Agile-2023-09-27 12 - 06 - 38
Agile-2023-09-27 12 - 06 - 38
Bwww.pm-tricks.com
Y: ElSayed Mohsen
ر ﻛ ﻮ د-ﺒ ﺎAll
©www.pm-tricks.com ﺢ اﻟrights
ﻂ اﻣ ﺴ ﻓ ﻘ، ﻠﻔ ﺔDo
reserved- ﻤ ﺨ ﺘnot
ﻲ اﻟ ﺮ و ﺳ ﺎﺋﻞ اﻟ ﺘ ﻮ اﺻ ﻞ اﻻ ﺟ ﺘ ﻤ ﺎﻋ2ﻳ ﺸ ﺮﻓ ﻨ ﺎ ﻣ ﺘ ﺎﺑﻌ ﺘ ﻜ ﻢ ﻋ ﺒ
share PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed
Agile Mohsen
اﻹدارة اﻟﺮﺷﻴﻘﺔ
Sayed Mohsen
2 ﻣ ﺎ ﻫ ﻲ اﻹ د ارة اﻟﺮﺷ ﻴﻘ ﺔ 6 أﻧ ﻮ اع د و رات ﺣ ﻴﺎ ة اﻟﻤ ﺸ ﺮو ع
Sayed Mohsen
10 اﻟﺤ ﺪ اﻷ د ﻧ ﻰ ﻣ ﻦ اﻟﻤ ﻨﺘﺞ اﻟﻘ ﺎ ﺑﻞ ﻟﻠﺘﻄ ﺒﻴﻖ 14 ﺷ ﺎﺷ ﺎت اﻟﻤ ﻌ ﻠﻮ ﻣ ﺎت
Sayed Mohsen
اﻟﺘﺤ ﻠﻴﻞ اﻟﺘﺼ ﻤ ﻴﻢ اﻟﺒﻨﺎء اﻻ ﺧ ﺘﺒﺎرات اﻟﺘﺴ ﻠﻴﻢ
ا ﻟﺘ ﺤ ﻠ ﻴ ﻞ
Analysis Design Build Test Deliver
اﻟﺘﺼﻤﻴﻢ
ا ﻟﺒ ﻨ ﺎء
اﻻ ﺧ ﺘ ﺒ ﺎر
ا ﻟﺘ ﺴ ﻠ ﻴ ﻢ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 9 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
ﺗﻌﺎون
Col l a b o r a t i o n
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 10 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Tra n s p a re n c y
اﻟ ﺸﻔ ﺎ ﻓ ﻴ ﺔ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 11 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Time t o
Sayed Mohsen Va l u e
ﺣﺎن اﻟﻮﻗﺖ ﻟﻠﺘﺮﻛﻴﺰ ﻋﻠﻰ اﻟﻘﻴﻤﺔ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 13 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 14 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
2. What is Agile ?
ﻣﺎ ﻫﻲ اﻹدارة اﻟﺮﺷﻴﻘﺔ ؟
§ Agile is a time boxed, iterative approach to software delivery that builds software incrementally from the start of the
project, instead of trying to deliver it all at once near the end.
.ﺑﺪًﻻ ﻣﻦ ﺗﺴﻠﻴﻢ اﻟﻤﻨﺘﺞ ﻛﺎﻣﻼ ﻣﺮة واﺣﺪة ﻓﻲ ﻧﻬﺎﻳﺔ اﻟﻤﺸﺮوع، ،اﻹدارة اﻟﺮﺷﻴﻘﺔ ﺗﺮﻛﺰ ﻋﻠﻰ ﺑﻨﺎء اﻟﻤﻨﺘﺞ ﻋﻠﻰ ﻋﺪة ﻣﺮاﺣﻞ وﺑﻔﺘﺮات زﻣﻨﻴﺔ ﻗﺼ ﻴﺮة
Sayed Mohsen
§ It works by breaking projects down into little bits of user functionality called user stories, prioritizing them, and then
continuously delivering them in short ( 1-4 ) week cycles called iterations.
ﺛ ﻢ ﺗ ﺴ ﻠ ﻴ ﻤ ﻬ ﺎ ﺑ ﺎ ﺳ ﺘ ﻤ ﺮ ا ر، و ﺗ ﺮ ﺗ ﻴ ﺒ ﻬ ﺎ ﺣ ﺴ ﺐ ا ﻷ و ﻟﻮ ﻳ ﺔ، إ ﻧﻪ ﻳ ﻌ ﻤ ﻞ ﻋ ﻦ ﻃ ﺮ ﻳ ﻖ ﺗ ﻘ ﺴ ﻴ ﻢ ا ﻟﻤ ﺸ ﺎ ر ﻳ ﻊ إ ﻟﻰ أ ﺟ ﺰ ا ء ﺻ ﻐ ﻴ ﺮ ة ﺗ ﺴ ﻤ ﻰ ﻗ ﺼ ﺺ ا ﻟﻤ ﺴ ﺘ ﺨ ﺪ م
. ( أﺳﺒﻮع ﺗﺴﻤﻰ اﻟﺘﻜﺮارات1-4) ﻓﻲ دورات ﻗﺼ ﻴﺮة
اﻷ ﺟ ﺎ ﻳ ﻞ ﻫ ﻲ ﻣ ﻨ ﻬ ﺠ ﻴ ﺔ ) ﻃ ﺮ ﻳ ﻘ ﺔ ( ﻹ د ار ة اﻟ ﻤ ﺸ ﺎ ر ﻳ ﻊ اﻟ ﺒ ﺮ ﻣ ﺠ ﻴ ﺔ و اﻟ ﻐ ﻴ ﺮ ﺑ ﺮ ﻣ ﺠ ﻴ ﺔ ﺗﺮ ﻛ ﺰ ﻋ ﻠ ﻰ ﺑ ﻨ ﺎ ء اﻟ ﻤ ﻨ ﺘ ﺞ ﻋ ﻠ ﻰ ﻋ ﺪ ة
ﻣﺮاﺣﻞ وﺑﻔﺘﺮات زﻣﻨﻴﺔ ﻗﺼﻴﺮة ،وﺗّﻮﻟﺪ ﻛﻞ ﻣﺮﺣﻠﺔ ﻣﻨﺘﺠًﺎ ﻣﺘﻤﻴ ًﺰ ﻋﻦ ﺳﺎﺑﻘﻪ ﺑﺨﺼﺎﺋﺺ إﺿﺎﻓﻴﺔ .وﻳﻌﺘﺒﺮﻫﺬا
اﻟﻤﻨﺘﺞ )اﻟﻤﺮﺣﻠﻲ( ﻣﻨﺘﺠًﺎ ﺣﻘﻴﻘﻴًﺎ ﻳﺴﺘﻄﻴﻊ اﻟﺰﺑﻮن )اﻟﻌﻤﻴﻞ( اﻟﺘﻔﺎﻋﻞ ﻣﻌﻪ ،واﻟﻐﺎﻳﺔ ﻣﻦ ذﻟﻚ ﺗﻘﺮﻳﺐ اﻟﻤﻨﺘﺞ
ﻟ ﻠ ﺰ ﺑ ﻮ ن ) اﻟ ﻌ ﻤ ﻴ ﻞ ( ﻟ ﻘ ﻴ ﺎ س ر ﺿ ﺎ ه ﺑ ﻤ ﺮ ا ﺣ ﻞ ﺗ ﻄ ﻮ ر ﻣ ﻨ ﺘ ﺠ ﻪ ،و ﻳ ﺘ ﻢ ﺗ ﻄ ﺒ ﻴ ﻖ اﻷ ﺟ ﺎ ﻳ ﻞ ﺑ ﻄ ﺮ ق ﻋ ﺪ ة ﻣ ﻨ ﻬ ﺎ اﻻ ﺳ ﻜ ﺮ م و ﻛ ﺎ ﻧ ﺒ ﺎ ن .
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 17 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
3. Agile Mindset
ﻋﻘﻠﻴﻪ اﻷﺳﻠﻮب اﻟﺮﺷﻴﻖ
Sayed Mohsen
make important project decisions (rather than just relying on a boss or project manager to make those decisions).
.ﺗﺪور اﻟﻌﻘﻠﻴﺔ اﻟﺮﺷﻴﻘﺔ ﺣﻮل ﺧﻠﻖ اﻟﺘﻐﻴﻴﺮ واﻻﺳﺘﺠﺎﺑﺔ ﻟﻪ ﻓﻲ اﻟﺒﻴﺌﺎت اﻟﺘﻰ ﻓﻴﻬﺎ ﻋﺪم ﻳﻘﻴﻦ §
.ﺗﺸﻤﻞ اﻻﺣﺘﺮام واﻟﺘﻌﺎون واﻟﺘﺤﺴﻴﻦ واﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ ﺗﻘﺪﻳﻢ اﻟﻘﻴﻤﺔ واﻟﻘﺪرة ﻋﻠﻰ اﻟﺘﻜﻴﻒ ﻣﻊ اﻟﺘﻐﻴﻴﺮ §
ﻣﻤﺎ ﻳﺴﻬﻞ ﻋﻠﻴﻬﻢ اﺗﺨﺎذ ﻗﺮارات ﻣﻬﻤﺔ ﺑﺸﺄن، اﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ ﻣﺴﺎﻋﺪة أﻋﻀﺎء اﻟﻔﺮﻳﻖ ﻋﻠﻰ ﻣﺸﺎرﻛﺔ اﻟﻤﻌﻠﻮﻣﺎت ﻣﻊ ﺑﻌﻀﻬﻢ اﻟﺒﻌﺾ §
.(اﻟﻤﺸﺮوع )ﺑﺪًﻻ ﻣﻦ اﻻﻋﺘﻤﺎد ﻓﻘﻂ ﻋﻠﻰ ﻣﺪﻳﺮ ﻣﺸﺮوع ﻻﺗﺨﺎذ ﺗﻠﻚ اﻟﻘﺮارات
ﻣ ﻤ ﺎرس ﻣ ﻨ ﻬ ﺠ ﻴ ﺔ
أن ﺗﻜﻮن رﺷﻴًﻘﺎ
اﺟ ﺎﻳ ﻞ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 20 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Agile Mindset ﻋ ﻘ ﻠﻴ ﻪ اﻷ ﺳ ﻠﻮ ب اﻟﺮﺷ ﻴ ﻖ
Sayed Mohsen
BEING
AGILE
أن ﺗﻜﻮن رﺷﻴًﻘﺎ
DOING
AGILE
ﻣ ﻤ ﺎرس ﻣ ﻨ ﻬ ﺠ ﻴ ﺔ اﺟ ﺎﻳ ﻞ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 22 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Agile Mindset ﻋ ﻘ ﻠﻴ ﻪ اﻷ ﺳ ﻠﻮ ب اﻟﺮﺷ ﻴ ﻖ
Sayed Mohsen
اﻷدوات أو اﻟﻤﻤﺎرﺳﺎت أو اﺗﺒﺎع ﻣﻨﻬﺠﻴﺔ ﻣﺤﺪدة.
vAgility involves
ü A new mindset ﻋ ﻘ ﻠﻴ ﺔ ﺟ ﺪ ﻳ ﺪ ة
ü way of thinking ﻃ ﺮﻳ ﻘ ﺔ ﺗﻔ ﻜ ﻴﺮ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 24 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
4. Agile Values and
Principles
ﻗ ﻴﻢ و ﻣ ﺒﺎ د ئ أﺟ ﺎ ﻳ ﻞ
Sayed Mohsen
!"#$%&'()#*%+,-&%./0(+#1%+2
• 3)4#5#46($+&()4&#),%7(8,#-)+
• 9-7:#)"&+-*,;(7%
• <6+,-.%7&8-$$(=-7(,#-)
• >%+/-)4#)"&,-&80()"%
.1اﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ اﻟﺘﻔﺎﻋﻞ ﺑﻴﻦ اﻷﻓﺮاد واﻟﻤﻌﻨﻴﻴﻦ أﻛﺜﺮ ﻣﻦ اﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ اﻟﻌﻤﻠﻴﺎت واﻷدوات.
.2اﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ ﻣﺨﺮﺟﺎت ﻗﺎﺑﻠﺔ ﻟﻠﻌﻤﻞ )ﺑﺮاﻣﺞ،ﻣﻨﺘﺞ ..اﻟﺦ( أﻛﺜﺮ ﻣﻦ اﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ اﻟﺘﻮﺛﻴﻖ اﻟﻤﺮﻛﺰ.
Sayed Mohsen
.3اﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ اﻟﺘﻌﺎون وإﺷﺮاك اﻟﻌﻤﻴﻞ أﻛﺜﺮ ﻣﻦ أن ﺗﺮﻛﺰ ﻋﻠﻰ اﻟﺘﻔﺎوض واﻻﻟﺘﺰام ﺑﺎﻟﻌﻘﻮد.
.4ﺗﻔﺘﺢ ﺑﺎب اﻻﺳﺘﺠﺎﺑﺔ ﻟﻠﺘﻐﻴﺮات اﻟﺘﻲ ﺗﻄﺮأ أﺛﻨﺎء اﻟﻤﺸﺮوع دون اﻟﺨﻮض ﺑﺘﻌﻘﻴﺪات ﻃﻠﺒﺎت اﻟﺘﻐﻴﻴﺮ ﺣﺘﻰ
و ﻟ ﻮ ﻛ ﺎ ﻧ ﺖ ﻋ ﻠ ﻰ ﺣ ﺴ ﺎ ب ﺗ ﻌ ﺪ ﻳ ﻞ ﺧ ﻄ ﺔ اﻟ ﻌ ﻤ ﻞ .
B*$#('"2.#$&3*(#5.2):$*%($*(.1$#(/2(0*)$,3$%,7$*,$$
6(0,1($1,#($(//(0*&5(:$*%(3$*"3()$.34$.4@")*)$&*)$$ !"#$%&'%()*$+#&,#&*-$&)$*,$).*&)/-$*%($0")*,1(#$*%#,"'%$(.#2-$$
.34$0,3*&3",")$4(2&5(#-$,/$5.2".62($),/*7.#(8
6(%.5&,#$.00,#4&3'2-8
12 1
C(20,1($0%.3'&3'$#(;"&#(1(3*):$(5(3$2.*($&3
9%($6()*$.#0%&*(0*"#():$#(;"&#(1(3*):$.34$$
11 2 4(5(2,+1(3*8$B'&2($+#,0())()$%.#3()) 0%.3'(
4()&'3)$(1(#'($/#,1$)(2/<,#'.3&=&3'$* (.1)8
/,#$*%($0")*,1(#D)$0,1+(*&*&5($.45.3*.'(8
Sayed Mohsen
E(2&5(#$7,#?&3'$),/*7.#($/#(;"(3*2-:$/#,1$$
F&1+2&0&*-:$*%($.#*$,/$1.G&1&=&3'$*%( 10 3
.1,"3*$,/$7,#?$3,*$4,3(:$&)$())(3*&.28 (5(#-$0,"+2($,/$7((?)$*,$0,"+2($,/$1,3*%):$$
7&*%$.$+#(/(#(30($*,$*%($)%,#*(#$*&1()0.2(8
AgileManifesto
H,3*&3",")$.**(3*&,3$*,$*(0%3&0.2$ 9 4 >")&3())$+(,+2($.34$4(5(2,+(#)$1")*$7,#?
(G0(22(30($.34$',,4$4()&'3$ *,'(*%(#$4.&2-$*%#,"'%,"*$*%($+#,@(0*8
(3%.30()$$.'&2&*-8
B'&2($+#,0())()$+#,1,*($)")*.&3.62($$ 8 5 >"&24$+#,@(0*)$.#,"34$1,*&5.*(4$&34&5&4".2)8$$
4(5(2,+1(3*8$9%($)+,3),#):$4(5(2,+(#):$.34$$ A&5($*%(1$*%($(35&#,31(3*$.34$)"++,#*$*%(-$$
7 6
")(#)$)%,"24$6($.62($*,$1.&3*.&3$.$0,3)*.3*$$ 3((4$.34$*#")*$*%(1$*,$'(*$*%($@,6$4,3(8
+.0($&34(/&3&*(2-8
9%($1,)*$(//&0&(3*$.34$(//(0*&5($1(*%,4$,/$0,35(-&3'$$
C,#?&3'$),/*7.#($&)$*%($+#&1.#-$1(.)"#($,/$+#,'#())8 &3/,#1.*&,3$*,$.34$7&*%&3$.$4(5(2,+1(3*$*(.1$&)$/.0(<*,<$$
/.0($0,35(#).*&,38
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 28 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
اﻟﻤﺒﺎدئ اﻻﺛﻨﻰ ﻋﺸﺮ ﻟﻤﻨﻬﺠﻴﺔ اﻷﺟﺎﻳﻞ:
ا ﻷ و ﻟﻮ ﻳ ﺔ ا ﻟﻘ ﺼ ﻮ ى ﻟﻨ ﺎ ﻫ ﻲ إ ر ﺿ ﺎء ا ﻟﻌ ﻤ ﻴ ﻞ ﻣ ﻦ ﺧ ﻼ ل ا ﻟﺘ ﺴ ﻠ ﻴ ﻢ ا ﻟﻤ ﺒ ﻜ ﺮ و ا ﻟﻤ ﺴ ﺘ ﻤ ﺮ ﻟﻠ ﺒ ﺮ ﻣ ﺠ ﻴ ﺎت ذ ا ت ا ﻟﻘ ﻴ ﻤ ﺔ . .1
اﻟﺘﺮﺣﻴﺐ ﺑﺘﻐﻴﻴﺮ اﻟﻤﺘﻄﻠﺒﺎت وﻟﻮ ﻓﻲ ﻣﺮاﺣﻞ ﻣﺘﻘﺪﻣﺔ ﻣﻦ اﻟﺘﻄﻮﻳﺮ .ﻓﻤﻨﺎﻫﺞ اﻷﺟﺎﻳﻞ ُﺗﺴﺨﺮ اﻟ ّﺘﻐﻴﻴﺮ ﻟﺼ ﺎﻟﺢ اﻟﻤﻴﺰة اﻟﺘﻨﺎﻓﺴﻴﺔ ﻟﻠﻌﻤﻴﻞ. .2
ﺗ ﺴ ﻠ ﻴ ﻢ ﺟ ﺰ ء ﻳ ﻌ ﻤ ﻞ ﻣ ﻦ ا ﻟﻤ ﻨ ﺘ ﺞ ﺑ ﺸ ﻜ ﻞ ﻣ ﺒ ﻜ ﺮ و ﻣ ﺴ ﺘ ﻤ ﺮ . .3
ﻣ ﻘ ﺪ م ا ﻟﺨ ﺪ ﻣ ﺔ و ﻃ ﺎ ﻟﺐ ا ﻟﺨ ﺪ ﻣ ﺔ ﻳ ﺠ ﺐ ا ن ﻳ ﻌ ﻤ ﻼ ﻣ ﻌ ﺎ ﺑ ﺸ ﻜ ﻞ ﻳ ﻮ ﻣ ﻲ ﺧ ﻼ ل ﻓ ﺘ ﺮ ة ا ﻟﻤ ﺸ ﺮ و ع . .4
ا ﻻ ﻋ ﺘ ﻤ ﺎد ﻓ ﻲ ﺑ ﻨ ﺎء ا ﻟﻤ ﺸ ﺎرﻳ ﻊ ﻋ ﻠ ﻰ أ ﻓ ﺮ ا د ﻣ ﺘ ﺤ ﻤ ﺴ ﻴ ﻦ .ﻣ ﻊ ﺗ ﻮ ﻓ ﻴ ﺮ ا ﻟﺒ ﻴ ﺌ ﺔ ا ﻟﻤ ﻨ ﺎﺳ ﺒ ﺔ و ا ﻟﺪ ﻋ ﻢ ا ﻟﻼ ز م ،و ﻣ ﻨ ﺤ ﻬ ﻢ ا ﻟﺜ ﻘ ﺔ ﻣ ﻦ أ ﺟ ﻞ إ ﻧﺠ ﺎ ز ا ﻟﻌ ﻤ ﻞ . .5
Sayed Mohsen
أ ﻓ ﻀ ﻞ ﻃ ﺮ ﻳ ﻘ ﺔ ﻟﻠ ﺘ ﻮ ا ﺻ ﻞ ﻫ ﻰ ا ﻟﺘ ﻔ ﺎﻋ ﻞ و ﺟ ﻬ ﺎ ﻟﻮ ﺟ ﻪ . .6
ﺗ ﺴ ﻠ ﻴ ﻢ ﻧﻈ ﺎ م ﻳ ﻌ ﻤ ﻞ ﻫ ﻮ أ د ا ة ا ﻟﻘ ﻴ ﺎ س ا ﻟﺮ ﺋ ﻴ ﺴ ﻴ ﺔ ﻟﻠ ﻌ ﻤ ﻞ . .7
.8ﻣﻨﺎﻫﺞ اﻷﺟﺎﻳﻞ ﺗﺸﺠﻊ اﻟﺘﻄﻮﻳﺮ اﻟﻤﺴﺘﺪام .ﻳﻨﺒﻐﻲ ﻋﻠﻰ اﻟﺮﻋﺎة واﻟﻤﻄﻮرﻳﻦ واﻟﻤﺴﺘﺨﺪﻣﻴﻦ أن ﻳﻜﻮﻧﻮا ﻗﺎدرﻳﻦ ﻋﻠﻰ اﻟﺤﻔﺎظ ﻋﻠﻰ وﺗﻴﺮة ﺛﺎﺑﺘﺔ
.9اﻻﻧﺘﺒﺎه اﻟﻤﺴﺘﻤﺮ ﻟﻠﺘﻤﻴﺰ اﻟﻔﻨﻲ واﻟﺘﺼﻤﻴﻢ اﻟﺠﻴﺪ ﻳﺤﺴﻦ ﻣﻦ اﻟﺮﺷﺎﻗﺔ.
.10اﻟﺒﺴﺎﻃﺔ— ﻓﻦ ﺗﻘﻠﻴﺺ اﻷﻋﻤﺎل ﻏﻴﺮ اﻟﻀ ﺮورﻳﺔ— أﻣﺮ أﺳﺎﺳﻰ .
.11ﻓﺮق اﻟﻌﻤﻞ ﻳﺠﺐ ان ﺗﻜﻮن ذاﺗﻴﺔ اﻟﺘﻨﻈﻴﻢ.
.12ﻳﺮاﺟﻊ ﻓﺮﻳﻖ اﻟﻌﻤﻞ ﻋﻠﻰ ﻓﺘﺮات ﻣﻨﺘﻈﻤﺔ ﻛﻴﻒ ﻳﺼ ﺒﺢ أﻛﺜﺮ ﻓﺎﻋﻠﻴﺔ ،ﺛﻢ ﻳﺪﻗﻖ وﻳﻀ ﺒﻂ ﺳﻠﻮﻛﻪ وﻓﻘﺎ ﻟﺬﻟﻚ.
!"#$%&'(()&*#&+,-"&."*%(/%&+(.&(.0*/,1*#,(/%&#(&'"-".*0"&&*0,'"&
2.*3#,3"%&*/4&#"35/,67"%8
)?*2,4&@""4A*3 ﻓ ﻴ ﺪ ﺑﺎ ك ﺳ ﺮﻳ ﻊ
Sayed Mohsen
اﻟ ﺘ ﻮ ا ﺟ ﺪ اﻟ ﺴ ﺮﻳ ﻊ و اﻟﻤ ﺴ ﺘ ﻤ ﺮ ﻓ ﻲ اﻟ ﺴ ﻮ ق @*%#".&B,="&#(&C*.)"#
*D'"*.&>"#&(+&E33"2#*/3"&D.,#"., ﻣ ﻌ ﺎﻳ ﻴﺮ ﻗ ﺒﻮ ل و اﺿ ﺤ ﺔ
Sayed Mohsen
cycles
أﻧﻮاع دورات ﺣﻴﺎة اﻟﻤﺸﺮوع
Sayed Mohsen
2 Iterative Life Cycle
د و ر ة اﻟ ﺤ ﻴ ﺎ ة اﻟ ﺘ ﻜ ﺮ ار ﻳ ﺔ
5 Hybrid Life Cycle
د و ر ة اﻟ ﺤ ﻴ ﺎ ة اﻟ ﻬ ﺠ ﻴ ﻦ
§ A more traditional approach, with the bulk of planning occurring upfront, then executing in a single pass; a sequential process.
§ Predictive life cycles expect to take advantage of high certainty around firm requirements, a stable team, and low risk.
§ Predictive projects do not typically deliver business value until the end of the project.
§ Example: Construction projects or projects that have many physical assets or have similar projects that have been completed in the past.
Sayed Mohsen
. ﻳ ﺘ ﻢ ا ﻟﺘ ﺨ ﻄ ﻴ ﻂ ﻟﻠ ﻤ ﺸ ﺮ و ع ﺑ ﺸ ﻜ ﻞ ﻣ ﻔ ﺼ ﻞ ﻣ ﺴ ﺒ ﻘ ﺎ، ا ﻟﻨ ﻬ ﺞ ا ﻟﺘ ﻘ ﻠ ﻴ ﺪ ي •
. و ا ﻟﻤ ﺨ ﺎﻃ ﺮ ا ﻟﻤ ﻨ ﺨ ﻔ ﻀ ﺔ، و ا ﻟﻔ ﺮ ﻳ ﻖ ا ﻟﻤ ﺴ ﺘ ﻘ ﺮ، د و ر ا ت ا ﻟﺤ ﻴ ﺎ ة ا ﻟﺘ ﻨ ﺒ ﺆ ﻳ ﺔ ﺗ ﺘ ﻤ ﺘ ﻊ ﺑ ﺪ ر ﺟ ﺔ ﻳ ﻘ ﻴ ﻦ ﻋ ﺎ ﻟﻴ ﺔ ﺣ ﻮ ل ا ﻟﻤ ﺘ ﻄ ﻠ ﺒ ﺎ ت •
.ﻻ ﺗﻘﺪم اﻟﻤﺸﺎرﻳﻊ اﻟﺘﻨﺒﺆﻳﺔ ﻋﺎدًة ﻗﻴﻤﺔ ﺣﺘﻰ ﻧﻬﺎﻳﺔ اﻟﻤﺸﺮوع •
ا ﻟﺘ ﺤ ﻠ ﻴ ﻞ
اﻟﺘﺼﻤﻴﻢ
ا ﻟﺒ ﻨ ﺎء
اﻻ ﺧ ﺘ ﺒ ﺎر
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 36 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
2-Iterative Life Cycles د و ر ة اﻟ ﺤ ﻴ ﺎ ة اﻟ ﺘ ﻜ ﺮ ار ﻳ ﺔ
§ An approach that allows feedback for unfinished work to improve and modify that work.
§ Projects benefit from iterative life cycles when complexity is high, when the project incurs frequent changes.
§ Iterative life cycles improve the product or result through successive prototypes or proofs of concept.
§ Each new prototype yields new stakeholder feedback and team insights. Then, the team incorporates the
new information by repeating one or more project activities in the next cycle.
§ Iterations help identify and reduce uncertainty in the project.
Sayed Mohsen
§ Iterative life cycles may take longer because they are optimized for learning rather than speed of delivery.
§ Example: Projects where learning and correction is expected to eventually get to the ideal solution.
.ﻧﻬﺞ ﻳﻌﺘﻤﺪ ﻋﻠﻰ اﻟﻔﻴﺪﺑﺎك ﻋﻠﻰ اﻟﻌﻤﻞ ﻏﻴﺮ اﻟﻤﻜﺘﻤﻞ ﻟﺘﺤﺴﻴﻦ وﺗﻌﺪﻳﻞ ﻫﺬا اﻟﻌﻤﻞ •
أو ﻋﻨﺪﻣﺎ ﻳﺨﻀﻊ اﻟﻨﻄﺎق ﻟﺘﺒﺎﻳﻦ آراء، أو ﻋﻨﺪﻣﺎ ﻳﺨﻀﻊ اﻟﻤﺸﺮوع ﻟﺘﻐﻴﻴﺮات ﻣﺘﻜﺮرة، ﺗﺴﺘﻔﻴﺪ اﻟﻤﺸﺎرﻳﻊ ﻣﻦ دورات اﻟﺤﻴﺎة اﻟﺘﻜﺮارﻳﺔ ﻋﻨﺪﻣﺎ ﻳﻜﻮن اﻟﺘﻌﻘﻴﺪ ﻣﺮﺗﻔًﻌﺎ •
.أﺻﺤﺎب اﻟﻤﺼﻠﺤﺔ ﺣﻮل اﻟﻤﻨﺘﺞ اﻟﻨﻬﺎﺋﻲ اﻟﻤﻄﻠﻮب
.ﺗﻌﻤﻞ دورات اﻟﺤﻴﺎة اﻟﺘﻜﺮارﻳﺔ ﻋﻠﻰ ﺗﺤﺴﻴﻦ اﻟﻤﻨﺘﺞ أو اﻟﻨﺘﻴﺠﺔ ﻣﻦ ﺧﻼل اﻟﻨﻤﺎذج اﻷوﻟﻴﺔ اﻟﻤﺘﺘﺎﻟﻴﺔ •
ﻳﻘﻮم اﻟﻔﺮﻳﻖ ﺑﺪﻣﺞ اﻟﻤﻌﻠﻮﻣﺎت اﻟﺠﺪﻳﺪة ﻋﻦ ﻃﺮﻳﻖ ﺗﻜﺮار ﻧﺸﺎط أو أﻛﺜﺮ، ﺑﻌﺪ ذﻟﻚ.ﻳﻨﺘﺞ ﻋﻦ ﻛﻞ ﻧﻤﻮذج أوﻟﻲ ﺟﺪﻳﺪ ﻣﻼﺣﻈﺎت ﺟﺪﻳﺪة ﻟﻠﻤﻌﻨﻴﻴﻦ ورؤى ﻟﻠﻔﺮﻳﻖ •
.ﻣﻦ أﻧﺸﻄﺔ اﻟﻤﺸﺮوع ﻓﻲ اﻟﺪورة اﻟﺘﺎﻟﻴﺔ
.ﺗﺴﺎﻋﺪ اﻟﺘﻜﺮارات ﻓﻲ ﺗﺤﺪﻳﺪ وﺗﻘﻠﻴﻞ ﻋﺪم اﻟﻴﻘﻴﻦ ﻓﻲ اﻟﻤﺸﺮوع •
.ﻗﺪ ﺗﺴﺘﻐﺮق دورات اﻟﺤﻴﺎة اﻟﺘﻜﺮارﻳﺔ وﻗ ًﺘﺎ أﻃﻮل ﻷﻧﻬﺎ ُﻣﺤﱠﺴﻨﺔ ﻟﻠﺘﻌﻠﻢ ﺑﺪًﻻ ﻣﻦ ﺳﺮﻋﺔ اﻟﺘﺴﻠﻴﻢ •
.ن ﻳﺼﻞ اﻟﺘﻌﻠﻢ واﻟﺘﺼﺤﻴﺢ ﻓﻴﻬﺎ ﻓﻲ اﻟﻨﻬﺎﻳﺔ إﻟﻰ اﻟﺤﻞ اﻟﻤﺜﺎﻟﻲBﻊ أYﻮﻗ
: ﻟﻤﺘEﻦ اl ﻣSﻲaﻟﺘyﻊ اeﺎرﻳd
ﻟﻤﺸM
اo
• hsen
©www.pm-tricks.com - All rights reserved- Do not share 37 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
2-Iterative Life Cycles د و ر ة اﻟ ﺤ ﻴ ﺎ ة اﻟ ﺘ ﻜ ﺮ ار ﻳ ﺔ
Analyze
Sayed Mohsen
Design
Sayed Mohsen
، ﻻ ﺗ ﺴ ﺘ ﻄ ﻴ ﻊ ا ﻟﻌ ﺪ ﻳ ﺪ ﻣ ﻦ ا ﻟﺸ ﺮ ﻛ ﺎت ا ﻧﺘ ﻈ ﺎ ر ا ﻛ ﺘ ﻤ ﺎل ﻛ ﻞ ﺷ ﻲ ء ؛ ﻓ ﻲ ﻫ ﺬ ه ا ﻟﺤ ﺎﻟﺔ. ﺗ ﻌ ﻤ ﻞ ﺑ ﻌ ﺾ ا ﻟﻤ ﺸ ﺎرﻳ ﻊ ﻋ ﻠ ﻰ ﺗ ﺤ ﺴ ﻴ ﻦ ﺳ ﺮ ﻋ ﺔ ا ﻟﺘ ﺴ ﻠ ﻴ ﻢ
٫ ﻳ ﺴ ﻤ ﻰ ﻫ ﺬ ا ا ﻟ ﺘ ﺴ ﻠ ﻴ ﻢ ا ﻟ ﻤ ﺘ ﻜ ﺮ ر ﻟ ﻠ ﻤ ﺨ ﺮ ﺟ ﺎ ت ا ﻟ ﺼ ﻐ ﻴ ﺮ ة ﺑ ﺪ و ر ة ا ﻟ ﺤ ﻴ ﺎ ة ا ﻟ ﻤ ﺘ ﺰ ا ﻳ ﺪ ة. ﻳ ﻜ ﻮ ن ا ﻟ ﻌ ﻤ ﻼ ء ﻋ ﻠ ﻰ ا ﺳ ﺘ ﻌ ﺪ ا د ﻟ ﺘ ﻠ ﻘ ﻲ ﺟ ﺰ ء ﻣ ﻦ ا ﻟ ﻤ ﻨ ﺘ ﺞ
§ An approach that is both iterative and incremental to refine work items and deliver frequently.
§ Agile life cycles combine both iterative and incremental approaches in order to adapt to high degrees of change
and deliver project value more often.
§ Agile life cycles are those that fulfill the principles of the Agile Manifesto.
Sayed Mohsen
§ In particular, customer satisfaction increases with early and continuous delivery of valuable products.
§ Example: Software projects or projects based on intellectual property and research.
• أﺳ ﻠﻮ ب ﺗﻜ ﺮاري و ﺗ ﺪ ر ﻳ ﺠ ﻲ ﻟ ﺘ ﺤ ﺴ ﻴ ﻦ ﻋ ﻨﺎ ﺻ ﺮ اﻟ ﻌ ﻤ ﻞ و ﺗ ﻘ ﺪ ﻳ ﻤ ﻬ ﺎ ﺑﺸ ﻜ ﻞ ﻣ ﺘ ﻜ ﺮر .
• ﺗ ﺠ ﻤ ﻊ د و رات اﻟ ﺤ ﻴ ﺎ ة اﻟﺮﺷ ﻴ ﻘ ﺔ ﺑﻴ ﻦ اﻟ ﻨ ﻬ ﺠ ﻴ ﻦ اﻟ ﺘ ﻜ ﺮاري و اﻟ ﺘ ﺰاﻳ ﺪ ي ﻣ ﻦ أﺟ ﻞ اﻟ ﺘ ﻜ ﻴ ﻒ ﻣ ﻊ د ر ﺟ ﺎ ت ﻋ ﺎ ﻟ ﻴ ﺔ ﻣ ﻦ اﻟ ﺘ ﻐ ﻴ ﻴ ﺮ و ﺗﻘ ﺪ ﻳ ﻢ
ﻗ ﻴﻤ ﺔ اﻟﻤ ﺸ ﺮو ع
• دورات اﻟﺤﻴﺎة اﻟﺮﺷﻴﻘﺔ ﻫﻲ ﺗﻠﻚ اﻟﺘﻲ ﺗﻔﻲ ﺑﻤﺒﺎدئ ﺑﻴﺎن اﺟﺎﻳﻞ Agile Manifesto.
Sayed Mohsen
• ﻳ ﺰد اد ر ﺿ ﺎ اﻟ ﻌ ﻤ ﻼ ء ﻣ ﻊ اﻟ ﺘ ﺴ ﻠﻴ ﻢ اﻟﻤ ﺒ ﻜ ﺮ و اﻟﻤ ﺴ ﺘ ﻤ ﺮ ﻟﻠﻤ ﻨ ﺘ ﺠ ﺎ ت ذ ات اﻟﻘ ﻴ ﻤ ﺔ .
• اﻟ ﺘ ﺴ ﻠﻴ ﻢ اﻟ ﺘ ﺪ رﻳ ﺠ ﻲ ﻟﻤ ﻨ ﺘ ﺠ ﺎ ت ذ ات ﻗ ﻴﻤ ﺔ و ﻗ ﺎ ﺑﻠﺔ ﻟ ﻼ ﺳ ﺘ ﺨ ﺪ ام ﺗﻌ ﺘﺒﺮ ﻫ ﻲ اﻟﻤ ﻘ ﻴ ﺎ س اﻷ ﺳ ﺎﺳ ﻲ ﻟﻠﺘﻘ ﺪ م .
§ It is not necessary to use a single approach for an entire project. Projects often combine elements of different
life cycles in order to achieve certain goals.
ﻓﻐﺎﻟﺒﺎ ﻣﺎ ﺗﺠﻤﻊ اﻟﻤﺸﺎرﻳﻊ ﺑﻴﻦ ﻋﻨﺎﺻﺮ دورات ﺣﻴﺎة ﻣﺨﺘﻠﻔﺔ. ﻟﻴﺲ ﻣﻦ اﻟﻀ ﺮوري اﺳﺘﺨﺪام ٔاﺳﻠﻮب واﺣﺪ ﻟﻜﺎﻣﻞ اﻟﻤﺸﺮوع
Sayed Mohsen
. وﻳﻌﺪ اﻟﺠﻤﻊ ﺑﻴﻦ اﻷﺳﺎﻟﻴﺐ اﻟﺘﻨﺒٔﻮﻳﺔ واﻟﻤﺘﻜﺮرة واﻟﻤﺘﺰاﻳﺪة واﻟﺮﺷﻴﻘﺔ أﺳﻠﻮﺑﺎ ﻫﺠﻴ ًﻨﺎ.ﻟﺘﺤﻘﻴﻖ أﻫﺪاف ﻣﺤﺪدة
§ Example: Projects with a mix of resources and experience levels or projects seeking or willing to learn new
methods or techniques.
. ﻣ ﺸ ﺎ رﻳ ﻊ ﺑ ﻤ ﺰ ﻳ ﺞ ﻣ ﻦ ا ﻟﻤ ﻮ ا رد و ﻣ ﺴ ﺘ ﻮ ﻳ ﺎ ت ا ﻟﺨ ﺒ ﺮ ة أ و ا ﻟﻤ ﺸ ﺎرﻳ ﻊ ا ﻟﺘ ﻲ ﺗ ﺴ ﻌ ﻰ أ و ﺗ ﺮ ﻏ ﺐ ﻓ ﻲ ﺗ ﻌ ﻠ ﻢ أ ﺳ ﺎﻟﻴ ﺐ أ و ﺗ ﻘ ﻨ ﻴ ﺎت ﺟ ﺪ ﻳ ﺪ ة
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 45 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
ﺗﺴﻠﺴﻞ دورات اﻟﺤﻴﺎة
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 46 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Characteristics of project Life Cycles
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 47 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
ﺧﺼﺎﺋﺺ دورات ﺣﻴﺎة اﻟﻤﺸﺮوع
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 48 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
7. Agile Methodologies,
Frameworks
ﻣﻨﻬﺠﻴﺎت اﻹدارة اﻟﺮﺷﻴﻘﺔ
Agile approaches and agile methods are umbrella terms that cover a variety of frameworks .
. ﺗ ﻌ ﺘ ﺒ ﺮ اﻷ ﺳ ﺎ ﻟ ﻴ ﺐ اﻟﺮﺷ ﻴ ﻘ ﺔ ﻣ ﺼ ﻄ ﻠﺤ ﺎ ت ﺷ ﺎ ﻣ ﻠﺔ ﺗ ﻐ ﻄ ﻲ ﻣ ﺠ ﻤ ﻮ ﻋ ﺔ ﻣ ﺘ ﻨ ﻮ ﻋ ﺔ ﻣ ﻦ اﻷ ﻃ ﺮ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 50 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
ﻫ ﻮ ﻣ ﺼ ﻄ ﻠﺢ ﻋﺎم ﻟﻠﻌ ﺪ ﻳﺪ ﻣ ﻦ اﻷ ﺳ ﺎﻟﻴﺐAgile اﻷ ﺳ ﻠﻮ ب اﻟﺮﺷ ﻴﻖ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 51 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
8. Scrum
اﺳﻜﺮم
ٕاﺳﻜﺮام
ا ﺟ ﺘ ﻤ ﺎع اﻟﺘ ﺨ ﻄ ﻴ ﻂ •
اﻻ ﺟ ﺘ ﻤ ﺎع اﻟﻴ ﻮ ﻣ ﻲ •
Sayed Mohsen
ا ﺟ ﺘ ﻤ ﺎ ع ا ﻟﻤ ﺮ ا ﺟ ﻌ ﺔ •
ا ﺟ ﺘ ﻤ ﺎع اﻟﺪ رو س •
ا ﻟﻤ ﺴ ﺘ ﻔ ﺎد ة
2*0,3(4&"%5(566'01-
Inputs from
End-Users,
Customers,
Teams and
Other F0#"1$J.)*(#
Stakeholders
Sayed Mohsen
I#,4"0*$,73(# ./"01'(768069
Requirement 1
Requirement 8
Requirement 3
Requirement 5
Requirement 2
./"01'()*&+,#-
!"#$%&'()*&+,#- .&"%5(:#*"$
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 56 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 57 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Scrum Roles أد و ار اﺳ ﻜ ﺮ م
Sayed Mohsen
Product owner
ا ﻟﺸ ﺨ ﺺ ا ﻟﻤ ﺴ ﺌ ﻮ ل ﻋ ﻦ ﺗ ﻌ ﻈ ﻴ ﻢ ﻗ ﻴ ﻤ ﺔ ا ﻟﻤ ﻨ ﺘ ﺞ •
و ا ﻟﻤ ﺴ ﺌ ﻮ ل ﻧﻬ ﺎ ﺋ ﻴ ﺎ ﻋ ﻦ ا ﻟﻤ ﻨ ﺘ ﺞ ا ﻟﻨ ﻬ ﺎ ﺋ ﻲ ا ﻟﺬ ي ﺗ ﻢ ﺗ ﻜ ﻮ ﻳ ﻨ ﻪ .
ﻟﺪ ﻳ ﻪ رؤ ﻳ ﺔ ﻟﻠ ﻤ ﺸ ﺮ و ع •
Sayed Mohsen
ا ﻟﺘ ﺄﻛ ﺪ ﻣ ﻦ ﻗ ﻴ ﻤ ﺔ ا ﻟﻌ ﻤ ﻞ ا ﻟﺬ ي ﻳ ﺆ د ﻳ ﻪ ﻓ ﺮ ﻳ ﻖ ا ﻟﺘ ﻄ ﻮ ﻳ ﺮ •
ﻳ ﺠ ﻤ ﻊ ا ﻟﻤ ﺪ ﺧ ﻼ ت ﻣ ﻦ ا ﻟﻤ ﺴ ﺘ ﺨ ﺪ ﻣ ﻴ ﻦ ا ﻟﻨ ﻬ ﺎﺋ ﻴ ﻴ ﻦ و ا ﻟﻌ ﻤ ﻼ ء •
و ا ﻟﻔ ﺮ ﻳ ﻖ و ا ﻟﻤ ﻌ ﻨ ﻴ ﻴ ﻦ
ﻣ ﺴ ﺆ و ل ﻋ ﻦ ﺗ ﺤ ﺪ ﻳ ﺪ أ و ﻟﻮ ﻳ ﺎ ت " ﺳ ﺠ ﻞ أ ﻋ ﻤ ﺎل ا ﻟﻤ ﻨ ﺘ ﺞ •
"Backlog
ﻳ ﻀ ﺒ ﻂ ا ﻟﻤ ﻴ ﺰ ا ت و ا ﻷ و ﻟﻮ ﻳ ﺔ ﻓ ﻲ ﻛ ﻞ ﺗ ﻜ ﺮ ا ر ﺣ ﺴ ﺐ ا ﻟﺤ ﺎ ﺟ ﺔ •
Sayed Mohsen
ﻳﺴﻬﻞ اﺟﺘﻤﺎﻋﺎت ﺳﻜﺮم اﻟﻴﻮﻣﻴﺔ وﻣﺴﺆوًﻻ ﻋﻦ إزاﻟﺔ •
أ ي ﻋ ﻮ ا ﺋ ﻖ ﻗ ﺪ ﻃ ﺮ ﺣ ﻬ ﺎ ا ﻟﻔ ﺮ ﻳ ﻖ ﺧ ﻼ ل ﺗ ﻠ ﻚ ا ﻻ ﺟ ﺘ ﻤ ﺎﻋ ﺎت .
Sayed Mohsen
ﻣ ﻬ ﻤ ﺔ اﻟﻜ ﺘﺎ ﺑﺔ ،ﻹ ن ﻣ ﻬ ﻤ ﺔ اﻟﻔ ﺮﻳ ﻖ ﻫ ﻮ إﻧ ﻬ ﺎء
اﻟ ﻌ ﻤ ﻞ ﻓ ﻰ اﻟﻮ ﻗ ﺖ اﻟﻤ ﻄ ﻠﻮ ب و ﺑﺎ ﻟﻄ ﺮﻳ ﻘ ﺔ
اﻟﺼ ﺤ ﻴﺤ ﺔ .
Sayed Mohsen
• 4$&5"-&*6/$(7"%(+E$(&9%8;(5%"9$&&3 • 4$&5"-&*6/$(7"%(5%"#89+(:8./*+0'($&+*;.+*"-'(.-#(#$/*<$%03
• J.&(+E$(<*&*"-("7(+E$(5%"L$9+3
• @.9*/*+.+$&(+E$(#.*/0(=9%8;(I$$+*-23 • =$/7("%2.-*>$#(.-#(&$/7(#*%$9+$#3
• A.+E$%(+E$(*-58+&(7%";(98&+";$%3 • G"$&(-"+(#*%$9+(68+($-.6/$& • !%"&&?@8-9+*"-./(1$.;3
ﻣﺴﺆول ﻋﻦ ﻧﺠﺎح اﻟﻤﻨﺘﺞ • ا ﻟ ﻘ ﺎ ﺋ ﺪ ا ﻟ ﺨﺎ د م • اﻟﻤﺒﺮﻣﺠﻮن ،اﻟﻜﺘﺎب ،اﻟﻤﺤﻠﻠﻴﻦ ،اﻟﻤﺨﺘﺒﺮﻳﻦ ،اﻟﻤﺼﻤﻤﻴﻦ . •
ﻣﺴﺆول ﻋﻦ ﻋﻤﻠﻴﺔ اﺳﻜﺮم • ﻣﺴﺆول ﻋﻦ ﺟﻮدة اﻟﻤﻨﺘﺞ واﻟﺘﻘﺪﻳﺮ واﻟﺘﺴﻠﻴﻢ.
Sayed Mohsen
•
ﻟﺪﻳﻪ رؤﻳﺔ ﻟﻠﻤﺸﺮوع •
ﺗﺴﻬﻴﻞ وﺗﻨﻈﻴﻢ اﺟﺘﻤﺎﻋﺎت اﻟﻮﻗﻮف اﻟﻴﻮﻣﻴﺔ • إﻋﺪاد ﺳﺠﻞ أﻋﻤﺎل اﻟﻤﻨﺘﺞ •
ﺗﺠﻤﻴﻊ اﻟﻤﺘﻄﻠﺒﺎت ﻣﻦ اﻟﻌﻤﻴﻞ • ﻻ ﻳﺴﻴﻄﺮ اﻧﻤﺎ ﻳﻤﻜﻦ اﻟﻔﺮﻳﻖ • ﺑﻨﺎء وﺗﻨﻔﻴﺬ اﻟﻤﻨﺘﺞ •
ﻣﺴﺎﻋﺪة اﻟﻔﺮﻳﻖ ﻋﻠﻰ ان ﻳﻜﻮن ذاﺗﻲ اﻟﺘﻨﻈﻴﻢ • ﺗﺴﻠﻴﻢ اﻟﻤﻨﺘﺞ •
ﻣﺴﺆول ﻋﻦ ﺗﺮﺗﻴﺐ أوﻟﻮﻳﺎت ﺳﺠﻞ أﻋﻤﺎل اﻟﻤﻨﺘﺞ •
ﻣﻴﺴﺮ وﻣﻨﻈﻢ ﻟﻼﺟﺘﻤﺎﻋﺎت • ذاﺗﻲ اﻟﺘﻨﻈﻴﻢ واﻟﺘﻮﺟﻴﻪ •
ﻗﺒﻮل ﻣﺎ ﺗﻢ ﺗﻨﻔﻴﺬه ﻣﻦ ﻗﺒﻞ اﻟﻔﺮﻳﻖ • ﻣﺪرب وﻣﻮﺟﻪ ﻟﻔﺮﻳﻖ اﻟﺘﻄﻮﻳﺮ • ﻓﺮﻳﻖ ﻣﺘﻌﺪد اﻟﻮﻇﺎﺋﻒ واﻟﻤﻬﺎرات •
ﺗﻌﺪﻳﻞ او ﺣﺬف او إﺿﺎﻓﺔ او ﺗﺮﺗﻴﺐ ﻗﺼﺺ • ﻳ ﻮﺟﻪ وﻳ ﺪر ب ا ﻟ ﻔﺮﻳ ﻖ وﻳ ﺰ ﻳ ﻞ ا ﻟ ﻌﻮا ﺋ ﻖ. • ﻟﺪﻳﻬﻢ ﺗﺨﺼﺼﺎت ﻋﻤﻴﻘﺔ •
ﺗﺄﻛﺪ ﻣﻦ ﺗﻄﺒﻴﻖ اﻟﻤﻤﺎرﺳﺎت اﻟﺮﺷﻴﻘﺔ. • ﻣﺸﺎرﻛﺔ اﻟﺘﻘﺪم ﻣﻦ ﺧﻼل اﺟﺘﻤﺎﻋﺎت اﻟﻮﻗﻮف اﻟﻴﻮﻣﻴﺔ. •
اﻟﻤﺴﺘﺨﺪم
ﻳﺴﺎﻋﺪ ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﻓﻲ إدارة ﺳﺠﻞ أﻋﻤﺎل • ﻋﺮض وﺗﺴﻠﻴﻢ اﻟﺰﻳﺎدات اﻟﻤﻜﺘﻤﻠﺔ. •
ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ • اﻟﻤﻨﺘﺞ. ﺗﺤﺪﻳﺚ ﺷﺎﺷﺎت اﻟﻤﻌﻠﻮﻣﺎت ﺑﺸﻜﻞ ﻣﺴﺘﻤﺮ ودورى •
ﺻﻮت اﻟﻌﻤﻴﻞ • ﻳﻤﻜﻦ أن ﻳﻄﻠﻖ ﻋﻠﻴﻪ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع. • ﻳﻤﻜﻦ ان ﻳﻄﻠﻖ ﻋﻠﻴﻪ ﻓﺮﻳﻖ اﻟﺘﺴﻠﻴﻢ •
ﻣﺎﻟﻚ ﻋﻤﻠﻴﺔ اﺳﻜﺮم •
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 64 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Project Manager vs Scrum Master vs Product Owner
ﻣ ﻘ ﺎ ر ﻧ ﺔ ﺑﻴ ﻦ ﻣ ﺪ ﻳﺮ ا ﻟﻤ ﺸ ﺮ و ع و ﻣ ﺪ ﻳ ﺮ ا ﺳ ﻜ ﺮ م و ﻣ ﺎ ﻟﻚ ا ﻟﻤ ﻨ ﺘ ﺞ
Sayed Mohsen
When you transit from traditional approach (Waterfall model) to Agile, the responsibilities of a Project
Manager are distributed among the variety of team members. Some responsibilities go to the Program
Manager, some to the Product Owner, some to the Scrum Master and some to the remaining team.
ﻳ ﺘ ﻢ ﺗ ﻮ ز ﻳ ﻊ ﻣ ﺴ ﺆ و ﻟﻴ ﺎ ت ﻣ ﺪ ﻳ ﺮ ا ﻟﻤ ﺸ ﺮ و ع ﺑ ﻴ ﻦ ﻣ ﺠ ﻤ ﻮ ﻋ ﺔ ﻣ ﺘ ﻨ ﻮ ﻋ ﺔ ﻣ ﻦ، ﻋ ﻨ ﺪ ﻣ ﺎ ﺗ ﻨ ﺘ ﻘ ﻞ ﻣ ﻦ ا ﻟﻨ ﻬ ﺞ ا ﻟﺘ ﻘ ﻠ ﻴ ﺪ ي ) ﻧﻤ ﻮ ذ ج ا ﻟﺸ ﻼ ل ( إ ﻟﻰ ا ﻷ ﺳ ﻠ ﻮ ب ا ﻟﺮ ﺷ ﻴ ﻖ
و ا ﻟﺒ ﻌ ﺾ ا ﻵ ﺧ ﺮ إ ﻟﻰ ﻣ ﺪ ﻳ ﺮ ا ﺳ ﻜ ﺮ م و ا ﻟﺒ ﻌ ﺾ ا ﻵ ﺧ ﺮ، و ﺑ ﻌ ﻀ ﻬ ﺎ إ ﻟﻰ ﻣ ﺎﻟﻚ ا ﻟﻤ ﻨ ﺘ ﺞ، ﺗ ﺬ ﻫ ﺐ ﺑ ﻌ ﺾ ا ﻟﻤ ﺴ ﺆ و ﻟﻴ ﺎت إ ﻟﻰ ﻣ ﺪ ﻳ ﺮ ا ﻟﺒ ﺮ ﻧﺎﻣ ﺞ. أ ﻋ ﻀ ﺎ ء ا ﻟﻔ ﺮ ﻳ ﻖ
. إ ﻟﻰ ا ﻟﻔ ﺮ ﻳ ﻖ ا ﻟﻤ ﺘ ﺒ ﻘ ﻲ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 66 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
د و ر ﻣ ﺪ ﻳ ﺮ اﻟ ﻤ ﺸ ﺮ و ع ﻓ ﻲ اﻻ ﺳ ﻠ ﻮ ب اﻟ ﺮ ﺷ ﻴ ﻖ
Role of Project Manager ( in Agile )
v When working on an agile project, project managers shift from being the center to serving the team.
v In an agile environment, project managers are servant leaders, changing their emphasis to coaching
people who want help, fostering greater collaboration on the team, and aligning stakeholder needs.
Sayed Mohsen
v As a servant leader, project managers encourage the distribution of responsibility to the team: to
those people who have the knowledge to get work done.
The value of project managers is not in their position, but in their ability to make everyone else better.
Sayed Mohsen
ﺳ ﺠ ﻞ أﻋ ﻤ ﺎل اﻟﻤ ﻨﺘﺞ ﺳ ﺠ ﻞ أﻋ ﻤ ﺎ ل اﻟ ﺘ ﻜ ﺮار
( اﻟﺰﻳﺎدات ) اﻟﻤﻨﺘﺞ
• &<%&*&',%#&(+&+"*#7."%G&(.&;(.)&."67,."="/#%
• ﻫ ﻰ ﻗ ﺎ ﺋﻤ ﺔ اﻟﻤ ﺘﻄ ﻠﺒﺎت اﻟﺘ ﻲ ﺗﻢ ﺗﺠ ﻤ ﻴ ﻌ ﻬ ﺎ ﻣ ﻦ
&/""4"4&#(&A7,'4&*&2.(473#8
اﻟﻌ ﻤ ﻴﻞ و اﻟﺘﻰ ﻳ ﻘ ﻮ م ﻣ ﺎﻟﻚ اﻟﻤ ﻨ ﺘ ﺞ ﺑﻜ ﺘﺎ ﺑﺘﻬ ﺎ،
• &")<#$%&3(=2,'"4&+.(=&,/27#&%(7.3"%&',
و ﺗﺘﻀ ﻤ ﻦ اﻟﻤ ﻴﺰات اﻟ ﺘ ﻰ ﻟﻬ ﺎ اﻷ و ﻟﻮ ﻳ ﺔ ﻓ ﻰ
&37%#(=".8
اﻟﺘﻨﻔ ﻴﺬ ،
Sayed Mohsen
• &B5"&2.(473#&A*3)'(0&,%&*&H',-"I&*.#,+*3#&,/
• ﺳ ﺠ ﻞ أﻋ ﻤ ﺎل اﻟﻤ ﻨﺘﺞ ﻫ ﻮ ﺳ ﺠ ﻞ ﺣ ﻰ اى ﺑﻴ ﺘﻢ
&;"#5*#&,#&,%&724*#"4&(/J4"=*/4&*%&/
ﺗ ﺤ ﺪ ﻳ ﺜ ﻪ ﺑﺎ ﺳ ﺘ ﻤ ﺮار ا ذ ا ﺗ ﻮ ﻓ ﺮت ﻣ ﻌ ﻠﻮ ﻣ ﺎ ت ﺟ ﺪ ﻳ ﺪ ة .
,/+(.=*#,(/&,%&*-*,'*A'"8
• ﻣ ﺎ ﻟﻚ اﻟﻤ ﻨ ﺘ ﺞ ﻫ ﻮ ﻣ ﻦ ﻳ ﻘ ﻮ م ﺑﺘﺮﺗ ﻴ ﺐ اﻻ و ﻟﻮ ﻳ ﺎ ت
• K.,(.,#,1"4&A:"&2.(473#&(;/".8
ﻳ ﺘ ﻢ إﻋ ﺎ د ة ﺗﺮﺗ ﻴ ﺐ اﻟ ﻌ ﻨ ﺎ ﺻ ﺮ اﻟﻤ ﻮ ﺟ ﻮ د ة ﻓ ﻲ ﺳ ﺠ ﻞ •
• <#"=%&,/"&2.(473#&A*3)'(0&,%&."J
أﻋﻤﺎل اﻟﻤﻨﺘﺞ ﻓﻲ ﺑﺪاﻳﺔ ﻛﻞ ﺗﻜﺮار Sprint
&2.,(.,#,1"4&*#"&%#*.#&(+&"*35&%2.,/#8
• &B5"&%2.,/#&A*3)'(0&3(/#*,/%&,#"=%&#(&A"&3(=2'"#"4
47.,/0"&37.."/#&%2.,/#8
• B5,%&',%#&,%&4"#".=,/"4&,/"&%2.,/#&2'*//,/0&=""#,/08
• K7''"4&+.(=&2.(473#&A*3)'(08 ﺳ ﺠ ﻞ أﻋ ﻤ ﺎ ل اﻟ ﺘ ﻜ ﺮار
• <#"=%&*."&A.()"/&,/#(&#*%)%8
Sayed Mohsen
ﺳ ﺠ ﻞ أﻋ ﻤ ﺎل اﻟﻤ ﻨﺘﺞ
ﻋﺒﺎرة ﻋﻦ ﻗﺎﺋﻤﺔ ﺑﺎﻟﻤﻬﺎم او ﺑﻨﻮد اﻟﻌﻤﻞ اﻟﺘﻲ ﻳﺤﺪدﻫﺎ ﻓﺮﻳﻖ اﺳﻜﺮم واﻟﺘﻲ ﻳﺠﺐ اﻻﻧﺘﻬﺎء ﻣﻨﻬﺎ اﺛﻨﺎء ﻓﺘﺮة اﻟﺘﻜﺮار Sprint •
ﻳﺘﻢ ﺗﺤﺪﻳﺪ ﻫﺬه اﻟﻘﺎﺋﻤﺔ ﻓﻲ اﺟﺘﻤﺎع اﻟﺘﺨﻄﻴﻂ ﻟﻠﺘﻜﺮار Sprint Planning Meeting . •
ﻳﺘﻢ ﺳﺤﺐ اﻻﻋﻤﺎل ﻣﻦ ﺳﺠﻞ أﻋﻤﺎل اﻟﻤﻨﺘﺞ اﻟﻰ ﺳﺠﻞ أﻋﻤﺎل اﻟﺘﻜﺮار •
اﻟﻔﺮﻳﻖ ﻣﻨﻈﻢ ذاﺗًﻴﺎ -ﻳﻘﻮم أﻋﻀﺎء اﻟﻔﺮﻳﻖ ﺑﺘﺤﺪﻳﺪ اﻟﻤﻬﺎم ﺣﺴﺐ ﺳﺮﻋﺘﻪ ،وﻻ ﻳﺘﻢ ﺗﻌﻴﻴﻦ اﻟﻤﻬﺎم .ﻣﻦ ﻗﺒﻞ اى ﺷﺨﺺ اﺧﺮ •
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 72 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
اﻟﻔﺮق ﺑﻴﻦ ﺳﺠﻞ أﻋﻤﺎل اﻟﻤﻨﺘﺞ وﺳﺠﻞ أﻋﻤﺎل اﻟﺘﻜﺮار
ﻳﺠﺘﻤﻊ ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﻣﻊ اﻟﻌﻤﻴﻞ ﻓﺮﻳﻖ اﻟﺘﻄ ﻮﻳﺮ اﺛﻨﺎء اﺟﺘﻤﺎع اﻟﺘﺨﻄ ﻴﻂ
ﻟﺠﻤﻊ ﻣﺘﻄﻠﺒﺎﺗﻪ وﻛﺘﺎﺑﺘﻬﺎ ﻓﻲ ﻳﻘ ﻮم ﺑﺴﺤﺐ اﻻﻋﻤﺎل ﻣﻦ ﺳ ﺠ ﻞ
ﺳﺠﻞ اﻋﻤﺎل اﻟﻤﻨﺘﺞ وﻳﺘﻐﻴﺮ أﻋﻤﺎل اﻟﻤﻨﺘﺞ و و ﺿ ﻌﻬﺎ ﻓﻲ ﺳ ﺠﻞ
ﻛﻴﻒ ﻳﺘﻢ اﻻﻧﺸﺎء اﻋﻤﺎل اﻟﺘﻜﺮار و ﺗﻘ ﺪ ﻳﺮﻫ ﺎ
ﺑﺎﺳﺘﻤﺮار ﻋﻨﺪ وﺟﻮد أي ﺗﻐﻴﻴﺮات
3%2/$4$%#
• &B5"&</3."="/#&,%"&%7=&(+&*''"&K.(473#&L*3)'(0&,#"=%
3(=2'"#"4&47.,/0&*&>2.,/#&*/4&*''&2."-,(7%&>2.,/#%8
Sayed Mohsen
• E#"&"/4&(+&*&>2.,/#G"&/";&</3."="/#&=7%#&A"&HM(/"GI
• <#&=7%#&A"&,/&7%"*A'"&3(/4,#,(/&NK(#"/#,*'':&%5,22*A'"&2.(473#O
)(('&!"#$%#
*+&,,'-($. اﻟﺰﻳﺎدة ﻫﻲ ﻣﺠﻤﻮع ﻛﻞ ﻋﻨﺎﺻﺮ ﺳﺠﻞ أﻋﻤﺎل اﻟﻤﻨﺘﺞ اﻟﻤﻜﺘﻤﻠﺔ أﺛﻨﺎء اﻟﺘﻜﺮار. §
!/"012#. ﻓﻲ ﻧﻬﺎﻳﺔ اﻟﺘﻜﺮار ،ﻳﺠﺐ أن ﺗﻜﻮن اﻟﺰﻳﺎدة اﻟﺠﺪﻳﺪة "ﺗﻢ"، §
ﻳﺠﺐ أن ﻳﻜﻮن ﻓﻲ ﺣﺎﻟﺔ ﺻﺎﻟﺤﺔ ﻟﻼﺳﺘﺨﺪام )ﻣﻨﺘﺞ ﻗﺎﺑﻞ ﻻﺳﺘﺨﺪام ( §
3
Events Or Ceremonies
اﺟ ﺘﻤ ﺎﻋ ﺎت٤
Sayed Mohsen
• اﺟ ﺘﻤ ﺎع اﻟﺘﺨ ﻄ ﻴ ﻂ ﻟﻠﺘﻜ ﺮار
• اﺟ ﺘﻤ ﺎع اﻟﻮ ﻗ ﻮ ف اﻟﻴﻮ ﻣ ﻲ
• اﺟ ﺘﻤ ﺎع اﻟﻤ ﺮاﺟ ﻌ ﺔ
• اﺟ ﺘﻤ ﺎع اﻟﺪ رو س اﻟﻤ ﺴ ﺘﻔ ﺎد ة
اﺛﻨ ﺎ ء اﻟ ﺘ ﻜ ﺮ ار
ﻻ ﺗ ﻐ ﻴ ﻴ ﺮ ﻓ ﻲ ﻧﻄ ﺎق ا ﻟﻌ ﻤ ﻞ
ﻻ ﺗ ﻐ ﻴ ﻴ ﺮ ﻓ ﻲ ا ﻟﻔ ﺮ ﻳ ﻖ
ﻟﻠ ﺤ ﻔ ﺎظ ﻋ ﻠ ﻰ ﻫ ﺪ ف ا ﻟﺘ ﻜ ﺮ ا ر
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 76 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 77 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
اﺟﺘﻤﺎع اﻟﺘﺨﻄﻴﻂ ﻟﻠﺘﻜﺮار
Sprint Planning Meeting
ﻣ ﺪ ة ا ﺟ ﺘ ﻤ ﺎع ا ﻟﺘ ﺨ ﻄ ﻴ ﻂ ٨ﺳ ﺎ ﻋ ﺎ ت ﻓ ﻲ ﺣ ﺎ ﻟﺔ ﻛ ﺎ ن ا ﻟﺘ ﻜ ﺮ ا ر ٤أ ﺳ ﺎ ﺑ ﻴ ﻊ ،و ﻣ ﺪ ﺗ ﻪ ٤ﺳ ﺎ ﻋ ﺎ ت ﻟﻮ •
ﻛ ﺎن ﻓ ﺘ ﺮ ة اﻟﺘ ﻜ ﺮ ا ر أﺳ ﺒ ﻮ ﻋ ﻴ ﻦ ﻓ ﻘ ﻂ .
Sayed Mohsen
ﻓ ﺮ ﻳ ﻖ ا ﻟﺘ ﻄ ﻮ ﻳ ﺮ ﻳ ﺮ ﻛ ﺰ ﻓ ﻲ ا ﺟ ﺘ ﻤ ﺎع ا ﻟﺘ ﺨ ﻄ ﻴ ﻂ ﻋ ﻠ ﻰ ﻣ ﺎ ا ﻟﺬ ي ﺳ ﻮ ف ﻳ ﺘ ﻢ ﺗ ﻨ ﻔ ﻴ ﺬ ه ا ﺛ ﻨ ﺎء •
ا ﻟﺘ ﻜ ﺮ ا ر و ﻛ ﻴ ﻒ ﺳ ﻴ ﺘ ﻢ ﺗ ﻨ ﻔ ﻴ ﺬ ه .
ﻳ ﺘ ﻢ ﺗ ﺤ ﺪ ﻳ ﺪ ﻣ ﻌ ﺎﻳ ﻴ ﺮ ا ﻟﻘ ﺒ ﻮ ل . •
ﺑ ﻴ ﺘ ﻢ ﻣ ﻨ ﺎﻗ ﺸ ﺔ أ ﻫ ﺪ ا ف ا ﻟﺘ ﻜ ﺮ ا ر و ﻣ ﺎ ﻫ ﻲ ا ﻟﻘ ﻴ ﻤ ﺔ ا ﻟﻤ ﺘ ﻮ ﻗ ﻌ ﺔ ﻣ ﻦ ا ﻟﺘ ﻜ ﺮ ا ر. •
ﻳ ﻨ ﺎﻗ ﺶ ا ﻟﻔ ﺮ ﻳ ﻖ ﻣ ﻊ ﻣ ﺎﻟﻚ ا ﻟﻤ ﻨ ﺘ ﺞ ﻣ ﺎ ﻫ ﻲ ا ﻟﻤ ﻬ ﺎم ا ﻟﺘ ﻲ ﺳ ﻮ ف ﻳ ﺘ ﻢ ﺳ ﺤ ﺒ ﻬ ﺎ ﻣ ﻦ ﺳ ﺠ ﻞ •
ا ﻋ ﻤ ﺎل ا ﻟﻤ ﻨ ﺘ ﺞ ا ﻟﻰ ﺳ ﺠ ﻞ ا ﻋ ﻤ ﺎل ا ﻟﺘ ﻜ ﺮ ا ر و ا ﻟﺘ ﻲ ﺳ ﻮ ف ﻳ ﺘ ﻢ ﺗ ﻨ ﻔ ﻴ ﺬ ﻫ ﺎ ا ﺛ ﻨ ﺎء ا ﻟﺘ ﻜ ﺮ ا ر.
ﻳ ﻘ ﻮ م ﻓ ﺮ ﻳ ﻖ ا ﻟﺘ ﻄ ﻮ ﻳ ﺮ ﺑ ﻌ ﻤ ﻞ ﺗ ﻘ ﺪ ﻳ ﺮ ﻟﻠ ﻤ ﻬ ﺎ م ا ﻟﺘ ﻲ ﺳ ﻮ ف ﻳ ﺘ ﻢ ﺗ ﻨ ﻔ ﻴ ﺬ ﻫ ﺎ ﺣ ﺴ ﺐ ﺳ ﺮ ﻋ ﺘ ﻪ •
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 78 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 79 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
§ This is a 15-minute time-boxed meeting.
§ The daily scrum is held every day at the same time and location.
§ The daily scrum is for the development team only.
Sayed Mohsen
§ All Attendees should stand- Standup!
§ Not for problem solving.
§ During the meeting, each team member answers three Questions:
Sayed Mohsen
• ﻳ ﺠ ﺐ ﻋ ﻠﻰ ﺟ ﻤ ﻴ ﻊ اﻟ ﺤ ﺎ ﺿ ﺮﻳ ﻦ اﻟﻮ ﻗ ﻮ ف .
• اﻻ ﺟ ﺘﻤ ﺎع ﻟﻌ ﺮض اﻟﻤ ﺸ ﺎﻛ ﻞ و ﻟﻴﺲ ﻟﺤ ﻞ اﻟﻤ ﺸ ﺎﻛ ﻞ .
• اﺳﻜﺮم ﻣﺴﺘﺮ ﻳﻘﻮم ﺑﺘﻨﻈﻴﻢ وﺗﻴﺴﻴﺮ اﻻﺟﺘﻤﺎع Facilitate meeting
• أي ﻧ ﻘ ﺎ ش ﺧ ﺎ ر ج اﻫ ﺪ اف اﻻ ﺟ ﺘ ﻤ ﺎ ع ﻳ ﻄ ﻠﺐ اﺳ ﻜ ﺮم ﻣ ﺴ ﺘ ﺮ ﻣ ﻨ ﺎ ﻗ ﺸ ﺘ ﻬ ﺎ ﺑﻌ ﺪ اﻻ ﺟ ﺘ ﻤ ﺎ ع
Sayed Mohsen
• Attendees will be the development team, the product owner,
scrum master, and sometimes other project stakeholders
ﻣ ﺪ ة اﺟ ﺘﻤ ﺎع اﻟﻤ ﺮاﺟ ﻌ ﺔ ٤ﺳ ﺎﻋ ﺎت ﻓ ﻲ ﺣ ﺎﻟﺔ ﻛﺎ ن اﻟﺘﻜ ﺮار ٤أﺳ ﺎ ﺑﻴﻊ ،و ﻣ ﺪ ﺗﻪ ﺳ ﺎﻋ ﺘﻴﻦ ﻟﻮ ﻛﺎن •
ﻓ ﺘﺮة اﻟﺘﻜ ﺮار أﺳ ﺒ ﻮ ﻋ ﻴﻦ ﻓ ﻘ ﻂ .
Sayed Mohsen
ﺑﻴﺘﻢ ﻧﻬﺎﻳﺔ ﻛﻞ ﺗﻜﺮار Sprint •
ﻳ ﻘ ﺪ م اﻟﻔ ﺮﻳ ﻖ ﻣ ﺎ أﻧ ﺠ ﺰه ﺧ ﻼ ل اﻟ ﺘ ﻜ ﺮار •
اﻟﺤﺎﺿﺮون ﻫﻢ ﻓﺮﻳﻖ اﻟﺘﻄﻮﻳﺮ ،وﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ،ﺳﻜﺮم ﻣﺴﺘﺮ ،وأﺣﻴﺎ ًﻧﺎ اﻟﻤﻌﻨﻴﻴﻦ اﻵﺧﺮﻳﻦ •
ﻓ ﻲ اﻟﻤ ﺸ ﺮو ع
ﺳ ﻴ ﻘ ﻮ م ﻓ ﺮﻳ ﻖ اﻟ ﺘ ﻄ ﻮ ﻳ ﺮ ﺑﻌ ﺮض اﻟ ﻌ ﻤ ﻞ اﻟﺬ ي ﺗﻢ اﻧ ﺠ ﺎ ز ه ﺧ ﻼ ل ﻣ ﺪ ة اﻟ ﺘ ﻜ ﺮار. •
ﻳﻘﻮم ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﺑﻘﺒﻮل او رﻓﺾ اﻟﻌﻤﻞ اﻟﺬى ﺗﻢ اﻻﻧﺘﻬﺎء ﻣﻨﻪ Shippable product •
ﻗ ﺼ ﺺ اﻟﻤ ﺴ ﺘﺨ ﺪ م ﻏ ﻴﺮ اﻟﻤ ﻜ ﺘﻤ ﻠﺔ ،ﻳ ﺘﻢ ار ﺟ ﺎ ﻋ ﻬ ﺎ إﻟﻰ ﺳ ﺠ ﻞ أﻋ ﻤ ﺎ ل اﻟﻤ ﻨ ﺘ ﺞ ﻹ ﻋ ﺎ د ة ﺗﺮﺗﻴ ﺐ •
اﻻ و ﻟﻮ ﻳ ﺎت .
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 84 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 85 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
. ﻳ ﻤ ﻜ ﻦ اﺳ ﺘ ﺨ ﺪ ام اﻷ د و ات و اﻟ ﺘ ﻘ ﻨ ﻴﺎ ت و اﻷ ﺳ ﺎ ﻟ ﻴ ﺐ ﻟﻠﺘ ﺤ ﻘ ﻖ ﻣ ﻦ اﻟ ﻨ ﻄ ﺎ ق ﻓ ﻲ اﻟﻤ ﺸ ﺎ رﻳ ﻊ اﻟﺮﺷ ﻴ ﻘ ﺔ
Tools, techniques, and approaches can be used to verify the scope in agile projects.
Tool and Technique Description
Definition of done ( DOD) A team's checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use.
ﺗ ﻌ ﺮ ﻳ ﻒ ا ﻟﻤ ﻨ ﺠ ﺰ .ﻗﺎﺋﻤﺔ ﺗﺤﻘﻖ ﻟﻠﻔﺮﻳﻖ ﺗﻀﻢ ﺟﻤﻴﻊ اﻟﻤﻌﺎﻳﻴﺮ اﻟﻤﻄﻠﻮﺑﺔ ﻟﻠﻮﻓﺎء ﺑﻬﺎ ﺑﺤﻴﺚ ﻳﻤﻜﻦ اﻋﺘﺒﺎر اﻟﺘﺴﻠﻴﻢ ﺟﺎﻫﺰ ﻟﻴﺴﺘﺨﺪﻣﻪ اﻟﻌﻤﻴﻞ
Definition of Ready( DOR) A team's checklist for a user-centric requirement that has all the information the team needs to be able to begin working on it.
ﺗ ﻌ ﺮ ﻳ ﻒ ا ﻟﺠ ﻬ ﻮ ز ﻳ ﺔ ﻳﺠﺐ أن ﺗﻜﻮن اﻟﻘﺼﺺ اﻟﻤﻮﺟﻮدة-ﻗﺎﺋﻤﺔ ﺗﺤﻘﻖ ﻟﻠﻔﺮﻳﻖ واﻟﺘﻲ ﺗﺤﺘﻮي ﻋﻠﻰ ﻛﺎﻓﺔ اﻟﻤﻌﻠﻮﻣﺎت اﻟﺘﻲ ﻳﺤﺘﺎﺟﻬﺎ اﻟﻔﺮﻳﻖ ﻟﻴﺘﻤﻜﻦ ﻣﻦ ﺑﺪء اﻟﻌﻤﻞ ﻋﻠﻴﻬﺎ
Sayed Mohsen
.. ﺟﺎﻫﺰةSprint Backlog أﻋﻠﻰ اﻟﺒﺎﻛﻠﻮج واﻟﺘﻲ ﺳﻴﻘﻮم اﻟﻔﺮﻳﻖ ﺑﺴﺤﺒﻬﺎ إﻟﻰ
>8 E(/&3&*&,3$,/$4,3($KE,EM
Sayed Mohsen
H8 *>"#34,73$0%.#
E8 *N(2,0&*-$0%.#
أﺛﻨﺎء ﻋﺮض اﻻﻃﻼق ،اوﺿﺢ اﻟﻌﻤﻴﻞ أن اﺣﺪى ﻗﺼﺺ اﻟﻤﺴﺘﺨﺪﻣﻴﻦ ﻟﻴﺴﺖ ﺟﺎﻫﺰة ﻟﻴﺴﺘﺨﺪﻣﻬﺎ اﻟﻌﻤﻴﻞ .ﻣﺎ ﻗﺎﺋﻤﺔ اﻟﻤﺮاﺟﻌﺔ اﻟﺘﻲ ﻳﻨﺒﻐﻲ
ﻟﻠﻔﺮﻳﻖ اﻟﻨﻈﺮ ﻓﻴﻬﺎ ﻟﻤﻌﺮﻓﺔ ﻣﺎ اﻟﺬى ﺗﻢ اﻏﻔﺎﻟﻪ ﻓﻲ ﻗﺼﺔ اﻟﻤﺴﺘﺨﺪم ؟
B
ﺗ ﻌ ﺮ ﻳ ﻒ ا ﻟﺠ ﻬ ﻮ ز ﻳ ﺔ أ-
ب -ﺗ ﻌ ﺮ ﻳ ﻒ ا ﻟﻤ ﻨ ﺠ ﺰ
ج -ﻣ ﺨ ﻄ ﻂ ا ﻟﺤ ﺮ ق ا ﻟﺘ ﻨ ﺎ ز ﻟﻲ
ب د -ﻣ ﺨ ﻄ ﻂ اﻟﺴ ﺮ ﻋ ﺔ
Sayed Mohsen
• Participants ( Scrum Master & Team ) Product owner (Optional)
• Lessons learned and opportunities for improvement.
• Review of the product owner’s feedback about the last iteration
• Discus:
Sayed Mohsen
ﻳﻘﺎم ﻫﺬا اﻻﺟﺘﻤﺎع ﺑﻌﺪ اﺟﺘﻤﺎع ﻣﺮاﺟﻌﺔ اﻟﺘﻜﺮار ،وﻟﻜﻦ ﻗﺒﻞ اﺟﺘﻤﺎع اﻟﺘﺨﻄﻴﻂ اﻟﺘﺎﻟﻲ ﻟﻠﺘﻜﺮار. •
ﻓ ﺮ ﺻ ﺔ ﻟ ﺘﺤ ﺴ ﻴﻦ أ د اء اﻟ ﻔ ﺮ ﻳ ﻖ و ﻣ ﺎ اﻟ ﺬ ى ﻳ ﻤ ﻜ ﻦ ﻓ ﻌ ﻠ ﻪ ﺑ ﺸ ﻜ ﻞ اﻓ ﻀ ﻞ ﺧ ﻼ ل اﻟ ﺘﻜ ﺮ ا ر اﻟ ﻘ ﺎ د م . •
ﻳ ﻘ ﺎ م ﻓ ﻲ ﻧ ﻬ ﺎ ﻳ ﺔ ﻛ ﻞ ﺗﻜ ﺮ ا ر . •
ا ﻟ ﻤ ﺸ ﺎ ر ﻛ ﻮ ن ا ﻟ ﻔ ﺮ ﻳ ﻖ و ا ﺳ ﻜ ﺮ م ﻣ ﺴ ﺘ ﺮ )ﺣ ﻀ ﻮ ر ﻣ ﺎ ﻟ ﻚ ا ﻟ ﻤ ﻨ ﺘ ﺞ ا ﺧ ﺘ ﻴ ﺎ ر ي ( •
ﻫ ﻮ ا ﺟ ﺘﻤ ﺎ ع ا ﻟ ﺪ ر و س ا ﻟ ﻤ ﺴ ﺘﻔ ﺎ د ة و ﻓ ﺮ ﺻ ﺔ ﻟ ﺘﺤ ﺴ ﻴﻦ أ د ا ء ا ﻟ ﻔ ﺮ ﻳ ﻖ و ا ﻟ ﻌ ﻤ ﻠ ﻴﺔ و ا ﻟ ﺠ ﻮ د ة . •
ﻣ ﺮ اﺟ ﻌ ﺔ ﻣ ﻼ ﺣ ﻈ ﺎت ﻣ ﺎﻟ ﻚ اﻟ ﻤ ﻨﺘﺞ ﺣ ﻮ ل اﻟ ﺘﻜ ﺮ ار اﻷ ﺧ ﻴﺮ . •
vﺧ ﻼ ل اﻻ ﺟ ﺘﻤ ﺎع ،ﺑﻴﺘﻢ ﻣ ﻨﺎﻗ ﺸ ﺔ :
ﻣ ﺎ اﻟﺬ ي ﻧ ﺠ ﺢ ﺑﺸ ﻜ ﻞ ﺟ ﻴﺪ ؟
ﻣ ﺎ اﻟﺬ ي ﻟﻢ ﻳ ﻌ ﻤ ﻞ ﺑﺸ ﻜ ﻞ ﺟ ﻴﺪ ؟
ﻀ ﺎ ﻟ ﺠ ﻌ ﻞ ا ﻟ ﺘ ﻜ ﺮ ا ر ا ﻟ ﻘ ﺎ د م أ ﻛ ﺜ ﺮ إ ﻧ ﺘ ﺎﺟ ﻴ ﺔ ؟ E l S a y e d M o h s e nﻣﺎ :اYﻟﺬBي ﻳﻤﻜﻦ ﻓﻌﻠﻪ أﻳ ً
©www.pm-tricks.com - All rights reserved- Do not share 89 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 90 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 91 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
1- Artifacts
Product backlog. is a list of features, or work requirements needed to build a product.
It’s compiled from input sources like customer.
The product backlog is a “live” artifact in that it is updated on-demand as new information is
available.
Sprint backlog. Lists work to be done in the current sprint. Pulled from product
backlog. Items are broken into tasks.
Increment .
2- Events or Ceremonies
Sprint Planning. Meeting is conducted before the start of a sprint. where the team decides
Sayed Mohsen
what to deliver in the coming sprint (from the product backlog) and how to go about it. Roles
Sprint Retrospective. A three-hour timebox event held after the sprint review (and before Development Team. Self-organizing group of 3-9
the next sprint planning). The team reviews their work, identifying opportunities for
improvement work processes in subsequent sprints. professionals responsible for delivering the
products. BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 92 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
-١و ﺛ ﺎ ﺋ ﻖ ا ﺳ ﻜ ﺮ م
-١ﺳ ﺠ ﻞ أﻋ ﻤ ﺎل اﻟ ﻤ ﻨ ﺘ ﺞ :ﻫﻲ ﻗﺎﺋﻤﺔ ﺑﺎﻟﻤﻴﺰات أو ﻣﺘﻄﻠﺒﺎت اﻟﻌﻤﻞ اﻟﻼزﻣﺔ ﻟﺒﻨﺎء ﻣﻨﺘﺞ.
ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﻗﺎم ﺑﺘﺠﻤﻴﻊ ﻫﺬه اﻟﻤﺘﻄﻠﺒﺎت ﻣﻦ اﻟﻌﻤﻴﻞ.
ﻋﺒﺎرة ﻋﻦ ﻗﻄﻌﺔ أﺛﺮﻳﺔ "ﺣﻴﺔ" ﺣﻴﺚ ﻳﺘﻢ ﺗﺤﺪﻳﺜﻬﺎ ﻋﻨﺪ اﻟﻄﻠﺐ ﻋﻨﺪ ﺗﻮﻓﺮ ﻣﻌﻠﻮﻣﺎت ﺟﺪﻳﺪة. .
-٢ﺳ ﺠ ﻞ أﻋ ﻤ ﺎل اﻟ ﺘ ﻜ ﺮ ار .ﻳﻮﺟﺪ ﺑﻪ اﻟﻌﻤﻞ اﻟﺬي ﻳﺘﻌﻴﻦ اﻟﻘﻴﺎم ﺑﻪ ﻓﻲ اﻟﺘﻜﺮار اﻟﺤﺎﻟﻲ.
ﺗﻢ ﺳﺤﺒﻪ ﻣﻦ ﺳﺠﻞ أﻋﻤﺎل اﻟﻤﻨﺘﺞ.
-٣اﻟ ﺰ ﻳ ﺎد ات ) اﻟ ﻤ ﻨ ﺘ ﺞ (
-٢ا ﺟ ﺘ ﻤ ﺎ ﻋ ﺎ ت ا ﺳ ﻜ ﺮ م
اﺟ ﺘ ﻤ ﺎع اﻟ ﺘ ﺨ ﻄ ﻴ ﻂ .ﻳﺘﻢ إﺟﺮاء اﻻﺟﺘﻤﺎع ﻗﺒﻞ ﺑﺪء اﻟﺘﻜﺮار .ﺣﻴﺚ ﻳﻘﺮر اﻟﻔﺮﻳﻖ ﻣﺎ ﻳﺠﺐ ﺗﻘﺪﻳﻤﻪ ﻓﻲ
-٣ا ﻻ د و ا ر
Sayed Mohsen
اﻟﺘﻜﺮار اﻟﻘﺎدم وﻛﻴﻔﻴﺔ اﻟﻘﻴﺎم ﺑﺬﻟﻚ.
ﻓ ﻮ اﺋ ﺪ اﺟ ﺘ ﻤ ﺎع اﻟ ﺘ ﺨ ﻄ ﻴ ﻂ:
ﻳﻮ ﺟﺪ ﺛﻼ ﺛﺔ أدوار رﺋﻴﺴ ﻴﺔ ﻓﻲ اﺳ ﻜﺮم
اﻟﻔﻬﻢ اﻟﻤﺸﺘﺮك ﻟﻠﻤﻨﺘﺞ ،ﺳﺤﺐ وﺗﺴﺠﻴﻞ اﻟﻤﻬﺎم ﻓﻲ ﺳﺠﻞ اﻋﻤﺎل اﻟﺘﻜﺮار ،ﺗﻘﺪﻳﺮ اﻟﻤﻬﺎم.
ﻣ ﺎﻟ ﻚ اﻟ ﻤ ﻨ ﺘ ﺞ :ﻫﻮ اﻟﺸﺨﺺ اﻟﻤﺴﺌﻮل ﻋﻦ إدارة ﺳﺠﻞ أﻋﻤﺎل
اﺟ ﺘ ﻤ ﺎع اﻟ ﻮ ﻗ ﻮ ف اﻟ ﻴ ﻮ ﻣ ﻲ .اﺟﺘﻤﺎع ﻣﺪﺗﻪ 15دﻗﻴﻘﺔ ﺣﻴﺚ ﻳﻠﺘﻘﻲ اﻟﻔﺮﻳﻖ ﻳﻮﻣًﻴﺎ أﺛﻨﺎء اﻟﺘﻜﺮار اﻟﻤﻨﺘﺞ وﺟﻤﻊ اﻟﻤﺘﻄﻠﺒﺎت ﻣﻦ اﻟﻌﻤﻴﻞ وﺗﺮﺗﻴﺒﻬﺎ داﺧﻞ ﺳﺠﻞ
ﻟﻔﺤﺺ اﻟﺘﻘﺪم وﺗﺤﺪﻳﺪ اﻟﻤﻮاﻧﻊ. اﻻﻋﻤﺎل
اﺟ ﺘ ﻤ ﺎع اﻟ ﻤ ﺮ اﺟ ﻌ ﺔ و اﻟ ﺘ ﺴ ﻠ ﻴ ﻢ .اﺟﺘﻤﺎع ﻣﺪﺗﻪ أرﺑﻊ ﺳﺎﻋﺎت ُﻳﻘﺎم ﻓﻲ ﻧﻬﺎﻳﺔ اﻟﺘﻜﺮار .ﻳﻌﺮض ﻣ ﺪ ﻳ ﺮ اﺳ ﻜ ﺮ م ﻫ ﻮ اﻟ ﻘ ﺎﺋﺪ اﻟ ﺨ ﺎد م ﻫﻮ اﻟﻤﺴﺆول ﻋﻦ اﻟﺘﺄﻛﺪ ﻣﻦ
اﻟﻔﺮﻳﻖ اﻟﻤﻨﺘﺞ ﻋﻠﻰ ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ وﻳﺠﻤﻊ اﻟﺘﻌﻠﻴﻘﺎت ﺣﻮل ﻣﺎ ﻳﺠﺐ اﺿﺎﻓﺘﻪ ﻓﻲ ﺳﺠﻞ اﻋﻤﺎل دﻋﻢ ﻋﻤﻠﻴﺔ ٕاﺳﻜﺮام وﻳﻌﻤﻞ ﻋﻠﻰ ﺿﻤﺎن اﻟﺘﺰام ﻓﺮﻳﻖ ٕاﺳﻜﺮام
اﻟﻤﻨﺘﺞ ﻟﻠﺘﺴﻠﻴﻢ ﻓﻲ اﻟﺘﻜﺮارات اﻟﻼﺣﻘﺔ. ﺑﺎﻟﻤﻤﺎرﺳﺎت واﻟﻘﻮاﻋﺪ ﻛﻤﺎ اﻧﻪ ﻳﺪرب اﻟﻔﺮﻳﻖ ﻋﻠﻰ إزاﻟﺔ
اﻟﻌﻘﺒﺎت.
اﺟ ﺘ ﻤ ﺎع اﻟ ﺪ ر و س اﻟ ﻤ ﺴ ﺘ ﻔ ﺎد ة او ﺑﺄ ﺛﺮ ر ﺟ ﻌ ﻲ .اﺟﺘﻤﺎع ﻣﺪﺗﻪ ﺛﻼث ﺳﺎﻋﺎت ﻳﻌﻘﺪ ﺑﻌﺪ اﺟﺘﻤﺎع
ﻣﺮاﺟﻌﺔ اﻟﺘﻜﺮار )وﻗﺒﻞ اﺟﺘﻤﺎع اﻟﺘﺨﻄﻴﻂ ﻟﻠﺘﻜﺮار اﻟﺘﺎﻟﻲ( .ﻳﺮاﺟﻊ اﻟﻔﺮﻳﻖ ﻋﻤﻠﻬﻢ ،وﻳﺤﺪد ﻓﺮص ﻓ ﺮ ﻳ ﻖ اﻟ ﺘ ﻄ ﻮ ﻳ ﺮ ﻫﻮ ﻓﺮﻳﻖ ذاﺗﻲ اﻟﺘﻨﻈﻴﻢ واﻟﺘﻮﺟﻴﻪ وﻣﺘﻌﺪد
ﺗﺤﺴﻴﻦ ﻋﻤﻠﻴﺎت اﻟﻌﻤﻞ ﻓﻲ اﻟﺘﻜﺮارات اﻟﻼﺣﻘﺔ. اﻟﻮﻇﺎﺋﻒ واﻟﻤﻬﺎرات وﻳﺘﻜﻮن ﻣﻦ ﺛﻼﺛﺔ اﻟﻰ ٩اﺷﺨﺎص
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 93 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Iteration Lifecycle: Example
!"#$%"&'()*$#+%$%"&'())
!"#$%&'()*+,'+,-,.#-,'/0))
,#-'
,-1+#-,'/)-2131))
,41/-,5,146
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 95 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Scrum Framework
2*0,3(4&"%5(566'01-
Inputs from
End-Users,
Customers,
Teams and
Other F0#"1$J.)*(#
Stakeholders
Sayed Mohsen
I#,4"0*$,73(# ./"01'(768069
Requirement 1
Requirement 8
Requirement 3
Requirement 5
Requirement 2
./"01'()*&+,#-
!"#$%&'()*&+,#- .&"%5(:#*"$
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 96 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
9. Scrum of Scrums
ٕاﺳﻜﺮام اﻟﺸﺎﻣﻠﺔ
üاﻻﺟﺘﻤﺎع ﻋﺎدة ﻳﻜﻮن ﺑﺸﻜﻞ ﻳﻮﻣﻰ وﻣﺪﺗﻪ ﻣﻦ 20-15دﻗﻴﻘﺔ واﻟﻬﺪف ﻣﻨﻪ ﻫﻮ اﻟﺘﻌﺎون ﻟﺤﻞ اﻟﻤﺸﺎﻛﻞ واﻟﻌﻮاﺋﻖ اﻟﺘﻰ ﺗﻮاﺟﻬﺎ اﻟﻔﺮق.
üإذا ﻛﺎﻧﺖ ﻓﺮق ﺳﻜﺮوم ﻣﻮﺟﻮدة ﻓﻲ ﻣﻮاﻗﻊ ﺟﻐﺮاﻓﻴﺔ ﻣﺨﺘﻠﻔﺔ ،ﻓﺴﻴﻜﻮن ﺳﻜﺎﻳﺐ ﻫﻮ أﻓﻀﻞ ﻃﺮﻳﻘﺔ.
Sayed Mohsen
.3ﻫﻞ ﻳﻮاﺟﻪ أي ﻣﻦ اﻟﻔﺮﻳﻖ أي ﻋﺎﺋﻖ؟
Sayed Mohsen
ü Establishing a MVP inspires the team to achieve that aim.
ü Minimum Viable Products ignite shorter-termed urgency and a feeling of accomplishment.
ﻫﻮ إﺻﺪار ﻣﻦ ﻣﻨﺘﺞ ﻳﺤﺘﻮي ﻋﻠﻰ ﻣﻴﺰات ﻛﺎﻓﻴﺔ ﻓﻘﻂ ﻟﻴﺘﻢ اﺳﺘﺨﺪاﻣﻬﺎ ﻣﻦ ﻗﺒﻞ اﻟﻌﻤﻼء اﻟﺬﻳﻦ ﻳﻤﻜﻨﻬﻢ ﺑﻌﺪ ذﻟﻚMVP اﻟﺤﺪ اﻷدﻧﻰ ﻣﻦ اﻟﻤﻨﺘﺞ اﻟﻘﺎﺑﻞ ﻟﻠﺘﻄﺒﻴﻖ §
.ﺗﻘﺪﻳﻢ ﻣﻼﺣﻈﺎت ﻟﻠﻤﺴﺘﻘﺒﻞ
.ﺟﻤﻴﻊ أﺻﺤﺎب اﻟﻤﺼﻠﺤﺔ ﻟﺪﻳﻬﻢ ﻓﺮﺻﺔ ﻟﺮؤﻳﺔ وﺗﺠﺮﺑﺔ ﺷﻜﻞ ﻣﻦ أﺷﻜﺎل ﻧﺘﺎﺋﺞ اﻟﻤﺸﺮوعMVP ، ﻣﻊ §
. ﺣﺘﻰ ﻟﻮ ﻛﺎﻧﺖ ﺑﺤﺪ أدﻧﻰ، ﺗﺼﺒﺢ اﻷﻓﻜﺎر واﻟﻤﻔﺎﻫﻴﻢ ﺣﻘﻴﻘﺔ §
.إﻟﻰ إﻟﻬﺎم اﻟﻔﺮﻳﻖ ﻟﺘﺤﻘﻴﻖ ﻫﺬا اﻟﻬﺪفMVP ﻳﺆدي إﻧﺸﺎء §
. ﻳﻤﻜﻦ أن ﺗﺸﻌﺮ اﻟﻔﺮق ﺑﺎﻹﺣﺒﺎط أو اﻹرﻫﺎق، ﻋﻨﺪﻣﺎ ﺗﻜﻮن اﻟﻨﺘﺎﺋﺞ ﻣﺠﺮدة ﺟًﺪا أو ﺑﻌﻴﺪة ﺟًﺪا §
ﻳﺸﻌﻞ اﻟﺤﺪ اﻷدﻧﻰ ﻣﻦ اﻟﻤﻨﺘﺠﺎت اﻟﻘﺎﺑﻠﺔ ﻟﻠﺘﻄﺒﻴﻖ إﻟﺤﺎًﺣﺎ ﻗﺼﻴﺮ اﻟﻤﺪى وﺷﻌﻮًرا ﺑﺎﻹﻧﺠﺎز §
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 100 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
اﻟ ﺤ ﺪ اﻷ د ﻧ ﻰ ﻣ ﻦ اﻟ ﻤ ﻨ ﺘ ﺞ اﻟ ﻘ ﺎ ﺑ ﻞ ﻟ ﻠ ﺘ ﻄ ﺒ ﻴ ﻖ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 101 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
اﻟ ﺤ ﺪ اﻷ د ﻧ ﻰ ﻣ ﻦ اﻟ ﻤ ﻨ ﺘ ﺞ اﻟ ﻘ ﺎ ﺑ ﻞ ﻟ ﻠ ﺘ ﻄ ﺒ ﻴ ﻖ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 102 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen11. Kanban
أﺳﻠﻮب ﻛﺎﻧﺒﺎن
Sayed Mohsen
Toyota
Taiichi Ohno
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 105 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 106 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 107 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
KANBAN METHOD أﺳﻠﻮب ﻛﺎﻧﺒﺎن
To Do In Progress Done
Sayed Mohsen
Payment gateway Printed materials
Site search
وﻋﻠﻰ ﻋﻜﺲ ٔاﻏﻠﺒﻴﺔ ﻣﻨﻬﺠﻴﺎت اﻷﺳﻠﻮب اﻟﺮﺷﻴﻖ Agileﻓ ٕﺎن ٔاﺳﻠﻮب ﻛﺎﻧﺒﺎن ﻻ ﻳﻮﺟﻪ اﺳﺘﺨﺪام ﺗﻜﺮارات ذات ﻓﺘﺮات زﻣﻨﻴﺔ ﻣﺤﺪدة،
Sayed Mohsen
•
Sayed Mohsen
§ Aim for collaborative improvements § ﺗ ﺤ ﺴ ﻴ ﻦ ﻗ ﺎ ﺑﻠﻴ ﺔ اﻟ ﺘ ﻌ ﺎ و ن
Sayed Mohsen
Kanban Scrum
No Time-boxed iterations Time-boxed iterations are an essential part
Roles : No required roles. The whole team owns Roles : Product owner, scrum master,
the Kanban board. development team
Release Continuous delivery Release At the end of each sprint
ﻛ ﺎ ﻧﺒ ﺎ ن ا ﺳ ﻜ ﺮا م
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 115 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
Extreme programming
( XP )
XP أﺳﻠﻮب
Sayed Mohsen
ü Responsiveness to changing customer requirements.
ü Extreme programming is also known as XP.
ü XP is all about software development best practices.
Sayed Mohsen
اﻟﺘﺸ ﺠ ﻴﻊ اﻟﻤ ﻼ ﺣ ﻈ ﺔ BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 118 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Roles in Extreme Programming
Sayed Mohsen
!"#$%&'%(%')*+$,"-$./-(%'#0$ !"#$'#(#+-.#/0$,"-$,/%3#$ <#5%&#$*&'$,/%3#$3"#$
?#&3-/@A)%'#@5*4%+%3*3-/@4
3"#$4-'#7$
-22)&%4*3-/$0%2%+*/$3-$ /#1)%/#2#&30$./%-/%3%#0$*&'$ *44#.3*=%+%3;$3#037$
8#&#/*+%9#'$0.#4%*+%0307
3"#$B4/)2$?*03#/7 '%/#43%-&$5-/$3"#$./-6#43$0%2%+*/$3-$ :'#*++;$-&#$5-/$
:'#*++;$5-)/$3-$3#&$%&$*$$
3"#$./-')43$-,&#/7 #(#/;$0%>$$
3#*27
'#(#+-.#/07
• Software feature from end-user perspective • و ﺻ ﻒ ﻟﻤ ﺘﻄ ﻠﺒﺎت اﻟﻤ ﻨﺘﺞ ﻣ ﻦ ﻣ ﻨﻈ ﻮ ر اﻟﻤ ﺴ ﺘﺨ ﺪ م اﻟﻨﻬ ﺎﺋﻲ
Sayed Mohsen
• As a <role>, I want <feature> so that <reason/value>. . اﻟﻘﻴﻤﺔ/ أرﻳﺪ >ﻣﻴﺰة >ﻟﻜﻰ < اﻟﺴ ﺒﺐ، <•ﺑﺼ ﻔﺘﻲ >دور
•As a [customer], I want [shopping cart feature] so that [I can easily purchase items online].
•As an [manager], I want to [generate a report] so that [I can understand which departments need more resources].
•As a [customer], I want to [receive an SMS when the item is arrived] so that [I can go pick it up right away]
Sayed Mohsen
.[ أرﻳﺪ ]ﻣﻴﺰة ﺳﻠﺔ اﻟﺘﺴﻮق[ ﺣﺘﻰ ]ﻳﻤﻜﻨﻨﻲ ﺑﺴﻬﻮﻟﺔ ﺷﺮاء اﻟﻌﻨﺎﺻﺮ ﻋﺒﺮ اﻹﻧﺘﺮﻧﺖ، [ﺑﺼﻔﺘﻲ ]ﻋﻤﻴًﻼ
.[ أرﻳﺪ ]إﻧﺸﺎء ﺗﻘﺮﻳﺮ[ ﺑﺤﻴﺚ ]ﻳﻤﻜﻨﻨﻲ ﻓﻬﻢ اﻷﻗﺴﺎم اﻟﺘﻲ ﺗﺤﺘﺎج إﻟﻰ ﻣﺰﻳﺪ ﻣﻦ اﻟﻤﻮارد، [ﺑﺼﻔﺘﻲ ]ﻣﺪﻳًﺮا
[ ﻋﻨﺪ وﺻﻮل اﻟﻌﻨﺼﺮ ]ﺣﺘﻰ ]ﻳﻤﻜﻨﻨﻲ اﻟﺬﻫﺎب ﻻﺳﺘﻼﻣﻪ ﻋﻠﻰ اﻟﻔﻮرSMS أرﻳﺪ [ ﺗﻠﻘﻲ رﺳﺎﻟﺔ، [ﺑﺼﻔﺘﻲ ]ﻋﻤﻴًﻼ
Sayed Mohsen
>#(.:&LQRS
&>#(.:&2(,/#%&%5(;&5(;&5*.4&,#&,%&#(&,=2'"="/#&*&7%".&%#(.:8
B5,%&3(7'4&4"2"/4&(/W ﺗﻮ ﺿ ﺢ ﻧ ﻘ ﺎط اﻟﻘ ﺼ ﺔ ﻣ ﺪ ى ﺻ ﻌ ﻮ ﺑﺔ ﺗﻨﻔ ﻴﺬ ﻗ ﺼ ﺔ اﻟﻤ ﺴ ﺘﺨ ﺪ م .
ﻗ ﺪ ﻳ ﻌ ﺘﻤ ﺪ ﻫ ﺬ ا ﻋ ﻠﻰ : >#(.:&DQU
• D(=2'"P,#:
• اﻟﺘﻌ ﻘ ﻴﺪ
• FP#"/#&(+&7/)/(;/% • اﻟﻤ ﺨ ﺎﻃ ﺮ
>#(.:&MQV
• F++(.# X&#,="8 • اﻟﺠ ﻬ ﺪ و اﻟﻮ ﻗ ﺖ .
B5"&%,1"&N*/4&5"/3""&%#(.:&2(,/#%&*%%,0/"4O&(+&*&%#(.:&4"2"/4%&(/&+*3#(.%G&%735&*%W
Sayed Mohsen
• >"'"3#"&% =*''"%#&%#(.:&*/4&"%#,=*#"&,#&&
C"4,7=J%,1"4&%#(.: >#(.:&LQV #(&A"&;(.#5&(/"&%#(.:&2(,/#
• E&="4,7=J%,1"4&%#(.:&*/4&*%%,0/&,#&+,-"&&
%#(.:&2(,/#%
• E&'*.0"J%,1"4&%#(.:&*/4&*%%,0/&,#,.#""/&&
!*.0"J%,1"4&%#(.: >#(.:&DQRS %#(.:&2(,/#%
Sayed Mohsen
*/4&RU8&B5,%&3*/&A"& (/&."'*#,-"&%,1,/08
"P#"/4"4&*%&."67,."4
• Z"/&35(%"&*/&"%#,=*#"&(+&SG&C,)"&35(%"&UG&F%#5".&&
Sayed Mohsen
35(%"&TG&*/4&C*.:&2,3)"4&V&,/"&+,.%#&.(7/4&(+"&&
"%#,=*#,(/
• B5":&35(%"&VG&VG&VG&*/4&U&."%2"3#,-"':&,/"&%"3(/4&&
.(7/4
• E#,%&2(,/#G"&"%#,=*#"%&*."&3'(%"8
• B5"&2.(473#&(;/".&3*/&*%)"&#"*=&,+&,#&;*/#%&#(&&
0(&;,#5"&=*[(.,#:&+,07."G&+,-"G&(.&35((%""&=(."&&
3(/%".-*#,-"&(2#,(/G&",05#
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 128 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Spike
Spike
C#+.0$%&$/#')4%&A$./-6#43$/%0D0 ﺗﻘ ﻠ ﻴ ﻞ اﻟ ﻤ ﺨ ﺎ ﻃ ﺮ
B"-)+'$/#1)%/#$2%&%2*+$3%2#$*&'$#55-/3E$&-3$2-/#$3"*&$3,-$'*;0
:&(#03%A*3%&A$*&$%00)#
!"#$03-/;$2*;$=#$3--$=%A$3-$=#$#03%2*3#'$*../-./%*3#+;$*&'$3"#$3#*2$2*;$)0#$*$0.%D#$
3-$*&*+;9#$3"#$%2.+%#'$=#"*(%-/$0-$3"#;$4*&$0.+%3$3"#$03-/;$%&3-$#03%2*=+#$.%#4#07
ü The sum of the story point sizes for the features actually completed in this iteration, allows the team to plan its
next capacity more accurately by looking at its historical performance.
ü To predict future velocity, A simple average is all that is needed to calculate an estimated velocity based on
past performance
Sprint Velocity
Sayed Mohsen
1 15 Sum up the individual velocities and divide the result by the
2 20 number of sprints: (15 + 20 + 13 + 24) / 4 = 18
3 13
4 24
Sayed Mohsen
Backlog
ﺗﺮﺗﻴﺐ أوﻟﻮﻳﺎت ﺳﺠﻞ اﻷﻋﻤﺎل
ﺗﺤﺴﻴﻦ ﺳﺠﻞ اﻷﻋﻤﺎل/
ﺗﻨﻘﻴﺢ ﺳﺠﻞ اﻷﻋﻤﺎل/
B5,%&=""#,/0&5"'2%&,/W
L(1,5&3'$ ")(#$$
B44&3'$3(7$")(#$$ إﺿﺎﻓﺔ ﻣﻌﺎﻳﻴﺮ اﻟﻘﺒﻮل ﻟﻜﻞ ﻗﺼﺔ
)*,#&() )*,#&()$*%.*$.#($$ ﻣﺴﺘﺨﺪم
&##(2(5.3*
Adding acceptance
Sayed Mohsen
criteria for upcoming
user stories.
PG&)*&3'$)*,#&()$ F+2&**&3'$Q.#'($
1.-6($#(+#&,#&*&=(4$ )*,#&()$&3*,$)1.22(#$
,#$#(1,5(48 ")(#$$)*,#&()
•A prioritized list of backlog items is produced during a backlog refinement meeting, which occurs before the sprint planning
meeting. The product owner then presents the updated backlog items during the sprint planning meeting.
backlog ﻳﻘﺪم ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﺑﻌﺪ ذﻟﻚ ﻋﻨﺎﺻﺮ.واﻟﺬي ﻳﺤﺪث ﻗﺒﻞ اﺟﺘﻤﺎع اﻟﺘﺨﻄﻴﻂ، •ﻳﺘﻢ إﻧﺘﺎج ﻗﺎﺋﻤﺔ ﺑﺄوﻟﻮﻳﺎت اﻟﺒﻨﻮد ﺧﻼل اﺟﺘﻤﺎع ﺗﺮﺗﻴﺐ اﻻوﻟﻮﻳﺎت
. ا ﻟﻤ ﺤ ﺪ ﺛ ﺔ أ ﺛ ﻨ ﺎ ء ا ﺟ ﺘ ﻤ ﺎ ع ا ﻟﺘ ﺨ ﻄ ﻴ ﻂ
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 133 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Backlog Grooming or Refinement: Example
ﺗﺮﺗﻴﺐ أوﻟﻮ ﻳﺎت ﺳ ﺠﻞ اﻷ ﻋﻤ ﺎل
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 134 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
اﻟﻔﺮق ﺑﻴﻦ اﺟﺘﻤﺎع اﻟﺘﺨﻄﻴﻂ ﻟﻠﺘﻜﺮار واﺟﺘﻤﺎع ﺗﺤﺴﻴﻦ ﺳﺠﻞ اﻋﻤﺎل اﻟﻤﻨﺘﺞ
واﺟﺘﻤﺎع ﺗﺤﺴﻴﻦ ﺳﺠﻞ اﻻﻋﻤﺎل اﺟﺘﻤﺎع اﻟﺘﺨﻄﻴﻂ ﻟﻠﺘﻜﺮار
ﻣﻦ ﺿﻤﻦ
اﺟﺘﻤﺎﻋﺎت اﺳﻜﺮم ؟
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 136 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
15. Information Radiators
ﺷﺎﺷﺔ ﻣﺮﺋﻴﺔ وﻣﺎدﻳﺔ ﺗﻌﺮض ﻣﻌﻠﻮﻣﺎت ﻟﺒﺎﻗﻲ اﻟﻤﺆﺳﺴ ﺔ وﺗﺴﻤﺢ ﺑﻤﺸﺎرﻛﺔ اﻟﻤﻌﺮﻓﺔ ﺣﺘﻰ اﻟﻠﺤﻈﺔ دون اﻟﺤﺎﺟﺔ ٕاﻟﻰ إزﻋﺎج اﻟﻔﺮﻳﻖ.
1 2
&"K.(*3#,-"':&=*/*0" &K.(-,4"&#.*/%2*."/3:&(/
%#*)"5('4". "P2"3#*#,(/8 ;(.)&A",/0&2".+(.="48
Sayed Mohsen
إد ارة ﺗﻮ ﻗ ﻌ ﺎت اﻟﻤ ﻌ ﻨﻴﻴﻦ ﺗﻮ ﻓ ﻴﺮ اﻟﺸ ﻔ ﺎﻓ ﻴﺔ ﻓ ﻲ
ﺑﺸ ﻜ ﻞ اﺳ ﺘﺒﺎﻗ ﻲ اﻟﻌ ﻤ ﻞ اﻟﺬ ي ﻳ ﺘﻢ ﺗﻨﻔ ﻴﺬ ه .
3
&K.(-,4""&#"*=$%&4*,':
&2.(0."%%G&;(.)&67*',#:G
,=2"4,="/#%G&*/4&.,%)%8
ﺗ ﻮ ﻓ ﻴ ﺮ ﻣ ﻌ ﻠﻮ ﻣ ﺎ ت ﺑﺎ ﻟ ﺘ ﻘ ﺪ م اﻟ ﻴ ﻮ ﻣ ﻲ
ﻟﻠﻔ ﺮﻳ ﻖ و ﺟ ﻮ د ة اﻟ ﻌ ﻤ ﻞ و اﻟ ﻌ ﻘ ﺒﺎ ت
و اﻟﻤ ﺨ ﺎﻃ ﺮ . BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 138 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Information Radiators ﺷ ﺎﺷ ﺎت اﻟﻤ ﻌ ﻠﻮ ﻣ ﺎت
>(="&(+"&,/+(.=*#,(/&.*4,*#(.%&3(==(/':&7%"4&,/&*0,'"&2.(["3#%&*."W
<=2"4,="/#&!(0%
ﻟﻮ ﺣ ﺔ ﻛﺎﻧ ﺒﺎن
ﺳ ﺠ ﻞ اﻟﻌ ﻮ اﺋﻖ
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 140 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
ﻣ ﺨ ﻄ ﻂ ا ﻟﻤ ﻬ ﺎم ﻏ ﻴ ﺮ ا ﻟﻤ ﻨ ﺠ ﺰ ة ﻫ ﻮ أ د ا ة ﺑ ﺴ ﻴ ﻄ ﺔ ﺗ ﺘ ﻌ ﻘ ﺐ ﺗ ﻘ ﺪ م ﻋ ﻤ ﻞ ا ﻟﻔ ﺮ ﻳ ﻖ ﻣ ﻘ ﺎ ﺑ ﻞ
ﻳﻌﺪ ﻣﺨﻄﻂ اﻟﻤﻬﺎم اﻟﻤﻨﺠﺰة أداة ُﺗﺴﺘﺨﺪم ﻟﺘﺘﺒﻊ ﻣﻘﺪار • ﻣ ﻘ ﺪ ا ر ا ﻟﻮ ﻗ ﺖ ا ﻟﻤ ﺘ ﺒ ﻘ ﻲ ﻹ ﻛ ﻤ ﺎ ل ا ﻟﻌ ﻤ ﻞ .ﻳ ﻮ ﺿ ﺢ ا ﻟﺮ ﺳ ﻢ ا ﻟﺒ ﻴ ﺎﻧﻲ ا ﻟﻤ ﻌ ﺪ ل ا ﻟﻤ ﺜ ﺎﻟﻲ
ا ﻟﻌ ﻤ ﻞ ا ﻟﺬ ي ﺗ ﻢ إ ﻧﺠ ﺎ ز ه ،و إ ﻇ ﻬ ﺎر ا ﻟﺤ ﺠ ﻢ ا ﻹ ﺟ ﻤ ﺎﻟﻲ ﻟﻠ ﻌ ﻤ ﻞ ﻟﻠ ﺠ ﻬ ﺪ ا ﻟﻼ ز م ﻟﻠ ﻮ ﺻ ﻮ ل إ ﻟﻰ ا ﻛ ﺘ ﻤ ﺎ ل ا ﻟﻌ ﻤ ﻞ ﻓ ﻲ ﺗ ﺎرﻳ ﺦ ﻣ ﺤ ﺪ د .
ﻳ ﺴ ﺎ ﻋ ﺪ ك ا ﻟﻤ ﺨ ﻄ ﻂ ﻋ ﻠ ﻰ :
ﻟﻤ ﺸ ﺮ و ع أ و ﺗ ﻜ ﺮ ا ر . • ﺗ ﻮ ا ﺻ ﻞ ا ﻟﺘ ﻘ ﺪ م
ﻋﻨﺪ إﺿﺎﻓﺔ ﻋﻤﻞ ﺟﺪﻳﺪ ،ﺳُﻴﻈﻬﺮ ﺧﻂ اﻟﻌﻤﻞ اﻹﺟﻤﺎﻟﻲ • • ﺗ ﺘ ﺒ ﻊ ا ﻟﻌ ﻤ ﻞ ا ﻟﻤ ﺘ ﺒ ﻘ ﻲ
• ا ﻟﺘ ﺨ ﻄ ﻴ ﻂ ﻟﻸ ﺣ ﺪ ا ث ا ﻟﻤ ﺴ ﺘ ﻘ ﺒ ﻠ ﻴ ﺔ
ﺑ ﻮ ﺿ ﻮ ح ا ﻟﺰ ﻳ ﺎد ة ﻓ ﻲ ا ﻟﻨ ﻄ ﺎق و ا ﻟﻌ ﻤ ﻞ ا ﻹ ﺟ ﻤ ﺎﻟﻲ . • ا ﻟﻮ ﺻ ﻮ ل إ ﻟﻰ إ ﻧﺠ ﺎز ا ﻟﻌ ﻤ ﻞ ﻓ ﻲ ا ﻟﻮ ﻗ ﺖ ا ﻟﻤ ﺤ ﺪ د
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 141 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Sayed Mohsen
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 142 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Impediment Logs ﺳ ﺠ ﻞ اﻟ ﻌ ﻮ اﺋﻖ
• B5"&#".=&,=2"4,="/# ."+".%&#(&*/:&+*3#(.*#&
2."-"/#% #5"&#"*=&+.(=&*35,"-,/0&,#%&%2.,/#&0(*'8
Impediment Log
• The prime responsibility of scrum masters is to quickly
resolve the impediments. Identified In Progress Resolved
Sayed Mohsen
• These impediments are showcased through impediment
logs, to give an overall view of impediments that are
resolved and outstanding.
. ﻳ ﺸ ﻴﺮ ﻣ ﺼ ﻄ ﻠ ﺢ ا ﻟ ﻌ ﺎ ﺋﻖ إ ﻟ ﻰ أ ي ﻋ ﺎ ﻣ ﻞ ﻳ ﻤ ﻨ ﻊ ا ﻟ ﻔ ﺮ ﻳ ﻖ ﻣ ﻦ ﺗﺤ ﻘ ﻴ ﻖ ﻫ ﺪ ف ا ﻟ ﺘ ﻜ ﺮ ا ر
. ا ﻟ ﻤ ﺴ ﺆ و ﻟ ﻴ ﺔ ا ﻟ ﺮ ﺋﻴ ﺴ ﻴ ﺔ ﻟ ﺴ ﻜ ﺮ م ﻣ ﺴ ﺘﺮ ﻫ ﻲ ﺣ ﻞ ا ﻟ ﻤ ﻌ ﻮ ﻗ ﺎ ت ﺑ ﺴ ﺮ ﻋ ﺔ
ﻹ ﻋ ﻄ ﺎ ء ﻧ ﻈ ﺮ ة ﺷ ﺎ ﻣ ﻠ ﺔ، ﻳ ﺘﻢ ﻋ ﺮ ض ﻫ ﺬ ه ا ﻟ ﻌ ﻮ ا ﺋﻖ ﻣ ﻦ ﺧ ﻼ ل ﺳ ﺠ ﻼ ت ا ﻟ ﻌ ﻮ ا ﺋﻖ
. ﻟ ﻠ ﻌ ﻮ ا ﺋ ﻖ ا ﻟ ﺘ ﻲ ﺗﻢ ﺣ ﻠ ﻬ ﺎ و ا ﻟ ﻤ ﻌ ﻠ ﻘ ﺔ
Sayed Mohsen
• اﻟﻘﻴﺎدة اﻟﺨﺎدﻣﺔ ﻫﻲ ﻣﻤﺎرﺳﺔ اﻟﻘﻴﺎدة ﻣﻦ ﺧﻼل ﺗﻘﺪﻳﻢ اﻟﺨﺪﻣﺔ ٕاﻟﻰ اﻟﻔﺮﻳﻖ ﻋﻦ ﻃﺮﻳﻖ اﻟﺘﺮﻛﻴﺰ ﻋﻠﻰ
.ﻓﻬﻢ وﺗﻠﺒﻴﺔ اﻻﺣﺘﻴﺎﺟﺎت وﺗﻄﻮﻳﺮ ٔاﻋﻀﺎء اﻟﻔﺮﻳﻖ ﻟﺘﻤﻜﻴﻦ ٔاﻋﻠﻰ ٔاداء ﻣﻤﻜﻦ ﻟﻠﻔﺮﻳﻖ
!"#$%$&"&'())
&'"*+,-.
ﺗﺴﻬﻴﻞ اﻟﻌﻤﻞ
43"5%'()&'"*
اﻟﺠﻤﺎﻋﻲ /'*,0'(
$3&'-"#&$,3 $*1'2$*'3&(
ﻳﻤﻜﻦ ﺗﻔﺎﻋﻞ إزاﻟﺔ اﻟﻌﻮاﺋﻖ
اﻟﻔﺮﻳﻖ
Sayed Mohsen
A servant
leader
9611,-&())
1-,:'#&)) اﻟﻘﺎﺋﺪ اﻟﺨﺎدم 43"5%'()"32))
*"3"7'*'3& '26#"&'(
ﻳﺪﻋﻢ إدارة اﻟﺘﻤﻜﻴﻦ واﻟﺘﻌﻠﻢ
اﻟﻤﺸﺮوع
8'%'5-"&'()) 43"5%'()"7$%'))
(6##'(('( 0"%6'(
ﻳﺤﺘﻔﻞ ﺑﺎﻟﻨﺠﺎﺣﺎت ﺗﻤﻜﻦ اﻟﻘﻴﻢ
اﻟﺮﺷﻴﻘﺔ
BY: ElSayed Mohsen
©www.pm-tricks.com - All rights reserved- Do not share 146 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Servant Leaders Facilitate
When project managers act as servant leaders, the emphasis shifts from:
Sayed Mohsen
• Facilitators help everyone do their best thinking and work.
• Facilitators help the team create acceptable solutions.
• A facilitator encourages collaboration through interactive meetings, informal dialog, and knowledge sharing.
. ﻳﺘﺤﻮل ﻣﺪراء اﻟﻤﺸﺮوع ﻣﻦ ﻛﻮﻧﻬﻢ ﻣﺮﻛﺰ اﻟﻤﺸﺮوع ٕاﻟﻰ ﺧﺪﻣﺔ اﻟﻔﺮﻳﻖ واﻹدارة، وﻋﻨﺪ اﻟﻌﻤﻞ ﻋﻠﻰ ﻣﺸﺮوع رﺷﻴﻖ
ﻣﻊ ﺗﻐﻴﻴﺮ ﺗٔﺎﻛﻴﺪﻫﻢ ٕاﻟﻰ ﺗﺪرﻳﺐ اﻷﺷﺨﺎص اﻟﺬﻳﻦ،ﻳﻌﻤﻞ ﻣﺪراء اﻟﻤﺸﺎرﻳﻊ ﻛﻘﺎدة ﺧﺎدﻣﻴﻦAgile ﻓﻲ ﺑﻴٔﻴﺔ اﻷﺳﻠﻮب اﻟﺮﺷﻴﻖ
. وﺗﻌﺰﻳﺰ اﻟﺘﻌﺎون ﺑﺼﻮرة ٔاﻛﺒﺮ ﻓﻲ اﻟﻔﺮﻳﻖ واﻟﻌﻤﻞ ﻋﻠﻰ ﺗﻮاﻓﻖ اﺣﺘﻴﺎﺟﺎت اﻟﻤﻌﻨﻴﻴﻦ،ﻳﺮﻳﺪون اﻟﻤﺴﺎﻋﺪة
ٔاي ﻋﻠﻰ اﻷﺷﺨﺎص اﻟﺬﻳﻦ: ﻳﺸﺠﻊ ﻣﺪراء اﻟﻤﺸﺎرﻳﻊ ﺗﻮزﻳﻊ اﻟﻤﺴٔﻮوﻟﻴﺎت ﻋﻠﻰ اﻟﻔﺮﻳﻖ،وﺑﺼﻔﺘﻬﻢ ﻗﺎدة ﺧﺎدﻣﻴﻦ
.ﻟﺪﻳﻬﻢ ﻣﻌﺮﻓﺔ ﺑٔﺎداء اﻟﻌﻤﻞ
Sayed Mohsen
• Communicate and re-communicate the project vision. . • اﻟ ﺘ ﻮ اﺻ ﻞ و إﻋ ﺎ د ة ﺗ ﻮ ﺻ ﻴ ﻞ رؤ ﻳ ﺔ اﻟﻤ ﺸ ﺮو ع
• Educate stakeholders around why and how to be agile. .• ﺗﻮﻋﻴﺔ اﻟﻤﻌﻨﻴﻴﻦ ﺣﻮل ﻟﻤﺎذا وﻛﻴﻒ ﺗﻜﻮن رﺷﻴًﻘﺎ
• Carry food and water.
B8 9%($I#,4"0*$!73(#$&)$#()+,3)&62(:$)&30($%($0,3*#,2)$*%($@,6D)$#(*"#3$,3$&35()*1(3*8
>8 9%($F0#"1$J.)*(#$&)$#()+,3)&62(:$)&30($%($1")*$#(1,5($&1+(4&1(3*)8
J7 !"#$<#(#+-.2#&3$!#*2$%0$/#0.-&0%=+#H$=#%&A$*$0#+5K-/A*&%9#'$3#*2H$5*4%+%3*3#'$=;$3"#$B4/)2$?*03#/7
Sayed Mohsen
<7 !"#$4-2.*&;$CL$%0$/#0.-&0%=+#H$=#%&A$%&$4"*/A#$-5 "%/%&A$*&'$5%/%&A7
اﻧﻀﻢ ﻣﻄﻮر ﺟﺪﻳﺪ إﻟﻰ ﻓﺮﻳﻖ ﺗﻄﻮﻳﺮ ﺗﻢ ﺗﺸﻜﻴﻠﻪ ﺑﺎﻟﻔﻌﻞ .إﻧﻪ ﻓﻲ ﺻﺮاع داﺋﻢ ﻣﻊ أﻋﻀﺎء اﻟﻔﺮﻳﻖ اﻵﺧﺮﻳﻦ وأﺻﺒﺤﺖ اﻟﺒﻴﺌﺔ ﻣﻌﺎدﻳﺔ .إذا ﻟﺰم
اﻷﻣﺮ ،ﻣﻦ اﻟﺬي ﻳﺠﺐ أن ﻳﺤﺪد اﻟﻤﺸﻜﻠﺔ وﻳﺒﺪأ ﻋﻤﻠﻴﺔ اﻟﺤﻞ؟
C ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﻫﻮ اﻟﻤﺴﺆول ،ﻷﻧﻪ ﻳﺘﺤﻜﻢ ﻓﻲ ﻋﺎﺋﺪ اﻻﺳﺘﺜﻤﺎر ﻋﻠﻰ اﻟﻮﻇﻴﻔﺔ. أ-
ب -اﺳﻜﺮم ﻣﺴﺘﺮ ﻣﺴﺆول ،ﻷﻧﻪ ﻳﺠﺐ ﻋﻠﻴﻪ إزاﻟﺔ اﻟﻌﻮاﺋﻖ.
ج -ﻳﻌﺘﺒﺮ ﻓﺮﻳﻖ اﻟﺘﻄﻮﻳﺮ ﻣﺴﺆوًﻻ ،ﻛﻮﻧﻪ ﻓﺮﻳﻖ ﻣﻨﻈﻢ ذاﺗًﻴﺎ ،ﻳﺘﻢ ﺗﺴﻬﻴﻠﻪ ﺑﻮاﺳﻄﺔ اﺳﻜﺮم ﻣﺴﺘﺮ .
د -اﻟﻤﻮارد اﻟﺒﺸﺮﻳﺔ ﻟﻠﺸﺮﻛﺔ ﻫﻲ اﻟﻤﺴﺆوﻟﺔ ﻋﻦ اﻟﺘﻮﻇﻴﻒ واﻟﻔﺼﻞ.
ج
BY: ElSayed Mohsen
152 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Q2 D-;&-*,%)&+0-6$4&7%,7-+/%8,#5%&.%%,#)"+&=%&0%$4@&()4&;0AC
E8 E#"&"/4&(+"&2.(["3#G&A"3*7%""&'"%%(/%&'"*./"4&=*:&A"&7%"4&(/&+7#7."&2.(["3#%8
L8 &E#"&"/4&(+&"*35&>2.,/#G&A"3*7%"":&"/*A'""&M"-"'(2="/#&B"*=&#(&,/%2"3#&,#%&2.(3"%%"%G
*4*2#"=&*/4"."A:&3(/%#*/#':&,=2.(-"8
D8 Y5"/"-"."&M"-"'(2="/#&B"*=&3(/%,4".%&,#&/"3"%%*.:G&%,/3""&#"*=&,%&%"'+J(.0*/,1"48
Sayed Mohsen
M8 <+"&M"-"'(2="/#&B"*=&,%&4"',-".,/0G&."#.(%2"3#,-"&=""#,/0%&*."&/(#&/"3"%%*.:88
G7 !"#$M/-')43$N,&#/$'#2*&'0$3"*3$3"#$<#(#+-.2#&3$!#*2$,-/D$-(#/3%2#$6)03$5-/$3"%0$B./%&3H$./-(%'#'$3"%0$
'-#0&O3$"*..#&$*A*%&7
Q7 !"#$<#(#+-.2#&3$!#*2$*&'$M/-')43$N,&#/$4-++*=-/*3#H$,%3"$*$(%#,$3-$/#2-(%&A$-/$2-'%5;%&A$%3#207
Sayed Mohsen
J7 J*&4#+$3"#$B./%&37
<7 :&4/#*0%&A$3"#$&)2=#/$-5$B./%&307
أﺛﻨﺎء اﺟ ﺘﻤ ﺎع ﺗﺨ ﻄ ﻴﻂ دو ر ة اﻟﺘﻄ ﻮ ﻳ ﺮ اﻟﻘ ﺼ ﻴﺮة ،ﻳ ﺒﺪ و أن ﺣ ﺠ ﻢ اﻟﻌ ﻤ ﻞ اﻟﻼ زم ﻟﻠﻮ ﻓ ﺎء ﺑ ﺎﻟﻌ ﻨﺎﺻ ﺮ اﻟﺘﻲ ﻳ ﻄ ﻠﺒﻬ ﺎ ﻣ ﺎﻟﻚ اﻟﻤ ﻨﺘﺞ
أﻛﺒﺮ ﻣ ﻦ ﻗ ﺪ رة ﻓ ﺮﻳ ﻖ اﻟﺘﻄ ﻮ ﻳ ﺮ .أي ﻋﻤ ﻞ أﻛﺜﺮ ﻣ ﻨﻄ ﻘ ﻴﺔ ؟
B
ﻳ ﻄ ﻠ ﺐ ﻣ ﺎ ﻟﻚ ا ﻟﻤ ﻨ ﺘ ﺞ ﻣ ﻦ ﻓ ﺮ ﻳ ﻖ ا ﻟﺘ ﻄ ﻮ ﻳ ﺮ ا ﻟﻌ ﻤ ﻞ ﻟﻮ ﻗ ﺖ إ ﺿ ﺎ ﻓ ﻲ ﻓ ﻘ ﻂ ﻟﻬ ﺬ ا ا ﻟﺘ ﻜ ﺮ ا ر ﺑ ﺸ ﺮ ط أ ﻻ ﻳ ﺤ ﺪ ث ذ ﻟﻚ ﻣ ﺮ ة أ ﺧ ﺮ ى . أ-
ب -ﻳ ﺘ ﻌ ﺎو ن ﻓ ﺮ ﻳ ﻖ ا ﻟﺘ ﻄ ﻮ ﻳ ﺮ و ﻣ ﺎﻟﻚ ا ﻟﻤ ﻨ ﺘ ﺞ ﻟﻼ ز ا ﻟﺔ ا ﻟﻌ ﻨ ﺎﺻ ﺮ ا و ﺗ ﻌ ﺪ ﻳ ﻠ ﻬ ﺎ
ج -ا ﻟﻐ ﺎء ا ﻟﺘ ﻜ ﺮ ا ر
ب د -ز ﻳ ﺎد ة ﻋ ﺪ د اﻟﺘ ﻜ ﺮ ارات
BY: ElSayed Mohsen
154 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
Q4 !"#$%&"'()$#"*+$,-$.(("/.0-)$0"$0&-$0-.1$23$.3$452(-$6*"7-/08
E8 B5"&B"*=&!"*4".&N>3.7=&C*%#".O&%5(7'4&*''(3*#"&%2"3,+,3&#*%)%&#(&,/4,-,47*'%
L8 B*%)%&%5(7'4&A"&.*/4(=':&*''(3*#"4&#(&#"*=&="=A".%G&7%,/0&K'*//,/0&K()".8
D8 B"*=&="=A".%&%5(7'4&%"'+J%"'"3#&#*%)%&*22.(2.,*#"&#(",.&%),''%8
Sayed Mohsen
M8 B5"&=(%#&3(=2'"P&#*%)%&%5(7'4&A"&*''(3*#"4&A:"&>3.7=&C*%#".8
Q7 !"#$3#*2$0"-)+'$/#1)#03$0)..-/3$5/-2$#>3#/&*+$3#*2$2#2=#/07$
Sayed Mohsen
J7 !"#$./-')43$-,&#/$0"-)+'$/#2-(#$3"#$4-2.+#>$*43%(%3%#0$5/-2$3"#$./-')43$=*4D+-A7
<7 !"#$3#*2$2#2=#/$=/%&A0$B)=6#43$?*33#/$F>.#/3$RB?F0S$3-$"#+.$3"#27
Q7 C-+'$-&#$'*%+;$03*&').$2##3%&A$5-/$*++$3"#$./-6#4307$
Sayed Mohsen
J7 G00%A&$-&#$4)03-2#/$.-%&3$-5$4-&3*43$5-/$*++$./-6#4307
<7 <#(#+-.$-&#$./-6#43$2*&*A#2#&3$.+*&7
G7 T&'#/03*&'$3"#$4)03-2#/O0$.#/0.#43%(#$*&'$./-(%'#$2#&3-/%&A$-&$*A%+#$2%&'0#30
Q7 &*J*++$5-/$*&$%&3#/&*+$3#*2$/#3/-0.#43%(#$*&'$4/#*3#$*&$%2./-(#2#&3$*43%-&$.+
Sayed Mohsen
J7 G0D$3"#$4)03-2#/$3-$,-/D$,%3"$3"#$./-')43$-,&#/$3-$./%-/%3%9#$*++$/#1)#030
<7 P-/D$,%3"$3"#$3#*2$3-$/#4#%(#$4)03-2#/$'%/#43%-&0$*&'$%2./-(#$3"#$./-4#00
ﻳﻄﻠﺐ اﻟﻌﻤﻴﻞ ﻣﻦ ﻓﺮﻳﻖ اﻟﻤﺸﺮوع ﺗﻀﻤﻴﻦ ﻣﻬﺎم ﺟﺪﻳﺪة ﻓﻲ ﺳﺠﻞ أﻋﻤﺎل اﻟﻤﻨﺘﺞ واﻟﺒﺪء ﻓﻲ ﺗﺤﻠﻴﻞ اﻟﻄﻠﺒﺎت اﻟﺠﺪﻳﺪة .ﻳﺘﻮﻗﻊ
اﻟﻌﻤﻴﻞ اﻟﻨﺘﺎﺋﺞ ﻓﻲ أﻗﺮب وﻗﺖ ﻣﻤﻜﻦ وﻳﻀﻐﻂ ﻋﻠﻰ اﻟﻔﺮﻳﻖ ﻟﺤﻀﻮر اﺟﺘﻤﺎﻋﺎت ﻏﻴﺮ ﻣﻬﻤﻪ .اﻟﻔﺮﻳﻖ ﻣﺤﺒﻂ ﻣﻦ ﻫﺬا اﻟﻮﺿﻊ.
C ﻛﻴﻒ ﻳﺠﺐ أن ﻳﺘﻌﺎﻣﻞ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع ﻣﻊ ﻫﺬا اﻟﻤﻮﻗﻒ؟
ﻓ ﻬ ﻢ و ﺟ ﻬ ﺔ ﻧ ﻈ ﺮ ا ﻟ ﻌ ﻤ ﻴ ﻞ و ﺗﻘ ﺪ ﻳ ﻢ ا ﻟ ﺘ ﻮ ﺟ ﻴ ﻪ ﺑﺸ ﺄن ا ﻟ ﻌ ﻘ ﻠ ﻴ ﺎت ا ﻟ ﻤ ﺮ ﻧ ﺔ أ-
ب -ا ﺗﺼ ﻞ ﺑﺎﻟ ﻔ ﺮ ﻳ ﻖ ﻟ ﻌ ﻤ ﻞ ا ﺟ ﺘ ﻤ ﺎع ﺑﺄﺛﺮ ر ﺟ ﻌ ﻲ و إ ﻧ ﺸ ﺎء ﺧ ﻄ ﺔ ﻋ ﻤ ﻞ ﻟ ﻠ ﺘ ﺤ ﺴ ﻴ ﻦ
ج -اﻃ ﻠﺐ ﻣ ﻦ اﻟﻌ ﻤ ﻴ ﻞ اﻟﻌ ﻤ ﻞ ﻣ ﻊ ﻣ ﺎﻟﻚ اﻟﻤ ﻨ ﺘ ﺞ ﻟﺘ ﺤ ﺪ ﻳ ﺪ أو ﻟﻮ ﻳﺎت ﺟ ﻤ ﻴ ﻊ اﻟﻄ ﻠﺒ ﺎت
ج د -ا ﻋ ﻤ ﻞ ﻣ ﻊ ا ﻟﻔ ﺮ ﻳ ﻖ ﻟﺘ ﻠ ﻘ ﻲ ﺗﻮ ﺟ ﻴ ﻬ ﺎت ا ﻟ ﻌ ﻤ ﻼ ء و ﺗﺤ ﺴ ﻴ ﻦ ا ﻟ ﻌ ﻤ ﻠ ﻴ ﺔ
BY: ElSayed Mohsen
158 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
G$./-6#43$2*&*A#/$%0$2*&*A%&A$*$";=/%'$./-6#437$<)/%&A$./-6#43$#>#4)3%-&H$3"#$./-6#43$2*&*A#/$,*0$
Q8 %&5-/2#'$3"*3$-(#/$"*+5$-5$3"#$./-6#43$=)'A#3$,*0$/#*++-4*3#'$3-$*$./-6#43$3"*3$%0$"*&'+%&A$*&$#2#/A#&4;$
3"*3$/#4#&3+;$-44)//#'7$$P"*3$0"-)+'$3"#$./-6#43$2*&*A#/$'-I$
G7 ?##3$,%3"$3"#$./-')43$-,&#/$3-$4-&5%/2$3"#$2%&%2)2$(%*=+#$./-')43R?UMS$-.3%-&7
Q7 ?##3$,%3"$3"#$./-6#43$3#*2$*&'$/#$./%-/%3%9#$3"#$=*4D+-A7
Sayed Mohsen
J7 '?##3$,%3"$3"#$./-6#43$0.-&0-/$3-$#>.+*%&$3"*3$3"#$./-6#43$4*&$&-3$=#$4-2.+#3#'$*0$.+*&&#
<7 ?##3$,%3"$3"#$3#4"&%4*+$+#*'$3-$/#(%#,$3"#$0./%&3$.+*&7
ﻣﺪﻳﺮ ﻣﺸﺮوع ﻳﺪﻳﺮ ﻣﺸﺮوع ﻫﺠﻴﻦ .أﺛﻨﺎء ﺗﻨﻔﻴﺬ اﻟﻤﺸﺮوع ،ﺗﻢ إﺑﻼغ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع أﻧﻪ ﺗﻤﺖ إﻋﺎدة ﺗﺨﺼﻴﺺ أﻛﺜﺮ ﻣﻦ ﻧﺼﻒ
ﻣﻴﺰاﻧﻴﺔ اﻟﻤﺸﺮوع ﻟﻤﺸﺮوع ﻳﺘﻌﺎﻣﻞ ﻣﻊ ﺣﺎﻟﺔ ﻃﻮارئ ﺣﺪﺛﺖ ﻣﺆﺧًﺮا .ﻣﺎذا ﻳﺠﺐ أن ﻳﻔﻌﻞ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع؟
A ﻗﺎﺑﻞ ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﻟﺘﺄﻛﻴﺪ اﻟﺨﻴﺎر اﻷدﻧﻰ ﻟﻠﻤﻨﺘﺞ اﻟﻘﺎﺑﻞ ﻟﻠﺘﻄﺒﻴﻖ ) ( MVP أ-
ب -ا ﻻ ﺟ ﺘ ﻤ ﺎع ﻣ ﻊ ﻓ ﺮ ﻳ ﻖ ا ﻟﻤ ﺸ ﺮ و ع و ﻋ ﺎد ة ﺗﺮ ﺗﻴ ﺐ أ و ﻟ ﻮ ﻳ ﺎت ﺳ ﺠ ﻞ ا ﻋ ﻤ ﻞ ا ﻟﻤ ﻨ ﺘ ﺞ .
ج -اﻻ ﺟ ﺘ ﻤ ﺎع ر اﻋ ﻲ اﻟﻤ ﺸ ﺮ و ع ﻟﺘ ﻮ ﺿ ﻴ ﺢ أ ن اﻟﻤ ﺸ ﺮ و ع ﻻ ﻳ ﻤ ﻜ ﻦ أ ن ﻳ ﻜ ﺘ ﻤ ﻞ ﻛ ﻤ ﺎ ﻫ ﻮ ﻣ ﺨ ﻄ ﻂ ﻟﻪ
G7 :&5-/2$3"#$5)&43%-&*+$2*&*A#/$3"*3$0#+5K-/A*&%9*3%-&$%&4+)'#0$3*0D$*++-4*3%-&7
Q7 J-&5%/2$,%3"$3"#$3#*2$2#2=#/0$3"*3$3"#$5)&43%-&*+$2*&*A#/$%0$/#0.-&0%=+#$5-/$3"#$'#+%(#/;7
J7 G0D$3"#$./-')43$-,&#/$3-$4+*/%5;$3"#$/-+#0$*&'$/#0.-&0%=%+%3%#0$-5$3"#$./-6#43$3#*27
Sayed Mohsen
<7 %&5-/2$3"#$5)&43%-&*+$2*&*A#/$3"*3$3*0D$*++-4*3%-&$%0$3"#$/#0.-&0%=%+%3;$-5$3"#$./-')43$-,&#/7
ﺧﻼل اﺟﺘﻤﺎع اﻟﺪروس اﻟﻤﺴﺘﻔﺎدة ،أﺑﻠﻎ أﺣﺪ أﻋﻀﺎء اﻟﻔﺮﻳﻖ أن ﻣﺪﻳًﺮا وﻇﻴﻔًﻴﺎ ﻳﺮﻳﺪ أن ﻳﺸﺎرك ﻓﻲ ﺗﺨﺼﻴﺺ اﻟﻤﻬﺎم.
ﻣﺎذا ﻳﺠﺐ أن ﻳﻔﻌﻞ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع؟
A أ ﺑﻠ ﻎ ا ﻟ ﻤ ﺪ ﻳ ﺮ ا ﻟ ﻮ ﻇ ﻴ ﻔ ﻲ أ ن ا ﻟ ﺘ ﻨ ﻈ ﻴ ﻢ ا ﻟ ﺬ ا ﺗﻲ ﻳ ﺘ ﻀ ﻤ ﻦ ﺗﺨ ﺼ ﻴ ﺺ ا ﻟ ﻤ ﻬ ﺎم . أ-
ب -ا ﻟ ﺘ ﺄﻛ ﻴ ﺪ ﻋ ﻠ ﻰ ا ﻟ ﻔ ﺮ ﻳ ﻖ أ ن ا ﻟ ﻤ ﺪ ﻳ ﺮ ا ﻟ ﻮ ﻇ ﻴ ﻔ ﻲ ﻫ ﻮ ا ﻟ ﻤ ﺴ ﺆ و ل ﻋ ﻦ ا ﻟ ﺘ ﺴ ﻠ ﻴ ﻢ .
ج -ا ﻃ ﻠ ﺐ ﻣ ﻦ ﻣ ﺎﻟ ﻚ ا ﻟﻤ ﻨ ﺘ ﺞ ﺗﻮ ﺿ ﻴ ﺢ أ د و ا ر و ﻣ ﺴ ﺆ و ﻟ ﻴ ﺎت ﻓ ﺮ ﻳ ﻖ ا ﻟﻤ ﺸ ﺮ و ع .
G7 B#&'$*$'*%+;$/#3/-0.#43%(#$/#.-/3$3-$*++$3#*2$2#2=#/0$%&03#*'$-5$"-+'%&A$03*&').$2##3%&A07
Q7 :&4+)'#$*$'*%+;$=/*%&03-/2%&A$0#00%-&$:&$3"#$03*&').$2##3%&A0$3-$/#0-+(#$.#&'%&A$:00)#07
Sayed Mohsen
J7 F&A*A#$3"#$./-6#43$3#*2$:&$%2.+#2#&3%&A$*&'$:2./-(%&A$D#;$*0.#430$-5$3"#$03*&').$2##3%&A07
<7 G0D$3"#$./-')43$-,&#/$3-$/#2-(#$3#*2$2#2=#/0$,"-$'-$&-3$4-2.+;$,%3"$03*&').$2##3%&A$/)+#07
ﻳ ﺪ ر ك ﻣ ﺪ ﻳ ﺮ اﻟ ﻤ ﺸ ﺮو ع أن أﻋ ﻀ ﺎء اﻟ ﻔ ﺮﻳ ﻖ ﺟ ﺪ د ﻓ ﻲ اﻟ ﻨ ﻬ ﺞ اﻟ ﻬ ﺠ ﻴ ﻦ و ﻻ ﻳ ﻘ ﺪ ر و ن اﻻ ﺟ ﺘ ﻤ ﺎﻋ ﺎت اﻟ ﻴ ﻮ ﻣ ﻴ ﺔ .ﻏ ﺎﻟ ًﺒ ﺎ ﻣ ﺎ ﻳ ﺼ ﻞ
أﻋ ﻀ ﺎء اﻟ ﻔ ﺮﻳ ﻖ ﻣ ﺘ ﺄ ﺧ ًﺮا أو ﻳ ﺘ ﺨ ﻄ ﻮ ن اﻻ ﺟ ﺘ ﻤ ﺎﻋ ﺎت ﺗﻤ ﺎًﻣ ﺎ.
ﻛﻴﻒ ﻳ ﺠ ﺐ ﻋﻠﻰ ﻣ ﺪ ﻳ ﺮ اﻟﻤ ﺸ ﺮو ع ﺗﺤ ﺴ ﻴﻦ ﻫ ﺬ ا اﻟﻮ ﺿ ﻊ ﻣ ﻊ ﻓ ﺮﻳ ﻖ اﻟﻤ ﺸ ﺮو ع ؟
C
ارﺳﺎل ﺗﻘﺮﻳًﺮا ﺑﺎﺟﺘﻤﺎع اﻟﺪروس اﻟﻤﺴﺘﻔﺎدة ﻳﻮﻣًﻴﺎ إﻟﻰ ﺟﻤﻴﻊ أﻋﻀﺎء اﻟﻔﺮﻳﻖ ﺑﺪًﻻ ﻣﻦ ﻋﻘﺪ اﺟﺘﻤﺎﻋﺎت اﻟﻮﻗﻮف اﻟﻴﻮﻣﻴﺔ أ-
ب -ﺗﻀﻤﻴﻦ ﺟﻠﺴﺔ ﻋﺼﻒ ذﻫﻨﻲ ﻳﻮﻣﻴﺔ ﻓﻲ اﺟﺘﻤﺎﻋﺎت اﻟﻮﻗﻮف اﻟﻴﻮﻣﻴﺔ ﻟﺤﻞ اﻟﻤﺸﻜﻼت اﻟﻤﻌﻠﻘﺔ.
ج -إﺷﺮاك ﻓﺮﻳﻖ اﻟﻤﺸﺮوع ﻓﻲ ﺗﻨﻔﻴﺬ وﺗﺤﺴﻴﻦ اﻟﺠﻮاﻧﺐ اﻟﺮﺋﻴﺴﻴﺔ ﻟﻼﺟﺘﻤﺎﻋﺎت اﻟﻴﻮﻣﻴﺔ.
ج د -ﻳﻄﻠﺐ ﻣﻦ ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ إزاﻟﺔ أﻋﻀﺎء اﻟﻔﺮﻳﻖ اﻟﺬﻳﻦ ﻻ ﻳﻤﺘﺜﻠﻮن ﻟﻘﻮاﻋﺪ اﺟﺘﻤﺎع اﻟﻮﻗﻮف.
G7 <%04-)/*A#$3"%0$/#1)#03H$*0$%3$%0$5-/$3"#$2*&*A#2#&3$3#*27
Q7 F&4-)/*A#$3"#$3#*2$+#*'$3-$2*D#$'#4%0%-&07
J7 <%04-)/*A#$3"#2$*0$4-&5+%430$2*;$=#$4/#*3#'7
Sayed Mohsen
<7 F&4-)/*A#$3"#$3#*2$2#2=#/0$3-$2*D#$'#4%0%-&07
د
BY: ElSayed Mohsen
162 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
G$4)03-2#/$/#(%#,#'$3"#$.+*&$5-/$*$./-6#43$,%3"$"%A"$)&4#/3*%&3;7$!"#$4)03-2#/$#>./#00#'$4-&4#/&#'$
Q12 *=-)3$3"#$,-/D$/#1)%/%&A$BN$2*&;$%3#/*3%-&0$,%3"$*$/%0D$-5$&-3$/#*4"%&A$3"#$2*&'*3-/;$'#+%(#/;$'*3#7$P"%4"$
*../-*4"$0"-)+'$3"#$./-6#43$2*&*A#/$)0#$%&$3"%0$0%3)*3%-&I
G7 "GA%+#$*../-*4
Q7 "V*&=*&$*../-*4
Sayed Mohsen
J7 "C;=/%'$*../-*4
<7 "M/#'%43%(#$*../-*4
G7 L#(%#,$3"#$./-6#43$=*4D+-A$')/%&A$3"#$3#*2O0$03*&').$2##3%&A7
Q7 P-/D$,%3"$3"#$./-')43$-,&#/$3-$#&0)/#$3"#$./-6#43$=*4D+-A$%0$./%-/%3%9#'7
J7 F&0)/#$3#*2$2#2=#/0$*/#$,-/D%&A$*44-/'%&A$3-$3"#$./-6#43$.+*&7
Sayed Mohsen
<7 F&4-)/*A#$./-6#43$3#*2$2#2=#/0$3-$./%-/%3%9#$3"#$./-')43$=*4D+-A7
د -ﺗﺸﺠﻴﻊ أﻋﻀﺎء ﻓﺮﻳﻖ اﻟﻤﺸﺮوع ﻋﻠﻰ إﻋﻄﺎء اﻷوﻟﻮﻳﺔ ﻟﺴﺠﻞ اﻋﻤﺎل اﻟﻤﻨﺘﺞ
ب
BY: ElSayed Mohsen
164 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
G$4-2.*&;$"*0$03*/3#'$'#(#+-.%&A$*$&#,$./-')437$<)/%&A$#>#4)3%-&H$3"#$./-6#43$3#*2$&-3%4#0$3"*3$*&-3"#/$
Q14 4-2.#3%3-/$"*0$+*)&4"#'$*$./-')43$,%3"$(#/;$0%2%+*/$5)&43%-&*+%3%#0$*&'$*$4"#*.#/$2*/D#3$./%4#7
P"*3$0"-)+'$"*(#$=##&$'-&#$'%55#/#&3+;$3-$*(-%'$3"%0$04#&*/%-I
G7 G&$%3#/*3%(#$+%5#$4;4+#$*../-*4"$0"-)+'$"*(#$=##&$*'-.3#'7
Q7 !"#$V*&=*&$2#3"-'$0"-)+'$"*(#$=##&$)3%+%9#'$3-$-.3%2%9#$3"#$,-/D$%&$./-A/#00$RP:MS7
Sayed Mohsen
J7 '?-/#$=*4D+-A$/#5%#&3$2##3%&A0$0"-)+'$"*(#$=##&$04"#')+#
<7 G$2%&%2)2$(%*=+#$./-')43$R?UMS$0"-)+'$"*(#$=##&$/#+#*0#'$3-$A#3$5##'=*4D$5/-2$3"#$2*/D#37
ﺴ ﺎ آﺧ ﺮ ﻗ ﺪ أﻃ ﻠﻖ ﻣ ﻨ ﺘ ًﺠ ﺎ
ﺑ ﺪ أت ﺷ ﺮﻛﺔ ﻓ ﻲ ﺗﻄ ﻮ ﻳ ﺮ ﻣ ﻨﺘﺞ ﺟ ﺪ ﻳ ﺪ .أﺛﻨﺎء اﻟﺘﻨﻔ ﻴﺬ ،ﻻ ﺣ ﻆ ﻓ ﺮﻳ ﻖ اﻟﻤ ﺸ ﺮو ع أن ﻣ ﻨﺎﻓ ً
ﺑ ﻮ ﻇ ﺎﺋﻒ ﻣ ﺘ ﺸ ﺎﺑ ﻬ ﺔ ﺟ ًﺪ ا و ﺳ ﻌ ﺮ أر ﺧ ﺺ .
ﻣ ﺎ اﻟﺬ ي ﻛﺎن ﻳ ﺠ ﺐ ﻓ ﻌ ﻠﻪ ﺑ ﺸ ﻜﻞ ﻣ ﺨ ﺘﻠﻒ ﻟﺘﺠ ﻨﺐ ﻫ ﺬ ا اﻟﺴ ﻴﻨﺎرﻳ ﻮ ؟
D
ﻛﺎن ﻳﺠﺐ اﻋﺘﻤﺎد ﻧﻬﺞ دورة اﻟﺤﻴﺎة اﻟﺘﻜﺮارﻳﺔ. أ-
ب -ﻛﺎن ﻳﺠﺐ اﺳﺘﺨﺪام ﻃﺮﻳﻘﺔ ﻛﺎﻧﺒﺎن ﻟﺘﺤﺴﻴﻦ اﻟﻌﻤﻞ اﻟﺠﺎري ( WIP).
ج -ﻛﺎن ﻳﺠﺐ ﺟﺪوﻟﺔ اﻟﻤﺰﻳﺪ ﻣﻦ اﺟﺘﻤﺎﻋﺎت ﺗﺮﺗﻴﺐ اوﻟﻮﻳﺎت ﺳﺠﻞ اﻋﻤﺎل اﻟﻤﻨﺘﺞ
د د -ﻛﺎن ﻳﺠﺐ إﺻﺪار اﻟﺤﺪ اﻷدﻧﻰ ﻣﻦ اﻟﻤﻨﺘﺞ اﻟﻘﺎﺑﻞ ﻟﻠﺘﻄﺒﻴﻖ ) ( MVPﻟﻠﺤﺼﻮل ﻋﻠﻰ ﺗﻌﻠﻴﻘﺎت ﻣﻦ اﻟﺴﻮق.
G7 W*4%+%3*3#$*$./%-/%3;$/#0-+)3%-&$-5$3"#$%00)#$,%3"$3"#$:!$'#.*/32#&37
Q7 T.'*3#$3"#$%00)#$+-A$*&'$#04*+*3#$3"#$./-=+#2$3-$3"#$./-')43$-,&#/7
J7 B)AA#03$3"*3$3"#$3#*2$2#2=#/$4-&3*43$3"#$:!$'#.*/32#&37
Sayed Mohsen
<7 G0D$3"#$-3"#/$3#*2$2#2=#/0$3-$03#.$%&$*&'$'-$3"#$,-/D7
G7 M/-(%'#$5##'=*4D$3-$3"#$3#*2$*&'$4-&')43$*$2##3%&A$3-$/#(%#,$3"#$3#*2$/)+#07
Q7 M/-(%'#$5##'=*4D$3-$3"#$3#*2$*&'$4-&')43$*$/#3/-0.#43%(#$2##3%&A$3-$5%&'$*$/--3$4*)0#
Sayed Mohsen
J7 M/-(%'#$5##'=*4D$3-$3"#$3#*2$*&'$4-*4"$3"#$&#,$3#*2$2#2=#/$%&$*A%+#$2#3"-'-+-A;7
<7 M/-(%'#$5##'=*4D$3-$3"#$3#*2$*&'$/#1)#03$*A%+#$3/*%&%&A$5-/$3"#$&#,$2#2=#/7
G7 F04*+*3#$3"#$.#/5-/2*&4#$%00)#$3-$3"#$3#*2$2#2=#/O0$5)&43%-&*+$2*&*A#/7
Q7 L#(%#,$3"#$")2*&$/#0-)/4#0$RCLS$.-+%4%#0$5-/$/#+#(*&3$4-//#43%(#$*43%-&07
Sayed Mohsen
J7 <%04)00$3"#$%00)#$,%3"$3"#$3#*2$2#2=#/$%&$*$-&#K-&K-&#$2##3%&A7
<7 G0D$3"#$3#*2$2#2=#/$3-$6)03%5;$3"#$'#+*;$')/%&A$*$3#*2$2##3%&A7
ﺗﻢ ﻓ ﻘ ﺪ ان أﺣ ﺪ اﻟﻤ ﻌ ﺎﻟﻢ اﻟﻬ ﺎﻣ ﺔ ﻟﻠﻤ ﺸ ﺮو ع ﻷ ن أﺣ ﺪ أﻋ ﻀ ﺎء اﻟﻔ ﺮﻳ ﻖ ﻟﻢ ﻳ ﻜ ﻤ ﻞ ﻣ ﻬ ﺎﻣ ﻪ ﻓ ﻲ اﻟﻮ ﻗ ﺖ اﻟﻤ ﺤ ﺪ د .أدى ذﻟﻚ
إﻟﻰ ﻣ ﻨﺎﻗ ﺸ ﺔ ﺳ ﺎﺧ ﻨﺔ ﺧ ﻼ ل ﻋ ﺮض ﺗﻮ ﺿ ﻴﺤ ﻲ ﻟﻠﻤ ﺴ ﺘﺨ ﺪ ﻣ ﻴﻦ اﻟﻨﻬ ﺎﺋﻴﻴﻦ .ﻣ ﺎذا ﻳ ﺠ ﺐ أن ﻳ ﻔ ﻌ ﻞ ﻣ ﺪ ﻳ ﺮ اﻟﻤ ﺸ ﺮو ع ﺑ ﻌ ﺪ ذﻟﻚ ؟
C ﺗﺼﻌﻴﺪ ﻣﺸﻜﻠﺔ اﻷداء إﻟﻰ اﻟﻤﺪﻳﺮ اﻟﻮﻇﻴﻔﻲ ﻟﻌﻀﻮ اﻟﻔﺮﻳﻖ. أ-
ب -ﻣﺮاﺟﻌﺔ ﺳﻴﺎﺳﺎت اﻟﻤﻮارد اﻟﺒﺸﺮﻳﺔ ) (HRﻟﻺﺟﺮاءات اﻟﺘﺼﺤﻴﺤﻴﺔ ذات اﻟﺼﻠﺔ.
ج -ﻣﻨﺎﻗﺸﺔ اﻟﻤﺸﻜﻠﺔ ﻣﻊ ﻋﻀﻮ اﻟﻔﺮﻳﻖ ﻓﻲ اﺟﺘﻤﺎع ﻓﺮدي.
د -اﻃﻠﺐ ﻣﻦ ﻋﻀﻮ اﻟﻔﺮﻳﻖ ﺗﺒﺮﻳﺮ اﻟﺘﺄﺧﻴﺮ أﺛﻨﺎء اﺟﺘﻤﺎع اﻟﻔﺮﻳﻖ.
ج
BY: ElSayed Mohsen
168 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
G$./-6#43$2*&*A#/$,*0$*0D#'$3-$./-(%'#$*&$%&'%4*3%-&$-5$3"#$3%2#$/#2*%&%&A$-&$*&$*A%+#$./-6#437$P"*3$3--+0$
Q18 4*&$=#$)0#'$3-$./-(%'#$3"%0$%&5-/2*3%-&I
G7 B3-/;$.-%&30$5-/$3"#$/#2*%&%&A$)0#/$03-/%#0
Q7 B3-/;$.-%&30$5-/$3"#$/#2*%&%&A$)0#/$03-/%#0
J7 M*/#3-$4"*/3
Sayed Mohsen
<7 G$/#+#*0#$=)/&'-,&$4"*/3
ُﻃ ﻠ ﺐ ﻣ ﻦ ﻣ ﺪ ﻳ ﺮ اﻟ ﻤ ﺸ ﺮو ع ﺗﻘ ﺪ ﻳ ﻢ ﻣ ﺆ ﺷ ﺮ إﻟ ﻰ اﻟ ﻮ ﻗ ﺖ اﻟ ﻤ ﺘ ﺒ ﻘ ﻲ ﻓ ﻲ ﻣ ﺸ ﺮو ع اﺟ ﺎﻳ ﻞ .
ﻣ ﺎ ﻫ ﻲ اﻷ دو ات اﻟﺘﻲ ﻳ ﻤ ﻜﻦ اﺳ ﺘﺨ ﺪ اﻣ ﻬ ﺎ ﻟﺘﻮ ﻓ ﻴﺮ ﻫ ﺬ ه اﻟﻤ ﻌ ﻠﻮ ﻣ ﺎت ؟
D ﻧﻘﺎط اﻟﻘﺼﺔ ﻟﻘﺼﺺ اﻟﻤﺴﺘﺨﺪم اﻟﻤﺘﺒﻘﻴﺔ أ-
ب -ﻧﻘﺎط اﻟﻘﺼﺔ ﻟﻘﺼﺺ اﻟﻤﺴﺘﺨﺪم اﻟﻤﺘﺒﻘﻴﺔ
ج -ﻣﺨﻄﻂ ﺑﺎرﻳﺘﻮ
د -اﺻﺪار ﻣﺨﻄﻂ اﻻﺣﺘﺮاق burndown chart
د
BY: ElSayed Mohsen
169 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
<)/%&A$*&$*A%+#$./-6#43H$*$./-6#43$2*&*A#/$+-03$-&#$-5$3"#$/#0-)/4#0H$*&'$*3$3"#$0*2#$3%2#H$)&4-(#/#'$&#,$
Q19 /#1)%/#2#&30H$,"%4"$,#/#$*''#'$3-$3"#$=*4D+-A7$P"*3$0"-)+'$3"#$./-6#43$2*&*A#/$'-$&#>3I
G7 L##(*+)*3#$3"#$04-.#$-5$3"#$4)//#&3$%3#/*3%-&$3-$D##.$3"#$0*2#$(#+-4%3;$*&'$3%2#+%
Q7 L##(*+)*3#$3"#$=*4D+-A$./%-/%3;$,%3"$3"#$./-')43$-,&#/$0%&4#$3"#$(#+-4%3;$"*0$=##&$%2.*43#'7
J7 L##(*+)*3#$3"#$(#+-4%3;$*0$3"#$%3#/*3%-&$')/*3%-&$,%++$=#$%2.*43#'$=;$&#,$/#1)%/#2#&307
Sayed Mohsen
<7 L##(*+)*3#$3"#$./-6#43$04"#')+#$*0$3"#$(#+-4%3;$,%++$=#$%2.*43#'$=;$3"#$+-00$-5$/#0-)/4#07
G7 B"*/#$3"%0$,%3"$3"#$3#*2$*&'$*0D$3"#2$3-$'#(#+-.$/#.-/30$5-/$3"#$'%/#43-/7
Q7 :&3/-')4#$3"#$*A%+#$*0.#43$3-$3"#$'%/#43-/$*&'$*A/##$-&$*$0-+)3%-&7
Sayed Mohsen
J7 F>.+*%&$3-$3"#$'%/#43-/$3"*3$*A%+#$./-6#430$"*(#$+%(#$/#.-/307
<7 :&(%3#$3"#$'%/#43-/$3-$*33#&'$3"#$'*%+;$03*&').$2##3%&A07
L8 C(-""%"&7%".&%#(.,"%&A*3)&#("&2.(473#&A*3)'(0&+(.&."2.,(.,#,1*#,(/8
D8 D(=2'"#""%"&7%".&%#(.,"%&,/"&37.."/#&%2.,/#&*/4&"P#"/4"&%2.,/#&'"/0#58
Sayed Mohsen
M8 ?"=(-""%"&7%".&%#(.,"%&*%":&*."&/(#&,=2(.#*/#8
أﺛﻨﺎء اﺟ ﺘﻤ ﺎع اﻟﻤ ﺮاﺟ ﻌ ﺔ ﺑ ﺄﺛﺮ ر ﺟ ﻌ ﻲ ،و ﺟ ﺪ اﻟﻔ ﺮﻳ ﻖ أن ﺟ ﻤ ﻴﻊ ﻗ ﺼ ﺺ اﻟﻤ ﺴ ﺘﺨ ﺪ ﻣ ﻴﻦ ﻟﻴﺴ ﺖ ﻛﺎﻣ ﻠﺔ .ﻣ ﺎ اﻟﺬ ي ﻳ ﺠ ﺐ ﻓ ﻌ ﻠﻪ
B8 9.?($.0*&,3$*,$#(+#&,#&*&=($*%($6.0?2,'$./*(#$(5(#-$&*(#.*&,3$*,$(5.2".*($&/$")(#$)*,#&()$.#($)*&22$5.2".62($*,$*%($6")&3())8
>8 F*,+$*%($&*(#.*&,3$.)$),,3$.)$+,))&62($&3$0.)($.3$(G*(#3.2$0%.3'($*%.*$1.?()$*%($+#,4"0*$&35.2".62($&)$&4(3*&/&(48
Sayed Mohsen
H8 O1+2(1(3*$/.0(<*,</.0($0,11"3&0.*&,3$6(*7((3$*%($*(.1$.34$+#,4"0*$,73(#$*,$0%.3'($*%($&*(#.*&,3$,6@(0*&5()$.)$3((4(48
E8 B++2-$.$+.&#$+#,'#.11&3'$*(0%3&;"($*,$#(.0*$*,$0%.3'()$&11(4&.*(2-:$(5(3$&3$*%($1&442($,/$*%($&*(#.*&,38
ﻳﻌﻤﻞ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع ﻋﻠﻰ ﻣﺸﺮوع رﺷﻴﻖ ﻓﻲ ﺑﻴﺌﺔ ﻋﻤﻞ ﻣﺘﻐﻴﺮة .ﻳﺸﻌﺮ راﻋﻲ اﻟﻤﺸﺮوع ﺑﺎﻟﻘﻠﻖ ﺑﺸﺄن ﺗﺤﻘﻴﻖ اﻟﻤﻨﺎﻓﻊ وﻳﻄﻠﺐ ﻣﻦ ﻣﺪﻳﺮ
A اﻟﻤﺸﺮوع اﻻﻧﺘﺒﺎه إﻟﻰ اﻟﺘﻐﻴﻴﺮات اﻟﺘﻲ ﻳﻤﻜﻦ أن ﺗﺆﺛﺮ ﻋﻠﻰ اﻟﻤﺸﺮوع.
ﻣﺎ اﻹﺟﺮاء اﻟﺬي ﻳﺠﺐ ﻋﻠﻰ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع اﺗﺨﺎذه ﻟﺘﺤﺪﻳﺪ اﻟﺘﻐﻴﻴﺮات اﻟﺘﻲ ﻗﺪ ﺗﺆﺛﺮ ﻋﻠﻰ اﻟﻤﻨﺘﺞ؟
أ -اﺗﺨﺎذ إﺟﺮاء ﻹﻋﺎدة ﺗﺮﺗﻴﺐ أوﻟﻮﻳﺎت ﺳﺠﻞ اﻋﻤﺎل اﻟﻤﻨﺘﺞ ﺑﻌﺪ ﻛﻞ ﺗﻜﺮار ﻟﺘﻘﻴﻴﻢ ﻣﺎ إذا ﻛﺎﻧﺖ ﻗﺼﺺ اﻟﻤﺴﺘﺨﺪﻣﻴﻦ ﻻ ﺗﺰال ذات ﻗﻴﻤﺔ ﻟﻸﻋﻤﺎ
ب – اﻳﻘﺎف اﻟﺘﻜﺮار ﻓﻲ أﺳﺮع وﻗﺖ ﻣﻤﻜﻦ ﻓﻲ ﺣﺎﻟﺔ ﺗﺤﺪﻳﺪ ﺗﻐﻴﻴﺮ ﺧﺎرﺟﻲ ﻳﺠﻌﻞ اﻟﻤﻨﺘﺞ ﻏﻴﺮ ذي ﻗﻴﻤﺔ.
أ ج -ﺗﻨﻔﻴﺬ اﻟﺘﻮاﺻﻞ وﺟﻬًﺎ ﻟﻮﺟﻪ ﺑﻴﻦ اﻟﻔﺮﻳﻖ وﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﻟﺘﻐﻴﻴﺮ أﻫﺪاف اﻟﺘﻜﺮار ﺣﺴﺐ اﻟﺤﺎﺟﺔ.
د -ﺗﻄﺒﻴﻖ أﺣﺪ اﺳﺎﻟﻴﺐ اﻟﺒﺮﻣﺠﺔ اﻟﻤﺰدوﺟﺔ ﻟﻠﺮد ﻋﻠﻰ اﻟﺘﻐﻴﻴﺮات ﻓﻮًرا ،ﺣﺘﻰ ﻓﻲ ﻣﻨﺘﺼﻒ اﻟﺘﻜﺮار.
BY: ElSayed Mohsen
173 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
(B3$,#'.3&=.*&,3$&)$)*#"''2&3'$*,$)*.#*$.3$&1+,#*.3*$+#,@(0*8$9%($+#,@(0*$1.3.'(#$%.)$&4(3*&/&(4$*%.*$*%($)0,+($4(/&3&*&,3$&)$*%
1.&3$&*(1$+#(5(3*&3'$*%($+#,@(0*$/#,1$)*.#*&3'8$B2*%,"'%$1,)*$,/$*%($)0,+($&*(1)$.#($4(/&3(4$.34$.'#((4$"+,3$.1,3'$*%($
)*.?(%,24(#):$*%(#($.#($.$/(7$&*(1)$*%.*$.#($%.#4$*,$'#.)+$.34$5(#-$0,1+2(G$*,$4(/&3($.*$*%&)$)*.'(8$C%.*$)%,"24$*%($+#,@(0*$
Q23 1.3.'(#$4,R
A. Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the
project.
B. Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with
the complex items.
Sayed Mohsen
C. Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added
to help define the project scope.
D. Recommend spitting the project into two smaller projects in order to work exclusively in an agile environment without
interference from a predictive approach.
ﺗﻮاﺟﻪ اﺣﺪى اﻟﻤﺆﺳﺴﺎت ﺻﻌﻮﺑﺔ ﻓﻲ ﺑﺪء ﻣﺸﺮوع ﻣﻬﻢ .ﺣﺪد ﻣﺪﻳﺮ اﻟﻤﺸﺮوع أن ﺗﻌﺮﻳﻒ اﻟﻨﻄﺎق ﻫﻮ اﻟﻌﻨﺼﺮ اﻟﺮﺋﻴﺴﻲ اﻟﺬي ﻳﻤﻨﻊ ﺑﺪء اﻟﻤﺸﺮوع .ﻋﻠﻰ اﻟﺮﻏﻢ ﻣﻦ أن
ﻣﻌﻈﻢ ﺑﻨﻮد اﻟﻨﻄﺎق ﻳﺘﻢ ﺗﺤﺪﻳﺪﻫﺎ واﻻﺗﻔﺎق ﻋﻠﻴﻬﺎ ﺑﻴﻦ اﻟﻤﻌﻨﻴﻴﻦ ،إﻻ أن ﻫﻨﺎك ﻋﺪًدا ﻗﻠﻴًﻼ ﻣﻦ اﻟﻌﻨﺎﺻﺮ اﻟﺘﻲ ﻳﺼﻌﺐ ﻓﻬﻤﻬﺎ واﻟﺘﻲ ﻳﺼﻌﺐ ﺗﺤﺪﻳﺪﻫﺎ ﻓﻲ ﻫﺬه
B اﻟﻤﺮﺣﻠﺔ .ﻣﺎذا ﻳﺠﺐ أن ﻳﻔﻌﻞ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع؟
أ -اﻟﺤﻔﺎظ ﻋﻠﻰ ﺣﻤﺎس اﻟﻤﻌﻨﻴﻴﻦ ﻟﻠﻌﻤﻞ ﻋﻠﻰ ﺗﻌﺮﻳﻒ اﻟﻨﻄﺎق اﻟﻰ ان ﻳﺘﻢ اﻟﻮﺻﻮل اﻟﻰ اﻟﻨﻄﺎق اﻟﺘﻔﺼﻴﻠﻲ اﻟﻜﺎﻣﻞ ﻗﺒﻞ ﺑﺪء اﻟﻤﺸﺮوع.
ب – اﻗﺘﺮاح ﺗﺴﻠﻴﻢ ﻋﻨﺎﺻﺮ اﻟﻨﻄﺎق اﻟﻤﺤﺪدة ﺟﻴًﺪا ﺑﺎﺳﺘﺨﺪام ﻧﻬﺞ ﺗﻨﺒﺆي واﺳﺘﺨﺪام ﻧﻬﺞ اﻷﺳﻠﻮب اﻟﺮﺷﻴﻖ ﻟﻠﺘﻌﺎﻣﻞ ﻣﻊ اﻟﻌﻨﺎﺻﺮ اﻟﻤﻌﻘﺪة.
ج -ﺗﺤﺪﻳﺚ ﺳﺠﻞ اﻟﻤﺨﺎﻃﺮ وﺗﺼﻌﻴﺪ اﻟﻤﺸﻜﻠﺔ إﻟﻰ ﻣﻜﺘﺐ إدارة اﻟﻤﺸﺮوع ) PMO) ،وﻃﻠﺐ إﺿﺎﻓﺔ اﻟﻤﺰﻳﺪ ﻣﻦ اﻟﻤﻮارد ﻟﻠﻤﺴﺎﻋﺪة ﻓﻲ ﺗﺤﺪﻳﺪ ﻧﻄﺎق اﻟﻤﺸﺮوع.
ب د -اﻟﺘﻮﺻﻴﺔ ﺑﺘﻘﺴﻴﻢ اﻟﻤﺸﺮوع إﻟﻰ ﻣﺸﺮوﻋﻴﻦ ﺻﻐﻴﺮﻳﻦ ﻣﻦ أﺟﻞ اﻟﻌﻤﻞ ﺣﺼﺮًﻳﺎ ﻓﻲ ﺑﻴﺌﺔ رﺷﻴﻘﺔ دون اﺳﺘﺨﺪام اﻟﻨﻬﺞ اﻟﺘﻨﺒﺆي ﻣﻄﻠﻘﺎ
BY: ElSayed Mohsen
174 PfMP®, PgMP®, PMP®, PBA® , RMP®, SP®, ACP®, P3O
&*&E&'*A(.*#(.:&,%&'*7/35,/0&*&/";&2.(473#G&4"+,/"4&#(&A"&"P"37#"4&,/&",05#&,#".*#,(/%&;,#5
Q24 &+,P"4&."'"*%"&4*#"8&E#"&A"0,//,/0&(+"&%"3(/4&,#".*#,(/G"&2.(["3#&=*/*0".&."*',1"%
&"#5*#&*&%,0/,+,3*/#&."07'*#(.:&+"*#7."&,%&=,%%,/0&,/"&2.(["3#&A*3)'(08&Y5*#&%5(7'4
\(2.(["3#&=*/*0".&4
E8 </-,#"&%#*)"5('4".%&#(&4,%37%%"&,=2*3#&(+&*44,/0"&."07'*#(.:&+"*#7."8
L8 </3."*%""&3*2*3,#:&(+"&#"*=&#(&,/3'74""&=,%%"4&+"*#7."8
Sayed Mohsen
D8 F%#,=*#""&."'*#"4&3(%#&*/4&*%)&+(.&*&2.(["3#&"P#"/%,(/8
M8 E%)"&2.(473#&(;/".&#(&*44"&=,%%,/0&+"*#7."&,/"&A*3)'(08
ﻳﺼﺪر أﺣﺪ اﻟﻤﺨﺘﺒﺮات ﻣﻨﺘًﺠﺎ ﺟﺪﻳًﺪا ،وﻣﻘﺮر ﺗﻨﻔﻴﺬه ﻓﻲ ﺛﻤﺎﻧﻴﺔ ﺗﻜﺮارات ﺑﺘﺎرﻳﺦ إﺻﺪار ﺛﺎﺑﺖ .ﻓﻲ ﺑﺪاﻳﺔ اﻟﺘﻜﺮار اﻟﺜﺎﻧﻲ ،ﻳﺪرك ﻣﺪﻳﺮ
اﻟﻤﺸﺮوع أن ﻫﻨﺎك ﻣﻴﺰة ﺗﻨﻈﻴﻤﻴﺔ ﻣﻬﻤﺔ ﻣﻔﻘﻮدة ﻓﻲ ﺳﺠﻞ اﻋﻤﺎل اﻟﻤﺸﺮوع .ﻣﺎذا ﻳﺠﺐ أن ﻳﻔﻌﻞ ﻣﺪﻳﺮ اﻟﻤﺸﺮوع؟
D
أ -دﻋﻮة اﻟﻤﻌﻨﻴﻴﻦ ﻟﻤﻨﺎﻗﺸﺔ ﺗﺄﺛﻴﺮ إﺿﺎﻓﺔ اﻟﻤﻴﺰة اﻟﺘﻨﻈﻴﻤﻴﺔ.
ب – زﻳﺎدة ﻗﺪرة اﻟﻔﺮﻳﻖ ﻟﺘﻀﻤﻴﻦ اﻟﻤﻴﺰة اﻟﻤﻔﻘﻮدة.
ج -ﺗﻘﺪﻳﺮ اﻟﺘﻜﻠﻔﺔ ذات اﻟﺼﻠﺔ وﻃﻠﺐ ﺑﺘﻤﺪﻳﺪ اﻟﻤﺸﺮوع.
د د -ﻣﻄﺎﻟﺒﺔ ﻣﺎﻟﻚ اﻟﻤﻨﺘﺞ ﺑﺈﺿﺎﻓﺔ اﻟﻤﻴﺰة اﻟﻤﻔﻘﻮدة ﻓﻲ ﺳﺠﻞ اﻻﻋﻤﺎل.
>8 E(/&3&*&,3$,/$4,3($KE,EM
Sayed Mohsen
H8 *>"#34,73$0%.#
E8 *N(2,0&*-$0%.#
أﺛﻨﺎء ﻋﺮض اﻻﻃﻼق ،اوﺿﺢ اﻟﻌﻤﻴﻞ أن اﺣﺪى ﻗﺼﺺ اﻟﻤﺴﺘﺨﺪﻣﻴﻦ ﻟﻴﺴﺖ ﺟﺎﻫﺰة ﻟﻴﺴﺘﺨﺪﻣﻬﺎ اﻟﻌﻤﻴﻞ .ﻣﺎ ﻗﺎﺋﻤﺔ اﻟﻤﺮاﺟﻌﺔ اﻟﺘﻲ ﻳﻨﺒﻐﻲ
ﻟﻠﻔﺮﻳﻖ اﻟﻨﻈﺮ ﻓﻴﻬﺎ ﻟﻤﻌﺮﻓﺔ ﻣﺎ اﻟﺬى ﺗﻢ اﻏﻔﺎﻟﻪ ﻓﻲ ﻗﺼﺔ اﻟﻤﺴﺘﺨﺪم ؟
B
ﺗ ﻌ ﺮ ﻳ ﻒ ا ﻟﺠ ﻬ ﻮ ز ﻳ ﺔ أ-
ب -ﺗ ﻌ ﺮ ﻳ ﻒ ا ﻟﻤ ﻨ ﺠ ﺰ
ج -ﻣ ﺨ ﻄ ﻂ ا ﻟﺤ ﺮ ق ا ﻟﺘ ﻨ ﺎ ز ﻟﻲ
ب د -ﻣ ﺨ ﻄ ﻂ اﻟﺴ ﺮ ﻋ ﺔ