0% found this document useful (0 votes)
44 views

Bills of Matirials

The document provides a bill of materials and cost estimate for a construction project broken into 8 sections. It lists the materials needed, quantity, unit, unit cost, and total cost for each item. The total material cost is $506,466.52, total labor cost is $227,909.93, and total direct cost is $734,376.42. With a contingency amount of $220,312.9 added, the overall total cost of the project is $954,689.32.

Uploaded by

Jessa Amida
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views

Bills of Matirials

The document provides a bill of materials and cost estimate for a construction project broken into 8 sections. It lists the materials needed, quantity, unit, unit cost, and total cost for each item. The total material cost is $506,466.52, total labor cost is $227,909.93, and total direct cost is $734,376.42. With a contingency amount of $220,312.9 added, the overall total cost of the project is $954,689.32.

Uploaded by

Jessa Amida
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

BILL OF MATERIALS

LABOR AND COST ESTIMATE

Description QTY Unit Material


Unit cost Total
1 METAL WORKS 27,150
12mm corrugated steel bar 80 Pcs 225 18,000

10mm corr. bar 50 Pcs 147 7,350


Tire wire G.I # 16 20 Kls 90 1,800
2 MASONRY WORKS 97,804
Portland Cement 137 Bags 290 39,730
Sand 22 Cu.m 1100 24,200
Gravel 15 Cu.m 1300 19,500
Pea Gravel 4 Cu.m 1300 5,200
10mm corr. Steel bar 22 pcs 147 3,234
Tire wire G.I # 16 6 Kls 90 540
CHB 4’’ 270 Pcs 20 5,400
3 FORM WORKS AND SCAFFOLDING 340,60
¼’’ Thick Ordinary Plywood 20 sheet 415 8,300
2’’x 2’’ x 12’ coco lumber 20 Pcs 85 1,700
2’’ x 3’’ x 12’ coco lumber 235 Pcs 100 23,500
Nails ( assorted) 7 Kls 80 560
4 CARPENTRY WORK 20,825
2’’ x 2’’ x12’ Good Lumber 35 Pcs 200 7,000
Wood Glue 1 Liter 125 125
¾’’ Thick Marine Plywood 8 Pcs 1350 10,800
4’’ Curnisa 6 Pcs 450 2,700
Nails ( assorted) 3 kls 80 240
5 RAILINGS WORK 167,437.52
Fabrication of Railing 1 lot 167,437. 52 167,437.52
6 ELETRICAL WORKS 47,987
Wire , Light and Fixtures 1 lot 47,987 47,987
7 PAINTING WORKS 85,433
Paints and Tools 1 lot 85,433 85,433
8 TILES WORK 25,770
60 X 60 Ceramic tiles 30 pcs 310 9300
30 x 30 Ceramic ties 25 pcs 210 5250
Tile Trim and Grout 1 lot 3820 3820
Tile Adhisave 10 bags 450 4500
Portland Cement 10 bags 290 2900
TOTAL MATERIAL COST ; 506,466.52
TOTAL LABOR COST ; 227,909.93
TOTAL DIRECT COST ; 734,376.42
CONTINGENCY : 220,312.9
OVER ALL TOTAL COST ; 954,689.32