The BIM (Building Information Modeling) is a powerful tool that has taken almost two
decades to develop. In the past few years, the use of BIM tools has been under increasing
pressure from many architects, engineers, and consultants (AEC industry), so construction
companies are now beginning to adopt these innovative ways to increase productivity. One
of the technologies that have emerged over the past decade and a half is the creation of
information modeling (BIM). This technology has made the design more sophisticated due
to the evolution of technologies that support BIM. Currently, the model industry in
developed countries can support not only 3D models, but also the areas of construction
management as well as planning, cost control, evaluation, safety education and
sustainability. This study focuses on identifying the problems / problems you face when
adopting BIM in a developing country. Prior knowledge of problems / potential problems
can be the difference between successful adoption and the inability to adopt BIM in a
timely and cost-effective manner [1].
*
Corresponding author: [email protected]
© The Authors, published by EDP Sciences. This is an open access article distributed under the terms of the Creative
Commons Attribution License 4.0 (http://creativecommons.org/licenses/by/4.0/).
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019
2
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019
construction process that may in turn help eradicate poverty in developing countries
(United Nations Millennium Goals) [12].
The use of BIM in a different area is expanding because researchers realize the potential
value of BIM can provide [13]. While the use of BIM for structural and energy analysis
with 27% and 25% frequencies, respectively, its main use is still in the faster development
of 3D geometric models and 3D synchronization with usable frequencies; [13] Has been
reported. The use of BIM is not limited to architects and engineers. There are also
incentives for owners, facility managers, contractors, and fabricators to use BIM [14].
Many of the important factors that lead to the adoption of BIM in a project are focused
on automation in the modeling process, improving the accuracy of construction documents,
improving inter-party communication in the design and construction process, automatically
reflecting changes in design. All observations after correcting a view and reducing
background coordination problems [13]. While many applications of BIM are dedicated to
building design, the emphasis is on some other areas, such as the use of BIM in energy
modeling, which cannot be referred to as BBIP. A review of the relatively comprehensive
literature on BIM and its applications shows that most sources, focusing mainly on
planning, design, construction, operation, and energy consumption, with the publication of
a more focused archive on energy design and consumption [15].
3
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019
3 Results
4
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019
6
5
4 China
3 India
2 Malaysia
1
0
2007 2008 2009 2010 2011 2012 2013 2014 2015
4 Discussion
5
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019
In other words, the main difference between BIM and conventional 3D CAD is that the
latter describes a building with Independent 3D displays such as plans, Section and
elevations. Editing one of these views requires that all other views be reviewed and
updated, and the error prone process being one of the main causes of poor documentation
[14]. In addition, the data in these 3D maps are only graphical entities, such as lines, bows
and circles, as opposed to the contextual meaning of BIM models, in which objects are
defined in terms of elements and systems such as spaces. , Walls, beams and columns [23].
Building information model carries all building related information, including its
physical and functional features and information lifecycle project, in a series of "smart
objects". For example, an air conditioning unit in a BIM also includes data on suppliers,
operations and maintenance procedures, flow rate and clearance conditions [24]. Also,
below, the efficiency of BIM compared to Auto CAD in the Indian industry is shown in
Table 2.
The Efficiency Difference Between CAD and BIM Applications for Particular
Project in Different Phases
Task CAD BIM Hours Saved Time
Schematic (Hours)
190 (Hours)
90 100 Savings
53%
Design Development 436 220 216 50%
Construction Documents 1023 815 208 20%
Checking and 175 16 159 91%
Coordination
Totals 1824 1141 683
The initial costs of BIM can be significant due to the investment required in software,
technology infrastructure, consultants and training [25]. Organizations also incur project-
6
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019
specific costs for setting up BIM models and changing workflows and team processes.
However, companies looking to estimate the financial benefits of BIM often find limited
information. This lack of detailed cost-benefit analysis may select some decisions against
investment [26]. Figures 2 and 3 show that BIM results in a change in the allocation of
resources and costs associated with the early stages of the project. Compared to the
traditional 3D CAD approach with BIM, BIM is considered more efficient and less time
consuming, so it is less expensive.
5 Conclusions
The BIM Using concentrates stakeholder engagement throughout the building’s life cycle.
At the same time, it provides a central repository of information, which can be accessed by
any interested party, when necessary, for the optimal and most efficient use of available
information. BIM will only succeed if stakeholders work together to achieve a shared
vision based on a common plan. This will allow society to take advantage of the many
benefits of BIM, including more accessible infrastructure and housing, a safer and more
predictable project implementation, a more sustainable and sustainable environment, and
high-quality provision of services to end-users.
Fig. 3. When using BIM, most of the effort happens during the construction documentation phase
when the ability to impact project cost and performance is declining and the cost of making design
changes is increasing.
7
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019
Fig. 4. Using a BIM workflow shifts the level of effort to earlier in the project when the ability to
impact project cost and performance is high and the cost of making design changes is low .
References
1. E. M. Nur, M. S. Rozana, L. B. Hamizah, A. Tajul, International Conference on
Research and Innovation in Information Systems (ICRIIS), 1-7 (2017)
2. Associated General Contractors of America, The Contractor’s Guide to BIM, 1st ed.
(AGC Research Foundation, Las Vegas, NV, 2005)
3. A. N. Boukara, A. Brief, Introduction to Building Information Modeling (2015)
4. A. Borrmann, M. König, C. Koch, J. Beetz, Building Information Modeling (Springer,
2015)
5. S. Azhar, A. Nadeem, Y. N. Johnny, H. Mok, Y. Leung, First International Conference
on Construction in Developing Countries (ICCIDC–I) 1, 435-436 (2008)
6. S. L. Fan, J. Miroslaw, W. H. Skibniewski Tsung, Journal of Applied Science and
Engineering 17(2), 157-166 (2014)
7. NBIMS, National BIM Standard - United States, Version 3-Scope, 1–5 (2015).
https://www.nationalbimstandard.org/
8. S. Azhar, M. Khalfan, T. Maqsood, Australasian Journal of Construction Economics and
Building 12 (4), 15-28, (2012)
9. B. Abbasnejad, H. I. Moud, International Journal of Engineering Research and
Applications, 2248-9622 (2013)
10. G. Yilmaz, A. Akcamete, O. Demirors, Automation in Construction 101, 245-263
(2019). DOI: 10.1016/j.autcon.2018.10.022
11. M. Marzouk, A. Abdel Aty, Construction research congress (2012), 2320-2328 (2012)
12. N. Bui, C. Merschbrock, B. E. Munkvold, Procedia Engineering 164, 487-494 (2016)
13. R. Kreider, J. Messner, C. Dubler, Proceeding of the 6th International Conference on
Innovation in Architecture, Engineering and Constraction,1-10 (2010). http://
bim.psu.edu/uses/Freq-Benefit/BIM_Use-2010_Innovation_in_AEC-
Kreider_Messner_Dubler.pdf
8
E3S Web of Conferences 164, 08002 (2020) https://doi.org/10.1051/e3sconf /202016408002
TPACEE-2019