0% found this document useful (0 votes)
340 views

Bill of Materials

The document is a bill of materials and cost estimate for Phase 1 of a proposed 3-storey residential building project. It includes 7 sections that estimate costs for general requirements, earthworks, concrete works, formworks/scaffoldings, steel works, masonry works, and sanitary/plumbing works. The total estimated cost is over 3.5 million pesos.

Uploaded by

johnnelson.lirio
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
340 views

Bill of Materials

The document is a bill of materials and cost estimate for Phase 1 of a proposed 3-storey residential building project. It includes 7 sections that estimate costs for general requirements, earthworks, concrete works, formworks/scaffoldings, steel works, masonry works, and sanitary/plumbing works. The total estimated cost is over 3.5 million pesos.

Uploaded by

johnnelson.lirio
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Project PROPOSED 3-STOREY RESIDENTIAL BUILDING

Location
Owner
Date
Subject PHASE - 1 : BILL OF MATERIALS & COST ESTIMATE

Item # DESCRIPTION UNIT QUANTITY UNIT PRICE P AMOUNT

1.00 GENERAL REQUIREMENTS


1.10 Mobilization/ Demolition/ Site Clearing L.S. 1 26,500.00 P 26,500.00
1.20 Production of Blueprints and Prof. Fees L.S. 1 60,000.00 P 60,000.00
1.30 Temporary Building Facilities L.S. 1 1,800.00 P 1,800.00
1.40 Temporary Electric & Water Bills L.S. 20 655.00 P 13,100.00
1.50 Sakolin (Trapal) L.S. 12 300.00 P 3,600.00
SUBTOTAL 105,000.00
2.00 EARTHWORKS
2.10 Soil Poisoning and Treatment L.S. 1 37,490.00 P 37,490.00
2.20 Gravel bed (3/4) CU.M. 69 1,100.00 P 75,900.00
2.30 Earthfill item 201 / Madrigal CU.M. 160 275.00 P 44,000.00
2.40 Headsize Boulder CU.M. 5 900.00 P 4,500.00
SUBTOTAL 161,890.00
3.00 CONCRETE WORKS
Footing, Column, Footing tie beam, floor Tie beam, Flooring, Beams ( Ground, second, third & roof beam ), slab & stairs.
FENCE: Retaining wall, columns & tie beam
3.10 Pozzolan Cement BAGS 1,144 260.00 P 297,440.00
3.20 Portland Cement BAGS 862 255.00 P 219,810.00
3.30 Washed gravel ( G1 & G2 ) CU.M. 320 1,100.00 P 352,000.00
3.40 Washed sand CU.M. 112 580.00 P 64,960.00
SUBTOTAL 934,210.00
4.00 FORM WORKS / SCAFOLDINGS ( w/ accessories )
4.10 Formworks for Beams, Columns, Slabs PCS 132 820.00 P 108,240.00
4.20 Cocolumber 2x3x12 PCS 950 126.00 P 119,700.00
4.30 Cocolumber 2x3x14 L.S. 230 145.00 P 33,350.00
4.40 CWN 1 1/2" BOXES 6 1,650.00 P 9,900.00
4.50 CWN 2" BOXES 5 1,590.00 P 7,950.00
4.60 CWN 3" BOXES 6 1,650.00 P 9,900.00
4.70 CWN 4" BOXES 9 1,680.00 P 15,120.00
SUBTOTAL 304,160.00
5.00 STEEL WORKS
5.10 Reinforced Steel Bar 10mm PCS 1,340 222.00 P 297,480.00
5.20 Reinforced Steel Bar 12mm PCS 265 276.00 P 73,140.00
5.30 Reinforced Steel Bar 16mm PCS 459 462.00 P 212,058.00
5.40 Welding rod KG 33 150.00 P 4,950.00
5.50 G.I. tie wire #16 ROLLS 23 1,800.00 P 41,400.00
5.60 2.5" X 2.5" X 1/4" Angle bar PCS 10 1,400.00 P 14,000.00
5.70 2" x 2" x 1/4" Angle bar PCS 112 940.00 P 105,280.00
5.80 2" x 2" x 3/16" Angle bar PCS 12 920.00 P 11,040.00
5.90 1 1 /2" x 1 1/2" x 3/16" Angle bar PCS 22 610.00 P 13,420.00
5.10 1" x 1 " x 3/16" Angle bar PCS 6 312.00 P 1,872.00
5.11 C-purlins 100 x 50 x 2.00mm thk. (Ga. #14) PCS 46 795.00 P 36,570.00
5.12 Tubular 2"x4"x2mmx6m PCS 3 1,700.00 P 5,100.00
5.13 Channel Bar 2x6x5mm PCS 2 3,620.00 P 7,240.00
5.14 Red Oxide Paint BOXES 8 2,800.00 P 22,400.00
5.15 Lacquer Thinner Ordinary BOXES 30 1,200.00 P 36,000.00
5.16 Consumables L.S. 1 20,000.00 P 20,000.00
SUBTOTAL 901,950.00
6.00 MASONRY WORKS
6.10 4" CHB (Interior Wall) PCS 2,156 13.50 P 29,106.00
6.20 6" CHB (Fence & Exterior Wall) PCS 1,675 17.50 P 29,312.50
6.30 Pozzolan Cement BAGS 265 250.00 P 66,250.00
6.40 Washed sand CU.M. 84 500.00 P 42,000.00
6.50 Fine sand CU.M. 36 525.00 P 18,900.00
6.60 12mm dia. @ 6 m. Length DSB PCS 640 276.00 P 176,640.00
6.70 10mm dia. @ 6 m. Length DSB PCS 185 222.00 P 41,070.00
SUBTOTAL 403,278.50
7.00 SANITARY / PLUMBING WORKS
7.10 PVC Pipe 1/2" PCS 4 95.00 P 380.00
7.20 PVC Pipe 2" PCS 11 260.00 P 2,860.00
7.30 PVC Pipe 3" PCS 10 460.00 P 4,600.00
7.40 PVC Pipe 4" PCS 6 420.00 P 2,520.00
7.50 Elbow 1/2" PCS 27 19.00 P 513.00
7.60 Elbow 3/4" PCS 12 25.00 P 300.00
7.70 Elbow 2" PCS 8 50.00 P 400.00
7.80 Elbow 3" PCS 17 75.00 P 1,275.00
7.90 Elbow 4" PCS 4 110.00 P 440.00
7.10 Short Elbow PCS 25 125.00 P 3,125.00
7.11 Putty PCS 6 110.00 P 660.00
7.12 Tee 1/2" x 3/4 PCS 10 35.00 P 350.00
7.13 Tee 2 x 2 PCS 10 55.00 P 550.00
7.14 Tee 4 x 4 PCS 3 160.00 P 480.00
7.15 Wye 2 x 2 PCS 3 110.00 P 330.00
7.16 Wye 3 x 2 PCS 19 113.00 P 2,147.00
7.17 Wye 3 x 3 PCS 2 130.00 P 260.00
7.18 Pipe Cement PCS 2 220.00 P 440.00
7.19 PPR Coupling 1/2 PCS 10 12.00 P 120.00
7.20 PPR Coupling 3/4 x 1/2 PCS 8 20.00 P 160.00
7.21 Coupling PCS 7 17.00 P 119.00
7.22 PPR Pipe 3/4 PCS 6 320.00 P 1,920.00
7.23 PPR Tee 1/2 PCS 10 25.00 P 250.00
7.24 PPR Tee 3/4 PCS 7 35.00 P 245.00
7.25 Long Elbow PCS 13 45.00 P 585.00
7.26 Elbow 2x45 PCS 16 32.00 P 512.00
7.27 Elbow 2x90 PCS 18 42.00 P 756.00
7.28 Elbow 3x45 PCS 16 58.00 P 928.00
7.29 PPR Pipe 1/2 PCS 34 235.00 P 7,990.00
7.30 Shower Drain, Flood Drain PCS 12 260.00 P 3,120.00
7.31 Fixture, Equipment, Tank, Consumables L.S. 1 145,000.00 P 145,000.00
7.32 Septic tank ( 2 units ), 6" CHB L.S. 1 22,100.00 P 22,100.00
7.33 Catch Basin / Area Drain, 4" CHB L.S. 1 16,000.00 P 16,000.00
7.34 Hose Bibb Faucet, Shower Head, etc. OWNER SUPPLY
SUBTOTAL 221,435.00
8.00 ELECTRICAL, MECHANICAL (ACU OUTLETS) & ELECTRONIC WORKS
8.10 Electrical Pipe 1/2" PCS 32 78.00 P 2,496.00
8.20 Electrical Pipe 3/4" PCS 16 98.00 P 1,568.00
8.30 Electrical Pipe 1" PCS 21 129.00 P 2,709.00
8.40 Junction Box PCS 23 31.00 P 713.00
8.50 Square Box PCS 11 80.00 P 880.00
8.60 Universal Convenience Outlet PCS 65 190.00 P 12,350.00
8.70 Switches (2 Gang, 3 Gang) PCS 30 212.00 P 6,360.00
8.80 6W Tri-color LED Downlight PCS 80 240.00 P 19,200.00
8.90 9W Surface Mounted Lighting Fixture PCS 19 315.00 P 5,985.00
8.10 T5 Lighting Fixture PCS 28 210.00 P 5,880.00
8.11 Strip Light with power supply for cove lighting PCS 16 420.00 P 6,720.00
8.12 All wires, Panel board, breakers, accessories L.S. 1 55,300.00 P 55,300.00
8.13 Air Conditioning Unit, Appliances, Equipment OWNER SUPPLY
SUBTOTAL 120,161.00
9.00 DOORS AND WINDOWS
9.10 Panel Doors (Hard Wood) PCS 12 8,100.00 P 97,200.00
9.20 Door Jamb 2"x6" S4S Hard Wood L.S. 1 7,240.00 P 7,240.00
9.30 Glass Window, Awning, Sliding, etc. L.S. 1 185,000.00 P 185,000.00
9.40 Glass Blocks PCS 60 120.00 P 7,200.00
SUBTOTAL 296,640.00
10.00 CARPENTRY WORKS
10.10 Bed, Closet, Cabinets, Console, etc. OWNER SUPPLY
11.00 THERMAL, MOISTURE CONTROL, WATERPROOFING, AND ROOFING INSTALLATION
11.10 Sikaflex Sealant PCS 5 375.00 P 1,875.00
11.20 Insulated Foam double sided 10mm ROLL 10 1,100.00 P 11,000.00
11.30 Waterproofing - Powermix (Bostik) PALE 3 3,485.00 P 10,455.00
11.40 Roofing Installation, Fascia Board, Gutter L.S. 1 110,000.00 P 110,000.00
SUBTOTAL 133,330.00
12.00 FINISHES
12.10 Ceramic Tiles, Quartz countertop, Grout L.S. 1 205,000.00 P 205,000.00
12.20 Painting works and consumables L.S. 1 312,000.00 P 312,000.00
SUBTOTAL 517,000.00
13.00 FASTENER AND ADHESIVES
13.10 Extra Hardener PCS 2 73.00 P 146.00
13.20 Umbrella Nail KG 126 100.00 P 12,600.00
13.30 Washers 1 1/2 PCS 150 4.75 P 712.50
13.40 Flat Washer 3/8 PCS 183 2.50 P 457.50
13.50 Electrical Tape PCS 22 40.00 P 880.00
13.60 Stikwel LITER 16 335.00 P 5,360.00
13.70 Rubber Tape PCS 13 150.00 P 1,950.00
13.80 Blind Rivet BOXES 14 232.75 P 3,258.50
13.90 Screws, Bolts, CWN, Consumables L.S. 1 25,000.00 P 25,000.00
SUBTOTAL 50,364.50
14.00 PERSONAL PROTECTIVE EQUIPMENT (PPE)
14.10 Gloves, Sweatshirt, Hardhat, Harness, Mask L.S. 1 12,000.00 P 12,000.00
SUBTOTAL 12,000.00
15.00 SPECIAL CONSTRUCTION AND INSTALLATION
15.10 Solar Panel Installation OWNER SUPPLY
MATERIALS & OTHER COST P 4,161,419.00
LABOR COST - 1,249,000.00
EQUIPMENT'S RENTAL ( w/ Fuel & oil ) - 6,000.00
SUBTOTAL P 5,416,419.00
PLUS: Contingency - 310,000.00
Project Management & Supervision - 107,000.00
TOTAL PROJECT COST P 5,833,419.00

(FIVE MILLION EIGHT HUNDRED THIRTY-THREE THOUSAND FOUR HUNDRED NINETEEN PESOS ONLY)

You might also like