PRDP Su - FMR Fs Outline
PRDP Su - FMR Fs Outline
Executive Summary
Crops
Barangay Total
crop 1 (in ha) crop 2 (in ha)
Brgy. 1
Total
Note on intercropping:
_____ ha are used for intercropping of __________ (insert crops intercropped)
L. Economic Indicators
1) Economic Net Present Value (ENPV) : ________
2) Economic Internal Rate of Return : ________
3) Benefit Cost Ratio : ________
M. Conclusion and Recommendations : a statement as to whether or not the project has been found feasible from the
marketing, technical, economic and operational view point.
I. Introduction
c. Existing I-REAP Enterprises to be supported by the Subproject (if none, then cite the existing agricultural
enterprise relative to the priority commodity that will be supported by the subproject)
d. Other I-BUILD Subprojects funded by the Project (Only if applicable, identify other subprojects funded by the
Project located in the same municipality/city and describe the status of its implementation. These include SPs
proposed and implemented by PLGU)
e. Estimation of RIA (Kindly calculate the total road influence area of the proposed FMR in hectares.
Two levels of delineation of RIA:
1. If possible, kindly delineate between the agricultural and residential areas
2. A second level of delineation: kindly segregate the area for each major commodity, if possible.
ii. Demographics (Brief description in 1 paragraph)
iii. Major Economy and Land Use (Brief description in 1 paragraph)
iv. On-farm data - Agricultural Area and Crops Planted, livestock and fisheries (Brief description in 1
paragraph)
v. Off-farm data – processing and marketing industry of agri-fishery products
vi. Poverty Incidence (Brief description in 1 paragraph)
a. Subproject objectives relative to % reduction in travel time and % reduction in hauling cost (PRDP SU target is 40%
reduction in average travel time from farm to markets in subproject areas and 30% reduction in hauling cost by the
end of Project); Include in the objective the need of the road to support the commodity in the VCA. Must also include
specific objectives relative to quantified benefits in economic analysis.
Note: add list approved by M&E…
IV. Project Feasibility Indicators (Responsible Component/Unit to review: Econ)
i. Supply Side (Existing Roads, Bridges and Transport System in the Road Influence Area-RIA by road type
and classification-Without Project Scenario)
ii. Describe the current road network condition in the project influence area vis-a-vis accessibility of the road
to market centers/trading points (specify also major market for products)
iii. Demand Side1 (Desired Roads, Bridges and Transport System in the Road Influence Area-RIA by road
type and classification – With Project Scenario)
Road Type (in km.)
Total
Road Gravel Earth Concrete
Classification Not
Passable Not Passable Passable Not Passable Passable Not Passable Passable
Passable
Brgy/FMR
Municipal
Provincial
National
Total
Note: The road network planning will best illustrate the supply and demand gap analysis
iv. Describe the desired road network condition in the project influence area vis-a-vis accessibility of the road
to market centers/trading points (specify also major market for products)-desired upgrade in terms of road
type and classification within PRDP lifespan)
v. Availability of public transport (land, water)
vi. Demand-Supply Analysis - Describe the gap (degree of the need) between the desired (With Project) and
current (Without Project) condition of the road network. (Include discussion/comparison on how the road
will be beneficial to the dominant commodity, as presented in VCA, with the project and without the
project.)
vii. Describe the priority (proposed) road segment out of the demand (what is the contribution of the proposed
road segment, especially to the commodity, over the demand in terms of road length ratio)
viii. Describe the Projected Traffic Volume over the priority road segment:
1. Normal Traffic Volume- increase due to increased number and usage of motor vehicles (refer
to traffic count survey for the “without” project scenario and project the traffic volume at the
end of the subproject design life for the “with” project scenario)
2. Generated traffic Volume- increase due to motor vehicle trips that would not have been
realized if the new facility had not been constructed.
3. Diverted/Attracted traffic volume- increase over existing traffic due to improvement.
4. Development/Induced traffic volume - increase due to change in land use due to construction
of the new facility.
* Combined effect of the four types of traffic is about 2% to 6% for urban and below 2% in
rural areas.
b. Technical Analysis
1
Demand Side- from the supply side or current road network by type and classification in terms of total kilometers, what
now are the total kilometers per road type of the desired road network after lining several proposals for PRDP funding. For
new construction, there will be an increase in length of concrete roads, however for rehabilitation, there will just be an
increase in concrete road length and an equivalent reduction in either earth or gravel road length or decrease in both types
to be shown in the table.
i. Horizontal road alignment analysis (describe the road type and classification of the connecting access road
(terminal points) if it is more superior than the proposed road; describe the existing road width compared
to the design road width based on traffic density <200ADT>, Are curve widening and side cut needed?
Are there permanent road obstructions?
ii. Vertical road alignment analysis (describe the terrain whether flat, rolling and mountainous, is it within
the maximum gradient of 18%, is there massive downgrading?)
iii. Drainage analysis/hydraulic analysis (describe the water catchment area and rainfall data, flood discharge
measurements, describe the minor and major river road crossings, side drainage, location and condition of
existing drainage structures)
iv. Geotechnical – soil and foundation analysis – indicate soil classification based on AASHTO Soil
Classification
v. Structural analysis of pavement thickness, bridge structures and other major structures.
vi. Proposed Sources and Location of Quarries, Borrow Pits and Construction Materials
a. Relative distance of quarry and construction materials to project site/Dumping site for surplus
excavation (Attach Certificate signed by Brgy. Captain and Lot Owner)
b. Handling of materials
c. Dependability and availability of required quantities
vii. Items of work and cost (POW Summary) – is it within the cost parameter?
viii. Implementation schedule of the sub-project (project duration, estimated start and end of construction)
c. Operational Analysis
i. Organizational Structure of the Project Management Implementing Unit (PMIU) to be set up at either the
provincial LGU, city LGU or municipal LGU, that will manage the project and their roles and
responsibilities. Mention the executive order creating the PMIU. (Pre-Implementation Phase)
ii. Plan for management during construction, key roles and responsibilities of assigned full time construction
site personnel. (Implementation Phase)
iii. Sustainability Plan (Post-Implementation)
a. Organizational Development Plan for the Operation and Maintenance Group (show the
schedule of operation and maintenance in table form)
b. Operation and Maintenance Plan and Budget (show the operation and maintenance financing
mix)
d. Social Analysis
i. Subproject Beneficiaries
ii. Indigenous Cultural Community/Indigenous Peoples (ICC/IP)
iii. Site and Right-of-Way acquisition
iv. Damage to standing crops, houses and/or properties
v. Physical displacement of persons
vi. Economic displacement of persons
vii. Grievance redress mechanism
viii. Labor-related Risks
ix. Occupational Health and Safety
x. Community Health and Safety
xi. Conflict Context Assessment
e. Environmental Analysis
i. Natural habitat
ii. Physical Cultural Resources
iii. Terrain, Soil Types and Rainfall
iv. Natural and Geologic Hazards/Risk Assessment
v. Resource Conservation and Pollution Control
vi. Integrated Pest Management/DA KASAKALIKASAN
vii. Status of Environmental Clearances
g. Financial Analysis
i. Total Project Cost by Financing Source and Cost Sharing (WB LP, GOP-DA, LGU)
- Show Table of Project Cost Sharing
- Provide a short write-up/narrative/explanation.
ii. Total Project Cost Breakdown
a. Direct
b. Indirect
- Provide a short write-up/narrative/explanation.
iii.Status of LGU equity availability and LFC certification – attach appropriation ordinance stating the 10%
equity for the SP and Cost for O & M for 10 years.
- Provide a short write-up/narrative/explanation.
-
h. Economic Analysis and Evaluation
1. Economic Benefits
- Enumerate the project benefits valuated for the analysis. Explain briefly each
benefit and how it is calculated
i. Existing vehicular traffic based on Traffic Survey Results2 and indicating representative
vehicles, passenger occupancy/average load by vehicle type, average daily trips, and
traveled /Unit to review: Econ)
Table ____a. Annual Average Daily Traffic within the subproject area, YYYY
Observed
Existing Average Ave. loading Purpose (for
No. of Average Average Transport
Mode of Operating capacity passenger or
Barangay vehicle No. of daily daily traffic Fares for
Transport in counta
Days per (passenger/ cargo/agri
Units trips year Passenger/
the Area cargo) produce)
Cargod
1) Brgy. X Motorcycle 10 6 60 300 2 persons/ 4
sacks
Jeep 2 2 10
Truck
Total
Source:
iii. Other considerations in the computation of VOC savings (i.e Length, VOC difference
● Length
- Discuss the length with improvement.
- If the proposed road is 100% new opening with the following conditions:
1. will serve as a short-cut - discuss what is the existing route of the vehicles,
the length currently being traversed and the road condition.
2. Entirely not accessible to all types of vehicles ---- VOC savings is not
applicable
2
If a traffic survey is done along the proposed road site or adjacent existing road. This may be done through classified
manual count and roadside origin-destination
● VOC Difference
- Discuss the VOC difference to be used in the computation
- Present and discuss the current road condition and corresponding length
Table ____ (No.) Commodity Production Areas to be served by the (Title of Road Sub-project), YYYY
No. of
Crop/ Area Mineral Fertilizer Seed % of
Average Turnover/ Annual
Barangay Livestock/ (in Requirement/ Requirement/ Production
Yield/ has. cropping/ Production
Fish/ Forest has.) has./ yr. has./ yr. Sold in Market
season/ yr.
1. Brgy. X
2. Brgy. Y
Source:
Source:
Source:
Source:_______________________________________
- This section should clearly discuss the existing farming practices in terms of
hauling the cost of agricultural goods going to the market and production inputs
from the market to the farm.
- Provide a short write-up/narrative/explanation for the table.
- If mode of transport differ between output and input hauling, then the 2 separate
tables must be presented
Table ____ (No.) Population within the Road Influence Area (RIA traversed and using the proposed road), YYYY
Ave. Annual Population Economically Active % of Commuters from
Number of
Barangay Population Growth Rate Population Economically Active
Household
(in %) (in %) Population
1. Brgy. X
2. Brgy. Y
Total
Source :_______________________________________
Table ____ (No.) Reduction in Transport Losses Per Crop in Barangay______, YYYY
Transport Losses Estimated Reduction in
Crop/ Fish/ Market Price Transport Losses WP
Barangay WOP Transport Losses
Forest (Php/kg.) (%)
(%) (in %)
1. Brgy. X rice 20 70 or 15/kg. 50,000.00 28,000.00
2. Brgy. Y
Total
Source:
2. Economic Costs