Heathrow Tower
Heathrow Tower
Terminal 5, London Heathrow: With the basic height and location requirements
selected, the project team’s task was to develop an
efficient and elegant tower design, simultaneously
The new control tower addressing the considerable construction challenges
of building on an island site surrounded by aircraft.
A key requirement was to cause no operational
disruption to the running of the airport; this had
Jeremy Edwards Richard Matthews Sean McGinn a significant effect on development of the design
solution and the construction that followed.
Functionality
The size and position of Terminal 5 necessitated a new
The location at Heathrow’s centre necessitates full
central location for Heathrow’s air-traffic control tower, 360˚ views from the cab, whilst the taxiways and
which introduced challenges for the project team in the stands at the tower base need an extremely low
tower’s design, fabrication, and delivery. viewing angle. To fulfil these requirements, the final
design provides what is thought to be the largest
cone of vision of any control tower in the world
Introduction (Fig 3). However, the requirements of floor space
for the controllers and their equipment had to be
This is the third Arup Journal article to deal with aspects of Arup’s work on Terminal 5
at Heathrow Airport, London. It follows accounts of the project’s 3-D and 4-D design
environment1, and the structural design of the main building2.
In March 2008, T5 opened, increasing further the size of the world’s busiest
two-runway airport, where in any one day the UK National Air Traffic Services (NATS)
controls the movements of over 1000 aircraft approaching and departing, as well as T1
Construction method
Importantly, the construction strategy was developed in parallel with the design.
A key aspect of the project was the use of the T5 agreement, the form of collaboration
contract used by BAA when appointing its design consultants and contractors. Visual
control
This allowed the tower design to be specifically tailored to suit the erection strategy, room
with designers and construction team working together from the outset. Gallery
The design team considered using a traditional slip-formed concrete cantilever
mast, but this would have required regular and uninterrupted concrete deliveries. Rest and
recreation
Security, operations, and radar restrictions applying in the airport would also have
necessitated an on-site batching plant, with cranes only usable in five-hour night-
time airport closures. In view of this, the team decided on a cable-stayed steel tower,
Plant
which could have half the mast diameter of an equivalent cantilevered mast structure.
A steel tower could also be prefabricated and transported to site in 12m lengths,
completely fitted out with stairs, lift cores, and mechanical-and-electrical risers,
and then bolted together. 4. Section through control tower cab.
In addition, a small-diameter cable-stayed mast satisfied concerns about the visual
impact of a traditional large-diameter concrete cantilever tower on the Heathrow
skyline, as well as making it possible to construct the cab at ground level around the
base of the mast, and later jack it up into position at the top. Building the cab at low
level had several safety advantages, though significant challenges were also involved
in making it structurally stable with the large hole through the middle for the mast.
These were met by using an idea from the petrochemical industry for erecting
process plant (Fig 5). Its great advantage is that is allows the complete cab to be
built at ground level without incorporating a temporary hole for jacking the cab up
the mast. Understanding the prefabrication, transportation, and erection requirements
was essential in defining the parameters to control the maximum diameter of the mast
and the design requirements for the cab structure.
Dynamic performance
Alongside the erection strategy, another factor critical to the structural requirements
for the mast was wind-induced movement of the completed tower.
Setting appropriate “comfort” criteria for tall buildings is more difficult than
most design cases faced by engineers; here the tower’s dynamic performance
was critical to the comfort of the air-traffic controllers. In the case of wind-induced
lateral movements, acceptable performance is both time-dependent and varies with 5. Tower jacking: three temporary works towers support
occupier sensitivity. The more often movement occurs, the less tolerant are occupiers strand-jacks and yoke system; the strands lift the yoke
and mast off the ground via hydraulic jaws to allow a new
of the level of lateral acceleration they experience. In the case of Heathrow, which section of mast to be inserted underneath.
often experiences fairly windy conditions, the frequent lower-strength winds formed
the critical design case.
Conclusion Jeremy Edwards is an Associate of Arup with the Building London 4 group. He is a structural
engineer and has had several roles on T5, including assistant structural engineer for the air-traffic
The new tower went ”live” in February 2007 when full control tower.
airport operations transferred and the old tower was Richard Matthews is a Director of Arup with the Building London 9 group. He leads the
closed after 52 years of service. structural engineering team for T5, and acted as Project Leader for BAA on the air-traffic
control tower.
Building a new air-traffic control tower in the
Sean McGinn is a Senior Associate of Arup with the Buildings Melbourne, Australia, group.
centre of Heathrow’s airside operations involved
He was lead structural engineer of the air-traffic control tower.
unique construction and operational requirements
that largely dictated its architectural and engineering
form (a more detailed description of the project has
been published elsewhere3). This tower satisfies
the air-traffic controllers’ requirements, yet was Credits
constructed with no disruption to the airport’s Client: BAA (building owner, airport operator, overall project manager) Building operator: NATS
daily operations and no accidents. Its successful Architect: Richard Rogers Partnership Project manager, structural engineer (superstructures),
acoustics, façade, wind and dynamics engineer: Arup - Andrew Allsop, Mike Banfi, Francesco
completion demonstrates the value of T5’s integrated Biancelli, Nick Boulter, Anita Bramfitt, Simon Cardwell, Jeremy Edwards, Rob Embury, Matteo
design and construction philosophy. Farina, Graham Gedge, James Hargreaves, Richard Henderson, Roger Howkins, Angus Low,
Richard Matthews, Chris Murgatoyd, Daniel Powell, Sean McGinn, Nils Svensson, Ian Wilson,
Peter Young, Andrea Zelco Engineer (substructure): Mott Macdonald Temporary works
designer: Dorman Long Technology Infrastructure engineer: TPS M&E engineer: DSSR Cost
manager: Turner & Townsend/EC Harris Construction integrator: Mace Steelwork supplier:
Watson Steel Substructure contractor: Laing O’Rourke Jacking and cab transportation:
Faggiolli M&E and infrastructure contractor: AMEC Façade supplier: Schmidlin Lift supplier:
Schindler Fit-out supplier: Warings Logistics: Amalga Illustrations: 1-10, 12-17 BAA/HATCT
project team; 11 Nigel Whale.
References
(1) BEARDWELL, G et al. Terminal 5, London Heathrow: 3-D and 4-D design in a single model
environment. The Arup Journal, 41(1), pp3-8, 1/2006.
(2) McKECHNIE, S. Terminal 5, London Heathrow: The main terminal building envelope.
The Arup Journal, 41(2), pp36-43, 2/2006.
(3) MATTHEWS, R. Creating Heathrow’s new eye in the sky. Civil Engineering, 161(2),
pp66-76, May 2008.