Method Statement For Installation of Sub-Main Distribution Boards (SMDB) & Distribution Boards (DB)
Method Statement For Installation of Sub-Main Distribution Boards (SMDB) & Distribution Boards (DB)
Contents
Purpose.......................................................................................................................................................2
Scope of Work.............................................................................................................................................2
Definition....................................................................................................................................................2
Abbreviation...........................................................................................................................................2
“Approved” or “Approval”..................................................................................................................2
“Shop Drawings”.................................................................................................................................2
“Final Inspection”................................................................................................................................2
“Method Statements”........................................................................................................................2
Reference Documents – Specifications, Drawings. Etc..............................................................................3
Tools and Equipment..................................................................................................................................3
Manpower...............................................................................................................................................3
Staff:....................................................................................................................................................3
Labour:................................................................................................................................................3
Responsible Personnel on Site...................................................................................................................3
Material Inspection / Storage.....................................................................................................................4
Construction Sequence and Methodology.................................................................................................4
Preparation before Installation..............................................................................................................4
Installation..................................................................................................................................................4
Installation Procedure – Wall-mounted Sub Main Distribution Boards & Distribution Boards................5
Inspection and Testing................................................................................................................................6
Health, Safety and Environment................................................................................................................6
Housekeeping.............................................................................................................................................7
Signage........................................................................................................................................................7
1
Page 2 of 7
Purpose
The purpose of this Method Statement is to describe the details used and controls to be carried out for
the installation of Sub-Main Distribution Boards & Distribution Boards to ensure that it complies to
Project requirements, specifications (Section 26 02413) and standards.
Scope of Work
This Method Statement applies to all Sub-Main Distribution Boards & Distribution Boards at Doha
Convention Centre & Tower Project Electrical Works.
Manpower and equipment shall be organized to meet the schedule as per the approved construction
program.
Definition
Abbreviation
SMDB - Sub Main Distribution Board
DB - Distribution Board
ADDC - Abu Dhabi Distribution Company
QAQC - Quality Assurance Quality Control
MS - Method Statement
MEP - Mechanical, Electrical, Plumbing
RFIA - Request for Inspection & Approval
MIR - Materials Inspection Request
ITP - Inspection and Test Plan
TBT - Tool Box Talk
“Approved” or “Approval”
Approved means approved in writing by the applicable Engineers. Assistant acting within the scope of
their delegated authority.
“Shop Drawings”
“Shop Drawings-(SD)” means the production of drawings where the contract designs drawings need
expressing in the more initial form to simplify and ease construction.
“Final Inspection”
“Final Inspection-(FI)” means the inspection of the records of works at completion or after pre-
determined elements to ensure that all previous inspections and tests have been satisfactorily
conducted and appropriately documented.
“Method Statements”
“Method Statements-(MS)” means a technical document to be read in conjunction with the approved
drawings, specification, standards and codes of practice (Sop’s), technical datasheets, schedules, work
instructions and any other technical document related to a particular work.
2
Page 3 of 7
3
Page 4 of 7
4. Site Engineer / Supervisor shall check the materials as per manufacturer's recommendation
before installation and shall be responsible for the installation as per approved shop drawings.
5. Safety Officer shall ensure that appropriate/necessary measures are in place at the work
location to avoid any unexpected events.
6. QAQC Inspector shall be responsible for carrying out inspections for the materials delivered on-
site. He shall document such inspections.
7. QAQC Engineer / Inspector shall monitor the installation activities progressively and shall record
all deviation from the specification in a form of snags or further as non-conformance
notification.
Installation
1. The floor of electrical rooms shall be painted and ready for permanent installation of SMDBs.
2. Move the panels from the storage area to the designated electrical room. Panels shipped on a
timber sub-base shall be lifted under the sub-base by forklift. Unpack and remove the panels
from its timber base. Care must be
4
Page 5 of 7
3. Move-in the panels using rollers to its final location. Care must be taken to ensure that the panel
does not overbalance while being move to its final location.
4. Align the panel horizontally and vertically. And fix the panel to floor using anchor bolts.
5. Clearance between panels and walls shall be following Approved shop drawing / Approved
Installation details.
6. Ensure that the panels are installed properly in its designated location as shown in the shop
drawings.
7. Remove all unused bolts, nuts, washers and clean the panel. Panel side covers and doors shall
be put back ensuring that they are properly tightened.
8. Ensure the tightness of all terminals using calibrated torque wrench before closing the shrouds.
9. Ensure that the Load Schedule / Wiring Diagram is provided inside the panel.
10. Installation and commissioning shall be as per manufacturer recommendation.
11. Cover or protect all installed Panelboards to prevent the accumulation of dust and debris
during construction.
12. Ensure that workmanship is neat and clean and complying to good construction practices.
5
Page 6 of 7
14. Cover or protect all installed Panelboards to prevent the accumulation of dust and debris during
construction.
15. Ensure that workmanship is neat and clean and complying to good construction practices.
Note:
RFIA must be processed and submitted to the Supervision Consultant 24 hours before the actual
inspection and/or witnesses.
The preparatory meeting shall be carried out to the execution team as per method statement,
material submittal & shop drawings before the start of work on-site (by QA. QC Personal).
6
Page 7 of 7
Housekeeping
Housekeeping shall be maintained by all personnel working at the site. Housekeeping for fabrication and
installation shall be as per the project safety plan and ETA-Debbas Safety Manual.
Signage
1. All necessary safety warning and caution signs shall be displayed at work locations.
2. QC Approval and Other Documentary Requirements ( Attachment)
3. Material Technical Submittal Approval
4. Shop Drawing Approval
5. Material Inspection Report (MIR) approval
6. Installation Request for Inspection & Approval (RFIA)