Work Plan Inspection of Laboratory Structural Work For 01.01.2024 (IHI) Afternoon & Evening Shift
Work Plan Inspection of Laboratory Structural Work For 01.01.2024 (IHI) Afternoon & Evening Shift
Laboratory Test
Inspection of Compressive Strength Test of Pier Column 4th Lift at Pier-08
Concrete Class-C30-15
Casting date-29/12/2023(Casting Ref:WD2-RFI(I)-16130-R1) Ekramul / Aminul
1 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16460 3days
3 days Testing date-01/01/2024 01751846727
7 days Testing date-05/01/2024
28 days Testing date-26/01/2024
Inspection of Compressive Strength Test of Precast Cement Concrete Block (300x300x200) for Embankment (575)nos
Concrete Class: C27-15
Ekramul / Aminul
2 Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16038) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16461 7days
01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Concrete Pouring of Base Slab for open ditch,
Ch: 287+000 ~ 287+020, South Side
Concrete Class: C27-15 Ekramul / Aminul
3 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16462 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16041) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Concrete Pouring of Side Wall for open ditch,
Chainage: 286+660 ~ 286+680, South Side
Concrete Class: C27-15 Ekramul / Aminul
4 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16463 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-15820 R1) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of concrete pouring of septic tank (2nd lift) at West Station Building
Concrete Class: C19-15
Ekramul / Aminul
5 Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16087) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16464 7days
01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Lean concrete pouring of open ditch (South side),
Ch: 286+960~286+980
Concrete Class: C18-15 Ekramul / Aminul
6 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16465 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16049) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Lean concrete pouring of open ditch (South side), Ch: 287+300~287+340
Concrete Class: C18-15
Ekramul / Aminul
7 Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16040) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16466 7days
01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Inspection of Compressive Strength Test of Concrete Pouring of Base Slab for open ditch,
Chainage: 287+200 to 287+220, South Side
Concrete Class: C27-15 Ekramul / Aminul
8 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16467 7days
Casting date-25/12/2023(Casting Ref:WD2-RFI(I)-16004) 01751846727
7 days Testing date-01/12/2024
28 days Testing date-22/01/2024
Ekramul / Aminul
9 Inspection of Mix Design for Open Stone Asphalt for River Training Work (RTW) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-14796 R1 New
01751846727
Ekramul / Aminul
10 Inspection of Mix Design for Open Stone Asphalt for River Training Work (RTW) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-14796 R1 New
01751846727
Inspection of Compressive Strength Test of Pier Column 3rd Lift at Pier-23 Ekramul / Aminul
11 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16211 7days
Concrete Class-C30-15 01751846727
Inspection of Compressive Strength Test of lean concrete pouring of open ditch (South side), Ekramul / Aminul
12 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15250 28 days
Ch: 286+600~286+620 Concrete Class-C18-15 01751846727
Inspection of Compressive Strength Test of Concrete pouring for vertical extension of the toe wall ( Left side of
embankment )at following chainages:
i) Ch: 287+362.5~287+365
Ekramul / Aminul
13 ii) Ch: 287+367.5~287+370 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15251 28 days
01751846727
iii) Ch: 287+372.5~287+375
iv) Ch: 287+377.5~287+380
Concrete Class-C18-15
1 of 6
Inspection of Compressive Strength Test of Concrete pouring of Cover Ditch Cover Slab Ekramul / Aminul
14 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15252 28 days
Qty: 30nos, Type:01 Concrete Class-C27-15 01751846727
Inspection of Compressive Strength Test of Precast Cement Concrete Block (300x300x200) for Embankment -641 nos Ekramul / Aminul
15 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15253 28 days
Concrete Class-C27-15 01751846727
Inspection of Compressive Strength Test of Concrete Pouring of Base Slab for open ditch, Ekramul / Aminul
16 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15254 28 days
Ch: 287+140- 287+160, South side Concrete Class-C27-15 01751846727
Inspection of Compressive Strength Test of Concrete pouring of septic tank side wall (2nd lift, H-1.175m) at Gate Lodge Ekramul / Aminul
17 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15255 28 days
Building Concrete Class-C28-15 01751846727
Inspection of Compressive Strength Test of CC block pitching at following chainages at Railway Embankment,
Ch: 286+800~286+820 left side ( Toe wall top 2nd stage & Berm Start )
Ch: 286+820~286+840 left side ( Toe wall top 2nd stage & Berm Start & Berm End )
Ekramul / Aminul
18 Ch: 287+140~287+160, Left side ( CC Block Edge) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15256 28 days
01751846727
Ch: 287+160~287+180, Left side ( Top of Toe Wall 2nd Stage & CC Block Edge)
Ch: 287+180~287+200, Left side ( Top of Toe Wall 2nd Stage & CC Block Edge)
Concrete Class-C27-15
RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P5 Pier Head. Ekramul / Aminul
19 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15257 28 days
Concrete Class-C27-15 01751846727
Inspection of Compressive Strength Test of Concrete Pouring for Pier Column 4th Lift at P19 Ekramul / Aminul
20 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15111 28 days
Concrete Class-C30-15 Casting date-04/12/2023(Casting Ref:WD2-RFI(I)-14848) 01751846727
Ekramul / Aminul
21 testing of ballast materials at ballast stock yard, Stock pile: 29, 30, 31 & 32 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16082 Continue
01751846727
testing of sub-ballast material (mixed material), Stock pile 15, Qty: 400 cum Ekramul / Aminul
22 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-15831 Continue
Location: Near Gate 01 01751846727
Testing of Fine Aggregate (Sylhet Sand and River Sand) for permanent Concrete work Ekramul / Aminul
23 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16222 Continue
Frequency test-99 01751846727
Testing of Coarse Aggregate for Permanent Concrete work
Ekramul / Aminul
24 (20mm and 10mm stone chips) East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16223 Continue
01751846727
Frequency test-89
testing of sub-ballast materials (Stock Pile-03) Ekramul / Aminul
25 East Side (Site Laboratory) 1-Jan-24 9:00 AM WD2-RFI(I)-16318 Continue
Location: IHI sub-ballast yard (Ch: 283+750), Quantity: 500 m3 01751846727
Field Test
Rescheduled for
1 Inspection for survey layout and FDT prior to lean concrete pouring at open ditch (South side), Ch: 287+360~287+380 WD2- West Side, Inside RoW 1-Jan-24 3:00 PM 2:30 PM Arif/Touhid WD2-RFI(I)-16472 Afternoon/Eveni
ng Shift
Rescheduled for
Inspection for survey layout and FDT for back filling of South side Open ditch at CH : 286+600 -286+620 , South side,
2 WD2- West Side, Inside RoW 1-Jan-24 4:00 PM 2:00 PM Arif/Touhid WD2-RFI(I)-16473 Afternoon/Eveni
ele=variable , Layer: 5th
ng Shift
Rescheduled for
Inspection for survey layout and FDT for back filling of South side Open ditch at CH : 286+620 -286+640 , South side,
3 WD2- West Side, Inside RoW 1-Jan-24 5:00 PM 6:00 PM Arif/Touhid WD2-RFI(I)-16474 NurulAmin Afternoon/Eveni
ele=12.2 , Layer: 1st
ng Shift
Rescheduled for
Inspection for survey layout and FDT for back filling of South side Open ditch at CH : 287+060 -287+080 , South side,
4 WD2- West Side, Inside RoW 1-Jan-24 3:15 PM 5:00 PM Arif/Touhid WD2-RFI(I)-16475 NurulAmin Afternoon/Eveni
ele=12.6 , Layer: 1st
ng Shift
Inspection of Survey Layout and visual check for railway excavation of Relocated Road ( Left Side )
5 WD2- West Side, Inside RoW 1-Jan-24 3:30 PM Arif/Touhid WD2-RFI(I)-16476 Done
Start Chainage: 285+960 End Chainage:286+000
Inspection of Survey Layout and FDD test of foundation bed of base coares layer of Relocated Road ( Left Side )
6 WD2- West Side, Inside RoW 1-Jan-24 3:45 PM Arif/Touhid WD2-RFI(I)-16477 Done
Start Chainage: 285+960 End Chainage:286+000
Inspection of Survey Layout and FDT for Embankment fill of Railway Embankment ( full Width)
7 Layer: 8th layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 3:00 PM Arif/Touhid WD2-RFI(I)-16478 New
Start Chainage: 287+405.2 End Chainage:287+440.574
Inspection of Survey Layout and FDT for Embankment fill of Railway Embankment ( Left Side ) Rescheduled for
8 Layer: 6th Layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 2:30 PM 3:30 PM Arif/Touhid WD2-RFI(I)-16479 Afternoon/Eveni
Start Chainage: 287+440.574 End Chainage: 287+450 ng Shift
Inspection of Survey Layout and FDT for Embankment fill of Railway Embankment ( Right Side ) Rescheduled for
9 Layer: 6th Layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 2:45 PM 3:45 PM Arif/Touhid WD2-RFI(I)-16480 Afternoon/Eveni
Start Chainage: 287+440.574 End Chainage: 287+450.700 ng Shift
2 of 6
Inspection of Survey Layout and FDT for Cladding Layer of Railway Embankment
10 Layer: 8th Elevation: 15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16481 Done
Start Chainage : 287+405.2 End Chainage : 287+420 (Left Side of Embankment)
Inspection of Survey Layout and FDT for Cladding Layer of Railway Embankment
11 Layer: 8th Elevation: 15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 10:30 AM Arif/Touhid WD2-RFI(I)-16482 Done
Start Chainage : 287+405.2 End Chainage : 287+420 (Right Side of Embankment)
Inspection of Survey Layout and FDT for Sand filling of Railway Embankment ( Inside of A1)
12 Layer: 2nd Layer Elevation: +15.3 MSL WD2- West Side, Inside RoW 1-Jan-24 5:00 PM Arif/Touhid WD2-RFI(I)-16483 Done
Start Chainage: 287+440.574 End Chainage: 287+449
Inspection for survey layout and FDT for back filling of South side Open ditch at
13 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16415 Done
Chainage: 286+600 to 286+620 , South side, Layer: 4th
Land
Inspection for concrete pouring of Precast Cement Concrete Block (300x300x200) for Embankment ( ), Concrete Class:
C27 WD2- West Side, CC Casting
1 1-Jan-24 7:45 AM Arif/Touhid WD2-RFI(I)-16469 New
-Pre pouring inspection Yard
-Concrete Pouring
Post Pouring Inspection of Precast Cement Concrete Block (300x300x200) for Embankment, Qty= ( 610 ) Nos, WD2- West Side, CC Casting
2 1-Jan-24 9:00 AM Arif/Touhid WD2-RFI(I)-16470 New
Casting Date: 30-12-2023 Yard
3 Post Inspection of Precast Cement Concrete Block (300x300x200) for Embankment (Surface Repair)Qty=200 Nos WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16471 New
Rescheduled for
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Side Wall for open ditch,
4 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16484 Mzaman Afternoon/Eveni
Ch: 287+280- 287+300, South Side
ng Shift
Rescheduled for
5 Post pouring inspection of south side open ditch at Ch: 287+200~287+220 WD2- West Side, Inside RoW 1-Jan-24 10:30 AM 3:00 PM Arif/Touhid WD2-RFI(I)-16485 Afternoon/Eveni
ng Shift
Rescheduled for
6 Post pouring inspection of south side open ditch at Ch: 287+260~287+280 WD2- West Side, Inside RoW 1-Jan-24 10:45 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16486 Day time work Afternoon/Eveni
ng Shift
Rescheduled for
7 Post pouring inspection of south side open ditch at Ch: 286+940~286+960 WD2- West Side, Inside RoW 1-Jan-24 9:30 AM 5:15 PM Arif/Touhid WD2-RFI(I)-16487 Afternoon/Eveni
ng Shift
Rescheduled for
8 Post pouring inspection of south side open ditch at Ch: 286+960~286+980 WD2- West Side, Inside RoW 1-Jan-24 9:40 AM 5:30 PM Arif/Touhid WD2-RFI(I)-16488 Afternoon/Eveni
ng Shift
Rescheduled for
9 Post pouring inspection of south side open ditch at Ch: 286+820~286+840 WD2- West Side, Inside RoW 1-Jan-24 3:45 PM 5:45 PM Arif/Touhid WD2-RFI(I)-16489 Day time work Afternoon/Eveni
ng Shift
Rescheduled for
10 Post pouring inspection of south side open ditch at Ch: 286+840~286+860 WD2- West Side, Inside RoW 1-Jan-24 4:30 PM 6:00 PM Arif/Touhid WD2-RFI(I)-16490 Day time work Afternoon/Eveni
ng Shift
Inspection for Concrete Pouring of CC Block pitching at Railway Embankment,
11 WD2- West Side, Inside RoW 1-Jan-24 5:00 PM Arif/Touhid WD2-RFI(I)-16491 New
Ch: 286+891.543 ~286+904.043, Right side ( Top of Toe Wall 1st Stage )
Rescheduled for
Inspection for Concrete Pouring of CC Block pitching at Railway Embankment,
12 WD2- West Side, Inside RoW 1-Jan-24 3:00 PM 5:15 PM Arif/Touhid WD2-RFI(I)-16492 Mzaman Afternoon/Eveni
Ch: 286+912 ~286+924 Right side ( Berm Start and End )
ng Shift
13 Inspection for lean concrete pouring of open ditch (South side), Ch: 287+360~287+380 WD2- West Side, Inside RoW 1-Jan-24 4:30 PM Arif/Touhid WD2-RFI(I)-16493 New
14 Inspection for rebar arrangement of Railing post, Underpass 02 (Middle Part, South Side). WD2- West Side, Inside RoW 1-Jan-24 4:45 PM Arif/Touhid WD2-RFI(I)-16494 New
Rescheduled for
Inspection for concrete pouring of weep holes of cc block pitching works of railway embankment at
15 WD2- West Side, Inside RoW 1-Jan-24 3:00 PM 4:50 PM Arif/Touhid WD2-RFI(I)-16495 Mzaman Afternoon/Eveni
Ch:286+912~286+924 Left Side
ng Shift
Rescheduled for
16 Inspection for lean concrete pouring of relocated road at Ch: 286+000~286+040 , Left Side WD2- West Side, Inside RoW 1-Jan-24 3:30 PM 4:40 PM Arif/Touhid WD2-RFI(I)-16496 Mzaman Afternoon/Eveni
ng Shift
Rescheduled for
Visual inspection for weep hole installation for cc block pitching works of railway embankment at
17 WD2- West Side, Inside RoW 1-Jan-24 11:30 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16497 Mzaman Afternoon/Eveni
Ch:286+912~286+924 Left Side
ng Shift
Visual Inspection of Turfing placement of Relocated Road Both Side,at
18 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16498 New
Ch: 0+000~0+054
Visual Inspection and Survey elevation check of 450mm width Filter layer of Railway Embankment ( Inside of A1, return
19 WD2- West Side, Inside RoW 1-Jan-24 5:30 PM Arif/Touhid WD2-RFI(I)-16499 New
wall ) Layer: 2nd Layer Elevation: + 15.3 MSL
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Base Slab for open ditch,
20 WD2- West Side, Inside RoW 1-Jan-24 9:30 AM Arif/Touhid WD2-RFI(I)-16422
Chainage: 286+860 to 286+880, South Side
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Base Slab for open ditch,
21 WD2- West Side, Inside RoW 1-Jan-24 10:00 AM Arif/Touhid WD2-RFI(I)-16423
Chainage: 286+880 to 286+904, South Side
3 of 6
Inspection of Rebar Arrangement, Formwork Alignment Check & Concrete Pouring of Base Slab for open ditch,
22 WD2- West Side, Inside RoW 1-Jan-24 10:30 AM Arif/Touhid WD2-RFI(I)-16424
Chainage: 286+940 to 286+912, South Side
Rescheduled for
23 Post Inspection inner Surface of Open Ditch ( After Surface Repair ) at Chainage:286+380 to 286+480 North side WD2- West Side, Inside RoW 1-Jan-24 10:30: AM 4:00 PM Arif/Touhid WD2-RFI(I)-16427 Day time work Afternoon/Eveni
ng Shift
Rescheduled for
24 Post Inspection inner Surface of Open Ditch ( After Surface Repair ) at Chainage:286+214.5 to 286+280 North side WD2- West Side, Inside RoW 1-Jan-24 11:00 AM 4:30 PM Arif/Touhid WD2-RFI(I)-16428 Day time work Afternoon/Eveni
ng Shift
25 Visual inspection of Geotextile installation for weep holes ( 1st Layer) of A1 and return wall WD2- West Side, Inside RoW 1-Jan-24 11:15 AM Arif/Touhid WD2-RFI(I)-16431
Rescheduled for
26 Post Inspection inner Surface of Open Ditch ( After Surface Repair ) at Ch:286+280- 286+380 North side WD2- West Side, Inside RoW 1-Jan-24 11:30 AM 5:00 PM Arif/Touhid WD2-RFI(I)-16075-R1 Day time work Afternoon/Eveni
ng Shift
Pier
1 Inspection of SPSP Cutting for Pier Head Support System at Pier P10 WD2-West Side, P10 1-Jan-24 2:00 PM Noman/Sobuj WD2-RFI(I)-16459 New
Post-Pouring (Concrete) Inspection for Pier Column 2nd Lift at P9
2 WD2- West Side, P9 1-Jan-24 4:00 PM Noman/Sobuj WD2-RFI(I)-16402 New
-Surface Preparation (Construction Joint) -Column Curing Inspection.
3 Inspection of Rebar Arrangement for Pier Column P23 (4th Lift) WD2- West Side, P23 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-16405 New
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P22
4 WD2- West Side, P22 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-16408 Continue
Pier Column 1st, 2nd & 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P13
5 WD2- West Side, P13 1-Jan-24 9:30 AM Noman/Sobuj WD2-RFI(I)-16380 Continue
Pier Head
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P19
6 WD2- West Side, P19 1-Jan-24 11:00 AM Noman/Sobuj WD2-RFI(I)-15258 Final Inspection
Pier Column 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P12
7 WD2-West Side, P12 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-16201 Continue
Pier Column 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P16
8 WD2- West Side, P16 1-Jan-24 10:00 AM Noman/Sobuj WD2-RFI(I)-15900 Continue
Pier Head
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P12
9 WD2- West Side, P12 1-Jan-24 9:00 AM Noman/Sobuj WD2-RFI(I)-15749 Final Inspection
Pier Column 1st & 2nd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P13
10 WD2- West Side, P13 1-Jan-24 10:30 AM Noman/Sobuj WD2-RFI(I)-15613 Continue
Pier Column 3rd Lift.
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of P13
11 WD2- West Side, P13 1-Jan-24 10:30 AM Noman/Sobuj WD2-RFI(I)-15614 Continue
Pier Column 4th Lift.
12 Inspection of Rebar Arrangement for Pier Head at Pier P7 WD2- West Side, P7 1-Jan-24 9:30 AM Noman/Sobuj WD2-RFI(I)-15898
13 Inspection of Rebar Arrangement for Pier Head at Pier P22 WD2- West Side, P22 1-Jan-24 10:00 AM Noman/Sobuj WD2-RFI(I)-16138
RTW
Dumping/ Placing of 34th load of Hard Rock at RTW Lane No. 06 11:00 PM to
1 WD2 - RTW LANE -06 1-Jan-24 Hasan WD2-RFI(I)-15942-R1 New
Weight Measurement = MT 8:00 AM
Dumping/ Placing of 33rd load of Hard Rock at RTW Lane No. 06 2:00 PM Continue to
2 'WD2 - RTW LANE- 06 1-Jan-24 Hasan WD2-RFI(I)-15938-R1
Weight Measurement = MT to 3:00 AM Next Day
9:30 AM
3 35th TRIP - HARD ROCK LOADING TO MATERIAL BARGE BEFORE DUMPING IN RTW LANE-06 WD2 - RTW LANE -06 1-Jan-24 Hasan WD2-RFI(I)-15941 Aynul(N)+kuddus(LN)
to 10:30 PM
Dumping/ Placing of 32nd load of Hard Rock at RTW Lane No. 06 8:30 AM
4 WD2 - RTW LANE -06 1-Jan-24 Hasan WD2-RFI(I)-15937-R1 Aynul(N)
Weight Measurement = MT to 2:00 PM
Viaduct
1 Inspection of Rebar Arrangement for Ballast stopper & Duct Walls at RC Slab. WD2-West Side, Viaduct 1-Jan-24 3:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16458 New
Inspection for Final Survey Layout and Visual Check Including Side Formwork before Concrete Casting of RC Slab.
2 WD2-West Side, Viaduct 1-Jan-24 4:00 PM Hasan WD2-RFI(I)-16457 New
-Survey check -Visual Check
Inspection of Surface Repairing Work including Surface Preparation, Mixing, Application of D-Cone Hole Filling for Ballast
3 Stopper Upstream, Downstream & P1 Side WD2-West Side, Viaduct Area 28-Dec-23 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16275 Final Inspection
- Masterflow 718-70%, White Cement-30%, Water
4 Inspection for Rebar Installation for RC Slab. 'WD2 - Viaduct Area 1-Jan-24 9:45 AM Hasan WD2-RFI(I)-16200 Final Inspection
Inspection of RCC Structure Surface Repairing Work Including Surface Preparation, Mixing, Application & Curing of PC T-
5 Girder Girder ID: G-01,G-02,G-03,G-04,G-05 & G-06. 'WD2 - Viaduct Area 1-Jan-24 10:00 AM Hasan WD2-RFI(I)-12622 Final Inspection
- Blowhole (Air Bubble)-Masterflow 718, White Cement, Water
Inspection of Surface Repairing Work including Surface Preparation, mixing, application of D-cone Hole Filling for Cross
6 Beams VP1 & P1 both side. 'WD2 - Viaduct Area 1-Jan-24 10:20 AM Hasan WD2-RFI(I)-15403 Final Inspection
- Masterflow 718-70%, White Cement-30%, Water
Track
4 of 6
Visual inspection of sleeper to rail fastening materials on site.
Quantity:
1 1. Elastic Rail Clip for UIC 60 kg Rail =110795 nos WD2-West Side, Inside RoW 1-Jan-24 9:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16500 Done
2. Elastic Rail Clip for UIC 60 kg Rail at fish plated joints = 2652 nos
Location: Max Track Materials Store
Inspection for survey layout and FDD test of sub-ballast bed at new line-03
2 WD2-West Side, Inside RoW 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16501 Done
Ch: 284+811~ 284+820, L=9.00m, W= 1.00m (Avg.), T= 150mm, Layer: 3rd layer
Post inspection of clearing & grubbing work at new line- 05
3 WD2-West Side, Inside RoW 1-Jan-24 10:30 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16502 Done
Ch: 285+480~285+560, L= 80.0m, W= 5.069m (Avg.)
Rescheduled for
Inspection for survey layout and FDD test of sub-ballast bed at new line-04
4 WD2-West Side, Inside RoW 1-Jan-24 3:00 PM 6:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16503 Tajudeen Afternoon/Eveni
Ch: 285+340~ 285+440, L=100.00m, W= 4.388m (Avg.), T= 150mm, Layer: 1st layer
ng Shift
Inspection for survey layout and FDD test of sub-ballast bed at new line-03
5 WD2-West Side, Inside RoW 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16437 Done
Ch: 284+811~ 284+820, L=9.00m, W= 1.00m (Avg.), T= 150mm, Layer: 2nd layer
Renovation
'Post pour inspection of Cover ditch cover slab, Type 02: Qty= 30 nos WD2-West Side, Inside RoW
1 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16504 Done
Casting date: 31 Dec 23, (Sl. No.: 0326~0355) Pre-cast slab yard
Rescheduled for
Post Inspection (after surface repairing) of Cover ditch cover slab, Type 02: Qty= 30 nos WD2-West Side, Inside RoW
2 1-Jan-24 4:00 PM 6:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16505 Tajudeen Afternoon/Eveni
Casting date: 01/01/2024, (Sl. No.: 0326~0355) Pre-cast slab yard
ng Shift
FOB
'Post pour inspection of stair column (1st lift) at FOB (North side),
1 WD2-West Side, Inside RoW 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16511 Done
GL: (F8~F9) / (A&C)
'Inspection for rough surface between stair column (1st lift top and stair beam-1 bottom) at FOB (North side)
2 WD2-West Side, Inside RoW 1-Jan-24 3:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16512 Done
GL: (F8~F9) / (A&C)
Inspection for rebar arrangement of stair column (2nd lift, H-1.00m) at FOB (North side). WD2-West Side, Foot Over
3 1-Jan-24 3:30 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16455 Done
GL: (A&C) / F8, Bridge
Truss
WD-2: East Side,Superstructure
1 Inspection of Touch Up Paint for Shipment 05 1-Jan-24 10:00 AM Mehedi/Zerin WD2-RFI(I)-16513 New
Steel Truss Storage Yard
2 Visual Inspection for STB after Tightening Type B (P3-P4) (L6-L8) WD2, P3-P4 1-Jan-24 10:00 AM Mehedi/Zerin WD2-RFI(I)-16208 Continue
3 Visual Inspection for STB after Tightening Type B (P3-P4) (L4-L6) WD2, West side, P3- P4 1-Jan-24 10:30 AM Mehedi/Zerin WD2-RFI(I)-16384 Continue
Station Building
Inspection for concrete pouring of long column at West Station Building
1 WD2-West Side, Station Building 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16506 Done
GL: (A&C) / 5, (C4-2Nos, 2nd lift, H-4.0m) GL: D / 5, (C3-1Nos, 1st lift, H-2.0m)
Material on-site Visual inspection for sampling and testing of 1st class machine made auto brick at West Station Building
2 WD2-West Side, Station Building 1-Jan-24 10:30 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16507 Done
Brand: BRL Qty: 10000.
Inspection for survey alignment of formwork long column at West Station Building
3 WD2-West Side, Station Building 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16442 Done
GL: (A&C) / 5, (C4-2Nos, 2nd lift, H-4.0m) GL: D / 5, (C3-1Nos, 1st lift, H-2.0m)
4 Inspection for Clay Tiles Installation Work for Equipment Room External Wall (South Side) WD2-West Side, Station Building 1-Jan-24 10:40 AM Sarwar/Jishan/Ashik WD2-RFI(I)-15909 Continue
5 Inspection for Roof Top Parapet and Stair Room Brick Work at West Station Building. GL: (2 ~ 4) / (B ~ C) WD2-West Side, Station Building 1-Jan-24 10:30 AM Sarwar/Jishan/Ashik WD2-RFI(I)-15731 Continue
6 Inspection of floor tiles work for Equipment Room at West Station Building GL: (B~C) / (2~4) WD2-West Side, Station Building 1-Jan-24 11:00 AM Sarwar/Jishan/Ashik WD2-RFI(I)-15162 R1 Done
7 Inspection for Brick Wall work at Ground Floor in West Station Building GL: (B~ D) / (1~2) & (C~D) / (2~4) WD2-West Side, Station Building 1-Jan-24 11:00 AM Sarwar/Jishan/Ashik WD2-RFI(I)-14322 R1 Done
Station Platform
Inspection for survey alignment of formwork & concrete pouring of shade column (2nd lift, H-1.550m) at Platform (North WD2-West Side, Station
1 1-Jan-24 5:00 PM Ashik/Jishan/Sarwar WD2-RFI(I)-16508 New
side) GL: P15~P20 Platform
Inspection for survey alignment of formwork & concrete pouring of shade column (1st lift, H-1.1650m) at Platform (North WD2-West Side, Station
4 1-Jan-24 10:30 AM Ashik/Jishan/Sarwar WD2-RFI(I)-15192 R1 Done
side) GL: P29~P30 Platform
Inspection for survey alignment of formwork & concrete pouring of shade column (3rd lift, H-1.491m) at Platform (North WD2-West Side, Station
5 1-Jan-24 10:00 AM Ashik/Jishan/Sarwar WD2-RFI(I)-16445 Done
side) GL: P41~P44 Platform
6 of 6