December 19,2023

This document is an overtime request form for a construction project providing details of the requested overtime including: date, total hours requested from 3pm to 6pm, reason for the overtime which is to concrete columns and footings, tasks to be completed, and a list of 26 employees involved. It must be submitted before end of regular hours and confirmed by phone to be eligible for overtime compensation. The supervisor/manager section is to approve or deny the request.

Uploaded by

asscjeff
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views1 page

December 19,2023

This document is an overtime request form for a construction project providing details of the requested overtime including: date, total hours requested from 3pm to 6pm, reason for the overtime which is to concrete columns and footings, tasks to be completed, and a list of 26 employees involved. It must be submitted before end of regular hours and confirmed by phone to be eligible for overtime compensation. The supervisor/manager section is to approve or deny the request.

Uploaded by

asscjeff
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Overtime Request Form (Site)

Overtime work will not be compensated unless this form is filled out and submitted prior to the commencement of the overtime. It must be sent before the
end of regular working hours at the construction site. Please email it to [email protected] and dial 0918-947-3572 to confirm receipt of the
email.

Project Information
Date of Request Project Name Site Location ID (For Manager)
12/19/23 ILOCOS SUR NATIONAL HIGHSCHOOL VIGAN CITY PID0007-Ilocos
NHS_20231213

Overtime Work Information


Date(s) of Proposed Overtime: 12/19/23
Total Hours of Overtime Requested: 3 hours
Start and End Time of Overtime: 3:00 pm to 6:00 pm
Reason for Overtime (Detailed Description):
Concreting of Columns at Lot 16 (5 sets of Column)
Concreting of Columns at Lot 15 ( 2 sets of Column)
Concreting of Isolated Footing

Tasks and Objectives


Breakdown of Overtime Activities (Attach diagrams or sketches on a separate sheet if necessary):

Concreting of Columns at Lot 16 (5 sets of Column)


Concreting of Columns at Lot 15 ( 2 sets of Column)
Concreting of Isolated Footing

List of Employees Involved in Overtime Work (Attach an extra sheet if more space is required):
# Name Position # Name Position
1 Engr. Jefferson Proj. Engineer 14 Michael Labor
2 Maricel Admin Staff 15 Bong Carpenter
3 Garry Foreman 16 Joseph Steelman
4 Pablo Pison Operator 17 Jerry B. Steelman
5 Jeboy Equipment Spt. 18 Nonoy Steelman
6 Shalmar BH Operator 19 Pedro Steelman
7 Robert Loader Optr 20 Tony Steelman
8 Rennel Driver 21 Rowel A. Labor
9 Mike BH Operator 22 Marius Steelman
10 Danilo Carpenter 23 Oliver Labor
11 Joshua Carpenter 24 Jordan Labor
12 Jason Carpenter 25 Rovic Labor
13 Renold Carpenter 26 Gelo Labor

Acknowledgment Supervisor/Manager Approval


I hereby acknowledge that the above information is To be filled out by Supervisor/Manager:
accurate, and I have read and understood the Approval Status: ☐ Approved ☐ Denied
company's overtime policy. I commit to effectively
utilize the overtime period for the tasks stated above. Comments (If any):

Requested By (Name): Engr. J. Antonio


Position/Title: Project Engineer