Estimate Model Question
Estimate Model Question
MODEL QUESTION
1. Choose the correct answer from the given alternatives (any fifteen): 2x10 = 20
i. The plinth area of building not includes
a) Area of the walls at the floor level
b) Internal shaft for sanitary installation up to 2 sq. m in area
c) Lift and wall including landing
d) Area of cantilevered porch
ii. According to Indian standards institute, the actual size of modular brick is
a) 23cm x 11.5cm x 7.5cm
b) 25cm x 13cm x 7.5cm
c) 19cm x 9cm x 9cm
d) 20cm x 10cm x 10cm
iii. Brick walls are measured in sq. m if the thickness of the wall is
a) 10cm
b) 15cm
c) 25.5cm
d) None of these.
iv. Calculate the required of shuttering for 150mm thick R.C.C. slab in 1:1.5:3
ratio and size of slab is 10m x 10m.
a) 106sq-m
b) 100sq-m
c) 105sq-m
d) None of these.
v. In long and short wall method of estimation, the length of long wall is the centre to
centre distance between the wall and
a) Breadth of the wall
b) Half breadth of wall on each side
c) One fourth breadth of wall on each side
d) None of these.
vi. The floor area includes the are of the balcony up to
a) 100%
b) 75%
c) 50%
d) 25%
vii. The most reliable estimate is
a) Detailed estimate
b) Preliminary estimate
c) Plinth area estimate
d) (b) and (c) both
viii. Density of cement is
a) 1428kg/m3
b) 1440kg/m3
c) 1450kg/m3
d) 1420kg/m3
ix. Number of traditional bricks required for 1cu-m brickwork
a) 5000 nos
b) 450 nos
c) 500 nos
d) 5500 nos
x. The total length of a cranked bar through a distance (d) at 300 in case of beam
of effective length L, is
a) l + 0.42d
b) l + (2 x 0.42d)
c) l + 0.27d
d) l + (2 x 0.27d)
xi. The ‘centre line method’ is specially adopted for estimating
a) Circular area
b) Rectangular area
c) Square area
d) All the above.
xii. The volume is measured correct to the nearest
a) 0.02 cum
b) 0.01 cum
c) 0.04 cum
d) 0.1 cum
xiii. A cement concrete road is 1000m long, 8m wide and 15cm thick over the sub-base
of 10cm thick gravel. The box cutting in road crust is
a) 500 m3
b) 1500 m3
c) 2000 m3
d) 1000 m3
xiv. If B is the width of formation, d is the height of the embankment, side slope S:1,
for a highway with no transverse slop, the area of cross section is
a) B + d + Sd
b) B x d – Sd2
c) 1/2 (Bd + Sd2)
d) 1/2 (Bd + Sd2) x 2
xv. The brick work is not measured in cu m in case of
a) Reinforced brick work
b) Brick work in arches
c) Half brick wall
d) (a) and (b) both
Group-B
2. 4+4
a) Define the following term- (i) Administrative approval. (ii) Technical sanction.
b) Factors to be considered during preparation of a detail estimate.
3. Prepare a detailed estimate form the given plan and section (i) Earthwork in excavation
(ii)1st class brick work in cement mortar (1:6) in substructure and superstructure (iii)Flooring
8