Work Plan Inspection of Laboratory Structural Work For 01.01.2024 (IHI) Afternoon & Evening Shift

The document outlines the daily work schedule and inspection plan for January 1st, 2024 for the Bangabandhu Sheikh Mujib Railway Bridge Construction Project in Bangladesh. It details 8 scheduled concrete strength tests to take place in the laboratory including tests for pier columns, precast blocks, base slabs, side walls, septic tanks, and lean concrete. Each test lists the concrete class, casting date, location, scheduled testing dates, and person in charge.

Uploaded by

China Civil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views6 pages

Work Plan Inspection of Laboratory Structural Work For 01.01.2024 (IHI) Afternoon & Evening Shift

The document outlines the daily work schedule and inspection plan for January 1st, 2024 for the Bangabandhu Sheikh Mujib Railway Bridge Construction Project in Bangladesh. It details 8 scheduled concrete strength tests to take place in the laboratory including tests for pier columns, precast blocks, base slabs, side walls, septic tanks, and lean concrete. Each test lists the concrete class, casting date, location, scheduled testing dates, and person in charge.

Uploaded by

China Civil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Bangladesh Railways

Bangabandhu Sheikh Mujib Railway Bridge Construction Project


Package - WD2: Western Part of Civil Works
The Engineers The Contractor
JV of OCG-CHODAI-DDC-in Association with ACE IHI-SMCC JV

Daily Work Schedule (IHI) for Structural & Laboratory Work


Date of Work Plan: 01/01 /2024
Inspection/Works Plan
SL No. Inspection Details Location Date of Inspection Time Rescheduled Time Person-In charge RFI Reference Consultant Representative Remarks

Laboratory Test
Inspection of Compressive Strength Test of Pier Column 4th Lift at Pier-08
Concrete Class-C30-15
Casting date-29/12/2023(Casting Ref:WD2-RFI(I)-16130-R1) Ekramul / Aminul
1 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16460 3days
3 days Testing date-01/01/2024 01751846727
7 days Testing date-05/01/2024
28 days Testing date-26/01/2024
Inspection of Compressive Strength Test of Precast Cement Concrete Block (300x300x200) for Embankment (575)nos
Concrete Class: C27-15
Ekramul / Aminul
2 Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16038) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16461 7days
01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Concrete Pouring of Base Slab for open ditch,
Ch: 287+000 ~ 287+020, South Side
Concrete Class: C27-15 Ekramul / Aminul
3 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16462 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16041) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Concrete Pouring of Side Wall for open ditch,
Chainage: 286+660 ~ 286+680, South Side
Concrete Class: C27-15 Ekramul / Aminul
4 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16463 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-15820 R1) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of concrete pouring of septic tank (2nd lift) at West Station Building
Concrete Class: C19-15
Ekramul / Aminul
5 Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16087) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16464 7days
01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Lean concrete pouring of open ditch (South side),
Ch: 286+960~286+980
Concrete Class: C18-15 Ekramul / Aminul
6 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16465 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16049) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Lean concrete pouring of open ditch (South side), Ch: 287+300~287+340
Concrete Class: C18-15
Ekramul / Aminul
7 Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16040) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16466 7days
01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Concrete Pouring of Base Slab for open ditch,
Chainage: 287+200 to 287+220, South Side
Concrete Class: C27-15 Ekramul / Aminul
8 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16467 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16004) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Ekramul / Aminul
9 Inspection of Mix Design for Open Stone Asphalt for River Training Work (RTW) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-14796 R1 New
01751846727
Ekramul / Aminul
10 Inspection of Mix Design for Open Stone Asphalt for River Training Work (RTW) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-14796 R1 New
01751846727
Inspection of Compressive Strength Test of Pier Column 3rd Lift at Pier-23 Ekramul / Aminul
11 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16211 7days
Concrete Class-C30-15 01751846727

Inspection of Compressive Strength Test of lean concrete pouring of open ditch (South side), Ekramul / Aminul
12 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15250 28 days
Ch: 286+600~286+620 Concrete Class-C18-15 01751846727

Inspection of Compressive Strength Test of Concrete pouring for vertical extension of the toe wall ( Left side of
embankment )at following chainages:
i) Ch: 287+362.5~287+365
Ekramul / Aminul
13 ii) Ch: 287+367.5~287+370 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15251 28 days
01751846727
iii) Ch: 287+372.5~287+375
iv) Ch: 287+377.5~287+380
Concrete Class-C18-15

1 of 6
Inspection of Compressive Strength Test of Concrete pouring of Cover Ditch Cover Slab Ekramul / Aminul
14 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15252 28 days
Qty: 30nos, Type:01 Concrete Class-C27-15 01751846727

Inspection of Compressive Strength Test of Precast Cement Concrete Block (300x300x200) for Embankment -641 nos Ekramul / Aminul
15 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15253 28 days
Concrete Class-C27-15 01751846727

Inspection of Compressive Strength Test of Concrete Pouring of Base Slab for open ditch, Ekramul / Aminul
16 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15254 28 days
Ch: 287+140- 287+160, South side Concrete Class-C27-15 01751846727

Inspection of Compressive Strength Test of Concrete pouring of septic tank side wall (2nd lift, H-1.175m) at Gate Lodge Ekramul / Aminul
17 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15255 28 days
Building Concrete Class-C28-15 01751846727

Inspection of Compressive Strength Test of CC block pitching at following chainages at Railway Embankment,
Ch: 286+800~286+820 left side ( Toe wall top 2nd stage & Berm Start )
Ch: 286+820~286+840 left side ( Toe wall top 2nd stage & Berm Start & Berm End )
Ekramul / Aminul
18 Ch: 287+140~287+160, Left side ( CC Block Edge) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15256 28 days
01751846727
Ch: 287+160~287+180, Left side ( Top of Toe Wall 2nd Stage & CC Block Edge)
Ch: 287+180~287+200, Left side ( Top of Toe Wall 2nd Stage & CC Block Edge)
Concrete Class-C27-15
RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P5 Pier Head. Ekramul / Aminul
19 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15257 28 days
Concrete Class-C27-15 01751846727

Inspection of Compressive Strength Test of Concrete Pouring for Pier Column 4th Lift at P19 Ekramul / Aminul
20 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15111 28 days
Concrete Class-C30-15 Casting date-04/12/2023(Casting Ref:WD2-RFI(I)-14848) 01751846727

Ekramul / Aminul
21 testing of ballast materials at ballast stock yard, Stock pile: 29, 30, 31 & 32 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16082 Continue
01751846727

testing of sub-ballast material (mixed material), Stock pile 15, Qty: 400 cum Ekramul / Aminul
22 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15831 Continue
Location: Near Gate 01 01751846727

Testing of Fine Aggregate (Sylhet Sand and River Sand) for permanent Concrete work Ekramul / Aminul
23 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16222 Continue
Frequency test-99 01751846727
Testing of Coarse Aggregate for Permanent Concrete work
Ekramul / Aminul
24 (20mm and 10mm stone chips) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16223 Continue
01751846727
Frequency test-89
testing of sub-ballast materials (Stock Pile-03) Ekramul / Aminul
25 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16318 Continue
Location: IHI sub-ballast yard (Ch: 283+750), Quantity: 500 m3 01751846727

testing of sub-ballast materials (Stock Pile-04) Ekramul / Aminul


26 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16319 Continue
Location: IHI sub-ballast yard (Ch: 283+750), Quantity: 500 m3 01751846727

testing of sub-ballast materials (Stock Pile-29) Ekramul / Aminul


27 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16320 Continue
Location: MAX sub-ballast yard (Ch: 284+300), Quantity: 300 m3 01751846727
testing of MDD test for excavated sand (foundation bed) for track line
Ekramul / Aminul
28 i) CH: 284+850~285+500 (line-03) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16326 Continue
01751846727
ii) CH: 284+940~285+000 (line-04)

Field Test
Rescheduled for
1 Inspection for survey layout and FDT prior to lean concrete pouring at open ditch (South side), Ch: 287+360~287+380 WD2- West Side, Inside RoW 1-Jan-24 3:00 PM 2:30 PM Arif/Touhid WD2-RFI(I)-16472 Afternoon/Eveni
ng Shift

Rescheduled for
Inspection for survey layout and FDT for back filling of South side Open ditch at CH : 286+600 -286+620 , South side,
2 WD2- West Side, Inside RoW 1-Jan-24 4:00 PM 2:00 PM Arif/Touhid WD2-RFI(I)-16473 Afternoon/Eveni
ele=variable , Layer: 5th
ng Shift

Rescheduled for
Inspection for survey layout and FDT for back filling of South side Open ditch at CH : 286+620 -286+640 , South side,
3 WD2- West Side, Inside RoW 1-Jan-24 5:00 PM 6:00 PM Arif/Touhid WD2-RFI(I)-16474 NurulAmin Afternoon/Eveni
ele=12.2 , Layer: 1st
ng Shift

Rescheduled for
Inspection for survey layout and FDT for back filling of South side Open ditch at CH : 287+060 -287+080 , South side,
4 WD2- West Side, Inside RoW 1-Jan-24 3:15 PM 5:00 PM Arif/Touhid WD2-RFI(I)-16475 NurulAmin Afternoon/Eveni
ele=12.6 , Layer: 1st
ng Shift
Inspection of Survey Layout and visual check for railway excavation of Relocated Road ( Left Side )
5 WD2- West Side, Inside RoW 1-Jan-24 3:30 PM Arif/Touhid WD2-RFI(I)-16476 Done
Start Chainage: 285+960 End Chainage:286+000
Inspection of Survey Layout and FDD test of foundation bed of base coares layer of Relocated Road ( Left Side )
6 WD2- West Side, Inside RoW 1-Jan-24 3:45 PM Arif/Touhid WD2-RFI(I)-16477 Done
Start Chainage: 285+960 End Chainage:286+000
Inspection of Survey Layout and FDT for Embankment fill of Railway Embankment ( full Width)
7 Layer: 8th layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 3:00 PM Arif/Touhid WD2-RFI(I)-16478 New
Start Chainage: 287+405.2 End Chainage:287+440.574

Inspection of Survey Layout and FDT for Embankment fill of Railway Embankment ( Left Side ) Rescheduled for
8 Layer: 6th Layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 2:30 PM 3:30 PM Arif/Touhid WD2-RFI(I)-16479 Afternoon/Eveni
Start Chainage: 287+440.574 End Chainage: 287+450 ng Shift

Inspection of Survey Layout and FDT for Embankment fill of Railway Embankment ( Right Side ) Rescheduled for
9 Layer: 6th Layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 2:45 PM 3:45 PM Arif/Touhid WD2-RFI(I)-16480 Afternoon/Eveni
Start Chainage: 287+440.574 End Chainage: 287+450.700 ng Shift

2 of 6
Inspection of Survey Layout and FDT for Cladding Layer of Railway Embankment
10 Layer: 8th Elevation: 15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16481 Done
Start Chainage : 287+405.2 End Chainage : 287+420 (Left Side of Embankment)
Inspection of Survey Layout and FDT for Cladding Layer of Railway Embankment
11 Layer: 8th Elevation: 15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 10:30 AM Arif/Touhid WD2-RFI(I)-16482 Done
Start Chainage : 287+405.2 End Chainage : 287+420 (Right Side of Embankment)
Inspection of Survey Layout and FDT for Sand filling of Railway Embankment ( Inside of A1)
12 Layer: 2nd Layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 5:00 PM Arif/Touhid WD2-RFI(I)-16483 Done
Start Chainage: 287+440.574 End Chainage: 287+449
Inspection for survey layout and FDT for back filling of South side Open ditch at
13 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16415 Done
Chainage: 286+600 to 286+620 , South side, Layer: 4th

Land
Inspection for concrete pouring of Precast Cement Concrete Block (300x300x200) for Embankment ( ), Concrete Class:
C27 WD2- West Side, CC Casting
1 1-Jan-24 7:45 AM Arif/Touhid WD2-RFI(I)-16469 New
-Pre pouring inspection Yard
-Concrete Pouring
Post Pouring Inspection of Precast Cement Concrete Block (300x300x200) for Embankment, Qty= ( 610 ) Nos, WD2- West Side, CC Casting
2 1-Jan-24 9:00 AM Arif/Touhid WD2-RFI(I)-16470 New
Casting Date: 30-12-2023 Yard
3 Post Inspection of Precast Cement Concrete Block (300x300x200) for Embankment (Surface Repair)Qty=200 Nos WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16471 New
Rescheduled for
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Side Wall for open ditch,
4 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16484 Mzaman Afternoon/Eveni
Ch: 287+280- 287+300, South Side
ng Shift
Rescheduled for
5 Post pouring inspection of south side open ditch at Ch: 287+200~287+220 WD2- West Side, Inside RoW 1-Jan-24 10:30 AM 3:00 PM Arif/Touhid WD2-RFI(I)-16485 Afternoon/Eveni
ng Shift
Rescheduled for
6 Post pouring inspection of south side open ditch at Ch: 287+260~287+280 WD2- West Side, Inside RoW 1-Jan-24 10:45 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16486 Day time work Afternoon/Eveni
ng Shift
Rescheduled for
7 Post pouring inspection of south side open ditch at Ch: 286+940~286+960 WD2- West Side, Inside RoW 1-Jan-24 9:30 AM 5:15 PM Arif/Touhid WD2-RFI(I)-16487 Afternoon/Eveni
ng Shift
Rescheduled for
8 Post pouring inspection of south side open ditch at Ch: 286+960~286+980 WD2- West Side, Inside RoW 1-Jan-24 9:40 AM 5:30 PM Arif/Touhid WD2-RFI(I)-16488 Afternoon/Eveni
ng Shift
Rescheduled for
9 Post pouring inspection of south side open ditch at Ch: 286+820~286+840 WD2- West Side, Inside RoW 1-Jan-24 3:45 PM 5:45 PM Arif/Touhid WD2-RFI(I)-16489 Day time work Afternoon/Eveni
ng Shift
Rescheduled for
10 Post pouring inspection of south side open ditch at Ch: 286+840~286+860 WD2- West Side, Inside RoW 1-Jan-24 4:30 PM 6:00 PM Arif/Touhid WD2-RFI(I)-16490 Day time work Afternoon/Eveni
ng Shift
Inspection for Concrete Pouring of CC Block pitching at Railway Embankment,
11 WD2- West Side, Inside RoW 1-Jan-24 5:00 PM Arif/Touhid WD2-RFI(I)-16491 New
Ch: 286+891.543 ~286+904.043, Right side ( Top of Toe Wall 1st Stage )
Rescheduled for
Inspection for Concrete Pouring of CC Block pitching at Railway Embankment,
12 WD2- West Side, Inside RoW 1-Jan-24 3:00 PM 5:15 PM Arif/Touhid WD2-RFI(I)-16492 Mzaman Afternoon/Eveni
Ch: 286+912 ~286+924 Right side ( Berm Start and End )
ng Shift
13 Inspection for lean concrete pouring of open ditch (South side), Ch: 287+360~287+380 WD2- West Side, Inside RoW 1-Jan-24 4:30 PM Arif/Touhid WD2-RFI(I)-16493 New
14 Inspection for rebar arrangement of Railing post, Underpass 02 (Middle Part, South Side). WD2- West Side, Inside RoW 1-Jan-24 4:45 PM Arif/Touhid WD2-RFI(I)-16494 New

Rescheduled for
Inspection for concrete pouring of weep holes of cc block pitching works of railway embankment at
15 WD2- West Side, Inside RoW 1-Jan-24 3:00 PM 4:50 PM Arif/Touhid WD2-RFI(I)-16495 Mzaman Afternoon/Eveni
Ch:286+912~286+924 Left Side
ng Shift

Rescheduled for
16 Inspection for lean concrete pouring of relocated road at Ch: 286+000~286+040 , Left Side WD2- West Side, Inside RoW 1-Jan-24 3:30 PM 4:40 PM Arif/Touhid WD2-RFI(I)-16496 Mzaman Afternoon/Eveni
ng Shift

Rescheduled for
Visual inspection for weep hole installation for cc block pitching works of railway embankment at
17 WD2- West Side, Inside RoW 1-Jan-24 11:30 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16497 Mzaman Afternoon/Eveni
Ch:286+912~286+924 Left Side
ng Shift
Visual Inspection of Turfing placement of Relocated Road Both Side,at
18 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16498 New
Ch: 0+000~0+054
Visual Inspection and Survey elevation check of 450mm width Filter layer of Railway Embankment ( Inside of A1, return
19 WD2- West Side, Inside RoW 1-Jan-24 5:30 PM Arif/Touhid WD2-RFI(I)-16499 New
wall ) Layer: 2nd Layer Elevation: + 15.3 MSL
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Base Slab for open ditch,
20 WD2- West Side, Inside RoW 1-Jan-24 9:30 AM Arif/Touhid WD2-RFI(I)-16422
Chainage: 286+860 to 286+880, South Side
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Base Slab for open ditch,
21 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16423
Chainage: 286+880 to 286+904, South Side
3 of 6
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Base Slab for open ditch,
22 WD2- West Side, Inside RoW 1-Jan-24 10:30 AM Arif/Touhid WD2-RFI(I)-16424
Chainage: 286+940 to 286+912, South Side
Rescheduled for
23 Post Inspection inner Surface of Open Ditch ( After Surface Repair ) at Chainage:286+380 to 286+480 North side WD2- West Side, Inside RoW 1-Jan-24 10:30: AM 4:00 PM Arif/Touhid WD2-RFI(I)-16427 Day time work Afternoon/Eveni
ng Shift
Rescheduled for
24 Post Inspection inner Surface of Open Ditch ( After Surface Repair ) at Chainage:286+214.5 to 286+280 North side WD2- West Side, Inside RoW 1-Jan-24 11:00 AM 4:30 PM Arif/Touhid WD2-RFI(I)-16428 Day time work Afternoon/Eveni
ng Shift
25 Visual inspection of Geotextile installation for weep holes ( 1st Layer) of A1 and return wall WD2- West Side, Inside RoW 1-Jan-24 11:15 AM Arif/Touhid WD2-RFI(I)-16431

Rescheduled for
26 Post Inspection inner Surface of Open Ditch ( After Surface Repair ) at Ch:286+280- 286+380 North side WD2- West Side, Inside RoW 1-Jan-24 11:30 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16075-R1 Day time work Afternoon/Eveni
ng Shift

Pier
1 Inspection of SPSP Cutting for Pier Head Support System at Pier P10 WD2-West Side, P10 1-Jan-24 2:00 PM Noman/Sobuj WD2-RFI(I)-16459 New
Post-Pouring (Concrete) Inspection for Pier Column 2nd Lift at P9
2 WD2- West Side, P9 1-Jan-24 4:00 PM Noman/Sobuj WD2-RFI(I)-16402 New
-Surface Preparation (Construction Joint) -Column Curing Inspection.
3 Inspection of Rebar Arrangement for Pier Column P23 (4th Lift) WD2- West Side, P23 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-16405 New
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P22
4 WD2- West Side, P22 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-16408 Continue
Pier Column 1st, 2nd & 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P13
5 WD2- West Side, P13 1-Jan-24 9:30 AM Noman/Sobuj WD2-RFI(I)-16380 Continue
Pier Head
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P19
6 WD2- West Side, P19 1-Jan-24 11:00 AM Noman/Sobuj WD2-RFI(I)-15258 Final Inspection
Pier Column 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P12
7 WD2-West Side, P12 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-16201 Continue
Pier Column 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P16
8 WD2- West Side, P16 1-Jan-24 10:00 AM Noman/Sobuj WD2-RFI(I)-15900 Continue
Pier Head
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P12
9 WD2- West Side, P12 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-15749 Final Inspection
Pier Column 1st & 2nd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P13
10 WD2- West Side, P13 1-Jan-24 10:30 AM Noman/Sobuj WD2-RFI(I)-15613 Continue
Pier Column 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P13
11 WD2- West Side, P13 1-Jan-24 10:30 AM Noman/Sobuj WD2-RFI(I)-15614 Continue
Pier Column 4th Lift.
12 Inspection of Rebar Arrangement for Pier Head at Pier P7 WD2- West Side, P7 1-Jan-24 9:30 AM Noman/Sobuj WD2-RFI(I)-15898
13 Inspection of Rebar Arrangement for Pier Head at Pier P22 WD2- West Side, P22 1-Jan-24 10:00 AM Noman/Sobuj WD2-RFI(I)-16138

RTW
Dumping/ Placing of 34th load of Hard Rock at RTW Lane No. 06 11:00 PM to
1 WD2 - RTW LANE -06 1-Jan-24 Hasan WD2-RFI(I)-15942-R1 New
Weight Measurement = MT 8:00 AM
Dumping/ Placing of 33rd load of Hard Rock at RTW Lane No. 06 2:00 PM Continue to
2 'WD2 - RTW LANE- 06 1-Jan-24 Hasan WD2-RFI(I)-15938-R1
Weight Measurement = MT to 3:00 AM Next Day
9:30 AM
3 35th TRIP - HARD ROCK LOADING TO MATERIAL BARGE BEFORE DUMPING IN RTW LANE-06 WD2 - RTW LANE -06 1-Jan-24 Hasan WD2-RFI(I)-15941 Aynul(N)+kuddus(LN)
to 10:30 PM
Dumping/ Placing of 32nd load of Hard Rock at RTW Lane No. 06 8:30 AM
4 WD2 - RTW LANE -06 1-Jan-24 Hasan WD2-RFI(I)-15937-R1 Aynul(N)
Weight Measurement = MT to 2:00 PM

Viaduct
1 Inspection of Rebar Arrangement for Ballast stopper & Duct Walls at RC Slab. WD2-West Side, Viaduct 1-Jan-24 3:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16458 New
Inspection for Final Survey Layout and Visual Check Including Side Formwork before Concrete Casting of RC Slab.
2 WD2-West Side, Viaduct 1-Jan-24 4:00 PM Hasan WD2-RFI(I)-16457 New
-Survey check -Visual Check
Inspection of Surface Repairing Work including Surface Preparation, Mixing, Application of D-Cone Hole Filling for Ballast
3 Stopper Upstream, Downstream & P1 Side WD2-West Side, Viaduct Area 28-Dec-23 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16275 Final Inspection
- Masterflow 718-70%, White Cement-30%, Water
4 Inspection for Rebar Installation for RC Slab. 'WD2 - Viaduct Area 1-Jan-24 9:45 AM Hasan WD2-RFI(I)-16200 Final Inspection

Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of PC T-
5 Girder Girder ID: G-01,G-02,G-03,G-04,G-05 & G-06. 'WD2 - Viaduct Area 1-Jan-24 10:00 AM Hasan WD2-RFI(I)-12622 Final Inspection
- Blowhole (Air Bubble)-Masterflow 718, White Cement, Water
Inspection of Surface Repairing Work including Surface Preparation, mixing, application of D-cone Hole Filling for Cross
6 Beams VP1 & P1 both side. 'WD2 - Viaduct Area 1-Jan-24 10:20 AM Hasan WD2-RFI(I)-15403 Final Inspection
- Masterflow 718-70%, White Cement-30%, Water

Track
4 of 6
Visual inspection of sleeper to rail fastening materials on site.
Quantity:
1 1. Elastic Rail Clip for UIC 60 kg Rail =110795 nos WD2-West Side, Inside RoW 1-Jan-24 9:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16500 Done
2. Elastic Rail Clip for UIC 60 kg Rail at fish plated joints = 2652 nos
Location: Max Track Materials Store
Inspection for survey layout and FDD test of sub-ballast bed at new line-03
2 WD2-West Side, Inside RoW 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16501 Done
Ch: 284+811~ 284+820, L=9.00m, W= 1.00m (Avg.), T= 150mm, Layer: 3rd layer
Post inspection of clearing & grubbing work at new line- 05
3 WD2-West Side, Inside RoW 1-Jan-24 10:30 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16502 Done
Ch: 285+480~285+560, L= 80.0m, W= 5.069m (Avg.)

Rescheduled for
Inspection for survey layout and FDD test of sub-ballast bed at new line-04
4 WD2-West Side, Inside RoW 1-Jan-24 3:00 PM 6:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16503 Tajudeen Afternoon/Eveni
Ch: 285+340~ 285+440, L=100.00m, W= 4.388m (Avg.), T= 150mm, Layer: 1st layer
ng Shift

Inspection for survey layout and FDD test of sub-ballast bed at new line-03
5 WD2-West Side, Inside RoW 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16437 Done
Ch: 284+811~ 284+820, L=9.00m, W= 1.00m (Avg.), T= 150mm, Layer: 2nd layer

Renovation
'Post pour inspection of Cover ditch cover slab, Type 02: Qty= 30 nos WD2-West Side, Inside RoW
1 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16504 Done
Casting date: 31 Dec 23, (Sl. No.: 0326~0355) Pre-cast slab yard

Rescheduled for
Post Inspection (after surface repairing) of Cover ditch cover slab, Type 02: Qty= 30 nos WD2-West Side, Inside RoW
2 1-Jan-24 4:00 PM 6:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16505 Tajudeen Afternoon/Eveni
Casting date: 01/01/2024, (Sl. No.: 0326~0355) Pre-cast slab yard
ng Shift

Gate Lodge Building


1 Inspection of brick wall works for gate lodge building WD2-West Side, Gate Lodge 1-Jan-24 11:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16000 R1 Continue

FOB
'Post pour inspection of stair column (1st lift) at FOB (North side),
1 WD2-West Side, Inside RoW 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16511 Done
GL: (F8~F9) / (A&C)
'Inspection for rough surface between stair column (1st lift top and stair beam-1 bottom) at FOB (North side)
2 WD2-West Side, Inside RoW 1-Jan-24 3:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16512 Done
GL: (F8~F9) / (A&C)
Inspection for rebar arrangement of stair column (2nd lift, H-1.00m) at FOB (North side). WD2-West Side, Foot Over
3 1-Jan-24 3:30 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16455 Done
GL: (A&C) / F8, Bridge

Truss
WD-2: East Side,Superstructure
1 Inspection of Touch Up Paint for Shipment 05 1-Jan-24 10:00 AM Mehedi/Zerin WD2-RFI(I)-16513 New
Steel Truss Storage Yard

2 Visual Inspection for STB after Tightening Type B (P3-P4) (L6-L8) WD2, P3-P4 1-Jan-24 10:00 AM Mehedi/Zerin WD2-RFI(I)-16208 Continue
3 Visual Inspection for STB after Tightening Type B (P3-P4) (L4-L6) WD2, West side, P3- P4 1-Jan-24 10:30 AM Mehedi/Zerin WD2-RFI(I)-16384 Continue

Station Building
Inspection for concrete pouring of long column at West Station Building
1 WD2-West Side, Station Building 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16506 Done
GL: (A&C) / 5, (C4-2Nos, 2nd lift, H-4.0m) GL: D / 5, (C3-1Nos, 1st lift, H-2.0m)
Material on-site Visual inspection for sampling and testing of 1st class machine made auto brick at West Station Building
2 WD2-West Side, Station Building 1-Jan-24 10:30 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16507 Done
Brand: BRL Qty: 10000.
Inspection for survey alignment of formwork long column at West Station Building
3 WD2-West Side, Station Building 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16442 Done
GL: (A&C) / 5, (C4-2Nos, 2nd lift, H-4.0m) GL: D / 5, (C3-1Nos, 1st lift, H-2.0m)
4 Inspection for Clay Tiles Installation Work for Equipment Room External Wall (South Side) WD2-West Side, Station Building 1-Jan-24 10:40 AM Sarwar/Jishan/Ashik WD2-RFI(I)-15909 Continue

5 Inspection for Roof Top Parapet and Stair Room Brick Work at West Station Building. GL: (2 ~ 4) / (B ~ C) WD2-West Side, Station Building 1-Jan-24 10:30 AM Sarwar/Jishan/Ashik WD2-RFI(I)-15731 Continue

6 Inspection of floor tiles work for Equipment Room at West Station Building GL: (B~C) / (2~4) WD2-West Side, Station Building 1-Jan-24 11:00 AM Sarwar/Jishan/Ashik WD2-RFI(I)-15162 R1 Done

7 Inspection for Brick Wall work at Ground Floor in West Station Building GL: (B~ D) / (1~2) & (C~D) / (2~4) WD2-West Side, Station Building 1-Jan-24 11:00 AM Sarwar/Jishan/Ashik WD2-RFI(I)-14322 R1 Done

Station Platform
Inspection for survey alignment of formwork & concrete pouring of shade column (2nd lift, H-1.550m) at Platform (North WD2-West Side, Station
1 1-Jan-24 5:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16508 New
side) GL: P15~P20 Platform

WD2-West Side, Station


2 Inspection for rough surface of shade column (1st lift top) at Platform (North side), GL: P21 1-Jan-24 2:30 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16509 New
Platform
5 of 6
WD2-West Side, Station
3 Inspection for rebar arrangement of Shade column (1st lift top to roof beam bottom) at Platform (North side). GL: P21 1-Jan-24 4:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16510 New
Platform

Inspection for survey alignment of formwork & concrete pouring of shade column (1st lift, H-1.1650m) at Platform (North WD2-West Side, Station
4 1-Jan-24 10:30 AM Ashik/Jishan/Sarwar WD2-RFI(I)-15192 R1 Done
side) GL: P29~P30 Platform
Inspection for survey alignment of formwork & concrete pouring of shade column (3rd lift, H-1.491m) at Platform (North WD2-West Side, Station
5 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16445 Done
side) GL: P41~P44 Platform

Source Visit & Sleeper Production


1 Inspection of Sampling & Testing of Perimeter Fence Materials Dhaka & Gazipur 1-Jan-24 10:00 AM Jahurul WD2-RFI(I)-16276

MAX Pre-Stress Limited


2 Inspection of PSC Plain Track & Turnouts Sleepers Manufacturing and Testing at MAX Pre-Stress Limited (January-2024) Ghatiarpara, Banglabandha, 1-Jan-24 8:00 AM Shamim Reza WD2-RFI(I)-16468 Continuous
Tetulia Panchagarah

MAX Pre-Stress Limited


Sampling and Testing of Concrete Materials (Cement, Coarse aggregate, and Fine aggregate) for Monthly (January-2024)
3 Ghatiarpara, Banglabandha, 1-Jan-24 9:00 AM Shamim Reza WD2-RFI(I)-16514 New
Quality Test for PSC Sleepers Production.
Tetulia Panchagarah

Md. Nayem Hasan


QA/QC Dept.
Date: 31/12/2023

6 of 6