstrate the 2.4.2.2 It may be necessary to dry-dock the ship
effectiveness of earth bonding straps, where or place it on a slipway for a more detailed
fitted. examination, if the afloat examination gives rise
to doubts as to the condition of the underwater
d) Inert gas system including alarms and safety structure or of tanks and cofferdam spaces.
devices, is to be tested to demonstrate that it is
in good working condition. 2.4.2.3 Where the ship is placed in dry dock or
on a slipway, the shell plating, the stern frame,
2.4 Annual surveys rudder(s), etc. are to be examined and attention
is to be given to those underwater parts of the
2.4.1 General ship particularly liable to deterioration due to
excessive corrosion or to damage by contact
2.4.1.1 The Surveyor is to satisfy himself with other vessels, quay walls or from causes
regarding the efficient condition of the following : such as chafing, touching or lying on the ground
Section 3
Machinery Surveys
3.1.2 Requirements of survey 3.1.2.3.1 All shafts, thrust block(s) and all
bearings and their seating are to be examined.
3.1.2.1 Main engines of internal combustion The lower halves of bearings need not be
type exposed if alignment and wear are found
acceptable.
3.1.2.1.1 The following parts are to be opened
out and examined. These should include all 3.1.2.4 Auxiliary machinery
cylinders, cylinder heads, covers valves and
valve gear, pistons, piston rods, cross heads, 3.1.2.4.1 All auxiliary machinery for essential
guides, connecting rods, crankshafts, vibration services is to be examined as considered
dampers and all bearings, bedplates, camshafts necessary by the Surveyor. Opening of
and driving gear, fuel pumps and fittings, machinery may be required if considered
scavenge pumps, scavenge blowers and their necessary by the Surveyor. Alarms and safety
prime movers, superchargers, air compressors, devices fitted on these units are to be included
intercoolers, clutches, reverse gears, crankcase in this Survey. The machinery is to include the
door fastenings and explosion relief devices and following :
such other parts of the machinery as may be
considered necessary. Integral piping systems Auxiliary engines, air compressors
are to be examined. The manoeuvring of together with all attached coolers, filters
engines is to be tested under working condition. and/or oil separators and safety devices,
In case of multi-engine installations, alternative and all pumps and components used for
survey proposals may be considered by IRS. essential services.;
3.1.2.6.3 In case where it is considered 3.1.2.8.1 All air receivers and other pressure
necessary, the parts subjected to pressure are vessels for essential services together with their
to be hydraulically tested and the thickness of mountings and safety devices are to be cleaned
plates and size of stays ascertained to internally and examined internally and
determine the safe working pressure. Collision externally. If an internal examination of an air
chocks, rolling stays and boiler stools are to be receiver is not practicable it is to be tested
examined and maintained in efficient condition. hydraulically to 1.3 times the working pressure.
The shell plating in way of welded lugs or
fabricated feet are to be carefully examined at 3.1.2.8.2 Selected pipes in the starting air
each Survey. Insulation and sheathing in way systems are to be removed for internal
are to be removed as considered necessary for examination and hammer tested. If an
this purpose. appreciable amount of lubricating oil is found in
the pipes the starting air system is to be
In fired boilers employing forced circulation the thoroughly cleaned by steaming or other
pumps used for this purpose are to be opened suitable means. Some of the pipes selected are
and examined at each boiler Survey. to be those adjacent to the starting air valves at
the cylinders and to the discharges from the air
3.1.2.6.4 The proper operation of the water level compressors.
indicators and safety devices are to be
confirmed at each Survey and the boiler is to be 3.1.2.9 Pumping and piping system
examined under steam and its safety valves are
to be adjusted to a pressure not greater than 3 3.1.2.9.1 The valves, cocks and strainers of the
per cent of the approved working pressure. The bilge system including bilge injection are to be
oil fuel burning system is to be examined under opened up as considered necessary by the
working conditions and a general examination Surveyor and, together with pipes, are to be
made of the fuel tank valves, pipe, deck control examined and tested under working conditions.
gear and oil discharge pipes between pumps Non-metallic flexible expansion pieces in the
and burners. main salt water circulating system are to be
examined. If non-return valves are fitted in hold
3.1.2.7 Survey of steam pipes bilges, these be opened up for examination.
Section 4
Surveys - Dredgers
4.1 General
(d) Attention is to be given to shell
4.1.1 This section provides additional survey plating in way of hopper overflows.
requirements for dredgers. Where surveys are
required on dredging or hopper equipment such (e) The attachment to the ship’s
as gantries, bottom doors and their operating structure of all main items of dredging
gear, positioning spuds and suction pipe equipment, including gantries, ‘A’
attachments, these will be limited to the extent frames and spud control gear supports,
considered necessary by the Surveyor to be is to be carefully examined to ensure
satisfied that their condition or malfunction will that no fracture is present.
not adversely affect the ship’s structure.
4.2.2 On ships over 10 years old:
4.1.2 When the ship is placed in dry dock or on
a slipway, the Surveyor is to examine the (a) Attention is to be given by the
hopper doors or hopper valves, ladders, spud Surveyor to the structure in way of
wells, and their fittings where applicable. dredging pumps.
Section 5
5.2.2.7 The Surveyor is to satisfy himself that all 5.3.1.5 Where applicable, inert gas systems for
pressure relief valves and/or safety discs the environmental control of cargo tanks and/or
throughout the system are satisfactorily spaces surrounding the cargo tanks are to be
operational. Primary refrigerant pressure relief generally examined.
valves are not to be tested onboard ship.
5.3.1.6 Where applicable, control devices for the
5.2.3 Special Survey of Ships over 10 years cargo containment system and cargo handling
old equipment, together with any associated shut-
down and/or interlock, are to be checked under
5.2.3.1 All pressure vessels of inert gas simulated working conditions, and if required,
installations are to be examined internally and recalibrated.
externally and tested.
5.3.1.7 The arrangements for manually operated
5.2.3.2 Cargo tanks are to be pressure tested to emergency shut-down are to be checked to
a pressure of 1.25 times the working pressure. ascertain they are in working order.
5.3 Intermediate Surveys 5.3.1.8 Cargo pipelines, valves and fittings are
to be generally examined, with special reference
5.3.1 General to expansion bellows, supports and vapour
seals on insulated pipes.
5.3.1.1 Cargo liquid level indicating devices are
to be generally examined. The low level, high 5.3.1.9 Portable and/or fixed drip trays, or
level and overfill alarms are to be examined and insulation for deck protection in the event of
tested to ascertain that they are operational. cargo leakage are to be examined for their
Consideration will be given to the acceptance of condition.
simulated tests provided that they are carried
out at the cargo temperature and/or pressure. 5.3.2 Refrigerating equipment
5.3.1.2 Where applicable, gas leakage systems 5.3.2.1 Where refrigerating equipment for cargo
are to be examined and tested to ascertain that temperature and pressure control is fitted the
they are in working order and calibrated using following are to be examined so far as
sample gas. practicable:
5.3.1.3 Where applicable, the correct functioning (a)The machinery under working condition.
of the cargo containment system temperature
indicating equipment, together with any (b) Shells of all pressure vessels in the system
associated alarms, is to be verified. including primary refrigerant gas and liquid
pipes, cargo vapour and liquid condensate pipes
5.3.1.4 Where applicable, the ventilation system and condenser cooling arrangements. Insulation
for the spaces surrounding the cargo tanks and need not be removed, but any deterioration or
evidence of dampness is to be investigated.
End of Chapter
Part 2
Contents
Chapter 10 Equipment
Part 3
Contents
Chapter 9 Bulkheads
Chapter 12 Rudders
Chapter 14 Welding
Contents
Chapter 1
Section 1
2.2 Structural terms
General 2.3 Material factor
1.1 Scope
Chapter 2
Materials of Construction
Section 1
2.2 Surface preparation, prefabrication primers
and paints or coatings
General
2.3 Internal cathodic protection
1.1 Scope
2.4 Aluminium and magnesium anodes
1.2 Steel
2.5 Corrosion protection coatings for salt water
1.3 Grades of steel ballast spaces
1.4 Aluminium
Section 3
Section 2
Deck Covering
Corrosion Protection 3.1 General
2.1 General
Chapter 3
Section 2 Section 5
Section 3
Section 6
Plating
3.1 General Buckling
6.1 General
Chapter 4
Longitudinal Strength
General Section 3
Section 4
4.2 Reinforcements
Openings in Longitudinal Strength 4.3 Hatchway corners
Members
4.1 Locations
Chapter 5
Section 1 Stem
1.2 Material
Section 4
1.3 Symbols
Stern Frames
Section 2 4.1 General
Section 3
Chapter 6
Bottom Structure
Section 1 Section 3
Section 5
6.2 Transverse framing
Single Bottom 6.3 Longitudinal framing
5.1 Transverse framing
Engine Seatings
Section 6
7.1 General
Double Bottom 7.2 Recommended scantlings
6.1 General
Chapter 7
Side Structure
General
Section 4
1.1 Scope
Side Shell Plating and Stiffeners
1.2 Symbols
4.1 Side shell plating
Section 5
Section 3
Girders
Design Loads
5.1 General
3.1 External pressure
Chapter 8
Deck Structure
5.2 Cantilevers
Structural Arrangement and Details
5.3 Pillars
2.1 General
Section 6
Section 3
Decks for Wheel Loading
Design Loads
6.1 General
3.1 Weather deck
6.2 Wheel loads
3.2 Accommodation decks
6.3 Deck plating
3.3 Decks forming tank boundaries
6.4 Deck stiffeners
Chapter 9
Bulkheads
Chapter 10
Section 1 Section 3
1.2 Definitions
Section 4
1.3 Symbols
Bulwarks and Guard Rails
Section 2 4.1 General requirements
Chapter 11
Section 1
4.1 Manholes
General 4.2 Companionways, doors and accesses on
weather decks
1.1 Scope
4.3 Openings on engine casing
Hatch Coamings
Section 5
2.1 Coaming heights
Hatch Covers
Section 6
3.1 General
Miscellaneous Openings
Chapter 12
Rudders
Section 1 Section 4
Section 2 Section 5
3.3 Bending moments, shear forces and 6.2 Vertical flange couplings
reactions
Chapter 13
Section 1 Section 3
General Anchors
1.1 Introduction 3.1 General
6.2 Testing
Towlines and Mooring Lines
Chapter 14
Welding
Chapter 15
Section 1 Section 3
End of Contents
Chapter 1
Contents
Section
1 General
2 Definitions
3 Documentation
Section 1
General
1.1.1 The Rules in this part apply to all-welded, 1.3.1 While the Rules cover requirements for the
single hull steel ships of normal form, classification of ships, the attention of all
proportions and speed for operation in inland concerned is drawn to requirements of various
waterways. local or national Regulations, Codes and
Recommendations which the vessel may also
1.1.2 For additional class notations relating to have to comply with.
various ship types, requirements as per Pt.5 are
to be complied with. 1.4 Loadline and stability
1.1.3 Ships of unconventional forms and 1.4.1 All ships will be assigned class only after it
proportions or intended for carriage of cargoes has been demonstrated that their intact/damage
not covered by the Rules or to be engaged in stability and loadline requirements (where
special service will receive individual applicable) are in compliance with the standards
consideration based on the general principles of laid down by the local or National statutory
the Rules. In these cases, however, additional authority.
calculations and/or model testing may be
required to be carried out and submitted for 1.4.2 For stability of passenger ships, the
approval. requirements specified in IRS Classification
Note: “Stability Requirements for Inland
1.1.4 Proposals for use of alternative materials Waterways’ Passenger Ships” are to be
e.g. aluminium, wood, etc. for some parts of the complied with.
ship shall receive special consideration.
1.5 Assumptions
1.2 Equivalence
1.5.1 It is assumed that significant dynamic
1.2.1 Alternative arrangements, scantlings and excitation of major orders from propellers and
equipment may be accepted provided they can machinery do not fall close to any natural
be shown to be equivalent to the overall safety frequency of the hull.
and strength standard of the Rules. Direct
calculations for the derivation of the scantlings 1.5.2 It is assumed that the ships will be
as an alternative to those derived by the Rule competently handled and loaded as per the
formulae, may be accepted on special approved loading manuals.
consideration. The calculation procedure and
the assumptions made are to be submitted for
approval.
Section 2
Definitions
2.1.1 The forward perpendicular, F.P., is the 2.2.1 The general terms used in the Rules for
perpendicular drawn at the intersection of the various structural parts of the ships are defined
maximum load water line with the fore side of as under:
the stem.
Strength Deck : In general the uppermost
In ships with unusual bow arrangement the continuous deck. Where a superstructure
position of the F.P. will be specially considered. deck has within 0.4L amidships, a
continuous length equal to or greater than
2.1.2 The after perpendicular, A.P., is the (1.5B + 3H), it is to be regarded as the
perpendicular drawn at the intersection of the strength deck instead of the covered part of
maximum load waterline with the after side of the uppermost continuous deck. (H is the
the rudder post or the centreline of the rudder height of the superstructure, [m]).
stock if there is no rudder post.
Superstructure : A decked structure on
In ships with unusual stern arrangement the freeboard deck extending from side to side
position of the A.P. will be specially considered. of the ship or with the side plating not
inboard of shell plating by more than 4 per
2.1.3 Rule length, L, is the distance, [m], cent of the breadth B.
between the forward and after perpendiculars.
However L is to be not less than 96 per cent, Deckhouse : A decked structure above the
and need not be greater than 97 per cent of the freeboard deck with the side plating being
extreme length on the maximum load waterline. inboard of the shell plating by more than 4
per cent of the breadth B.
In ships with unusual bow and/or stern
arrangement the Rule length, L, will be specially Bottom Structure : Shell plating with
considered. stiffeners and girders below the upper turn
of bilge and all other elements below and
2.1.4 "Amidship" is at 0.5L aft of the F.P. including the inner bottom plating in case of
the double bottom. Sloping hopper tank top
2.1.5 Breadth, B, is the greatest moulded is to be regarded as a bulkhead.
breadth [m].
Side Structure : Shell plating with stiffeners
2.1.6 Depth, D, is the moulded depth [m], and girders between the upper turn of bilge
measured amidships from top of the keel to the and the uppermost continuous deck at side.
moulded deck line of the uppermost continuous A rounded gunwale is included in the side
deck at side. When a rounded gunwale is structure.
arranged the depth is to be measured to the
continuation of the moulded deck line. Deck Structure : Deck plating with stiffeners,
girders, and supporting pillars.
2.1.7 Draught, T, is the moulded draught
amidships corresponding to the maximum load Girder : A collective term for the primary
waterline, [m]. supporting members, other terms include :
2.1.8 The block co-efficient, Cb, is the moulded
Transverses - transverse girders under
block co-efficient calculated as follows :-
the deck.
Section 3
Documentation
3.2.1 The following supporting plans and 3.4 Plans for approval
calculations are to be submitted for information :
3.4.1 Plans as relevant are to be submitted for
General arrangement. approval as indicated in Table 3.4.1. These
should as far as practicable be complete in all
Tank plan. necessary details.
Lines plan and Hydrostatic curves or 3.5.1 A copy of the final approved loading
tables. manual and suitable scantlings plans including
details of corrosion control system; if any, are to
Docking plan. be placed on board the ship.
material grades
Double bottom indication of access
height and location of overflows
loading on inner bottom
Watertight subdivision bulkheads & openings and their closing appliances
watertight tunnels
Aft-end structure propeller outline
Sternframe or sternpost propeller thrust
Propeller shaft brackets structural details in way of rudder and propeller bearings
Aft peak tank height and location of overflow
Engine room structure type, power and r.p.m. of propulsion machinery
Engine and thrust block seatings weight of machinery, boilers, etc.
Fore-end construction openings on non-watertight bulkheads and diaphragm plates
Fore peak tank height and location of overflows
Oil tight/water tight and partition intended tank contents & their densities
bulkheads in cargo tanks, ballast tanks height and location of overflow/air pipes
and deep tanks tanks intended to be partially filled
corrosion protection; if any
Superstructures, deckhouses and height of sills from deck and closing appliances for
machinery casings companion ways
Hatchways position and type
Hatch covers loads if different from those specified in the rules
sealing and securing arrangement, spacing of bolts or
wedges
Rudder, stock and tiller speed of the ship (ahead & astern)
Steering gear arrangement material of bearings, coupling bolts, stock and the locking
device
rudder carrier.
Masts & derrick posts derrick length and loading
Support structure for masts, derrick dimensions and positions of stays and shrouds
posts & cranes quality of material
Testing plan of tanks & bulkheads
Welding details
Notes:
2) One drawing may contain more than one of the items from each group
End of Chapter
Chapter 2
Materials of Construction
Contents
Section
1 General
2 Corrosion Protection
3 Deck Covering
Section 1
General
k = 0.78 for steel with a minimum yield stress of ta, ts = plating thickness of aluminium and mild
315 [N/mm2] steel respectively.
Section 2
Corrosion Protection
2.2.1 Steelwork is to be cleared of millscale and 2.3.1 Impressed current cathodic protection
suitably cleaned before the application of systems are not permitted in any tank.
surface paints and coatings. It is recommended
that blast cleaning or other equally effective When a cathodic protection system is to be fitted
means be employed for this purpose. in tanks for the carriage of liquid cargo with flash
point not exceeding 60C, a plan showing
2.2.2 Where a primer is used to coat steel after details of the locations and attachment of
surface preparation and prior to fabrication, the anodes is to be submitted. The arrangements
composition of the coating is to be such that it will be considered for safety against fire and
will have no significant deleterious effect on explosion aspects only.
subsequent welding work and that it is
compatible with the paints or other coatings 2.3.2 Particular attention is to be given to the
subsequently applied. Unless the primer used is locations of anodes in relation to the structural
type approved by IRS for this purpose, tests as arrangements and openings of the tank.
detailed in Pt.3, Ch.2, Sec.3 of the Main Rules
are to be made to determine the influence of the 2.3.3 Anodes are to be of approved design and
primer coating on the characteristics of the weld. sufficiently rigid to avoid resonance in the anode
support. Weldable steel cores are to be fitted,
2.2.3 Paints or other coatings are to be suitable and these are to be so designed as to retain the
for the intended purpose in the locations where anode even when the anode is wasted.
2.3.6 Where cores or supports are welded to the 2.4.4 Magnesium or magnesium alloy anodes
main structure, they are to be kept clear of the are permitted only in tanks intended solely for
toes of brackets and similar stress raisers. water ballast.
Where they are welded to asymmetrical
stiffeners, they are to be connected to the web 2.5 Corrosion protection coatings for salt
with the welding kept at least 25 [mm] away water ballast spaces
from the edge of the web. In the case of
stiffeners or girders with symmetrical face 2.5.1 In case of ships which normally carry salt
plates, the connection may be made to the web water for ballast purposes, all ballast spaces,
or to the centreline of the face plate but well having boundaries formed by the hull envelope,
clear of the free edges. However, it is are to have a suitable corrosion protection
recommended that anodes are not fitted to face coating applied in accordance with the
plates of high tensile steel longitudinals. manufacturer's requirements.
Section 3
Deck Covering
End of Chapter
Chapter 3
Contents
Section
1 General
2 Corrosion Additions
3 Plating
4 Stiffeners and Girders
5 End Attachments
6 Buckling
Section 1
General
midpoint of horizontally stiffened plate field = allowable bending stress, [N/mm2] as given
in the relevant Chapters.
half the stiffener spacing above the lower
support of vertically stiffened plate field, or at y = minimum yield stress of material, [N/mm2],
the lower edge of plate when the thickness may be taken as 235 [N/mm2] for normal
is changed within the plate field. strength steel.
k = material factor as defined in Ch.2, Sec.1.2. 550 + 2L [mm] for longitudinal framing.
E = modulus of elasticity, 2.06 x 105 [N/mm2] for 1.3.2 In aft peak and fore peak the frame
steel. spacing is not to exceed 600 [mm] or that given
in 1.3.1, whichever is less.
1.3 Frame spacing
1.3.3 Where the actual frame spacing is higher
1.3.1 The normal frame spacing between aft than that mentioned above, the minimum
peak and 0.2L from F.P. may be taken as: thicknesses of various structural members as
given in the Rules may require to be increased.
450 + 2L [mm] for transverse framing
Section 2
Corrosion Additions
1) Where the relevant ballast or liquid cargo tanks extend upto the exposed weather deck the minimum
corrosion addition in the region extending upto 1.5 [m] below the weather deck corrosion addition is
to be increased by 0.5 [mm].
2) Hold of dry bulk cargo carriers refers to the cargo holds of vessels with class notation Bulk Carrier
and Ore Carrier.
3) Other category space denotes the hull exterior and all spaces other than water ballast and cargo oil
tanks and holds of dry bulk cargo carriers.
Section 3
Plating
Section 4
For curved stiffeners, 'l' may be based on the 4.2.3 The effective width of plating attached to a
chord length. girder, 'be' is to be taken as per the following:
For intermediate values of a/b and number of = 60 per cent of span of the girder, for girders
point loads, values of 'c' may be obtained by fixed at both ends, [m].
interpolation.
4.2.4 In case of girders on corrugated bulkheads
a = span of the girder, for simply supported which run across the corrugations, the effective
girders, [m]. width of attached plating is to be taken as 10%
of that obtained from 4.2.3.
Section 5
End Attachments
5.1 End attachments of stiffeners The arm lengths, 'a and b' (See Fig.4.1.1)
are to be such that:
5.1.1 Continuity of all stiffeners participating in
longitudinal strength is to be maintained over i) a, b 0.8 lb
transverse members within 0.5L amidships.
Longitudinals abutting at transverse members and
may be accepted provided the brackets
connecting the ends of the longitudinals are of ii) a+b 2.0 lb.
adequate size and are either continuous or
properly aligned. where,
t = (4.0 + 0.3 Z) + tc [mm] Where the face plate of the girder is not
continuous over the bracket, the free edge of the
Thickness of flanged bracket is to be not bracket is to be stiffened and the face plate of
less than: the girder is to be extended well beyond the toe
of the bracket.
t = (3.0 + 0.25 Z) + tc [mm]
5.2.2 The thickness 't' of brackets on girder is
Width of flange, w 40 + Z/25 [mm], but not not to be less than that of the girder web.
to be less than 50 [mm].
The arm length 'a' including the depth of girder
where, is not to be less than:
Section 6
Buckling
= 1.0 for deck, longitudinally stiffened side for 'lm' and 'i' See 6.2.2.
shell and single bottom plating
y
y 1 when E 0.5 y
4 E
where,
6.2 Ideal elastic buckling stress = 1.05 when stiffeners are flat bars
6.2.1 The E value for platings may be taken as: s = shorter side of plate panel, [mm]
End of Chapter
Chapter 4
Longitudinal Strength
Contents
Section
1 General
2 Vertical Bending Moments
3 Hull Section Modules and Moment of Inertia
4 Openings in Longitudinal Strength Members
Section 1
General
Section 2
2.1 Still water bending moment In addition other loading conditions which may
be more onerous, e.g. intermediate conditions of
2.1.1 Still water bending moments are to be special loading or discharging sequences, are to
calculated for the following loading conditions as be investigated.
a minimum:
2.1.2 The design value of still water bending
a) Fully loaded condition with design cargo moment Ms at 0.4L amidships is to be taken as
distribution(s) the greater of the following:
Section 3
3.1 Calculation of section properties bottom about the transverse neutral axis is to be
obtained as follows:
3.1.1 When calculating the moment of inertia
and section moduli, the net sectional area (after Z = In / (100.z) [cm3]
deduction for openings) of all continuous
longitudinal strength members is to be taken into where,
account. Small isolated lightening holes in
girders need not be deducted. z = the vertical distance [m] from the horizontal
neutral axis upto the strength deck at side or the
Superstructures not forming strength deck (See base line, as relevant.
Ch.1, Sec.2.2), deckhouses, bulwarks and non-
continuous longitudinal hatch coamings are not However, in case of ships where continuous
to be included in the above calculations. trunks or longitudinal hatch coamings are to be
included in the section modulus calculation as
In case of ships with continuous trunks or per Sec.3.1.1, the distance z for calculation of
longitudinal hatch coamings, their net sectional modulus at deck is to be taken as the greater of
area may be included in the calculations the following:
provided they are effectively supported by
longitudinal bulkheads or deep girders. The z = z as above
section modulus at deck however, is then to be z = zn [0.9 + 0.2 y/B]
calculated as given in 3.1.3.
where,
3.1.2 The main strength members included in
the calculation of hull moment of inertia and zn = the vertical distance from the horizontal
section modulus are to extend continuously neutral axis to top of continuous strength
through the cargo region and sufficiently far number.
towards the ends of the ship. Longitudinal
bulkheads are to terminate at effective y = athwartship distance from the centreline of
transverse bulkheads and large transition the ship to the side of the strength member.
brackets are to be fitted in line with the
longitudinal bulkheads. zn and y are to be measured to the point giving
the largest value of z.
3.1.3 The midship section modulus 'Z' at deck or
Section 4
4.1.2 Openings in the strength deck within 0.6L 4.2.2 Circular openings with diameter equal to or
amidships are as far as practicable to be located greater than 0.325 [m] are to have edge
inside the line of large hatch openings. reinforcement having sectional area A not to
Necessary openings outside this line are to be less than:
kept well clear of the ship's side and hatch
corners. A = 2.5 b.t. [cm2]
4.2.1 All openings are to be adequately framed 4.2.3 Elliptical openings are to have their major
and arrangements in way of corners and axis in the fore and aft direction. Where the ratio
openings are to be such as to maintain of the major axis to minor axis is less than 2, the
structural continuity and minimize the creation of openings are to be reinforced as given in 4.2.2
stress concentrations. taking b as the breadth of the opening (minor
axis).
Corners of hatchways are to be reinforced as
given in Ch.8, Sec.2. Smaller openings in the
a = 0.15b [m]
End of Chapter
Chapter 5
Contents
Section
1 General
2 Bar Keel
3 Stem
4 Stern Frames
Section 1
General
Section 2
Bar Keel
2.1.1 The scantlings of bar keel are not to be Minor deviations from the above values may be
less than : accepted provided the required sectional area is
maintained.
Depth = 75 + 0.75 L [mm]
Section 3
Stem
3.1 Bar stem the summer load waterline is not to be less than:
3.1.1 The cross sectional area 'A' of a bar stem, t = ( 0.08 L + 5.0 ) [mm]
below the summer load waterline, is not to be
less than 3.2.2 The thickness of the plate stem may be
gradually reduced to that of the side shell at the
A = 0.6L [cm2]; or 12 [cm2] stem head.
Section 4
Stern Frames
4.1.1 Sternframes, shaft brackets etc. are to be A = (8 + 0.4L) T [cm2] for L < 60 [m]
designed such that they are effectively
integrated into the ship's structure. = 32 T [cm2] for L > 60 [m]
4.1.2 In castings, sudden changes of section or Fabricated propeller posts (see Fig. 4.2.1 (b))
possible constrictions to the flow of metal during
castings are to be avoided. All fillets are to have l = 150 T [mm]
adequate radii, which in general should not be
less than 50 to 75 [mm], depending on the size w = 100 T [mm]
of the casting.
r = 18 T [mm]
4.1.3 Fabricated and cast steel sternframes are
to be strengthened at intervals by webs spaced t1 = 11 T [mm]
not more than 700 [mm] apart. In way of the
upper part of the sternframe arch, these webs tw = 5 T [mm]
are to line up with the floors.
Cast steel propeller posts ( see Fig. 4.2.1 (c))
4.1.4 Rudder posts and propeller posts are to be
connected to floors of increased thickness. l = 125 T [mm]
4.1.5 It is recommended that the after body of
w = 85 T [mm]
the ship be so shaped as to ensure adequate
flow of water to the propeller so as to prevent
r = 20 T [mm]
uneven formation of eddies, as far as possible.
Where the sections adopted differ from the a, b, c = as shown in Figures 4.3.1 (a) and (b)
above, the section modulus about the [m].
longitudinal axis is to be equivalent to that with
the Rule scantlings. The above requirement of ZT is to be increased
by 15 per cent for cast steel solepieces.
On sternframes without solepieces, the modulus
of the propeller post, about the longitudinal axis,
may be gradually reduced by 15 per cent below
the propeller boss, provided the thicknesses are
maintained as above.
where,
4.3 Sole piece 4.3.2 The section modulus 'Zv' of the sole piece
against vertical bending is not to be less than :
4.3.1 The section modulus 'ZT' of the sole piece
against transverse bending is not to be less than ZT
Zv [cm 3 ]
2
1 c Fr x
ZT [cm 3 ]
90 b 4.3.3 The sectional area of sole piece is not to
be less than:
where,
1 c . Fr
Fr = Rudder force [N] as defined in Pt.3, Ch.12, As . [cm 2 ]
Sec. 3 5400 b
x = distance of the cross section under 4.3.4 The sole piece is to extend at least two
consideration from the centre line of rudder frame spaces forward of the forward edge of the
stock, [m]. 'x' is not to be taken as less than a/2. propeller boss and beyond this, the cross
4.4 Shaft brackets The connection of the bracket arms to the shell
plating is to be by full penetration welding.
4.4.1 Where the propeller shafting is exposed to
the sea for some distance clear of the main hull, 4.4.4 The scantlings of solid or built-up shaft
it is generally to be supported adjacent to the brackets are to comply with the following:
propeller by independent brackets having two
arms. It is recommended that the angle t = 0.4 dts [mm]
included between the arms differs from the
angle included between the propeller blades. In A = 4.5 dts2 . 10-3 [cm2]
very small ships the use of single arm brackets
will be considered. ZT = 30 dts3 . 10-6 [cm3]
4.4.3 Generally, bracket arms are to be carried ZT = Section modulus of the bracket arms
through the shell plating and attached to floors against transverse bending
End of Chapter
Chapter 6
Bottom Structure
Contents
Section
1 General
2 Structural Arrangement and Details
3 Design Loads
4 Bottom and Inner Bottom Plating
5 Single Bottom
6 Double Bottom
7 Engine Seatings
Section 1
General
Section 2
2.1 General 2.1.2 The continuity of the bottom, bilge and inner
bottom longitudinals is to be maintained in
2.1.1 Depth of wells constructed in the double accordance with Ch.3, Sec.5.1.1.
bottom, in connection with the drainage
arrangement of holds, is to be kept in the 2.1.3 The bilge keel and the ground bar to which
minimum. it is attached, are to be gradually tapered at ends
and arranged to finish in way of suitable internal
stiffening.
Butt welds in the bilge keel and the ground bar the inner bottom plating in cargo holds are to be
are to be well clear of each other and those in the effectively protected. The edges of all holes are
shell plating. to be smooth.
2.1.4 The weld connections are to comply with 2.2.2 To ensure the free passage of air and water
the requirements of Ch.16. from all parts of the tanks to air pipes and
suctions, air and drain holes are to be provided in
2.2 Access, ventilation and drainage all non-watertight members. The air holes are to
be placed as near to the inner bottom as possible
2.2.1 Adequate access is to be provided to all and their total area is to be greater than the area
parts of the double bottom. Where the vertical of the filling pipes. The drain holes are to be
dimension of the lightening hole exceeds 50 placed as near to the bottom as possible.
percent of the web height adequate
reinforcements are to be provided. The diameter 2.2.3 The access opening to pipe tunnel is to be
of lightening holes in the bracket floors is not to visible above the floor plates and is to be fitted
exceed 1/3 of the breadth of the brackets. with a rigid watertight closing device. A notice
Lightening holes or manholes are normally not to board stating that the access opening to the pipe
be cut in floors or girders towards their ends and tunnel is to be kept closed, is to be fitted near the
under large pillars or supporting structures. opening. The opening is to be regarded as an
Manholes in innerbottom are to have opening in watertight bulkhead.
reinforcement rings, and the man hole covers in
Section 3
Design Loads
3.2 Watertight floors and girders = cargo density [t/m3] normally not to be taken
as less than 0.7 [t/m3]
3.2.1 The design pressure 'p' on watertight floors
and girders in double bottom tanks is to be taken H = height [m], to deck or top of hatchway
as the greater of: coaming.
Section 4
t = (to+0.03L) k + tc [mm] but not less than 6.0 MGRAB = Mass of unladen grab [t]; MGRAB is not to
[mm] be taken less than 7 tonnes
Section 5
Single Bottom
depth at centreline d = 40B [mm] in general The thickness of face plate is not to be less than
1/15 of the face width.
thickness of web, t = d/100 + 2.5 [mm]
The top of floors, in general, is to be level from
Section modulus side to side. However, in ships having
considerable rise of floor, the depth of web at 10
Z = 0.006 s.lf2 . T1 [cm3] in cargo holds per cent of the span from ends, is not to be less
than half the depth at centreline.
= 0.0072 s.lf2 . T1 [cm3] in machinery and other
spaces If the height of floors between engine girders is
reduced in way of crankcase, the face plate area
where, is to be suitably increased, however the reduced
height is normally not to be less than 2/3 of 'd' as
lf = span of floor, measured on the top of floor given above.
plate from side to side
5.1.2 On all ships one centre girder is to be fitted
and in addition side girders are to be fitted such
s p l2
Z Z c [cm 3 ]
12 σ
Section 6
Double Bottom
6.1 General The depth 'd' of the centre girder is not to be less
than:
6.1.1 Where double bottom spaces are used as
tanks, the centre girder is to be watertight unless d = 250 + 20B + 50T [mm],
the double bottom is divided by watertight side with a minimum of 650 [mm].
girders or the tanks are narrow.
In case of ships with considerable rise of floors
the depth 'd' may have to be increased.
as that of the inner bottom longitudinal and l = span of longitudinals [m], measured between
thickness as that of the floor. Between plate the plate floors
floors, transverse brackets are to be fitted at
every frame at the margin plate and at a spacing = (210 - 140 fB)/k [N/mm2], maximum 160/k
not exceeding 1.25 [m] on either side of the [N/mm2] for bottom longitudinals within 0.4L
centre girder. The thickness of brackets is to be amidships
same as that of the plate floors. The brackets are
to extend upto the adjacent longitudinal and are = (210 - 100 fB)/k [N/mm2], maximum 160/k
to be flanged 75 [mm] at their free edges. [N/mm2] for inner bottom longitudinals within 0.4L
amidships
6.3.4 The section modulus 'Z' of the bottom and
inner bottom longitudinals is not to be less than: = 160/k [N/mm2] within 0.1L from ends.
Section 7
Engine Seatings
7.1.2 Sufficient fore and aft girders are to be 7.2.1 For engines of power less than 1500 kW
arranged in way of the main machinery to and RPM greater than 1200, the scantlings of
effectively distribute its weight and to ensure engine girder face plate, web and floors in way of
adequate rigidity of the structure. The girders are engine seatings may be calculated as given
generally to extend over the full length of the below. Scantlings for other engines will be
engine room and are to be suitably scarphed into specially considered.
the bottom structure beyond.
P
7.1.3 The scantlings of engine seatings are to be Top plate area; A = 20 + 120 [cm2]
adequate to resist gravitational, thrust, torque, R
dynamic and vibratory forces which may be
imposed on them. The recommendations given Thickness of top plate; tp = 0.1A + 14 [mm]
by the engine manufacturer are also to be taken
into account. Girder web thickness; tg = 0.043A + 7 [mm]
7.1.4 Where the top plate of the engine seating is Floor web thickness; tf = 0.02A + 6 [mm]
situated above the floors or the inner bottom,
adequate transverse strength by means of where,
brackets in line with the floors is to be ensured. In
way of the recess for crankcase, brackets as P = maximum power of the engine [kW]
large as practicable are to be fitted.
R = rpm of engine at maximum power
End of Chapter
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 1 of 5
___________________________________________________________________________________
Chapter 7
Side Structure
Contents
Section
1 General
2 Structural Arrangement and Details
3 Design Loads
4 Side Shell Plating and Stiffeners
5 Girders
Section 1
General
1.1 Scope
ZR
1.1.1 The scantlings and arrangement of side fD
structure as defined in Ch.1, Sec.2 and also ZD
those of sides of the superstructures are
to comply with the requirements of this Chapter. ZR
fB
1.2 Symbols ZB
L, B, T, Cb, k as defined in Ch.1, Sec.2. fS = fD for side shell area above neutral axis
s = spacing of stiffeners, [mm]. = fB for side shell area below neutral axis
the side plating of the superstructures is to be each side of a superstructure end bulkhead
increased by 25 per cent in way of the break. located within 0.5L amidships if the
superstructure deck is a partial strength deck.
2.1.5 The thickness of the shell plating is to be
increased locally by 50 per cent in way of 2.2.2 Where a rounded sheer strake is adopted,
sternframe, propeller brackets and rudder horn. the radius in general, is not to be less than 15
For reinforcements in way of anchor pockets, times the plate thickness.
hawse pipes etc. refer to Ch.13.
2.2.3 Bulwarks are generally not to be welded to
2.1.6 The weld connections are to comply with the top of the sheer strake within 0.6L amidships.
the requirements of Ch.14.
2.2.4 Where the sheer strake extends above the
2.2 Sheer strake deck stringer plate, the top edge of the sheer
strake is to be kept free from notches and
2.2.1 The thickness of sheer strake as obtained drainage openings if any, are to have smooth
from 4.1.1 is to be increased by 30 per cent on transition in the longitudinal direction.
Section 3
Design Loads
Table 3.1.1
b) For intermediate lengths (L) in Zone 1, the value of 'p' is to be linearly interpolated
ho = vertical distance [m], from the maximum load waterline to the loadpoint.
hs = The vertical distance [m] from the load point For very large tanks which may be partially filled,
to the top of tank sloshing pressures may have to be considered.
Section 4
4.1 Side shell plating Between the regions specified above ` σ ' may be
obtained by linear interpolation.
4.1.1 The thickness 't' of side shell is not to be
less than: 4.3 Main frames
t = (4 + 0.04L) k + tc [mm] 4.3.1 The section modulus 'Z' of the main frames
bracketed at both ends as per 4.3.2 is not to be
4.1.2 The side shell plating is also to comply with less than :
the requirements of buckling strength given in
Ch.3, Sec.6. 𝑠𝑝𝑙 𝑘
𝑍 𝑍 𝑐𝑚 𝑎𝑛𝑑
2400
4.1.3 The breadth of the sheer strake is not to be
less than 100 D [mm]. 5.5√𝐿𝑘 𝑐𝑚
Where the free edge of the bracket exceeds 40 4.5 Peak frames
times the bracket thickness, the brackets are to
be flanged. The flange width is to be at least 1/15 4.5.1 Vertical peak frames forward of the collision
of the length of the free edge. bulkhead and aft of the after peak bulkhead are
to have section modulus 'Z' not less than
4.3.3 Brackets at ends of the main frame may be
omitted provided the frame is carried through the s p l2 k
supporting members and the section modulus Z Z c [cm 3 ] and
obtained as per 4.3.1 is increased by 75 per cent. 1600
4.4.2 The lower end of the superstructure frame 4.5.2 Peak frames are to be bracketed at top and
is to be connected to the bracket or frame below bottom and in way of side stringers, the
or else it is to be bracketed above the deck. The connection is to provide adequate shear strength.
upper end is to be bracketed to the deck beam or
longitudinal.
Section 5
Girders
5.1.6 The net cross sectional area 'A' of the girder where,
web at ends is not to be less than
h = girder height [mm].
A = 0.06 Sbpk + 0.01 h tc [cm2] for stringers and
upper ends of the web frames. 5.1.7 Tripping brackets are to be fitted in
accordance with the requirements given in Ch.3,
= 0.08 Sbpk + 0.01 h tc [cm2] for lower ends of Sec.4.4.4.
the web frames.
End of Chapter
Chapter 8
Deck Structure
Contents
Section
1 General
2 Structural Arrangement and Details
3 Design Loads
4 Deck Plating and Stiffeners
5 Deck Girders and Pillars
6 Decks for Wheel Loading
Section 1
General
1.1 Scope
where,
1.1.1 The scantlings and arrangement of deck
structure as defined in Ch.1, Sec.2 are to comply ZR = Rule midship section modulus [cm3], as
with the requirements given in this Chapter. required by Ch.4.
b = spacing of girders, [m]. zn = vertical distance [m], from the neutral axis of
the hull girder to the strength deck, in general. For
S = span of girders, [m]. ships with continuous trunks refer to Ch.4,
tc, Zc = corrosion additions to thickness and Sec.3.1.3.
section modulus respectively as given in Ch.3,
Sec.2.1. z = vertical distance [m], from the neutral axis of
the hull girder to the deck under consideration or
ZR to the free flange of the deck longitudinal or girder
fD as relevant.
ZD
Section 2
2.1.2 The continuity of the deck longitudinals is to or equivalent are adopted, insert plates are to be
be maintained in accordance with Ch.3, fitted at the hatch corners in strength deck. The
Sec.5.1.1. insert plates are to be 25 per cent thicker than the
deck plating outside the line of hatchways and
2.1.3 The deck within the line of hatchway are to extend as shown in Fig.2.1.6. The butts of
openings is preferably to be stiffened insert plates are to be well clear of those in
transversely or alternatively the arrangements coaming.
are to provide adequate transverse buckling
strength. Where the deck outside the line of
hatchway openings is framed longitudinally, the
transverse beams or buckling stiffeners between
the hatchways are to extend at least upto the
second longitudinal from the hatch side or
equivalent.
Section 3
Design Loads
3.1 Weather deck where 'q' is deck cargo loading [t/m2].
3.1.1 The design pressure 'p' on exposed decks 3.1.3 For weather decks forming crowns of tanks,
is to be taken as: the design pressure 'p' is to be taken as the
greater of that given by 3.1.1 and 3.3.1.
p = H1 - 10 ho [kN/m2], minimum 5 [kN/m2]
3.2 Accommodation decks
where,
3.2.1 The design pressure 'p' on accommo-dation
ho = vertical distance [m], from the maximum decks is to be taken as :
load waterline to the deck.
H1 = as given in Table 3.1.1. p = 4.5 [kN/m2]
Section 4
to = 5 for strength decks and forecastle decks = 160/k [N/mm2] within 0.1L from ends and for
short decks.
= 4.0 for other decks.
Elsewhere, may be obtained by linear
4.1.3 The strength deck plating outside the line of interpolation.
hatchways is also to comply with the
requirements of buckling strength given in Ch.3, The longitudinals are also to comply with the
Sec.6. requirements of buckling strength given in Ch.3,
Sec.6.
4.1.4 In way of ends of bridges, poops and
forecastles, the thickness of the strength deck 4.2.2 The section modulus 'Z' of transverse
stringer strake is to be increased by 20 per cent beams is not to be less than:
over four frame spaces fore and also aft of the
end bulkheads.
𝑠𝑝𝑙 𝑘
4.2 Deck stiffeners 𝑍 𝑍 𝑐𝑚
1600
4.2.1 The section modulus 'Z' of deck where,
longitudinals is not to be less than:
p = applicable design pressure [kN/m2] as given
2 in Sec.3.
spl
Z Z c [cm 3 ]
12
Section 5
= (190 - 145fDfz)/k, max. 160/k [N/mm2] for 5.3.2 Pillars are to be fitted in the same vertical
continuous longitudinal girders within 0.4L line wherever possible, and arrangements are to
amidships. be made to effectively distribute the load at the
heads and heels. Where pillars support eccentric
= 160/k [N/mm2] for longitudinal girders within loads, they are to be strengthened for the
0.1L from ends and for transverse girders in additional bending moments imposed upon them.
general. Doubling or insert plates are generally to be fitted
at the head and heel of hollow pillars.
Elsewhere, `' may be obtained by linear
interpolation. 5.3.3 The pillars are to have a bearing fit and are
to be attached to the head and heel plates by
5.1.4The net cross sectional area 'A' of the girder continuous welding.
web at ends
is not to be less than: 5.3.4 Where the heels of hold pillars are not
directly above the intersection of plate floors and
A = 0.07 . S.b.p k + 0.01h tc [cm2] girders, partial floors and intercostal girders are
to be fitted as necessary to support the pillars.
where, Lightening holes or manholes are not to be cut in
the floors and girders below the heels of pillars.
h = girder height [mm].
Section 6
6.1 General
where,
6.1.1 Where it is proposed either to stow wheeled
vehicles on the deck or to use wheeled vehicles W = maximum axle load, [t]. For fork lift trucks,
for cargo handling, the requirements of this the total weight is to be taken as the axle load.
section are to be complied with in addition to
those given in the preceding sections. n = number of "load areas" per axle
6.1.2 The requirements given below are based on a = extent [mm], of the load area parallel to the
the assumption that the considered element stiffener (see Fig. 6.2.1)
(Deck plating and/or stiffener) is subjected to one
load area only, and that the element is continuous b = extent [mm], of the load area perpendicular to
over several evenly spaced supports. The the stiffener (see Fig.6.2.1)
requirements for other loads and/or boundary
conditions will be specially considered.
c 2 b s p k .10 3
W 3 6 t c1f a t c [mm]
p 9.81 10 [kN/m2] m
n.a.b W
for cargo handling vehicles
in harbour condition
where,
where,
fa = (1.1 - 0.25 s/l) for s l, however need not be
taken as greater than 1.0 c3 = (1.15 - 0.25 b/s) for b s, however need not
be taken as greater than 1.0
a,b,s,l = deck panel dimensions [mm] (see
Fig.6.2.1) r
m
c1 = 0.137 in general for sailing conditions (a/l) 4.7 a/l 6.5
2
6.4.1 The section modulus 'Z' of deck beams and 6.5.1 The scantlings of girders will be specially
considered based on the most severe condition
longitudinals subjected to wheel loadings is not to
of moving or stowed vehicles. Also see Sec.6.1.3.
be less than:
c 3 .a.b.l.p 10 6
Z Z c [cm 3 ]
m
End of Chapter
Chapter 9
Bulkheads
Contents
Section
1 General
2 Subdivision and Arrangement
3 Structural Arrangement and Details
4 Design Loads
5 Plating and Stiffeners
6 Girders
Section 1
General
1.1.1 The requirements of this chapter cover the tc, Zc = corrosion additions to thickness and
arrangement and scantlings of watertight and section modulus respectively as given in Ch.3,
deep tank bulkheads. Sec.2.1
s = spacing of stiffeners [mm] fs =fD for side shell area above neutral axis
l = span of stiffeners [m] fs = fB for side shell area below neutral axis.
Section 2
In ships with machinery aft, the aftpeak 2.3.1 Doors, manholes, permanent access
bulkhead may form the aft boundary of the openings or ventilation ducts are not to be cut in
machinery space. the collision bulkhead below the uppermost
continuous deck.
Additional transverse watertight bulkheads are
to be fitted to ensure adequate transverse 2.3.2 Openings may be accepted in other
strength. watertight bulkheads provided the number and
the size of openings is kept to a minimum
2.1.2 The ordinary transverse watertight bulk- compatible with the design and proper working
heads in the holds should be spaced at of the ship. Where penetrations of watertight
reasonably uniform intervals. Where non- bulkheads are necessary for access, piping,
uniform spacing is unavoidable and the length of ventilation, electrical cables, etc., arrangements
a hold is unusually large, the transverse strength are to be made to maintain the watertight
of the ship is to be maintained by providing integrity. In way of openings, suitable
additional web frames, increased framing etc. reinforcements are to be provided to ensure that
the strength is at least equal to that of the
2.2 Position and height of bulkheads unpierced bulkhead.
Section 3
3.1.1 Oil fuel or oil carried as cargo in the deep 3.2.1 A centreline wash bulkhead is to be fitted
tanks is to have a flash point of 60C and above in peak spaces used as tanks, where the
in closed cup test. Where tanks are intended for breadth of the tank exceeds 0.5B and also in
other liquid cargoes of a special nature the deep tanks used for fuel oil extending from side
scantlings and arrangements will be considered to side.
in relation to the nature of the cargo.
3.2.2 The area of perforations is generally to be
3.1.2 The continuity of bulkhead longitudinals between 5% to 10% of the total area of
within a distance of 0.15D from the bottom or bulkhead. The plating is to be suitably stiffened
the strength deck is to be maintained in in way of the openings.
accordance with Ch.3, Sec.5.1.1.
3.3 Supporting bulkheads
3.1.3 Carlings, girders or floors are to be fitted
below the corrugated bulkheads at their 3.3.1 Bulkheads or parts thereof supporting
supports. These supporting members are to be deck structure are also to be designed as pillars.
aligned to the face plate strips of the The permissible axial loads and buckling
corrugations. strength are to be calculated in accordance with
Ch.3, Sec.6. In calculating sectional properties
3.1.4 The weld connections are to comply with the width of attached plating is not to be taken in
the requirements of Ch.16. excess of 40 times the plate thickness. Also see
Ch.8, Sec.5.1.1.
Section 4
Design Loads
4.2 Tank bulkhead loads hs = vertical distance [m] from the loadpoint to
the top of the tank or hatchway.
4.2.1 The design pressure 'p' for tank bulkheads
are normally to be taken as the greater of For very large tanks which may be partially
filled, sloshing pressures may have to be
p = 12.5 hs [kN/m2] considered.
hp = vertical distance [m] from the loadpoint to 4.3.1 The design pressure 'p' for wash bulk-
the top of the air pipe. heads may be taken as 50% of that for
boundary bulkhead in the same location.
Section 5
= 160/k for transverse tank bulkheads and For built up corrugation bulkheads, where the
collision bulkhead; thickness of the flange and web are different,
the thickness of the wider plating is also not to
be less than :
Between neutral
At strength deck or
Region Framing system At neutral axis axis and strength
at bottom
deck or bottom
(175-130 fs)/k max. To be obtained by
Vertical 140/k
120/k linear interpolation
0.4L amidships
(185-105 fs)/k max. To be obtained by
Longitudinal 160/k
120/k linear interpolation
Within 0.1L from
160/k 160/k 160/k
ends
to be obtained by linear interpolation between allowable values
Elsewhere
at regions specified above.
t.d(b c/3)
Z actual [cm 3 ]
2000
where, t,d,b and c [mm], are as shown in Fig.
5.1.3.
= (215 - 145 fs)/k, max. 160/k [N/mm2] at = 160/k for tank bulkhead and collision
deck/bottom level within 0.4L amidships bulkhead
= 160/k at neutral axis within 0.4L amidships = 210/k for dry bulk cargo bulkheads.
= 160/k for longitudinals within 0.1L from ends. 5.3.2 The thickness of web and flange is to be
as required in 5.1.2.
For longitudinals between the regions specified
above may be obtained by linear interpolation. 5.3.3 Actual section modulus of corrugations is
to be obtained as per 5.2.4.
5.3.4 Brackets are normally to be fitted at the p = applicable design pressure given in Sec.4.
ends of non-continuous stiffeners. Where
stiffeners are sniped at the ends, the thickness m = 16 for stiffeners fixed at both ends
of the plating supported by the stiffeners is not
to be less than: = 12 for stiffeners fixed at one end (lower end in
case of vertical stiffeners) and simply supported
t = 0.0395 [(l - 0.0005s) s.p.k] + tc [mm] at the other end.
5.4 Vertical and transverse stiffeners on = 8 for stiffeners simply supported at both ends.
ordinary watertight bulkheads
= 220/k
5.4.1 The section modulus of bulkhead stiffeners
is not be less than 5.4.2 The thickness of web and flange is to be
as required in 5.1.2. For sniped ends, the
spl 2 thickness of bulkhead plating is to be as per
Z 5.3.4.
m
5.4.3 Actual section modulus of corrugations is
where, to be obtained as per 5.2.4.
Section 6
Girders
6.1.2 The section modulus requirement 'Z' of 6.1.3 The depth of the girders should not be less
simple girders is not to be less than: than 2.5 times the depth of the cutout (if any) for
the passage of continuous stiffeners. The net
b.p.S 2 x 10 3 cross sectional area 'A' of the girder web at ends
Z Z c [cm 3 ] is not to be less than
m
A = CkSbp + 0.01 dw tc [cm2]
where,
where,
m = 12 for continuous longitudinal girders with
end attachments in accordance with Ch.3, C = 0.060 for tank and collision bulkheads
Sec.5.
C = 0.045 for other watertight bulkheads
= 10 for other girders with end attachments in
accordance with Ch.3, Sec.5. dw = depth of web [mm].
= (190 - 45fS), max 160/k [N/mm2], for However, for lower end of vertical girders value
continuous longitudinal girders within 0.4L of C to be taken as 0.08 and 0.06 respectively.
amidships.
6.1.4 Tripping brackets are to be fitted in
= 160/k [N/mm2] for continuous longitudinal accordance with the requirements given in Ch.3,
girders within 0.1L from ends and for vertical or Sec.4.
End of Chapter
Chapter 10
Contents
Section
1 General
2 Scantling
3 Structural Arrangement and Details
4 Bulwarks and Guard Rails
Section 1
General
1.1 Scope 1.2.2 The lowest tier is normally the tier that is
directly situated on the deck to which the rule
1.1.1 The scantlings of the bulwarks and of the depth 'D' is measured or on superstructures
exposed bulkheads of the superstructures and which are less than 1.8 [m] in height.
deckhouses are to comply with the requirements
of this chapter. The scantlings of the decks of 1.3 Symbols
the superstructures and deckhouses are to be in
accordance with the requirements of Ch.8, and 1.3.1 L and k as defined in Ch.1, Sec.2.
those of the sides of the superstructures are to
be in accordance with the requirements of Ch.7. s = spacing of stiffeners [mm].
Section 2
Scantlings
2.1 End bulkheads and exposed sides of 2.1.2 The section modulus Z of stiffeners on
deckhouses fronts, sides and aft ends of deck houses and
the front and aft ends of superstructures is not to
2.1.1 The thickness 't' of steel plating of the be less than:
fronts, sides and aft ends of deckhouses and the
front and aft ends of superstructures is not to be Z = 3.6 sl2 x 10-3 . k [cm3] - for uppermost tier
less than:
I is not to be taken less than 2.0 [m].
t = (0.004 s + 2.5) k - for lowest tier
When a multiple tier erection is fitted, the section
= (0.004 s + 1.5) k - for upper tiers modulus of stiffeners on lower tiers is to be
increased at the rate of 15% per tier fitted above
the tier under consideration.
Section 3
Section 4
For Zone 1 : 900 [mm] 4.2.1 Bulwarks are to be stiffened at the upper
edge by a strong rail section and supported by
For Zone 2 : 600 [mm] stays from the deck, spaced not more than 2.0
[m] apart. Where bulwarks are cut in way of a
For Zone 3 : 300 [mm]. gangway or other openings, stays of increased
Bulwark stays are to be supported by, or are to h = height of the bulwark [m].
be in line with, suitable underdeck stiffening,
which is to be connected by double continuous s = spacing of bulwark stays [m].
fillet welds in way of the bulwark stay
connection. In the calculation of section modulus 'Z', only the
material connected to the deck is to be included.
Bulwarks are to be adequately strengthened in The contribution from bulwark plating and/or
way of the eyeplates for cargo gear. In way of stay flange may be considered depending upon
the mooring pipes, the plating is to be increased the construction details.
in thickness and also adequately stiffened.
4.4 Guard rails
4.2.2 Bulwarks are generally not to be welded to
the top of the sheerstrake within 0.6L amidships 4.4.1 The guard rails are to be supported by
and so arranged as to ensure their freedom from stanchions fitted not more than 3.0 [m] apart;
main structural stresses.
At least every third stanchion is to be supported
4.3 Bulwark scantlings by a bracket or stay.
4.3.1 The thickness of the bulwark plating is not 4.4.2 Lengths of chain may be accepted in lieu
to be less than 4.0 [mm]. of guard rails if they are fitted between two fixed
stanchions and/or bulwarks.
4.3.2 The section modulus 'Z' at the bottom of
the bulwark stay is not to be less than: 4.4.3 The clear opening below the lowest course
of the guard rails is not to exceed 230 [mm].
Z = (33 + 0.44 L) h2 s [cm3]
End of Chapter
Chapter 11
Contents
Section
1 General
2 Hatch Coamings
3 Hatch Covers
4 Miscellaneous Openings
5 Ventilators
6 Air and Sounding Pipes
7 Scuppers and Sanitary Discharges
Section 1
General
1.1 Scope
1.1.3 For the purpose of this section,
1.1.1 This Chapter applies to all ship types in weathertightness of hatch covers means that
general. Additional requirements pertaining to closing appliances do not permit entry of water
special ship types are given in Pt.5. into the ship which may prejudice the safety of
the vessel under the navigational conditions
1.1.2 The requirements of National or local envisaged.
authorities should also be applied, where
relevant.
Section 2
Hatch Coamings
2.2.2 Hatch end coamings when not in line with masthouse or to each other unless they form a
the deck transverses are to extend below the part of the longitudinal strength members. The
deck, at least three longitudinal frame spaces ends of supporting structures of hatch cover
beyond the side coaming. stowage rails are not to end abruptly and are to
be tapered by suitable end brackets.
2.2.3 Continuous hatchway coamings or
coamings forming an effective part of the deck 2.3 Coaming scantlings
girder system are to be made from steel of same
tensile strength as that of the deck plating. 2.3.1 The scantlings of hatch coaming plating
and stiffeners are to be not less than that
2.2.4 If the junction of hatch coamings forms a required for the adjacent deck.
sharp corner, the side and end coamings are to
be extended in the form of tapered brackets in 2.3.2 Hatchway coamings 300 [mm] and above
longitudinal and transverse directions are to be stiffened in their upper edge.
respectively.
Coaming stays are to be fitted at spacing of not
2.2.5 Extension brackets or rails arranged more than 3.0 [m]. The stays are to end on
approximately in line with the cargo hatch side stiffened plating. The coamings are to be
coamings and intended for the stowage of steel satisfactorily stiffened against buckling.
hatch covers are not to be welded to deckhouse,
Section 3
Hatch Covers
q = specified cargo loading [t/m2] on the hatch m = 8 for members simply supported at ends
cover.
= 12 for members which can be considered as
3.2.3 The design internal pressure on hatch fixed at both ends.
covers above tanks are to be determined as per
the design pressure on deck structure given in The moment of inertia of stiffeners and girders is
Ch.8. not to be less than:
3.3.1 The thickness of steel hatch cover plating For other materials the requirement will be
is not to be less than: specially considered.
t 15.8 s p/ x 10 3 t c [mm], or 3.4.2 For covers above cargo and ballast tanks,
fillet welds on tank side are to be double
continuous.
3 [mm] whichever is greater
3.5 Hatch cover edges
where,
3.5.1 The cover edges are to be adequately
p = design pressure as per 3.2 stiffened to withstand the forces imposed upon
them during opening and closing of the hatches.
= 160/k [N/mm2]
3.6 Wooden hatch covers
Hatch covers of G.I. sheet and other material
will be specially considered. 3.6.1 Wooden hatch cover planks are to have a
finished thickness not less than 1/24th of the
3.3.2 The plating of hatch covers acting as unsupported span, with a minimum of 20 [mm].
compression flanges for the hatch cover The planks of wood covers are to be connected
stiffeners and girders is to be effectively at their underside by cross planks spaced not
stiffened against buckling. more than 1.5 [m].
In the middle part of the simply supported span 3.6.2 The ends of all wooden hatch covers are
the critical buckling stress sc is to be such that: to be protected by encircling with galvanized
steel bands.
c 1.15 b [N/mm2]
3.7 Portable hatch beams
where,
3.7.1 The section modulus and the moment of
b = calculated bending stress in the inertia of the portable hatch beams stiffened at
compression flange corresponding to the design their upper and lower edges by continuous flat
load as given in 3.2. bars are to satisfy the requirements of 3.4.
c = the critical buckling stress as per Ch.3, 3.7.2 Carriers or sockets, or other suitable
Sec.6. arrangements are to be provided as means of
the efficient fitting and securing of portable
3.4 Stiffeners and girders hatch beams.
3.4.1 The section modulus of the stiffeners and 3.7.3 Sliding hatch beams are to be provided
girders is not to be less than the following : with an efficient device for locking them in their
correct fore and aft positions when the hatchway
6.25 spl 2 is closed.
Z [cm 3 ]
m
3.9.1 The gaskets and the securing A metallic contact is to be kept between the
arrangements are to be designed for the hatchcover and the hull to effect electrical
expected relative movement between cover and earthing.
coaming or special devices are to be fitted to
restrict such movement. 3.9.4 Where tarpaulins are fitted to make hatch
covers weathertight. They are to be free from
3.9.2 Securing arrangements together with jute, and are to be waterproof and of ample
suitable gasketting material are to ensure strength. At least two layers of tarpaulins are to
weathertightness of the covers to the be provided and these are to be secured by
satisfaction of the surveyors. battens and wedges or equivalent
arrangements.
Section 4
Miscellaneous Openings
4.1.1 Manholes on the weather decks are to be 4.3.1 Machinery space openings are to have
closed by substantial covers capable of closing efficient closing appliances. The openings and
them watertight. coamings for fiddley, funnel and machinery
space ventilators in the casing in those positions
4.2 Companionways, doors and accesses on are to be provided with strong covers of steel or
weather decks other equivalent material permanently attached
in their proper positions and capable of being
4.2.1 Companionways on exposed deck are to secured weathertight.
be equivalent in strength and weathertightness
to a deckhouse in the same portion. The height 4.3.2 Skylights are to be of substantial
of the doorway sills above deck is not to be less construction and secured firmly to the deck. For
than 100 [mm] for Zone 3 and 150 [mm] for skylights the coaming height is not to be less
Zone 1 & 2 on exposed locations. than that required for the hatch coamings.
Efficient means are to be provided for closing
For doorways directly leading to engine room and securing the hinged scuttles, if any. The
the sill height above deck is to be not less than thickness of glasses in fixed or opening skylights
400 [mm]. is to be appropriate to their position and size as
required for side scuttles. Glasses are to be
In addition the sill heights above load waterline protected against mechanical damage, and are
should not be less than the values mentioned to be fitted with deadlights or storm covers
below: permanently attached.
Zone 1 1000 [mm] 4.3.3 Side scuttles in the engine casings are to
be provided with fireproof glass.
Zone 2 600 [mm]
Section 5
Ventilators
5.1 General
Table 5.2.1 : Ventilator coaming
5.1.1 The scantlings of exposed ventilator heights [mm]
coamings are to be equivalent to the scantlings
of deckhouses in the same position. In cargo Without
spaces and other areas where mechanical With closing
closing
damage is likely, the ventilator trunks are to be appliances
appliances
well protected. Zone 1 1000 1700
5.2 Coaming heights Zone 2 600 1000
Zone 3 300 500
5.2.1 Ventilators on exposed decks are to have
the lower edge of openings at a height of not 5.3 Closing appliances
less than 300 [mm] above deck.
5.3.1 Ventilator openings are to be fitted with
In addition the heights of lower edge of openings efficient weathertight closing appliances if
above waterline are to be not less than specified applicable as specified in Table 5.2.1.
in Table 5.2.1.
Section 6
6.1.2 Striking plates of suitable thickness, or 6.2.2 Lower heights may be approved in cases
their equivalent, are to be fitted under all where these are essential for the working of the
sounding pipes. ship, provided closing appliances are of an
approved automatic type.
6.1.3 Air and sounding pipes leading through
cargo containment areas or other spaces where 6.3 Closing appliances
mechanical damage is likely to occur, are to be
well protected. 6.3.1 Permanently attached closing appliances
to prevent free entry of water are to be fitted to
6.2 Height of air pipes all sounding pipes and for air pipes where
required as per 6.2.1.
6.2.1 The height of air pipes from the upper
surface of decks exposed to the weather, to the 6.3.2 Where the closing appliances are not of an
point from where water may have access below, automatic type, provision is to be made for
is not normally to be less than 300 [mm]. relieving vacuum when the tanks are being
pumped out.
Section 7
Zone 1 - 1000 [mm] 7.3.2 All these items, if made of steel or other
approved material with low corrosion resistance,
Zone 2 - 600 [mm] are to be suitably protected against wastage.
Zone 3 - 300 [mm]. 7.3.3 The lengths of pipe attached to the shell
fittings, elbow pieces or valves are to be of
7.3 Materials for valves, fittings and pipes galvanized steel or other equivalent approved
material.
End of Chapter
Chapter 12
Rudders
Contents
Section
1 General
2 Arrangement and Details
3 Design Loads
4 Rudder Blades
5 Rudder Stock and Pintles
6 Rudder Couplings
Section 1
General
Section 2
2.1.3 All rudder bearings are to be accessible for trunk (steering gear flat) is more than 300 [mm]
measuring wear without lifting or unshipping the above the deepest waterline in way trimmed
rudder. condition. When the rudder carrier is fitted below
the deepest load water line, two separate seals
2.1.4 Satisfactory arrangement is to be provided or stuffing boxes are to be provided.
to prevent water from entering the steering gear
compartment and lubricant from being washed 2.1.5 Suitable arrangement is to be provided to
away from the rudder carrier. A seal or stuffing prevent the rudder from lifting and accidental
box is to be fitted above the deepest load water unshipping.
line for this purpose unless the top of the rudder
Section 3
Design Loads
where,
= 1.0 otherwise. 3.3.1 The bending moment (BM) and shear force
(SF) distributions along the entire height of the
Table 3.1.1 rudder blade and rudder stock as well as the
K2 bearing reactions (R) may be obtained by direct
Profile type calculation. The rudder is to be assumed as
ahead astern simply supported at the centres of the upper
NACA:00 bearing and the neck bearing. In case of rudders
1.1 0.80
Gottingen profiles supported by the sole piece or rudder horn the
Hollow profiles 1.35 0.90 flexibility of the sole piece or rudder horn, and
rudder and rudder stock is to be taken into
Flat side profiles 1.1 0.90 consideration.
3.2 Rudder torque 3.3.2 For common types of rudders , the following
approximate values may be used:
3.2.1 The rudder torque on regular shaped
rudders in both the ahead and astern conditions - For balanced rudders with heel support :-
of travel is to be calculated as follows:
Fr . b
Qr = Fr . r [N-m]; BM [N m]
8
where,
Section 4
Rudder Blades
4.1.3 In general, welds between plates and heavy 4.1.5 Arrangement is to be provided to drain the
pieces are to be made as full penetration welds. rudders completely. Drain plugs are to be
Where back welding is not practicable, welding is provided with efficient packing.
to be performed against backing bar or
equivalent.
Section 5
where BM is the bending moment at the cross thickness of the pintle housing is not to be less
section under consideration obtained as per 3.3. than 0.25 dp.
5.1.4 The diameter of the rudder stock at neck 5.2.4 Where liners are fitted to pintles, they are to
bearing is to be maintained to a point as far as be shrunk on or otherwise efficiently secured. If
practicable above the top of the neck bearing and liners are to be shrunk on, the shrinkage
may subsequently be tapered to that required at allowance is to be indicated on the plans. Where
the rudder carrier. The length of the taper is to be liners are formed by stainless steel weld deposit,
at least three times the reduction in diameter. the pintles are to be of weldable quality steel, and
Particular care is to be taken to avoid the details of the procedure are to be submitted.
formation of a notch at the upper end of the taper. Bushing is to be effectively secured against
movement.
5.1.5 Sudden changes of section or sharp
corners in way of the rudder coupling, jumping 5.2.5 Pintle clearances are normally to be as
collars and shoulders for rudder carriers are to be given in Table 5.2.5.
avoided. Jumping collars are not to be welded to
the rudder stock. Keyways in the rudder stock are Attention is to be paid to the manufacturer's
to have rounded ends and the corners at the base recommendations particularly where bush
of the keyway are to be adequately radiused. material requires pre-soaking.
Section 6
Rudder Couplings
n = total number of bolts; ks = material factor for the rudder stock material;
em = mean distance of the bolt axis from the kb = material factor for the bolt material
centre of the bolt system [mm].
n = total number of bolts, not to be less than 8.
6.1.2 Coupling bolts are to be fitted bolts and a
minimum of six (6) bolts are to be provided. Their 6.2.2 The first moment of area of the bolts about
nuts are to be effectively locked. the centre of the coupling to be not less than:
End of Chapter
Chapter 13
Contents
Section
1 General
2 Structural Arrangement for Anchoring Equipment
3 Anchors
4 Anchor Chain Cables
5 Towlines and Mooring Lines
6 Windlass
Section 1
General
1.1.3 Attention is drawn to any relevant 3) Type and breaking load of steel and fibre
requirements of the local Authorities with which ropes.
the ship is to be registered.
1.3 Symbols
1.1.4 The requirements for anchoring and
mooring equipment specified in this Section are 1.3.1 L,B,T as defined in Ch.1, Sec.2.
Section 2
2.1 General suitable size and provided with chafing lips. The
chain lockers boundaries are to be watertight.
2.1.1 The fore end of the vessel is to be arranged Provisions are to be made to minimize the
in such a way that the anchors do not protrude ingress of water to the chain locker in bad
beyond the side shell. The anchors are normally weather. Adequate arrangement for drainage of
to be housed in hawse pipes and anchor pockets chain lockers is to be provided.
of adequate size, scantlings and suitable form to
prevent movement of anchor and chain due to Provisions are to be made for securing the
wave action. inboard ends of the chains to the structure. The
strength of this attachment should be between 15
The arrangements are to provide an easy lead of per cent to 30 per cent of the breaking strength of
chain cable from windlass to the anchors. Upon the chain cable. It is recommended that suitable
release of the brake, the anchors are to arrangements be provided so that in an
immediately start falling by their own weight. emergency the chain can be readily made to slip
Substantial chafing lips are to be provided at shell from an accessible position outside the chain
and deck. These are to have sufficiently large, locker.
radiused faces to minimise the probability of
cable links being subjected to large bending 2.1.4 The windlass and chain stoppers are to be
stresses. Alternatively, roller fairleads of suitable efficiently bedded and secured to deck. The
design may be fitted. thickness of deck plating is to be increased in way
of the windlass and chain stoppers and adequate
Alternative arrangements for housing of anchors stiffening underneath is to be provided.
will be specially considered.
2.1.5 Hawse pipe scantlings
2.1.2 The shell plating and framing in way of the
hawse pipes are to be reinforced as necessary. .1 The gross thickness of the hawse pipes is not
to be less than:
2.1.3 When two chain cables are used, the chain
locker is to be divided into two compartments, — for t0 <10 mm; t = min (t0 + 2; 10)
each capable of housing the full length of one
line. The chain locker is to have adequate — for t0 ≥ 10 mm; t = t0
capacity and depth to provide an easy direct lead
for the cable into the chain pipes, when the cable Where t0 = gross thickness of adjacent shell
is fully stowed. The chain pipes are to be of plating [mm]
Section 3
Anchors
3.1.2 The mass of each bower anchor as required 3.1.7 Anchor shackles are to be of a design and
in this Section is for anchors of equal mass. The material suitable to the service for which the
masses of individual anchors may vary by 7 per anchor is intended.
cent of the calculated masses, provided that the
total mass of the anchors is not less than would 3.2 Manufacture and testing
have been required for anchors of equal mass.
3.2.1 Anchors and anchor shackles are to be
3.1.3 Where the maximum current expected in manufactured and tested in accordance with the
service differs considerably from 8 [km/hr], the requirements of Pt.2, Ch.10 of the Rules and
anchor weight is to be suitably modified. Where Regulations for the Construction and
the maximum current expected in service Classification of Steel Ships.
considerably exceeds 8 [km/hr] or 4.32 [knots],
the calculated anchor mass is to be increased by 3.3 Bow Anchors
the factor:
3.3.1 Cargo Vessels
.
Curent speed in km/hr
8 3.3.1.1 The total mass ‘P’ of the bow anchors of
cargo carriers is to be calculated in accordance
with the following:
.
Curent speed in knots
𝑃 𝑘𝐵𝑇
4.32
.
Where the maximum current expected in service Where, 𝑘 𝑐
8
is less than 8 [km/hr] or 4.32 [knots], the
calculated anchor mass may be reduced by the Loa is the length overall
factor:
.
c is a coefficient defined in Table 3.3.1.1
Current speed in km/hr
8 For pushed barges, k = c
𝐵 𝐵𝑖
3.1.4 The mass of the head, including pins and
fittings, of an ordinary stockless anchor is not to
be less than 60 per cent of the total mass of the where Bi is the individual breadth of each hull.
anchor.
Table 3.3.1.1 : Value of Coefficient ‘c’
3.1.5 The mass 'ex stock' of stocked bower or
stream anchors is not to be less than 80 per cent Deadweight [tonnes] c
of the tabular mass of ordinary stockless bower
anchors. The mass of the stock is to be 25 per ≤ 400 45
cent of the total mass of the anchor including the > 400 ≤ 650 55
shackle etc. but excluding the stock. > 650 ≤ 1000 65
> 1000 70
3.1.6 When anchors of a design approved for the
designation 'High Holding Power' are used as
3.3.2 Passenger vessels and vessels not stern anchors whose total mass is equal to 25%
intended for carriage of goods (e.g. launches) of the maximum mass P calculated in accordance
with 3.3.1.1 for the largest formation considered
3.3.2.1 Passenger vessels and vessels not as a nautical unit.
intended for the carriage of goods, apart from
pushers, are to be fitted with bow anchors whose 3.4.6 Vessels intended to propel downstream
total mass ‘P’ is obtained from the formula in rigid convoys that are longer than 86 [m] are to
3.3.1.1 where: be fitted with stern anchors whose total mass
equals 50% of the greatest mass P calculated in
k: Coefficient corresponding to 3.3.1.1 but, accordance with 4.3.1.1 for the largest formation
where, in order to obtain the value of the considered as a nautical unit.
empirical coefficient c, the maximum
displacement, in m3, is to be taken instead of the 3.4.7 Stern anchors requirements are not
deadweight tonnage. applicable to the following:
3.3.3 Increased bower anchor mass • vessels for which the calculated stern
anchor mass will be less than 150 [kg]
3.3.3.1 For passenger vessels, and for vessels
having a large windage area (such as container • vessels intended to operate on
vessels), the bow anchor mass is to be increased reservoirs, lakes;
as follows:
• pushed barges and pontoons;
𝑃 𝑃 4𝐴
• tugs intended for towing operations
where, 𝐴 is the Transverse profile view (windage only.
area) of the hull above waterline at the draught T,
in m2. 3.5 Mass Reduction
For calculating the area 𝐴 , all superstructures, 3.5.1 The anchor masses calculated in
deckhouses and cargoes (e.g. containers) having accordance with 3.3 and 3.4 may be reduced for
a breadth greater than B/4 are to be taken into certain special anchors, such as high holding
account. power anchors. Examples of such anchors and
the permissible mass reduction is specified in
Parts of windscreens or bulwarks which are more Table 3.5.1
than 0.8 [m] in height are to be regarded as parts
of houses when determining𝐴 . Table 3.5.1 : High Holding Power Anchors
Section 4
In such cases it is recommended that a short 4.3.2 Where the anchors have a mass greater
length of chain or a swivel is fitted between the than that required in 3.3.1 to 3.3.3, the breaking
anchor and the wire rope, having a length equal load of the anchor chain cable is to be determined
at least the distance from the anchor in the as a function of that highest anchor mass.
stowed position to the winch.
4.3.3 The attachments between anchor and
4.1.4 Where wire rope is used in lieu of chain chain are to withstand a tensile load 20% higher
cable for anchoring, galvanised wire rope with an than the tensile strength of the corresponding
independent wire core in accordance with Part 2, chain.
≤ 500 0.35 P’
𝑃 500
> 500 and ≤ 2000 𝑅 0.35 𝑃′
15000
Where the actual anchor mass is greater than required, P ’ is to be taken as the actual anchor
mass
Where the actual anchor is an anchor of the High Holding Power type, the equivalent mass of a
normal anchor is to be used for P’
4.4.1 Bow anchor chain cables The length of stern anchor chain cables is not to
be less than 40 [m]. However, where vessels
Refer to Table 4.4.1 for the minimum length of need to stop facing downstream they are to be
bow anchor chain cables. equipped with a stern anchor chain of not less
than 60 [m] in length.
Section 5
5.1 General
Table 5.1.3 : Minimum breaking strength of
5.1.1 Towlines and mooring lines may be of steel mooring lines, Rs
wire, natural fibre or synthetic fibre and are to be
made by an approved manufacturer. During Rs [kN]
loading and unloading of tank vessels carrying Loa *B * T
inflammable liquids, steel wire ropes only are to 𝐿𝑜𝑎 ∗ 𝐵 ∗ 𝑇
be used for mooring purposes. 𝑅𝑠 60
≤ 1000 [m3] 10
5.1.2 Vessels are to be equipped with three 𝐿𝑜𝑎 ∗ 𝐵 ∗ 𝑇
mooring lines. The length and breaking strength > 1000 [m3] 𝑅𝑠 150
of mooring lines are to be as required by Table 100
5.1.2 and Table 5.1.3 respectively. Also see
Sec.1.1.2. 5.1.4 Pushed barges may be equipped with
atleast least four wire ropes having a theoretical
Ropes and lines should preferably be of the breaking strength of 440 [kN] instead of the
following type: towing ropes.
— 6 × 24 wires + 7 fibre cores for towing ropes 5.2 Manufacture and testing
and mooring lines.
5.2.1 Steel wire ropes are to be manufactured
5.1.3 The diameter of a fibre rope is not to be less and tested in accordance with the requirements
than 20 [mm] of Pt.2, Ch.10 of the Rules and Regulations for
the Construction and Classification of Steel
Table 5.1.2 : Mooring Lines Ships.
Mooring line Minimum length [m] 5.3 Mooring arrangement
l’ = min (l1, l2)
5.3.1 Means are to be provided to enable
l1 = Loa + 20 mooring lines to be efficiently secured on board
1st line
ship by an adequate number of suitably placed
l2 = lmax1 bollards on either side of the ship.
1. lmax = 100 [m] 5.3.3 Mooring winches should be fitted with drum
brakes of sufficient strength to prevent unreeling
2. This line is not required on vessels with Loa of the mooring lines.
< 20 [m].
5.3.4 Adequate stiffening is to be provided in way less than one third of the total power, in [kW], of
of Bollards, Mooring winches etc. the main engine(s).
5.4 Towing lines 5.4.2 Self-propelled vessels and pushers that are
also intended to tow are to be equipped with an
5.4.1 Tugs are to be equipped with a number of at least 100 [m] long towing line whose breaking
lines that are suitable for their operation. strength in [kN], is not less than one quarter of the
However, the main cable is to be at least 100 [m] total power, in [kW], of the main engine(s).
long and have a breaking strength, in [kN], not
Section 6
Windlass
End of Chapter
Chapter 14
Welding
Contents
Section
1 General
2 Welding
3 Welded Connections
Section 1
General
Section 2
Welding
2.1 Welders and supervision electrodes suitable for the lower grade will be
generally acceptable except at structural
2.1.1 Welders are to be proficient in the type of discontinuities or other points of stress
work on which they are to be engaged. The concentration.
records of their tests and qualifications are to be
kept by the builders and made available to the 2.2.3 For the connection of steel of different
Surveyors. A sufficient number of skilled tensile strengths, the electrodes are to be
supervisors are to be employed to ensure suitable for the tensile strength of the component,
effective control at all stages of assembly and on the basis of which the weld fillet size has been
welding operations. determined in Sec.3.
2.2.1 Electrodes and welding consumables 2.3.1 The parts to be welded are to be fitted in
approved by IRS in accordance with the accordance with the approved joint detail. The
requirements of Pt.2, Ch.11 and suitable for the edge preparation is to be accurate and uniform.
type of joint and grade of steel, are to be used. Means are to be provided for maintaining the
parts to be welded, in correct position during the
2.2.2 For the connection of two different grades welding operations. Excessive force is not to be
of steel of the same tensile strength properties, employed in aligning the parts before welding and
2.4.4 Adequate precautions are to be taken to 2.6.4 Defective sections of welds as found by
ensure that the welding site is protected from the visual or non- destructive examination or
deleterious effects of high moisture, severe wind leakages under hydrostatic tests, are to be
and extreme cold. gouged out as necessary and carefully rewelded.
Section 3
Welded Connections
3.1.2 For joints of plates with difference in throat thickness = tp . weld factor . d/s
thickness of more than 4 [mm], the thicker plate
is to be tapered. The taper is not to exceed 1:3. where,
Edge preparation after the tapering is to be as
indicated in Sec.3.1.1. tp = thickness [mm], of the thinner of the two parts
being connected.
3.1.3 All manual butt welds are normally to be
welded from both sides. Where a back ceiling run d = distance [mm], between the successive weld
is not practicable or in certain cases when the fillets.
stress level in the members is very low, welding
on one side may be permitted provided the s = length [mm], of the correctly proportioned
welding process is found satisfactory. weld fillets, clear of end craterss is not to be less
than 75 [mm].
3.1.4 Where stiffening members, attached by
continuous fillet welds, cross the finished butt or The weld factors for various connections are
seam welds, these welds are to be made flush in generally to be as given in Table - 3.2.1.
way of the faying surface. Similarly for butt welds
in webs of stiffening members, the butt weld is to Where an approved automatic deep penetration
be first completed and made flush with the procedure is used, the weld factors may be
stiffening member before the stiffener is reduced by 15 per cent
connected to the plating by fillet weld. The ends
of the flush portion are to run out smoothly 3.2.2 The throat thickness is not to be less than
without notches or any sudden change of section. 3.0 [mm] and generally not to be greater than
Where such conditions can not be complied with, 0.44 tp for double continuous welds and the
a scallop is to be arranged in the web of the greater of 0.44 tp or 4.5 [mm] for intermittent
stiffening member. Scallops are to be of such size welds.
Side Structure
Transverse frames to side shell
in tanks 0.13 *
elsewhere 0.11 *
Side longitudinals to shell plating 0.13 *
Web frames & side to shell plating
stringers
within 0.2 x span from ends 0.35 *
elsewhere 0.20 *
to face plate and tripping bracket 0.15 *
Web frames to side stringers 0.3 *
Bilge keel to ground bars 0.2 *
Bilge keel ground bar to side shell 0.35 * Single cont.
Deck Structure
Strength deck to shell F.P. See Note 3
Other decks to shell and bulkheads 0.3 * Generally
Deck beams to deck plating
in tanks 0.13 *
elsewhere 0.11 *
Deck longitudinals to decks 0.13 *
Deck girders to deck plating
elsewhere 0.20 *
to face plating and tripping brackets 0.15 *
Cantilever webs to shell, decks, face plates and 0.35 *
longitudinal girders at ends
Pillars to deck, inner bottom and pillar 0.40 *
brackets
elsewhere 0.40 *
to faceplate 0.30 *
elsewhere 0.20 *
to faceplate & tripping brackets 0.15 *
elsewhere 0.3 * *
Webs to face plates 0.3 *
Webs to webs of other primary members 0.3 *
Boundaries of tripping brackets 0.15 *
elsewhere 0.25 *
Internal bulkheads boundaries 0.13 *
Stiffeners to external bulkheads 0.10 *
Note 2 Preferably to be deep penetration or full penetration weld depending on the thickness of the engine girders.
3.2.3 The leg length is not to be less than √2 d) All framing within holds of bulk carriers
times the specified throat thickness. intended for carriage of coal.
3.2.4 Where the connection is highly stressed, e) All welding inside tanks intended for
deep penetration or full penetration welding may chemicals or edible liquid cargoes.
be required. Where full penetration welding s
required, the abutting plate may require to be f) All lap welds in tanks.
beveled.
g) Primary and secondary members to plating in
3.2.5 Continuous welding is to be adopted in the way of end connections and end brackets to
following locations and in any other region of high plating in the case of lap connection.
dynamic loading:-
h) Other connections as given in Table - 3.2.1.
a) Boundaries of weathertight decks and
erections, including hatch coamings, 3.2.6 Where intermittent welding is used, the
companionways and other openings. welding is to be made continuous around the
ends of brackets, lugs, scallops and at other
b) Boundaries of tanks and watertight orthogonal connections with other members. In
compartments. tanks for water ballast, cargo oil or fresh water,
only scalloped welding is to be used.
c) All structures in the afterpeak and the
afterpeak bulkhead stiffeners. 3.2.7 Where structural members pass through
the boundary of a tank, and leakage into the
End of Chapter
Chapter 15
Contents
Section
1 Hull Inspection
2 Workmanship
3 Testing
Section 1
Hull Inspection
Section 2
Workmanship
2.1 General
2.3.1 Flanging and bending of plates while cold
2.1.1 All workmanship is to be of good quality and forming are not to have an average bending
in accordance with good shipbuilding practice. radius less than three times the plating thickness.
Any defect is to be rectified to the satisfaction of The minimum radius is not to be less than twice
the Surveyor before being covered with paint, the plating thickness.
cement or other composition.
2.3.2 During joggling of plates and profiles, the
2.1.2 The assembly sequence and welding depth of joggle is not to be less than four times
sequence are to be agreed prior to construction and the bending radius not less than twice the
and are to be to the satisfaction of the Surveyor. web thickness.
2.2 Plate edges and cut-outs 2.4 Hammering, bending and straightening
2.2.1 Openings, holes and other cut-outs in the 2.4.1 Steel being worked on when hot, is not to
main structural components are to be rounded off be overheated, and it is to be hammered and bent
by adequately large radii. The free edges of cut- in the appropriate heat condition. Steel which is
outs, hatch corners etc. are to be properly burnt, is not to be used.
prepared and are to be free from notches. All
edges should be faired. 2.4.2 Flame heating may be employed to
straighten buckled plating when the buckling is
2.3 Cold forming not severe.
Section 3
Testing
3.1.3 Hydropneumatic testing is a combination of b) leak testing is carried out prior to the
hydrostatic and air testing, consisting of filling the application of the protective coating.
tank with water up to its top and applying an
additional air pressure. The value of the However, when leak testing is not carried out,
additional air pressure is to be at least as given in protective coating in way of the following welds
Sec.3.4. should be applied only after the structural testing
has been satisfactorily completed:
3.1.4 Leak testing is an air or other medium test
carried out to demonstrate the tightness of the all erection welds, both manual and
structure. automatic
3.1.5 Hose testing is carried out to demonstrate all manual fillet weld connections on tank
the tightness of structural items not subjected to boundaries and manual penetration
hydrostatic or leak testing and to other welds.
components which contribute to the watertight or
weathertight integrity of the hull. 3.4 Leak testing
tanks, including independent tanks Prior to inspection, it is recommended that the air
pressure in the tank is raised to 10 [KN/m2] and
watertight or weathertight structures. kept at this level for about 1 hour to reach a
stabilized state, with a minimum number of
The purpose of these tests is to check the personnel in the vicinity of the tank, and then
tightness and/or the strength of structural lowered to the test pressure.
elements.
3.4.2 Welds are to be coated with an efficient
Tests are to be carried out in the presence of the indicating liquid.
Surveyor at a stage sufficiently close to
completion so that any subsequent work would 3.4.3 A U-tube filled with water up to a height
not impair the strength and tightness of the corresponding to the test pressure is to be fitted
structure. to avoid overpressure of the compartment tested
[a] Leak or hydropneumatic testing may be accepted under the conditions specified in 3.4, provided that at least one tank for each
type is structurally tested. This however does not apply to cargo space boundaries in tankers and tanks for segregated cargoes or
pollutants. If the structural test reveals weakness or severe faults not detected by the leak test, all tanks are to be structurally
tested.
[b] Where applicable, the highest point of tank is to be measured to the deck and excluding hatches.
[c] When hose test cannot be performed without damaging possible outfitting (machinery, cables, switchboards, insulation, etc.)
already installed, it may be replaced, at the discretion of IRS by a careful visual inspection of all the crossings and welded joints;
where necessary, dye penetrant test or ultrasonic leak test may be required.
[d] The test may be made before or after the door is fitted. In case test is done before, hose testing is to be carried out in place
after the door is fitted.
End of Chapter
Part 4
Contents
Contents
Chapter 1
Chapter 2
Section 1
1.3 Design pressure
General 1.4 Design temperature
Section 6
Section 3
Flexible Hoses
Copper and Copper Alloys Pipes and
Fittings 6.1 General
Cast Iron Pipes and Fittings 7.2 Testing after assembly on board
Chapter 3
1.2 Plans
Section 2
1.3 Materials
2.5 Drainage from spaces above fore and after 5.1 General
peaks and above machinery spaces
5.2 Cooling water main supply
2.6 Drainage from machinery spaces
5.3 Cooling water standby supply
2.7 Sizes of bilge suctions
5.4 Relief valves on cooling water pumps
2.8 Bilge pumps and ejectors
5.5 Sea inlets for cooling water pumps
2.9 Pump types
6.1 General
Section 3
6.2 Pumps
Air and Sounding Piping Systems
6.3 Control of pumps and alarms
3.1 General
6.4 Filters
3.2 Air pipes
6.5 Valves and cocks on lubricating oil tanks
3.3 Sounding arrangements
Section 7
Section 4
Engine Exhaust Gas Piping Systems
Fuel Oil Systems
7.1 General
4.1 General
4.6 Oil fuel burning arrangements 8.2 Vessels without auxiliary power
4.7 Remote stop of oil fuel pumps and fans 8.3 Vessels with auxiliary power
Chapter 4
Section 1 Section 3
General Propellers
Chapter 5
Chapter 6
Steering Gears
Chapter 7
Chapter 8
7.4 Regulation
Switchboards
7.5 Short circuit
4.1 General
7.6 Tests
4.2 Instruments
8.1.3 Installation
Control Gear
8.1.4 Ventilation
5.1 General
8.2 Luminaries
Section 9
8.2.1 General
Chapter 9
General
Section 3
1.1 Scope
Fire Detection
1.2 Applicable requirements depending on vessel
type 3.1 General
1.4 Definitions
Section 4
1.5 Ship Types
Fire Extinction
Section 2
4.1 Water supply system
Chapter 10
Spare Gear
End of Contents
Chapter 1
Contents
Section
1 General
2 Machinery Room Arrangements
3 Trials
4 Certification of Machinery and Components based upon Quality management
Systems
Section 1
General
1.2.1 In ships intended to be built under Special Air compressors, air receivers and other
Survey, all important units of equipment are to be pressure vessels necessary for the operation
surveyed at the manufacturer's works. The of main propulsion and essential machinery.
workmanship is to be to the Surveyor's
satisfaction and the Surveyor is to be satisfied Alarm and control equipment as detailed in
that the components are suitable for the intended Ch.7; and
purpose and duty. Examples of such units are :
Electrical equipment and electrical propelling
Main propulsion engines, including their machinery as detailed in Ch.8.
associated gearing, flexible couplings,
scavenge blowers and superchargers; 1.3 Extent of survey
Boilers supplying steam for propulsion or for 1.3.1 The Surveyors are to examine and test the
services essential for the safety or the materials and workmanship from the
operation of the ship at sea, including commencement of work until the final test of the
superheaters, economisers, desuperheaters, machinery under full power working conditions.
steam receivers. All other boilers having Any defects, etc., are to be indicated as early as
working pressures exceeding 3.5 bar, and possible. On completion, the Surveyors will
having heating surfaces greater than 4.65 submit a report and, if this is found to be
[m2]; satisfactory by IRS, a certificate of class will be
granted and an appropriate notation assigned in
Auxiliary engines of 110 [kW] (150 shp) and accordance with Pt.1.
1.4 Departures from the rules shaft power and corresponding revolutions
per minute giving the maximum torque for
1.4.1 Where it is proposed to depart from the which the machinery is to be classed; and
requirements of the Rules, IRS will be prepared
to give due consideration to the circumstances of For auxiliary machinery, the maximum
any special case. continuous shaft power and corresponding
revolutions per minute which will be used in
1.5 Plans and particulars service.
1.8 Power ratings 1.11.1 The flash point (closed cup test) of oil fuel
is to be not less than 55C, unless specially
1.8.1 In the following Chapters, where the approved. 1.11.2 Fuels with flash points lower
dimensions of any particular component are than 55C, but not less than 43C, unless
determined from shaft power, P in [kW] (H, in specially approved, may be used in ships
shp), and revolutions per minute, R, the values to intended for service restricted to certain
be used are to be derived from the following : geographical limits, where it can be ensured that
the temperature of the machinery spaces will
For main propelling machinery, the maximum always be 10C below the flash point of the fuel.
Section 2
Section 3
Trials
Section 4
A list of suppliers of materials and 4.4.4 The certificate will be valid for 3 years
components and proposed arrangements to subject to surveillance assessments being
ensure compliance with IRS requirements for carried out every 6 months.
certification.
4.4.5 When significant faults or deficiencies are
4.4 Approval and maintenance of approval found during surveillance assessments or
surveillance assessments are not carried out, the
4.4.1 After receipt and appraisal of the certificate of approval may be
information required by 4.3, an assessment of the withdrawn/suspended at the discretion of IRS.
Works would be carried out by the Surveyors to
ensure compliance with the quality manual. 4.5 Certification of products
4.4.2 If the initial assessment of the Works 4.5.1 After issue of the Quality Assurance
confirms that the implementation of the quality Approval Certificate, the manufacturer would be
management systems is satisfactory, IRS will authorized to issue certificate for products on
issue to the manufacturer a Quality Assurance behalf of IRS subject to the certificates being
Approval Certificate which will include details of countersigned by IRS Surveyors. Arrangements
the products for which approval has been given. for this will be specially advised by IRS.
End of Chapter
Chapter 2
Contents
Section
1 General
2 Carbon and Low Alloy Steel Pipes and Fittings
3 Copper and Copper Alloy Pipes and Fittings
4 Cast Iron Pipes and Fittings
5 Plastic Pipes
6 Flexible Hoses
7 Hydraulic Tests on Pipes and Fittings
Section 1
General
1.1 Scope
1.2.3 In addition to the pressure piping systems
1.1.1 The requirements of this Chapter apply to in Table 1.2.1, Class III pipes may be used for
the design and construction of piping systems, open ended piping, e.g. overflows, vents, boiler
including pipe fittings forming parts of such waste steam pipes, open ended drains etc.
systems but excluding steam piping systems and
systems where the temperature exceeds 300C. 1.3 Design pressure
1.1.2 For steam piping systems and systems 1.3.1 The design pressure, P, is the maximum
having temperatures greater than 300C, the permissible working pressure and is to be not
Rules and Regulations for the Construction & less than the highest set pressure of the safety
Classification of Steel Ships will be applicable. valve or relief valve.
1.2 Classes of pipes 1.3.2 The design pressure of feed piping and
other piping on the discharge from pumps is to be
1.2.1 For the purpose of testing, type of joints to taken as the pump pressure at full rated speed
be adopted, heat treatment and welding against a shut valve. Where a safety valve or
procedure, piping systems are divided into three other protective device is fitted to restrict the
classes, as given in Table 1.2.1. pressure to a lower value than the shut valve
load, the design pressure is to be the highest set
1.2.2 For Class I piping, the Rules and pressure of the protective device.
Regulations for the Construction & Classification
of Steel Ships will be applicable.
Section 2
2.1 Materials 2.1.2 Materials for Class III piping systems may
be manufactured and tested in accordance with
2.1.1 Materials for Class I and Class II piping the requirements of acceptable national
systems, also for ship-side valves and fittings and /international specifications. Pipes having forge
valves on the collision bulkhead, are to be butt welded longitudinal seams are not to be used
manufactured and tested in accordance with the for oil fuel systems, for heating coils in oil tanks,
appropriate requirements of Ch.8, Pt.2, or for pressures exceeding 0.4 [N/mm2]. The
Inspection and Testing of Materials, of Rules & manufacturer's test certificate will be acceptable
Regulations for the Construction and and is to be provided for each consignment of
Classification of Steel Ships. material.
Fig. 2.3.1
Table 2.3.1 : Type of flange connections
Lub. and fuel oil Other media
Class of piping Typical flange Typical flange
tC
application application
A-B-C
II A-B-C > 250 250
A-B-C-D-E
III A-B-C-E A - B - C -D - E
2.3.4 Where flanges are secured by screwing, as The vanishing thread on a pipe is to be not less
indicated in Fig.2.3.1, the pipe and flange are to than three pitches in length, and the diameter at
be screwed with a vanishing thread and the the root of the thread is to increase uniformly from
diameter of the screwed position of pipe over the the standard root diameter to the diameter at the
thread is not to be appreciably less than the top of the thread. This may be produced by
outside diameters of the unscrewed pipe. After suitably grinding the dies, and the flange should
the flange has been screwed hard home, the pipe be tapered out to the same formation.
is to be expanded into the flange.
2.4 Threaded sleeve joints 2.5.2 Selected butt welds of pipes of outside
diameter of 101.6 [mm] and over in Class II piping
2.4.1 Threaded sleeve joints, in accordance with systems are to be radiographed at Surveyor's
national or other established standards, may be discretion. Use of ultrasonic examination in lieu
used with carbon steel pipes within the limits of radiography will be specially considered.
given in Table 2.4.1 and for services other than
pipe systems conveying combustible fluids. 2.5.3 Selected fillet welds in pipes of 101.6 [mm]
outside diameter and over in Class II piping
systems are to be examined by magnetic particle
Table 2.4.1 : Limiting design conditions for or liquid penetrant flaw testing at Surveyor's
threaded sleeve joints discretion.
Section 3
Section 4
4.1 Spheroidal or nodular graphite cast iron in general, be accepted in Class III piping
systems except as stated in 4.2.2.
4.1.1 Spheroidal or nodular graphite iron castings
for pipes, valves and fittings in Class II and III 4.2.2 Grey cast iron is not to be used for the
piping systems are to be made in a grade having following:
a specified minimum elongation not less than 12
per cent on gauge length of 5.65So, where So a) Pipes for steam systems and fire
is the actual cross-sectional area of the test extinguishing systems;
piece.
b) Pipes, valves and fittings for boiler blow
4.1.2 Castings for Class II and III systems, also down systems and other piping systems
for ship-side valves and fittings and valves on subject to shock or vibration;
collision bulkhead, are to be manufactured and
tested in accordance with the requirements of c) Ship-side valves and fittings;
acceptable national specifications. A
manufacturer's test certificate will be accepted d) Valves fitted on collision bulkhead;
and is to be provided for each consignment of
material. e) Clean ballast lines through cargo oil tanks to
forward ballast tanks;
4.1.3 Where the elongation is less than the
minimum required by 4.1.1, the material is, in f) Bilge lines in tanks;
general, to be subject to the same limitations as
grey cast iron. g) Outlet valves of fuel tanks with static head.
4.2 Grey cast iron 4.2.3 Grey iron castings for piping systems are to
comply with acceptable national/international
4.2.1 Grey cast iron pipes, valves and fittings will, specifications.
Section 5
Plastic Pipes
5.1 General
c) Sanitary and domestic waste pipes wholly
5.1.1 Proposals to use plastics material in situated above the freeboard deck; and
shipboard piping systems will be considered in
relation to the properties of the materials, the d) Water pipes associated with air conditioning
operating conditions of temperature and plants.
pressure, and the intended service. Any
proposed service for plastics pipe not mentioned Not withstanding the foregoing, plastics pipes are
in these Rules is to be submitted for special not to be used in sea water systems where
consideration. leakage or failure of the pipes could give rise to
the danger of flooding.
5.1.2 The specification of the plastics material,
including mechanical and thermal properties and 5.2.3 Since plastics materials are generally heat
chemical resistance data, is to be submitted for sensitive and very susceptible to fire damage,
consideration. plastics pipes will not be acceptable for service
essential to safety, such as the following :
5.1.3 These requirements are applicable to
thermo-plastic pipes but, where appropriate, may a) Fire extinguishing pipes;
also be applied to pipes manufactured in fibre-
reinforced thermosetting resins. b) Bilge pipes in cargo holds;
5.1.4 Plastics pipes are not to be used where they c) Bilge and ballast pipes in the machinery
will be subjected to temperatures above 60C or space;
below 0C. Special consideration will be given to
particular materials in appropriate applications at d) Main and auxiliary water circulating pipes;
higher temperatures.
e) Feed and condensate pipes; and
5.2 Applications
f) Pipes carrying oil or other flammable liquids.
5.2.1 Plastics pipes of approved type may be
used for the following 5.3 Intactness of bulkheads and decks
services:
5.3.1 Where plastics pipes are arranged to pass
a) Air and sounding pipes to tanks used through watertight or fire- resisting bulkheads or
exclusively for carrying water ballast or fresh decks, provision is to be made for maintaining the
water, with the exception of the portion above integrity of the bulkhead or deck in the event of
deck; pipe failure. Details of the arrangements are to be
submitted for approval.
b) Sounding pipes to cargo holds;
5.4 Design and construction
c) Water ballast and fresh water pipes situated
inside tanks used exclusively for carrying 5.4.1 Pipes and fittings are to be of robust
water ballast or fresh water; and construction and are to comply with the
requirements of such national/international
d) Scupper pipes draining inboard provided standards as may be consistent with their
they are not led within the boundaries of intended use. Particulars of scantlings and joints
refrigerated chambers. The first two items (a are to be submitted for consideration.
and b) are not applicable to passenger ships.
5.4.2 All pipes are to be adequately but freely
5.2.2 Plastics pipes may be used for domestic supported. Suitable provision for expansion and
and similar services for which there are no Rule contraction is to be made in each range of pipes
requirements, such as for the following: to allow for large movements between plastics
pipe and steel structure, the coefficient of thermal
a) Domestic cold sea and fresh water systems; expansion for plastics being eight or more times
that of steel.
b) Sanitary systems;
5.4.3 All fittings and branches are to be suitable pipes and joints between pipes and fittings, as
for the intended service and are to have joints of appropriate, is to be determined by hydraulic
cemented, flanged or other approved types. pressure tests to destruction of sample
assemblies. The pressure is to be so applied that
5.4.4 The strength of the pipes and fittings and failure of the test sample assembly occurs in not
the acceptability of any jointing system employed less than 5 minutes. Deformation of the pipes and
is to be check tested at the Surveyor's discretion. fittings during tests is acceptable.
The strength of pipes, fittings, joints between
Section 6
Flexible Hoses
Section 7
7.1 Hydraulic tests before installation on hydraulic pressure to 1.5 times the nominal
board pressure rating at ambient temperature.
However, the test pressure need not be more
7.1.1 All Class II pipes and their associated than 7 [N/mm2] above the design pressure
fittings are to be tested by hydraulic pressure to specified for the design temperature.
the Surveyor's satisfaction. Further, all steam,
feed, compressed air and fuel oil pipes, together 7.2 Testing after assembly on board
with their fittings, are to be similarly tested where
the design pressure is greater than 0.35 [N/mm2]. 7.2.1 Heating coils in tanks and fuel oil piping are
The test is to be carried out after completion of to be tested by hydraulic pressure, after
manufacture and before installation on board installation on board, to 1.5 times the design
and, where applicable, before insulating and pressure but in no case to less than 0.35 [N/mm2].
coating.
7.2.2 Where bilge pipes are accepted in way of
7.1.2 The test pressure is to be 1.5 times the double bottom tanks or deep tanks, the pipes
design pressure. after fitting are to be tested by hydraulic pressure
to the same pressure as the tanks through which
7.1.3 All valve bodies are to be tested by they pass.
End of Chapter
Chapter 3
Contents
Section
1 General
2 Bilge and Ballast Piping Systems
3 Air and Sounding Piping Systems
4 Fuel Oil Systems
5 Engine Cooling Water Systems
6 Lubricating Oil Piping Systems
7 Engine Exhaust Gas Piping Systems
8 Pumping and Piping Systems for Vessels not Fitted with Propelling Machinery
Section 1
General
1.1.1 The requirements of this Chapter are h) Steering gear piping systems;
applicable to all ships except where otherwise
stated. i) Sea water and fresh water service piping
systems;
1.1.2 Piping systems layouts, for which no
requirements are given herein, will be specially j) Air and sounding piping systems;
considered.
k) Steam and feed water piping systems
1.2 Plans
l) Sanitary piping systems;
1.2.1 The following plans in diagrammatic form
are to be submitted for consideration before m) Fire main and fire extinguishing piping
proceeding with the work. systems.
a) General arrangement of pumps and piping 1.2.2 The plans are to include the information
systems; like, wall thickness, maximum working pressure
temperature and material of all pipes and type,
b) Fuel oil filling, transfer and service piping size and material of the valves and fittings.
systems;
1.3 Materials
c) Bilge and ballast piping systems;
1.3.1 The materials to be used in piping systems
d) Lubricating-oil piping systems; are to be suitable for the service intended. In
general, except where otherwise stated, pipes,
e) Liquid cargo pumping systems; valves and fittings are to be made of steel, cast
iron, copper, copper alloy or other approved
f) Hydraulic power piping systems for essential material.
services;
1.3.2 Cast iron is not to be used for: 1.7.3 All the valves and cocks are to be fitted in
places where they are easily accessible at all
a) Shipside and collision bulkhead fittings; times and are to be fitted with legible nameplates
indicating their function in the system and their
b) Outlet valves of fuel tanks with static head; installation is to be such that it can be readily
observed that they are open or closed.
c) Bilge and ballast lines passing through
double bottom tanks, pipe tunnel and cargo 1.7.4 All the valves and cocks fitted with remote
oil tanks; control are to be provided with local manual
control independent of the remote operating
d) Any piping which can be subjected to shock mechanism. The operation of the local control is
such as water hammer. not to render the remote control system
inoperable.
1.3.3 Materials sensitive to heat such as
aluminium, lead or plastics, are not to be used in 1.7.5 The valves, cocks and other fittings which
systems essential to the safe operation of the are attached directly to plating, which is required
ship. to be of watertight construction, are to be secured
to the plating by means of studs screwed into the
1.4 Design pressure plating and not by bolts passing through
clearance holes. Alternatively the studs may be
1.4.1 The design pressure is considered to be, welded to the plating.
the most severe condition of co-incident pressure
and temperature expected in normal operation. 1.8 Shipside fittings (other than sanitary
For this purpose the maximum difference in discharges and scuppers)
pressure between inside and outside of the part
is to be considered. 1.8.1 All sea inlet and overboard discharge
valves are to be fitted in either of the following
1.5 Design temperature ways:
1.5.1 Unless otherwise specified the tempe- a) directly on the shell plating;
rature used in design is to be not less than the
mean metal temperature (through the thickness) b) to the plating of fabricated steel water boxes
expected under operating conditions for the part of rigid construction integral with the ship's
considered. plating;
1.5.2 When sudden cyclic changes in tempe- c) to short, rigid distance pieces welded to the
rature are apt to occur in normal operation with shell plating.
only minor pressure fluctuations, the design is to
be governed by the highest probable operating 1.8.2 Valves for ship-side applications are to be
temperature and corresponding pressure. installed such that the section of piping
immediately inboard of the valve can be removed
1.6 Redundancy without affecting the watertight integrity of the
hull.
1.6.1 Redundancy is the ability of a system or a
component thereof to maintain or restore its 1.8.3 All valves and cocks fitted directly to the
function when one failure has occurred. This can shell plating are to have spigots extending
be achieved for instance by installation of more through the plating. These spigot on valves may
units or alternative means for performing the however be omitted, if valves are fitted on pads
function. which themselves form spigots in way of plating.
1.7 Valves and cocks 1.8.4 Valves and cocks are to be attached to the
shell plating by bolts tapped into the plating and
1.7.1 All the valves and cocks are to be so fitted with countersunk heads, or by studs
designed and constructed so that the valve screwed into heavy steel pads fitted to the
covers or glands will not slacken up when the plating. The stud holes are not to penetrate the
valves are operated. pad plating.
1.7.2 All the valves are to be designed to close 1.8.5 Ship side valves and fittings, if made of
with right hand (clockwise when facing the end of steel or material with low corrosion resistance,
the stem) motion of the wheel of the valve. are to be suitably protected against wastage.
Section 2
The after peak may be drained by means of a self 2.5.1 Provision is to be made for the drainage of
closing cock situated in a well lighted and chain locker and watertight compartments above
accessible position, and draining into engine the fore peak tank by hand or power pump
room or tunnel. suctions.
2.3.3 The collision bulkhead is not to be pierced 2.5.2 Steering gear compartments or other small
below the bulkhead deck by more than one pipe enclosed spaces situated above the after peak
for dealing with the contents inside the fore peak tank are to be provided with suitable means of
tank except as permitted in 2.3.4. The pipe is to drainage, either by hand or power bilge suctions.
be provided with a screw down valve capable of
being operated from above the bulkhead deck 2.5.3 If the compartments referred to in 2.5.2 are
and the chest of the valve is to be secured to the adequately isolated from the adjacent 'tween
collision bulkhead inside the tank except as decks, they may be drained by scuppers of not
permitted by 2.3.5. An indicator is to be provided less than 38 [mm] bore, discharging into the
to indicate whether the valve is open or shut. tunnel (or machinery spaces in case of ships with
machinery aft) and fitted with self-closing cocks
2.3.4 In ships, other than passenger vessels, situated in well lighted and visible positions.
where the forepeak is divided into two These arrangements are not applicable to
compartments, the collision bulkhead may be passenger ships unless they are specially
pierced by two pipes, i.e. one for each approved in relation to subdivision
compartment and fitted as in 2.3.3. considerations.
2.3.5 In ships other than passenger ships, the 2.5.4 Accommodation spaces which overhang
valve required by 2.3.3 may be fitted on the after machinery spaces may also be drained as in
side of the collision bulkhead, provided the valve 2.5.3.
is readily accessible at all time and is not subject
to mechanical damage. 2.6 Drainage from machinery spaces
2.4 Drainage from tanks, cofferdams and void 2.6.1 The bilge drainage arrangements for
spaces machinery spaces are to be in accordance with
the requirements of 2.1.
2.4.1 All the tanks except self-draining tanks,
whether for water ballast, oil fuel, liquid cargoes, 2.6.2 In ships in which the propelling machinery
etc. are to be provided with suction pipes led to is situated at the after end of the ship, it will
suitable power pumps. The pumping plant is to generally be necessary for the bilge suctions to
be so arranged that any water or liquid within any be fitted in the forward wings as well as in the
compartment of the ship can be pumped out after end of the machinery space, but each case
through at least one suction, when the ship is on will be dealt with according to the size and
an even keel and is either upright or has a list of structural arrangements of the compartment.
not more than 5 degrees.
2.6.3 Where the machinery space is divided into
2.4.2 Where the length of the ballast tank watertight compartments, the drainage system
exceeds 30 [m], an additional suction is to be for all compartments except for main engine room
provided at the forward end of the tank. Where is to be same as for cargo holds except that one
the width of the tank is unusually large, suctions direct bilge suction from each watertight
near the centreline in addition to wing suctions compartment would also be required.
may be required.
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 5 of 12
___________________________________________________________________________________
2.7 Sizes of bilge suctions engines power exceeds 220 [kW] (300 shp), at
least two power bilge pumps are to be provided
2.7.1 The internal diameter of the bilge pipes is and at least one of which is to be independently
not to be less than that found by the following driven. See Part 5, Chapter 3 for requirements
formula to the nearest 5 [mm] commercial size regarding passenger ships.
available:
2.8.2 The capacity of the bilge pump may be
found by the following formula:
a) dm = 1.5 L (B D) + 25 [mm]
Q = 5.75 x 10-3 x d2 [m3/hour]
welded or heavy flange joints. The open ends of 2.10.9 The arrangement of valves, pumps, cocks
such pipes are to be fitted with non-return valves. and their pipe connections is to be such as to
The pipes are to be tested, after fitting, to a prevent the possibility of placing one watertight
pressure of not less than the maximum head to compartment in communication with another, or
which the tanks may be subjected. of cargo spaces, machinery spaces or other dry
spaces coming in communication with the sea or
2.10.3 Expansion bends, not glands, are to be the tanks. For this purpose the bilge suction, pipe
fitted to pipes passing through double bottom of any pump also having sea suction is to be fitted
tanks or deep tanks. with a non-return valve which cannot permit
communication between the bilges and the sea
2.10.4 The intactness of the machinery spaces, or the compartments in use as tanks.
bulkheads and of tunnel plating is not to be
impaired by fitting of scuppers discharging into 2.10.10 Screw-down non-return valves are to be
machinery spaces or tunnel from adjacent provided in the following fittings:
compartments which are situated below the
bulkhead deck. These scuppers may, however, a) Bilge distribution chest valves;
be led into a strongly built scupper drain tank
situated in the machinery space or tunnel but b) Direct bilge suction and bilge pump
closed to these spaces and drained by means of connection to main line;
a suction of appropriate size led from the main
bilge line through a screw-down non-return valve. c) Bilge suction hose connections on the pumps
or on the main line;
a) The scupper tank air pipe is to be led above
the bulkhead deck and provision is to be d) Emergency bilge suctions.
made for ascertaining the level of the water
in the tank; 2.10.11 Bilge suction pipes from machinery
spaces and shaft tunnel, except emergency bilge
b) Where one tank is used for the drainage of suction, are to be led from easily accessible mud
several watertight compartments, the boxes fitted with straight tail pipes to the bilges.
scupper pipes are to be provided with screw- The open ends of the tail pipes are not to be fitted
down non-return valves. with strum boxes. The mud boxes are to be
provided with covers which can be easily opened
2.10.5 No drain valve or cock is to be fitted to the and closed for cleaning purposes.
collision bulkhead. Drain valves or cocks are not
to be fitted to other watertight bulkheads if 2.10.12 Strum boxes are to be fitted to the open
alternative means of drainage are practicable. ends of bilge suction pipes from the cargo holds.
These arrangements are not permissible in The diameter of holes from these strum boxes is
passenger ships. not to be more than 10 [mm] and the total area of
the holes is not to be less than twice the area of
2.10.6 Where drain valves or cocks are fitted to the pipes.
bulkheads other, than collision bulkhead, as
permitted by 2.10.5, the drain valves or cocks are 2.10.13 Where access manholes to bilge wells
to be at all times readily accessible and are to be are necessary, they are to be fitted as near to the
capable of being shut off from positions above the suction strums as practicable.
bulkhead deck. Indicators are to be provided to
show whether the drains are open or shut. 2.10.14 Adequate distance is to be provided
between the open ends of suction pipes and bilge
2.10.7 Bilge pipes which are required for draining well bottom to permit adequate and easy flow of
cargo or machinery spaces are to be entirely water and to facilitate cleaning.
distinct from sea inlet pipes or from pipes which
may be used for filling or emptying spaces where 2.10.15 All the valves, cocks and mud boxes are
water or oil is carried. This does not, however, to be located in easily accessible positions above
exclude a bilge ejection connection, a connecting or at the same level as the floor plates. Where
pipe from a pump to its suction valve chest, or a this is unavoidable, they may be fitted
deep tank suction pipe suitably connected immediately below the floor plates provided the
through a change-over device to bilge, ballast or floor plates are capable of being opened and
oil line. closed easily and suitable name plates are fitted
indicating the fittings below.
2.10.8 The arrangement of pumps, valves and
piping is to be such that any pump could be 2.10.16 Where relief valves are fitted to pumps
opened up for overhaul and repairs without having sea connections, these valves are to be
affecting the operation of the other pumps. fitted in readily visible positions above the
Section 3
3.1 General 3.2.6 Vent pipes from lubricating oil storage tanks
may terminate in the machinery spaces, provided
3.1.1 Reference to oil in this Section is to be that the open ends are so situated that issuing oil
taken to mean oil which has a flash point of 60C cannot come into contact with electrical
or above (closed cup test). equipment or heated surfaces.
3.1.2 The portions of vent, overflow and sounding 3.2.7 The open ends of vent pipes to oil fuel and
pipes fitted above the weather deck are to be of cargo oil tanks are to be situated where no
steel. danger will be incurred from issuing oil or vapour
when the tank is being filled.
3.1.3 Name plates are to be affixed to the upper
ends of all vent and sounding pipes. 3.2.8 For details regarding height and closing
devices for vent pipes see Pt.3, Ch.11.
3.2 Air pipes
3.2.9 The open ends of vent pipes to oil fuel,
3.2.1 Vent pipes are to be fitted to all tanks, cargo oil and ballast tanks fitted with anodes for
cofferdams, tunnels and other compartments cathodic protection, are to be fitted with a wire
which are not fitted with alternative ventilation gauze diaphragm of incorrodible material which
arrangements. can be readily removed for cleaning. The clear
area through the wire gauze is to be at least equal
3.2.2 The vent pipes are to be fitted at the to the area of the vent pipe.
opposite end of the tank to which the filling pipes
are placed and/or at the highest part of the tank 3.2.10 In the case of all tanks which can be
and are to be of the self draining type. Where the pumped up either by ship's pumps or by shore
tank top is of unusual or irregular profile, special pumps through a filling main, the total cross-
consideration will be given to the number and sectional area of the vent pipes to each tank, or
positions of the vent pipes. of the overflow pipes where an overflow system
is provided, is to be not less than 25 per cent
3.2.3 Tanks provided with anodes for cathodic greater than the effective area of the respective
protection are to be provided with vent pipes at filling pipes.
forward and aft ends.
3.3 Sounding arrangements
3.2.4 Vent pipes to double bottom tanks, deep
tanks extending to the shell plating or tanks which 3.3.1 All tanks, cofferdams and pipe tunnels are
can be run up from the sea and sea chests are to to be provided with sounding pipes or other
be run up from the sea and sea chests are to be approved means for ascertaining the level of
led above the bulkhead deck. liquid in the tanks. Bilges of compartments which
are not at all times readily accessible are to be
3.2.5 Vent pipes to oil fuel and cargo oil tanks, provided with sounding pipes. The soundings are
cofferdams, all tanks which can be pumped up, to be taken as near the suction pipes as
shaft tunnels and pipe tunnels are to be led above practicable.
the bulkhead deck and to open air.
3.3.2 Where gauge glasses are used for oil spray will not reach any of machinery
indicating the level of liquid in tanks containing components mentioned above. The short
lubricating oil, oil fuel or other flammable liquid, sounding pipes are to be fitted with self-closing
the glasses are to be of heat resisting quality, cocks having cylindrical plugs with weight loaded
adequately supported, protected from levers permanently attached and with pedals for
mechanical damage and fitted with self-closing opening or other approved arrangements. Short
valves at the lower ends and at the top ends if sounding pipes to tanks not intended for oil are to
these are connected to the tanks below the be fitted with screw caps attached by chain to the
maximum liquid level. pipe or with shut off cocks.
3.3.3 Except as permitted by 3.3.4 sounding 3.3.5 In passenger ships, short sounding pipes
pipes are to be led to positions above the are permissible only for sounding cofferdams and
bulkhead deck which are at all times accessible double bottom tanks situated in the machinery
and in the case of oil fuel tanks, cargo oil tanks space and are in all cases to be fitted with self
and lubricating oil tanks, the sounding pipes are closing cocks as described in 3.3.4.
to be led to safe positions on the open deck.
3.3.6 Striking plates of adequate thickness and
3.3.4 Short sounding pipes may be fitted to size are to be fitted under open ended sounding
double bottom tanks and cofferdams in shaft pipes. Where slotted pipes having closed ends
tunnels and machinery spaces provided the are employed, the closing plugs are to be of
pipes are readily accessible. Short sounding substantial construction.
pipes to oil fuel tanks, cargo oil tanks and
lubricating oil tanks are not to be placed in the 3.3.7 The upper ends of all sounding pipes are to
vicinity of boilers, preheaters, heated surfaces, be provided with efficient closing devices. The
electric generators or motors with commutator or sounding pipes are to be arranged to be as
collector rings or electric appliances which are straight as practicable, and if curved, the
not totally enclosed. The short sounding pipes curvature is to be large enough to permit easy
are to be arranged in such a way that overflow or passage of sounding rod/chain.
Section 4
4.1.1 Oil fuel for machinery and boilers is 4.2.1 Oil fuel tanks are to be separated from fresh
normally to have a flash point not lower than 60C water and lubricating oil tanks by means of
(closed cup test). For emergency generator cofferdams.
engines, the oil fuel is to have a flash point not
lower than 43C (closed cup test). 4.2.2 Oil fuel tanks are not to be located directly
above the highly heated surfaces.
4.1.2 Fuels with flash point lower than 60C may
be used in ships intended for service restricted to 4.3 Oil fuel piping
geographical limits where it can be ensured that
the temperature of the machinery and boiler 4.3.1 Oil fuel pressure pipes are to be led, where
spaces will always be 10C below the flash point practicable, remote from heated surfaces and
of the fuel. In such cases safety precautions and electrical appliances, but where this is
the arrangements for storage and pumping will be impracticable the pipes are to have a minimum
specially considered. However, the flash point of number of joints and are to be led in well lighted
the fuel is not to be less than 43C unless and readily visible positions.
specially approved.
4.3.3 Pipes in connection with compartments 4.4.7 Where a power driven pump is necessary
storing fresh water are to be separate and distinct for transferring oil fuel, a stand by pump is to be
from any pipes which may be used for oil or oily provided and connected ready for use, or,
water and are not to be led through tanks which alternatively, emergency connections may be
contain oil, nor are oil pipes to be led through made to another suitable power driven pump.
fresh water tanks.
4.4.8 All pumps which are capable of developing
4.3.4 Pipes conveying vegetable oils or similar a pressure exceeding the design pressure of the
cargo oils are not to be led through oil fuel tanks, system are to be provided with relief valves. Each
nor are oil fuel pipes to be led through tanks relief valve is to be in close circuit, i.e. arranged
containing such cargoes. to discharge back to the suction side of the pump
and to effectively limit the pump discharge
4.3.5 In passenger ships, provision is to be made pressure to the design pressure of the system.
for the transfer of oil fuel from any oil fuel storage
or settling tank to any other oil fuel storage tank. 4.4.9 Valves or cocks are to be interposed
between the pumps on the suction and discharge
4.4 Arrangement of valves, cocks, pumps and pipes in order that any pump may be shut off for
fittings opening up and overhaul.
4.4.1 The oil fuel and pumping piping 4.4.10 Drip trays are to be fitted under all oil fuel
arrangements are to be distinct from other appliances which are required to be opened up
pumping systems as far as practicable and the frequently for cleaning or adjustment.
means provided for preventing dangerous
interconnection in service are to be thoroughly 4.5 Filling arrangements
effective.
4.5.1 The bunkering of the ship is to be carried
4.4.2 All valves and cocks forming part of the oil out through a permanently fitted pipeline,
fuel installation are to be capable of being provided with the required fittings and ensuring
controlled from readily accessible positions fuel delivery to all storage tanks. The open end of
which, in the machinery spaces are to be above the fitting pipe is to be led to the tank bottom.
the working platform.
In passenger ships fuel bunkering stations are to
4.4.3 Every oil fuel suction pipe from a double be isolated from other spaces and are to be
bottom tank is to be fitted with a valve or a cock. efficiently drained and ventilated.
4.4.4 For oil fuel tanks which are situated above 4.5.2 Provision is to be made against over-
the double bottom tanks, the inlet and outlet, pressure in the filling pipes, and any relief valve
pipes which are connected to the tank at a point fitted for this purpose is to be discharge in to an
lower than the outlet of the overflow pipe or below overflow tank or other safe position.
the top of the tanks without an overflow pipe, are
to be fitted with shut off valves located on the tank 4.6 Oil fuel burning arrangements
itself.
4.6.1 Filters are to be fitted in the supply lines to
4.4.5 In the machinery spaces valves, mentioned the main and auxiliary machinery. For non-
in 4.4.4, are to be capable of being closed locally redundant units for essential services, it must be
and from positions outside these spaces which possible to clean the filters without stopping the
will always be accessible in the event of fire unit or reducing the supply of filtered oil to the
occurring in these spaces. Instructions for closing unit.
the valves are to be indicated at the valves and
at the remote control positions.
For auxiliary engines one single oil fuel filter for 4.7 Remote stop of oil fuel pumps and fans
each engine may be accepted.
4.7.1 Emergency stop of power supply to the
4.6.2 Where an oil fuel booster pump is fitted, following pumps and fans is to be arranged from
which is essential to the operation of the main a central place outside the engine and boiler
engine(s), a standby pump is to be provided. The room:
standby pump is to be connected ready for
immediate use but where two or more main oil fuel transfer pump;
engines are fitted, each with its own pump, a oil fuel booster pump;
complete spare pump may be accepted provided nozzle cooling pumps when oil fuel is
that it readily accessible and can be easily used as coolant;
installed. oil fuel purifiers;
pumps for oil-burning installations;
4.6.3 Where pumps are provided for fuel valve fans for ventilation of engine rooms.
cooling, the arrangements are to be as in 4.6.2.
Section 5
Section 6
6.1 General
6.3 Control of pumps and alarms
6.1.1 Lubricating oil systems are to be entirely
separated from other systems. This requirement, 6.3.1 The power supply, to all independently
however, does not apply to hydraulic governing driven lubricating oil pumps is to be capable of
and maneuvering systems for main and auxiliary being stopped from a position outside the space
engines. which will always be accessible in the event of fire
occurring in the compartment in which they are
6.1.2 Lubricating oil tanks are to be separated situated, as well as from the compartment itself.
from other tanks containing water, fuel oil or
cargo oil by means of cofferdams. 6.3.2 All main and auxiliary engines intended for
essential services are to be provided with means
6.2 Pumps of indicating the lubricating oil pressure supply to
them. Where such engines and turbines are of
6.2.1 Where lubricating oil for the main engine(s) more than 75 [kW] (100 shp), audible and visual
is circulated under pressure, a standby alarms are to be fitted to given warning of an
lubricating oil pump is to be provided where one appreciable reduction in pressure of the
main engine is fitted and the output of the engine lubricating oil supply. Further, these alarms are to
exceeds 370 [kW] (500 shp). be actuated from the outlet side of any
restrictions, such as filters, coolers, etc.
6.2.2 Satisfactory lubrication of the engines is to
be ensured while starting and maneuvering. 6.4 Filters
6.2.3 Similar provisions to those of 6.2.1 and 6.4.1 In systems, where lubricating oil is
6.2.2 are to be made where separate lubricating circulated under pressure, provision is to be
oil systems are employed for piston cooling, made for efficient filtration of the oil. For non-
reduction gearing, oil operated couplings and redundant units, for essential services, it must be
controllable pitch propellers, unless approved possible to clean the filters without stopping the
alternative arrangements are provided. Where unit or reducing the supply of filtered oil to the
the oil glands for stern tubes are provided with oil units.
circulating pump, and the continuous running of
this pump is necessary during normal operation, 6.5 Valves and cocks on lubricating oil tanks
then a standby pump for this purpose is to be
provided. 6.5.1 Outlet valves and cocks on lubricating oil
service tanks, other than double bottom tanks,
6.2.4 Independently driven rotary type pumps are situated in machinery spaces are to be capable
to be fitted with non-return valves on the of being closed locally and from positions outside
discharge side of the pumps. the space which will always be accessible in the
event of fire occurring in these spaces. Remote
6.2.5 A relief valve in close circuit is to be fitted controls need only be fitted to outlet valves and
on the pump discharge if the pump is capable of cocks which are open in normal service and are
developing a pressure exceeding the design not required for other outlets such as those on
pressure of the system, the relief valve is to storage tanks.
effectively limit the pump discharge pressure to
the design pressure of the system.
Section 7
Section 8
8.1 Scope above the load waterline which are at all times
readily accessible. The suction lift is not to
8.1.1 Following requirements are applicable to exceed 7.3 [m] and is to be well within the
vessels not fitted with propelling machinery. capacity of the pump.
8.2 Vessels without auxiliary power 8.2.4 The pump capacity is to be based upon the
diameter of the suction pipe required for the
8.2.1 Hand pumps are to be fitted in number and compartment and as determined in Sec.2.
position, as may be required for the efficient
drainage of the vessel. 8.3 Vessels with auxiliary power
8.2.2 In general, one hand pump is to be provided 8.3.1 In vessels in which auxiliary power is
for each compartment. Alternatively, two pumps available on board, power pump suctions are to
connected to a bilge main, having at least one be provided for dealing with the drainage of tanks
branch to each compartment are to be provided and of the bilges of the principal compartments.
through non-return
valves. 8.3.2 The pumping arrangements are to be as
required for self propelled vessels, so far as these
8.2.3 The hand pumps are to be capable of being requirements are applicable.
worked from the upper deck or from positions
End of Chapter
Chapter 4
Contents
Section
1 General
2 Main Propulsion Shafting
3 Propellers
4 Vibrations and Alignment
Section 1
General
1.1.1 The requirements of this Chapter are 1.3.1 Primemovers and reduction gearings are to
applicable to all ships but may be modified for be designed, manufactured and tested in
ships intended for special services. accordance with the requirements of Rules and
Regulations For the Construction & Classi-
1.1.2 Prime movers of electric generators of less fication of Steel Ships.
than 50 [kW] capacity, supplying power for
lighting loads only, when the ship is in harbour, 1.3.2 Engines below 100 [kW] including gear
need not be built under survey. boxes used for propulsion and for essential
auxiliary machinery may be accepted based on
1.1.3 Attention is drawn to any relevant statutory certificate from approved manufacturers. Such
requirements of the country in which the ship is engines between 100 [kW] and 300 [kW] are to
to be registered. be type approved. Engines of 300 [kW] and over
including gear boxes used for propulsion and for
1.1.4 Power transmission systems not specified essential auxiliary machinery, are to be type
in this Chapter will be specially considered. approved and undergo unit certification. Unit
certification may be exempted for those engines
1.2 Materials approved in accordance with the Alternative
Certification Scheme of IRS (See Pt.1, Ch.1,
1.2.1 Materials intended for the main parts of the Sec.4 of the ‘Rules and Regulations for the
prime movers and power transmission systems Construction and Classification of Steel Ships’
are to be manufactured and tested in accordance
with the requirements of Pt.2, Inspection and 1.4 Turning Gear
Testing of Materials, of Rules & Regulations for
the Construction and Classification of Steel 1.4.1 Arrangements are to be provided to turn the
Ships. primemover of main propulsion systems and
auxiliary drives.
Section 2
2.1 Scope
b) Alloy steels - Not exceeding 800 [N/mm2]
2.1.1 The requirements of this Section relate, in
particular, to formulae for determining the 2.3.2 Ultrasonic tests are required on shaft
diameters of shafting for main propulsion forgings where the diameter is 250 [mm] or
installations, but requirements for couplings, greater.
coupling bolts, keys, keyways, sternbushes and
associated components are also included. The 2.4 Intermediate and thrust shafts
diameter of shafting as calculated may require to
be modified as a result of alignment 2.4.1 The diameter, d, of the shaft is to be not less
considerations and vibration characteristics (See than determined by the following formula :
Sec.8) or the inclusion of stress raisers, other
than those contained in this section. 410 P
d 103.5 k a 3 [mm]
2.2 Plans and particulars (U 160) R
2.2.1 The following plans, in triplicate, together where,
with the necessary particulars of the machinery,
including the maximum power and revolutions a = 0.95 for turbine installations, electric
per minute, are to be submitted for approval propulsion installations and oil engine
before the work is commenced: installations with slip type couplings;
Final gear shaft; = 1.0 for other oil engine installations;
2.2.2 The specified minimum tensile strength of = 1.10 for shafts with transverse or radial holes,
each shaft is to be stated. where the diameter of the hole is not greater than
0.3 d;
2.2.3 A shafting arrangement plan indicating the
relative position of the main engines, flywheel, = 1.20 for shafts with longitudinal slots having a
flexible coupling, gearing, thrust block, line length of not more than 1.4 d and a width of not
shafting and bearings, stern tube, 'A' brackets more than 0.2 d, where d is calculated with k=1.0;
and propeller, as applicable, is to be submitted
for information. U = Specified minimum tensile strength of the
material [N/mm2]
2.3 Materials for shafting
P = maximum shaft power [kW];
2.3.1 The materials are to comply with the
relevant requirements of Ch.5, Pt.2, Inspection R = Revolutions per minute corresponding to
and Testing of Materials, of Rules & Regulations maximum shaft power giving maximum torque.
for the Construction and Classification of Steel
Ships. The specified minimum tensile strength of 2.4.2 For shafts with design features other than
forgings is to be selected within the following stated in 2.4.1, the value of k will be specially
general limits : considered.
k = 1.22 for a shaft carrying a keyless propeller, 2.6.1 For hollow shafts where the bore exceeds
or where the propeller is attached to an integral 40 per cent of the outside diameter the minimum
flange, and where the shaft is fitted with shaft diameter is not to be less than that given by
continuous liner or is oil lubricated and provided the following equation :
with an approved type of oil sealing gland;
1
= 1.26 for a shaft carrying a keyed propeller, and do d 4
[mm]
where the shaft is fitted with a continuous liner or 3 d
is oil lubricated and provided with an approved 1 - i
type of oil sealing gland; do
U = Specified minimum tensile strength of the 2.6.2 Where the diameter of central hole does not
shaft [N/mm2], but is not to be taken greater than exceed 0.4 times the outside diameter, no
600 [N/mm2]; increase over Rule size need be provided.
2.5.2 The diameter, dp of the tailshaft determined 2.7.1 The thickness of coupling flanges is not to
in accordance with the formula in 2.5.1 is to be less than the minimum required diameter of
extend over a length not less than that to the the coupling bolts calculated as in para 2.9,
forward edge of the bearing immediately forward where UB = U or 0.2 times the rule diameter of the
of the propeller or 2.5 dp whichever is the greater. shaft under consideration, whichever is greater.
2.5.3 The diameter of the portion of the tailshaft 2.7.2 The fillet radius at the base of the coupling
and tubeshaft forward of the length required by flange is to be not less than 0.08 of the diameter
2.5.2 to the forward end of the forward sterntube of the shaft at the coupling. The fillets are to have
seal is to be determined in accordance with the a smooth finish and are not to be recessed in way
formula in 2.5.1 except that: of nuts and bolt heads.
k = 1.15, when k = 1.22 or 1.26 as required by 2.7.3 Where the propeller is attached by means
2.5.1 of a flange, the thickness of the flange is to be not
less than 0.25 times the actual diameter of the
k = 1.18, when k = 1.25 or 1.29 as required by adjacent part of the tailshaft. The fillet radius at
2.5.1 the base of the coupling flange is to be not less
than 0.125 times the diameter of the shaft at the
The change of diameter from that required by coupling.
2.5.1 to that required by this clause should be
gradual.
2.8.2 Hydraulic and other shrink fit couplings will dp = diameter of tail shaft under the liner [mm].
be specially considered upon submittal of
detailed pre-loading and stress calculations and 2.10.2 The thickness of the continuous liner
fitting instructions. In general, the torsional between the bearings is not to be less than 0.75t.
holding capacity is to be at least 2.8 times the
transmitted torque and pre-load stress is not to 2.10.3 Continuous liners are preferably to be cast
exceed 70 per cent of the yield strength. in one length. If made of several lengths, the
joining of the separate pieces is to be made by
2.8.3 Provision is to be made to resist astern pull. welding through the whole thickness of liner
before shrinking. In general, the lead content of
2.9 Coupling bolts the gunmetal of each length forming a butt
welded liner is not to exceed 0.5 per cent. The
2.9.1 The diameter of the coupling bolts of the composition of the electrode or filler rods is to be
fitted type at the joining faces of the coupling is to substantially lead free.
be not less than that given by the following
formula: 2.10.4 The liners are to withstand a hydraulic
pressure of 0.2 [N/mm2] after rough machining.
0.427 d 3 (U 155) 2.10.5 The liners are to be carefully shrunk or
db [mm]
N D UB forced upon the shaft by hydraulic pressure, and
they are not to be secured by pins.
where, 2.10.6 Effective means are to be provided for
preventing water from reaching the shaft at the
db = diameter of the fitted coupling bolts [mm]; part between the after end of the liner and the
propeller boss.
d = required diameter [mm] for the shaft in
accordance with 2.4 or 2.5 as appropriate 2.10.7 If the liner does not fit the shaft tightly
calculated by taking the value of k as 1.0; between the bearing portions in the stern tube,
the space between the shaft and the liner is to be
U = specified minimum tensile strength of the filled with a plastic insoluble non- corrosive
shaft material in [N/mm2]; compound.
UB = specified minimum tensile strength of the 2.11 Keys and keyways
bolt material in [N/mm2];
2.11.1 Round ended or sled-runner ended keys
and also U UB 1.7U; are to be used, and the key ways in the propeller
boss and cone of the tail shaft are to be provided
N = Number of bolts in the coupling; with a smooth fillet at the bottom of the keyways.
The radius of the fillet is to be at least 0.0125 of
D = Pitch circle diameter of bolt holes [mm]. the diameter of the tail shaft at the top of the cone.
The sharp edges at the top of the keyways are to
2.9.2 The diameter of the non-fitted bolts will be be removed.
specially considered upon the submittal of
detailed pre-loading and stress calculations and 2.11.2 Two screwed pins are to be provided for
fitting instructions. securing the key in the keyway, and the forward
pin is to be placed at least one-third of the length
2.10 Tailshaft liners of the key from the end. The depth of the tapped
holes for the screwed pins is not to exceed the
2.10.1 The thickness, t, of bronze or gunmetal pin diameter and the edges of the holes are to be
liners fitted on tail shafts, in way of bearings, is slightly beveled.
not to be less than given by following formula :
2.11.4 The effective sectional area of the key in e) For water lubricated bearings lined with two
d3 or more circumferentially spaced sectors of
shear, is to be not less than [mm2] an approved plastics material, in which it can
2.6 d 1 be shown that the sectors operate on
hydrodynamic principles, the length of the
where, bearing is to be such that the nominal bearing
pressure will not exceed 0.55 [N/mm2]. The
d = diameter [mm], required for the intermediate length of the bearing is not to be less than
shaft determined in accordance with 2.4, based twice actual diameter of shaft.
on material having a specified minimum tensile
strength of 400 [N/mm2]; 2.12.2 Forced water lubrication is to be provided
for all bearings lined with rubber or plastics and
d1 = diameter of shaft at mid-length of the key for those bearings lined with lignum vitae where
[mm]. the shaft diameter is 380 [mm] or over. The
supply water may come from a circulating pump
2.12 Stern tube and bearings or other pressure source. The water grooves in
the bearings are to be of ample section and of a
2.12.1 The length of the bearing in the sternbush shape which will be little affected by weardown,
next to and supporting the propeller is to be as particularly for bearings of the plastic type.
follows :
2.12.3 The shut off valve or cock controlling the
a) For water lubricated bearings which are lined supply of water is to be fitted direct to the after
with lignum vitae, rubber composition or peak bulkhead, or to the sterntube where the
staves of approved plastic material; the water supply enters the sterntube forward of the
length is to be not less than 4 times the rule bulkhead.
diameter required for the tailshaft under the
liner; 2.12.4 Where a tank supplying lubricating oil to
the sterntube is fitted, it is to be located above the
b) For bearings which are white-metal lined, oil load water line and is to be provided with a low
lubricated and provided with an approved level alarm device in the engine room.
type of oil sealing gland; the length of the
bearing is to be approximately twice the rule 2.12.5 Where sternbush bearings are oil
diameter required for the tailshaft and is to be lubricated, provision is to be made for cooling the
such that the nominal bearing pressure will oil by maintaining water in the after peak tank
not exceed 0.8 [N/mm2]. The length of the above the level of the sterntube or by other
bearing is to be not less than 1.5 times its rule approved means. Means of ascertaining the
diameter; temperature of the oil in the sternbush are also to
be provided.
c) For bearings of cast iron, bronze which are
oil lubricated and fitted with an approved oil 2.12.6 The oil sealing glands used for sterntube
sealing gland; the length of the bearing is, in bearings, which are oil lubricated, are to be of
general, to be not less than 4 times the rule approved type.
diameter required for tailshaft;
Section 3
Propellers
L = Length of the blade Section of the expanded 3.4.1.3 Fillets at the root of the blades are not to
cylindrical Section at 25 per cent radius or 35 per be considered in the determination of blade
cent radius, as applicable, [mm]; thickness.
is to be sealed at the forward end with a well-fitted shaft; and, where necessary, a filler piece is to be
soft rubber packing ring. When the rubber ring is fitted in the propeller - hub keyway to provide a
fitted in an external gland, the hub counterbore is flat unbroken seating for the ring. The recess
to be filled with suitable material, and clearances formed at the small end of the taper by the over
between shaft liner and hub counterbore are to hanging propeller hub is to be packed with red
be kept to a minimum. When the rubber ring is lead putty or rust-preventing compound before
fitted internally, ample clearance is to be provided the propeller nut is put on.
between liner and hub and the ring is to be
sufficiently sized to squeeze in to the clearance 3.5.3 Effective means are to be provided to
space when the propeller is driven up on the prevent the slackening of the propeller nut.
Section 4
4.3.1 Where the machinery is installed on 4.4.5 Restricted speed ranges will be imposed in
resilient mountings, linear vibration (steady state regions of speed where stresses are considered
and transient) is not to exceed the limiting values to be excessive for continuous running. Similar
agreed with the manufacturers of the machinery restrictions will be imposed, or other protective
nor those of the resilient mountings. measures required to be taken, where vibratory
torques are considered to be excessive for
4.3.2 Misalignment arising from such vibration is particular machinery items.
not to impose excessive loading on machinery
components within the system. 4.4.6 Where calculations indicate the possibility
of excessive torsional vibration within the range
4.4 Torsional vibration of working speeds, torsional vibration
measurements, using the appropriate recognized
4.4.1 Torsional vibration calculations, including techniques, may be required to be taken from the
an analysis of the vibratory torques and stresses machinery installation for the purpose of
for the dynamic systems formed by the oil determining the need for restricted speed ranges.
4.6.1 For all main propulsion shafting systems, 4.7.2 For geared installations, where two or more
the Shipbuilders are to ensure that amplitudes pinions are driving the final reduction wheel,
due to lateral vibrations are satisfactory calculations are to be submitted to verify that
throughout the speed range. shaft alignment is such that proper bearing
reactions are maintained under all operating
4.6.2 Unless previous experience of similar conditions.
installations shows it to be unnecessary,
calculations of lateral, or bending, vibration 4.7.3 Shaft alignment is to be verified by
characteristics of the shafting system are to be measurement.
End of Chapter
Chapter 5
Contents
Section
1 General
Section 1
General
1.1 Scope
1.2.3 It is desirable that there should be a margin
1.1.1 The requirements of this Chapter are between the normal pressure at which the boiler
applicable to pressure vessels of seamless and or pressure vessel operates and the lowest
fusion welded construction, and their mountings pressure at which any safety valve is set to lift, to
and fittings, for the following uses : prevent unnecessary lifting of the safety valve.
b) Exhaust gas heated boilers; 1.3.1 The metal temperature, T, used to evaluate
the allowable stress is to be taken as the actual
c) Economizers, superheaters, reheaters and metal temperature expected under operating
steam receivers for, and associated with (a) conditions for the pressure part concerned, and
and(b); is to be stated by the manufacturer when plans of
the pressure parts are submitted for
d) Steam heated steam generators; consideration.
e) Other pressure vessels, not included in (a) to 1.3.2 For boilers, the design metal temperature is
(d). not to be taken less than the following values,
unless justified by an exact calculation of the
1.1.2 Consideration will be given to temperature drop and is in no case to be taken
arrangements or details of boilers, pressure less than 250C:
vessels and equipment which can be shown to
comply with other recognized standards, a) For steam heated steam generators,
provided they are not less effective. secondary drums of double evaporation
boilers, steam receivers and pressure parts
1.2 Design pressure of fired pressure vessels not heated by hot
gases and adequately protected by
1.2.1 The design pressure is the maximum insulation, the metal temperature, T is to be
permissible working pressure and is to be not taken as the maximum temperature of the
less than the highest set pressure of any safety internal fluid;
valve.
b) For pressure parts heated by hot gases, T is
1.2.2 The calculations made to determine the to be taken as not less than 25C in excess
scantlings of the pressure parts are to be based of the maximum temperature of the internal
on the design pressure, adjusted where fluid;
necessary to take account of pressure variations
corresponding to the most severe operational
conditions.
Steam-heated steam
Boilers Other pressure vessels
generators
15
Class 1 p > 3.5 Di > 1 1000 P > 50 or t > 38
p
20
15 P 50 or Di > 1 1000 and 16 <
Class 2 p 3.5 Di < 1 1000
p
p
t 38 or material temperature > 150C
20
Di 1 1000 and t 16 and
Class 3
p
material temperature 150C
Notes:
1.5.3 In special circumstances relating to service 1.6.3 The specified minimum tensile strength of
conditions, materials, operating temperature, the low alloy steel plates, pipes, forgings and
carriage of dangerous gases and liquids, etc., it castings is to be within the general limits of 400 -
may be required that certain pressure vessels be 500 [N/mm2], and pressure vessels made in
manufactured in accordance with the these steels are to be either seamless or Class 1
requirements of a superior class. fusion welded.
1.6.2 The specified minimum tensile strength of 1.6.5 Where it is proposed to use materials other
carbon and carbon manganese steel plates, than those specified in Pt.2, Inspection and
pipes, forgings and castings is to be within the Testing of Materials, of Rules & Regulations for
following general limits : the Construction and Classification of Steel
Ships, details of the chemical compositions, heat
a) For seamless and Class 1 and Class 2 fusion treatment and mechanical properties are to be
welded pressure vessels - 340 - 520 [N/mm2]; submitted for approval. In such cases the values
of the mechanical properties used for deriving the
b) For boiler furnaces, combustion chambers allowable stress are to be subject to agreement
and flanged plates - 400 - 520 [N/mm2]. by IRS.
1.6.6 Where a fusion welded pressure vessel is b) weight of the vessel and normal contents
to be made of alloy steel and approval of the under operating and test conditions;
scantlings is required on the basis of the high
temperature properties of the material, c) superimposed loads such as other pressure
particulars of the welding consumables to be vessels, operating equipment, insulation,
used, including typical mechanical properties and corrosion-resistant or erosion-resistant
chemical composition of the deposited weld linings and piping;
metal, are to be submitted for approval.
d) reactions of supporting lugs, rings, saddles or
1.7 Pressure parts of irregular shape other types of supports;
1.8 Adverse working conditions 1.9.1 The boilers and pressure vessels are to be
designed in accordance with the requirements of
1.8.1 Where working conditions are adverse, Ch.5, Pt.4, Main and Auxiliary Machinery, of
special consideration may be required to be given Rules & Regulations for the Construction and
to increasing the scantlings derived from the Classification of Steel Ships.
formulae, e.g. by increasing the corrosion or
other allowance at present shown in the 1.10 Manufacture
formulae, or by adopting a design pressure
higher than defined in 1.2, to offset the possible 1.10.1 The manufacture of boilers and pressure
reduction of life in service caused by the adverse vessels is to be carried out in accordance with the
conditions. In this connection, where necessary, requirements of Ch.10, Pt.4, Main and Auxiliary
account should also be taken of any excess of Machinery, of Rules & Regulations for the
loading resulting from : Construction and Classification of Steel Ships.
End of Chapter
Chapter 6
Steering Gears
Contents
Section
1 General
2 Design Criteria
Section 1
General
1.1 General
1.1.5 Steering gears may be manually operated
1.1.1 All ships are to be provided with reliable (steering chains and rods or hand/hydraulic) or
steering systems which would allow the vessel to fully powered (electric or electric/hydraulic).
be steered safely having regard to the use and However, when the rule diameter of the
principal dimensions of the ship. This rudderstock exceeds 150 [mm] in way of tiller, a
requirement does not apply to ships intended to fully powered steering gear is to be provided.
be pushed only. Proposals to fit a hand tiller only
will receive special consideration. 1.1.6 Manually operated gears or power assisted
gears are only acceptable when the operation
1.1.2 For ships not fitted with rudders but does not require an effort exceeding 16 [kgf]
equipped with steering propellers/nozzles or under normal conditions.
Voith-Schneider propellers, see 2.5. For ships
fitted with rudders, a steering gear is to be 1.1.7 If a fully powered steering gear is fitted an
provided. independent secondary means of steering is to
be provided.
1.1.3 The steering gear is to be secured to the
seating by fitted bolts, and suitable chocking 1.1.8 Requirements for chemical tankers, gas
arrangements are to be provided. The seating is carriers and similar vessels will be specially
to be of substantial construction. considered by IRS.
Section 2
Design Criteria
2.2.2 Powered steering gears are to be fitted with 2.4.1 If the position of the rudder(s) is not clearly
means to limit the torque exerted by the drive. perceivable from the steering station, a reliable
rudder angle indicator is to be provided at the
2.2.3 In case of failure of the main drive and the steering station.
secondary drive not engaging automatically, it is
to be possible to engage the secondary drive by 2.4.2 Any rudder angle indicator fitted, is to
hand at the steering position within 5 seconds, function for both the main and secondary steering
with the rudder in any position. gear.
2.2.4 At the steering station, automatic indication 2.5 Rudder propellers and Voith Schneider
is to be provided as to which drive is in operation. equipment
2.2.5 If the independent secondary drive is 2.5.1 Where a steering propeller/nozzle or Voith
manual the power drive is not to actuate the hand Schneider propeller is fitted, two independent
where,
e 2 3 2 138 [ N/mm 2 ]
du = The rudder stock diameter in way of the tiller
where, calculated in accordance with Pt.3, Ch.12, Sec.3;
= The bending stress, [N/mm2] 2.6.7 The shear area of the key, As, is not to be
less than :
= The torsional shear stress, [N/mm2]
0.18 Q r
Qr = The rudder torque [N-m] calculated as per As [cm 2 ]
Pt.3, Ch.12, Sec.3.2;
dm
are to be provided to ensure that the pin can be when necessary. In the case of hydraulic steering
lowered only when the rudder is exactly central. gears which are fitted with isolating valves on the
In addition, an indicator is to be fitted at the deck body of the gear and duplicate power units, an
to show when the rudder is exactly central. additional mechanical brake need not be fitted.
2.6.10 Steel-wire rope, chain and other 2.7.2 In bow rudders having a vertical locking pin
mechanical systems, when these are used for operated from the deck above, positive means
rudder stock diameters of 120 [mm] and less but are to be provided to ensure that the pin can be
excluding allowance for strengthening in ice, will lowered only when the rudder is exactly central.
be specially considered. In general the breaking In addition, an indicator is to be fitted at the deck
strength of rods/chains etc. is not to be less than: to show when the rudder is exactly central.
2.7 Locking or brake gear and springs 2.8.1 Suitable stopping arrangements are to be
provided for the rudder. Cut-outs on the steering
2.7.1 An efficient locking or brake arrangement is engine are to be arranged to operate at a smaller
to be fitted to all gears to keep the rudder steady angle of helm than those for the rudder.
End of Chapter
Chapter 7
Contents
Section
1 General Requirements
2 Essential Features for Control and Alarm Systems
3 Control and Supervision of Machinery
Section 1
General Requirements
1.1.1 This Chapter applies to all ships and is in List of control points.
addition to other relevant Chapters of the Rules.
Test facilities provided.
1.1.2 Attention should also be given to any
relevant requirements of National, International Test schedules.
or Local Authorities which would apply to the
ships in service. 1.2.2 Control systems. Plans are required for
the following:
1.1.3 This Chapter states requirements for
systems of automatic or remote control which Ballast systems.
may be used for controlling the machinery
contained in 1.2.2. The design and installation of Bilge systems.
other control equipment is to be such that there
is no risk of danger due to failure. Cargo pumping systems for tankers.
1.1.4 The details of control systems will vary with
Controllable pitch propellers.
the type of machinery being controlled and
special consideration will be given to each case.
Electrical generating plant.
1.2 Plans
Fire detection systems.
1.2.1 Where control systems are applied to
essential machinery or equipment as listed in Main propelling machinery including
1.2.2, plans are to be submitted in triplicate. They essential auxiliaries.
are to include or to be accompanied by:
Steam raising plant.
Details of operating medium, i.e. pneumatic,
hydraulic or electric, including standby Transverse thrust units.
sources of power.
Steering gear plant.
Description and/or block diagram showing
method of operation. Inert gas generators.
Line diagrams of control circuits. 1.2.3 Alarm systems. Details of the overall alarm
system linking engine room, wheelhouse and,
Lists of points monitored. where applicable, accommodation spaces are to
be submitted.
1.2.4 Control Station. Location and details of 1.3.2 Equipment used in control, alarm and safety
control station are to be submitted, e.g. control systems should whenever practicable, be
panels. selected from the List of Type Approved Control
and Electrical Equipment published by IRS. A
1.2.5 Standard system. Where it is intended to copy of IRS Test Requirements for the Type
employ a system which has been previously Approval of Control and Electrical Equipment will
approved, plans may not be required to be be furnished on application.
submitted.
1.3.3 Assessment of performance parameters,
1.2.6 Computer based systems. In addition to such as accuracy, repeatability and the like, are
documentation specified at 1.2.2 following plans/ to be in accordance with an acceptable National
documents are to be submitted as applicable: or International Standard.
- System requirement specification
1.4 Alterations or additions
- System block diagram showing details of
hardware 1.4.1 When an alteration or addition to the
approved system(s) is proposed, plans are to be
- Software quality plans when requested submitted for approval. The alterations or
additions are to be carried out under survey, and
- Factory acceptance test procedures. the inspection, testing and installation is to be to
the Surveyor's satisfaction.
1.3 Alarm and control equipment
1.4.2 Any changes in software are to be
1.3.1 Major units of equipment associated with submitted for consideration. Where considered
control, alarm and safety systems as defined in necessary, validation tests may be required to be
1.2 are to be surveyed at the manufacturers' carried out to verify the software performance.
works and the inspection and testing is to be to Software version changes are to be identified and
the Surveyor's satisfaction. submitted to surveyor on request.
Section 2
2.2.1 A system of alarm displays and controls are 2.3.5 If an alarm has been acknowledged and a
to be provided which readily ensure identification second fault occurs before the first was rectified
of faults in the machinery and satisfactory then audible and visual alarms are again to
supervision of related equipment. operate.
2.3 Alarm system 2.3.6 Failure of the power supply to the alarm
system is to be indicated.
2.3.1 Where an alarm system, which will provide
warning of faults in the machinery and control 2.3.7 The alarm system should be designed with
systems is installed, the requirements of 2.3.1 to self-monitoring properties. As far as practical,
2.3.10 are to be satisfied. any fault in the alarm system should cause it to
fail to the alarm condition.
2.3.2 Machinery and control system faults are to
be indicated at the relevant control station to 2.3.8 The alarm system is to be designed as far
advise duty personnel of a fault condition. as practical to function independently of control
2.3.10 The alarm system is to be capable of being 2.5.2 Computer based systems are to be
tested. provided with self-monitoring facilities
2.3.11 The alarm system is to be designed with 2.5.3 Systems is to revert to a defined safe state
self-monitoring capabilities. on initial startup or restart in the event of failure.
2.3.12 In wheelhouse illumination of all 2.5.4 In the event of failure of any programmable
indications and controls are to be provided with electronic equipment the system is to fail to a
dimming facility. defined safe state or maintain safe operation, as
applicable.
2.4 Control systems
2.5.5 Where software is used for control of
2.4.1 Control systems for machinery operations essential equipment, the software is to be
are to be stable throughout their operating range. certified towards software quality assurance.
2.4.2 Failure of the power supply to a control Note: The certification of software for computer
system for propulsion machinery and associated based control systems is to be carried out in
systems is to operate an audible and visual accordance with IRS ‘Guidelines on Certification
alarm. of Software for Computer based Systems’.
2.4.3 When remote or automatic controls are 2.5.6 Alternate means of back-up fully
provided, sufficient instrumentation is to be fitted independent and hard wired are to be provided.
at the relevant control stations to ensure effective Alternatively, if they are dependent on software
control and indicate that the system is functioning then the software is to be certified by IRS towards
correctly. software quality assurance.
2.4.4 Where valves are operated by remote or 2.5.7 Failure of power supply is to initiate an
automatic control, the system of control should alarm.
include the following safety features:
2.5.8 Emergency stop systems are to be hard
(a) Failure of actuator power should not permit a wired and where they are implemented through
closed valve to open inadvertently. computer based system, then the software is to
be certified by IRS.
(b) Positive indication is to be provided at the
remote control station for the service to show 2.5.9 Essential equipment in integrated system
the actual valve position or alternatively that are to be able to operate independently.
the valve is fully open or closed. Valve
position indicating systems are to be of an 2.5.10 Failure of one part of integrated system is
approved type. not to affect the functionality of other parts of the
integrated system.
(c) Equipment located in places which may be
flooded should be capable of operating when 2.6 Fire detection alarms systems
submerged.
2.6.1 Where an automatic fire detection system
(d) A secondary means of operating the valves, is to be fitted in a machinery space the
which may be local manual control is to be requirements of 2.6.2 to 2.6.9 are to be satisfied.
provided.
2.6.2 A fire detector indicator panel is to be 2.6.6 Detector heads of an approved type are to
located in such a position that a fire in the be located in the machinery spaces so that all
machinery spaces will not render it inoperative. potential fire outbreak points are guarded.
2.6.3 The audible fire alarm is to have a 2.6.7 The fire detection system is to be capable
characteristic tone which distinguishes it from of being tested.
any other alarm system. The audible fire alarm is
to be audible on all parts of the bridge and in the 2.6.8 It is to be demonstrated to the Surveyor's
accommodation areas. satisfaction that detector heads are so located
that air currents will not render the system
2.6.4 The alarm system should, so far as ineffective.
practicable, be designed with self-monitoring
properties. 2.6.9 A drawing showing the location of the fire
detector heads and the fire indicator panel, is to
2.6.5 Failure of power supply to the alarm system be submitted.
is to be indicated.
Section 3
3.6.3 Where transverse thrust units are remotely 3.8 Main propulsion shafting
controlled, means are to be provided at the
remote control station to stop the propulsion 3.8.1 Where a tank supplying lubricating oil to the
unit. sternbush is fitted, it is to be located above the
load waterline and is to be provided with a low
3.6.4 The following systems are to be provided level alarm.
with alarms:
End of Chapter
Chapter 8
Contents
Section
1 General Requirements
2 System Design
3 Cables
4 Switchboards
5 Control Gear
6 Rotating Machines - Construction and Testing
7 Transformers - Construction and Testing
8 Miscellaneous Equipment
9 Trials
Section 1
General Requirements
Section 2
System Design
a) Power supplied control circuits and instrumentation circuits, where technical or safety reasons require
connection to earth, provided the current in the hull is limited to not more than 5 amps in both normal
and fault conditions.
c) Limited and locally earthed systems, provided that any possible resulting current does not flow directly
through any of the dangerous spaces.
b) Limited and locally earthed systems, such as starting and ignition systems of internal combustion
engines, provided that any possible resulting current does not flow directly through any of the
dangerous spaces.
c) Insulation level monitoring devices, provided the circulation current does not exceed 30 mA under the
most unfavourable conditions.
Note 5 : All final sub-circuits, i.e. all circuits fitted after the last protective device are to be of two insulated
wires the hull return being achieved by connecting to the hull, one of the busbars of the distribution board
from which wires originate.
2.1.2.1 Every insulated distribution system is to 2.1.3.1 The number and rating of service
be provided with lamps or other devices to generating sets are to be adequate to ensure the
indicate the state of electrical insulation from operation of services essential for the propulsion
earth and to give an alarm in case of abnormally and safety of the ship. The power source can be
low insulated values. Where lamp indicators are in the form of:
used, the lamps are to be of the metal filament
type and their power is not to exceed 30 watts. a) two diesel alternator sets
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 5 of 25
___________________________________________________________________________________
b) one diesel generator and battery. The battery 10 for 24 - 55 V circuits
is to be capable of supplying all essential services
for a period of at least 30 minutes. Means are to 14 for 110 - 127 V circuits
be provided to charge the batteries even when
main engine is stationary. 18 for 220 - 250 V circuits
Note: Generator driven by main propulsion unit is This provision is not applicable to final sub-
accepted as main source of power provided that circuits for cornice lighting, panel lighting and
a battery source is arranged in 2.1.3.1 (b) as back electric signs where lampholders are closely
up source. The generator voltage is to regulated. grouped. In such cases, the number of points is
unrestricted provided the maximum operating
2.1.3.2 On oil tankers and similar vessels, where current in the sub-circuit does not exceed 10
electrical power is required for essential amperes.
equipment, the generating plant and converting
plant is to be of such capacity that this essential 2.1.6.4 Lighting of unattended spaces, such as
equipment can be operated satisfactorily even cargo spaces is to be controlled by multi-pole
with one generating set or converting set out of linked switches located outside such spaces.
action. Provision is to be made for the complete isolation
of these circuits and locking in the "OFF" position
2.1.4 Essential services of the means of control.
2.1.4.1 Where essential services are duplicated, 2.1.6.5 Emergency lighting where required to be
they are to be served by individual circuits provided for passenger vessels, is to be fitted in
separated throughout their length as widely as is accordance with Part 5, Chapter 3.
practicable and without the use of common
feeders, protective devices or control circuits. 2.1.6.6 Where more than one light is installed in
a space, the lighting is to be supplied from at least
2.1.5 Diversity factor two final sub-circuits in such a way that failure of
one of the circuits does not leave the space in
2.1.5.1 Circuits supplying two or more final sub- darkness.
circuits are to be rated in accordance with the
total connected load subject, where justified, to 2.1.6.7 In general, main and emergency lighting
the application of a diversity factor. Where spare are to be provided at the following locations,
ways (feeders) are provided on a section or where required by the Rules/ statutory
distribution board, an allowance for future authorities, as applicable:
increase of load is to be added to the total
connected load before application of any diversity (a) at all stowage and designated preparation
factor. positions for life-saving appliances;
2.1.5.2 The diversity factor may be applied when (b) at all muster stations and, where applicable,
calculating cable size and when calculating the embarkation stations and over sides;
rating of switchgear and fusegear.
(c) escape route alleyways, stairways and exits;
2.1.5.3 The diversity factors are not applicable to
supply cables to distribution switchboards for (d) accommodation areas, cabins and personnel
lighting and heating. lift cars;
2.1.6 Lighting circuits (e) in other areas intended for use by persons
with reduced mobility;
2.1.6.1 Lighting circuits are to be supplied by final
sub-circuits, which are separate from those for (f) in the machinery spaces and main generating
heating and power. This provision need not be stations, including their control positions and their
applied to cabin fans and small wardrobe exits;
heaters.
(g) in the wheelhouse;
2.1.6.2 A final sub-circuit of rating exceeding 15
amperes is not to supply more than one point. (h) at all stowage positions for fireman’s outfits.
2.2.2 Protection against overload the necessary breaking capacity. The generator
breakers are not to be used for this purpose.
2.2.2.1 Protection against overloads may be
provided by circuit-breakers, automatic switches 2.2.4.2 Fused circuit-breakers with fuses
or fuses. The tripping characteristics of these connected to the load side may be used where
devices are to be appropriate to the system. operation of the circuit-breaker and fuses is co-
Fuses rated above 320 amperes are not to be ordinated.
used for protection against overload, but may be
used for short- circuit protection. 2.2.4.3 The characteristics of the arrangement
are to be such that:-
2.2.3 Protection against short-circuit
a) When the short-circuit current is broken, the
2.2.3.1 Protection against short-circuit currents is circuit-breaker on the load side is not to be
to be provided by circuit-breakers or fuses. damaged and is to be capable of further
service,
2.2.3.2 The breaking capacity of every protective
device is to be not less than the maximum value b) When the circuit-breaker is closed on the
of the short-circuit current which can flow at the short-circuit current, the remainder of the
point of installation at the instant of contact installation is not to be damaged. However, it
separation. is admissible that the circuit-breaker on the
load side may require servicing after the fault
2.2.3.3 The making capacity of every circuit- has been cleared.
breaker or switch intended to be capable of being
closed, if necessary, on short circuit, is to be not 2.2.5 Protection of circuits
less than the maximum value of the short-circuit
current at the point of installation. On alternating 2.2.5.1 Short circuit protection is to be provided
current this maximum value corresponds to the in each live pole of a direct current system and in
peak value allowing for maximum asymmetry. each phase of an alternating current system.
2.2.3.4 Every protective device or contactor not 2.2.5.2 Protection against overloads is to be
intended for short circuit interruption is to be provided as follows:-
adequate for the maximum short-circuit current
which can occur at the point of installation having a) Two-wire direct current or single-phase
regard to the time required for the short circuit to alternating current system - at least one line
be removed. or phase,
2.2.3.5 In the absence of precise data of rotating b) Insulated three-phase alternating current
machines the following short-circuit currents at system - at least two phases,
the machine terminals are to be assumed. The
short circuit current is to be the sum of short c) Earthed three-phase alternating current
circuit currents of generators and that of motors; system - all three phases.
2.2.4 Combined circuit-breakers and fuses 2.2.6.1 In addition to over-current protection, the
provisions of 2.2.6.2 to 2.2.6.7 are to be adhered
2.2.4.1 The use of a circuit-breaker of breaking to as a minimum.
capacity less than the prospective short-circuit
current at the point of installation is permitted, 2.2.6.2 For generators not arranged to run in
provided that it is preceded on the generator side parallel a multi-pole circuit-breaker arranged to
by fuses, or by a circuit-breaker having at least open simultaneously all insulated poles or in the
Indian Register of Shipping
Rules and Regulations for the Construction and Classification of Inland Waterways Vessels - 2023
Page 9 of 25
___________________________________________________________________________________
case of generators rated at less than 50 [kW] a provided by the same protective device for the
multi-pole linked switch with a fuse in each motor and its supply cable. The overload
insulated pole on the generator side is to be protection may be replaced by an overload alarm,
provided. The fuse rating in such cases is to be if desired by the Owner.
maximum 125 per cent of the generator rated
current. 2.2.8 Protection of power transformers
2.2.6.3 For generators arranged to run in parallel 2.2.8.1 The primary circuits of power
a circuit-breaker arranged to open transformers are to be protected against short-
simultaneously all insulated poles is to be circuit by circuit-breakers or fuses. The rating of
provided. This circuit-breaker is to be provided fuses or the setting for overcurrent releases of
with:- circuit breakers is not to exceed 125 per cent of
rated primary current.
a) For direct current generators, instantaneous
reverse-current protection operating at not 2.2.8.2 When transformers are arranged to
more than 15 per cent rated current, operate in parallel, means are to be provided for
isolation of the secondary circuits. Switches and
b) For alternating current generators - circuit-breakers are to be capable of withstanding
surge currents.
i) A reverse-power protection, with
time delay selected and set within 2.2.9 Protection of lighting circuits
the limits of 2 per cent to 15 per cent
of full load to a value fixed in 2.2.9.1 Lighting circuits are to be provided with
accordance with characteristics of overload and short- circuit protection.
primemovers.
2.2.10 Protection of meters, pilot lamps,
ii) A device for protection against the capacitors and control circuits
effects of parallel connection in
opposite phase. 2.2.10.1 Protection is to be provided for
voltmeters, voltage coils of measuring
2.2.6.4 The reverse-current protection is to be instruments, earth indicating devices and pilot
adequate to deal with the reverse-current lamps, together with their connecting leads by
conditions emanating from the network, e.g. from means of protective devices fitted to each
winches. The reverse-power protection specified insulated pole or phase.
for alternating current generators may be
replaced by other devices ensuring adequate 2.2.10.2 A pilot lamp installed as an integral part
protection of the prime movers. of another item of equipment need not be
individually protected, provided it is fitted in the
2.2.6.5 Generator circuit-breakers are normally to same enclosure. Where a fault in a pilot lamp
be provided with under voltage release. would jeopardise the supply to essential
equipment such lamps are to be individually
2.2.7 Protection of feeder circuits protected.
2.3.1.1 Solar power may be used as an additional 2.3.1.7 Manufacturer’s instructions regarding
source for charging battery systems. Suitable maintenance and replacement of PV modules
changeover arrangements are to be provided to are to be available onboard.
ensure charging of the batteries when the output
from photovoltaic (PV) panels is not sufficient to 2.3.1.8 Tests and trials are to be carried out to
charge the batteries. verify satisfactory operation of solar power
systems.
2.3.1.2 The components of solar power systems
are to be suitably sized for charging the 2.3.1.9 PV modules are to comply with
connected batteries. recognised standards such as:
2.3.1.3 The PV panels and associated power (a) IEC 61215-1:2021 Terrestrial
system components are to be suitable for marine photovoltaic (PV) modules - Design
use. qualification and type approval - Part 1:
Test requirements
2.3.1.4 Following are to be considered while
designing and sizing the solar power system: (b) IEC 61215-2:2021 Terrestrial
photovoltaic (PV) modules - Design
environmental conditions qualification and type approval - Part 1:
geographical conditions Test procedures
solar radiation
rated voltage and current (c) IEC 61701:2020 - Photovoltaic (PV)
photovoltaic module maintenance modules - Salt mist corrosion testing
requirements
storage battery capacity (d) IEC 61730-1:2016 – Photovoltaic
(PV) module safety qualification,
2.3.1.5 Adequate space and access is to be Requirements for construction
provided for operation, inspection and
maintenance. Cables are to be secured by cable (e) IEC 62716:2016 – Photovoltaic (PV)
ties, hangers or similar fittings and terminated modules - Ammonia corrosion testing
appropriately. (for modules installed on-board ammonia
carriers)
2.3.1.6 All live parts of the solar power system are
to be insulated and protected by barrier/
enclosure, where required by the Rules.
Section 3
Cables
3.1 General
3.3.5 Cables fitted in the following locations:- for windlass and capstan motors are to be not
less than one hour rated on the basis of the one
Decks exposed to weather; hour [kW] rating of the motor. In all cases the
rating is to be subject to the voltage drop being
Bathrooms; within the specified limits.
Table 3.5.2 : Heat resisting PVC insulation Table 3.5.3 : Butyl insulation current rating
current rating (Based on ambient temp. 45C)
(Based on ambient temp. 45C)
Nominal
Single 3 or 4
Nominal cross- 2 core
Single 3 or 4 core core
cross- 2 core section
core core
section
[mm2] amperes amperes amperes
[mm2] amperes amperes amperes
1 15 13 11
1 13 11 9
1.5 19 16 13
1.5 17 14 12
2.5 26 22 18
2.5 24 20 17
4 35 30 25
4 32 27 22
6 45 38 32
6 41 35 29
10 63 54 44
10 57 48 40
16 84 71 59
16 76 65 53
25 110 94 77
25 100 85 70
35 140 119 98
35 125 106 88
50 165 140 116
50 150 128 105
70 215 183 151
70 190 162 133
95 260 221 182
95 230 196 161
120 300 255 210
120 270 230 189
150 340 289 238
150 310 264 215
185 390 332 273
185 350 298 245
240 460 391 322
240 415 353 291
300 530 450 371
300 475 404 333
d.c. a.c. d.c. a.c. d.c. a.c.
d.c. a.c. d.c. a.c. d.c. a.c.
400 610 590 519 502 427 413
400 570 560 485 475 400 390
500 690 640 587 544 483 448
500 650 620 550 530 455 435
630 790 690 672 587 553 483
630 740 670 630 570 520 470
1.5 20 17 14 1 20 17 14
2.5 28 24 20 1.5 24 20 17
4 38 32 27
2.5 32 27 22
6 48 41 34
4 42 36 29
10 67 57 47
6 55 47 39
16 90 77 63
10 75 64 53
25 120 102 84
16 100 85 70
35 145 123 102
25 135 115 95
50 180 153 126
35 165 140 116
70 225 191 158
50 200 175 140
95 275 234 193
d.c. a.c. d.c. a.c. d.c. a.c. 240 570 485 400
400 650 630 553 536 445 441 300 660 560 460
Notes:
1 For cables in refrigerated chambers and holds and for vessels restricted to service in non-tropical
waters, correction factors for 35C may be acceptable.
2 Correction factors for intermediate values of the ambient temperature can be ascertained by
interpolation.
3.6.3 Intermittent service : Where the load is 3.8 Connections between entrained ships
intermittent, the correction factors in Table 3.6.2
may be applied for half hour and one hour ratings. 3.8.1 Cables are to be suitable for use in the
In no case is a shorter rating than one half hour connections between entrained ships i.e., are to
rating to be used, whatever the degree of be flexible, robust and of commensurate cross-
intermittency. section area.
3.8.2 The connection is to include provisions for protective covering (e.g. armour or sheath) is
the continuity of out-of-balance or earth-fault adequate to withstand the possible damage.
current return. The connecting device is to
include provisions to ensure that this circuit is
closed before, and opened after, the live circuits. Table 3.9.1 : Distance between supports
3.9.2 Cables having insulating materials with 3.10.2 Cables, in spaces where there is
different maximum-rated conductor temper- exceptional risk of mechanical damage (e.g. on
atures are not to be bunched together, or, where weather decks, in cargo hold areas and inside the
this is not practicable, the cables are to be cargo holds) and also below the floor in engine
operated so that no cable reaches temperature room, are to be suitably protected, even if
higher than that permitted for the lowest armoured, unless the steel structure affords
temperature-rated cable in the group. adequate protection.
3.9.3 Cables having a protective covering which 3.10.3 Metal casings for mechanical protection of
may damage the covering of other cables are not cables are to be efficiently protected against
to be bunched with those other cables. corrosion.
3.9.4 The minimum internal radius of bends of 3.11 Earthing of metal coverings
installed cables is to be generally in accordance
with following : 3.11.1 Metal coverings of cables are to be
effectively earthed at both ends of the cable,
4d for cables without braiding, except in final sub-circuits, where earthing at the
armouring or other metal sheath supply end only will be considered adequate.
and with an overall diameter not This does not necessarily apply to
exceeding 25 [mm] instrumentation cables where single point
6d for all other cables earthing may be desirable for technical reasons.
(d = overall diameter of cable)
3.11.2 The electrical continuity of all metal
coverings of cables throughout the length of the
3.9.5 Cables, are to be effectively supported and cable, particularly at joints and tappings, is to be
secured in a manner that prevents damage to ensured.
their coverings.
3.11.3 The lead sheath of lead-sheathed cables
3.9.6 Supports and accessories are to be robust is not to be used as the sole means of earthing
and are to be of corrosion-resistant material or the non-current carrying parts of items of
suitably corrosion inhibited before erection. equipment.
3.9.7 The distance between supports, for 3.12 Penetration of bulkheads and decks by
horizontal as well as vertical runs of cables, is to cables
be chosen according to the type/size of cable, but
generally in accordance with Table 3.9.1. 3.12.1 Penetration of watertight bulkheads or
decks is to be carried out with either individual
3.10 Mechanical protection of cables watertight glands or with packed watertight boxes
carrying several cables. In either case, the
3.10.1 Cables exposed to risk of mechanical watertight integrity and strength of the bulkheads
damage are to be protected by metal channels or and decks are to be maintained. Where cables
casing or enclosed in steel conduit unless the with polyvinyl chloride insulation are being
3.13 Installation of cables in pipes and 3.14.4 Cable clips are to include cables of all
conduits phases of a circuit unless the clips are of non-
magnetic material.
3.13.1 Installation of cables in pipes and conduits
is to be carried out in such a manner that there is 3.14.5 When installing two, three or four single-
no damage to the cable covering. core cables forming respectively single-phase
circuits, three-phase circuits or three-phase and
3.13.2 Metal conduit systems are to be earthed neutral circuits, the cables are to be in contact
and are to be mechanically and electrically with one another, as far as possible. In any case,
continuous across joints. Individual short lengths the distance between the external covering of two
of conduit need not be earthed. adjacent cables is not to be greater than one
diameter.
3.13.3 The internal radius of bend of pipes and
conduit is to be not less than that laid down for 3.14.6 In the case of circuits using two or more
cables, provided that for pipes exceeding 64 parallel connected cables per phase, all cables
[mm] diameter the internal radius of bend is not are to have the same length and cross sectional
less than twice the diameter of the pipe. area.
3.13.4 The drawing-in factor (ratio of the sum of 3.14.7 Where single core cables of rating
the cross-sectional areas of the cables, based on exceeding 50 amperes are used, magnetic
their external diameter, to the internal cross- material is not to be placed between single-core
section area of the pipe) is not to exceed 0.4. cables of a group. If these cables pass through
steel plates, all cables of the same circuit are to
3.13.5 Expansion joints are to be provided where pass through the plate or gland so constructed
necessary. that there is no magnetic material between the
cables, and suitable clearance is provided
3.13.6 Cable pipes and conduits are to be between the cable core and magnetic material.
adequately and effectively protected against This clearance, wherever practicable, is not to be
corrosion. Where necessary, openings are to be less than 75 [mm] when the current exceeds 300
provided at the highest and lowest points to amperes. For currents between 50 amperes and
permit air circulation and to prevent accumulation 300 amperes the clearance may be
of water. proportionately reduced.
3.13.7 Where cables are laid in trunks, the trunks 3.14.8 If single-core cables of current rating
are to be so constructed as not to afford passage greater than 250 amperes are run along a steel
for fire from one deck or compartment to another. bulkhead, wherever practicable the cables
should be spaced away from the steel.
Section 4
Switchboards
4.1.1 Switchboards, section boards and 4.4.1 Circuit breakers and switches are to be of
distribution boards are to be constructed of, or the air break type and are to be constructed in
enclosed with non-flammable, non-hydroscopic accordance with an acceptable National or
material and are to be so installed that live parts International Standard.
are sufficiently guarded and adequate space is
provided for maintenance. Also they are to be 4.4.2 Report of tests to establish the capacity of
protected where necessary in way of pipes etc. circuit-breakers are to be submitted for
consideration when required.
4.1.2 All measuring instruments and all
apparatus controlling circuits are to be clearly and 4.4.3 Overcurrent releases are to be calibrated in
indelibly labeled for identification purposes. An amperes and settings marked on the circuit-
indelible label is to be permanently secured breaker.
adjacent to every fuse and every circuit breaker
and marked with particulars of the full load 4.5 Fuses
current of the generator, motor or cable which the
fuse or circuit breaker protects. Where inverse 4.5.1 Fuses are to comply with an acceptable
time limit and/or reverse current devices are National or International Standard.
provided in connection with a circuit breaker, the
appropriate settings of these devices are to be 4.5.2 Fuse links and fuse bases are to be marked
stated on the label. Name plates are to be of with particulars of rated current and rated voltage.
flame retardant material. Each fuse position is to be permanently and
indelibly labeled with the current carrying
4.2 Instruments capacity of the circuit protected by it and with the
appropriate approved size of fuse or replaceable
4.2.1 Sufficient instrumentation is to be provided element.
for measuring voltage, current, frequency and, for
alternating current generators above 50 [kW]. 4.6 Testing
4.2.2 Where alternating current generators are 4.6.1 Before installation, switchboards complete
required to operate in parallel, synchronising or in sections with all components are to pass the
arrangements are to be fitted. following tests at the manufacturer's works and a
certificate furnished. A high voltage test is to be
4.3 Instrument transformers carried out in all switching and control apparatus
for systems greater than 60V with a test voltage
4.3.1 The secondary windings of instrument of 1000V plus twice the rated voltage with a
transformers are to be earthed.
Section 5
Control Gear
5.1.2 Control gear, including isolating and 5.2.3 Immediately after the high voltage test, the
reversing switches, is to be so arranged that insulation resistance between (a) all current-
shunt field circuits are not disconnected without carrying parts connected together and earth, and
adequate discharging path being provided. (b) between current-carrying parts of opposite
polarity or phase, is not to be less than 1
5.2 Testing megaohm when tested with a direct current
voltage of at least 500 V.
5.2.1 Control gear and resistors are to be tested
by the manufacturers with a high voltage applied 5.2.4 Instruments and ancillary apparatus may be
between the earthed frame and all live parts and disconnected during the high voltage test.
a certificate furnished by them to this effect. For
operating voltages above 55 V, the test voltage is 5.2.5 Functional Test : The correct functions of
to be 1000 V plus twice the rated voltage with a the installation components in line with the
minimum of 2000 V. The voltage is to be connections intended to be made, have to be
alternating at any frequency between checked as far as possible.
Section 6
Notes:
1 T = Thermometer method
R = Resistance method
2 When Class F or Class H insulation is employed, the permitted temperature rises are respectively
20C and 40C higher than the values given for Class B insulation.
b) 0.5 per cent of rated voltage for generators of 6.5.3 Alternating current generators required to
rating exceeding 100 [kW]. run in parallel are to be stable from 20 per cent
full load [kW] up to the total combined full load
6.4.5 The inherent regulation of service [kW] of the group, and load sharing is to be such
generators is to be such that the following that the load on any generator does not normally
conditions are fulfilled:- differ from its proportionate share of the total load
by more than 15 per cent of the rated output [kW]
a) For shunt or stabilised shunt wound of the largest machine or 25 per cent of the rated
generators when the voltage has been set at output [kW] of the individual machine, whichever
full load, the steady voltage at no load is not is less.
to exceed 115 per cent of the full load value,
and the voltage obtained at any intermediate 6.5.4 When generators are operated in parallel,
value of load is not to exceed the no-load the KVA loads of the individual generating sets
value. are not to differ from their proportionate share of
the total KVA load by more than 5 per cent of the
b) For compound wound generators with the rated KVA output of the largest machine when
generator at full load operating temperature, operating at 0.8 power factor.
and starting at 20 per cent load with voltage
within 1 per cent of rated voltage, then at full 6.6 Inspection and testing
load the voltage is to be within 2.5 per cent
of rated voltage. The average of the 6.6.1 On machines for essential services tests
ascending and descending load/voltage are to be carried out in accordance with the
curves between 20 per cent load and full load relevant standard and a certificate furnished by
is not to vary more than 4 per cent from rated the manufacturers.
voltage.
6.6.2 Generators and motors of 100 [kW] or over
6.4.6 Generators are to be capable of delivering intended for essential services are to be
continuously the full load current and normal inspected by the Surveyors during manufacture
rated voltage at the terminals when running at full and testing.
Section 7
7.1.2 Transformers are to be of the dry, natural 7.4.1 The inherent regulation at 0.8 power factor
air cooled type. Proposals for the use of liquid is not to exceed 5 per cent.
cooled transformers will be subject to special
consideration. 7.4.2 Regulation of the complete system is to
comply with 3.4.2.
7.2 Installation
7.5 Short circuit
7.2.1 Transformers are to be placed in easily
accessible well ventilated spaces free from any 7.5.1 All transformers are to be constructed to
gaseous or acid fumes. They are to be clear of withstand, without damage, the thermal and
non-protected ignitable materials, and so mechanical effects of a short-circuit at the
arranged as to be protected against shocks and terminals of any winding for 2 seconds with rated
any damage resulting from water, oil, liquid fuel, primary voltage and frequency without damage.
steam etc.
7.6 Tests
7.3 Construction
7.6.1 Transformers for essential services are to
7.3.1 Transformers are to be double wound be tested by the manufacturer in accordance with
except those for motor starting. the relevant standard and test certificates
supplied.
7.3.2 Each transformer is to be provided with a
Section 8
Miscellaneous Equipment
8.3.3.4 In all wet situations socket outlets and conductors are to be avoided. All clamps used
plugs are to be effectively shielded against rain are to be of brass or copper, preferably of the
and spray and are to be provided with means for serrated contact type, and efficiently locked.
maintaining this quality after removal of the plug. Soldered connections are not acceptable.
8.4 Heating and cooking equipment 8.5.3 The resistance of the lightning conductors,
measured between the mast head and the
8.4.1 General position on the earth plate or hull to which the
lightning conductor is earthed, is not to exceed
8.4.1.1 Heaters are to be so constructed, 0.02 ohms.
installed and protected that clothing, bedding and
other inflammable material cannot come in 8.5.4 The lightning conductors are to be
contact with them in such a manner as to cause composed of continuous copper tape and/or
risk of fire. There is to be no excessive heating of rope, having a section not less than 100 [mm2]
adjacent bulkheads or decks. and are to be riveted with copper rivets or
fastened with copper clamps to an appropriate
8.5 Lightning conductors copper spike of not less than 13 [mm] in diameter
and projecting at last 150 [mm] above the top of
8.5.1 Lightning conductors are to be fitted to each the mast. The lower end of the lightning
mast of all wood, composite and steel ships conductor is to be securely clamped to a copper
having wooden masts or topmasts. They need plate having an area of at least 0.2 [m2], fixed to
not be fitted to steel ships having steel masts, the ship's hull well below the light load waterline
unless the mast is partly or completely insulated in such a manner that it is immersed under all
from the ship's hull. conditions of heel. In steel ships fitted with
wooden masts, the lower end of the lightning
8.5.2 Lightning conductors are to be run as conductor is to be securely clamped to the
straight as possible, and sharp bends in the nearest metal forming part of the hull.
Section 9
Trials
9.4.3 The operation of engine governors, 9.5.1 Voltage drop is to be measured, where
synchronising devices, overspeed trips, reverse- necessary, to verify that this is not excessive.
current, reverse-power, over-current and under-
voltage trips and other safety devices.
End of Chapter
Chapter 9
Contents
Section
1 General
2 Fire Protection
3 Fire Detection
4 Fire Extinction
Section 1
General
1.1 Scope
1.2.3 Additional requirements for fire safety on
1.1.1 The requirements of this Chapter are passenger ships are given in Part 5, Chapter 3.
applicable to all ship types.
1.3 Plans and information
1.1.2 Special attention is drawn to National and
International Statutory Requirements of countries 1.3.1 The plans and information detailed in 1.3.2,
where the ship is registered or operating and where applicable, are to be submitted for
which are outside the scope of classification as approval together with all relevant details like
defined in these Rules. Rule dimensions of the ship L, B and D and the
number of passengers.
1.1.3 Consideration will be given to the
acceptance of the statutory requirements of 1.3.2 Following plans are to be submitted for
National Authorities as an alternative to the approval
requirements of this Chapter.
a) Means of escape and, where required,
1.1.4 Consideration will be given to special cases the relevant dimensioning.
where the arrangements are equivalent to those
required by these Rules. b) Fire Alarm system
1.1.5 Consideration will be given to the c) Arrangement of Fire pumps and fire main
acceptance of the approval of a National including pumps head and capacity,
Authority in respect of fire insulating materials, hydrant and hose locations
fire fighting appliances and items of equipment as
an alternative to the relevant requirements of this d) Arrangement of fixed fire-extinguishing
Chapter. systems
1.4.3 Passenger Spaces are spaces on board 1.4.13 Machinery spaces are all spaces
intended for passengers and enclosed areas containing propulsion machinery, boilers, oil fuel
such as offices, shops, hairdressing salons, units, internal combustion engines, generators
drying rooms, laundries, saunas, toilets, and major electrical machinery, oil filling stations,
washrooms, passageways, connecting passages refrigerating, stabilizing, ventilation and air
and stairs not encapsulated by walls. conditioning machinery, and similar spaces, and
trunks to such spaces.
1.4.4 Store Room of high risk is a space for the
storage of flammable liquids or a room with an 1.4.14 Oil fuel unit is the equipment used for the
area of over 4 [m2] for storing supplies. preparation of oil fuel for delivery to an oil fired
boiler, or equipment used for the preparation for
1.4.5 Passageway is an area intended for the delivery of heated oil to an internal combustion
normal movement of persons and goods. engine, and includes any oil pressure pumps,
filters and heaters dealing with oil at a pressure
1.4.6 Main engine room is a space where the of more than 0.18 [N/mm2] gauge.
propulsion engines are installed.
1.4.15 Service spaces are those spaces used
1.4.7 Engine room is a space where combustion for galleys, pantries containing cooking
engines are installed. appliances, lockers, mail and specie rooms, store
rooms, workshops other than those forming part
1.4.8 Boiler room is a space housing a fuel- of machinery spaces, and similar spaces and
operated installation designed to produce steam trunks to such spaces.
or heat a thermal fluid
1.5 Ship types
1.4.9 Cargo spaces are all spaces used for
cargo (including cargo oil tanks) and trunks to 1.5.1 Passenger ship is a ship which carries
such spaces. more than twelve passengers, a passenger being
every person other than :
1.4.10 Non-combustible material is a material
which neither burns nor gives off flammable the master and members of the crew or
vapours in sufficient quantity for self-ignition other persons employed or engaged in
when heated to approximately 750C according any capacity on board a ship on the
to an established test procedure. Any other business of the ship; and
material is a combustible material. a child under one year of age.
1.4.11 Steel or other equivalent material. 1.5.2 Cargo ship is any ship which is not a
Where the words steel or other equivalent passenger ship or a fishing vessel.
material occur, 'equivalent material' means any
non- combustible material which, by itself or due 1.5.3 Fishing vessel is a vessel used for
to insulation provided, has structural and integrity catching living resources of the sea.
properties equivalent to steel at the end of the
Section 2
Fire Protection
Section 3
Fire Detection
3.2.1.1 Fire alarm systems consist of : 3.2.2.1.2 Fire detectors required in accordance
with 3.2.3.2 are to be automatic. One manually
a) fire detection system, operated call point is to be installed at each exit
of the compartment fitted with fire detectors. In
b) fire indicator system, Cargo Ships, manual call points are to be readily
accessible in the corridors and escape routes in
c) control panel crew accommodation spaces of each deck such
that no part is more than 20 [m] from a manual
as well as the external power supply. call point.
3.2.1.2 The fire detection system may be divided 3.2.2.1.3 The system and its components are to
into one or more sections. be able to withstand voltage fluctuations and
surges, changes in ambient temperature,
3.2.1.3 The fire indicator system may have one vibrations, humidity, shocks, impacts and
or more indicator devices. corrosion such as commonly occur on ships.
3.2.1.4 The control panel is the central control 3.2.2.2 Energy Supply
unit of the fire alarm system. It also includes parts
of the fire indicator system (i.e. an indicator 3.2.2.2.1 Energy sources and electric circuits
device). necessary for the operation of the fire alarm
system are to be self-monitoring. Any fault
3.2.1.5 A fire detection section may have one or occurring is to activate a visual and acoustic
more fire detectors alarm signal on the control panel which can be
distinguished from a fire alarm signal.
3.2.1.6 Fire detectors may be
3.2.2.2.2 There are to be at least two power
a) heat detectors, sources for the electrical part of the fire alarm
system, one of which is to be an emergency
b) smoke detectors, power system (i.e. emergency power source and
emergency switchboard). There are to be two
separate power-feeds solely for this purpose. body, whereby under-sensitivity or over-
These is to lead to an automatic switch in or near sensitivity of the detectors is to be avoided.
the control panel of the fire alarm system.
3.2.2.5.5 Heat detectors are to be set so that with
3.2.2.3 Fire Detection System temperature increase rates of less than 1
[°C/min] they respond at temperatures of
3.2.2.3.1 Fire detectors are to be grouped in fire between 54 [°C] and 78 [°C]. With higher rates of
detection sections. temperature increase, the heat detector is to
respond within temperature limits where under-
3.2.2.3.2 Fire detection systems are not to be or over-sensitivity of the heat detector is avoided.
used for any other purpose. Only closing of the
doors in accordance with Pt.5, Ch.3, 5.3.2.12 and 3.2.2.5.6 The permissible operating temperature
similar functions may be activated and indicated of heat detectors may be increased to 30 [°C]
on the control panel. above the maximum temperature in the upper
part of engine and boiler rooms.
3.2.2.3.3 Fire detection systems are to be
designed in such a way that the first indicated fire 3.2.2.5.7 The sensitivity of flame detectors is to
alarm does not prevent fire alarms set off by other be sufficient to detect flames against an
detectors. illuminated background. Flame detectors are also
to be equipped with a system for identifying false
3.2.2.4 Fire Detection Sections alarms.
3.2.2.4.2 Engine rooms and boiler rooms are to 3.2.2.6.4 On or near each indicator device there
constitute separate fire detection sections. is to be clear information on the areas monitored
and the location of the fire detection sections.
3.2.2.5 Fire Detectors
3.2.3 Installation Requirements of Fire Alarm
3.2.2.5.1 Only heat, smoke or ion detectors are System
to be used as fire detectors. Other types may only
be used as additional detectors. 3.2.3.1 Fire detectors are to be installed in such
a manner as to ensure the best possible
3.2.2.5.2 Fire detectors are to be type-approved. operation of the system. Locations in the vicinity
of deck girders and ventilation shafts or other
3.2.2.5.3 All automatic fire detectors are to be locations where air currents could adversely
designed in such a way that they can be tested to affect system operation and locations where
ensure that they are working properly and impacts or mechanical damage are likely are to
brought back into service without having to be avoided.
replace any components.
3.2.3.2 In general, fire detectors located on the
3.2.2.5.4 Smoke detectors are to be set so that ceiling are to be at least 0.5 [m] away from
they respond to a reduction in visibility per metre bulkheads. The maximum distance between fire
caused by smoke of more than 2 % to 12.5 %. detectors and bulkheads is to conform to the
Smoke detectors fitted in galleys, engine rooms Table3.2.3.2: IRS may require or approve other
and boiler rooms are to respond within sensitivity distances on the basis of tests which prove the
limits meeting the requirements of the inspection characteristics of the detectors.
3.2.3.3 The routing of electric cables for the fire unless this is necessary for fire detection in those
alarm system through engine rooms and boiler areas or connection to the corresponding power
rooms or other high fire risk areas is not permitted supply.
Section 4
Fire Extinction
shall be such as to avoid the possibility of area of the largest room to be protected subject
freezing. Suitable drainage provisions are to be to 4.2.1.4 (b).
provided for fire main piping. Isolation valves are
to be installed for all open deck fire main 4.2.1.4 For large areas to be protected, either of
branches used for purposes other than fire the following approaches may be followed
fighting. depending upon the fire risk:
4.2.2.3 The pump for the water supply to the space containing oil fuel units are to be provided
spray nozzles is to be activated automatically by with:
a pressure drop in the system. The pump is to be
dimensioned so that it can continuously provide a) An approved foam type fire extinguisher
a sufficient water supply at the necessary of at least 45 [litre] capacity or carbon
pressure if all the spray nozzles necessary for dioxide extinguisher of 15 [kg] capacity or
covering the area of the largest room to be dry powder extinguisher of 15 [kg]
protected are activated simultaneously (Also capacity to be directed on to any part of
refer Cl. 4.2.1.3 and 4.2.1.4). The pump is to the fuel and lubricating oil pressure
supply the automatic pressurised water sprinkler systems, gearing and other fire hazards.
exclusively. In the event of pump failure, it is to
be possible to provide the spray nozzles with a b) At least two portable foam extinguishers
sufficient water supply from another on-board or equivalent.
pump.
4.3.1.2 Where the size of the space precludes
4.2.2.4 The system is to be divided into sections, access under normal operating conditions,
each with no more than 50 spray nozzles. A provision is to be made to inject the extinguishing
larger number of spray nozzles may be medium into the space from an external location
authorised by IRS with appropriate corroboration, whilst maintaining the fire integrity of the space
in particular a hydraulic calculation. boundaries.
4.2.2.5 The number and the layout of spray 4.3.1.3 Machinery spaces with electrical
nozzles are to ensure effective distribution of installations are to be provided with one or more
water in the rooms to be protected. extinguishers suitable for extinguishing electrical
fire as deemed necessary. One or more of the fire
4.2.2.6 Spray nozzles are to be triggered at a extinguishers required by this section may be of
temperature between 68 [°C] and 79 [°C], in the the type required by this paragraph.
galley areas at a maximum of 93 [°C] and in the
saunas at a maximum of 141 [°C]. 4.3.1.4 In ships constructed of composite
material, engines rooms where total power output
4.2.2.7 The installation of components of is 375 [kW] and above are to be provided with any
automatic pressurised water sprinklers within the one of the fixed fire-extinguishing systems as per
rooms to be protected is to be limited to the 4.3.2, instead of compliance with 4.3.1.1 a) and
necessary minimum. No such system 4.3.1.2,
components are to be installed in main engine
rooms. 4.3.2 Fixed fire extinguishing system
a) Combustion air for the propulsion engines a) The extinguishing agent is to be conveyed
is not to be extracted from rooms that are to to the room, which is to be protected and
be protected by permanently installed fire- distributed there by means of a fixed piping
fighting systems. This is not applicable system. Inside the room to be protected the
where there are two mutually independent piping and associated fittings are to be
and hermetically separated main engine made of steel. Tank connecting pipes and
rooms or if next to the main engine room expansion joints are to be exempt from this
there is a separate engine room with a bow provided the materials used have
thruster, ensuring that the ship can equivalent properties in case of fire. Pipes
continue to make steerageway under its are to be both internally and externally
own power in the event of fire in the main protected against corrosion.
engine room.
b) Outlet nozzles are to be dimensioned and
b) Any forced ventilation present in the room fitted such that the extinguishing agent is
to be protected is to switch off automatically evenly distributed. In particular the
if the fire-fighting system is triggered. extinguishing agent is also to be effective
beneath the floor plates.
c) There are to be devices available with
which all apertures which can allow air to 4.3.2.6 Triggering Device
enter or gas to escape from the room to be
protected can be quickly closed. It is to be a) Fire-fighting systems with automatic
clearly recognisable whether they are open triggering is not permissible.
or closed.
b) It is to be possible to trigger the fire-fighting
d) The volume of starting air receivers, system from a suitable place outside the
converted to free air volume, is to be added room to be protected.
to the gross volume of the machinery space
when calculating the necessary quantity of c) Triggering devices are to be installed in
the fire extinguishing medium. Alternatively, such a way that they can be operated even
a discharge pipe from the safety valves in case of a fire and in the event of damage
may be fitted and led directly to the open by fire or explosion in the room to be
air. protected the necessary quantity of
extinguishing agent can still be conveyed.
e) Over- or under-pressure resulting from the Non-mechanical triggering devices are to
inflow of extinguishing agent is not to be powered from two different mutually
destroy the components of the surrounding independent power sources. These power
partitions of the room to be protected. It is sources are to be located outside the room
to be possible for the pressure to equalise to be protected. Control lines in the room to
without danger. be protected are to be designed so as to
remain functional for at least 30 [minutes] in
f) Protected rooms are to have a facility for the event of fire. This requirement is to be
extracting the extinguishing agent and the fulfilled in the case of electric wiring if it
combustion gases. Such facilities are to be complies with the International Standard
capable of being operated from positions IEC 6033121: 1999. If triggering devices
outside the protected rooms and which are installed in such a way that they are out
must not be made inaccessible by a fire of sight, the panel covering them is to be
within such spaces. If there are identified by the ‘fire-fighting installation’
permanently installed extractors, it is not to symbol, having a side length of at least 10
be possible for these to be switched on cm, and the following text in red lettering on
while the fire is being extinguished. a white background:
a) The room to be protected is to be monitored d) If the fire-fighting system is intended for the
by means of a fire alarm system (See 3.2). protection of several rooms, the triggering
The alarm is to be noticeable in the devices for each room have to be separate
wheelhouse, the accommodation spaces and clearly identified.
and the room to be protected.
e) The instructions are to be posted alongside f) A sign with the following text in red letters
all triggering devices and are to be clearly on a white ground is to be clearly posted at
visible and indelible. They are to contain, in the entrance to any space the extinguishing
particular, instructions regarding: agent may reach:
WARNING, FIRE-FIGHTING
i. triggering of the fire-fighting system; INSTALLATION !
LEAVE THE ROOM AS SOON AS THE
ii. the need for checking to ensure that all WARNING SIGNAL SOUNDS
persons have left the room to be (description of the signal)
protected;
4.3.2.8 Pressure tanks, fittings and pressure
iii. action to be taken by the crew when pipes
the firefighting system is triggered and
when accessing the protected room a) Pressure tanks, fittings and pressure pipes
after triggering or flooding, in particular are to comply with the provisions of
with regard to the possible presence of national/local authorities.
dangerous substances;
b) Pressure tanks are to be installed in
iv. action to be taken by the crew in the accordance with the manufacturer's
case of failure of the fire-fighting instructions.
system.
c) Pressure tanks, fittings and pressure pipes
f) The operating instructions are to mention are not to be installed in accommodation
that before the fire-fighting system is spaces.
triggered, combustion engines drawing air
from the room to be protected are to be shut d) The temperature in cabinets and
down. installation spaces containing pressure
tanks is not to exceed 50 [°C].
4.3.2.7 Warning System
e) Cabinets or installation spaces on deck are
a) Permanently installed fire-fighting systems to be firmly fixed in place and have air vents
are to be provided with acoustic and optical which are to be arranged in such a way that
warning systems. in the event of a leak in the pressure tank
no gas can escape into the interior of the
b) The warning system is to be set off ship. Direct connections to other rooms are
automatically as soon as the fire-fighting not permitted.
system is first triggered. The warning signal
is to sound for an appropriate time before 4.3.2.9 Quantity of extinguishing agent
the extinguishing agent is released and it is
not to be possible to switch it off. a) If the quantity of extinguishing agent is
intended for protecting more than one
c) Warning signals are to be clearly visible in room, the total amount of extinguishing
the rooms to be protected and outside the agent available does not need to be greater
accesses to them and clearly audible even than the quantity necessary for the largest
under operating conditions producing the room to be protected.
loudest inherent noise. They are to be
clearly distinct from all other acoustic and 4.3.2.10 Fire extinguishing system using CO2
optical signals in the room to be protected.
4.3.2.10.1 Fire-fighting systems using CO2 as the
d) The acoustic warning signals are to be extinguishing agent are to comply with the
clearly audible in the adjacent rooms even following provisions in addition to the 4.3.2.2 to
when connecting doors are closed and 4.3.2.9:
under operating conditions producing the
loudest inherent noise. a) CO2 containers are to be housed outside
the room to be protected in a space or
e) If the warning system is not self-monitoring cabinet hermetically separated from other
as regards short-circuits, wire breaks and rooms. The doors to these installation
voltage drops, it is to be possible to check spaces and cabinets are to open outwards,
that it is working properly. be lockable and bear on the outside a
f) The appropriate time mentioned under a) If there are several rooms to be protected,
4.3.2.7 b) is to be at least 20 [seconds]. each with a different gross volume, each
There is to be a reliable device to ensure room is to be provided with its own fire-
the delay before delivery of the CO2 gas. fighting system.
4.3.2.11 Fire extinguishing system using HFC- b) Each container of IG-541 that is installed in
227 ea (heptafluropropane) the room to be protected is to be equipped
with a pressure relief valve. This is to
4.3.2.11.1 Fire-fighting systems using HFC-227 harmlessly release the contents of the
ea (heptafluropropane) as the extinguishing container into the room to be protected if
agent is to comply with the following provisions in the container is exposed to the effects of
addition to the 4.3.2.2 to 4.3.2.9: fire and the fire-fighting system has not
been triggered.
a) If there are several rooms to be protected,
each with a different gross volume, each c) Each container is to be fitted with a device
room is to be provided with its own fire- for checking the contents.
fighting system.
d) the filling pressure of the container is not to
b) Each container of HFC-227ea that is exceed 200 [bar] at + 15 [°C].
installed in the room to be protected is to be
equipped with a pressure relief valve. This e) the volume of IG-541 for the room to be
is to harmlessly release the contents of the protected is to be at least 44 % and no more
container into the room to be protected if than 50 % of the room's gross volume. This
the container is exposed to the effects of volume is to be supplied within 120
fire and the fire-fighting system has not [seconds].
been triggered.
4.3.2.13 Fire extinguishing system using FK-
c) Each container is to be fitted with a device 5-1-12
for checking the gas pressure.
4.3.2.13.1 Fire-fighting systems using FK-5-1-12
d) The containers are not to be filled to more as the extinguishing agent is to comply with the
than 1.15 [kg/l]. The specific volume of the
following provisions in addition to the 4.3.2.2 to continuously into the room for a minimum of
4.3.2.9: 30 [minutes].
a) If there are several rooms to be protected, c) The pumps, their switching mechanisms
each with a different gross volume, each and the valves that are required in order for
room is to be provided with its own the system to operate should be installed in
firefighting system. a room outside the rooms to be protected.
The room in which they are installed should
b) Each container of FK-5-1-12 installed in the be separated from adjacent by at least type
room to be protected is to be equipped with A30 partition walls.
an overpressure relief valve. The pressure
relief valve is to harmlessly release the d) The fire-fighting system must be completely
contents of the container into the room to full of water at all times at least as far as the
be protected if the container is exposed to trip valves and be under the required initial
the effects of fire and the fire-fighting operating pressure. The water supply
system has not been triggered. pumps must be automatically initiated when
the system is triggered. The system must
c) Each container is to be fitted with a device feature a continuously operating water
for checking the gas pressure. supply. Measures must be taken to ensure
impurities do not affect system operation.
d) The containers are not to be filled to more
than 1.00 [kg/l]. The specific volume of the e) The capacity and design of the system's
unpressurised FK-5-1-12 is to be taken as pipe network must be based on a hydraulic
0.0719 [m3/kg]. calculation.
e) The volume of FK-5-1-12 for the room to be f) The number and arrangement of nozzles
protected is to be at least 4 % of the room’s must ensure sufficient distribution of water
gross volume. This volume is to be supplied in the rooms to be protected. The spray
within 10 [seconds]. nozzles must be located so as to ensure
that the water mist is distributed throughout
f) The FK-5-1-12 containers are to be the room to be protected, especially in
provided with a pressure monitor which those areas where there is a higher risk of
triggers an acoustic and optical alarm fire, including behind the fittings and
signal in the wheelhouse in the event of an beneath the floor.
unauthorised loss of propellant.
g) The fire-fighting system's electrical
g) After flooding, the concentration in the room components in the room to be protected
to be protected is not to exceed 10 %. must at a minimum comply with protection
class IP54. The system is to feature two
4.3.2.14 Fire extinguishing system using independent energy sources with
water as the extinguishing agent automatic switching. One of the power
sources must be located outside the room
4.3.2.14.1 Fire-fighting systems using water as to be protected. Each power source should
the extinguishing agent may only release this on its own be capable of ensuring the
agent into the room to be protected in the form of operation of the system.
a water mist. The droplet size must be between 5
and 300 [microns]. h) The fire-fighting system must feature
redundant pumps.
4.3.2.14.2 Fire-fighting systems using water mist
as the extinguishing agent is to comply with the i) The fire-fighting system must be equipped
following provisions in addition to the 4.3.2.2 to with a monitoring device which triggers an
4.3.2.9: alarm signal in the wheelhouse in the
following cases:
a) The fire-fighting system is to have a type-
approval pursuant to MSC/Circ. 11651 or - drop in water tank level (if fitted),
another recognized Standard. - power supply failure,
- loss of pressure in the low
b) The fire-fighting system must be sized pressure system pipework,
according to the largest of the rooms to be - loss of pressure in the high
protected and must be able to spray water pressure circuit,
End of Chapter
Chapter 10
Spare Gear
Contents
Section
1 General
Section 1
General
1.1 General
1.2 Table of spare parts
1.1.1 Adequate spare parts for the propelling and
essential auxiliary machinery together with 1.2.1 For guidance purposes spare parts for main
necessary tools for maintenance and repair are and auxiliary machinery installations are shown
to be readily available for use. in the following Tables:-
1.1.2 Spare parts are to be supplied and their Table 1.2.1 - Spare parts for main internal
location is to be the responsibility of the Owner combustion engines;
but must take in to account the design and
arrangements of the machinery and the intended Table 1.2.2 - Spare parts for auxiliary boilers;
service and operation of the ship. Account should
also be taken of the recommendations of the Table 1.2.3 - Spare parts for auxiliary air
machinery manufacturer and any applicable compressors.
statutory requirements of the country of
registration of the ship.
Sr.
Item Spare Part Qty.
No.
Pads for one face of thrust block 1 set
1 Main thrust block Complete white metal thrust shoe of solid ring type 1
Inner and outer race with rollers, where roller thrust bearings
1
are fitted
Exhaust valves, complete with casings, seats, springs and
1 set
other fittings for one cylinder
Air inlet valves, complete with casings, seats springs and other
1 set
fittings for one cylinder
2 Cylinder valves Starting air valve, complete with casing, seat, springs and
1
other fittings
Relief valve, complete 1
Fuel valves of each size and type fitted complete with all
1/4 set
fittings, for one engine
Special gaskets and packing of each size and type fitted for
3 1 set
cylinder cover and cylinder liner for one cylinder
Sr.
Item Spare Part Qty.
No.
Tube stoppers or Tube stoppers or plugs, of each size used, for boiler
1 10
plugs superheater and economiser tubes
2 Fire bars Fire bars for one boiler, where coal fired Half set
3 Oil fuel burners Oil fuel burners complete, for one boiler 1 set
Sr.
Item Spare Part Qty.
No.
1 Piston rings Rings of each size fitted for one piston 1 set
2 Valves Suction and delivery valves, complete, of each size fitted Half set
End of Chapter
Part 5
Contents
Chapter 2 Tankers
Chapter 4 Tugs
Contents
Chapter 1
Section 2
Section 3
Bulk Carriers
Ore Carriers
2.1 Hull arrangement
3.1 Hull arrangement
2.2 Longitudinal strength
Chapter 2
Tankers
Section 1 Section 3
4.1 General
Section 6
4.2 Class Notations
4.8 Definitions
Section 7
Section 5 Fire Safety Requirements for Tankers
Carrying Dangerous Goods
Vessels Carrying Dangerous Cargoes
in Liquid State ( Type N & C Vessels ) 7.1 Application
Chapter 3
Passenger Vessels
Section 1
2.2 Subdivision and transverse bulkheads
General 2.3 Watertight doors and doors
Chapter 4
Tugs
Section 1 Section 2
Stability
Section 3
5.1 General
Towing Arrangement
Section 6
3.1 General
Chapter 5
General
Section 3
1.1 Application
Pushing, Towing – Devices and
1.2 Documentation Connecting Elements
3.1 General
Section 2
End of Contents
Chapter 1
Contents
Section
1 General
2 Bulk Carriers
3 Ore Carriers
Section 1
General
1.1.1 The requirements of this chapter apply to 1.2.1 The following additional documents are to
single deck vessels designed primarily for be submitted for approval, as applicable:
carriage of dry bulk cargoes and are
supplementary to those given for the assignment a) Design values of maximum mass of bulk
of main characters of class. It is implied that the cargo to be carried in the vessel and total
cargo loading would largely be homogeneous, volume of holds upto top of the hatch
without any hold being empty in fully loaded coaming.
condition.
b) Maximum density of heavy bulk cargo
1.1.2 In general, bulk carriers, built in compliance envisaged and the corresponding angle of
with the above mentioned requirements, as repose.
applicable, will be eligible to be assigned one of
the following class notations: c) Details of all envisaged loading conditions
clearly stating special features if any e.g.
BULK CARRIER loading in heaps. Calculations of still water
BULK CARRIERS, “Strengthened for heavy bending moments in all these loading
Cargoes”. conditions and also for transient conditions
during loading / unloading, if more onerous,
The notation “BULK CARRIER” implies that any are to be submitted.
hold may be filled up to the top of hatch coaming
with bulk cargo of density at least upto 0.8 [t/m3]. 1.3 Design loads in cargo holds
= 1.0 [t/m3] for vessels with class notation, “Bulk Flooding pressure, p = 10h [kN/m2]
carrier” “Strengthened for heavy cargoes” and for
“Ore carriers”. where,
H = height [m], from the load point to the top of C = 1.0 for inner bottom
hatch coaming.
= Tan2 (45 - /2) for vertical bulkheads
h = Maximum density of heavy bulk cargo
envisaged [t/m3]. = Sin2α . Tan2(45° - /2) + Cos2α for sloping
bulkheads
hc = height [m], from the load point to the actual
cargo surface determined by considering the α = angle of sloping bulkhead with the horizontal
corresponding hold geometry, cargo volume at plane, [degrees]
density h angle of repose and the loading pattern
e.g. loading in heaps. q = f . H [t/m2], or
Section 2
Bulk Carriers
2.1 Hull arrangement bulkheads may have to be fitted from side to side
or in wing spaces to provide sufficient transverse
2.1.1 Bulk carriers are to be constructed with two strength.
longitudinal bulkheads bounding the cargo space
or with single side skin construction in association 2.2 Longitudinal strength
with hopperside tanks at the bottom and topside
tanks fitted below the deck. Between the 2.2.1 The longitudinal strength is to be in
longitudinal bulkheads or hopperside tanks, accordance with the requirements given in Pt.3
double bottom construction is generally to be Ch.4, considering the maximum of still water
adopted. However, for vessels upto 65 [m] in bending moments calculated as per 1.2.1.
length single bottom construction with floors at
each frame may be accepted. 2.3 Bottom structure
2.1.2 For vessels of L ≥ 65 [m] longitudinal 2.3.1 The scantlings and arrangements are, in
framing system is to be adopted within the cargo general, to be as per Pt.3, Ch.6, except as given
region on deck and in the double bottom, wing below.
spaces or hopperside and topside tanks.
2.3.2 In double bottom spaces, the spacing of
2.1.3 The number and disposition of transverse plate floors and girders is generally not to exceed
bulkheads are to be as per Pt.3, Ch.9. Additional 2.5 [m] and 3 [m], respectively.
2.3.3 The scantlings of inner bottom and hopper longitudinal bulkhead may be reduced by 20%
side plating and stiffeners based on Pt.3, Ch.6 provided a strut is fitted at mid span of the
and design pressures given in 1.3.2 are minimum stiffeners. The strut is to have the same cross
requirements. It should be noted that for vessels sectional area as the greater of the members
where cargoes are to be regularly discharged by interconnected.
grabs, the scantlings would require to be
increased suitably to reduce the risk of local 2.5.5 The inner bottom plating is to be extended
damage and erosion and are to be as per Pt.3, into the wing tank structure in the form of a gusset
Ch.6, 4.2.3.. plate, arranged to ensure a smooth structural
transition in way of transverse primary members.
2.3.4 In addition to the requirements of Pt.3, The gusset plate is to be of sufficient width to
Ch.6, the section modulus of single bottom floors provide effective scarfing of the inner bottom into
in cargo holds is also to be not less than the the wing tank structure.
following:
2.5.6 All watertight and non-watertight bulkheads
Z = 0.006 s le2 (f . H – 0.3T) [cm3] in wing tanks are to be suitably reinforced in way
of double bottom scarfing arrangements.
- Where the cargo is always to be leveled Openings in wing tank bulkheads are to be kept
clear of these areas.
Z = 0.006 s le2 (1.25f . H – 0.3T) [cm3]
2.5.7 Ends of longitudinal bulkheads are to be
- Where the cargo is loaded in heaps. well scarfed into the fore and aft structure.
2.8.2 Where bulkheads are of corrugated webs with the plane of bulkheads) is not to be
construction, the angle of corrugation (i.e. of less than 55°.
Section 3
Ore Carriers
End of Chapter
Chapter 2
Tankers
Contents
Section
1 General
2 Hull Scantlings
3 Structural Arrangement
4 General Requirements for Tankers Carrying Dangerous Goods
5 Vessels Carrying Dangerous Cargoes in Liquid State ( Type N & C Vessels)
6 Vessels Carrying Dangerous Cargoes in Gaseous State ( Type G Vessels)
7 Fire Safety Requirements for Tankers Carrying Dangerous Goods
Section 1
General
Section 2
Hull Scantlings
Section 3
Structural Arrangement
3.6.4.2 The tanks are to be supported by the 3.7.4 The thickness of separate end brackets
floors or bottom longitudinals. is generally to be not less than that of the
thicker of the primary member webs being
3.6.4.3 When stringer is chocked against connected, but may be required to be locally
tanks in way of some web frames or side increased at the toes. The bracket is to extend
shell transverses, chocking may consist in a to adjacent tripping brackets, stiffeners or
bolted assembly. Arrangements are to be other support points. Bracket toes are to be
provided to avoid an accidental shifting well radiused. Where the bracket is attached
during navigation in case of applying to a corrugated bulkhead, the plating at the
bracket toe is to be suitably reinforced. 3.7.8 Longitudinals within the range of cargo
tanks are not permitted to have closely
3.7.5 Tripping brackets are generally to be spaced scallops except in way of ballast pipe
fitted close to the toes of end brackets, in way suctions. Reinforcement in these areas will be
of cross ties and generally at every fourth specially considered. Small air and drain
stiffener elsewhere. Arrangements should holes, cut-outs at erection butts and similar
also be made to prevent tripping at the widely spaced openings are, in general not to
intersection with other primary members.
be less than 200 [mm] clear of the toes of end
3.7.6 In way of cross ties and their end brackets, intersections with primary
connections lightening holes are not to be cut supporting members and other areas of high
in side and longitudinal bulkhead stringers. stress. All openings are to be well rounded
Lightening holes are also to be avoided on with smooth edges.
vertical webs on longitudinal bulkheads and in
3.7.9 Where holes are cut for heating coils,
wing ballast tanks.
the lower edge of the hole is to be not less
3.7.7 Holes cut in primary longitudinal than 100 [mm] from the inner bottom. Where
members within 0.1D of deck and bottom are, large notches are cut in the transverses for
in general to be reinforced. Where holes are the passage of longitudinal framing, adjacent
cut in primary longitudinal members in areas to openings for heating coils, the notches for
of high stress and where primary members longitudinals are to be collared.
are of higher tensile steel, they are to be
elliptical, or equivalent, to minimise stress
concentration.
Section 4
General Requirements for Tankers Carrying Dangerous Goods
4.1 General
In English:
4.1.1 Application
The European Agreement concerning
4.1.1.1 The requirements in this section the International Carriage of
apply to tankers intended for carriage of Dangerous Goods by River.
dangerous goods in bulk.
4.1.1.4 Electronic copies of the ADN can be
4.1.1.2 Attention is also drawn to National downloaded from the site of the United
and International technical and operational Nations Economic Commission for Europe
requirements of countries where the vessel at:
is registered or operating, which are outside
https://www.unece.org/trans/danger/p
Classification.
ubli/adn/adn_e.html
4.1.1.3 The requirements of Classification of
4.1.2 ADN, The European Agreement
Inland Waterways tankers intended for the
concerning the International Carriage of
carriage of dangerous liquids in bulk are
Dangerous Goods by River.
based on the United Nation’s ADN
regulations. The ADN are the regulations for The European Agreement concerning the
the transport of dangerous goods. The International Carriage of Dangerous Goods by
abbreviation ADN stands for: Inland Waterways (ADN) was done at Geneva
on 26 May 2000 on the occasion of a
In French:
Diplomatic Conference held under the joint
Accord europeen relatif au transport auspices of the United Nations Economic
international des marchandises Commission for Europe (UNECE) and the
Dangereuses par voies de Navigation
interieures. Central Commission for the Navigation of the
Rhine (CCNR).
TANK DESIGN 1
Closed Tank
TANK DESIGN 2 X X X
Open Tank with flame arresters
TANK DESIGN 3 X X X
Open Cargo Tank
TANK DESIGN 4 X X X
Type C Tankers
Walls Distinct from
Independent Integral
outer hull
TANK TYPE 1 TANK TYPE 2
TANK TYPE 3
Pressure Tank
X N.A N.A
Cargo Tank Design
TANK DESIGN 1
Closed Tank
TANK DESIGN 2 X X N.A
Open Tank with flame arresters
TANK DESIGN 3 N.A N.A N.A
Open Cargo Tank
TANK DESIGN 4 N.A N.A N.A
Type G Tankers
Walls Distinct from
Independent Integral
outer hull
TANK TYPE 1 TANK TYPE 2
TANK TYPE 3
Pressure Tank
X N.A N.A
Cargo Tank Design
TANK DESIGN 1
Closed Tank
TANK DESIGN 2 X N.A N.A
Open Tank with flame arresters
TANK DESIGN 3 N.A N.A N.A
Open Cargo Tank
TANK DESIGN 4 N.A N.A N.A
Fore and aft, by planes inclined at plane of the vessel, which comprises cargo
45˚ towards the cargo area, tanks, hold spaces, cofferdams, double-hull
starting at the boundary of the spaces and double bottom; these planes
cargo area part below deck normally coincide with the outer cofferdam
Vertically, 3 [m] above the deck bulkheads or hold end bulkheads. Their
intersection line with the deck is refers to as
4.8.7.3 Cargo area (part below deck) the boundary of the cargo area part below
means the space between two vertical deck.
planes perpendicular to the centre-line
4.8.10 Cargo tank (when anti-explosion occur rarely and, if so, for short
protection is required, comparable to zone periods only.
0) means a tank which is permanently
attached to the vessel and intended for the 4.8.14 Certified safe type electrical
carriage of dangerous goods. apparatus means an electrical apparatus
which has been tested and approved by the
4.8.11 Cargo Tank Design competent authority regarding its safety of
4.8.11.1 Pressure cargo tank means a operation in an explosive atmosphere, e.g.
cargo tank independent of the vessel’s hull, intrinsically safe apparatus;
built according to dedicated recognized flameproof enclosure apparatus;
standards for a working pressure ≥ 400 apparatus protected by
[kPa] pressurization;
4.8.11.2 Closed cargo tank means a cargo powder filling apparatus;
tank connected to the outside atmosphere apparatus protected by
through a device preventing unacceptable encapsulation;
overpressure or under pressure increased safety apparatus.
4.8.11.3 Open cargo tank with flame 4.8.15 Cofferdam (when anti-explosion
arrester means a cargo tank connected to protection is required, comparable to zone 1)
the outside atmosphere through a device means an athwartship compartment which is
fitted with a flame arrester. bounded by watertight bulkheads and which
can be inspected. The cofferdam is to extend
4.8.11.4 Open cargo tank means a cargo
over the whole area of the end bulkheads of
tank in open connection with the outside
the cargo tanks. The bulkhead not facing the
atmosphere.
cargo area is to extend from one side of the
4.8.12 Cargo tank type vessel to the other and from the bottom to the
deck in one frame plane.
4.8.12.1 Independent cargo tank means a
cargo tank which is permanently built in, but 4.8.16 Deflagration means an explosion
which is independent of the vessel’s which propagates at subsonic speed (see EN
structure. 13237:2011);
4.8.12.2 Integral cargo tank means a 4.8.17 Design pressure means the pressure
cargo tank which is constituted by the on the basis of which the cargo tank or the
vessel’s structure itself and bounded by the residual cargo tank has been designed and
outer hull or by walls separate from the outer built.
hull.
4.8.18 Detonation means an explosion which
4.8.12.3 Cargo tank with wall distinct propagates at supersonic speed and is
from the outer hull means an integral characterized by a shock-wave (see EN
cargo tank of which the bottom and side 13237:2011);
walls do not form the outer hull of the vessel
4.8.19 Explosion means a sudden reaction
or an independent cargo tank.
of oxidation or decomposition with an
4.8.13 Classification of zones (see IEC increase in temperature or in pressure or both
publication 79-10, EU directive 1999/92/CE ): simultaneously (see EN 13237:2011);
Zone 0: areas in which dangerous 4.8.20 Flame arrester means a device
explosive atmospheres of gases, mounted in the vent of part of an installation
vapours or sprays exist or in the interconnecting piping of a system of
permanently or during long installations, the purpose of which is to permit
periods; flow but prevent the propagation of a flame
Zone 1: areas in which dangerous front. This device is to be tested according to
explosive atmospheres of gases, the European standard EN ISO 16852:2010;
vapours or sprays are likely to 4.8.21 Flame arrester plate stack means the
occur occasionally; part of the flame arrester the main purpose of
Zone 2: areas in which dangerous which is to prevent the passage of a flame
explosive atmospheres of gases, front;
vapours or sprays are likely to
4.8.22 Flame arrester housing means the 4.8.29 Loading instrument: A loading
part of a flame arrester the main purpose of instrument consists of a computer (hardware)
which is to form a suitable casing for the flame and a programme (software) and offers the
arrester plate stack and ensure a mechanical possibility of ensuring that in every ballast or
connection with other systems; loading case:
the permissible values concerning
4.8.23 Flash-point means the lowest
longitudinal strength as well as the
temperature of a liquid at which its vapours
form a flammable mixture with air. maximum permissible draught are
not exceeded; and
4.8.24 Gas (for the purposes of Class 2) the stability of the vessel complies
means a substance which: with the requirements applicable to
a) at 50 [° C] has a vapour pressure the vessel. For this purpose, intact
greater than 300 [kPa] (3 bar); or stability and damage stability are to
b) is completely gaseous at 20 [° C] be calculated.
under standard pressure of 101.3
[kPa]; 4.8.30 Maximum working pressure means
the maximum pressure occurring in a cargo
Otherwise, Gases means gases or tank or a residual cargo tank during operation.
vapours; This pressure equals the opening pressure of
high velocity vent valves.
4.8.25 Gas detection system means a fixed
system capable of detecting in time significant 4.8.31 Naked light means a source of light
concentrations of flammable gases given off using a flame which is not enclosed in a
by the cargoes at concentrations below the flameproof enclosure.
lower explosion limit and capable of activating
the alarms; 4.8.32 Opening pressure means the
pressure referred to in a list of substances at
4.8.26 High-velocity vent valve means a which the high velocity vent valves open.
pressure relief valve designed to have
nominal flow velocities which exceed the 4.8.33 Packing group means a group to
flame velocity of the flammable mixture, thus which, for packing purposes, certain
preventing flame transmission. This type of substances may be assigned in accordance
installation is to be tested in accordance with with their degree of danger. The packing
standard EN ISO 16852:2010; groups have the following meanings which
are explained in a more detailed manner in
4.8.27 Identification number means the Part 2 of the ADN:
number for identifying a substance to which Packing group I: Substances
no UN number has been assigned or which presenting high danger;
cannot be classified under a collective entry Packing group II: Substances
with a UN number. These numbers have four presenting medium danger; and
figures beginning with 9.
Packing group III: Substances
4.8.28 Liquid means a substance which at 50 presenting a lower danger.
[° C] has a vapour pressure of not more than
300 [kPa] (3 bar) which is not completely 4.8.34 Pressure relief device means a
gaseous at 20 [° C] and 101.3 [kPa], and spring-loaded device which is activated
which: automatically by pressure the purpose of
a) has a melting point or initial melting which is to protect the cargo tank against
point of 20 [° C] or less at a unacceptable excess internal pressure;
pressure of 101.3 [kPa], or 4.8.35 Pressure receptacle means a
b) is liquid according to the ASTM D collective term that includes cylinders, tubes,
4359-90 test method or pressure drums, closed cryogenic
c) is not pasty according to the criteria receptacles, metal hydride storage systems,
applicable to the test for bundles of cylinders and salvage pressure
determining fluidity (penetrometer receptacles;
test)
4.8.36 Pressures. For tanks, all kinds of 4.8.42 Slops means a mixture of cargo
pressures (e.g. working pressure, opening residues and washing water, rust or sludge
pressure of the high velocity vent valves, test which is either suitable or not suitable for
pressure) are to be expressed as gauge pumping;
pressures in kPa (bar); the vapour pressure of
substances, however, is to be expressed as 4.8.43 Tanker. A vessel which has been
an absolute pressure in kPa (bar). specially designed and constructed for the
carriage of liquids or gases in bulk.
4.8.37 Receptacle means a containment
vessel for receiving and holding substances 4.8.44 Test pressure means the pressure at
or articles, including any means of closing. which a cargo tank, a residual cargo tank, a
This definition does not apply to shells (see cofferdam or the loading and unloading pipes
also Cryogenic receptacle, Inner receptacle, is to be tested prior to being brought into
Rigid inner receptacle and Gas cartridge); service for the first time and subsequently
regularly within prescribed times.
4.8.38 Receptacle for residual products
means a tank, intermediate bulk container or 4.8.45 UN number means the four-figure
tank-container or portable tank intended to identification number of the substance or
collect residual cargo, washing water, cargo article as indicated in the United Nations
residues or slops which are suitable for Model Regulations
pumping; 4.8.46 Water film means a deluge of water
4.8.39 Receptacle for slops means a steel for protection against brittle fracture;
drum intended to collect slops which are 4.8.47 Water spray system means an on-
unsuitable for pumping; board installation that, by means of a uniform
4.8.40 Safety valve means a spring-loaded distribution of water, is capable of protecting
device which is activated automatically by all the vertical external surfaces of the
pressure the purpose of which is to protect the vessel’s hull fore and aft, all vertical surfaces
cargo tank against unacceptable excess of superstructures and deckhouses and deck
internal pressure or negative internal surfaces above the superstructures, engine
pressure (see also, High velocity vent valve, rooms and spaces in which combustible
Pressure-relief device and Vacuum valve); materials may be stored. The capacity of the
water spray system for the area to be
4.8.41 Service space means a space which protected should be at least 10 [l/m2 per
is accessible during the operation of the minute]. The water spray system is to be
vessel and which is neither part of the designed for full-year use. The spray system
accommodation nor of the cargo tanks, with should be operable from the wheelhouse and
the exception of the forepeak and after peak, the safe area;
provided no machinery has been installed in
these latter spaces;
Section 5
Vessels Carrying Dangerous Cargoes in Liquid State
(Type N & C Vessels)
5.1 Application required in the other Parts of the Rules for the
parts of the vessel not affected by the cargo,
5.1.1 This section applies to propelled and as applicable.
non-propelled tankers of Types C, N Closed,
N Open with flame arrestors and N Open, in 5.2.1.1 Documents for Approval
general, intended for the carriage of
a) Ventilation duct arrangement in
dangerous liquid oil and chemical cargoes of
gas-dangerous spaces and
Classes 3, 6.1, 8 and 9 in bulk.
adjacent zones
5.2 Documents to be submitted
b) Details of hull structure in way of
5.2.1 Following plans and documents are to cargo tanks, including support
be submitted in addition to the documentation arrangement for tanks, saddles,
o masts and similar round 5.3.7 The suitability of the lining or coating
timber; and its compatibility with the intended cargoes
is the responsibility of the Builder and Owner.
o engine parts; IRS will require the confirmation of the
manufacturer that the lining or coating used to
o parts of the electrical protect the cargo tank structure is compatible
installation; with the cargoes mentioned in list of cargoes.
o loading and unloading 5.4 Requirements for Type N Tankers
appliances;
5.4.1 General
o lids of boxes which are 5.4.1.1 Application
placed on the deck.
5.4.1.1.1 Requirements of this subsection
The use of wood or plastic materials are applicable to Type N tankers.
within the cargo area is only
5.4.2 Arrangement
permitted for:
5.4.2.1 Protection against the penetration of
o supports and stops of any gases - Type N closed and Type N open
kind. with flame arrester
The use of plastic materials or 5.4.2.1.1 The vessel is to be designed so
rubber within the cargo area is only as to prevent gases from penetrating into
permitted for: the accommodation and the service
spaces.
o coating of cargo tanks and
of piping for loading and 5.4.2.1.2 Outside the cargo area, the
unloading; lower edges of door-openings in the
sidewalls of superstructures and the
o all kinds of gaskets (e.g. for coamings of access hatches to under-
dome or hatch covers); deck spaces are to have a height of not
less than 0.50 [m] above the deck. This
o electric cables; requirement need not be complied with if
the wall of the superstructures facing the
o hose assemblies for cargo area extends from one side of the
loading and unloading; vessel to the other and has doors the sills
of which have a height of not less than
o insulation of cargo tanks 0.50 [m]. The height of this wall is not to be
and of piping for loading less than 2.00 [m]. In this case, the lower
and unloading; edges of door-openings in the sidewalls of
superstructures and of coamings of
o photo-optical copies of the access hatches behind this wall are to
certificate of approval. have a height of not less than 0.10 [m].
The sills of engine room doors and the
All permanently fitted materials in
coamings of its access hatches are to,
the accommodation or wheelhouse, however, always have a height of not less
with the exception of furniture, are than 0.50 [m].
not to readily ignite. They are not to
evolve fumes or toxic gases in 5.4.2.1.3 In the cargo area, the lower
dangerous quantities, if involved in edges of door-openings in the sidewalls of
a fire. superstructures are to have a height of not
less than 0.50 [m] above the deck and the
5.3.5 The paint used in the cargo area is not sills of hatches and ventilation openings of
to be liable to produce sparks in case of premises located under the deck are to
impact. have a height of not less than 0.50 [m]
above the deck. This requirement does not
5.3.6 To avoid corrosive attack of the cargo apply to access openings to double-hull
tank structure by chemical cargoes, it is and double bottom spaces.
strongly recommended the structure be
protected by suitable lining or coating.
5.4.2.1.4 The bulwarks, foot-rails, etc. are conditions when they are to be closed.
to be provided with sufficiently large All ventilation inlets of accommodation
openings which are located directly above and service spaces leading outside are
the deck. to be fitted with fire flaps. Such
ventilation inlets are to be located not
5.4.2.2 Ventilation less than 2 [m] from the cargo area.
5.4.2.2.1 General Ventilation inlets of service spaces in the
cargo area below deck may be located
5.4.2.2.1.1 Each hold space is to have within such area.
two openings. The dimensions and
location of these openings are to be such 5.4.2.2.2.3 The flame-arresters pre-
as to permit effective ventilation of any scribed in 5.4.2.6.4.1, 5.4.3.2.3,
part of the hold space. If there are no 5.4.3.2.4.2, 5.4.3.2.4.3, 5.4.8.4, 5.4.8.5,
such openings, it is to be possible to fill 5.4.8.6 and 5.4.8.7 are to be type
the hold spaces with inert gas or dry air. approved for this purpose by the IRS.
5.4.2.6.4.1 When the list of substances open ends of overflow pipes leading on the
on the vessel contains substances for deck are to be provided with a protective
which protection against explosion is device consisting of a gauze diaphragm or
required in column (17) of Table C of a perforated plate.
Chapter 3.2 of ADN, the ventilation
openings of cofferdams are to be fitted 5.4.2.9 Exhaust pipes
with a flame-arrester withstanding a 5.4.2.9.1 Exhausts are to be evacuated
deflagration from the vessel into the open air either
5.4.2.7 Engines upwards through an exhaust pipe or
through the shell plating. The exhaust
5.4.2.7.1 Only internal combustion outlet is to be located not less than 2 [m]
engines running on fuel with a flashpoint of from the cargo area. The exhaust pipes of
more than 55 [°C] are allowed. This engines are to be arranged so that the
provision does not apply to internal exhausts are led away from the vessel.
combustion engines which are part of The exhaust pipes are not to be located
propulsion and auxiliary systems. These within the cargo area.
systems are to meet the requirements of
IRS Classification Note “Natural Gas 5.4.2.9.2 Exhaust pipes are to be provided
Fuelled Vessels for Coastal and Inland with a device preventing the escape of
Waters”. sparks, e.g. spark arresters.
5.4.2.7.2 Ventilation inlets of the engine 5.4.2.10 Bilge pumping and ballasting
room and, when the engines do not take in arrangements
air directly from the engine room, the air 5.4.2.10.1 Bilge and ballast pumps for
intakes of the engines are to be located not spaces within the cargo area are to be
less than 2 [m] from the cargo area. installed within such area.
5.4.2.7.3 Sparking is not to be possible This provision does not apply to:
within the cargo area.
double hull spaces and double
5.4.2.7.4 The surface temperature of the bottoms which do not have a
outer parts of engines used during loading common boundary wall with the
or unloading operations, as well as that of cargo tanks;
their air inlets and exhaust ducts are not to
exceed the allowable temperature cofferdams, double hull spaces,
according to the temperature class of the hold spaces and double bottoms
substances carried. This provision does where ballasting is carried out
not apply to engines installed in service using the piping of the fire fighting
spaces provided the provisions of system in the cargo area and bilge
5.4.9.3.7 are fully complied with. pumping is performed using
eductors.
5.4.2.7.5 The ventilation in the closed
engine room is to be designed so that, at 5.4.2.10.2 Where the double bottom is
an ambient temperature of 20 [°C], the used as oil fuel tank, it is not to be
average temperature in the engine room connected to the bilge piping system.
does not exceed 40 [°C].
5.4.2.10.3 Where the ballast pump is
5.4.2.8 Oil fuel tanks installed in the cargo area, the standpipe
and its outboard connection for suction of
5.4.2.8.1 When the vessel is provided with ballast water is to be located within the
hold spaces, the double bottoms within cargo area but outside the cargo tanks.
these spaces may be arranged as oil fuel
tanks, provided their depth is not less than 5.4.2.10.4 A cargo pump-room below deck
0.6 [m]. Oil fuel pipes and openings of is to be capable of being drained in an
such tanks are not permitted in the hold emergency by an installation located in the
space. cargo area and independent from any
other installation. This installation is to be
5.4.2.8.2 The open ends of the air pipes of provided outside the cargo pump room.
oil fuel tanks are to extend to 0.5 [m] above
the open deck. Their open ends and the
where:
LOA X BOA X D : Product of the tank vessel main dimensions, in [m3]
LOA : overall length of the hull, in [m]
BOA : extreme breadth in [m]
D : Shortest vertical distance between the top of the keel and the lowest point of the
deck at the side of the vessel; (moulded depth) within the cargo area in [m].
In the case of trunk deck vessels, D’ is to be substituted for D.
D’ is to be determined by the following formula:
𝒃𝒕 𝒍𝒕
𝑫 𝑫 𝒉𝒕
𝑩 𝑳
Where,
ht: Height, in [m], of trunk (distance between trunk deck and main deck on trunk side
measured at LOA/2)
bt : Trunk breadth, in [m]
lt : Trunk length, in [m]
5.4.3.1.4 When the vessel is provided with This provision does not apply to
pressure tanks, these tanks are to be vessels with independent built-in
designed for working pressure of 400 [kPa] cylindrical tanks having a length to
diameter ratio ≤ 7
5.4.3.1.5 The cargo tank is to comply with
the following:
5.4.3.1.6 The cargo tanks independent of arranged for being filled with ballast water
the vessel’s hull are to be fixed so that they only. Double bottoms may, however, be
cannot float. used as fuel oil tanks, provided they
comply with 5.4.2.8.
5.4.3.1.7 The capacity of a suction well is
to be limited to not more than 0.10 [m3]. 5.4.3.1.13 A cofferdam, the centre part of
a cofferdam or another space below deck
5.4.3.1.8 The cargo tanks are to be in the cargo area may be arranged as a
separated by cofferdams of at least 0.60 service space, provided the bulkheads
[m] in width from the accommodation, bounding the service space extend
engine room and service spaces outside vertically to the bottom. This service space
the cargo area below deck or, if there are is only to be accessible from the deck.
no such accommodation, engine room and
service spaces, from the vessel’s ends. 5.4.3.1.14 The service space is to be
Where the cargo tanks are installed in a watertight with the exception of its access
hold space, a space of not less than 0.50 hatches and ventilation inlets.
[m] is to be provided between such tanks
and the end bulkheads of the hold space. 5.4.3.1.15 Where independent cargo
In this case an insulated end bulkhead tanks are used, or for double-hull
meeting the definition for Class “A-60” construction where the cargo tanks are
according to SOLAS 74 Ch II-2, Reg 3, is integrated in the vessel’s structure, the
deemed equivalent to a cofferdam. For space between the wall of the vessel and
pressure cargo tanks, the 0.50 [m] wall of the cargo tanks is to be not less
distance may be reduced to 0.20 [m]. than 0.6 [m]. The space between the
bottom of the vessel and the bottom of the
5.4.3.1.9 Hold spaces, cofferdams and cargo tanks is not to be less than 0.5 [m].
cargo tanks are to be capable of being The space may be reduced to 0.4 [m]
inspected. under the pump sumps. The vertical space
between the suction well of a cargo tank
5.4.3.1.10 All spaces in the cargo area are and the bottom structures is to be not less
to be capable of being ventilated. Means than 0.1 [m]. When a hull is constructed in
for checking their gas-free condition are to the cargo area as a double hull with
be provided. independent cargo tanks located in hold
5.4.3.1.11 The bulkheads bounding the spaces, the above values are applicable to
cargo tanks, cofferdams and hold spaces the double hull. If in this case the minimum
are to be watertight. The cargo tanks and values for the inspections of independent
the bulkheads bounding the cargo area tanks referred to in 5.4.3.1.17 are not
are to have no openings or penetrations feasible, it must be possible to remove the
below deck. The bulkhead between the cargo tanks easily for inspection.
engine room and the cofferdam or service 5.4.3.1.16 Where service spaces are
space in the cargo area or between the located in the cargo area under deck, they
engine room and a hold space may be are to be arranged so as to be easily
fitted with penetrations provided that they accessible and to permit persons wearing
conform to the provisions of 5.4.2.4.5 and protective clothing and breathing
5.4.2.4.6.1(if applicable). The bulkhead apparatus to safely operate the service
between the cargo tank and the cargo equipment contained therein. They are to
pump room below deck may be fitted with be designed so as to allow injured or
penetrations provided that they conform to unconscious personnel to be removed
the provisions of 5.4.2.4.6.2. The from such spaces without difficulty, if
bulkheads between the cargo tanks may necessary by means of fixed equipment.
be fitted with penetrations provided that
the loading and unloading pipes are fitted 5.4.3.1.17 Cofferdams, double-hull
with shut-off devices in the cargo tank from spaces, double bottoms, cargo tanks, hold
which they come. These pipes are to be spaces and other accessible spaces within
fitted at least 0.60 [m] above the bottom. the cargo area are to be arranged so that
The shut-off devices are to be operable they may be completely inspected and
from the deck. cleaned. The dimensions of openings
except for those of double hull spaces and
5.4.3.1.12 Double hull spaces and double double bottoms which do not have a wall
bottoms in the cargo area are to be adjoining the cargo tanks are to be
Longitudinal extent : At least 0.10 LOA, but not less than 5 [m]
Longitudinal extent: At least 0.10 LOA, but not less than 5 [m]
c) Any bulkhead within the damaged area is to be assumed damaged, which means that the
location of bulkheads is to be chosen to ensure that the vessel remains afloat after the flooding
of two or more adjacent compartments in the longitudinal direction.
Table 3: Permeability
a) a mark inside the tank indicating tank stop valves. It is to be possible to easily
the liquid level of 97% check the functioning of the sensors and
electric circuits or these are to be
b) a level gauge “intrinsically safe apparatus”.
c) a level alarm device which is 5.4.5.6 When the control elements of the
activated at the latest when a shut-off devices of the cargo tanks are
degree of filling of 90% is reached located in a control room, it is to be possible
d) a high level sensor for actuating to stop the loading pumps and read the level
the facility against overflowing gauges in the control room, and the visual
when a degree of filling of 97.5% is and audible warning given by the level alarm
reached device, the high level sensor referred to in
5.4.5.1 d) and the instruments for measuring
e) for Type N closed, an instrument the pressure and temperature of the cargo
for measuring the pressure of the is to be noticeable in the control room and
vapour phase inside the cargo tank on deck.
f) an instrument for measuring the 5.4.5.7 When refrigerated substances are
temperature of the cargo if in carried the opening pressure of the safety
column (9) of Table C of Chapter system is to be determined by the design of
3.2 of ADN a heating installation is the cargo tanks. In the event of the transport
required or if in column (20) a of substances that must be carried in a
possibility of heating the cargo is refrigerated state the opening pressure of
required or if a maximum the safety system is not to be less than 25
temperature is indicated. [kPa] greater than the maximum pressure
g) a connection for a closed-type or calculated according to 5.4.6.2.
partly closed-type sampling device, 5.4.5.8 High Level Sensor
and/or at least one sampling
opening as required in column (13) 5.4.5.8.1 The high level sensor referred in
of Table C of Chapter 3.2 of ADN. 5.4.5.1 d) above is to give a visual and
audible alarm on board and at the same
5.4.5.2 When the degree of filling in percent time actuate an electrical contact which in
is determined, an error of not more than the form of a binary signal interrupts the
0.5% is permitted. It is to be calculated on electric current loop provided and fed by
the basis of the total cargo tank capacity the shore facility against overflowing
including the expansion trunk. during loading operations. The signal is to
5.4.5.3 The level gauge is to allow readings be transmitted to the shore facility via a
watertight two-pin lug of a connecter
from the control position of the shut-off
devices of the particular cargo tank. The device in accordance with IEC 60309 for
direct current of 40 to 50 volts,
permissible maximum filling level of 95%
and 97%, as given in list of substances is to identification color white, position of the
be marked on each level gauge. Permanent nose 10 h. The plug is to be permanently
fitted to the vessel close to the shore
reading of the overpressure and vacuum is
to be possible from a location from which connections of the loading and unloading
loading or unloading operations may be piping.
interrupted. The permissible maximum 5.4.5.8.2 The high level sensor is also to
overpressure and vacuum is to be marked be capable of switching off the vessel’s
on each level gauge. Readings are to be own discharging pump.
possible in all weather conditions.
5.4.5.8.3 The high level sensor is to be
5.4.5.4 The level alarm device is to give a independent of the level alarm device, but
visual and audible warning on board when it may be connected to the level gauge.
actuated. The level alarm device is to be
independent of the level gauge. 5.4.5.8.4 During discharging by means of
the on-board pump, it is to be possible for
5.4.5.5 The visual and audible signals given the shore facility to switch it off. For this
by the level alarm device are to be clearly purpose, an independent intrinsically safe
distinguishable from those of the high level power line, fed by the vessel, is to be
sensor. The visual alarm is to be visible at switched off by the shore facility by means
each control position on deck of the cargo
5.4.6.2.9 For all cargo systems, the heat 5.4.6.4.1 When water-spraying is required
transmission coefficient as used for the in column (9) of Table C of Chapter 3.2 of
determination of the holding time is to be ADN, a water-spray system is to be
determined by calculation. Upon installed in the cargo area on deck for the
completion of the vessel, the correctness purpose of cooling the tops of cargo tanks
of the calculation is to be checked by by spraying water over the whole surface
means of a heat balance test. The so as to avoid safely the activation of the
calculation and test is to be performed high-velocity vent valve at 10 [kPa] or as
under supervision by IRS. The heat regulated.
transmission coefficient is to be 5.4.6.4.2 The spray nozzles are to be so
documented and kept on board. The heat installed that the entire cargo deck area is
transmission coefficient is to be verified at covered and the gases released are
every renewal of the certificate of precipitated safely. The system is to be
approval. capable of being put into operation from
5.4.6.3 Cargo heating system the wheelhouse and from the deck. Its
capacity is to be such that when all the
5.4.6.3.1 Boilers which are used for spray nozzles are in operation, the outflow
heating the cargo are to be fuelled with a is not less than 50 litres per square metre
liquid fuel having a flashpoint of more than of deck area and per hour.
55 °C. They are to be placed either in the
engine room or in another separate space 5.4.7 Pumps and piping
below deck and outside the cargo area, 5.4.7.1 Cargo pumps are to be capable of
which is accessible from the deck or from being shut down from the cargo area and
the engine room. from a position outside cargo area.
5.4.6.3.2 The cargo heating system is to 5.4.7.2 Piping for loading and unloading is to
be designed so that the cargo cannot be independent of any other piping of the
penetrate into the boiler in the case of a vessel.
leak in the heating coils. A cargo heating
system with artificial draught is to be 5.4.7.3 The piping for loading and unloading
ignited electrically. is to be arranged so that, after loading or
unloading operations, the liquid remaining in
5.4.6.3.3 The ventilation system of the these pipes may be safely removed and
engine room is to be designed taking into may flow either into the vessel’s cargo tanks
account the air required for the boiler. or the tanks ashore;
5.4.6.3.4 Where the cargo heating system 5.4.7.4 Piping for loading and unloading is to
is used during loading, unloading or gas- be clearly distinguishable from other piping.
freeing, the service space which contains
this system is to fully comply with the 5.4.7.5 Each shore connection of the
requirements of 5.4.9.3.7.1. This venting piping and shore connections of the
requirement does not apply to the inlets of piping for loading and unloading, through
the ventilation system. These inlets are to which the loading or unloading operation is
be located at a minimum distance of 2 [m] carried out, is to be fitted with a shut-off
from the cargo area and 6 [m] from the device. However, each shore connection is
openings of cargo tanks or residual cargo to be fitted with a blind flange when it is not
tanks, loading pumps situated on deck, in operation.
openings of high velocity vent valves, 5.4.7.6 Piping for loading and unloading and
pressure relief devices and shore
venting piping, is not to have flexible
connections of loading and unloading
connections fitted with sliding seals.
piping and must be located not less than 2
m above the deck. The requirements of 5.4.7.7 The stop valves or other shut-off
5.4.9.3.7.1 are not applicable to the devices of the piping for loading and
unloading of substances having a unloading are to indicate whether they are
flashpoint of 60 °C or more when the open or shut.
5.4.7.8 The piping for loading and unloading b) Gas formation during loading:
is to have, at the test pressure, the required multiply the largest loading flow by
elasticity, leakproofness and resistance to a factor of not less than 1.25
pressure.
c) Density of the vapour mixture of the
5.4.7.9 The piping for loading and unloading cargo based on 50% volume vapour
is to be fitted with pressure gauges at the
of 50% volume air;
outlet of the pumps. The permissible
maximum overpressure or vacuum is to be d) Loss of pressure through ventilation
indicated on each measuring device. pipes, valves and fittings. Account
Readings are to be possible in all weather will be taken of a 30% clogging of
conditions.
the mesh of the flame-arrester;
5.4.7.10 When piping for loading and
unloading are used for supplying the cargo e) Clocking pressure of the safety
tanks with washing or ballast water, the valves
suctions of these pipes are to be located
The permissible maximum loading and
within the cargo area but outside the cargo
tanks. Pumps for tank washing systems with unloading flows for each cargo tank or for
associated connections may be located each group of cargo tanks is to be given in
outside the cargo area, provided the an on-board instruction.
discharge side of the system is arranged in
5.4.7.13 Compressed air generated outside
such a way that the suction is not possible
the cargo area or wheelhouse can be used
through that part. A spring-loaded non-
in the cargo area subject to the installation
return valve is to be provided to prevent any
of a spring-loaded non-return valve to
gases from being expelled from the cargo
ensure that no gases can escape from the
area through the tank washing system.
cargo area through the compressed air
5.4.7.11 A non-return valve is to be fitted at system into accommodation or service
the junction between the water suction pipe spaces outside the cargo area.
and the cargo loading pipe.
5.4.7.14 If the vessel is carrying several
5.4.7.12 The permissible loading and dangerous substances liable to react
unloading flows are to be calculated. dangerously with each other, a separate
Calculations concern the permissible pump with its own piping for loading and
maximum loading and unloading flow for unloading is to be installed for each
each cargo tank or each group of cargo substance. The piping is not to pass through
tanks, taking into account the design of the a cargo tank containing dangerous
ventilation system. These calculations are to substances with which the substance in
take into consideration the fact that in the question is liable to react.
event of an unforeseen cut-off of the vapour
5.4.7.15 Additional requirements for Type N
return piping of the shore facility, the safety
open vessel carrying substances having
devices of the cargo tanks will prevent
corrosive properties, Type Closed and Type
pressure in the cargo tanks from exceeding
N open with flame arrester
the following values:
5.4.7.15.1 Pumps and accessory loading
over-pressure: 115% of the
and unloading piping is to be located in the
opening pressure of the high-
cargo area
velocity vent valve;
5.4.7.15.2 Cargo pumps situated on deck
vacuum pressure: not more than are to be located not less than 6 [m] from
the construction vacuum pressure entrances to or openings of, the
but not exceeding 5 [kPa] (0.05 accommodation and service spaces
bar). outside the cargo area.
The main factors to be considered are the 5.4.7.15.3 No cargo piping is to be located
following: below deck, except those inside the cargo
tanks and inside the cargo pump-room;
a) Dimensions of the ventilation
system of the cargo tanks 5.4.7.15.4 The shore connections are to
be located not less than 6 [m] from the
5.5.9.3.2 and 5.5.9.3.3 are accepted in less than 0.50 [m] above the deck. This
cofferdams, double-hull spaces, double requirement need not be complied with if
bottoms, hold spaces and service spaces the wall of the superstructures facing the
below deck. When the vessel is only cargo area extends from one side of the
authorized to carry substances for which vessel to the other and has doors the sills
no antiexplosion protection is required in of which have a height of not less than
column (17) of Table C in Chapter 3.2 of 0.50 [m]. The height of this wall is not to be
ADN, cable penetration is permitted in the less than 2.00 [m]. In this case, the lower
hold spaces. edges of door-openings in the sidewalls of
superstructures and of coamings of
5.4.10 Inspection and Testing access hatches behind this wall are to
5.4.10.1 Pressure tests have a height of not less than 0.10 [m].
The sills of engine room doors and the
5.4.10.1.1 The cargo tanks, residual cargo coamings of its access hatches are to,
tanks, cofferdams, piping of loading and however, always have a height of not less
unloading, with the exception of discharge than 0.50 [m].
hoses are subjected to initial tests before
being put into service and thereafter at 5.5.2.1.3 In the cargo area, the lower
prescribed intervals. edges of door-openings in the sidewalls of
superstructures are to have a height of not
5.4.10.1.2 Where a heating system is less than 0.50 [m] above the deck and the
provided inside the cargo tanks, the sills of hatches and ventilation openings of
heating coils are to be subjected to initial premises located under the deck are to
tests before being put into service and have a height of not less than 0.50 [m]
thereafter at prescribed intervals above the deck. This requirement does not
5.4.10.1.3 The test pressure for the cargo apply to access openings to double-hull
and double bottom spaces.
tanks and residual cargo tanks is not to be
less than 1.3 times the design pressure. 5.5.2.1.4 The bulwarks, foot-rails, etc. are
The test pressure for the cofferdams and to be provided with sufficiently large
open cargo tanks is to be not less than 10 openings which are located directly above
[kPa] gauge pressure. the deck.
5.4.10.1.4 The test pressure for piping for 5.5.2.2 Ventilation
loading and unloading is to be not less
than 1000 [kPa] gauge pressure. 5.5.2.2.1 Each hold space is to have two
openings, the dimensions and location of
5.4.10.1.5 The maximum intervals for the which are to be such as to permit effective
periodic teats is to be 11 years. ventilation of any part of the hold space. If
5.5 Requirements for Type C Tankers there are no such openings, it is to be
possible to fill the hold spaces with inert
5.5.1 General gas or dry air.
5.5.1.1 Application 5.5.2.2.2 Double-hull spaces and double
bottoms within the cargo area which are
5.5.1.1.1 Requirements of this subsection
not arranged for being filled with ballast
are applicable to Type C tankers.
water, hold spaces and cofferdams are to
5.5.2 Arrangement be provided with ventilation systems.
5.5.2.1 Protection against the penetration of 5.5.2.2.3 Any service spaces located in
gases the cargo area below deck are to be
provided with a system of forced
5.5.2.1.1 The vessel is to be designed so ventilation with sufficient power for
as to prevent gases from penetrating into ensuring at least 20 changes of air per
the accommodation and the service hour based on the volume of the space.
spaces. The ventilation exhaust ducts are to
5.5.2.1.2 Outside the cargo area, the extend down to 50 [mm] above the bottom
lower edges of door-openings in the of the service space. The air is to be
sidewalls of superstructures and the supplied through a duct at the top of the
coamings of access hatches to under- service space. The air inlets are to be
deck spaces are to have a height of not located not less than 2 [m] above the deck,
at a distance of not less than 2 [m] from the cargo area. Doors opening outward
tank openings and 6 [m] from the outlets of and not located in a recess the depth of
safety valves. The extension pipes, which which is at least equal to the width of the
may be necessary, may be of the hinged doors are to have their hinges face the
type. cargo area.
5.5.2.2.4 Ventilation of accommodation 5.5.2.4.3 Entrances from the deck and
and service spaces is to be possible. openings of spaces facing the weather are
to be capable of being closed. The
5.5.2.2.5 Ventilators used in the cargo following instruction is to be displayed at
area are to be designed so that no sparks the entrance of such spaces:
may be emitted on contact of the impeller
blades with the housing and no static
electricity may be generated. DO NOT OPEN DURING LOADING,
5.5.2.2.6 Notice boards are to be fitted at UNLOADING AND DEGASSING
the ventilation inlets indicating the WITHOUT PERMISSION.
conditions when they are to be closed. Any
ventilation inlets of accommodation and CLOSE IMMEDIATELY.
service spaces leading outside are to be
fitted with fire flaps. Such ventilation inlets 5.5.2.4.4 Entrances and windows of
are to be located not less than 2 [m] from superstructures and accommodation
the cargo area. Ventilation inlets of service spaces which can be opened as well as
spaces in the cargo area may be located other openings of these spaces are to be
within such area. located not less than 2 [m] from the cargo
area. No wheelhouse doors and windows
5.5.2.2.7 The flame-arresters prescribed are to be located within 2 [m] from the
in 5.5.2.6.4, 5.5.3.2.5, 5.5.3.2.6, 5.5.3.2.7, cargo area, except where there is no direct
5.5.8.4, 5.5.8.5, 5.5.8.6 and 5.5.8.7 are to connection between the wheelhouse and
be of a type approved for this purpose by the accommodation.
IRS.
5.5.2.4.5 Penetrations
5.5.2.3 Engine rooms
5.5.2.4.5.1 Driving shafts of the bilge or
5.5.2.3.1 Internal combustion engines for ballast pumps in the cargo area may
the vessel’s propulsion as well as internal penetrate through the bulkhead between
combustion engines for auxiliary the service space and the engine room,
machinery is to be located outside the provided the arrangement of the service
cargo area. Entrances and other openings space is in compliance with 5.5.3.1.16,
of engine rooms are to be at a distance of 5.5.3.1.17, 5.5.3.1.18 and 5.5.3.1.19.
not less than 2 [m] from the cargo area.
The engine rooms are to be accessible 5.5.2.4.5.2 The penetration of the shaft
from the deck; the entrances are not to through the bulkhead is to be gastight
face the cargo area. and is to be approved by IRS.
5.5.2.3.2 Where the doors are not located 5.5.2.4.5.3 The necessary operating
in a recess whose depth is at least equal instructions are to be displayed.
to the door width, the hinges are to face
the cargo area. 5.5.2.4.5.4 Penetrations through the
bulkhead between the engine room and
5.5.2.4 Accommodation and service spaces the service space in the cargo area and
the bulkhead between the engine room
5.5.2.4.1 Accommodation spaces and the and the hold spaces may be provided for
wheelhouse are to be located outside the electrical cables, hydraulic and piping for
cargo area forward of the fore vertical measuring, control and alarm systems,
plane or abaft the aft vertical plane provided that the penetration are
bounding the part of the cargo area below approved by IRS. The penetrations are
deck. Windows of the wheelhouse which to be gastight. Penetrations through a
are located not less than 1 [m] above the bulkhead with an “A-60” fire protection
bottom of the wheelhouse may tilt forward. insulation according to SOLAS 74,
5.5.2.4.2 Entrances to spaces and Chapter II-2, Regulation 3, are to have
openings of superstructures are not to face an equivalent fire protection.
5.5.2.4.5.5 Pipes may penetrate the suction side in the cargo pump-
bulkhead between the engine room and room immediately at the
the service space in the cargo area bulkhead. The necessary
provided that these are pipes between operation of the control devices in
the mechanical equipment in the engine the pump-room, starting of
room and the service space which do not pumps and necessary control of
have any openings within the service the liquid flow rate is to be
space and which are provided with shut- effected from the deck;
off devices at the bulkhead in the engine
room. the bilge of the cargo pump-room
is equipped with a gauging
5.5.2.4.5.6 Notwithstanding 5.5.3.1.14, device for measuring the filling
pipes from the engine room may pass level which activates a visual and
through the service space in the cargo audible alarm in the wheelhouse
area or a cofferdam or a hold space or a when liquid is accumulating in the
double-hull space to the outside cargo pump-room bilge;
provided that within the service space or
cofferdam or hold space or doublehull the cargo pump-room is provided
space they are of the thick-walled type with a permanent gas–detection
and have no flanges or openings. system which automatically
indicates the presence of
5.5.2.4.5.7 Where a driving shaft of explosive gases or lack of oxygen
auxiliary machinery penetrates through a by means of direct-measuring
wall located above the deck the sensors and which actuates a
penetration is to be gastight. visual and audible alarm when
the gas concentration has
5.5.2.4.6 A service space located within
reached 20% of the lower
the cargo area below deck is not to be
explosive limit. The sensors of
used as a cargo pump room for the loading
this system are to be placed at
and unloading system, except where:
suitable positions at the bottom
the pump room is separated from and directly below the deck.
the engine room or from service Measurement is to be
spaces outside the cargo area by continuous. The audible and
a cofferdam or a bulkhead with visual alarms are installed in the
an “A-60” fire protection wheelhouse and in the cargo
insulation according to SOLAS pumproom and, when the alarm
74, Chapter II-2, Regulation 3, or is actuated, the loading and
by a service space or a hold unloading system is shut down.
space; Failure of the gas detection
system is to be immediately
the “A-60” bulkhead required signalled in the wheelhouse and
above does not include on deck by means of audible and
penetrations referred to in visual alarms;
6.5.7.5.1;
the ventilation system prescribed
ventilation exhaust outlets are in 5.5.2.2.3 has a capacity of not
located not less than 6 [m] from less than 30 changes of air per
entrances and openings of the hour based on the total volume of
accommodation and service the service space.
spaces outside the cargo area;
5.5.2.4.7 The following instruction is to be
the access hatches and displayed at the entrance of the cargo
ventilation inlets can be closed pump-room:
from the outside;
BEFORE ENTERING THE CARGO
all piping for loading and PUMP-ROOM CHECK WHETHER
unloading as well as those of
stripping systems are provided IT IS FREE FROM GASES AND
with shut-off devices at the pump CONTAINS SUFFICIENT OXYGEN.
5.5.2.5.4 The premises to be inerted are to 5.5.2.7.2 Ventilation inlets of the engine
be equipped with connections for room, and when the engines do not take in
introducing the inert gas and monitoring air directly from the engine room, air
systems so as to ensure the correct intakes of the engines are to be located not
atmosphere on a permanent basis. less than 2 [m] from the cargo area.
oil fuel tanks, provided their depth is not bottoms which do not have a
less than 0.6 [m]. Oil fuel pipes and common boundary wall with
openings of such tanks are not permitted the cargo tanks;
in the hold space.
cofferdams, double-hull
5.5.2.8.2 The open ends of the air pipes of spaces, hold spaces and
all oil fuel tanks are to extend to not less double bottoms where
than 0.5 [m] above the open deck. Their ballasting is carried out using
open ends and the open ends of overflow the piping of the fire-fighting
pipes leading to the deck are to be fitted system in the cargo area and
with a protective device consisting of a bilge pumping is performed
gauze diaphragm or a perforated plate. using eductors.
5.5.2.9 Exhaust pipes 5.5.2.10.2 Where the double bottom is
used as a liquid oil fuel tank, it is not to be
5.5.2.9.1 Exhausts are to be evacuated
connected to the bilge piping system.
from the vessel into the open air either
upwards through an exhaust pipe or 5.5.2.10.3 Where the ballast pump is
through the shell plating. The exhaust installed in the cargo area, the standpipe
outlet is to be located not less than 2 [m] and its outboard connection for suction of
from the cargo area. The exhaust pipes of ballast water is to be located within the
engines are to be arranged so that the cargo area but outside the cargo tanks.
exhausts are led away from the vessel.
The exhaust pipes are not to be located 5.5.2.10.4 A cargo pump-room below deck
within the cargo area. is to be capable of being drained in an
emergency by an installation located in the
5.5.2.9.2 Exhaust pipes are to be provided cargo area and independent from any
with a device preventing the escape of other installation. This installation is to be
sparks, e.g. spark arresters. provided outside the cargo pump-room.
5.5.2.10 Bilge pumping and ballasting 5.5.3 Cargo Containment
arrangements
5.5.3.1 Hold spaces and cargo tanks
5.5.2.10.1 Bilge and ballast pumps for
spaces within the cargo area are to be 5.5.3.1.1 The maximum permissible
installed within such area. capacity of a cargo tank is to be
determined in accordance with the
This provision does not apply to: following table:
double-hull spaces and double
where:
LOA X BOA X D : Product of the tank vessel main dimensions, in [m3]
LOA : overall length of the hull, in [m]
BOA : extreme breadth in [m]
D : Shortest vertical distance between the top of the keel and the lowest point of the deck
at the side of the vessel; (moulded depth) within the cargo area in [m].
This provision does not apply to 5.5.3.1.10 A local recess in the cargo
vessels with independent built–in deck, contained on all sides, with a depth
cylindrical tanks having a length to greater than 0.1 [m], designed to house
diameter ratio ≤ 7. the loading and unloading pump, is
permitted if it fulfils the following
5.5.3.1.6 In the cargo area (except conditions:
cofferdams) the vessel is to be designed
as a flush–deck double-hull vessel, with The recess is not to be greater than
double-hull spaces and double bottoms, 1 [m] in depth;
but without a trunk; Cargo tanks
Longitudinal extent: At least 0.10 LOA, but not less than 5 [m]
Transverse extent : 0.79 [m] inboard from the vessel’s side at right angles to
the centerline at the level corresponding to the maximum
draught , or when applicable, the distance allowed by sec
Chapter 9, 9.3.4 of ADN, reduced by 0.01[m]
Longitudinal extent: At least 0.10 LOA, but not less than 5 [m]
Vertical extent : From the base 0.59[m] upwards, the sump excepted
Table 5: Permeability
Engine Room 85%
Accommodation 95%
Double Bottom, Oil Fuel Tanks, Ballast 0% or 95%
Tanks, etc. depending on whether,
according to their function, they have to
be assumed as full or empty for vessel
floating at the maximum permissible
draft
5.5.5.4 The level alarm device is to give a electrical circuits actuating the rapid closing
visual and audible warning on board when device are to be secured according to the
actuated. The level alarm device is to be quiescent current principle or other
independent of the level gauge. appropriate error detection measures. The
state of operation of electrical circuits which
5.5.5.5 High Level Sensors cannot be controlled using the quiescent
5.5.5.5.1 The high level sensor referred to current principle are to be capable of being
in 5.5.5.1d) above is to give a visual and easily checked. It is to be possible to actuate
audible alarm on board and at the same the rapid closing device independently of the
time actuate an electrical contact which in electrical signal. The rapid closing device is
the form of a binary signal interrupts the to actuate a visual and audible alarm on
electric current loop provided and fed by board.
the shore facility, thus initiating measures 5.5.5.7 The visual and audible signals
at the shore facility against overflowing given by the level alarm device are to be
during loading operations. The signal is to clearly distinguishable from those of the high
be transmitted to the shore facility via a level sensor. The visual alarm is to be visible
watertight two–pin plug of a connector at each control position on deck of the cargo
device in accordance with standard EN tank stop valves. It is to be possible to easily
60309 for direct current of 40 to 50 volts, check the functioning of the sensors and
identification colour white, position of the electric circuits or these are to be
nose 10 h. The plug is to be permanently “intrinsically safe apparatus”.
fitted to the vessel close to the shore
connections of the loading and unloading 5.5.5.8 Cargo tank pressure and
piping. temperature monitoring
5.5.5.5.2 The high level sensor is also to 5.5.5.8.1 When the pressure or
be capable of switching off the vessel’s temperature exceeds a set value,
own discharging pump. instruments for measuring the vacuum or
overpressure of the gaseous phase in the
5.5.5.5.3 The high level sensor is to be cargo tank or the temperature of the cargo,
independent of the level alarm device, but is to activate a visual and audible alarm in
it may be connected to the level gauge. the wheelhouse. When the wheelhouse is
5.5.5.5.4 During discharging by means of unoccupied the alarm is also to be
the on-board pump, it is to be possible for perceptible in a location occupied by a
the shore facility to switch it off. For this crew member.
purpose, an independent intrinsically safe 5.5.5.8.2 When the pressure exceeds the
power line, fed by the vessel, is to be set value during loading and unloading,
switched off by the shore facility by means the instrument for measuring the pressure
of an electrical contact. It is to be possible is to, by means of the plug referred to in
for the binary signal of the shore facility to 5.5.5.5 and 5.5.5.6 above, initiate
be transmitted via a watertight two–pole immediately an electrical contact which is
socket or a connector device in to put into effect measures to interrupt the
accordance with standard EN 60309, for loading or unloading operation. If the
direct current of 40 to 50 volts, vessel’s own discharge pump is used, it is
identification colour white, position of the to be switched off automatically. The
nose 10 h. This socket is to be instrument for measuring the overpressure
permanently fitted to the vessel close to or vacuum is to activate the alarm at latest
the shore connections of the unloading when an overpressure is reached equal to
piping. 1.15 times the opening pressure of the
5.5.5.6 Vessels which may be delivering pressure relief device, or a vacuum
products required for operation of vessels pressure equal to the construction vacuum
are to be equipped with a transhipment pressure but not exceeding 5 [kPa] (0.05
facility compatible with European standard bar). The maximum allowable temperature
EN 12827:1999 and a rapid closing device is indicated in column (20) of Table C of
enabling refuelling to be interrupted. It is to Chapter 3.2 of ADN. The sensors for the
be possible to actuate this rapid closing alarms mentioned in this paragraph may
device by means of an electrical signal from be connected to the alarm device of the
the overflow prevention system. The sensor.
5.5.5.8.3 When it is prescribed in column the safety valves, by one or more of the
(20) of Table C of Chapter 3.2 of ADN, the following means:
instrument for measuring the overpressure
of the gaseous phase is to activate a a) a system for the regulation of cargo
visible and audible alarm in the tank pressure using mechanical
wheelhouse when the overpressure refrigeration;
exceeds 40 [kPa] (0.4 bar) during the b) a system ensuring safety in the
voyage. When the wheelhouse is event of the heating or increase in
unoccupied, the alarm is also to be pressure of the cargo. The
perceptible in a location occupied by a insulation or the design pressure of
crew member. the cargo tank, or the combination
5.5.5.9 Where the control elements of the of these two elements, is to be
shut-off devices of the cargo tanks are such as to leave an adequate
located in a control room, it is to be possible margin for the operating period and
to stop the loading pumps and read the level the temperatures expected; in
gauges in the control room, and the visual each case the system is to be
and audible warning given by the level alarm deemed acceptable by IRS and is
device, the high level sensor referred to in to ensure safety for a minimum
5.5.5.1d) and the instruments for measuring time of three times the operation
the pressure and temperature of the cargo period;
are to be noticeable in the control room and 5.5.6.1.2 The systems prescribed in
on deck. Satisfactory monitoring of the 5.5.6.1.1 are to be constructed, installed
cargo area is to be ensured from the control and tested to the satisfaction of IRS. The
room. materials used in their construction are to
5.5.5.10 The vessel is to be so equipped be compatible with the cargoes to be
that loading or unloading operations can be carried. For normal service, the upper
interrupted by means of switches, i.e. the ambient design temperature limits are to
quick-action stop valve located on the be:
flexible vessel–to–shore connecting line Air: +45° C;
must be capable of being closed. The switch
is to be placed at two points on the vessel Water: +32° C.
(fore and aft). This provision applies only 5.5.6.1.3 The cargo storage system is to
when prescribed in column (20) of Table C
be capable of resisting the full vapour
of Chapter 3.2 of ADN. The interruption
pressure of the cargo at the upper limits of
system is to be designed according to the the ambient design temperatures,
quiescent current principle.
whatever the system adopted to deal with
5.5.5.11 When refrigerated substances are the boil-off gas. This requirement is
carried the opening pressure of the safety indicated by remark 37 in column (20) of
system is to be determined by the design of Table C of Chapter 3.2 of ADN.
the cargo tanks. In the event of the transport 5.5.6.2 Refrigeration system
of substances that must be carried in a
refrigerated state the opening pressure of 5.5.6.2.1 The refrigeration system referred
the safety system is to be not less than 25 to in 5.5.6.1.1a) is to be composed of one
[kPa] (0.25 bar) greater than the maximum or more units capable of keeping the
pressure calculated according to 5.5.6.2. pressure and temperature of the cargo at
the upper limits of the ambient design
5.5.6 Cargo Pressure and Temperature
temperatures at the prescribed level.
Control
Unless another means of regulating cargo
5.5.6.1 Requirements for maintenance of pressure and temperature deemed
cargo pressure and temperature satisfactory by IRS is provided, provision
is to be made for one or more stand-by
5.5.6.1.1 Unless the entire cargo system is units with an output at least equal to that
designed to resist the full effective vapour of the largest prescribed unit. A stand-by
pressure of the cargo at the upper limits of unit is to include a compressor, its engine,
the ambient design temperatures, the its control system and all necessary
pressure of the tanks is to be kept below accessories to enable it to operate
the permissible maximum set pressure of independently of the units normally used.
5.5.7.8 The flanges and stuffing boxes are 5.5.7.17 A non-return valve is to be fitted at
to be provided with a spray protection the junction between the water suction pipe
device. and the cargo loading pipe.
5.5.7.9 Piping for loading and unloading, 5.5.7.18 The permissible loading and
and venting piping, are not to have flexible unloading flows are to be calculated.
connections fitted with sliding seals. Calculations concern the permissible
maximum loading and unloading flow for
5.5.7.10 The distance referred to in 5.5.7.1 each cargo tank or each group of cargo
and 5.5.7.6 may be reduced to 3 [m] if a tanks, taking into account the design of the
transverse bulkhead complying with ventilation system. These calculations are to
5.5.2.1.2 is situated at the end of the cargo take into consideration the fact that in the
area. The openings are to be provided with event of an unforeseen cut–off of the vapour
doors. The following notice is to be return piping of the shore facility, the safety
displayed on the doors: devices of the cargo tanks will prevent
DO NOT OPEN DURING LOADING AND pressure in the cargo tanks from exceeding
UNLOADING WITHOUT the following values:
ensure that no gases can escape from the 5.5.8.5 Receptacles for residual products
cargo area through the compressed air are to be equipped with:
system into accommodation or service
spaces outside the cargo area. a connection enabling gases
released during filling to be
5.5.7.20 If the vessel is carrying several evacuated safely;
dangerous substances liable to react
dangerously with each other, a separate a possibility of indicating the
pump with its own piping for loading and degree of filling;
unloading is to be installed for each connections with shut-off devices,
substance. The piping is not to pass through for pipes and hose assemblies.
a cargo tank containing dangerous
substances with which the substance in 5.5.8.6 Receptacles for residual products
question is liable to react. are to be connected to the venting piping of
cargo tanks only for the time necessary to fill
5.5.8 Tanks and receptacles for residual them. During the filling of the receptacle,
products and receptacles for slops released gases are to be safely evacuated.
5.5.8.1 If vessels are provided with a tank 5.5.8.7 Receptacles for residual products
for residual products, it is to comply with the and receptacles for slops placed on the deck
provisions of 5.5.8.3, 5.5.8.4, 5.5.8.5, are to be located at a minimum distance
5.5.8.6 and 5.5.8.7.Receptacles for residual from the hull equal to one quarter of the
products and receptacles for slops are to be vessel’s breadth.
located only in the cargo area. During the
filling of the receptacles for residual 5.5.9 Requirements for Electrical Installations
products, means for collecting any leakage
is to be placed under the filling connections. 5.5.9.1 Documents concerning electrical
installations
5.5.8.2 Receptacles for slops are to be fire
resistant and are to be capable of being 5.5.9.1.1 In addition to the other required
closed with lids. The receptacles for slops documentations, the following documents
are to be marked and be easy to handle. are to be on board:
Section 6
Vessels Carrying Dangerous Cargoes in Gaseous State
(Type G Vessels)
6.4.2.1.2 Outside the cargo area, the 6.4.2.2.4 The ventilation exhaust ducts are
lower edges of door-openings in the to be located up to 50 [mm] above the
sidewalls of superstructures and the bottom of the service space. The air is to
coaming of access hatches to under-deck be supplied through a duct at the top of the
spaces are to have a height of not less service space. The air inlets are to be
than 0.50 [m] above the deck. This located not less than 2 [m] above the deck,
requirement need not be complied with if at a distance of not less than 2[m] from
the wall of the superstructures facing the tank openings and not less than 6 [m] from
cargo area extends from one side of the the outlets of safety valves. The extension
vessel to the other and has doors the sills pipes which may be necessary may be of
of which have a height of not less than the hinged type.
0.50 [m]. The height of this wall is not to be
less than 2 [m]. In this case, the lower 6.4.2.2.5 Ventilation of accommodation
edges of door-openings in the sidewalls of and service spaces is to be possible
superstructures and the coamings of 6.4.2.2.6 Ventilators used in the cargo
access hatches behind this wall are to area are to be designed so that no sparks
have a height of not less than 0.10 [m]. may be emitted on contact of the impeller
The sills of engine room doors and the blades with the housing and no static
coamings of its access hatches are to, electricity may be generated.
however, always have a height of not less
than 0.50 [m]. 6.4.2.2.7 Notice boards are to be fitted at
the ventilation inlets indicating the
6.4.2.1.3 In the cargo area, the lower conditions when they are to be closed. All
edges of door-openings in the sidewalls of ventilation inlets of accommodation and
superstructures are to have a height of not service spaces leading outside are to be
less than 0.50 [m] above the deck and the fitted with fire flaps. Such ventilation inlets
sills of hatches and ventilation openings of are to be located not less than 2 [m] from
premises located under the deck are to the cargo area. Ventilation inlets of service
have a height of not less than 0.50 [m] spaces in the cargo area may be located
above the deck. This requirement does not within such area.
apply to access openings to double-hull
and double bottom spaces. 6.4.2.3 Engine rooms
6.4.2.1.4 The bulwarks, foot-rails, etc are 6.4.2.3.1 Internal combustion engines for
to be provided with sufficiently large the vessel’s propulsion as well as internal
openings which are located directly above combustion engines for auxiliary
the deck. machinery are to be located outside the
cargo area. Entrances and other openings
6.4.2.2 Ventilation of engine rooms are to be at a distance of
6.4.2.2.1 Each hold space is to have two not less than 2 [m] from the cargo area.
openings. The dimensions and location of 6.4.2.3.2 The engine rooms are to be
these openings are to be such as to permit accessible from the deck; the entrances
effective ventilation of any part of the hold are not to face the cargo area. The hinges
space. If there are no such openings, it is are to face the cargo area when the doors
to be possible to fill the hold spaces with are not located in a recess whose depth is
inert gas or dry air. at least equal to the door width.
6.4.2.2.2 Double-hull spaces and double 6.4.2.4 Accommodation and Service
bottoms within the cargo area which are Spaces
not arranged for being filled with ballast
water, hold spaces and cofferdams, are to 6.4.2.4.1 Accommodation spaces and the
be provided with ventilation systems. wheelhouse are to be located outside the
cargo area forward of the fore vertical
6.4.2.2.3 Any service spaces located in plane or abaft the aft vertical plane
the cargo area below deck are to be bounding the part of cargo area below
provided with a system of forced deck. Windows of the wheelhouse which
ventilation with sufficient power for are located not less than 1 [m] above the
ensuring at least 20 changes of air per bottom of the wheelhouse may tilt forward.
hour based on the volume of the space.
6.4.2.6 Engines from the vessel into the open air either
upwards through an exhaust pipe or
6.4.2.6.1 Only internal combustion through the shell plating. The exhaust
engines running on fuel with a flashpoint of outlet is to be located not less than 2 [m]
more than 55 [°C] are allowed. This from the cargo area. The exhaust pipes of
provision does not apply to internal engines are to be arranged so that the
combustion engines which are part of exhausts are led away from the vessel.
propulsion and auxiliary systems. These The exhaust pipes are not to be located
systems are to meet the requirements of within the cargo area.
IRS Classification Note “Natural Gas
Fuelled Vessels for Coastal and Inland 6.4.2.8.2 Exhaust pipes of engines are to
Waters”. be provided with a device preventing the
escape of sparks, e.g. spark arresters.
6.4.2.6.2 Ventilation inlets of the engine
room and, when the engines do not take in 6.4.2.9 Bilge Pumping and Ballasting
air directly from the engine room, the air Arrangements
intakes of the engines are to be located not
less than 2 [m] from the cargo area. 6.4.2.9.1 Bilge and ballast pumps for
spaces within the cargo area are to be
6.4.2.6.3 Sparking is not to be possible installed within such area. This provision
within the cargo area. does not apply to:
6.4.2.6.4 The surface temperature of the double-hull spaces and double
outer parts of engines used during loading bottoms which do not have a
or unloading operations, as well as that of common boundary wall with the
their air inlets and exhaust ducts are not to cargo tanks;
exceed the allowable temperature
according to the temperature class of the cofferdams and hold spaces where
substances carried. This provision does ballasting is carried out using the
not apply to engines installed in service piping of the fire-fighting system in
spaces provided the provisions of the cargo area and bilge–pumping
6.4.8.3.7 are fully complied with. is performed using eductors.
6.4.2.6.5 The ventilation in the closed 6.4.2.9.2 Where the double bottom is used
engine room is to be designed so that, at as a liquid oil fuel tank, it is not to be
an ambient temperature of 20 [°C], the connected to the bilge piping system.
average temperature in the engine room 6.4.2.9.3 Where the ballast pump is
does not exceed 40 [°C]. installed in the cargo area, the standpipe
6.4.2.7 Oil Fuel Tanks and its outboard connection for suction of
ballast water is to be located within the
6.4.2.7.1 When the vessel is fitted with cargo area.
hold spaces and double bottoms, double
bottoms within the cargo area may be 6.4.2.9.4 It is to be possible for an under-
arranged as oil fuel tanks, provided their deck pump-room to be stripped in an
depth is not less than 0.6 [m]. Oil fuel pipes emergency using a system located in the
and openings of such tanks are not cargo area and independent of any other
permitted in the hold space. system. This stripping system is to be
located outside the pump-room.
6.4.2.7.2 Open ends of air pipes of all oil
fuel tanks are to extend to not less than 0.5 6.4.3 Cargo Containment
[m] above the open deck. The open ends 6.4.3.1 Hold Spaces and Cargo Tanks
and the open ends of overflow pipes
leading to the deck are to be fitted with a 6.4.3.1.1 The maximum permissible
protective device consisting of a gauze capacity of a cargo tank is to be
diaphragm or a perforated plate. determined in accordance with Table 6.
6.4.2.8 Exhaust Pipes where
6.4.2.8.1 Exhausts are to be evacuated
Where,
ht: Height, in m, of trunk (distance between trunk deck and main deck on trunk side
measured at L/2)
bt : Trunk breadth, in [m]
lt : Trunk length, in [m]
6.4.3.1.5.2.2 The side stringers and are to be suitably insulated to ensure that
the web frames are to have a height of the temperature of the vessel’s structure
not less than 10% of the depth, does not fall below the minimum allowable
however, not less than 0.30 [m]; design temperature. The insulation
material is to be resistant to flame spread.
6.4.3.1.5.2.3 The side stringers and
web frames are to be fitted with a face 6.4.3.1.10 The hold spaces are to be
plate made of flat steel and having a separated from the accommodation,
cross-section of not less than that of engine rooms and service spaces outside
7.5 [cm2] and 15 [cm2], respectively; the cargo area below deck by bulkheads
provided with a Class A-60 fire protection
6.4.3.1.5.2.4 The distance between insulation according to SOLAS 74,
the sideplating of the vessel and the Chapter II-2, Regulation 3. A space of not
cargo tanks are to be not less than 0.80 less than 0.20 [m] is to be provided
[m]and between the bottom and the between the cargo tanks and the tank
cargo tanks not less than 0.60 [m]. The bulkheads of the tank spaces. Where the
depth below the suction wells may be cargo holds have plane end bulkheads,
reduced to 0.50 [m]; this space is not to be less than 0.50[m].
6.4.3.1.5.2.5 The lateral distance 6.4.3.1.11 The hold spaces and cargo
between the suction well of the cargo tanks are to be capable of being
tanks and the bottom structure is to be supported.
not less than 0.10 [m];
6.4.3.1.12 All spaces in the cargo region
6.4.3.1.5.2.6 The cargo tank are to be capable of being ventilated.
supports and fastenings are to extend Means for checking their gas free
not less than 10° below the horizontal condition are to be provided.
centreline of the cargo tanks.
6.4.3.1.13 The bulkheads bounding the
Note 1) : Alternatively, for a different cargo tanks, cofferdams and hold spaces
design of the hull in the cargo area, are to be watertight. The cargo tanks and
proof is to be submitted by way of the bulkheads bounding the cargo area
calculations that in the event of a are to have no openings or penetrations
lateral collision with another vessel below deck. The bulkhead between the
having a straight bow, an energy of engine room and the service spaces within
22 [MJ] can be absorbed without any the cargo area or between the engine
rupture of the cargo tanks and the room and a hold space may be fitted with
piping leading to the cargo tanks. penetrations provided that they conform to
Alternative construction in the provisions of 6.4.2.4.5
accordance with Chapter 9, 9.3.4 of
ADN are acceptable. 6.4.3.1.14 Double-hull spaces and double
bottoms in the cargo area are to be
6.4.3.1.6 The cargo tanks are to be fixed arranged for being filled with ballast water
so that they cannot float. only. Double bottoms may, however, be
6.4.3.1.7 The capacity of suction well is to used as fuel tanks, provided they comply
be limited to not more than 0.10 [m3]. For with the requirements of 6.4.2.7.
pressure cargo tanks, however, the 6.4.3.1.15 A space in the cargo area below
capacity of a suction well may be of 0.20 deck may be arranged as a service space,
[m3]. provided that the bulkhead bounding the
6.4.3.1.8 Side-struts linking or supporting service space extends vertically to the
the load-bearing components of the sides bottom and the bulkhead not facing the
of the vessel with the load-bearing cargo area extends from one side of the
components of the longitudinal walls of vessel to the other in one frame plane.
cargo tanks and side-struts linking the This service space is only to be accessible
load-bearing components of the vessel’s from the deck.
bottom with the tank bottom are not to be 6.4.3.1.16 The service space is to be
provided. watertight with the exception of its access
6.4.3.1.9 Cargo tanks intended to contain hatches and ventilation inlets.
products at a temperature below -10 [°C]
vessel, the vessel is to comply with the more than 0.7B in width, proof is to be
intact and damage stability requirements. submitted that the following stability
Intermediate stages during operations are requirements have been complied with:
also to be taken into consideration. The
proof of sufficient stability is to be shown a) In the positive area of the righting
for every operating, loading and ballast lever curve up to immersion of the
condition in the stability booklet, to be first non-watertight opening,
approved. If it is unpractical to pre- righting lever(GZ) is not to be less
calculate the operating, loading and than 0.1 [m]
ballast conditions, an approved loading b) The surface of the positive area of
instrument is to be installed and used the righting lever curve up to
which contains the contents of the stability immersion of the first non-
booklet. watertight opening and in any
6.4.4.1.4 Floatability after damage is to be event up to an angle of heel ≤27˚ is
proved for the most unfavorable loading not to be less than 0.024 [m rad]
condition. For this purpose, calculated c) The metacentric height (GM) is not
proof of sufficient stability is to be to be less than 0.1 [m]
established for critical intermediate stages
of flooding and for the final stage of These conditions are to be met bearing
flooding. in mind the influence of all free surface
in tanks for all stages of loading and
6.4.4.2 Intact Stability unloading.
6.4.4.2.1 The requirements for intact 6.4.4.2.3 The more stringent requirement
stability resulting from the damage stability of 6.4.4.2.1 and 6.4.4.2.2 is to be applied
calculation is to be fully complied with. to the vessel.
6.4.4.2.2 For vessels with cargo tanks of
a) a level gauge;
6.4.4.3.5 If openings through which
undamaged compartments may b) a level alarm device which is
additionally become flooded are capable activated at the latest when a
of being closed watertight, the closing degree of filling of 86% is reached;
appliances are to be marked accordingly. c) a high level sensor for actuating
6.4.4.3.6 Where cross- or down-flooding the facility against overflowing
openings are provided for reduction of when a degree of filling of 97.5% is
unsymmetrical flooding, the time of reached;
equalization is not to exceed 15 min, d) an instrument for measuring the
provided during the intermediate stages of pressure of the gas phase inside
flooding sufficient stability has been the cargo tank;
proved.
e) an instrument for measuring the
6.4.5 Safety and Control Installations temperature of the cargo;
6.4.5.1 Cargo tanks are to be provided with f) a connection for a closed-type
the following equipment: sampling device.
6.4.5.2 When the degree of filling in percent in 6.4.5.5.1 above. The socket is to be
is determined, an error of not more than permanently fitted to the vessel close to
0.5% is permitted. It is to be calculated on the shore connections of the loading and
the basis of the total cargo tank capacity unloading piping.
including the expansion trunk.
6.4.5.6 The visual and audible signals given
6.4.5.3 The level gauge is to allow readings by the level alarm device are to be clearly
from the control position of the shut-off distinguishable from those of the high level
devices of the particular cargo tank. The sensor. The visual alarm is to be visible at
permissible maximum filling level of 91%, each control position on deck of the cargo
95% and 97%, as given in list of substances tank stop valves. It is to be possible to easily
is to be marked on each level gauge. check the functioning of the sensors and
Permanent reading of the overpressure and electric circuits or these are to be of the “fail
vacuum is to be possible from a location safe” design.
from which loading or unloading operations
may be interrupted. The permissible 6.4.5.7 When the pressure or the
maximum overpressure and vacuum is to be temperature exceeds a set value, the
marked on each level gauge. Readings are instruments for measuring the pressure and
to be possible in all weather conditions. temperature of the cargo is to activate an
audible and visible alarm in the wheelhouse.
6.4.5.4 The level alarm device is to give a When the wheelhouse is unoccupied, the
visual and audible warning on board when alarm is also to be audible in a location
actuated. The level alarm device is to be occupied by a crew member.
independent of the level gauge.
6.4.5.8 When the pressure exceeds a set
6.4.5.5 High Level Sensor value during loading or unloading, the
instrument for measuring the pressure is to
6.4.5.5.1 The high level sensor referred in simultaneously initiate an electrical contact
6.4.5.1 c) above is to give a visual and which, by means of the plug referred to in
audible alarm on board and at the same 6.4.5.5 above, enables measures to be
time actuate an electrical contact which in taken to interrupt the loading and unloading
the form of a binary signal interrupts the operation. If the vessel’s own discharge
electric current loop provided and fed by pump is used, it is to be switched off
the shore facility against overflowing automatically. The sensors for the alarms
during loading operations. The signal is to referred to above may be connected to the
be transmitted to the shore facility via a alarm installation.
watertight two-pin lug of a connecter
device in accordance with IEC 60309 for 6.4.5.9 When the control elements of the
direct current of 40 to 50 volts, shut-off devices of the cargo tanks are
identification color white, position of the located in a control room, it is to be possible
nose 10 h. The plug is to be permanently to stop the loading pumps and read the level
fitted to the vessel close to the shore gauges in the control room, and the visual
connections of the loading and unloading and audible warning given by the level alarm
piping. device, the high level sensor referred to in
6.4.5.1 c) and the instruments for measuring
6.4.5.5.2 The high level sensor is also to the pressure and temperature of the cargo
be capable of switching off the vessel’s is to be noticeable in the control room and
own discharging pump. on deck. Satisfactory monitoring of the
6.4.5.5.3 The high level sensor is to be cargo is to be ensured from the control
independent of the level alarm device, but room.
it may be connected to the level gauge. 6.4.5.10 The vessel is to be so equipped
6.4.5.5.4 During discharging by means of that loading or unloading operations can be
the on-board pump, it is to be possible for interrupted by means of switches, i.e. the
the shore facility to switch it off. For this quick-action stop valve located on the
purpose, an independent intrinsically safe flexible vessel-to-shore connecting line is to
power line, fed by the vessel, is to be be capable of being closed. The switches
switched off by the shore facility by means are to be placed at two pints on the vessel
of an electrical contact. The signal is to be (fore and aft). The interruption systems are
transmitted via arrangements as indicated to be designed according to the quiescent
current principle.
6.4.5.12.1 Drip trays are to be installed 6.4.6.1.1 Unless the entire cargo system is
under the shore connections of the piping designed to resist the full effective vapour
for loading and unloading through which pressure of the cargo at the upper limits of
the loading and unloading operation is to the ambient design temperatures, the
be carried out. They are to be made of pressure of the tanks is to be kept below
materials which are able to resist the the permissible maximum set pressure of
temperature of the cargo and be insulated the safety valves, by one or more of the
from the deck. The drip trays are to have a following means:
sufficient volume and an overboard drain. a) a system for the regulation of cargo
6.4.5.12.2 A water spray system to cover: tank pressure using mechanical
refrigeration;
exposed cargo tank
b) a system ensuring safety in the
domes and exposed parts
event of the heating or increase in
of cargo tanks;
pressure of the cargo. The
exposed on-deck storage insulation or the design pressure of
vessels for flammable or the cargo tank, or the combination
toxic products; of these two elements, is to be
such as to leave an adequate
parts of the cargo deck margin for the operating period and
area where a leakage may the temperatures expected; in
occur. each case the system is to be
The capacity of the water spray acceptable by IRS and is to ensure
system is to be such that when safety for a minimum time of three
all spray nozzles are in times the operation period;
operation, the outflow is of 300 c) when the LNG is used as fuel, a
[lit/m2] of cargo deck area per system for the regulation of cargo
hour. The system is to be tank pressure whereby the boil-off
capable of being put into vapours are utilized as fuel;
operation from the wheelhouse
and from the deck; d) any other system, subject to
special consideration
6.4.5.12.3 A water film around the shore
connection of the piping for loading and 6.4.6.1.2 The systems prescribed in
unloading in use to protect the deck and 6.4.6.1.1 are to be constructed, installed
the shipside in way of the shore and tested to the satisfaction of IRS. The
connection of the piping for loading and materials used in their construction are to
unloading in use during connecting and be compatible with the cargoes to be
disconnecting the loading arm or hose. carried. For normal service, the upper
The water film is to have sufficient ambient design temperature limits are:
capacity. The system is to be capable of air: +45° C;
being put into operation from the wheel
house and from the deck. water: +32° C.
6.4.6.2.9 For all cargo systems, the heat 6.4.7.2.3 The piping for loading and
transmission coefficient as used for the unloading on deck, the venting piping with
determination of the holding time are to be the exception of the shore connections but
determined by calculation. Upon including the safety valves, and the valves
completion of the vessel, the correctness are to be located within the longitudinal
of the calculation is to be checked by line formed by the outer boundaries of the
means of a heat balance test. The domes and not less than one quarter of the
calculation and test is to be performed vessel’s breadth from the outer shell. This
under supervision of IRS. The heat requirement does not apply to the relief
transmission coefficient is to be pipes situated behind the safety valves. If
documented and kept on board. The heat there is, however, only one dome
transmission coefficient is to be verified at athwartships, these pipes and their valves
every renewal of the certificate of are to be located at a distance not less
approval. than 2.7 [m] from the shell. Where cargo
tanks are placed side by side, all the
6.4.6.3 Water Spray System connections to the domes are to be
located on the inner side of the domes.
6.4.6.3.1 When water-spraying is required The external connections may be located
in column (9) of Table C of Chapter 3.2 of on the fore and aft centre line of the dome.
ADN a water-spray system is to be The shut-off devices is to be located
installed in the cargo area on deck for the directly at the dome or as close as possible
purpose of reducing gases given off by the to it. The shut-off devices of the loading
cargo by spraying water. The system is to and unloading piping are to be duplicated,
be fitted with a connection device for one of the devices being constituted by a
supply from the shore. The spray nozzles remote-controlled quick-action stop
are to be so installed that released gases device. When the inside diameter of a
are precipitated safely. The system is to be shut-off device is less than 50 [mm] this
capable of being put into operation from device may be regarded as a safety device
the wheelhouse and from the deck. The against bursts in the piping.
capacity of the water-spray system is to be
such that when all the spray nozzles are in 6.4.7.2.4 The shore connections are to be
operation, the outflow is of 50 [lit/m2] of located not less than 6 [m] from the
cargo deck area and per hour. entrances to or openings of, the
accommodation and service spaces
6.4.7 Pumps and Piping outside the cargo area.
6.4.7.1 Pumps, compressors and accessory Each shore connection of the venting piping
loading and unloading piping are to be and shore connections of the piping for
placed in the cargo area. Cargo pumps and loading and unloading, through which the
compressors are to be capable of being shut loading or unloading operation is carried out,
down from the cargo area and, in addition,
from a position outside the cargo area.
is to be fitted with a shut‐off device and a
Cargo pumps and compressors situated on quick‐action stop valve. However, each shore
deck are to be located not less than 6 [m] connection is to be fitted with a blind flange
from entrances to, or openings of, the when it is not in operation.
accommodation and service spaces outside
the cargo area.
6.4.7.6 The piping for loading and unloading active cathodic corrosion
are to have, at the test pressure, the protection;
required elasticity, leak proofness and
local installations outside the
resistance to pressure.
cargo area (e.g. connections of
6.4.7.7 The piping for unloading is to be starters of diesel engines);
fitted with pressure gauges at the inlet and
outlet of the pump. Reading of the pressure the device for checking the
gauges is to be possible from the control insulation level referred to in
6.4.8.2.2 below:
6.4.8.4.3 Independent cargo tanks are to design having conductors with a cross-
be earthed. section of not less than 1.5 [mm2] are to be
used. These cables are to be as short as
6.4.8.4.4 Receptacles for residual possible and installed so that damage is
products are to be capable of being not likely to occur.
earthed.
6.4.8.5.6 The cables required for the
6.4.8.5 Electrical Cables electrical equipment referred to in
6.4.8.5.1 All cables in the cargo area are 6.4.8.3.2 and 6.4.8.3.3 are accepted in
to have a metallic sheath. cofferdams, double-hull spaces, double
bottoms, hold spaces and service spaces
6.4.8.5.2 Cables and sockets in the cargo below deck.
area are to be protected against
mechanical damage. 6.4.9 Inspection and Testing
Section 7
Fire Safety Requirements for Tankers Carrying Dangerous Goods
space to be protected. The control lines 7.2.2.6.2 The alarm device is to be set off
located in the space to be protected are to automatically as soon as the fire-
be so designed as to remain capable of extinguishing system is first activated. The
operating in the event of a fire for a alarm device is to function for an
minimum of 30 minutes. The electrical appropriate period of time before the
installations are deemed to meet this extinguishing agent is released; it is not to
requirement if they conform to the IEC be possible to turn it off.
60331–21:1999 standard. When the
triggering devices are so placed as not to 7.2.2.6.3 Alarm signals are to be clearly
be visible, the component concealing them visible in the spaces to be protected and
are to carry the “Fire-fighting system” their access points and be clearly audible
symbol, each side being not less than 10 under operating conditions corresponding
[cm] in length, with the following text in red to the highest possible sound level. It is to
letters on a white ground: be possible to distinguish them clearly
from all other sound and visual signals in
FIRE-EXTINGUISHING SYSTEM the space to be protected.
7.2.2.5.4 If the fire-extinguishing system is 7.2.2.6.4 Sound alarms are to also be
intended to protect several spaces, it is to clearly audible in adjoining spaces, with
comprise a separate and clearly–marked the communicating doors shut, and under
triggering device for each space. operating conditions corresponding to the
highest possible sound level.
7.2.2.5.5 The instructions are to be posted
alongside all triggering devices and are to 7.2.2.6.5 If the alarm device is not
be clearly visible and indelible. The intrinsically protected against short
instructions are to be in a language the circuits, broken wires and drops in voltage,
master can read and understand. They are it is to be possible to monitor its operation.
to include information concerning:
7.2.2.6.6 A sign with the following text in
a) the activation of the fire- red letters on a white background is to be
extinguishing system; clearly posted at the entrance to any space
the extinguishing agent may reach:
b) the need to ensure that all persons
have left the space to be protected; WARNING, FIRE-EXTINGUISHING
SYSTEM!
c) The correct behaviour of the crew
in the event of activation and when LEAVE THIS SPACE IMMEDIATELY
accessing the space to be WHEN THE … (DESCRIPTION) ALARM
protected following activation or IS ACTIVATED!
diffusion, in particular in respect of
the possible presence of 7.2.2.7 Pressurised tanks, fittings and
dangerous substances; piping
7.2.2.7.1 Pressurised tanks, fittings and
piping are to conform to the requirements
d) the correct behaviour of the crew in of the competent authority.
the event of the failure of the fire
extinguishing system to function 7.2.2.7.2 Pressurised tanks are to be
properly. installed in accordance with the
manufacturer’s instructions.
7.2.2.5.6 The instructions are to mention
that prior to the activation of the fire- 7.2.2.7.3 Pressurised tanks, fittings and
extinguishing system, combustion engines piping are not to be installed in the
installed in the space and aspirating air accommodation.
from the space to be protected, are to be 7.2.2.7.4 The temperature of cabinets and
shut down. storage spaces for pressurised tanks is not
7.2.2.6 Alarm device to exceed 50 [°C].
a) before being brought into service; 7.2.2.10.1.3 The level of filling of CO2
tanks is not to exceed 0.75 [kg/l]. The
b) each time it is put back into service volume of depressurised CO2 is to be
after activation; taken to be 0.56 [m3/kg];
c) after every modification or repair; 7.2.2.10.1.4 The concentration of CO2 in
d) regularly, not less than every two the space to be protected is to be not
years. less than 40% of the gross volume of the
space. This quantity is to be released
7.2.2.9.3 During the inspection, the expert within 120 seconds. It is to be possible to
is required to check that the system monitor whether diffusion is proceeding
conforms to the requirements of 7.2.2. correctly;
7.2.2.9.4 The inspection is to include, as a 7.2.2.10.1.5 The opening of the tank
minimum: valves and the control of the diffusing
valve are to correspond to two different
a) an external inspection of the entire operations;
system;
7.2.2.10.1.6 The appropriate period of
b) an inspection to ensure that the time mentioned in 7.2.2.6 b) is to be not
piping is leakproof; less than 20 seconds. A reliable
c) an inspection to ensure that the installation is to ensure the timing of the
control and activation systems are diffusion of CO2.
in good working order; 7.2.2.11 Fire-extinguishing system
d) an inspection of the pressure and operating with HFC-227 ea
contents of tanks; (heptafluoropropane)
7.2.2.11.1.1 Where there are several 7.2.2.12.1.2 Every tank containing IG-
spaces with different gross volumes, 541 placed in the space to be protected
each space is to be equipped with its is to be fitted with a device to prevent
own fire-extinguishing system; overpressure. This device is to ensure
that the contents of the tank are safely
7.2.2.11.1.2 Every tank containing HFC- diffused in the space to be protected if
227 ea placed in the space to be the tank is subjected to fire, when the
protected is to be fitted with a device to fire-extinguishing system has not been
prevent overpressure. This device is to brought into service;
ensure that the contents of the tank are
safely diffused in the space to be 7.2.2.12.1.3 Each tank is to be fitted with
protected if the tank is subjected to fire, a device for checking the contents;
when the fire-extinguishing system has
not been brought into service; 7.2.2.12.1.4 The filling pressure of the
tanks is not to exceed 200 [bar] at a
7.2.2.11.1.3 Every tank is to be fitted with temperature of +15 [°C];
a device permitting control of the gas
pressure; 7.2.2.12.1.5 The concentration of IG-541
in the space to be protected is to be not
7.2.2.11.1.4 The level of filling of tanks is less than 44% and not more than 50% of
not to exceed 1.15 [kg/l]. The specific the gross volume of the space. This
volume of depressurised HFC-227 ea is quantity is to be released within 120
to be taken to be 0.1374 [m3/kg]; seconds.
7.2.2.11.1.5 The concentration of HFC- 7.2.2.13 Fire-extinguishing system
227 ea in the space to be protected is to operating with FK-5-1-12
be not less than 8% of the gross volume
of the space. This quantity is to be 7.2.2.13.1 In addition to the requirements
released within 10 seconds; of 7.2.2.1 to 7.2.2.9, fire-extinguishing
systems using FK-5-1-12 as an
7.2.2.11.1.6 Tanks of HFC-227 ea are to extinguishing agent is to comply with the
be fitted with a pressure monitoring following provisions:
device which triggers an audible and
visual alarm in the wheelhouse in the 7.2.2.13.1.1 Where there are several
event of an unscheduled loss of spaces with different gross volumes,
propellant gas. Where there is no every space is to be equipped with its
wheelhouse, the alarm is to be triggered own fire-extinguishing system;
outside the space to be protected; 7.2.2.13.1.2 Every tank containing FK-5-
7.2.2.11.1.7 After discharge, the 1-12 placed in the space to be protected
concentration in the space to be is to be fitted with a device to prevent
protected is not to exceed 10.5% overpressure. This device is to ensure
(volume); that the contents of the tank are safely
diffused in the space to be protected if
7.2.2.11.1.8 The fire-extinguishing the tank is subjected to fire, when the
system is not to comprise aluminium fire-extinguishing system has not been
parts. brought into service;
7.2.2.12 Fire-extinguishing system 7.2.2.13.1.3 Every tank is to be fitted with
operating with IG-541 a device permitting control of the gas
pressure;
7.2.2.12.1 In addition to the requirements
of 7.2.2.1 to 7.2.2.9, fire-extinguishing 7.2.2.13.1.4 The level of filling of tanks is
systems using IG-541 as an extinguishing not to exceed 1[kg/l]. The specific
agent is to conform to the following volume of depressurized FK-5-1-12 is to
provisions: be taken to be 0.0719 [m3/kg];
7.2.2.12.1.1 Where there are several 7.2.2.13.1.5 The volume of FK-5-1-12 in
spaces with different gross volumes, the space to be protected is to be not
every space is to be equipped with its less than 5.5% of the gross volume of the
own fire-extinguishing system; space. This quantity is to be released
within 10 seconds;
End of Chapter
Chapter 3
Passenger Vessels
Contents
Section
1 General
2 Vessel Arrangement
3 Machinery and Systems
4 Electrical Installations
5 Fire Protection, Detection and Extinction
6 Additional Requirements for Ro-Ro PAX Notation
7 Additional Requirements for PRM Notation
Section 1
General
1.1.1 This Chapter applies to self-propelled 1.3.1 Passenger vessel: a day trip or cabin
passenger vessels. vessel constructed and equipped to carry more
than 12 passengers.
1.1.2 Attention is drawn to technical and
operational requirements of National/Local 1.3.2 Day-trip vessel: a passenger vessel
authorities where the vessel is registered or without overnight passenger cabins.
operating.
1.3.3 Cabin vessel: a passenger vessel with
1.2 Notation overnight passenger cabins.
1.2.1 Vessels complying with the requirements of 1.3.4 Main Engine Room: Space where the
this chapter are eligible for the assignment of the propulsion engines are installed
notation PASSENGER VESSEL.
1.3.5 Engine Room: Space where combustion
1.2.2 An additional class notation FERRY will be engines are installed.
assigned to a vessel on regular scheduled
service. 1.3.6 Boiler Room: a space housing a fuel-
operated installation designed to produce steam
1.2.3 An additional class notation RO-RO PAX or heat a thermal fluid.
will be assigned to passenger vessels intended
for carriage of passengers and vehicles and built 1.3.7 Wheelhouse: the area which houses all the
in accordance with Sec 6 of this chapter. control and monitoring instruments necessary for
manoeuvring the vessel.
1.2.4 An additional class notation PRM will be
assigned to a passenger vessel in which areas 1.3.8 Crew Accommodation: a space intended
are provided for use by persons with reduced for the use of persons normally living on board,
mobility, according to the provisions of Sec 7 of including galleys, store rooms, toilets and
this chapter.
washing facilities, laundry facilities, 1.3.14 Evacuation Areas: part of muster areas
passageways, but not the wheelhouse. of the vessel from which evacuation of persons
can be carried out.
1.3.9 Passenger Space: space on board
intended for passengers and enclosed areas 1.3.15 Store Room of high risk: a space for the
such as offices, shops, hairdressing salons, storage of flammable liquids or a room with an
drying rooms, laundries, saunas, toilets, area of over 4 [m2] for storing supplies.
washrooms, passageways, connecting passages
and stairs not encapsulated by walls. 1.3.16 Passageway: an area intended for the
normal movement of persons and goods.
1.3.10 Accommodation Space: a living space of
a crew accommodation or a passenger space. 1.3.17 Persons with reduced mobility: persons
On board passenger vessels, galleys are not facing particular problems when using public
regarded as accommodation space. transport, such as the elderly and the
handicapped and persons with sensory
1.3.11 Stairwell: the well of an internal staircase disabilities, persons in wheelchairs, pregnant
or of a lift. women and persons accompanying young
children.
1.3.12 Galley: a room equipped with an open
flame cooking appliance or any electrically 1.4 Material
heated cooking plate or hot plate with a power of
not more than 5 [kW]. 1.4.1 Glass doors and walls in passageways and
also window panes are to be manufactured from
1.3.13 Muster Areas: areas of the vessel which pre-stressed glass or laminated glass. They may
are specially protected and in which persons also be made from a synthetic material.
muster in the event of danger.
Section 2
Vessel Arrangement
2.1 Stability and Freeboard 2.2.2 Bulkheads rising up to the deck are to be
provided as follows :
2.1.1 The intact stability, damage stability and
freeboard of the vessel are to be in accordance a) A Collision Bulkhead: The distance
with IRS Classification Note “Stability between the collision bulkhead and the
Requirements for Inland Waterways Passenger forward perpendicular is to be at least
Ships”. 0.04LWL and not more than 0.04LWL + 2
[m].
2.1.2 The maximum draught is to be in
compliance with the requirements of 2.1.1 and is b) An Aft-Peak Bulkhead, where vessel
to be marked on the vessel’s sides at about mid- length exceeds 25 [m]: The aft peak
length. bulkhead is to be installed at a distance of
between 1.4 [m] and 0.04 LWL + 2 [𝑚]
2.2 Subdivision and Transverse Bulkheads measured from the aft point of the
intersection of the hull with the maximum
2.2.1 The number and position of bulkheads are draught line.
to be selected such that, in the event of flooding,
the vessel remains buoyant according to the 2.2.3 A transverse bulkhead may be fitted with a
requirements used for the compliance of 2.1.1. bulkhead recess, if all parts of this recess lie
Every portion of the internal structure, which within the area which is externally bounded by a
affects the efficiency of the subdivision of such vertical surface running at a distance of BWL/5
vessels, is to be watertight, and is to be of a parallel to the course of the hull in the line of
design which will maintain the integrity of the maximum draught.
subdivision.
2.2.6 Collision bulkheads are to have no b) after being closed by remote control, the
openings and no doors. door is to be such that it can be opened
again locally and closed safely. Closure is
2.2.7 Doors are not permitted in bulkheads not to be impeded by carpeting, foot rails
separating the engine rooms from passenger or other obstructions;
space or crew accommodation.
c) the time taken for the remote-controlled
2.2.8 Where double bottoms are fitted, their closure process is to be at least 30
height is to be at least 0.65 [m], and where wing [seconds] but not more than 60 [seconds];
voids are fitted, their width is to be at least 0.65
[m]. d) during the closure procedure an audible
alarm is to sound by the door;
2.3 Watertight Doors and Doors
e) the door drive and alarm are also to be
2.3.1 Manually operated doors without remote capable of operating independently of the
control, in bulkheads referred to in 2.2.4, are on-board power supply. There is to be a
permitted only in areas not accessible to device at the location of the remote
passengers. They are to: control that displays whether the door is
open or closed.
a) remain closed at all times and be opened
only temporarily to allow access; 2.3.3 Doors in bulkheads referred to in 2.2.4, and
their actuators are to be located in the area which
b) be fitted with suitable devices to enable is externally bounded by a vertical surface
them to be closed quickly and safely; running at a distance of BWL/5 parallel to the
course of the hull in the line of maximum draught.
c) display the following notice on both sides
of the doors: 2.3.4 There is to be a warning system in the
wheelhouse to indicate which of the doors in
‘Close door immediately after passing bulkheads referred to in 2.2.4 are open.
through’.
2.3.5 Remote controls of bulkhead doors
A manually controlled remote controlled according to 2.3.2 are to be clearly indicated as
bulkhead door in the passenger space may be such.
provided on vessels of length not more than
45[m] and authorized to carry number of 2.3.6 Cold-storage room doors, even when
passengers restricted to that length of the vessel locked, are also to be capable of being opened
in meters, if: from the inside.
b) this door is accessible directly from the 2.4.1 Windows may be situated below the margin
deck and is not more than 10 [m] away line if they are watertight, cannot be opened,
from the deck; possess sufficient strength, protected by
deadlights or portable covers and conform to
c) the lower edge of the door opening lies at 1.4.1.
least 0.3 [m]above the floor of the
passenger space, and
2.4.2 Requirements of 2.4.1 are deemed to be On day trip vessels, one of these two exits
fulfilled if the construction of watertight windows can be replaced by two emergency exits.
complies with the following provision: Rooms, with the exception of cabins, and
groups of rooms that have only one exit,
a) Pre-stressed glass complying with are to have at least one emergency exit.
International Standard ISO 614 : 2012 is
used. b) If rooms are located below the bulkhead
deck, one of the exits can be a watertight
b) Round windows comply with International bulkhead door, (complying with 2.3.2),
Standard leading into an adjacent compartment
from which the upper deck can be
ISO 1751 : 2012, reached directly. The other exit is to lead
Series B: medium heavy-duty directly or, if permitted in accordance with
windows (a), as an emergency exit into the open
Type: non-opening window. air, or to the bulkhead deck. This
requirement does not apply to individual
c) Angular windows comply with cabins.
International Standard
ISO 3903 : 2012, c) Exits according to (a) and (b) are to be
Series E: heavy-duty windows suitably arranged and are to have a clear
width of at least 0.8 [m] and a clear height
Type: non-opening window
of at least 2 [m]. For doors of passenger
cabins and other small rooms, the clear
d) ISO Standard windows may be replaced
width can be reduced to 0.7 [m].
by windows whose construction is at least
equivalent to the requirements of b) to c). d) In the case of rooms or groups of rooms
intended for more than 80 passengers the
2.4.3 Cabins without an opening window are to sum of the widths of all exits intended for
be connected to a ventilation system. passengers and which are to be used by
them in an emergency is to be at least
2.5 Passenger Spaces 0.01 [m] per passenger.
2.5.1 Location of Passenger Spaces e) If the total width of the exits is determined
by the number of passengers, the width of
2.5.1.1 On all decks, passenger spaces are to be
each exit is to be at least 0.005 [m] per
located aft of the collision bulkhead and, if they
passenger.
are below the bulkhead deck, forward of the aft-
peak bulkhead.
f) Emergency exits are to have a shortest
2.5.1.2 Passenger spaces are to be separated side at least 0.6 [m] long or a minimum
from the engine and boiler rooms by gas-tight diameter of 0.7 [m]. They are to open in
boundaries. the direction of escape and be marked on
both sides.
2.5.1.3 Deck areas, which are enclosed by
awnings or similar mobile installations not only 2.5.3 Doors of Passenger Spaces
above but also fully or partially to the side, are to
comply with the same requirements as enclosed 2.5.3.1 Doors of passenger spaces are to comply
passenger spaces. with the following requirements:
2.5.2 Number and Width of the Exits of a) With the exception of doors leading to
Passenger Spaces connecting corridors, they are to be
capable of opening outwards or be
2.5.2.1 The number and width of the exits of constructed as sliding doors.
passenger spaces are to comply with the
following requirements: b) Cabin doors are to be made in such a way
that they can also be unlocked from the
a) Rooms or groups of rooms designed or outside at any time.
arranged for 30 or more passengers or
including berths for 12 or more c) Powered doors are to open easily in the
passengers, are to have at least two exits. event of failure of the power supply to this
mechanism.
b) Their clear height is not to be less than 2 a) They are to be surrounded by a fixed
[m]. bulwark or guard rail at least 1 [m] high
or a railing according a recognized
c) Connecting corridors more than 1.5 [m] standard such as IS9448.
wide are to have handrails on either side.
2.5.7 Embarking and Disembarking
d) Where a part of the vessel or a room Arrangement
intended for passengers is served by a
single connecting corridor, the clear width 2.5.7.1 Parts of the deck intended for
thereof is to be at least 1 [m]. passengers, and which are not enclosed, are to
comply with the following requirements:
e) Connecting corridors are to be free of
steps. a) Openings and equipment for embarking or
disembarking and openings for loading or
f) They are to lead only to open decks, unloading are to be such that they can be
rooms or staircases. secured and have a clear width of at least
1 [m].
g) Dead ends in connecting corridors are not
to be longer than two meters. b) If the openings and equipment for
embarking or disembarking cannot be
2.5.5 Stairs and their Landing observed from the wheelhouse,
appropriate auxiliary means are to be
2.5.5.1 Stairs and their landings in the passenger provided.
spaces are to comply with the following
requirements: 2.6 Escape from Passenger Spaces
b) They are to have a clear width of at least a) Stairways, exits and emergency exits are
0.8 [m]. If they lead to connecting to be so arranged that, in the event of a
corridors or areas used by more than 80 fire in any given area, the other areas may
passengers, the stairs are to have a width be evacuated safely.
of at least 0.01 [m] per passenger.
b) The escape routes are to lead by the
c) They are to have a clear width of at least shortest route to evacuation areas.
1 [m] if they provide the only means of
access to a room intended for c) Escape routes are not to lead through
passengers. engine rooms or galleys.
d) Staircases in the same room are to be d) There are to be no rungs, ladders or the
provided on each side of the vessel. In like installed at any point along the
case, staircases in the same room are not escape routes.
provided on each side, then the
Section 3
3.1.3.3.2 Where, in addition to the main bilge c) The alarm is to provide an audible
pumping system, an emergency bilge pumping warning, and a separate visual warning,
system is provided, it is to be independent of the for each protected space at the control
main system and so arranged that a pump is position. Once activated the audible alarm
capable of operating on any compartment under is to continue to sound until
flooding conditions; in this case, the valves and acknowledged.
cocks necessary for the operation of the
emergency system need to be capable of being 3.2 Air and Sounding Pipes
operated from above the bulkhead deck.
3.2.1 Short sounding pipes are permissible only
3.1.3.3.3 Every valve which is required to be for sounding cofferdams and double bottom
operated from above the bulkhead deck is to tanks situated in a machinery space, and are in
have its means of control, at its place of all cases to be fitted with self-closing cocks as
operation, clearly marked to show the purpose it described in Pt.4, Ch.3, 3.3.4. In addition:
serves and how it may be opened and closed. It
is to be provided with a means to indicate
whether it is open or closed.
a) Short sounding pipes to fuel oil, (flash 3.3.1 Open ended pipes and ventilation ducts are
point not less than 55°C), lubricating oil to be arranged such that in any condition of
tanks and other flammable oil tanks flooding, water cannot enter other watertight
(flash point not less than 55°C) are to be compartments:
fitted with an additional small diameter
self-closing test cock, in order to ensure a) If several compartments are connected by
means of open ended pipelines or
that the sounding pipe is not under a
ventilation ducts they are to be arranged
pressure of oil before opening-up the
such that the open ends are situated
sounding cock. above the maximum assumed damage
condition.
b) Provision is to be made to ensure that
discharge of oil through this test cock b) Pipelines/ ventilation ducts are not
does not present an ignition hazard. required to comply with (a) above if they
c) An additional small diameter self-closing are provided with shut off valves capable
test cock is not required for lubricating oil of being operated from above the
tanks. bulkhead deck. Shut-off devices above
the bulkhead deck are to be clearly
3.2.2 Elbow sounding pipes are not permitted. indicated as such.
3.2.3 Sounding pipes of fuel tanks are not to c) Pipelines having no open end are to be
terminate in accommodation or passenger considered as not damaged if they are
spaces. situated inboard of the line B/5 and the
distance from the bottom is more than 0.5
3.3 Prevention of communication between [m]
compartments in the event of damage
Section 4
Electrical Installations
4.1.2 The electrical equipment and installations 4.2.2.1 Emergency source of power is to be
are to be maintained to ensure that the vessel is provided to supply the following:
in an operational and habitable condition.
a) navigation lights;
4.1.3 The main source of electrical power may be
driven by auxiliary or the main propulsion engine. b) search lights
It is to be capable of illuminating any part of the
vessel normally accessible to and used by the c) audible warning devices;
passengers or crew, and provide power to main
electrical systems, which are to operate without d) emergency lighting;
recourse to the emergency source of power.
e) radiotelephone installations;
4.2 Emergency source of electrical power
f) general alarm, PA System and on-board
4.2.1 General message communications systems
essential for safety and operation of
4.2.1.1 All passenger vessels are to be provided vessel;
with an emergency source of electrical power.
k) control and power systems to power- 4.2.5 Types of Emergency Source of Electrical
operated watertight doors and fire doors Power
and their status indication;
4.2.5.1 The following are admissible for use as an
l) personnel lifts and lifting equipment for emergency source of power:
persons with reduce mobility provided for
evacuation purposes; a) auxiliary generator sets with their own
independent fuel (flash point of not less
than 43[°C]) supply, and independent
m) emergency bilge pump and equipment
cooling system which, in the event of a
necessary for the operation of remote
power failure, start and take over the
controlled bilge valves; and
supply of power within 30 [seconds]
automatically or, if they are located in the
n) davits and hoisting gear for gangways
immediate vicinity of the wheelhouse or
intended for emergency use and rescue
any other location permanently manned
boats, where installed.
by crew members, can be brought into
operation manually; or
4.2.3 Operating Period of Emergency power
supply
b) accumulator batteries, which, in the
event of a power failure, connect
4.2.3.1 The emergency source of power is to be
automatically or, if they are located in the
capable of powering the items listed in 4.2.2.1
immediate vicinity of the wheelhouse or
without refueling or recharging for a projected
any other location permanently manned
operating period depending on the purpose of the
by crew members, can be connected
vessel and as agreed by the national/local
manually. Accumulator battery banks are
authority. In any case, the operating period of the
to be capable of being isolated. They are
emergency of power is not to be less than 60
to be capable of powering the power
[minutes].
consumers as mentioned in 4.2.2.1
throughout the prescribed period without
4.2.4 Arrangement
recharging and without an unacceptable
voltage reduction.
4.2.4.1 The emergency power plant is to be
installed outside the main engine room, outside
To enable the crew to undertake a) or b) above,
the rooms housing the main power sources and
emergency battery lighting is to be provided in
outside the room where the main switchboard is
way of the emergency means of power supply
located; it is to be separated from these rooms by
described. This may be by the use of torches
partitions according to Section 5. The emergency
stowed in a readily accessible place nearby.
power plant is to be installed either above the
margin line or as far away as possible from the
4.2.6 Control and Monitoring
main power sources, to ensure that, in the event
of flooding, it is not flooded at the same time as
4.2.6.1 Where emergency generating sets are
these power sources.
fitted they are to be capable of being started
readily when cold.
4.2.4.2 Cables feeding the electrical installations
in the event of an emergency are to be installed
4.2.6.2 The emergency switchboard may be
and routed in such a way as to maintain the
supplied from the main switchboard during
continuity of supply of these installations in the
normal operation.
event of fire or flooding affecting the main power
supply. Unless emergency power cables are
4.2.6.3 Where the emergency source of power is
suitably protected against fire and flame to a
an accumulator battery, arrangements are to be
duration as decided in 4.2.3.1, they are not to be
such that emergency lighting will automatically
routed through the main engine room, galleys or
come into operation on failure of the main lighting 4.3.3.2 For the following rooms and locations,
supply. adequate lighting and emergency lighting is to be
provided:
4.2.6.4 An indicator is to be mounted in the
machinery space, or in the wheelhouse, to a) locations where life-saving equipment is
indicate when any accumulator battery fitted in stored and where such equipment is
accordance with 4.2.5 is being discharged. normally prepared for use;
4.5.2.2 The public address system is to be The alarm triggers are to be protected against
capable of broadcasting messages from the unintentional use and installed at a height above
wheelhouse to: the floor of 0.85 [m] to 1.10 [m];
4.6.2.1 Required electrically operated bell or 4.7.1 Passenger vessels are to have suitable
other equivalent warning systems for sounding guidance systems to clearly identify the escape
the general emergency alarm signal are to routes and emergency exits when the normal
comply with the relevant requirements of the emergency lighting is less effective due to smoke.
appropriate Statutory Authority and with the Such guidance systems are to take the form of
requirements of this sub- Section. low-location lighting (LLL).
4.6.2.2 The vessel is to be equipped with an 4.7.2 In addition to the emergency lighting as
alarm system enabling the vessel's command to required by 4.3.3 the escape routes, including
alert passengers. This alarm is to be clearly and stairways, exits and emergency exits, are to be
unmistakably audible in all rooms accessible to marked by low-location lighting (LLL) throughout
passengers. It is to be capable of being triggered the whole of the escape route, particularly at
from the wheelhouse and from a location that is corners and intersections.
permanently staffed.
4.7.3 In general ,the LLL system is to be as per
4.6.2.3 The vessel is to be equipped with an the requirements in IMO Resolution A.752(18)
independent alarm system enabling the vessel's “Guidelines for Evaluation, Testing and
command to alert the crew and shipboard Application of Low-Location Lighting on
personnel, in the accommodation, engine rooms Passenger Ships”. Requirement for time duration
and where appropriate, pump rooms. The alarm of functioning of LLL System given in clause 2.3
system is also to reach the recreation rooms for of A.752(18) is dispensed and instead the LLL
the shipboard personnel, the cold-storage rooms system is to function for at least 30 minutes after
and other store rooms of high risk. Alarm triggers its activation.
are to be protected against unintentional use.
4.8 Watertight Doors and Doors
4.6.2.4 Means are to be provided to allow the
system to be capable of sounding the alarm 4.8.1 Refer to Section 2 for the requirements for
required by 4.6.2.3 independently of the alarm to watertight doors and doors.
the passenger spaces required by 4.6.2.2.
Section 5
5.1 General
b) Ventilation systems showing the
5.1.1 Statutory Requirements penetrations on divisions, location of
dampers, means of closing, etc.
5.1.1.1 Attention is drawn to fire safety
requirements of National/Local Authorities where c) Escape plan
the vessel is registered or operating.
5.2 Definitions
5.1.2 Documentation
5.2.1 Non-combustible: a substance which
5.1.2.1 For fire safety of passenger vessels neither burns nor produces flammable vapours in
additional plans and information are to be such quantities that they ignite spontaneously
submitted as detailed below for approval: when heated to approximately 750 [°C];
a) Structural fire protection, showing the 5.2.2 Flame-retardant: material which does not
method of construction, purpose and readily catch fire, or whose surface at least
category of the various spaces of the restricts the spread of flames pursuant to the
vessels, the fire rating of bulkheads and following test procedures :
decks, means of closings of openings
divisions, draught stops. a) Code for Fire Test Procedures, Annex
1 Part 5 (Test for surface flammability -
d) Code for Fire Test Procedures, Annex 5.3.2 Structural Fire Protection
1 Part 9 (Test for bedding components)
of the; 5.3.2.1 The minimum required fire integrity of all
bulkheads and decks is shown in Table 5.3.2.1
5.2.3 Self-extinguishing: the characteristic of a (a) or 5.3.2.1(b), as applicable. Requirements
burning substance whereby it extinguishes itself given in Table 5.3.2.1 (a) and 5.3.2.1 (b) are not
of its own accord within a short period once the applicable to day trip vessels of length less than
ignition source has been removed, i.e. does not 24 [m].
continue to burn;
5.3.2.2 In day trip vessels of length less than 24
5.2.4 Fire-resistance: the property of structural [m], the machinery space boundaries are to be
components or devices as certified by the constructed of steel (rated A0) or equivalent
following test procedure : material. The engine space is to be capable of
being closed down in order that the fire
a) Code for Fire Test Procedures Annex extinguishing medium cannot escape. Where it
1, Part 3, (Part 3 – Test for "A", "B" and is not practical to have a machinery space, the
"F" class divisions) engine is to be enclosed in a box. The box is to
perform the same function as the machinery
5.2.5 Code for Fire Test Procedures: the space boundaries referred earlier. Partitions
International Code for the Application of Fire Test between galley, store rooms of high risk
Procedures (FTP code) adopted under containing flammable liquids and other areas are
Resolution MSC.307(88) by the Maritime Safety also to be of Type A0 or equivalent material.
Committee of the International Maritime
Organization (IMO);
Table 5.3.2.1(a) : Partitions between rooms, in which no pressurised sprinkler systems according
to Pt.4, Ch.9, 4.2 are installed
Table 5.3.2.1(b): Partitions between rooms, in which pressurised sprinkler systems according to
Pt.4, Ch.9, 4.2 are installed
2) Partitions between accommodation spaces and internal muster areas are to correspond to Type A0, but
external muster areas only to Type B15.
3) Partitions between cabins and corridors are to comply with Type B0. Partitions between cabins and
saunas are to comply with Type A0, for rooms that are fitted with pressurised sprinkler systems, they are to
comply with type B15.
4) Partitions between engine rooms according to 4.2.4.1 are to comply with Type A60; in other cases they
are to comply with Type A0.
5) Partitions between store rooms for the storage of flammable liquids and control centres / muster areas
are to comply with Type A60, for rooms fitted with pressurised sprinkler systems A30. Partitions between
store rooms for the storage of flammable liquids and stairwells/ accommodation spaces are to be of Type
A30.
6) Partitions between store rooms for the storage of flammable liquids and galleys are to be of Type A30
and A0 where pressurized sprinklers are fitted. Partitions between other store rooms of high risk and galleys
are to be of Type A0. Type B15 is sufficient for partitions between galleys, on one side, and cold-storage
rooms and food store rooms of high risk, on the other.
7) Windows below the muster areas/embarkation stations are to have same fire integrity as the structure on
which it is fitted.
5.3.2.3 For the purpose of determining the b) Stairwell: the well of an internal staircase
appropriate fire integrity standard to be applied to or of a lift;
boundaries between adjacent spaces, such
spaces are classified according to their fire risk c) Muster Areas: areas of the vessel which
described in the following categories. The title of are specially protected and in which
each category is intended to be typical rather persons muster in the event of danger;
than restrictive.
d) Accommodation Spaces: a room of an
a) Control Centres : a wheelhouse, an area
accommodation or a passenger space.
which contains an emergency electrical
On-board passenger vessels, galleys are
power plant or parts thereof or an area
not regarded as accommodation space.
with a centre permanently occupied by
crew , such as for fire alarm equipment, e) Engine Room: space where combustion
remote controls of doors or fire dampers; engines are installed;
5.3.3.2 Galleys are to be fitted with ventilation 5.4.1.2 On passenger vessels, which do not have
systems and stoves with extractors. The air a fire detection system with remote identification
extraction ducts of the extractors are to satisfy the of individual fire detectors, a fire detection section
requirements according to 5.3.3.1 and, is not to comprise more than the area constituted
additionally, be fitted with manually operated fire in accordance with 5.3.2.14. The activation of a
dampers at the inlet openings. Insulation on fire detector in an individual cabin in this fire
galley ducts are to be in accordance with the detection section is to set off a visual and
applicable requirements of 5.3.2.1 for galley. acoustic signal in the passageway outside that
cabin.
5.3.4 Control of Smoke Spread
5.4.1.3 Power supply requirements for fire alarm
5.3.4.1 In vessels of 24 m length and over, control system are to be as per Pt. 4, Ch. 9, 3.2.2.2. With
centres, stairwells and internal muster areas are respect to requirements of Pt. 4, Ch. 9, 3.2.2.2.2,
to be fitted with natural or mechanical smoke on day-trip vessels up to 25 [m] length, a
extraction systems. Smoke extraction systems separate emergency power supply is sufficient.
are to satisfy the following requirements:
5.5 Fire Extinction
a) they are to offer sufficient capacity and
reliability; 5.5.1 Portable Fire Extinguishers
b) they are to comply with the operating 5.5.1.1 In addition to the portable extinguishers
conditions for passenger vessels; according to Pt.4, Ch.9, Sec.4, at least the
following portable extinguishers are to be
c) if smoke extraction systems also serve available on board:
as general ventilators for the rooms, this
shall not hinder their function as smoke a) one portable extinguisher for every
extraction systems in the event of a fire; 120 [m2] of gross floor area in passenger
spaces;
d) smoke extraction systems are to have
a manually operated triggering device; b) one portable extinguisher per group of
10 cabins, rounded upwards;
e) mechanical smoke extraction systems
are to additionally be such that they can
c) one portable extinguisher in each 5.5.2.5 Materials for fire-fighting equipment are to
galley and in the vicinity of any room in either be heat-resistant or be suitably protected
which flammable liquids are stored or against failure to work when subjected to high
used. In galleys the extinguishing agent temperatures.
shall also be suitable for fighting fat fires.
5.5.2.6 Pipes and hydrants are to be arranged in
These additional fire extinguishers are to meet such a way that the risk of freezing is avoided.
the requirements of Pt.4, Ch.9, 4.4.6 & 4.4.7. In
every galley and in hairdressing salons and 5.5.2.7 The fire extinguishing pumps are to:
perfumeries, there is to be a fire blanket to hand.
a) be installed or housed in separate
5.5.2 Water supply system compartments;
5.5.2.1 vessels are to be provided with a system b) be such that they can be operated
consisting of: independently of each other;
5.5.2.2 Systems are to be designed and 5.5.3.1 Engine rooms where total power output is
dimensioned in such a way that: 375 [kW] and above, are to be fitted with a fixed
fire extinguishing system according to Pt.4, Ch.9,
a) any point of the vessel can be reached Sec.4, 4.3.2.
from at least two hydrants in different
places, each with a single hose length of 5.5.4 Breathing Apparatus
not more than 20 [m];
5.5.4.1 On cabin vessels there are to be:
b) the pressure at the hydrants is at least
300 [kPa]; and a) two self-contained breathing
apparatus sets corresponding to EN 137
c) on all decks a water jet length of at : 2006 of Type 2 with full-face masks
least 6 [m] can be attained. corresponding to EN 136 : 1998 or
equivalent and provided with spare
If a hydrant cupboard is provided, an charges or a breathing air compressor;
‘extinguisher hose’ symbol, of at least 10 cm side
length, is to be affixed to the outside of the b) two sets of equipment consisting of at
cupboard. least a protective suit, helmet, boots,
gloves, axe, crowbar, torch and safety-
5.5.2.3 Hydrant valves with screw threads or line,
cocks are to be such that they can be set so that
each of the fire extinguisher hoses can be c) four smoke hoods.
separated and removed during operation of the
fire extinguishing pumps. 5.5.4.2 For cabin vessels with a length of not
more than 45 [m], 5.5.4.1 is not applicable,
5.5.2.4 Fire extinguisher hoses in the internal provided smoke-hoods in a number
area are to be rolled up on an axially connected corresponding to the number of berths are readily
reel. accessible in each cabin.
Section 6
6.1.3 Documentation to be submitted 6.4.1.1 Scuppers from cargo spaces intended for
the carriage of motor vehicles with fuel in their
6.1.3.1 In addition to the documentation required tanks for their own propulsion are not to be led to
other parts of the rules following information is to machinery or other places where sources of
be submitted: ignition may be present.
recognized standard such as IEC 60079 6.5.1.3.1 Electrical equipment and cables in
publications or EN 50014-50020, and if they have exhaust ventilation ducts are to be as stated in
been tested and approved by a testing authority 6.5.1.1.2 and to have the minimum explosion
recognized by IRS. Notes and restrictions at the group IIA and temperature class T3.
certificate have to be observed. Cables are to be
armoured or screened, or run inside a metal tube. 6.6 Fire Safety
6.5.1.2 Installations in special category 6.6.2.2 In view of serious loss of stability, which
spaces situated below the bulkhead deck could arise due to large quantities of water
accumulating on the deck or decks consequent
6.5.1.2.1 An electrical equipment installed is to be on the operation of fixed pressure water-spraying
as stated in 6.5.1.1.2 and to have the minimum system, scuppers are to be fitted so as to ensure
explosion group IIA and temperature class T3. that such water is rapidly discharged directly
overboard.
6.5.1.3 Ventilation
Section 7
7.1.3 These rules do not address port facilities a) Connecting corridors intended for
and similar installations, which are subject to use by persons with reduced mobility
national/local requirements. are to have a clear width of 1.3 [m].
7.3.4.2 Lifts intended for persons with reduced 7.3.6.1 In addition to 2.5.7.1, parts of the deck
mobility, and lifting equipment, like stairlifts or intended for passengers, and which are not
lifting platforms, are to be constructed according enclosed, are to comply with the following
to a relevant recognized standard or requirements:
requirements of statutory authorities.
c) Openings, used normally for the
7.3.5 Bulwarks and Guard Rails embarking or disembarking of persons
with reduced mobility, are to have a clear
7.3.5.1 In addition to 2.5.6.1, parts of the deck width of at least 1.5 [m].
intended for passengers, and which are not
enclosed, are to comply with the following 7.3.7 Passageways in passenger spaces
requirements:
7.3.7.1 Passageways intended for use by
b) Bulwarks and railings of decks intended persons with reduced mobility are to have a clear
for use by persons with reduced mobility width of 1.3 [m] and be free of doorsteps and sills
are to be at least 1.1 [m] high. more than 0.025 [m] high. Walls in passageways
intended for use by persons with reduced mobility
7.3.6 Embarking and Disembarking are to be equipped with handrails at a height of
Arrangement 0.9 [m] above the floor.
End of Chapter
Chapter 4
Tugs
Contents
Section
1 General
2 Hull Arrangement and Strength
3 Towing Arrangement
4 Pushing Arrangements
5 Stability
6 Tests and Trials
Section 1
General
1.1.1 The requirements of this chapter apply to - Maximum and continuous bollard pull and the
tugs and are supplementary to those given for the breaking strength of the tow rope.
assignment of main characters of class.
Towing hook
A tug is a vessel designed primarily for towage of
other vessels, which does not exclude occasional - It's attachment and corresponding
pushing duties, if arranged for this purpose. strengthening of hull structure, slip
arrangements.
A pusher tug is a vessel designed primarily for
pushing other vessels. Bollard Pull test program
1.1.2 Vessels built in compliance with the above - Items specified in Sec.6.
requirements will be eligible to be assigned the
class notation " TUG" or “PUSHER TUG”. 1.2.2 Additional Certificates of Approval are to be
submitted for :-
1.1.3 The maximum value of bollard pull [tonnes]
measured during bollard pull test will be entered a) Towing hook with attachments
in the Register of Ships as " BPmax ....... ". In b) Towline.
addition, if requested, the continuous bollard pull
[tonnes] measured as per the procedure given in 1.3 Materials
Sec.5.2 will be entered in the Register of Ships
as "BPcont ..... ". 1.3.1 Towing hook including its attachment is to
be made of forged steel, special quality carbon
1.2 Documentation and carbon-manganese steel castings or
fabricated from rolled steel products
1.2.1 The following additional plans and manufactured and tested in accordance with Pt.2
documents are to be submitted for approval, as of the ‘Rules and Regulations for the
applicable. Construction and Classification of Steel Ships.
Section 2
Section 3
Towing Arrangement
3.1.1 The towline is to be in accordance with Pt.3, 3.2.1 Towing hook should be provided with an
Ch.13, Sec.3.2. efficient slip arrangement to facilitate release of
the towline regardless of the angle of heel and the
3.1.2 The position of the towing hook or towing direction of the towline. The releasing device is
winch is to be carefully selected so as to minimise also to be operable from the bridge. The breaking
the heeling moment as well as the risk of girting strength of the hook, or its equivalent should at
due to the pull exerted by the tow rope. least be 50 percent more than that of the towline.
Section 4
Pushing Arrangements
Section 5
Stability
5.1 General
GZ’ = Righting lever GZ, [m], at angle of deck
5.1.1 In addition to the general requirements, the immersion or at 30 degrees, whichever is lower.
stability of tugs is to be assessed considering the
effect of transverse heeling force caused when Ft = The transverse heeling force, [tonnes],
the tow rope is not in line with the tug’s generally may be taken at 0.5 BPmax.
longitudinal centerline. Compliance with the
following criteria is recommended, as a minimum: Iv = Vertical distance, [m], from the center of
propeller(s) to the center of towline.
GZ’ > 1.5 (Ft . lv) / (Displacement) [m]
Section 6
6.2 Bollard pull test procedure 6.2.5 An approved and calibrated load measuring
device, preferably giving a continuous read-out is
6.2.1 The proposed test programme is to be to be fitted between the eye of the towline and the
submitted prior to the testing. bollard.
6.2.2 Test for continuous bollard pull is to be 6.2.6 During the test, efficient communication is
carried out with the main engines running at the to be maintained between the vessel and the
maximum attainable engine RPM without shore personnel recording the bollard pull.
exceeding the maximum RPM and torque
recommended by the engine builder for 6.2.7 The vessel is to maintain a fixed course for
continuous operation. at least 10 minutes during which the bollard pull
is to be recorded.
6.2.3 The test is to be carried out with the vessel's
own propellers only. All auxiliary machinery 6.2.8 The pull maintained uniformly for minimum
which are normally driven from the main of 10 minutes without any tendency to decline
engine(s) or propeller shaft(s) while towing, are shall be certified as the vessel's continuous
to be connected during the test. bollard pull, subject to a limit of 50% of the
breaking strength of the towline supplied.
End of Chapter
Chapter 5
Contents
Section
1 General
2 Hull Arrangement and Strength
3 Pushing, Towing - Devices and Connecting Elements
4 Machinery and Electrical Installation
Section 1
General
Barges are non-self propelled vessels designed 1.2.1 The following additional plans and
and constructed for carriage of dry cargoes in documents are to be submitted for approval, as
holds or liquid cargoes in tanks. applicable.
Pontoons are non-self propelled vessels - Towing arrangement and details of towing
designed and constructed for carriage of non- brackets, bollards and other fittings with
perishable cargoes or equipment on deck. under deck stiffening.
1.1.2 Vessels built in compliance with the above - Details of structure and fittings, if any, to
requirements will be eligible to be assigned class which deck cargo securing lashings etc. are
notations " BARGE " or " PONTOON ", as attached.
appropriate.
- In case of pusher tugs or integral tug/barge
Barges and pontoons for special purpose or for systems or combination units comprising
carriage of specialised cargoes are also to many modules, details of the connecting
comply with the requirements of relevant elements, attachments and supporting
Chapters of Pt.5, and such vessels would be structures.
eligible for assignment of additional or
Section 2
2.2.1 For barges and pontoons having no rise of The section modulus of deck girders is not to be
floor, the keel plate thickness may be same as less than that required by Pt.3, Ch.8, Sec.5,
adjacent bottom shell. taking the value of the coefficient 'm' as 8.
2.2.2 On hard chine vessels, where a solid round 2.3.4 The scantlings of stanchions are to be
bar is provided at the knuckles, the diameter of based on the external pressure on bottom or the
round chine bar is not to be less than three times static cargo load on deck, whichever is higher;
the bottom plate thickness. and the buckling requirements given in Pt.3,
Ch.3, Sec.6. Stanchions in tank spaces are also
2.3 Truss arrangements to be checked for tension caused by internal
pressure.
2.3.1 A truss is a system of internal framing
members comprising deck and bottom girders in 2.3.5 The cross sectional area of diagonals may
association with regularly spaced stanchions and be approximately 50% of that of the adjacent
diagonal bracings inclined at about 45 degrees stanchion.
Section 3
Section 4
4.1 General
End of Chapter